Construction method for roof unitsInfo
- Publication number
- JPH07122295B2 JPH07122295B2 JP2190014A JP19001490A JPH07122295B2 JP H07122295 B2 JPH07122295 B2 JP H07122295B2 JP 2190014 A JP2190014 A JP 2190014A JP 19001490 A JP19001490 A JP 19001490A JP H07122295 B2 JPH07122295 B2 JP H07122295B2
- Authority
- JP
- Japan
- Prior art keywords
- roof
- work
- unit
- nut
- drainage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、ユニット住宅の屋根を構成する屋根ユニット
の螻羽(けらば)施工方法に係り、クレーン吊り込み作
業用の吊りボルトを螺合するためのナットが設けられる
屋根ユニットに利用できるものである。Description: TECHNICAL FIELD The present invention relates to a method for constructing a roof unit constituting a roof of a unit house, and a screw for suspending a crane is screwed into the roof unit. It can be used for a roof unit provided with a nut for.
ユニット工法で建てられるユニット住宅は、建設現場に
おいて複数の住宅ユニットをクレーン吊り込み作業で所
定位置に配置して組み合わせることにより建てられ、こ
のユニット住宅の屋根も複数の屋根ユニットをクレーン
吊り込み作業で所定位置に配置することにより形成され
る。従来から屋根ユニットのクレーン吊り込み作業は吊
りボルトを使用して行われ、このため屋根ユニットには
この吊りボルトを螺合するためのナットを設けなければ
ならない。A unit house constructed by the unit construction method is built by arranging and combining a plurality of housing units at a predetermined position at the construction site by crane hoisting work.The roof of this unit house is also built by crane hoisting work. It is formed by arranging it at a predetermined position. Conventionally, the crane hoisting operation of the roof unit is performed by using a hanging bolt, and therefore the roof unit must be provided with a nut for screwing the hanging bolt.
ユニット住宅はできるだけ多くの作業を工場で終了して
しまい、これにより工業化率の向上、建設現場作業割合
の低下を図り、建築コストの低減、建設現場作業期間の
短縮を達成することを主要目的としている。このため、
屋根ユニットについては、屋根仕上材等の取り付け作業
を工場で終了してしまい、工場での完成度を高めること
が求められている。The main purpose of the unit housing is to finish as much work as possible at the factory, thereby increasing the industrialization rate, reducing the work rate at the construction site, reducing the construction cost, and shortening the construction site work period. There is. For this reason,
As for the roof unit, the work of installing roof finishing materials and the like is completed at the factory, and it is required to improve the degree of perfection at the factory.
前述の通り屋根ユニットには吊りボルト螺合用のナット
を設けなればならないが、このナットは建設現場でのク
レーン吊り込み作業時に使用されるものであるため、工
場ではこのナットの配置箇所を未完成部分として残して
おき、建設現場でのクレーン吊り込み作業後にこの箇所
を完成させなければならない。このナット配置箇所につ
いての建設現場での完成作業が面倒で手間と時間がかか
るものとなると、ユニット住宅の前記主要目的を充分に
達成できなくなるため、このような問題が発生すること
のない解決手段が求められている。As mentioned above, the roof unit must be provided with a nut for screwing the hanging bolt, but this nut is used during crane lifting work at the construction site. It must be left as a part and completed after the crane hoisting work at the construction site. If the completion work at the construction site for the nut placement location is troublesome and time-consuming, the main purpose of the unit housing cannot be sufficiently achieved, and therefore such a problem does not occur. Is required.
本発明の目的は、屋根ユニットの工場での完成度を高め
ることができるとともに、吊りボルト螺合用ナットの配
置箇所についての建設現場での完成作業を短時間で容易
に行なえる屋根ユニットの螻羽施工方法を提供するとこ
ろにある。It is an object of the present invention to improve the degree of completion of a roof unit in a factory, and also to complete the completion work at a construction site about the location of a hanging bolt screwing nut in a short time easily. It is in the process of providing a method.
