[go: up one dir, main page]

CN110409497A - Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel - Google Patents

Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel Download PDF

Info

Publication number
CN110409497A
CN110409497A CN201910545233.2A CN201910545233A CN110409497A CN 110409497 A CN110409497 A CN 110409497A CN 201910545233 A CN201910545233 A CN 201910545233A CN 110409497 A CN110409497 A CN 110409497A
Authority
CN
China
Prior art keywords
tunnel
water
construction
prefabrication
shallow embedding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910545233.2A
Other languages
Chinese (zh)
Inventor
张鸿
施志勇
翟世鸿
杨秀礼
张永涛
谭啸峰
杨钊
蒋道东
孟奎
许超
李雪松
方之遥
刘毅
陈培帅
杨睿
徐杰
程茂林
华晓涛
吴中正
杨擎
黄威
江鸿
冯德定
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201910545233.2A priority Critical patent/CN110409497A/en
Publication of CN110409497A publication Critical patent/CN110409497A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/07Tunnels or shuttering therefor preconstructed as a whole or continuously made, and moved into place on the water-bed, e.g. into a preformed trench

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of construction methods suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, comprising the following steps: Step 1: cofferdam is arranged in submerged tunnel one end to be onstructed, the excavation that draws water, which is formed, originates foundation pit, and assembled equipment assembly will be tunneled in it and is completed;Step 2: with the walking for tunneling assembled equipment, the synchronous soil for excavating front end of anterior shield;And the prefabricated tunnel structure of synchronous hoisting is put into from the open top end in open supporting cabin, and is pushed out to predeterminated position, and the prefabricated tunnel structure in two pieces of front and back is connected;Step 3: repeating step 2, it is advanced into after the tunnel other end receives foundation pit and hangs out, complete the laying of all prefabricated tunnel structures.In present invention construction, similar mobile cofferdam function and mobile pattern foundation pit supporting structure function are provided, Temporary Cofferdam and permanent pattern foundation pit supporting structure is not necessarily to, significantly saves project cost, while can be reduced construction time waters area occupied and time, reduce underwater soil dredging amount.

