JPS6059228A - Steel sheet pile sheathing work using stay steel sheet pile - Google Patents
Steel sheet pile sheathing work using stay steel sheet pileInfo
- Publication number
- JPS6059228A JPS6059228A JP16650483A JP16650483A JPS6059228A JP S6059228 A JPS6059228 A JP S6059228A JP 16650483 A JP16650483 A JP 16650483A JP 16650483 A JP16650483 A JP 16650483A JP S6059228 A JPS6059228 A JP S6059228A
- Authority
- JP
- Japan
- Prior art keywords
- steel sheet
- sheet piles
- driven
- sheet pile
- stay
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【発明の詳細な説明】
この発明は、土留工において所定間隔に掘削側に張り出
すように円孤状に土留鋼矢板として直線鋼矢板を連結し
打込み、各円弧の交点部より反対側に控え鋼矢板として
直線鋼矢板を連結して最終端部にアンカー金具を固着し
て一体に打込んだ後、所定地盤まで根切り施工する鋼矢
板土留工法に関する。Detailed Description of the Invention In earth retaining work, straight steel sheet piles are connected and driven as earth retaining steel sheet piles at predetermined intervals so as to protrude toward the excavation side. This invention relates to a steel sheet pile earth retaining method in which straight steel sheet piles are connected as steel sheet piles, anchor fittings are fixed to the final ends, and the anchor fittings are fixed and driven into one piece, and then root cutting is carried out to a predetermined ground level.
従来、土留工における土留壁の安定には、腹起し、切梁
または土留アンカーを建込んで行われているが、この切
梁または土留アンカーの設置は、切梁またはアンカー設
置位置が施工できる位置まで&!切りを行ってから切梁
またはアンカーを行って土留壁の安定を図っている。こ
の場合、切梁またはアンカーを設置して、さらに切梁ま
たは土留アンカー設置位置下を掘削すると土留壁には掘
削にしたがって変形し、切梁または土留アンカーの荷重
が増加したり地表面の変形が大きくなる欠点があった。Conventionally, the stabilization of earth retaining walls in earth retaining works has been carried out by raising the slope, installing struts or earth retaining anchors, but the installation of these struts or earth retaining anchors can be done at the position where the struts or anchors are installed. To the position &! After cutting, struts or anchors are installed to stabilize the retaining wall. In this case, if you install a strut or anchor and then excavate below the location where the strut or earth retaining anchor is installed, the earth retaining wall will deform due to the excavation, and the load on the strut or earth retaining anchor will increase and the ground surface will deform. There was a drawback to growing up.
この発明は、−上述の欠点を解決して掘削側に張り出す
ように円孤状の土留鋼矢板及び控え鋼矢板として直線鋼
矢板を連結して、その最終端部にアンカー金具を取付け
て打込む土留工法を提供するものである。This invention solves the above-mentioned drawbacks and connects straight steel sheet piles as circular arc-shaped earth retaining steel sheet piles and bracing steel sheet piles so as to protrude toward the excavation side, and attaches anchor fittings to the final ends of the straight steel sheet piles. This method provides an earth retaining method that can be used in a variety of ways.
次に、この発明の実施例を図面に基づいて説明する。第
1図は、この発明の平面図、第2図は縦断面図、第3図
は控え鋼矢板とアンカー金具の取付は詳細図である。図
において、地盤左向に所定間隔に土留鋼矢板/として直
線Wi矢板を掘削側に張り出すように円孤状に連結して
打込み、各円弧の交点部乙から控え鋼矢板−として直線
鋼矢板を主働崩壊角の背面A−A線まで連結し打込み、
かつ控え鋼矢板2の最端部に平板状または凹形状のアン
カー金具3を固着して、(必要あれば補強M&を図示の
ように取付ける)一体として所定深さまで地盤Sに4〕
込む鋼矢板土留工法である。Next, embodiments of the present invention will be described based on the drawings. FIG. 1 is a plan view of the present invention, FIG. 2 is a longitudinal sectional view, and FIG. 3 is a detailed view of the installation of the steel sheet pile and anchor fittings. In the figure, the straight Wi sheet piles are connected and driven in a circular arc so as to project toward the excavation side at predetermined intervals to the left of the ground as earth retaining steel sheet piles, and the straight steel sheet piles as retaining steel sheet piles are driven from the intersection point B of each arc. Connect and drive to the back A-A line of the active collapse angle,
In addition, a flat or concave anchor metal fitting 3 is fixed to the end of the steel sheet pile 2, and the anchor metal fittings 3 are fixed to the ground S to a predetermined depth (if necessary, reinforcement M& is installed as shown).
This is a steel sheet pile earth retaining method.
したがって、土留鋼矢板/が円孤状に連結、打込むこと
により背面からの荷重を土留鋼矢板/の引張力で抵抗さ
せることができ、また、控え鋼矢板2の最端部にアンカ
ー金具3を取付けることにより周面土との摩擦力により
引張抵抗力を増大させることが可能となり、一度に所定
深さまで地盤Sを掘削することができる。Therefore, by connecting and driving the earth-retaining steel sheet piles in an arc shape, the load from the back can be resisted by the tensile force of the earth-retaining steel sheet piles. By attaching it, it becomes possible to increase the tensile resistance force due to the frictional force with the surrounding soil, and the ground S can be excavated to a predetermined depth at one time.