本発明に係る屋根ユニットの螻羽施工方法は、吊りボル
トを螺合するナットが設けられ、前記吊りボルトによる
クレーン吊り込み作業でユニット住宅の所定位置に配置
されることによりこのユニット住宅の屋根を構成する屋
根ユニットにおいて、工場で、切欠部が形成された埋木
を螻羽捨て水切りと対向させて螻羽に配置する作業と、
前記切欠部の位置において前記ナットを前記屋根ユニッ
トの骨組みに取り付ける作業と、前記切欠部と対応する
位置に欠除部が形成された耐水シートを前記埋木と前記
螻羽捨て水切りとに被せる作業とを含む作業を行い、建
設現場で前記クレーン吊り込み作業後に前記ナットから
前記吊りボルトを取り外した後、前記切除部を耐水シー
ト片で塞ぐ作業と、前記埋木と前記螻羽捨て水切りとに
螻羽カバーを被せる作業とを含む作業を行うことを特徴
とするものである。In the roof unit construction method for a roof unit according to the present invention, a nut for screwing a hanging bolt is provided, and the roof of this unit house is configured by arranging the nut at a predetermined position in a crane hoisting operation using the hanging bolt. In the roof unit to do, in the factory, the operation of arranging the embedded tree in which the cutout portion is formed on the feathers facing the drainage drainer
The work of attaching the nut to the frame of the roof unit at the position of the cutout portion, and the work of covering the buried tree and the drainage of the turkey feather with a water resistant sheet having a cutout portion at a position corresponding to the cutout portion. After including the work, after removing the hanging bolt from the nut after the crane hanging work at the construction site, work to close the cutout part with a waterproof sheet piece, and cover the buried tree and the drainage drainage with a feather cover It is characterized by performing work including work.
工場では埋木と螻羽捨て水切りとに耐水シートを被せる
作業まで行われ、埋木の切欠部と耐水シートの切除部と
からナットが露出している。建設現場ではナットに吊り
ボルトを螺合することにより屋根ユニットのクレーン吊
り込み作業が行われ、この作業後、吊りボルトはナット
から取り外される。そして、この後、耐水シートの欠除
部を耐水シート片で塞ぐ作業と、埋木と螻羽捨て水切り
とに螻羽カバーを被せる作業とが行われ、これにより、
工場では未完成部分として残されていたナット配置箇所
が建設現場で完成することになる。At the factory, even up to the work of covering the burying trees and the drainage of the feathers with a waterproof sheet, the nuts are exposed from the cutouts of the burial tree and the cutouts of the waterproof sheet. At the construction site, the crane is suspended from the roof unit by screwing the suspension bolt to the nut, and after this work, the suspension bolt is removed from the nut. Then, after this, the work of closing the cutout portion of the waterproof sheet with the waterproof sheet piece, and the operation of covering the burrow cover with the buried tree and the drainage drainage of the spectacle feathers are performed, thereby,
The location of the nuts, which was left unfinished at the factory, will be completed at the construction site.
以下に本発明の一実施例を添付図面に基づいて説明す
る。An embodiment of the present invention will be described below with reference to the accompanying drawings.
第1図は本実施例が適用されたユニット住宅の屋根1を
示し、この屋根1は3種類の屋根ユニット、すなわち中
央屋根ユニット2と、この中央屋根ユニット2の両隣り
の中間屋根ユニット3と、この中間屋根ユニット3の片
隣りの軒側屋根ユニット4とからなり、これらの屋根ユ
ニット2,3,4が桁方向に各2個並設され、屋根1は切妻
屋根となっている。それぞれの屋根ユニット2,3,4の螻
羽5にはナット6が設けられており、また屋根ユニット
の桁方向連結部7にもナット6が設けられている。FIG. 1 shows a roof 1 of a unit house to which this embodiment is applied. The roof 1 includes three types of roof units, that is, a central roof unit 2 and an intermediate roof unit 3 on both sides of the central roof unit 2. The intermediate roof unit 3 and the eave-side roof unit 4 that is adjacent to the one side, and the roof units 2, 3 and 4 are arranged side by side in the direction of the girder, and the roof 1 is a gable roof. A nut 6 is provided on the wing 5 of each roof unit 2, 3 and 4, and a nut 6 is also provided on the girder direction connecting portion 7 of the roof unit.