Description

Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel
Technical field
The present invention relates to underwater prefabricated tunnel structure assembling fields.It is more particularly related to which one kind is suitable for The construction method in water-bed shallow embedding prefabrication and assembly construction tunnel.
Background technique
The method of construction of submerged tunnel has in the world at present: when edpth of tunnel is deeper, mainly using drilling and blasting method and shield Method;When edpth of tunnel is shallower, method can only be built using immersed tunnelling method and weir;
So-called immersed tunnelling method is that successively sinking is extremely excavated by prefabricated entire tunnel tube coupling (general length 70-200 meters) Water-bed foundation trench in carry out sinking docking, then backfill, which faces that underwater dredging mud amount is big, environment influences that big, immersed tube is floating Fortune requires high, high cost disadvantage to fairway depth, such as port Zhuhai and Macao bridge seabed tunnel.The so-called weir method of building is that construction is faced on the water When coffering, drain water in cofferdam and carry out deep foundation pit construction, then carry out tunnel structure cast-in-place construction, the engineering method in foundation pit With the construction time is long, occupancy water surface area is big, environment influences big, a large amount of Temporary Cofferdam and foundation pit supporting project is at high cost The disadvantages of (typically constitute from engineering direct cost 40% or so);As Wuhan East Lake tunnel, Wuxi Taihu Lake tunnel are all made of weir and build method Construction.
Method and immersed tunnelling method disadvantage are built in view of underwater shallow tunnel weir and civil construction industry greatly develops prefabrication and assembly construction With the historical background of do mechanization operation, it is badly in need of a kind of novel construction method that can be realized do mechanization operation, prefabrication and assembly constructionization construction, thus It can accelerate progress, reduce influence of the over-water construction to environment, project cost is greatly reduced.
Summary of the invention
In order to achieve the goal above, the present invention provides a kind of construction party suitable for water-bed shallow embedding prefabrication and assembly construction tunnel Method, comprising the following steps:
Step 1: setting up cofferdam in submerged tunnel one end to be onstructed, the excavation that draws water, which is formed, originates foundation pit, and pick is completed in it It is assembled into assembled equipment;
The assembled equipment of the driving includes anterior shield and backing mutually hinged, wherein the anterior shield front end, which is equipped with, to be used for The cutter hub of digging;The backing top upwardly extends and opening, and open end is higher than the water surface in waters to be onstructed, is formed for throwing Put the open supporting cabin of the prefabricated tunnel structure of lifting;The anterior shield rear end is equipped with incremental launching device;The backing rear end part It opens wide, forms a push mouth passed through for prefabricated tunnel structure;
Set spiral conveying tube in the assembled equipment of the driving, one end towards the anterior shield cutter hub digging position, inhale The soil for taking anterior shield pick to dig, the other end are in communication with the outside by the open end in open supporting cabin, the soil of absorption are delivered to outer Portion;Wherein, the spiral conveying tube is spliced by two pieces points of spiral conveying tube inclinations;
Step 2: with the walking for tunneling assembled equipment, the synchronous soil for excavating front end of anterior shield;And the prefabricated tunnel of synchronous hoisting Road structure is held in the backing from the open top end investment in the open supporting cabin;Then the incremental launching device pushing tow is put The prefabricated tunnel structure set pushes out from the push mouth of the backing to predeterminated position, and by the prefabricated tunnel knot of this part Structure and upper one piece of prefabricated tunnel structure connect, and in its bottom and side synchronous grouting, the underwater backfilling of earthwork of structural top;
Step 3: repeating said steps two, until tunneling assembled equipment runs to the reception positioned at the submerged tunnel other end Foundation pit completes the laying of all prefabricated tunnel structures.
Preferably, the described construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, in the step 1, In Originating to be provided in foundation pit promotes that tunnels assembled equipment to originate reaction frame, provides to tunnel assembled equipment and originates counter-force.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the incremental launching device are Hydraulic cylinder or hydraulic stem.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the driving assembly are set Standby sealed bottom, and during push, seamless seal can be achieved at the push mouth of the backing between prefabricated tunnel structure Contact, in order to underwater construction.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the step 1 are also wrapped It includes: assigning interim building enclosure towards the one end in waters originating in foundation pit;
The step 2 further include: before tunneling assembled equipment walking, remove the interim building enclosure.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, before step 2, if When submerged tunnel bottom foundation soil is soft layer, consolidation process is carried out to soft de- ground, guarantees that ground meets equipment construction Requirement for bearing capacity.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the reception foundation pit It is setting cofferdam, and draws water and excavate formation.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the driving assembly are set It is standby internal equipped with screw conveyor, the interior installation helical feed pipeline.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, the anterior shield is along width The two sides in direction are vertically equipped with breast boards respectively.
Preferably, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, all prefabricated tunnel knots Structure paving is laid with after splicing completion, and the both ends for being formed by tunnel are connected with the tunnel constructed on revetment respectively, forms one The complete channel of item.
The present invention is include at least the following beneficial effects:
1, the present invention uses open cut tunneling construction, rather than the tunneling of traditional handicraft is tunneled, and project amount is smaller;
2, in the present invention, dregs is directly vertically sent to ground using screw conveyor by the way that backing top is open, is not taken up an area, And it is simple to operate, cost is reduced, and traditional shield machine is to be transported by assembled molding to active well, then is vertically hung It is transported to ground, is taken up a large area;
3, conventional tunnel construction is all to use Prefabricated Concrete section of jurisdiction or stage, but the present invention is by prefabricated profiled whole stage tunnel Road (can also be fragment section of jurisdiction) is directly hung in shield machine by the opening on backing top, and the tunnel being completed with rear is assembled Connection molding;
