[go: up one dir, main page]

JP7614434B1 - Process Planning Method - Google Patents

Process Planning Method Download PDF

Info

Publication number
JP7614434B1
JP7614434B1 JP2024134423A JP2024134423A JP7614434B1 JP 7614434 B1 JP7614434 B1 JP 7614434B1 JP 2024134423 A JP2024134423 A JP 2024134423A JP 2024134423 A JP2024134423 A JP 2024134423A JP 7614434 B1 JP7614434 B1 JP 7614434B1
Authority
JP
Japan
Prior art keywords
monopile
marine structure
structural analysis
transition piece
manufacturing process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2024134423A
Other languages
Japanese (ja)
Inventor
和彦 瀬谷
哲郎 能勢
和也 玉田
敦郎 大嶽
伸 深津
敬 入江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Engineering Co Ltd
Original Assignee
Nippon Steel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Engineering Co Ltd filed Critical Nippon Steel Engineering Co Ltd
Priority to JP2024134423A priority Critical patent/JP7614434B1/en
Application granted granted Critical
Publication of JP7614434B1 publication Critical patent/JP7614434B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

Figure 0007614434000001

【課題】建設プロジェクトの工程を短縮可能な工程計画方法を提供することを目的とする。
【解決手段】モノパイル基礎の建設プロジェクトの工程を計画する工程計画方法であって、モノパイル基礎のモデルの構造解析を、コンピュータが複数回行う構造解析工程SA3と、1回目の構造解析工程SA3に含まれる地震応答解析の完了後であって2回目の構造解析工程SA3に含まれる地震応答解析の完了前に開始される第1製作工程SB1と、を備え、第1製作工程SB1は、トランジションピースのうちインターフェイスフランジを製作せず、トランジションピースのうちインターフェイスフランジ以外の部分を製作し、第1製作工程SB1は、モノパイル本体のうちトランジションピースと水平方向視で重複する状態で接続される接続部を製作し、モノパイル本体のうち接続部以外の部分を製作しない。
【選択図】図5

Figure 0007614434000001

An object of the present invention is to provide a construction project process planning method capable of shortening the process of a construction project.
[Solution] A process planning method for planning the processes of a monopile foundation construction project, comprising: a structural analysis process SA3 in which a computer performs a structural analysis of a model of the monopile foundation multiple times; and a first production process SB1 that is started after completion of the earthquake response analysis included in the first structural analysis process SA3 and before completion of the earthquake response analysis included in the second structural analysis process SA3, wherein the first production process SB1 does not produce an interface flange of the transition piece, but produces parts of the transition piece other than the interface flange, and the first production process SB1 produces a connection part of the monopile body that is connected to the transition piece in a state that overlaps with it when viewed horizontally, and does not produce parts of the monopile body other than the connection part.
[Selected figure] Figure 5

Description

本開示は、工程計画方法に関する。 This disclosure relates to a process planning method.

従来、工場において製作された構造物を、施工現場において組み立てて設置することが行われている。
特許文献1には、工場において予め製作される単位構造体が、一枚の平滑な金属板から成っていると同時に、その外表面に水平方向の補強リブが溶接されている垂直構造物の構築方式が開示されている。
Conventionally, structures are manufactured in a factory and then assembled and installed at a construction site.
Patent Document 1 discloses a method of constructing a vertical structure in which a unit structure, which is prefabricated in a factory, consists of a single smooth metal plate and has horizontal reinforcing ribs welded to its outer surface.

特開昭62-86273号公報Japanese Unexamined Patent Publication No. 62-86273

前記従来の構築方式では、建設プロジェクトの工程の短縮に課題がある。 The conventional construction method described above poses challenges in shortening the construction project schedule.

本開示は、前述した事情に鑑みてなされたものであって、建設プロジェクトの工程を短縮可能な工程計画方法を提供することを目的とする。 This disclosure has been made in consideration of the above-mentioned circumstances, and aims to provide a process planning method that can shorten the process of a construction project.

本開示の一態様に係る工程計画方法は、モノパイル本体と、トランジションピースと、を有し、洋上風車のタワーを支持するモノパイル基礎の建設プロジェクトの工程を計画する工程計画方法であって、前記モノパイル基礎のモデルの構造解析を、コンピュータが複数回行う構造解析工程と、1回目の前記構造解析工程に含まれる地震応答解析の完了後であって2回目の前記構造解析工程に含まれる地震応答解析の完了前に、前記モノパイル基礎を構成する部材のうち少なくとも一部を製作する第1製作工程と、を備え、前記第1製作工程は、前記トランジションピースを製作し、前記第1製作工程は、前記トランジションピースのうちインターフェイスフランジを製作せず、前記トランジションピースのうち前記インターフェイスフランジ以外の部分を製作し、前記第1製作工程は、前記モノパイル本体を製作し、前記第1製作工程は、前記モノパイル本体のうち前記トランジションピースと水平方向視で重複する状態で接続される接続部を製作し、前記モノパイル本体のうち前記接続部以外の部分を製作しないことを特徴とする。 A process planning method according to one aspect of the present disclosure is a process planning method for planning the process of a construction project of a monopile foundation that has a monopile body and a transition piece and supports the tower of an offshore wind turbine, comprising: a structural analysis step in which a computer performs structural analysis of a model of the monopile foundation multiple times; and a first manufacturing step in which at least a part of the components that constitute the monopile foundation is manufactured after completion of an earthquake response analysis included in the first structural analysis step and before completion of an earthquake response analysis included in the second structural analysis step, the first manufacturing step manufacturing the transition piece, the first manufacturing step not manufacturing an interface flange of the transition piece, and manufacturing a part of the transition piece other than the interface flange, the first manufacturing step manufacturing the monopile body, the first manufacturing step manufacturing a connection part of the monopile body that is connected in a state where it overlaps with the transition piece in a horizontal view, and not manufacturing a part of the monopile body other than the connection part.

本開示によれば、建設プロジェクトの工程を短縮可能な工程計画方法を提供することができる。 This disclosure provides a process planning method that can shorten the construction project process.

実施形態に係る海洋構造物の第1例を示す図である。FIG. 1 is a diagram showing a first example of a marine structure according to an embodiment. 図1に示す海洋構造物が複数設置された状態を示す図である。FIG. 2 is a diagram showing a state in which a plurality of the marine structures shown in FIG. 1 are installed. 図1に示すIII-III方向における、モノパイル本体の断面図である。3 is a cross-sectional view of the monopile body in the III-III direction shown in FIG. 1. 図1に示すIV部の拡大図である。FIG. 2 is an enlarged view of a portion IV shown in FIG. 実施形態に係る工程計画方法のフローである。3 is a flow chart of a process planning method according to an embodiment.