螻羽5におけるナット6の配置構造は各屋根ユニット2,
3,4について共通であるため、第2図は中間屋根ユニッ
ト3の螻羽5におけるナット6の配置構造を示してい
る。The arrangement structure of the nuts 6 on the Nobuta feather 5 is as follows:
Since 3 and 4 are common to each other, FIG. 2 shows the arrangement structure of the nuts 6 in the wing 5 of the intermediate roof unit 3.
中間屋根ユニット3のアングル材からなる骨組み8には
屋根下地材9と壁下地材10とが結合され、これらの屋根
下地材9、壁下地材10の外面には耐水シート11,12が敷
かれている。屋根下地材9には耐水シート11の上から屋
根仕上材13が取り付けられ、壁下地材10には耐水シート
11,12の外側から壁仕上材14が取り付けられている。屋
根仕上材13と耐水シート11とで螻羽捨て水切り15の下水
平部15Aが挟着され、この螻羽捨て水切り15は垂直部15B
から延びる上傾斜部15Cを有し、この上傾斜部15Cは屋根
仕上材13の端部上方を覆うものとなっている。A roof base material 9 and a wall base material 10 are joined to a frame 8 made of an angle material of the intermediate roof unit 3, and waterproof sheets 11 and 12 are laid on the outer surfaces of the roof base material 9 and the wall base material 10. ing. A roof finishing material 13 is attached to the roof base material 9 from above the water resistant sheet 11, and a water resistant sheet is used for the wall base material 10.
Wall finishing material 14 is attached from the outside of 11,12. The roof finishing material 13 and the waterproof sheet 11 sandwich the lower horizontal portion 15A of the drainage 15, which is a vertical portion 15B.
Has an upper inclined portion 15C extending from the upper inclined portion 15C, and the upper inclined portion 15C covers an upper end portion of the roof finishing material 13.
中間屋根ユニット3の螻羽5には埋木16が配置され、こ
の埋木16は、第3図、第4図で明らかな通り、螻羽捨て
水切り15と対向しながら屋根1の棟から軒に向かって延
び、その長手方向の2箇所に切欠部17が形成されてい
る。埋木16および螻羽捨て水切り15の上傾斜部15Cには
耐水シート18が被せられ、この耐水シート18には埋木16
の切欠部17と対応する位置に切除部19が形成されてい
る。中間屋根ユニット3には埋木16の切欠部17と対応す
る位置においてナット6が配置され、このナット6は前
記耐水シート11,12、骨組み8に上下に貫通挿入されて
骨組み8に溶接で接合され、その上端開口部は埋木16の
切欠部17に臨んでいる。A burial tree 16 is arranged on the Nobori wing 5 of the intermediate roof unit 3, and this vegetative tree 16 extends from the ridge of the roof 1 toward the eaves while facing the drainage drainage 15, as shown in FIGS. 3 and 4. Notches 17 are formed at two positions in the longitudinal direction. The water resistant sheet 18 is placed on the upper sloped portion 15C of the buried tree 16 and the drainage 15 of the feathers for throwing away feathers.
A cutout portion 19 is formed at a position corresponding to the cutout portion 17. A nut 6 is arranged in the intermediate roof unit 3 at a position corresponding to the cutout portion 17 of the embedded tree 16, and the nut 6 is vertically inserted through the water resistant sheets 11 and 12 and the frame 8 and joined to the frame 8 by welding. The upper end opening faces the notch 17 of the embedded tree 16.
