Landfill method in reclaimed land

Info

Publication number
JPH0466179A
JPH0466179A JP2175429A JP17542990A JPH0466179A JP H0466179 A JPH0466179 A JP H0466179A JP 2175429 A JP2175429 A JP 2175429A JP 17542990 A JP17542990 A JP 17542990A JP H0466179 A JPH0466179 A JP H0466179A
Authority
JP
Japan
Prior art keywords
garbage
landfill
dusts
soil
reclaimed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2175429A
Other languages
Japanese (ja)
Inventor
Tsuneo Azegami
畔上 統雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PLANDO KENKYUSHO KK
Original Assignee
PLANDO KENKYUSHO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PLANDO KENKYUSHO KK filed Critical PLANDO KENKYUSHO KK
Priority to JP2175429A priority Critical patent/JPH0466179A/en
Publication of JPH0466179A publication Critical patent/JPH0466179A/en
Pending legal-status Critical Current

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

PURPOSE:To tighten reclaiming control and to efficiently perform reclamation by carrying out a landfill of various dusts which are stored in a storage area by time sharing processing corresponding to the amount and disposal way of various dusts. CONSTITUTION:Various dusts are classified into usual dust, earth and sand, coarse matter, incineration ash or the like. For example, a reclaimed land 3 is divided into three areas 3A, 3B, 3C and, first dusts of kinds predetermined from the various dusts temporarily stored in a dust storage area 9 are disposed to the reclaimed area 3A in order in predetermined amounts and, subsequently, the dusts are pressed from above, for example, by a bulldozer to uniformize dust pressure and covered with soil. Further, drain treatment is applied to the surface of soil. The dusts of kinds predetermined in the same way as mentioned above are disposed to the reclaimed area 3B in order in predetermined amounts during the pressing and soil covering treatment of the reclaimed area 3A. The reclaimed area 3C is for the next disposal of dusts.

Description

【発明の詳細な説明】 [発明の目的] (産業上の利用分野) この発明は、埋立地におけるごみ埋立て方法に関する。[Detailed description of the invention] [Purpose of the invention] (Industrial application field) The present invention relates to a method for disposing of waste in a landfill.

(従来の技術) 従来、予め指定された埋立地にごみ質に関係なくごみ処
理業者がトラックなどで運んできて、計画性なく勝手に
捨てて、その上をブルドーザなどで転圧してごみの埋立
てを行なっていた。
(Conventional technology) Conventionally, garbage disposal companies would transport garbage regardless of its quality to a pre-designated landfill site by truck, dump it without any planning, and then compact the garbage with a bulldozer or the like. was doing the following.

(発明が解決しようとする課題) ところで、上述した従来のごみ埋立て方法では、各種の
ごみか均一に捨てられていないため、地盤が不安定であ
ると共に、後日捨てられたごみ層の一部が不等沈下して
しまう恐れがあった。
(Problems to be Solved by the Invention) By the way, in the conventional garbage landfill method described above, various types of garbage are not disposed of uniformly, resulting in unstable ground and a portion of the garbage layer that is later discarded. There was a risk that the area would sink unevenly.

また、各種のごみが勝手に捨てられているために、その
後の作業が大変であると共に、事故が生じる恐れもあっ
た。また、ごみ埋立ての作業順番などの計画が何らなさ
れておらず無秩序でしがも管理がなされていないのが現
状である。
In addition, since various types of garbage were thrown away without permission, subsequent work was difficult and there was a risk of accidents occurring. Furthermore, the current situation is that there is no plan in place for the order of work in garbage landfills, and the area is chaotic and unmanaged.

この発明の目的は、上記問題点を改善するため、ごみ質
に応じたごみの種類・量を時分割にかつ作業順番を決め
て埋立てを行なうことにより、地盤が安定して不等沈下
が起らず、埋立て管理を強化し効率よく埋立てるように
した埋立地におけるごみ埋立て方法を提供することにあ
る。
The purpose of this invention is to improve the above-mentioned problems by time-sharing the type and amount of garbage according to the quality of the garbage and determining the order of work for reclamation, thereby stabilizing the ground and preventing uneven settlement. An object of the present invention is to provide a method for disposing of waste at a landfill site, which prevents waste from occurring, strengthens landfill management, and efficiently disposes of waste.