以下、図面を参照し、本開示の一実施形態に係る海洋構造物及び海洋構造物の工程計画方法を説明する。
本実施形態に係る海洋構造物は、洋上風車のタワーを支持する基礎構造である。海洋構造物は、例えば、ジャケット式基礎であってもよいし、モノパイル基礎であってもよいし、その他任意の構造体であってよい。
Hereinafter, an offshore structure and a process planning method for an offshore structure according to an embodiment of the present disclosure will be described with reference to the drawings.
The marine structure according to this embodiment is a foundation structure that supports the tower of an offshore wind turbine. The marine structure may be, for example, a jacket foundation, a monopile foundation, or any other structure.

(海洋構造物について)
図1は、実施形態に係る海洋構造物1の第1例を示す図である。
図2は、図1に示す海洋構造物1が複数設置された状態を示す図である。
図1に示すように、本実施形態において、海洋構造物1は、モノパイル基礎である。図2に示すように、海洋構造物1は、例えば、同一のウインドファーム又は海域(以下、設置場所A)に複数存在してよい。
(Regarding marine structures)
FIG. 1 is a diagram showing a first example of a marine structure 1 according to an embodiment.
FIG. 2 is a diagram showing a state in which a plurality of marine structures 1 shown in FIG. 1 are installed.
As shown in Fig. 1, in this embodiment, the marine structure 1 is a monopile foundation. As shown in Fig. 2, a plurality of marine structures 1 may be present in the same wind farm or sea area (hereinafter, installation site A), for example.

本実施形態において、モノパイル基礎である海洋構造物1は、図1に示すように、モノパイル本体10と、トランジションピース20と、付属設備30と、を有する。
モノパイル本体10は、海底OFに打設される筒状の部材である。本実施形態において、モノパイル本体10とは、例えば、少なくとも一部が土中部に根入れされている鋼管のことをいう。本実施形態において、モノパイル本体10の内面及び外面のうち少なくとも一方には、被覆防食されていてもよい。
本実施形態において、モノパイル本体10は、例えば図1に示すように、任意の長さを有する筒状の部材である単位筒状体11を長手方向に複数接続することで形成される。モノパイル本体10は、鋼製であってもよいし、その他任意の材料により構成されてもよい。
また、本実施形態において、上述のように同一の設置場所Aに設けられる複数の海洋構造物1は、モノパイル本体10の形状の一部又は全部が共通していてもよいし、複数の海洋構造物1のそれぞれの配置場所における地盤や水深等の条件に合わせて適宜個別に形状が設定されてもよい。
In this embodiment, the marine structure 1, which is a monopile foundation, has a monopile body 10, a transition piece 20, and an auxiliary facility 30, as shown in FIG.
The monopile body 10 is a cylindrical member that is driven into the seabed OF. In this embodiment, the monopile body 10 refers to, for example, a steel pipe at least a part of which is embedded in the ground. In this embodiment, at least one of the inner and outer surfaces of the monopile body 10 may be coated with an anti-corrosive coating.
In this embodiment, the monopile body 10 is formed by connecting a plurality of unit cylindrical bodies 11, which are cylindrical members having any length, in the longitudinal direction, as shown in Fig. 1. The monopile body 10 may be made of steel or any other material.
In addition, in this embodiment, as described above, multiple marine structures 1 installed at the same installation location A may have part or all of the shape of the monopile body 10 in common, or the shape may be set individually as appropriate to suit the conditions such as the ground and water depth at the respective installation locations of the multiple marine structures 1.

図3は、図1に示すIII-III方向における、モノパイル本体10の断面図である。
本実施形態において、モノパイル本体10は、図3に示すように、横断面における断面形状が円状に形成されてよい。このような断面形状を有する単位筒状体11は、例えば、図3に示すように、複数の湾曲した板11Aの端部同士を接続することによって形成されてもよいし、鋼板を曲げ加工することで形成されてもよいし、筒状の部材が一体成形されることで形成されてもよい。
あるいは、モノパイル本体10は、断面形状が楕円状に形成されてもよいし、その他任意の断面形状に形成されてもよい。
FIG. 3 is a cross-sectional view of the monopile body 10 taken along the line III-III shown in FIG.
In this embodiment, the monopile body 10 may be formed so that its cross section has a circular shape as shown in Fig. 3. The tubular unit 11 having such a cross-sectional shape may be formed, for example, by connecting ends of a plurality of curved plates 11A as shown in Fig. 3, by bending a steel plate, or by integrally molding a tubular member.
Alternatively, the monopile body 10 may be formed to have an elliptical cross-sectional shape, or any other cross-sectional shape.

上述のように、モノパイル本体10は、単位筒状体11を長手方向に複数接続することで形成される。この時、モノパイル本体10において、土中に設置される部分や、特に海底OFの表面(海底面)に近い部分は、その他の部分に比べて比較的大きな曲げモーメントが作用することがある。このため、当該部分に位置する単位筒状体11は、他の部分に位置する単位筒状体11よりも大きな板厚としてもよい。 As described above, the monopile body 10 is formed by connecting multiple unit tubular bodies 11 in the longitudinal direction. At this time, the portion of the monopile body 10 that is installed underground, and in particular the portion close to the surface (seabed surface) of the seabed OF, may be subjected to a relatively large bending moment compared to other portions. For this reason, the unit tubular bodies 11 located in these portions may have a greater plate thickness than the unit tubular bodies 11 located in other portions.

図4は、図1に示すIV部の拡大図である。
モノパイル本体10の内部には、図4に示すように、ケーブルCが設けられてもよい。ケーブルCは、例えば、洋上風車WMの内部に設けられた不図示の各種機器と、海底OFに敷設された不図示の海底ケーブルと、を接続するためのケーブルである。不図示の海底ケーブルと、図4に示すケーブルCと、を接続可能とするため、モノパイル本体10の海底面に近い部分の側壁には、不図示の孔が設けられてもよい。なお、ケーブルCと不図示の海底ケーブルとが、不図示のジョイントによって接続されている場合、ケーブルCと不図示の海底ケーブルとの境界は、不図示のジョイントが位置する箇所によって確認してもよい。また、海底に着底しているものを、不図示の海底ケーブルと理解することにより、ケーブルCと不図示の海底ケーブルとの境界を確認してもよい。
FIG. 4 is an enlarged view of part IV shown in FIG.
A cable C may be provided inside the monopile body 10 as shown in Fig. 4. The cable C is, for example, a cable for connecting various devices (not shown) provided inside the offshore wind turbine WM with a submarine cable (not shown) laid on the seabed OF. In order to enable the submarine cable (not shown) to be connected to the cable C shown in Fig. 4, a hole (not shown) may be provided in a side wall of the monopile body 10 near the seabed surface. When the cable C and the submarine cable (not shown) are connected by a joint (not shown), the boundary between the cable C and the submarine cable (not shown) may be confirmed by the location of the joint (not shown). Also, the boundary between the cable C and the submarine cable (not shown) may be confirmed by understanding that the cable that has landed on the seabed is the submarine cable (not shown).

