JPS63151795A - Method of construction of tunnel - Google Patents
Method of construction of tunnelInfo
- Publication number
- JPS63151795A JPS63151795A JP61294990A JP29499086A JPS63151795A JP S63151795 A JPS63151795 A JP S63151795A JP 61294990 A JP61294990 A JP 61294990A JP 29499086 A JP29499086 A JP 29499086A JP S63151795 A JPS63151795 A JP S63151795A
- Authority
- JP
- Japan
- Prior art keywords
- water
- construction
- tunnel
- shield
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 19
- 238000010276 construction Methods 0.000 title description 25
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 31
- 239000004576 sand Substances 0.000 claims description 4
- 238000004804 winding Methods 0.000 claims description 4
- 239000002002 slurry Substances 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000005641 tunneling Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 235000012907 honey Nutrition 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 239000010802 sludge Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は比較的浅い水底下におけるトンネルの築造工法
に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing a tunnel under relatively shallow water.
従来、水底下にトンネルを築造する工法としては王とし
てシールド工法と沈埋工法とがありた。Conventionally, there have been two main methods for constructing tunnels under water: the shield method and the submerged method.
シールド工法とは、自立せず崩壊しやすい地質中にトン
ネルを掘削するために開発された工法で「5HIELD
J とよはれる鋼製の筒を地中に埋込みこの士に流
入してくる土を掘削し、またシールドが進んだ後には、
セグメントとよばれる鋼製またはコンクリート製の分割
されたライニングをシールドと同心に円筒状に組立てゆ
くことにより、士の崩れるのを防止しながら安全にトン
ネルを構築する工法である。The shield method is a construction method developed to excavate tunnels in geological formations that are not self-supporting and prone to collapse.
J. After embedding a steel cylinder in the ground and excavating the soil that flows into this area, and after the shield has advanced,
This is a construction method that safely constructs tunnels by assembling divided steel or concrete linings called segments into a cylindrical shape concentrically with the shield, while preventing the lining from collapsing.
また、沈埋工法は、あらかじめ陸上で製作しておいてた
覆工構造体(沈埋かん)を水底に並べて連結してゆ<
−&のプレハブ工法である。In addition, in the submerged method, lining structures (submerged cans) that have been manufactured on land in advance are lined up and connected to the bottom of the water.
−& is a prefabricated construction method.
シールド工法においては、第7図のように豆坑It−掘
削しても、さらに立坑1までのトンネル2を開削工法な
どによって組長して掘削する会費があり、経済的ではな
かった1、
水底下の床面により更に深い場所を掘削するので高水圧
対策が困難であったし、立坑1を境圧してシールド工法
と開削工法との変更が必要であって工事期間が長くなっ
ていた。In the shield method, even if a mini-pit is excavated as shown in Figure 7, there is a membership fee for excavating the tunnel 2 up to the vertical shaft 1 using the cut-and-cover method, which is not economical1. It was difficult to take measures against high water pressure because the excavation was deeper than the floor surface, and it was necessary to apply boundary pressure to shaft 1 and change between the shield method and the open-cut method, which lengthened the construction period.
また沈埋工法の場合は第8図に示すようにシールド工法
と同様にトンネル2を開削工法などによって地老部を延
長して掘削する必要があり経済的ではなかった。また沈
埋管4の沈設、水底下の溝掘り作業などがあるので水上
交通がその間は制約を受けていた。In addition, in the case of the immersion method, as shown in Figure 8, it is necessary to extend and excavate a tunnel 2 using the cut-and-cover method, which is not economical, as is the case with the shield method. In addition, water transportation was subject to restrictions during this period due to the work involved in sinking the immersed pipe 4 and digging trenches under the water.
また第8図に示すように開削工法区間と沈埋工法区間と
があって工法の変更が必要であり工事期間が長くなって
いたし、沈埋管40表進用ドッグが工事場所の近くに必
要であるのでドッグが近くにない場合は沈埋工法の採用
が不可能であったし、沈埋管4の埋設位置が深くなると
、管外からの水中潜水作業のため沈埋管の接続作業が困
難になってい喪。In addition, as shown in Figure 8, there are sections using the open-cut method and sections using the immersed method, which required a change in construction method and lengthened the construction period, and a 40-way submerged pipe extension dog was required near the construction site. Therefore, if the dog was not nearby, it was impossible to adopt the submerged method, and if the submerged pipe 4 was buried deep, it became difficult to connect the submerged pipe because it had to be submerged from outside the pipe. .