[発明の構成] (課題を解決するための手段) 上記目的を達成するために、この発明は、埋立地の脇に
設けられたごみ貯留場に各種のごみをごみ質に応じて一
時的に貯留し、埋立地の大きさ、予め決められた各種の
ごみ量およびごみの捨て方に応じて前記ごみ貯留場に貯
留されてある各種のごみを時分割処理で埋立地に埋立て
ることを特徴とする埋立地におけるごみ埋立て方法であ
る。
[Structure of the Invention] (Means for Solving the Problems) In order to achieve the above object, the present invention temporarily stores various types of garbage in a garbage storage area provided beside a landfill site according to the quality of the garbage. The method is characterized in that the various types of garbage stored in the garbage storage area are stored in the landfill and are disposed of in a time-sharing manner according to the size of the landfill, the amount of various types of garbage determined in advance, and the method of disposing of the garbage. This is a method of disposing of waste at a landfill site.

また、この発明は前記埋立地におけるごみ埋立て方法に
おいて、時分割処理をごみの捨てる工程。
Further, the present invention provides a method for disposing of waste at a landfill site, in which time-sharing processing is performed as a step of disposing of waste.

転圧工程、覆土工程および排水工程の順番に行なうのが
望ましい。
It is desirable to perform the compaction process, soil covering process, and drainage process in this order.

さらに、この発明は前記埋立地におけるごみ埋立て方法
において、埋立地を少なくとも3分割にして、各種のご
みを効率よく捨てる場所と、転圧・覆土処理する場所と
、次の埋立て場所とに分けてごみ埋立てを行なうのが望
ましい。
Furthermore, in the method for reclaiming waste at a landfill, the present invention divides the land into at least three parts, and divides the land into at least three parts, a place for efficiently disposing of various types of waste, a place for compaction/covering, and a place for the next landfill. It is desirable to separate the waste into landfills.

(作用) この発明の埋立地におけるごみ埋立て方法を採用するこ
とにより、各種のごみはトラックなどで運ばれてきて埋
立地の脇に設けられたごみ貯留場にごみ質に応じて一時
的に貯留される。この貯留場にごみ質に応じて貯留され
た各種のごみは、埋立地の大きさ、予め決められた各種
のごみ量およびごみの捨て方に応じて各種のごみが埋立
地に時分割処理で一定の割合で埋立てられる。
(Function) By adopting the garbage landfilling method at a landfill site of this invention, various types of garbage are transported by truck etc. and are temporarily stored in a garbage storage area set up beside the landfill site depending on the quality of the garbage. stored. Various types of garbage are stored in this storage area according to their quality, and various types of garbage are sent to the landfill for time-sharing processing depending on the size of the landfill, the predetermined amount of each type of garbage, and the method of disposing of the garbage. A certain percentage of waste is landfilled.

而して、埋立地に埋められたごみ層の地盤は安定化され
るため、後日不等沈下が生じることがなくなる。各種の
ごみは時分割処理により予め決められた量だけ順番に捨
てられるから、その後の作業管理が容易となり、事故が
生じる恐れもなくなる。しかも各種のごみは計画的に処
理される。
As a result, the ground of the garbage layer buried in the landfill is stabilized, so that uneven subsidence will not occur later. Since various kinds of garbage are disposed of in a predetermined amount in sequence through time-sharing processing, subsequent work management becomes easier and there is no risk of accidents occurring. Furthermore, all types of garbage are disposed of in a planned manner.

また、ごみの捨てる工程、転圧工程、覆土工程および排
水工程を順番に行なうことによって、各種のごみ、覆土
、水処理を指定された時間内に納められ効率よく管理さ
れる。さらに、埋立地を少なくとも3分割して、ごみを
捨てる作業、転圧・覆土を行なう作業を効率よく時間を
無駄にせず管理されて行なわれる。
In addition, by performing the garbage disposal process, compaction process, soil covering process, and drainage process in order, various types of garbage, soil covering, and water treatment can be collected within a specified time and managed efficiently. Furthermore, the landfill site is divided into at least three parts, and the work of disposing of garbage, compaction, and covering with soil can be managed efficiently and without wasting time.