トランジションピース20は、図1及び図4に示すように、モノパイル本体10の上部に配置される。具体的には、トランジションピース20は、水平方向視において、モノパイル本体10の上端を含む一部と重複するように設けられる。すなわち、モノパイル本体10の上部は、トランジションピース20に下方から挿入される。図4に示すように、モノパイル本体10の上端を含む一部、及びトランジションピース20は、コーン形状であることが好ましい。すなわち、モノパイル本体10の上端を含む一部及びトランジションピース20は、下方から上方に向けて縮径する円錐台状であることが好ましい。
図4に示すように、モノパイル本体10の上端を含む一部とトランジションピース20とは、水平方向視において互いに重なるように配置された状態で、グラウトGによって固定されてよい。グラウトGは、モノパイル本体10の上部とトランジションピース20との間の隙間(アニュラースペース)に注入される。
トランジションピース20は、例えば、鋼製であってもよいし、その他任意の材料によって構成されてもよい。
上述のようにしてモノパイル本体10の上部に配置されるトランジションピース20は、モノパイル本体10と洋上風車WMのタワーTとを接続する。タワーTはトランジションピース20との接続位置から上側へ延びる。洋上風車WMは洋上に設置される。
本実施形態において、トランジションピース20は、図4に示すように、インターフェイスフランジIFを有する。インターフェイスフランジIFは、トランジションピース20の上端に設けられる。本実施形態において、同様のインターフェイスフランジIFは、洋上風車WMのタワーTの下端にも設けられている。トランジションピース20と洋上風車WMのタワーTとの接続は、図4に示すように、トランジションピース20及び洋上風車WMのタワーTのそれぞれに設けられたインターフェイスフランジIF同士をボルトBによって接合することによってなされる。なお、トランジションピース20は、タワーTとの接続角度を調整する機能を有していてもよい。この構成により、洋上風車WMのタワーTの下端との接続時に、洋上風車WMのタワーTが鉛直方向に延びるように調整できる。
トランジションピース20の内部には、図4に示すように、ケーブルCが設けられてもよい。トランジションピース20の内部には、ケーブルCを通すために、円形、楕円形その他の任意の形状を有する孔Hが設けられてもよい。なお、上述のように、海洋構造物1は、図2に示すように、同一の設置場所Aに複数存在することがある。このとき、複数の海洋構造物1において、トランジションピース20の内部に設けられた孔Hの形状は、共通していることが好ましい。
なお、本実施形態において、トランジションピース20は、上述のように同一の設置場所Aに複数設けられる海洋構造物1において、共通の構造のものが用いられてよいし、異なっていてもよい。
The transition piece 20 is disposed on the upper part of the monopile body 10, as shown in Figures 1 and 4. Specifically, the transition piece 20 is provided so as to overlap a part of the monopile body 10 including its upper end when viewed in the horizontal direction. That is, the upper part of the monopile body 10 is inserted into the transition piece 20 from below. As shown in Figure 4, the part of the monopile body 10 including its upper end and the transition piece 20 are preferably cone-shaped. That is, the part of the monopile body 10 including its upper end and the transition piece 20 are preferably truncated cones whose diameter decreases from the bottom to the top.
4 , a portion of the monopile body 10 including its upper end and the transition piece 20 may be fixed by grout G in a state in which they are arranged so as to overlap each other when viewed in the horizontal direction. The grout G is injected into the gap (annular space) between the upper part of the monopile body 10 and the transition piece 20.
The transition piece 20 may be made of, for example, steel, or any other material.
The transition piece 20 disposed on the upper part of the monopile body 10 as described above connects the monopile body 10 to the tower T of the offshore wind turbine WM. The tower T extends upward from the connection position with the transition piece 20. The offshore wind turbine WM is installed on the ocean.
In this embodiment, the transition piece 20 has an interface flange IF as shown in Fig. 4. The interface flange IF is provided at the upper end of the transition piece 20. In this embodiment, a similar interface flange IF is also provided at the lower end of the tower T of the offshore wind turbine WM. The connection between the transition piece 20 and the tower T of the offshore wind turbine WM is achieved by joining the interface flanges IF provided on the transition piece 20 and the tower T of the offshore wind turbine WM with bolts B as shown in Fig. 4. Note that the transition piece 20 may have a function of adjusting the connection angle with the tower T. With this configuration, the tower T of the offshore wind turbine WM can be adjusted to extend in the vertical direction when connected to the lower end of the tower T of the offshore wind turbine WM.
A cable C may be provided inside the transition piece 20 as shown in Fig. 4. A hole H having a circular, elliptical or any other shape may be provided inside the transition piece 20 in order to pass the cable C through. As described above, a plurality of marine structures 1 may exist at the same installation site A as shown in Fig. 2. In this case, it is preferable that the shape of the hole H provided inside the transition piece 20 in the plurality of marine structures 1 is the same.
In this embodiment, the transition pieces 20 may have a common structure or may be different in the marine structures 1 that are installed in the same installation location A as described above.

付属設備30は、海洋構造物1において、作業者が移動及び各種作業を可能とするために設けられる。本実施形態において、付属設備30は、例えば図4に示すように、係船設備31、梯子32、踊場33及び作業床34、通路35を含む。付属設備30のそれぞれは、例えば、鋼製であってもよいし、その他任意の材料によって構成されてもよい。
なお、本実施形態において、付属設備30は、上述のように同一の設置場所Aに複数設けられる海洋構造物1において、共通の構造のものが用いられてよいし、異なっていてもよい。
The auxiliary facilities 30 are provided to enable workers to move and perform various operations on the marine structure 1. In this embodiment, the auxiliary facilities 30 include a mooring facility 31, a ladder 32, a landing 33, a work platform 34, and a passageway 35, as shown in Fig. 4 for example. Each of the auxiliary facilities 30 may be made of steel, for example, or may be made of any other material.
In this embodiment, the auxiliary equipment 30 may have a common structure for multiple marine structures 1 installed at the same installation site A as described above, or may be different.