以上までの中間屋根ユニット3の製作作業は工場で行わ
れる。すなわち、骨組み8に結合された屋根下地材9、
壁下地材10に耐水シート11,12を介して屋根仕上材13、
壁仕上材14を取り付ける作業、螻羽5に埋木16を捨て水
切り15と対向させて配置する作業、埋木16および螻羽捨
て水切り15の上傾斜部15Cに耐水シート18を被せる作
業、埋木16の切欠部17の位置においてナット6を骨組み
8に取り付ける作業はそれぞれ工場で行われる。また、
中間屋根ユニット3の前記連結部7にも工場でナット6
が取り付けられる。ここまで工場で製作された中間屋根
ユニット3はトラックで建設現場に運ばれる。The above-described manufacturing work of the intermediate roof unit 3 is performed in the factory. That is, the roof base material 9 connected to the frame 8,
Roof finishing material 13, with water resistant sheets 11 and 12 on the wall base material 10.
Work to attach the wall finish material 14, work to dispose the embedded tree 16 on the feathers 5 so as to face the drainer 15, drainage 16 and work to cover the sloped portion 15C of the drainage 15 with the waterproof sheet 18, cutout portion of the bush 16 The work of attaching the nut 6 to the skeleton 8 at the position 17 is carried out at the factory. Also,
At the factory, nuts 6 are also attached to the connecting portion 7 of the intermediate roof unit 3.
Is attached. The intermediate roof unit 3 manufactured up to this point in the factory is transported by truck to the construction site.
建設現場では、第3図に示す通り、螻羽5のナット6お
よび連結部7のナット6に吊りボルト20が螺合され、こ
れらの吊りボルト20にワイヤ21を掛けて中間屋根ユニッ
ト3をクレーン22で吊り上げる。このクレーン吊り込み
作業により中間屋根ユニット3はユニット住宅の所定位
置に配置され、前述した他の屋根ユニット2,4もクレー
ン吊り込み作業で所定位置に配置され、これらの屋根ユ
ニット2,3,4によりユニット住宅の屋根1が形成され
る。At the construction site, as shown in FIG. 3, hanging bolts 20 are screwed onto the nuts 6 of the feathers 5 and the nuts 6 of the connecting portion 7, and the hanging bolts 20 are hung by the wires 21 to attach the intermediate roof unit 3 to the crane 22. Lift up with. By this crane hoisting work, the intermediate roof unit 3 is placed at a predetermined position in the unit house, and the other roof units 2 and 4 described above are also placed at predetermined positions by the crane hoisting work, and these roof units 2, 3, 4 This forms the roof 1 of the unit house.
クレーン吊り込み作業後、それぞれの吊りボルト20はナ
ット6から取り外され、前記耐水シート18の切除部19に
は、第4図の通り、この切除部19より一回り大きい耐水
シート片23があてがわれ、耐水シート18に熱溶着等で固
着される。これにより切除部19は耐水シート片23で塞が
れることになる。After the crane hoisting work, the respective hanging bolts 20 are removed from the nuts 6, and the cut-out portion 19 of the water-resistant sheet 18 has a water-proof sheet piece 23 larger than the cut-out portion 19 as shown in FIG. And is fixed to the waterproof sheet 18 by heat welding or the like. As a result, the cutout portion 19 is blocked by the waterproof sheet piece 23.