(実施例) 以下、この発明の実施例を図面に基づいて詳細に説明す
る。
(Example) Hereinafter, an example of the present invention will be described in detail based on the drawings.

第1図を参照するに、道路1の脇には埋立地3に入るゲ
ート5が設けられており、各種のごみ、覆土などをトラ
ックで運んできたごみ運搬業者は道路1.ゲート5を経
て管理室7て受付けを行なう。管理室7では、例えばご
みの種類、量などがごみ運搬業者より報告され、その報
告に基づきその情報が例えばコンピュータに入力される
Referring to Figure 1, there is a gate 5 to enter the landfill 3 on the side of the road 1, and garbage transporters who have transported various types of garbage, soil cover, etc. by truck enter the road 1. Pass through gate 5 and enter management room 7 for reception. In the control room 7, the type and amount of garbage, for example, are reported by the garbage transporter, and based on the report, the information is input into, for example, a computer.

管理室7に設置されたコンピュータには例えば埋立地3
にどの種類のごみをとれ位捨てたらよいか予め計画が組
立てられているから、ごみ運搬業者が運んできた各種の
ごみはごみ質に応じて埋立地3の脇に設けられたごみ貯
留場9に一時的に貯留される。しかも、このごみ貯留場
9には各種のごみが分別されて貯留される。
For example, the computer installed in the management room 7
Since a plan has been made in advance as to which type of garbage should be thrown away, the various types of garbage carried by the garbage transporter are placed in the garbage storage area 9 set up next to the landfill site 3 according to the quality of the garbage. is temporarily stored. Moreover, various types of garbage are sorted and stored in this garbage storage area 9.

各種のごみとは、普通のごみ、土砂、粗大物。Various types of garbage include ordinary garbage, earth and sand, and bulky items.

焼却灰などを指して区分けされている。It is classified to refer to incineration ash, etc.

前記埋立地3は例えば3A、3B、3Cと3分割にして
あり、まず埋立地3Aへごみ貯留場9に一時的に貯留さ
れている各種のごみから予め決められごみの種類と量を
順番に捨てる。次いて、例えばブルドーザでごみを上か
ら転圧しごみ圧を均一にすると共に覆土を敷く。さらに
、覆土の表面に排水処理を行なう。
The landfill site 3 is divided into three parts, for example, 3A, 3B, and 3C. First, the types and amounts of garbage are sequentially determined in advance from among various types of garbage temporarily stored in the garbage storage area 9 to the landfill site 3A. dispose of. Next, the garbage is compacted from above using a bulldozer, for example, to equalize the pressure of the garbage, and a covering soil is laid down. Furthermore, drainage treatment will be performed on the surface of the covered soil.

埋立地3Aで転圧、覆土処理を行なっている間に埋立地
3Bには上述と同様に予め決められたごみの種類と量を
順番に捨てる。埋立地3Cは次にごみを捨てる埋立地と
しである。
While compaction and soil covering are being carried out at the landfill site 3A, predetermined types and amounts of garbage are sequentially disposed of at the landfill site 3B in the same way as described above. Landfill 3C is the next landfill where garbage will be disposed of.

このように、埋立地3を例えば3A、3B、3Cと3分
割にしてごみを捨てる工程と、転圧・覆土処理工程とを
交互に行え得るようにすると、効率よく埋立てを行なう
ことができる。
In this way, if the landfill site 3 is divided into three parts, for example 3A, 3B, and 3C, and the process of discarding garbage and the compaction/soil covering process can be performed alternately, the landfill can be efficiently carried out. .

埋立地3の大きさを予め、しかもごみの種類。The size of the landfill site 3 must be determined in advance, as well as the type of garbage.

量を確実に得て、こみ貯留場9に一時的に貯留させるこ
とにより、埋立地3にごみを捨てる作業か時分割処理に
て要領よく行なわれる。しかも、特定のごみが一ケ所に
かたまって捨てることなく均一にばらまかれるから、地
盤が安定して、後日不等沈下を起こすことかない。
By reliably obtaining the amount of waste and temporarily storing it in the waste storage area 9, the work of disposing of the waste in the landfill 3 can be carried out in a time-sharing manner. What's more, because specific waste is not collected in one place and thrown away, it is evenly distributed, which stabilizes the ground and prevents uneven subsidence later on.