係船設備31は、海洋構造物1における、作業船を付けるための部材である。本実施形態において、図4に示す係船設備31は、例えば、上下方向に延びる一対の棒状の部材を有する。作業者は、この係船設備31に作業船を付けた状態で、作業船から海洋構造物1に移動する。
梯子32は、海洋構造物1に移動した作業者が上下に移動するために用いられる。本実施形態において、図4に示す梯子32は、例えば、係船設備31の有する一対の棒状の部材同士の間に設けられる。
踊場33は、図4に示すように、梯子32の上端に設けられる。本実施形態において、踊場33は、作業船から海洋構造物1に移動し、梯子32を用いて上方に移動した作業者が降り立つ場所である。
作業床34は、作業者が各種作業を行うための場所である。作業床34には、例えば図4に示すように、物資を吊り上げるためのダビットクレーンDCが設けられてもよい。
通路35は、作業者が移動する部分である。本実施形態において、通路35は、梯子32と、踊場33と、を含む。換言すれば、本実施形態において、梯子32及び踊場33をまとめて通路35といってもよい。
以上の各構成によって、本実施形態に係る海洋構造物1は構成される。
The mooring equipment 31 is a member for mooring a work boat in the marine structure 1. In this embodiment, the mooring equipment 31 shown in Fig. 4 has, for example, a pair of rod-shaped members extending in the vertical direction. With the work boat moored to the mooring equipment 31, a worker moves from the work boat to the marine structure 1.
The ladder 32 is used for a worker who has moved to the marine structure 1 to move up and down. In this embodiment, the ladder 32 shown in Fig. 4 is provided between a pair of rod-shaped members of the mooring equipment 31, for example.
As shown in Fig. 4, the landing 33 is provided at the upper end of the ladder 32. In this embodiment, the landing 33 is a place where a worker who moves from the work boat to the marine structure 1 and moves upward using the ladder 32 gets off.
The work floor 34 is a place where workers perform various tasks. For example, as shown in Fig. 4, the work floor 34 may be provided with a davit crane DC for lifting materials.
The passage 35 is a portion where a worker moves. In this embodiment, the passage 35 includes the ladder 32 and the landing 33. In other words, in this embodiment, the ladder 32 and the landing 33 may be collectively referred to as the passage 35.
The marine structure 1 according to this embodiment is constituted by the above-mentioned components.

(工程計画方法について)
次に、本実施形態に係る工程計画方法について説明する。本実施形態に係る工程計画方法は、洋上風車WMのタワーTを支持する海洋構造物1の建設プロジェクトの工程を計画する方法である。本実施形態に係る海洋構造物1の製作には、以下に述べる工程計画方法が適用される。本実施形態に係る海洋構造物1は、前記工程計画方法に基づく工程により製作され、洋上に設置される。
なお、本実施形態において、海洋構造物1を製作するとは、材料を調達すること、材料を加工して各種部材を形成すること、各種部材を組み立てて海洋構造物1を形成すること、を含むものとする。
(About the process planning method)
Next, a process planning method according to this embodiment will be described. The process planning method according to this embodiment is a method for planning the process of a construction project of an offshore structure 1 that supports the tower T of an offshore wind turbine WM. The process planning method described below is applied to the manufacture of the offshore structure 1 according to this embodiment. The offshore structure 1 according to this embodiment is manufactured through a process based on the process planning method, and installed offshore.
In this embodiment, manufacturing the marine structure 1 includes procuring materials, processing the materials to form various components, and assembling the various components to form the marine structure 1.

図5は、実施形態に係る工程計画方法のフローである。
図5に示すように、本実施形態に係る工程計画方法は、設計検討フローSAと、製作フローSBと、を含む。
設計検討フローSAは、海洋構造物1の形状を検討するフローである。図5に示すように、設計検討フローSAは、事前調査工程SA1と、形状検討工程SA2と、構造解析工程SA3と、を備える。
FIG. 5 is a flow chart of a process planning method according to the embodiment.
As shown in FIG. 5, the process planning method according to this embodiment includes a design review flow SA and a production flow SB.
The design review flow SA is a flow for reviewing the shape of the marine structure 1. As shown in Fig. 5, the design review flow SA includes a preliminary investigation process SA1, a shape review process SA2, and a structure analysis process SA3.

事前調査工程SA1は、海洋構造物1及び洋上風車WMが設置される設置場所Aにおける、地盤条件や波浪条件等をはじめとする固有の条件を調査する工程である。具体的には、事前調査工程SA1においては、例えば、風況観測、地質調査、深浅測量、室内土質試験等が行われる。事前調査工程SA1における各種調査の結果は、例えば、形状検討工程SA2や、構造解析工程SA3における解析の条件に反映される。
なお、事前調査工程SA1の前後において、製作フローSBにおける前第1製作工程SB1a(後述する)を開始してもよい。
The preliminary investigation process SA1 is a process of investigating specific conditions, including ground conditions and wave conditions, at the installation site A where the marine structure 1 and the offshore wind turbine WM will be installed. Specifically, in the preliminary investigation process SA1, for example, wind observation, geological investigation, bathymetry, indoor soil testing, etc. are performed. The results of the various investigations in the preliminary investigation process SA1 are reflected in the analysis conditions in, for example, the shape consideration process SA2 and the structure analysis process SA3.
In addition, a pre-first production process SB1a (described later) in the production flow SB may be started before or after the preliminary inspection process SA1.

形状検討工程SA2は、海洋構造物1の形状を検討し、海洋構造物1のモデルを作成する工程である。具体的には、例えば、モノパイル基礎である海洋構造物1における、モノパイル本体10の径や板厚、トランジションピース20の径や板厚等を検討し、構造解析工程SA3に用いるモデルを作成する。 The shape examination process SA2 is a process for examining the shape of the marine structure 1 and creating a model of the marine structure 1. Specifically, for example, the diameter and thickness of the monopile body 10 and the diameter and thickness of the transition piece 20 of the marine structure 1, which is a monopile foundation, are examined, and a model to be used in the structural analysis process SA3 is created.