4, two sides are equipped with breast boards at the top of anterior shield, for the soil body at the top of supporting and retaining system shield body to ground (or mud face) two sides, therefore Anterior shield is directly excavated to ground, and backing is backfilled to former mud face (ground) in tunnel assembly molding rear shell immediately;
5, added with counterweight on shield body inside panel, to overcome suffered buoyancy;
6, when carrying out prefabricated whole segment tunnel consolidation service under water, driving assembly equipment of the invention is similar to a shifting Dynamic cofferdam structure can provide similar mobile cofferdam function and mobile pattern foundation pit supporting structure function, be not necessarily to Temporary Cofferdam and permanent foundation pit branch Shield, significantly saves project cost, while can be reduced construction time waters area occupied and time, reduces underwater soil dredging amount;
Further advantage, target and feature of the invention will be partially reflected by the following instructions, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is the sectional view of step 1 of the present invention construction signal;
Fig. 2 is the sectional view of step 2 of the present invention construction signal;
Fig. 3 is the sectional view of step 3 of the present invention construction signal;
Fig. 4 is the top view of step 1 of the present invention construction signal;
Fig. 5 is the top view of step 2 of the present invention construction signal;
Fig. 6 is the top view of step 3 of the present invention construction signal.
Specific embodiment
Present invention will be described in further detail below with reference to the accompanying drawings, to enable those skilled in the art referring to specification text Word can be implemented accordingly.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained;In the description of the present invention, term " transverse direction ", " vertical To ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", the instructions such as "outside" side Position or positional relationship are to be based on the orientation or positional relationship shown in the drawings, and are merely for convenience of description of the present invention and simplification of the description, It is not that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, because This is not considered as limiting the invention.
The present invention provides a kind of construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, comprising the following steps:
If previous step, submerged tunnel bottom foundation soil are soft layer, consolidation process is carried out to soft de- ground, is protected Card ground meets equipment construction requirement for bearing capacity;Rotary churning pile can be used herein or stirring grabs stake and carries out stiffening basic ground;
As shown in Figure 1 and Figure 4, it Step 1: setting up cofferdam 4 in submerged tunnel one end to be onstructed, draws water, formation originates base Hole will tunnel assembled 1 assembly of equipment in it and complete;The assembled equipment 1 of the driving includes anterior shield 101 and backing mutually hinged 102, wherein 101 front end of anterior shield is equipped with the cutter hub for digging;102 top of backing upwardly extends and opening, and Open end is higher than the water surface in waters to be onstructed, forms the open supporting cabin 103 of the prefabricated tunnel structure 2 for launching lifting;Institute It states 101 rear end of anterior shield and incremental launching device is installed;102 rear end of backing is locally opened wide, and is formed one and is passed through for prefabricated tunnel structure 2 Push mouth;Set spiral conveying tube 3 in the assembled equipment 1 of the driving, one end towards the anterior shield 101 cutter hub digging position It sets, draws the soil that the pick of anterior shield 201 is dug, the other end is in communication with the outside by the open end in open supporting cabin 103, by the mud of absorption Soil is delivered to outside;Wherein, the spiral conveying tube 3 is spliced by two pieces points of spiral conveying tube inclinations;Such as Fig. 2 and Fig. 5 institute Show, Step 2: with the walking for tunneling assembled equipment 1, the synchronous soil for excavating front end of anterior shield 101;And the prefabricated tunnel of synchronous hoisting Road structure 2 is held in the backing 102 from the open top end investment in the open supporting cabin 103;Then the incremental launching device The prefabricated tunnel structure 2 that pushing tow has been shelved pushes out from the push mouth of the backing 102 to predeterminated position, and by this part Prefabricated tunnel structure 2 and upper one piece of prefabricated tunnel structure 2 connect;As shown in Figure 3 and Figure 6, Step 3: repeating said steps Two, until tunneling assembled equipment 1 runs to the reception foundation pit 7 positioned at the submerged tunnel other end, complete all prefabricated tunnel structures Laying;Wherein, all prefabricated tunnel structures 2 paving is laid with after splicing completes, be formed by the both ends in tunnel respectively with revetment On the tunnel 6 constructed be connected, form a complete channel.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described In step 1, promotes that tunnels assembled equipment to originate reaction frame originating to be provided in foundation pit, provide the beginning to tunnel assembled equipment 1 Send out counter-force.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described Incremental launching device is hydraulic cylinder or hydraulic stem.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described 1 sealed bottom of assembled equipment is tunneled, and during push, at the push mouth of the backing 102 between prefabricated tunnel structure 2 Seamless seal contact can be achieved, in order to underwater construction.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described Step 1 further include: assign interim building enclosure 5 towards the one end in waters originating in foundation pit;
The step 2 further include: before tunneling assembled equipment 1 and walking, remove the interim building enclosure 5.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described In step 2, after prefabricated tunnel structure 2 connects, toward its bottom and side synchronous grouting, and top synchronizes backfill.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, in step Before rapid two, if submerged tunnel bottom foundation soil is soft layer, consolidation process is carried out to soft de- ground, guarantees that ground is full Sufficient equipment construction requirement for bearing capacity.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described Receiving foundation pit is also to set up cofferdam, and draw water to be formed.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described It tunnels inside assembled equipment and is equipped with screw conveyor, the interior installation helical feed pipeline.
In one of embodiment, the construction method for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel is described The two sides of anterior shield in the width direction are vertically equipped with breast boards respectively, for supporting and retaining system shield body top to ground (or mud face) two sides The soil body, therefore anterior shield is directly excavated to ground, and backing is backfilled to former mud face (ground) in tunnel assembly molding rear shell immediately.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and legend shown and described herein.