この後、埋木16および螻羽捨て水切り15の上傾斜部15C
には耐水シート18、耐水シート片23の上から螻羽カバー
24が被せられ、第5図の通り、この螻羽カバー24は埋木
16、螻羽捨て水切り15の上傾斜部15Cを覆う水平部24Aを
有するとともに、水平部24Aの屋根仕上材13側の端部に
は螻羽捨て水切り15の上傾斜部15Cの上面に係止される
係止部24Bが設けられ、また水平部24Aの壁仕上材14側の
端部には垂直部24Cが設けられ、この垂直部24Cにおいて
螻羽カバー24は釘25で埋木16に固定される。以上により
中間屋根ユニット3の螻羽5は螻羽カバー24により雨仕
舞いされる。After this, the upper sloped part 15C of the buried tree 16 and the drainage 15
On the waterproof sheet 18 and the waterproof sheet piece 23 from the top
24 is covered, and as shown in Fig. 5, this feather cover 24 is a buried tree.
16, while having a horizontal portion 24A that covers the upper inclined portion 15C of the thrown away drainer 15, the end of the horizontal portion 24A on the side of the roof finishing material 13 is locked to the upper surface of the upper inclined portion 15C of the thrown away drainer 15. A locking portion 24B is provided, and a vertical portion 24C is provided at the end of the horizontal portion 24A on the wall finishing material 14 side. At this vertical portion 24C, the furrow cover 24 is fixed to the bush 16 by a nail 25. As described above, the feathers 5 of the intermediate roof unit 3 are rained off by the feather cover 24.
螻羽カバーによる雨仕舞いは他の屋根ユニット2,4につ
いても行われ、またそれぞれの屋根ユニット2,3,4の連
結部7には屋根仕上材の連結部26(第1図参照)が配置
され、この連結部7も雨仕舞いされた構造になる。The rain cover by the Nomoto feather cover is also performed on the other roof units 2, 4, and the connecting portion 26 (see FIG. 1) of the roof finishing material is arranged at the connecting portion 7 of each roof unit 2, 3, 4. The connecting portion 7 also has a structure in which it is protected from rain.
以上のように本実施例によれば、吊りナット20を螺合す
るためのナット6を連結部7以外では螻羽5に配置した
ため、工場では、耐水シート片23と螻羽カバー24の取り
付け作業を除き、中間屋根ユニット3を生産するために
行わなければならない全ての作業を行え、工場でのこの
屋根ユニット3の完成度を高めることができる。また、
埋木16には切欠部17が、耐水シート片18には欠除部19が
それぞれ形成されているため、ナット6の上端開口部を
外部に露出させた状態で中間屋根ユニット3を建設現場
に運ぶことができ、このため建設現場ではただちにナッ
ト6に吊りボルト20を螺合させることができて屋根ユニ
ット3のクレーン吊り込み作業を迅速に開始できる。As described above, according to the present embodiment, the nut 6 for screwing the hanging nut 20 is arranged on the feathers 5 except the connecting portion 7. Therefore, in the factory, the work of attaching the waterproof sheet piece 23 and the feather cover 24 is excluded. , All the work that must be done to produce the intermediate roof unit 3 can be done and the completeness of this roof unit 3 in the factory can be increased. Also,
Since the notch 17 is formed in the embedded tree 16 and the notch 19 is formed in the waterproof sheet piece 18, the intermediate roof unit 3 is carried to the construction site with the upper end opening of the nut 6 exposed to the outside. Therefore, at the construction site, the hanging bolt 20 can be immediately screwed into the nut 6 and the crane hoisting operation of the roof unit 3 can be started quickly.
さらに、クレーン吊り込み作業終了後は、吊りボルト20
をナット6から取り外した後、耐水シート片23で耐水シ
ート18の欠除部19を塞ぐ作業とこの上に螻羽カバー24を
被せる作業とを行うことにより、螻羽5を完成させるこ
とができ、工場で未完成部分として残されていたナット
6の配置箇所を短時間で完成させることができる。この
ため、ユニット住宅の主要目的、すなわち建設現場作業
をできるだけ簡単化してその施工時間を短縮することを
十分に達成できるようになる。In addition, after lifting the crane,
After removing the nut 6 from the nut 6, the work 5 for closing the cutout portion 19 of the water resistant sheet 18 with the water resistant sheet piece 23 and the work for covering the rye feather cover 24 on it can complete the feather 5 Thus, the location where the nut 6 is left as an unfinished portion can be completed in a short time. Therefore, the main purpose of the unit house, that is, the work at the construction site can be simplified as much as possible and the construction time can be shortened sufficiently.