本発明は上記の事情に鑑みなされたもので、その目的と
するところは全区間を通して同一のシールド掘進機でト
ンネルの条構が可能になり、開削工法を不用にすること
ができて経済的になるし海上交通の制約、沈埋管接続作
業の問題点がなく彦るし特別の高水圧対策が不必要にな
りまた工事期間を短縮することができまた沈埋管の製造
ドックが不必要になるトンネルの築造工法を提供するこ
とにある。The present invention was made in view of the above circumstances, and its purpose is to make it possible to construct a tunnel using the same shield excavation machine throughout the entire section, thereby making it possible to eliminate the need for the cut-and-cover method, thereby making it economical. This tunnel eliminates the limitations of marine transportation and the problems associated with connecting immersed pipes, eliminates the need for special high water pressure measures, shortens the construction period, and eliminates the need for a manufacturing dock for immersed pipes. Our goal is to provide construction methods for
〔問題点1に′s決するための手段及び作用〕上記の目
的を達成するために本発明は、地表に構築した発進立坑
から水底にかけてシールド掘進機により掘削すると共に
シールド掘進機の推進に伴ないセグメントの巻立を行い
、水底到達後シールド掘進機で水底に所定の深さの*を
掘削すると共にセグメントの巻立により沈埋管を形成し
てこの沈埋管を水底の掘削溝に設置し沈埋管の水中宍出
部分に埋戻し土砂を布設するようにした。[Means and operations for resolving problem 1] In order to achieve the above object, the present invention excavates from a starting shaft built on the surface of the earth to the bottom of the water using a shield excavator, and as the shield excavator advances. The segments are rolled up, and after reaching the water bottom, a shield excavator is used to excavate a specified depth * on the water bottom, and the segments are rolled up to form an immersed pipe, which is then installed in an excavated trench on the water bottom to create an immersed pipe. Backfill earth and sand was laid in the underwater part of the site.
以下、本発明の実施例を第1図乃至第6図に基づいて説
明する。Embodiments of the present invention will be described below with reference to FIGS. 1 to 6.
本発明に係るトンネルの築造工法に用いるシールド掘進
機10はカッタヘッド11と推進ジヤツキ12とを備え
ており、このシールド掘進e10はアーチイキュレート
式で複数に折り曲がるもので、トンネル切羽の掘削と機
外へのズリ出しおよびセグメント130壱立を行うもの
でおる。またシールド掘進機10のシールド本体14の
後端部には第6図に示すように複数のテールシール15
が設けてあり、掘進時テールシール15はセグメント+
3もしくは沈埋管16になるセグメント17の外局面に
摺接し水蜜を保持するものである。The shield excavator 10 used in the tunnel construction method according to the present invention is equipped with a cutter head 11 and a propulsion jack 12. This is used to remove the waste from the machine and to set up the segment 130. Further, at the rear end of the shield main body 14 of the shield excavator 10, a plurality of tail seals 15 are provided as shown in FIG.
is provided, and the tail seal 15 during excavation is segment +
3 or the outer surface of the segment 17, which becomes the submerged pipe 16, to hold the water honey.
地表18に第1図に示すように発進立坑19を構築し、
この発進立坑19から水底20にかけて斜めにシールド
掘進機10によってトンネル21t″掘削する。A starting shaft 19 is constructed on the ground surface 18 as shown in Figure 1,
A tunnel 21t'' is excavated obliquely from the starting shaft 19 to the water bottom 20 by the shield excavator 10.
この場合、スラリポンプ22の駆動で処理プラント23
の泥水を送泥水管24を介してカッタヘッド11内に送
り、掘削土砂(ズリ)をスラリー化し、排泥水ポンプ2
5の駆動によりスラリー化したズリを排泥水管26t−
介して処理プラント23に排出する。In this case, the treatment plant 23 is driven by the slurry pump 22.
The mud water is sent into the cutter head 11 through the mud water pipe 24, the excavated earth and sand (sludge) is turned into slurry, and the mud water pump 2
The slurry made into slurry by the drive of No. 5 is removed from the slurry water pipe 26t-
and is discharged to the treatment plant 23 via.
前記シールド掘進機10の推進に伴なってこのシールド
掘進機10が具備するセグメント巻立装置(図示省略)
によってセグメン)13の巻立を行う。A segment winding device (not shown) included in the shield excavator 10 as the shield excavator 10 is propelled.
Winding of segment) 13 is performed.
このようにしてトンネル2Iの掘111tt t−行い
地中と水底20との分岐点Bに到達するとシールド掘進
機10を水平に姿勢制御し水底20に深さBの溝Aを掘
削する。In this way, the tunnel 2I is excavated 111ttt-t-, and when the tunnel 2I is excavated and reaches the branching point B between the underground and the water bottom 20, the shield excavator 10 is controlled horizontally and a trench A of depth B is excavated in the water bottom 20.
