[go: up one dir, main page]

UA97150C2 - Method of soil recultivation - Google Patents

Method of soil recultivation

Info

Publication number
UA97150C2
UA97150C2 UAA200913003A UAA200913003A UA97150C2 UA 97150 C2 UA97150 C2 UA 97150C2 UA A200913003 A UAA200913003 A UA A200913003A UA A200913003 A UAA200913003 A UA A200913003A UA 97150 C2 UA97150 C2 UA 97150C2
Authority
UA
Ukraine
Prior art keywords
dump
recultivation
soil
cutting
working
Prior art date
Application number
UAA200913003A
Other languages
Russian (ru)
Ukrainian (uk)
Inventor
Илья Львович Гуменик
Анатолий Иванович Панасенко
Алексей Владимирович Ложников
Original Assignee
Государственное Высшее Учебное Заведение “Национальный Горный Университет”
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Государственное Высшее Учебное Заведение “Национальный Горный Университет” filed Critical Государственное Высшее Учебное Заведение “Национальный Горный Университет”
Priority to UAA200913003A priority Critical patent/UA97150C2/en
Publication of UA97150C2 publication Critical patent/UA97150C2/en

Links

Landscapes

  • Road Repair (AREA)

Abstract

A method of soil recultivation includes removal of fertile layer of soil, displacement to the outer dump of overburden from cutting of permanent and working trenches, formation of the inner dump and recultivation. The outer dump is formed with sequential decrease of height of dump blocks with inclination in direction of propagation of excavation front. After cutting of the working trench one forms the inner dump, beginning just near the outer dump and then with repeating the relief of the outer dump.
UAA200913003A 2009-12-14 2009-12-14 Method of soil recultivation UA97150C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
UAA200913003A UA97150C2 (en) 2009-12-14 2009-12-14 Method of soil recultivation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
UAA200913003A UA97150C2 (en) 2009-12-14 2009-12-14 Method of soil recultivation

Publications (1)

Publication Number Publication Date
UA97150C2 true UA97150C2 (en) 2012-01-10

Family

ID=52286182

Family Applications (1)

Application Number Title Priority Date Filing Date
UAA200913003A UA97150C2 (en) 2009-12-14 2009-12-14 Method of soil recultivation

Country Status (1)

Country Link
UA (1) UA97150C2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108920870A (en) * 2018-07-24 2018-11-30 中国铁路设计集团有限公司 A kind of tunnel open excavation section excavation of foundation pit face design method based on BIM

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108920870A (en) * 2018-07-24 2018-11-30 中国铁路设计集团有限公司 A kind of tunnel open excavation section excavation of foundation pit face design method based on BIM
CN108920870B (en) * 2018-07-24 2022-08-12 中国铁路设计集团有限公司 BIM-based tunnel open excavation section foundation pit excavation surface design method

Similar Documents

Publication Publication Date Title
CN202936799U (en) Foundation pit dewatering bracing structure based on environment control purpose
PE20141630A1 (en) METHOD FOR FORMING A RETAINING WALL AND A CORRESPONDING RETAINING WALL
CN103235853B (en) Adopt the multiple base pool layout method based on earthwork balance in limit for coal-mining subsidence rand
CN205742299U (en) A kind of an ultra shallow buries the float Structure of shield tunnel
CN104179506B (en) The treatment process of a kind of shield structure mud lining
UA97150C2 (en) Method of soil recultivation
UA52255U (en) Method for restoration of land
CN100532729C (en) High vacuum well-points dewatering groundwork treatment method by shallow ramming compaction and deep blasting compaction
CN202370539U (en) Front tunnel face excavated soil pre-reinforcing structure of tunnel
CN203346865U (en) Soft soil foundation preloading processing structure
CN109235458B (en) Method for forming dam by injecting water into accumulation body to promote slip
CN101538849B (en) Foundation treatment method combining vibration ramming compaction at shallow layer and blasting compaction at deep layer with well-point dewatering
CN103821525B (en) Cable tunnel rapid constructing method under high water level geological conditions
CN204059329U (en) A kind of foundation structure of combining employing piling prepressing and heavy tamping treatment
CN104500079A (en) Tunnel excavation method in shallow-buried bias-pressure toppling-deformation bulk solid and strong-unloading rock structure
RU2009106841A (en) METHOD FOR UNDERGROUND SALES DEVELOPMENT
CN202969441U (en) Non-alignment bucket tooth tunnel digging bucket
UA62264U (en) Method for open mining of watered fields of soft minerals
Gu et al. Analysis of forming reason of mud breakout in Tong-Yu tunnel.
CN202831034U (en) Sand excavator
UA100419C2 (en) METHOD OF OPEN DEVELOPMENT OF WATERFRONTED DEPOSITS OF SOFT MINING MINES
UA154267U (en) Method of disclosure of rock salt deposits in complex hydrogeological conditions
CN103628484B (en) Soil rock geology deep foundation ditch oppositely docks construction method
UA54734U (en) Method for reclamation of downslopes
UA84929U (en) Method for dump formation in mode of rock deformation