以上の実施例は屋根が切妻屋根の場合であったが、本発
明を適用できる屋根はこれに限定されず、例えば第6図
に示す通りペントハウス32が設けられる屋根31の屋根ユ
ニット33にも適用できる。In the above embodiment, the roof is a gable roof, but the roof to which the present invention can be applied is not limited to this, and is also applied to the roof unit 33 of the roof 31 provided with the penthouse 32 as shown in FIG. 6, for example. it can.
また、本発明は屋根仕上材や螻羽カバーが短寸法のもの
を順次差し込む構造になっている場合にも適用できる。The present invention can also be applied to the case where the roof finishing material and the feather cover have a structure in which short-sized ones are sequentially inserted.
さらに、埋木の切欠部や耐水シートの欠除部は前記実施
例の凹欠状のものに限定されず、例えば孔等の開口形状
でもよい。Further, the cutout portion of the embedded tree and the cutout portion of the water resistant sheet are not limited to the recessed shape of the above-mentioned embodiment, and may be an opening shape such as a hole.
本発明によれば、吊りボルト螺合用のナットを設けてい
るにもかかわらず屋根ユニットを工場で完成度を高めて
生産することができ、かつ、建設現場ではナットが配置
された箇所を短時間で完成させることができ、建設現場
作業の簡単化を達成できる。According to the present invention, a roof unit can be produced in a factory with a high degree of perfection in spite of providing a nut for screwing a hanging bolt, and at a construction site, a place where the nut is arranged can be located in a short time. Can be completed in, and the construction site work can be simplified.
第1図は本発明が適用される屋根の一例である切妻屋根
の斜視図、第2図は第1図で示された屋根ユニットの螻
羽部分の断面図、第3図は第2図の屋根ユニットのクレ
ーン吊り込み作業を示す斜視図、第4図は螻羽を構成す
る各部材を示す分解斜視図、第5図は吊りボルトを取り
外して螻羽カバー等を取り付けた後を示す第2図と同様
の図、第6図は本発明を適用できる他の屋根を示す斜視
図である。 1,31…屋根、2,3,4,33…屋根ユニット、5…螻羽、6…
ナット、8…骨組み、11,12,18…耐水シート、15…螻羽
捨て水切り、16…埋木、17…切欠部、19…欠除部、20…
吊りボルト、22…クレーン、23…耐水シート片、24…螻
羽カバー。FIG. 1 is a perspective view of a gable roof which is an example of a roof to which the present invention is applied, FIG. 2 is a cross-sectional view of the nodule portion of the roof unit shown in FIG. 1, and FIG. 3 is the roof of FIG. Fig. 4 is a perspective view showing the crane hanging operation of the unit, Fig. 4 is an exploded perspective view showing each member constituting the wing, and Fig. 5 is the same as Fig. 2 showing the wing cover removed and the wing cover removed. And FIG. 6 are perspective views showing another roof to which the present invention can be applied. 1,31 ... Roof, 2,3,4,33 ... Roof unit, 5 ... Motowa, 6 ...
Nuts, 8 ... Skeleton, 11, 12, 18 ... Water resistant sheet, 15 ... Drainage of spectacles, 16 ... Budding, 17 ... Notch, 19 ... Notch, 20 ...
Hanging bolts, 22 ... Cranes, 23 ... Water resistant sheet pieces, 24 ... Rubber cover.