埋立地3の大きさ、ごみの種類、量をもとに予めごみを
捨てる作業の順番などの計画を組み、その計画に沿って
実行することにより、効率よい埋立てを行なうことがで
きると共に、埋立て管理が良好となる。
By making a plan in advance, such as the order in which garbage should be disposed of, based on the size of the landfill site 3, the type and amount of garbage, and carrying out the work according to that plan, efficient landfilling can be carried out. Landfill management will be better.

また、ある埋立地では同質のごみだけで区割埋立てを行
なうと早く造成させることもできるし、有毒物の入った
ごみについては薬品を入れて反応させて問題のないよう
に処理して埋立てることも可能である。
In addition, in certain landfills, it is possible to quickly develop the area by filling in sections with only the same type of waste, and with regard to waste containing toxic substances, chemicals can be added to cause a reaction and treated to ensure that there are no problems before being sent to the landfill. It is also possible to

なお、この発明は、前述した実施例に限定されることな
く、適宜な変更を行なうことにより、その他の態様で実
施し得るものである。
Note that this invention is not limited to the embodiments described above, and can be implemented in other forms by making appropriate changes.

[発明の効果コ 以上のごとき実施例の説明より理解されるように、この
発明によれば、各種のごみはトラックなどで運ばれてき
て埋立地の脇に設けられたごみ貯留場にごみ質に応じて
一時的に貯留される。この貯留場にごみ質に応じて貯留
された各種のごみは、埋立地の大きさ、予め決められた
各種のごみ量およびごみの捨て方に応じて各種のごみか
埋立地に時分割処理で一定の割合で埋立てることかでき
る。
[Effects of the Invention] As can be understood from the description of the embodiments described above, according to the present invention, various types of garbage are transported by trucks, etc., and the garbage is stored in a garbage storage area set up beside a landfill. Temporarily stored depending on the situation. The various types of garbage stored in this storage area depending on the type of garbage can be processed in time-sharing manner, depending on the size of the landfill, the predetermined amount of each type of garbage, and the method of disposing of the garbage. A certain percentage can be landfilled.

而して、埋立地に埋められたごみ層の地盤は安定化し、
後日不等沈下を起こすことがなくなる。
As a result, the ground of the garbage layer buried in the landfill is stabilized,
Unequal subsidence will not occur later.

各種のごみは時分割処理により予め決められた量だけ順
番に捨てられるから、その後の作業管理が容易となり、
事故が生じることもなくなる。しかも、各種のごみは計
画的に処理され埋立て管理を容易に行なうことができる
Since various types of garbage are disposed of in a predetermined amount in order through time-sharing processing, subsequent work management becomes easier.
Accidents will no longer occur. Moreover, various types of garbage can be systematically processed and landfill management can be easily performed.

また、ごみの捨てる工程、転圧工程、覆土工程および排
水工程を順番に行なうことによって、各種のごみ、覆土
、水処理を指定された時間内に納めればよく効率よく管
理することができる。さらに、埋立地を少なくとも3分
割して、ごみを捨てる作業、転圧・覆土を行なう作業を
効率よく時間を無駄にせず管理することができる。
Further, by sequentially performing the garbage disposal process, compaction process, soil covering process, and drainage process, various types of garbage, soil covering, and water treatment can be efficiently managed as long as they are completed within a specified time. Furthermore, by dividing the landfill site into at least three parts, the work of disposing of garbage, compaction, and covering with soil can be managed efficiently and without wasting time.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明のごみを埋立てる埋立地の概略平面図
である。 3.3A、3B、3C・・・埋立地 7・・・管理室 9・・・ごみ貯留場
FIG. 1 is a schematic plan view of a landfill site according to the present invention. 3.3A, 3B, 3C... Landfill 7... Management room 9... Garbage storage area

Claims (3)