ここで、本実施形態では、後述する前第1製作工程SB1a(後述する)において、モノパイル本体10やトランジションピース20を構成する材料のうち汎用性の高いものを、予め在庫として確保することがある。すなわち、例えば、モノパイル本体10やトランジションピース20を構成する材料として、径や板厚、材質が異なる複数の種類の鋼管を、予め調達しておくことがある。このような場合、複数の種類の鋼管における径や板厚は、所定の数値刻みで変化する。なお、前記所定の数値は、例えば、任意の数値で適宜決定されてよい。また、前記所定の数値は、例えば、離散値である。
このとき、本実施形態において、形状検討工程SA2では、海洋構造物1の形状を複数検討してもよい。形状検討工程SA2において、モノパイル本体10やトランジションピース20の径や板厚は、在庫として確保された鋼管に合わせて、所定の数値刻みで設定されることが好ましい。また、前記所定の数値は、例えば、在庫として確保された鋼管に合わせて、離散値であることが好ましい。このことで、例えば、次に述べる構造解析工程SA3を行いやすくすることができる。また、モノパイル本体10やトランジションピース20の材料を調達する際に、在庫の余剰が生じることを抑えやすくすることができる(詳細は後述する)。
形状検討工程SA2において海洋構造物1の形状が検討された後は、製作フローSBにおける中第1製作工程SB1b(後述する)を開始するとともに、構造解析工程SA3に移行する。ただし、中第1製作工程SB1bの開始は、必須ではない。すなわち、中第1製作工程SB1bを開始するか否かは、適宜判断される。
Here, in this embodiment, in the first pre-fabrication process SB1a (described later), materials constituting the monopile body 10 and the transition piece 20 that are highly versatile may be secured in advance as inventory. That is, for example, multiple types of steel pipes with different diameters, plate thicknesses, and materials may be procured in advance as materials constituting the monopile body 10 and the transition piece 20. In such a case, the diameters and plate thicknesses of the multiple types of steel pipes change in predetermined numerical increments. The predetermined numerical values may be, for example, any numerical values as appropriate. The predetermined numerical values are, for example, discrete values.
At this time, in this embodiment, a plurality of shapes of the marine structure 1 may be considered in the shape consideration step SA2. In the shape consideration step SA2, the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 are preferably set in predetermined numerical increments in accordance with the steel pipes secured as inventory. Moreover, the predetermined numerical values are preferably discrete values in accordance with the steel pipes secured as inventory, for example. This makes it easier to perform, for example, the structural analysis step SA3 described below. Also, it makes it easier to prevent excess inventory when procuring materials for the monopile body 10 and the transition pieces 20 (details will be described later).
After the shape of the marine structure 1 is considered in the shape consideration step SA2, the first intermediate manufacturing step SB1b (described later) in the manufacturing flow SB is started and the process proceeds to the structural analysis step SA3. However, the start of the first intermediate manufacturing step SB1b is not essential. In other words, whether or not to start the first intermediate manufacturing step SB1b is determined appropriately.

構造解析工程SA3は、海洋構造物1のモデルの構造解析を行う工程である。本実施形態において、構造解析工程SA3は複数回行われてよい。換言すれば、本実施形態において、構造解析工程SA3は、海洋構造物1のモデルの構造解析を、コンピュータが複数回行う工程であってよい。
構造解析工程SA3は、形状検討工程SA2において検討された海洋構造物1の形状によって行われる。図5に示すように、構造解析工程SA3は、解析実施ステップSA3aと、第1確認ステップSA3bと、第2確認ステップSA3cと、第3確認ステップSA3dと、見直しステップSA3eと、を含む。
The structural analysis step SA3 is a step of performing a structural analysis of the model of the marine structure 1. In this embodiment, the structural analysis step SA3 may be performed multiple times. In other words, in this embodiment, the structural analysis step SA3 may be a step in which a computer performs a structural analysis of the model of the marine structure 1 multiple times.
The structural analysis process SA3 is performed based on the shape of the marine structure 1 considered in the shape consideration process SA2. As shown in Fig. 5, the structural analysis process SA3 includes an analysis implementation step SA3a, a first confirmation step SA3b, a second confirmation step SA3c, a third confirmation step SA3d, and a review step SA3e.

解析実施ステップSA3aは、海洋構造物1のモデルの構造解析を行うステップである。本実施形態において、解析実施ステップSA3aでは、例えば、固有値解析、風波統合解析、地震応答解析等が行われる。固有値解析、風波統合解析および地震応答解析は骨組み構造解析や有限要素解析で行われてもよい。また、風波統合解析および地震応答解析は時刻歴応答解析で行われることが好ましい。また、解析実施ステップSA3aでは、付属設備30について、静的解析が行われてもよい。静的解析において、荷重として、例えば、波荷重や船舶接岸荷重、牽引荷重等が考慮されてもよい。
なお、形状検討工程SA2において海洋構造物1の形状が複数検討されている場合、解析実施ステップSA3aでは、例えば、それぞれの形状に対して解析を行う。
The analysis execution step SA3a is a step of performing a structural analysis of the model of the marine structure 1. In this embodiment, for example, eigenvalue analysis, wind-wave integrated analysis, earthquake response analysis, etc. are performed in the analysis execution step SA3a. The eigenvalue analysis, wind-wave integrated analysis, and earthquake response analysis may be performed by frame structure analysis or finite element analysis. It is also preferable that the wind-wave integrated analysis and earthquake response analysis are performed by time history response analysis. In the analysis execution step SA3a, a static analysis may be performed on the auxiliary equipment 30. In the static analysis, for example, wave load, ship docking load, towing load, etc. may be considered as loads.
When multiple shapes of the marine structure 1 are considered in the shape consideration step SA2, for example, an analysis is performed for each shape in the analysis implementation step SA3a.

第1確認ステップSA3bは、解析実施ステップSA3aにおいて行われた解析の結果を確認するステップである。具体的には、第1確認ステップSA3bにおいては、解析実施ステップSA3aを行った際の海洋構造物1のモデル全体の形状によって、海洋構造物1の全ての部材を最終化可能であるか否かを確認する。
海洋構造物1のモデル全体の形状によって、海洋構造物1の全ての部材を最終化可能であると判定される場合(SA3b:できる)、構造解析工程SA3を終了し、海洋構造物1の形状が最終決定とされる。海洋構造物1の全ての部材を最終化可能ではないと判定される場合(SA3b:できない)、第2確認ステップSA3cに移行する。
The first confirmation step SA3b is a step for confirming the result of the analysis performed in the analysis performing step SA3a. Specifically, in the first confirmation step SA3b, it is confirmed whether or not all the members of the marine structure 1 can be finalized based on the overall shape of the model of the marine structure 1 when the analysis performing step SA3a is performed.
When it is determined that all the components of the marine structure 1 can be finalized based on the overall shape of the model of the marine structure 1 (SA3b: Yes), the structural analysis step SA3 is terminated and the shape of the marine structure 1 is finally determined. When it is determined that all the components of the marine structure 1 cannot be finalized (SA3b: No), the process proceeds to a second confirmation step SA3c.