Claims (1)
前記吊りボルトによるクレーン吊り込み作業でユニット
住宅の所定位置に配置されることによりこのユニット住
宅の屋根を構成する屋根ユニットにおいて、工場で、切
欠部が形成された埋木を螻羽捨て水切りと対向させて螻
羽に配置する作業と、前記切欠部の位置において前記ナ
ットを前記屋根ユニットの骨組みに取り付ける作業と、
前記切欠部と対応する位置に欠除部が形成された耐水シ
ートを前記埋木と前記螻羽捨て水切りとに被せる作業と
を含む作業を行い、建設現場で前記クレーン吊り込み作
業後に前記ナットから前記吊りボルトを取り外した後、
前記欠除部を耐水シート片で塞ぐ作業と、前記埋木と前
記螻羽捨て水切りとに螻羽カバーを被せる作業とを含む
作業を行うことを特徴とする屋根ユニットの螻羽施工方
法。1. A nut for screwing a hanging bolt is provided,
In the roof unit that constitutes the roof of this unit house by being placed at a predetermined position in the unit house by the crane hoisting work using the hanging bolt, in the factory, the buried tree with the notch formed is opposed to the drainage drainage A work of arranging on the Nobuta feather, and a work of attaching the nut to the frame of the roof unit at the position of the cutout portion,
Performing a work including a work of covering a water resistant sheet having a cutout portion at a position corresponding to the cutout portion on the embedded tree and the drainage drainage of the 螑 feather, and hanging from the nut after the crane hanging work at a construction site. After removing the bolt,
A roof feather construction method for a roof unit, comprising: a work of closing the cutout portion with a water-resistant sheet piece; and a work of covering the buried tree and the drainage drainage of the grass blade with a roof cover.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2190014A JPH07122295B2 (en) | 1990-07-17 | 1990-07-17 | Construction method for roof units |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2190014A JPH07122295B2 (en) | 1990-07-17 | 1990-07-17 | Construction method for roof units |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0476144A JPH0476144A (en) | 1992-03-10 |
JPH07122295B2 true JPH07122295B2 (en) | 1995-12-25 |
Family
ID=16250936
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2190014A Expired - Lifetime JPH07122295B2 (en) | 1990-07-17 | 1990-07-17 | Construction method for roof units |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH07122295B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6047186B2 (en) * | 2015-02-20 | 2016-12-21 | パナホーム株式会社 | Roof structure |
-
1990
- 1990-07-17 JP JP2190014A patent/JPH07122295B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH0476144A (en) | 1992-03-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH07122295B2 (en) | Construction method for roof units | |
JP2693846B2 (en) | Prefabricated house with balcony | |
JP2514765B2 (en) | Hanging unit mounting structure for building unit with terrace | |
JP2871740B2 (en) | Construction method of roof in industrialized house | |
JPS6315709Y2 (en) | ||
JP3751371B2 (en) | Unit building | |
JP2680212B2 (en) | balcony | |
CN109629663A (en) | A kind of absolutely dry formula concrete house structural and preparation method thereof that is linked and packed of standardization | |
JPH0717701Y2 (en) | Balcony floor waterproof structure | |
JP2510366B2 (en) | Building decoration structure | |
JPH077442Y2 (en) | roof balcony | |
JP3100265B2 (en) | Eave sky foundation structure | |
JPH07103652B2 (en) | How to carry a vertical gutter in a unit building | |
JPH08319704A (en) | Balcony unit and waterproofing structure | |
JPH0323956Y2 (en) | ||
JP2602609Y2 (en) | Balcony floor panel | |
SU1021734A1 (en) | Building and structure three-dimensional roof | |
JP2857185B2 (en) | Construction method of industrialized house | |
JPH08302888A (en) | Ceiling panel and method for constructing house using the same | |
JPH0334981Y2 (en) | ||
JPH0380224B2 (en) | ||
JPH02266031A (en) | Total floor type washing machine waterproof pan | |
JPS63293247A (en) | Roof unit equipped with window | |
JPS6233841Y2 (en) | ||
JPS58120945A (en) | Formation of roof |