Claims (10)

1. a kind of construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which comprises the following steps:
Step 1: setting up cofferdam in submerged tunnel one end to be onstructed, the excavation that draws water, which is formed, originates foundation pit, and driving is completed in it and is spelled Installing is standby assembled;
The assembled equipment of the driving includes anterior shield and backing mutually hinged, wherein the anterior shield front end is equipped with for digging Cutter hub;The backing top upwardly extends and opening, and open end is higher than the water surface in waters to be onstructed, is formed and is hung for launching The open supporting cabin of the prefabricated tunnel structure of dress;The anterior shield rear end is equipped with incremental launching device;The backing rear end is locally opened wide, Form a push mouth passed through for prefabricated tunnel structure;
Set spiral conveying tube in the assembled equipment of the driving, one end towards the anterior shield cutter hub digging position, before absorption The soil that shield pick is dug, the other end are in communication with the outside by the open end in open supporting cabin, and the soil of absorption is delivered to outside;Its In, the spiral conveying tube is spliced by two pieces points of spiral conveying tube inclinations;
Step 2: with the walking for tunneling assembled equipment, the synchronous soil for excavating front end of anterior shield;And the prefabricated tunnel knot of synchronous hoisting Structure is held in the backing from the open top end investment in the open supporting cabin;Then the incremental launching device pushing tow is shelved Prefabricated tunnel structure, push out from the push mouth of the backing to predeterminated position, and by the prefabricated tunnel structure of this part and Upper one piece of prefabricated tunnel structure connects, and in its bottom and side synchronous grouting, the underwater backfilling of earthwork of structural top;
Step 3: repeating said steps two, until tunneling assembled equipment runs to the reception foundation pit positioned at the submerged tunnel other end, Complete the laying of all prefabricated tunnel structures.
2. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described In step 1, promotes that tunnels assembled equipment to originate reaction frame originating to be provided in foundation pit, provide the beginning to tunnel assembled equipment Send out counter-force.
3. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described Incremental launching device is hydraulic cylinder or hydraulic stem.
4. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described Assembled device bottom sealing is tunneled, and during push, it can be real between prefabricated tunnel structure at the push mouth of the backing Existing seamless seal contact, in order to underwater construction.
5. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described Step 1 further include: assign interim building enclosure towards the one end in waters originating in foundation pit;
The step 2 further include: before tunneling assembled equipment walking, remove the interim building enclosure.
6. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that in step Before rapid two, if submerged tunnel bottom foundation soil is soft layer, consolidation process is carried out to soft de- ground, guarantees that ground is full Sufficient equipment construction requirement for bearing capacity.
7. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described Receiving foundation pit is also setting cofferdam, and draws water and excavate formation.
8. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described It tunnels inside assembled equipment and is equipped with screw conveyor, the interior installation helical feed pipeline.
9. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that described The two sides of anterior shield in the width direction are vertically equipped with breast boards respectively.
10. the construction method as described in claim 1 for being suitable for water-bed shallow embedding prefabrication and assembly construction tunnel, which is characterized in that institute There is prefabricated tunnel structure paving to be laid with after splicing completes, be formed by the both ends in tunnel respectively with the tunnel phase constructed on revetment Connection forms a complete channel.
CN201910545233.2A 2019-06-21 2019-06-21 Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel Pending CN110409497A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910545233.2A CN110409497A (en) 2019-06-21 2019-06-21 Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910545233.2A CN110409497A (en) 2019-06-21 2019-06-21 Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel

Publications (1)

Publication Number Publication Date
CN110409497A true CN110409497A (en) 2019-11-05

Family

ID=68359683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910545233.2A Pending CN110409497A (en) 2019-06-21 2019-06-21 Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel

Country Status (1)

Country Link
CN (1) CN110409497A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113882429A (en) * 2021-10-08 2022-01-04 中铁工程装备集团有限公司 Construction method and construction structure of underground structure