上述の通り、この発明は従来の鋼矢板アースアンカー工
法や鋼矢板二重締切工法に比して、工期的に有利となり
、土留工林料の転用も可能となり、工費の低順が期待さ
れる。As mentioned above, compared to the conventional steel sheet pile earth anchor construction method and steel sheet pile double cofferdam construction method, this invention is advantageous in terms of construction period, enables the diversion of earth retaining materials, and is expected to lower construction costs. .
【図面の簡単な説明】
第1図は、この発明の平面図、第2図は縦断面図、第3
図は控え鋼矢板とアンカー金具の取付は詳細図である。
/:ニに情調矢板
2:控え鋼矢板
3、アンカー金具
Il:補 強材
S:地 盤
乙:交 点 部[Brief Description of the Drawings] Fig. 1 is a plan view of the present invention, Fig. 2 is a longitudinal sectional view, and Fig. 3 is a longitudinal sectional view of the present invention.
The figure shows a detailed view of the installation of the steel sheet pile and anchor fittings. /: 2nd floor sheet pile 2: Steel sheet pile 3, anchor metal fittings Il: Reinforcement material S: Ground O: Intersection part
Claims (1)
線鋼矢板を掘削側に張り出すように円弧状に直結して打
込み、各円弧の交点部より反対側に控え鋼矢板として直
線鋼矢板を連結して、直線鋼矢板の最終端部にアンカー
金具を固着して一体として主慟崩壊角の背面まで打込ん
だ後、所定地盤まで根切り施工することを特徴とする控
え鋼矢板による鋼矢板土留工法In earth retaining work, straight steel sheet piles as earth retaining steel sheet piles are directly connected and driven in an arc shape so as to project toward the excavation side at specified intervals, and the straight steel sheet piles are connected as backing steel sheet piles on the opposite side from the intersection of each arc. The steel sheet pile earth retaining method is characterized in that the anchor fittings are fixed to the final end of the straight steel sheet piles, and the anchor fittings are driven as one piece to the back of the main slope collapse angle, and then the roots are cut to a specified ground level. construction method
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16650483A JPS6059228A (en) | 1983-09-12 | 1983-09-12 | Steel sheet pile sheathing work using stay steel sheet pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16650483A JPS6059228A (en) | 1983-09-12 | 1983-09-12 | Steel sheet pile sheathing work using stay steel sheet pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6059228A true JPS6059228A (en) | 1985-04-05 |
Family
ID=15832579
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16650483A Pending JPS6059228A (en) | 1983-09-12 | 1983-09-12 | Steel sheet pile sheathing work using stay steel sheet pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6059228A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7946791B2 (en) * | 2005-08-09 | 2011-05-24 | Pilepro, Llc | Arrangement of sheet-pile components |
US9657454B2 (en) * | 2000-07-28 | 2017-05-23 | Pnd Engineers, Inc. | Earth retaining system such as a sheet pile wall with integral soil anchors |
US10094088B1 (en) * | 2017-10-31 | 2018-10-09 | Earth, Inc. | Sheet pile retaining wall system |
-
1983
- 1983-09-12 JP JP16650483A patent/JPS6059228A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9657454B2 (en) * | 2000-07-28 | 2017-05-23 | Pnd Engineers, Inc. | Earth retaining system such as a sheet pile wall with integral soil anchors |
US10287741B2 (en) | 2000-07-28 | 2019-05-14 | Pnd Engineers, Inc. | Earth retaining system such as a sheet pile wall with integral soil anchors |
US7946791B2 (en) * | 2005-08-09 | 2011-05-24 | Pilepro, Llc | Arrangement of sheet-pile components |
KR101085041B1 (en) * | 2005-08-09 | 2011-11-22 | 파일프로 엘엘씨 | Structure of Sheet-pile Wall Constructs |
US10094088B1 (en) * | 2017-10-31 | 2018-10-09 | Earth, Inc. | Sheet pile retaining wall system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2576932B2 (en) | Construction method of independent mountain retaining wall | |
CN108005086B (en) | A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure | |
JPS6059228A (en) | Steel sheet pile sheathing work using stay steel sheet pile | |
JPH11303087A (en) | Retaining wall using corrosion-resistant structure anchor | |
JP2007303099A (en) | Foundation structure | |
KR102194381B1 (en) | Pile for Earth self-retaining wall using double I beam | |
JPH02289718A (en) | Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill | |
KR102195496B1 (en) | Pile for earth self-retaining wall using cast in place concrete pile with double I beam | |
JP3244324B2 (en) | Mountain retaining method | |
JP3633326B2 (en) | Ground reinforcement method | |
JPS59192125A (en) | Settlement work of concrete pile with screw | |
JP2000017647A (en) | How to install underwater structures | |
JPH04115024A (en) | Yamadome construction method | |
JP2523234B2 (en) | Anchor retaining wall | |
JP3012896B2 (en) | Reverse cutting method combined with advance cutting | |
JP2893422B2 (en) | Construction method of underground structure | |
JPH0634041U (en) | Multi-blade conical steel pile | |
JP2785828B2 (en) | Steep slope construction method for existing embankment slope | |
JP2628150B2 (en) | Shovel anchor | |
JPS6043495B2 (en) | How to build a retaining wall | |
JP2881001B1 (en) | Earth retaining wall construction method for cutting land mountain | |
JPS6272817A (en) | Construction of retaining wall concurrently serving as sheathing | |
JP3362961B2 (en) | How to build large underground structures | |
JPS6051226A (en) | Steel sheet pile sheathing work using stay steel sheet pile | |
JP2006016774A (en) | Method for using diameter-enlarged pipe pile |