第2確認ステップSA3cは、全ての部材を最終化可能ではないと判定された海洋構造物1のモデルについて、海洋構造物1のモデルのうちの一部の形状において最終化可能であるか否かを確認するステップである。なお、海洋構造物1のモデルのうちの一部とは、海洋構造物1における、モノパイル本体10又はトランジションピース20のいずれかをいう。この場合、海洋構造物1のモデルのうちの一部とは、モノパイル本体10の一部であってもよいし、トランジションピース20の一部であってもよい。
海洋構造物1のモデルの一部のうち、最終化可能であると判定される部材(SA3c:できる部材)は、製作フローSBにおける後第1製作工程SB1c(後述する)を開始する。海洋構造物1のモデルの一部のうち、最終化可能でないと判定される部材(SA3c:できない部材)は、第3確認ステップSA3dに移行する。
The second confirmation step SA3c is a step of confirming whether or not the shape of a part of the model of the marine structure 1, for which it has been determined that not all components are finalizable, is finalizable. Note that the part of the model of the marine structure 1 refers to either the monopile body 10 or the transition piece 20 in the marine structure 1. In this case, the part of the model of the marine structure 1 may be a part of the monopile body 10 or a part of the transition piece 20.
Of the parts of the model of the marine structure 1, those parts that are determined to be finalizable (SA3c: parts that can be finalized) start the first manufacturing process SB1c (described later) in the manufacturing flow SB. Of the parts of the model of the marine structure 1, those parts that are determined to be not finalizable (SA3c: parts that cannot be finalized) move to the third confirmation step SA3d.

第3確認ステップSA3dは、海洋構造物1のモデルの一部のうち、最終化可能でないと判定された部材について、必要な補強の程度を確認するステップである。すなわち、第3確認ステップSA3dは、海洋構造物1のモデルについて、形状の変更をどの程度行う必要があるかを確認するステップである。
最終化可能でないと判定された部材について、比較的大規模な形状の修正が必要と判断された場合(SA3d:再び形状検討工程が必要)、該当する部材について、形状検討工程SA2に移行し、形状を再検討する。最終化可能でないと判定された部材について、大規模な形状の修正は必要ないと判断された場合(SA3d:部材断面や材質の見直し程度でよい)、該当する部材について、見直しステップSA3eに移行する。
The third confirmation step SA3d is a step of confirming the degree of necessary reinforcement for a member determined not to be finalizable among a part of the model of the marine structure 1. That is, the third confirmation step SA3d is a step of confirming the degree of the need to change the shape of the model of the marine structure 1.
If it is determined that a relatively large-scale shape modification is required for a component that is determined to be incomplete (SA3d: another shape review step is required), the component is transferred to the shape review step SA2, where the shape is reconsidered. If it is determined that a large-scale shape modification is not required for a component that is determined to be incomplete (SA3d: only a review of the component cross section and material is sufficient), the component is transferred to the review step SA3e.

見直しステップSA3eは、最終化可能でないと判定された部材について、大規模な形状の修正は必要ないと判断された場合に、海洋構造物1における該当する部材のモデルの形状を見直すステップである。見直しステップSA3eでは、例えば、該当する部材のモデルの断面の形状や、用いる材質の見直しを行う。見直しステップSA3eが完了した部材については、再び解析実施ステップSA3aを行う。
本実施形態において、形状検討工程SA2及び構造解析工程SA3は、最終的に海洋構造物1の形状が決定されるまで繰り返し行ってよい。
The review step SA3e is a step for reviewing the shape of the model of the corresponding member in the marine structure 1 when it is determined that large-scale shape modification is not necessary for the member determined to be not finalizable. In the review step SA3e, for example, the cross-sectional shape of the model of the corresponding member and the material used are reviewed. For members for which the review step SA3e has been completed, the analysis implementation step SA3a is performed again.
In this embodiment, the shape consideration step SA2 and the structure analysis step SA3 may be repeated until the shape of the marine structure 1 is finally determined.

本実施形態において、例えば、モノパイル本体10やトランジションピース20を構成する材料として、所定の数値刻みで径が変化する複数の種類の鋼管が在庫として確保されている場合、構造解析工程SA3は、海洋構造物1のモデルの構造解析を所定の径刻みでしか行わなくてもよい。この場合、形状検討工程SA2において、複数の形状として、在庫として確保された複数の種類の鋼管に合わせて、所定の径刻みのモデルを検討することが好ましい。換言すれば、構造解析工程SA3において、モノパイル本体10やトランジションピース20の径は、上述の形状検討工程SA2において、在庫として確保された複数の種類の鋼管に合わせて、所定の数値刻みで設定されたものが用いられてよい。具体的には、例えば、前記所定の径は、直径7000mmから15000mmまでの範囲で、500mm刻みであることが好ましいが、その他任意の数値であってもよい。 In this embodiment, for example, when multiple types of steel pipes whose diameters vary in a predetermined numerical increment are secured as stock as materials for constructing the monopile body 10 and the transition piece 20, the structural analysis step SA3 may perform structural analysis of the model of the marine structure 1 only in the predetermined diameter increment. In this case, it is preferable to consider models in the predetermined diameter increments as multiple shapes in the shape consideration step SA2 in accordance with the multiple types of steel pipes secured as stock. In other words, in the structural analysis step SA3, the diameters of the monopile body 10 and the transition piece 20 may be set in the above-mentioned shape consideration step SA2 in the predetermined numerical increments in accordance with the multiple types of steel pipes secured as stock. Specifically, for example, the predetermined diameter is preferably in the range of 7000 mm to 15000 mm in diameter in 500 mm increments, but may be any other numerical value.

また、例えば、モノパイル本体10やトランジションピース20を構成する材料として、所定の数値刻みで板厚が変化する複数の種類の板材や鋼管が在庫として確保されている場合、構造解析工程SA3は、海洋構造物1のモデルの構造解析を所定の板厚刻みでしか行わなくてもよい。この場合、形状検討工程SA2において、複数の形状として、在庫として確保された複数の種類の板材や鋼管に合わせて、所定の板厚刻みのモデルを検討することが好ましい。換言すれば、構造解析工程SA3において、モノパイル本体10やトランジションピース20の板厚は、上述の形状検討工程SA2において、在庫として確保された複数の種類の板材や鋼管に合わせて、所定の数値刻みで設定されたものが用いられてよい。具体的には、例えば、前記所定の板厚は、70mmから100mmまでの範囲で、5mm刻みであることが好ましいが、その他任意の数値であってもよい。 In addition, for example, when multiple types of plate materials or steel pipes whose thickness varies in a predetermined numerical increment are secured as materials constituting the monopile body 10 or the transition piece 20, the structural analysis step SA3 may perform structural analysis of the model of the marine structure 1 only in the predetermined plate thickness increment. In this case, it is preferable to consider models with a predetermined plate thickness increment as multiple shapes in the shape consideration step SA2 in accordance with the multiple types of plate materials and steel pipes secured as inventory. In other words, in the structural analysis step SA3, the plate thickness of the monopile body 10 or the transition piece 20 may be set in a predetermined numerical increment in accordance with the multiple types of plate materials and steel pipes secured as inventory in the above-mentioned shape consideration step SA2. Specifically, for example, the predetermined plate thickness is preferably in 5 mm increments in the range from 70 mm to 100 mm, but may be any other numerical value.