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05332090A (en) * 1992-05-29 1993-12-14 Maeda Corp Shield construction method
JP2003003503A (en) * 2001-06-26 2003-01-08 Ishikawajima Harima Heavy Ind Co Ltd Underwater shield
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel
CN106088149A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 A kind of mechanization rapid constructing method of precast splice type underground gallery
CN106089218A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 Precast assembly underground gallery bimodulus development machine
CN106907164A (en) * 2017-03-27 2017-06-30 中铁隧道勘测设计院有限公司 A kind of water-bed combination of mine shield tunnel docking structure form and its construction method
CN107762523A (en) * 2017-12-06 2018-03-06 徐州迈斯特机械科技有限公司 A kind of constructing tunnel shield structure
CN108868781A (en) * 2018-05-28 2018-11-23 中铁五局集团有限公司 A kind of shield construction method for shale sandy silt soil stratum
CN208486292U (en) * 2018-06-27 2019-02-12 中铁工程装备集团有限公司 A kind of waterproof open cut piping lane equipment suitable for rich water soft stratum
CN208633148U (en) * 2018-08-08 2019-03-22 天津恒信有源机械设备有限公司 One kind is bright to open push-bench

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05332090A (en) * 1992-05-29 1993-12-14 Maeda Corp Shield construction method
JP2003003503A (en) * 2001-06-26 2003-01-08 Ishikawajima Harima Heavy Ind Co Ltd Underwater shield
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel
CN106088149A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 A kind of mechanization rapid constructing method of precast splice type underground gallery
CN106089218A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 Precast assembly underground gallery bimodulus development machine
CN106907164A (en) * 2017-03-27 2017-06-30 中铁隧道勘测设计院有限公司 A kind of water-bed combination of mine shield tunnel docking structure form and its construction method
CN107762523A (en) * 2017-12-06 2018-03-06 徐州迈斯特机械科技有限公司 A kind of constructing tunnel shield structure
CN108868781A (en) * 2018-05-28 2018-11-23 中铁五局集团有限公司 A kind of shield construction method for shale sandy silt soil stratum
CN208486292U (en) * 2018-06-27 2019-02-12 中铁工程装备集团有限公司 A kind of waterproof open cut piping lane equipment suitable for rich water soft stratum
CN208633148U (en) * 2018-08-08 2019-03-22 天津恒信有源机械设备有限公司 One kind is bright to open push-bench

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113882429A (en) * 2021-10-08 2022-01-04 中铁工程装备集团有限公司 Construction method and construction structure of underground structure

Similar Documents

Publication Publication Date Title
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN106907164A (en) A kind of water-bed combination of mine shield tunnel docking structure form and its construction method
CN106567717A (en) Construction oblique channel structure utilizing subway exit and entrance and construction method
CN106223989A (en) Unsymmetrial loading tunnel hole excavation safeguard structure and construction method
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form
CN110017145A (en) A kind of sea area shield mine joins jointing and its construction method in Tunnel
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN105041327B (en) Bored tunnel is counter to dig shield method of reseptance
CN103726495A (en) Offshore deep foundation pit supporting structure and construction method thereof
CN105863648A (en) Underground-excavation shallow-covering large-cross-section tunnel construction method
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
JP4132442B2 (en) Tunnel construction method
CN104480929A (en) Pile and wall integrated construction method for applying occlusive pile into permanent basement external wall
CN100425773C (en) Grille type connection method of rigid joint for underground continuous wall
CN108360384B (en) Construction method of jacking for underwater channel
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN110409497A (en) Construction method suitable for water-bed shallow embedding prefabrication and assembly construction tunnel
CN112145227B (en) Facility for preventing water inrush and mud gushing of tunnel and construction method
CN214091881U (en) Structure suitable for bias hole entering under poor geological conditions
CN108755719A (en) Seabed municipal tunnel over strait cofferdam open cutting construction method
JP2009174179A (en) Method for constructing shield excavator receptacle and method for reaching shield excavator
CN106958448B (en) A kind of shallow tunnel construction method and system
CN221973520U (en) A split shield launching shaft and tunnel connection structure used in nuclear power plants
CN206034466U (en) Foundation ditch or basic groove precipitation system for construction
CN107012888B (en) A kind of tunneling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191105

RJ01 Rejection of invention patent application after publication