地中部分は一般の薄肉のセグメント13を用い、水中部
分のセグメント17は巻立てられて沈埋管16になされ
、その沈埋管29は第5図に示すように隔壁27を備え
、しかも隔壁27間の上部に貯水部28を有するもので
ある。また隔壁27には作業者30が出入りできる開口
部3Iが設けてあり、この開口部31には蓋体32が設
けである。The underground portion uses ordinary thin-walled segments 13, and the underwater portion segments 17 are rolled up to form the immersed pipe 16, and the immersed pipe 29 is provided with partition walls 27 as shown in FIG. It has a water storage part 28 in the upper part. Further, the partition wall 27 is provided with an opening 3I through which a worker 30 can enter and exit, and this opening 31 is provided with a lid 32.
そして沈埋管16を安定させるために貯水部28に注入
する。Then, in order to stabilize the immersed pipe 16, it is injected into the water storage section 28.
前記セグメント17の巻立後、運搬布設船33で埋戻し
土砂34を運搬し沈埋管29の水中表出部分に布設する
。After the segments 17 are rolled up, the backfilling soil 34 is transported by a transport construction ship 33 and laid in the underwater exposed portion of the submerged pipe 29.
対岸の地表に到達立坑(図示省略)を構築し、シールド
掘進機10が到達立坑に到達後分解して搬出し、必要部
分を坑内から止水しまた二次穆工(コンクリート施工)
を行う。A vertical shaft (not shown) is constructed to reach the ground surface on the opposite shore, and after the shield excavator 10 reaches the vertical shaft, it is disassembled and carried out, and the necessary parts are water-tightened from inside the shaft and secondary sill construction (concrete construction) is carried out.
I do.
以上詳述したように本発明に係るトンネルの築造工法は
、地表に構築した発進立坑から水底にかけてシールド掘
進機によりmsuすると共にシールド掘進機の推進に伴
ないセグメントの巻立を行い、水底到達後シールド掘進
機で水底に所定の深さの溝を掘削すると共にセグメント
の壱豆により沈埋管を形成してこの沈埋管を水底の掘削
溝に設置し沈埋管の水中表出部分に埋戻し土砂を布設す
るようにしたことを特徴とするものである。As detailed above, the tunnel construction method according to the present invention involves msuing from a starting shaft constructed on the surface of the earth to the bottom of the water using a shield tunneling machine, and winding up the segments as the shield tunneling machine advances, and after reaching the bottom of the water. A trench with a predetermined depth is excavated on the water bottom using a shield excavator, and an immersed pipe is formed using a segment.The immersed pipe is installed in the excavated trench on the water bottom, and the exposed part of the immersed pipe is backfilled with earth and sand. This is characterized by the fact that it can be installed.
したがって、地中の掘削及び水底の掘削をシールド掘進
機で行うように全区間全通して同一のシールド掘進機で
トンネルの条構が可能になり、開削工法を不用にするこ
とができて経済的になる。Therefore, just as a shield excavator is used to excavate underground and underwater, it is possible to construct a tunnel using the same shield excavator throughout the entire section, making it possible to eliminate the need for open-cut construction methods and making it more economical. become.
また水底下の出来あがりは沈埋管と同一になるものの海
上交通の制約、沈埋管接続作業の問題点がなくなる。In addition, although the result under the water is the same as that of a submerged pipe, there are no restrictions on marine transportation and problems associated with connecting submerged pipes.
また沈埋管の埋設位置は水底の床面とほぼ同一レベルで
あるので特別の高水圧対策は不必要であるし、同一工法
(シールド工法)で工事を連続的に施工できるので工事
期間を短縮することができまた沈埋管の製造ドックが不
必賛になる。In addition, since the buried pipe is buried at almost the same level as the waterbed floor, special measures against high water pressure are not required, and the construction period can be shortened because the construction can be carried out continuously using the same construction method (shield construction method). This also makes the manufacturing dock of immersed pipes unavoidable.
