Pollak et al., 2014 - Google Patents
Tunneling Under the Sydney Opera House: The Vehicle Access and Pedestrian Safety ProjectPollak et al., 2014
- Document ID
- 9898036311480600543
- Author
- Pollak S
- Sokol N
- Adams M
- McTaggart G
- Clarke B
- Publication year
- Publication venue
- North American Tunneling: 2014 Proceedings
External Links
Snippet
The current traffic arrangements for servicing the Sydney Opera House (SOH) necessitates that delivery vehicles share the open forecourt and boardwalk areas with visitors, complicating logistics and resulting in several incidents per year. The Vehicle Access and …
- 230000005641 tunneling 0 title description 9
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/29—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
- E04C3/293—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
- E04C3/294—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete of concrete combined with a girder-like structure extending laterally outside the element
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B41/00—Equipment or details not covered by groups E21B15/00 - E21B40/00
- E21B41/0035—Apparatus or methods for multilateral well technology, e.g. for the completion of or workover on wells with one or more lateral branches
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Fang et al. | Shallow tunnelling method (STM) for subway station construction in soft ground | |
CA2853564C (en) | Undercut excavation method with continuous concrete floors | |
RU2510444C2 (en) | Three-arched underground station of column type and its erection methods (yurkevich device and methods) | |
Frischmann et al. | Protection of the Mansion House against Damage Caused by Ground Movements due to the Docklands Light Railway Extension. | |
Sandbak et al. | Ground support strategies at the turquoise ridge joint venture, Nevada | |
Amiri et al. | Comparison of shallow tunneling method with pile and rib method for construction of subway station in soft ground | |
HOEK et al. | Design of large powerhouse caverns in weak rock | |
Pollak et al. | Tunneling Under the Sydney Opera House: The Vehicle Access and Pedestrian Safety Project | |
Florkowska | Example building damage caused by mining exploitation in disturbed rock mass | |
Sokol et al. | Tunnelling under the Sydney Opera House: the vehicle access and pedestrian safety project | |
Yeow et al. | Case histories back analyses for the application of the Observational Method under Eurocodes for the SCOUT project | |
Çimentepe | Evaluation of structural analysis methods used for the design of TBM segmental linings | |
Zargar et al. | Top-Down construction method: A case study of commercial building in Tehran | |
De Matteis et al. | The 3D-BIM-FEM modeling of the mairie des Lilas Paris metro station line 11–from design to execution | |
Herranz et al. | SEM crossover cavern in Downtown LA | |
Arumugam et al. | Seismic and safety performance assessment and strengthening of tunnels in Wellington | |
Lyons et al. | Development of sprayed concrete linings for London underground bond street station upgrade project, London, UK | |
Sandbak et al. | Ground support strategies for weak ground masses at the Turquoise Ridge Joint Venture, Nevada | |
Hadjigeorgiou et al. | An investigation into the behaviour of shotcrete pillars | |
Skalla et al. | 3 SEM Stations on ECLRT: Design and construction challenges mastered | |
Barták | Influence of New Construction Projects on Vinohrady Tunnels | |
Merlini et al. | Brenner Base Tunnel, Lots Mules 2-3 (Italy): The construction experience of the emergency stop in Trens | |
Yang | Numerical Modeling Techniques to Solving Complex Geotechnical | |
King | Rock Tunnels | |
Oh et al. | Numerical analysis of shaft and tunnel design adjacent to station cavern |