上述のように、構造解析工程SA3における径や板厚を、在庫として確保された複数の種類の板材や鋼管に合わせて所定の数値刻みで設定することで、在庫の余剰が生じることを抑えやすくすることに加えて、構造解析工程SA3において一度に実行する解析の回数を抑えることができる。よって、構造解析工程SA3を行いやすくすることができる。
以上のようにして、設計検討フローSAが行われる。
As described above, by setting the diameter and plate thickness in the structural analysis step SA3 in predetermined numerical increments in accordance with the multiple types of plate materials and steel pipes secured as inventory, it is possible to easily prevent excess inventory from occurring and also to reduce the number of analyses to be performed at one time in the structural analysis step SA3. This makes it easier to perform the structural analysis step SA3.
In this manner, the design review flow SA is performed.

ここで、構造解析工程SA3においては、上述の各種解析に数か月の期間を要することがある。また、海洋構造物1の形状(例えば、部材断面、材質等)は、初回の構造解析工程SA3の時点で概ね決定されることが多い。このとき、数回の構造解析工程SA3が行われ、海洋構造物1の形状が最終決定された後に海洋構造物1の製作を開始する場合、海洋構造物1の建設プロジェクトの工程を短縮する余地がある。
そこで本実施形態では、以下のように製作フローSBを行うことで、建設プロジェクトの工程を短縮することに寄与する。
Here, in the structural analysis step SA3, the various analyses described above may take several months. Furthermore, the shape of the marine structure 1 (e.g., member cross sections, materials, etc.) is often roughly determined at the time of the first structural analysis step SA3. In this case, if the structural analysis step SA3 is performed several times and the manufacture of the marine structure 1 is started after the shape of the marine structure 1 is finally determined, there is room to shorten the process of the construction project of the marine structure 1.
In this embodiment, the manufacturing flow SB is carried out as follows, thereby contributing to shortening the process of a construction project.

製作フローSBは、海洋構造物1を製作するフローである。具体的には、製作フローSBは、海洋構造物1を構成する材料の調達や、調達した材料の加工等を行うフローである。図5に示すように、製作フローSBは、第1製作工程SB1と、第2製作工程SB2と、組立工程SB3と、を備える。 The production flow SB is a flow for producing the marine structure 1. Specifically, the production flow SB is a flow for procuring materials that constitute the marine structure 1 and processing the procured materials. As shown in FIG. 5, the production flow SB includes a first production process SB1, a second production process SB2, and an assembly process SB3.

第1製作工程SB1は、例えば、上述した構造解析工程SA3であって、1回目の構造解析工程SA3に含まれる地震応答解析、の完了後であって、2回目の構造解析工程SA3に含まれる地震応答解析、の完了前に開始される工程である。第1製作工程SB1は、海洋構造物1を構成する部材のうち少なくとも一部を製作する工程である。
各部材の解析結果が相互に影響し合うので、通常は、上述の構造解析工程SA3が全て終わってから製作(調達)を開始するところ、本実施形態では、第1製作工程SB1が、例えば、上述の構造解析工程SA3において最終化可能とされた部材の製作を先行して開始することで、海洋構造物1の完成を早期化することに寄与する。
本実施形態において、第1製作工程SB1では、例えば、海洋構造物1を構成する部材の一部を製作してもよい。第1製作工程SB1において製作する前記一部の例については後述する。あるいは、第1製作工程SB1では、海洋構造物1を構成する部材の全部を製作してもよい。
The first manufacturing process SB1 is, for example, the structural analysis process SA3 described above, which is started after the completion of the earthquake response analysis included in the first structural analysis process SA3 and before the completion of the earthquake response analysis included in the second structural analysis process SA3. The first manufacturing process SB1 is a process for manufacturing at least a part of the members constituting the marine structure 1.
Since the analysis results of each component affect each other, production (procurement) would normally begin after all of the above-mentioned structural analysis process SA3 is completed. However, in this embodiment, the first production process SB1 contributes to accelerating the completion of the marine structure 1 by, for example, starting the production of components that are deemed to be finalizable in the above-mentioned structural analysis process SA3 in advance.
In this embodiment, the first manufacturing process SB1 may, for example, manufacture a part of the members constituting the marine structure 1. An example of the part manufactured in the first manufacturing process SB1 will be described later. Alternatively, the first manufacturing process SB1 may manufacture all of the members constituting the marine structure 1.

本実施形態において、第1製作工程SB1は、前第1製作工程SB1aと、中第1製作工程SB1bと、後第1製作工程SB1cと、を有する。なお、本実施形態において、第1製作工程SB1は、これらの工程のうち1つ、又は2つのみを備えていてもよい。また、本実施形態において、第1製作工程SB1を実施するとは、これらの工程のうち少なくともいずれか1つを実施することをいう。 In this embodiment, the first manufacturing process SB1 has a front first manufacturing process SB1a, a middle first manufacturing process SB1b, and a rear first manufacturing process SB1c. Note that in this embodiment, the first manufacturing process SB1 may include only one or two of these processes. Also, in this embodiment, performing the first manufacturing process SB1 means performing at least one of these processes.

前第1製作工程SB1aは、第1製作工程SB1のうち、事前調査工程SA1の前後に開始される工程である。前第1製作工程SB1aでは、モノパイル本体10やトランジションピース20を構成する材料のうち汎用性の高いものを、予め在庫として確保する工程である。前第1製作工程SB1aでは、例えば、モノパイル本体10やトランジションピース20を構成する材料として、径や板厚、材質が異なる複数の種類の鋼管の発注等を行う。
この時、複数の種類の鋼管における径や板厚は、所定の数値刻みで変化するようにしてよい。なお、前記所定の数値は、例えば、任意の数値で適宜決定されてよい。また、前記所定の数値は、例えば、離散値であってよい。
The first pre-fabrication process SB1a is a process that is started before or after the preliminary investigation process SA1 during the first fabrication process SB1. The first pre-fabrication process SB1a is a process for securing in advance as an inventory materials that are highly versatile among the materials that constitute the monopile body 10 and the transition pieces 20. In the first pre-fabrication process SB1a, for example, an order is placed for multiple types of steel pipes with different diameters, plate thicknesses, and materials as materials that constitute the monopile body 10 and the transition pieces 20.
In this case, the diameters and wall thicknesses of the multiple types of steel pipes may be changed in increments of a predetermined value. The predetermined value may be, for example, any value that is appropriately determined. The predetermined value may be, for example, a discrete value.