【特許請求の範囲】[Claims] (1)埋立地の脇に設けられたごみ貯留場に各種のごみ
をごみ質に応じて一時的に貯留し、埋立地の大きさ、予
め決められた各種のごみ量およびごみの捨て方に応じて
前記ごみ貯留場に貯留されてある各種のごみを時分割処
理で埋立地に埋立てることを特徴とする埋立地における
ごみ埋立て方法。
(1) Various types of garbage are temporarily stored in a garbage storage area set up next to the landfill, depending on the quality of the garbage, and the size of the landfill, amount of each type of garbage, and method of disposal are determined in advance. A method for reclaiming garbage in a landfill, characterized in that various kinds of garbage stored in the garbage storage area are disposed of in a landfill in a time-sharing manner.
(2)前記請求項(1)において、時分割処理をごみの
捨てる工程、転圧工程、覆土工程および排水工程の順番
に行なうことを特徴とする埋立地におけるごみ埋立て方
法。
(2) A method for reclaiming waste at a landfill site according to claim (1), characterized in that the time-sharing treatment is performed in the order of a step of discarding the waste, a compaction step, a step of covering soil, and a step of draining water.
(3)前記請求項(1)において、埋立地を少なくとも
3分割にして、各種のごみを効率よく捨てる場所と、転
圧・覆土処理する場所と、次の埋立て場所とに分けてご
み埋立てを行なうことを特徴とする埋立地におけるごみ
埋立て方法。
(3) In claim (1), the landfill site is divided into at least three parts, and the garbage is divided into a place for efficiently disposing of various types of garbage, a place for compaction and soil covering, and a place for the next landfill. A method for disposing of waste at a landfill site, which is characterized by:
JP2175429A 1990-07-04 1990-07-04 Landfill method in reclaimed land Pending JPH0466179A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2175429A JPH0466179A (en) 1990-07-04 1990-07-04 Landfill method in reclaimed land

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2175429A JPH0466179A (en) 1990-07-04 1990-07-04 Landfill method in reclaimed land

Publications (1)

Publication Number Publication Date
JPH0466179A true JPH0466179A (en) 1992-03-02

Family

ID=15995949

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2175429A Pending JPH0466179A (en) 1990-07-04 1990-07-04 Landfill method in reclaimed land

Country Status (1)

Country Link
JP (1) JPH0466179A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07251192A (en) * 1993-12-20 1995-10-03 Sang-Bae Han Biological contact material unit for foul and waste liquid treatment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07251192A (en) * 1993-12-20 1995-10-03 Sang-Bae Han Biological contact material unit for foul and waste liquid treatment

Similar Documents

Publication Publication Date Title
Owusu-Nimo et al. Characteristics and management of landfill solid waste in Kumasi, Ghana
US4430021A (en) Secure chemical waste landfill
US5288171A (en) Method of recycling construction and demolition debris
NL194034C (en) Garbage depot.
JP5085945B2 (en) Disposal of granular waste
US6106197A (en) Landfill garbage management process
US5324138A (en) In situ process for increasing the capacity of a municipal solid waste landfill
Spencer Landfill space reuse
JPH0466179A (en) Landfill method in reclaimed land
US5599138A (en) Landfill garbage system
JP2003024928A (en) Cleaning method for polluted soil
JP2004358347A (en) Contaminated soil cleaning method and contaminated soil cleaning plant
ATE345881T1 (en) LANDFILL FOR THE STORAGE OF MATERIALS OR COMPOSITES OR MIXTURES THEREOF, METHOD FOR TREATING THEM AND DEVICE THEREOF
KR940003567B1 (en) Waste storaging method and system using waste tire
JP2744579B2 (en) Paddy soil structure
JPH0985211A (en) Engineering technique for solidifying cinder harmlessly and stably using shielding partition wall
Chan et al. Reuse of redundant gravels and phyto-conditioned sewage sludge
DE29805120U1 (en) Arrangement for the construction and design of landfills
JP3453706B2 (en) Managed waste disposal equipment and disposal law
JPH0671243A (en) Industrial waste treatment work method
RU2243040C1 (en) Method of recuperation of sites of solid household wastes burial
CA2147588C (en) Landfill garbage system
Johnson Rural waste management through resource conservation
JP2002113436A (en) Land-filling method for wastes
ATE181687T1 (en) WASTE PROCESSING