第1図は本発明工法による地中トンネルの築造の説明図
、第2図は本発明工法による水底トンネルの築造の説明
図、第3@は第1図■−−線に沿う断面図、第4図は第
2図IV−fV線に沿う断面図、柄5図はセグメントよ
り成る沈埋管の縦断面図、第6図はシールド掘進機のテ
ールシール部分の構成説明(2)、第7図、第8図は従
来のトンネルの築造工法の説明図である。
10はシールド掘進機、13.17はセグメント、16
は沈埋管、19は発進立坑、20は水底、Aは溝。Figure 1 is an explanatory diagram of the construction of an underground tunnel by the construction method of the present invention, Figure 2 is an explanatory diagram of the construction of an underwater tunnel by the construction method of the present invention, Figure 3 is a sectional view along the line ■-- in Figure 1, Figure 4 is a cross-sectional view taken along line IV-fV in Figure 2, figure 5 is a vertical cross-sectional view of an immersed pipe consisting of segments, figure 6 is an explanation of the structure of the tail seal part of the shield excavator (2), and figure 7 , FIG. 8 is an explanatory diagram of a conventional tunnel construction method. 10 is a shield excavator, 13.17 is a segment, 16
19 is the starting shaft, 20 is the water bottom, and A is the ditch.
Claims (1)
機により掘削すると共にシールド掘進機の推進に伴ない
セグメントの巻立を行い、水底到達後シールド掘進機で
水底に所定の深さの溝を掘削すると共にセグメントの巻
立により沈埋管を形成してこの沈埋管を水底の掘削溝に
設置し沈埋管の水中表出部分に埋戻し土砂を布設するよ
うにしたことを特徴とするトンネルの築造工法。A shield excavator excavates from the starting shaft built on the surface of the earth to the bottom of the water, and as the shield excavator advances, segments are rolled up.After reaching the bottom, the shield excavator excavates a trench of a predetermined depth on the water bottom. A method for constructing a tunnel, characterized in that an immersed pipe is formed by winding segments, the immersed pipe is installed in an excavated trench at the bottom of the water, and backfilling earth and sand is laid in the exposed underwater part of the immersed pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61294990A JPS63151795A (en) | 1986-12-12 | 1986-12-12 | Method of construction of tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61294990A JPS63151795A (en) | 1986-12-12 | 1986-12-12 | Method of construction of tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS63151795A true JPS63151795A (en) | 1988-06-24 |
Family
ID=17814918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP61294990A Pending JPS63151795A (en) | 1986-12-12 | 1986-12-12 | Method of construction of tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63151795A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003003502A (en) * | 2001-06-26 | 2003-01-08 | Ishikawajima Harima Heavy Ind Co Ltd | Underwater excavation shield machine |
JP2007537375A (en) * | 2004-05-12 | 2007-12-20 | ブイーグ・トラボ・ピュブリクス | Construction method and equipment for tunnels submerged on the seabed |
-
1986
- 1986-12-12 JP JP61294990A patent/JPS63151795A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003003502A (en) * | 2001-06-26 | 2003-01-08 | Ishikawajima Harima Heavy Ind Co Ltd | Underwater excavation shield machine |
JP2007537375A (en) * | 2004-05-12 | 2007-12-20 | ブイーグ・トラボ・ピュブリクス | Construction method and equipment for tunnels submerged on the seabed |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105714748A (en) | Excavating construction method for surge shaft in gravel and sandy soil layer | |
JPS63151795A (en) | Method of construction of tunnel | |
JP7303756B2 (en) | Open shield machine and tunnel construction method | |
JP3971241B2 (en) | Method of laying pipe in submarine ground and excavation tip device used for pipe laying method | |
JP2526333B2 (en) | How to build a vertical shaft | |
Haswell | Thames Cable Tunnel. | |
JP2809105B2 (en) | How to build an underground tank | |
JP2874906B2 (en) | Shaft construction method | |
CN110409497A (en) | Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel | |
JP3809631B2 (en) | Submarine tunnel connection method | |
JP3031506B2 (en) | Shield method | |
JP2016008377A (en) | Rectangular section propulsion method | |
JPS6255397A (en) | Construction of large depth pit | |
JP2526335B2 (en) | How to build a vertical shaft | |
JP2004003229A (en) | Method for constructing vertical shaft | |
CN213329036U (en) | Partition wall that triaxial stirring stake constitutes | |
JPH07259078A (en) | Construction method of steel material for shield opening and underground continuous wall, and mirror opening method of vertical shaft | |
JP3031507B2 (en) | Shield arrival method | |
JPH0122410B2 (en) | ||
JP2791664B2 (en) | Simple underground continuous wall method | |
JP2004238981A (en) | Tunnel construction method | |
JPH02311617A (en) | Construction of foundation pile | |
JPS57140421A (en) | Construction of large-diameter in-situ cast pile | |
JPS5972324A (en) | Construction of artificial islet for excavation of shaft | |
JP2779680B2 (en) | Construction method of underwater tunnel and underwater excavator |