中第1製作工程SB1bは、第1製作工程SB1のうち、構造解析工程SA3の開始前に開始される工程である。本実施形態において、中第1製作工程SB1bは、形状検討工程SA2によって海洋構造物1の形状が検討された後に開始される。
中第1製作工程SB1bでは、例えば、前第1製作工程SB1aで調達されない材料の調達が行われる。具体的には、中第1製作工程SB1bでは、例えば、モノパイル本体10又はトランジションピース20を構成する材料のうち、形状検討工程SA2で形状が最終化されたものの発注等を行う。
The first intermediate manufacturing process SB1b is a process in the first manufacturing process SB1 that is started before the start of the structural analysis process SA3. In this embodiment, the first intermediate manufacturing process SB1b is started after the shape of the marine structure 1 is considered in the shape consideration process SA2.
In the first intermediate manufacturing process SB1b, for example, materials that are not procured in the first previous manufacturing process SB1a are procured. Specifically, in the first intermediate manufacturing process SB1b, for example, an order is placed for materials constituting the monopile body 10 or the transition piece 20, the shapes of which have been finalized in the shape review process SA2.

ここで、上述のように、形状検討工程SA2及び構造解析工程SA3において、海洋構造物1のモノパイル本体10やトランジションピース20の径及び板厚は、前第1製作工程SB1aにおいて調達された板材や鋼管に合わせて、所定の数値刻みで設定される。このことで、例えば、構造解析工程SA3の進行に伴いモノパイル本体10やトランジションピース20の径及び板厚が決定され次第、適切な材料を用いて部材の加工を開始できるようにすることができる。 As described above, in the shape consideration process SA2 and the structural analysis process SA3, the diameters and thicknesses of the monopile body 10 and transition pieces 20 of the marine structure 1 are set in predetermined numerical increments to match the plate materials and steel pipes procured in the first manufacturing process SB1a. This makes it possible to start processing the components using appropriate materials as soon as the diameters and thicknesses of the monopile body 10 and transition pieces 20 are determined as the structural analysis process SA3 progresses.

また、上述のようにモノパイル本体10やトランジションピース20の径及び板厚が設定されることで、前第1製作工程SB1a及び中第1製作工程SB1bにおいて準備することが必要な材料の種類を抑えることができる。よって、在庫の余剰が生じることを抑えやすくすることができる。
なお、上述のように調達された複数の径及び板厚を有する材料のうち、モノパイル本体10やトランジションピース20に用いられなかったものについては、他の部材や構造体等に転用されることが好ましい。このことによっても、より確実に、在庫の余剰が生じることを抑えやすくすることができる。
なお、中第1製作工程SB1bにおいては、海洋構造物1の付属設備30に用いられる材料が調達されてもよい。ただし、海洋構造物1の付属設備30に用いられる材料は、前第1製作工程SB1aや後第1製作工程SB1cにおいて、調達されてもよい。
中第1製作工程SB1bによっては、上述のように材料を先行して調達することで、海洋構造物1の完成の早期化に寄与することができる。
In addition, by setting the diameters and plate thicknesses of the monopile body 10 and the transition pieces 20 as described above, it is possible to reduce the types of materials that need to be prepared in the first front manufacturing process SB1a and the first intermediate manufacturing process SB1b. This makes it easier to prevent excess inventory.
In addition, among the materials having a plurality of diameters and plate thicknesses procured as described above, it is preferable that those not used for the monopile body 10 or the transition piece 20 are diverted to other members, structures, etc. This also makes it possible to more reliably prevent excess inventory from occurring.
In addition, in the first intermediate manufacturing process SB1b, materials to be used for the auxiliary equipment 30 of the marine structure 1 may be procured. However, the materials to be used for the auxiliary equipment 30 of the marine structure 1 may be procured in the first front manufacturing process SB1a or the first rear manufacturing process SB1c.
The first intermediate manufacturing process SB1b can contribute to hastening the completion of the marine structure 1 by procuring materials in advance as described above.

後第1製作工程SB1cは、第1製作工程SB1のうち、構造解析工程SA3の開始後に開始される工程である。本実施形態において、後第1製作工程SB1cは、例えば、構造解析工程SA3の第2確認ステップSA3cにおいて、海洋構造物1のモデルの一部のうち、最終化可能であると判定される部材(SA3c:できる部材)を製作する。上述のように、第2確認ステップSA3cにおける海洋構造物1のモデルのうちの一部とは、海洋構造物1における、モノパイル本体10又はトランジションピース20のいずれかをいう。後第1製作工程SB1cにおいては、これらのいずれかのうち、最終化可能と判断され、製作を開始可能となったものについて製作することが好ましい。 The post-first manufacturing process SB1c is a process in the first manufacturing process SB1 that is started after the start of the structural analysis process SA3. In this embodiment, the post-first manufacturing process SB1c, for example, manufactures a part of the model of the marine structure 1 that is determined to be finalizable (SA3c: possible part) in the second confirmation step SA3c of the structural analysis process SA3. As described above, the part of the model of the marine structure 1 in the second confirmation step SA3c refers to either the monopile body 10 or the transition piece 20 of the marine structure 1. In the post-first manufacturing process SB1c, it is preferable to manufacture either of these that is determined to be finalizable and for which manufacturing can be started.

後第1製作工程SB1cでは、主に材料を加工して、海洋構造物1における各種部材を形成することが行われる。本実施形態において、後第1製作工程SB1cの開始時期は、例えば、各部材の設計難易度や製作工程、海上施工工程等に応じて適宜設定されることが好ましい。あるいは、後第1製作工程SB1cは、例えば、構造解析工程SA3の進行に伴って各種部材のそれぞれの形状が決定され次第開始されてもよい。 In the first post-production process SB1c, materials are mainly processed to form various components of the marine structure 1. In this embodiment, it is preferable that the start time of the first post-production process SB1c is appropriately set depending on, for example, the design difficulty of each component, the production process, the offshore construction process, etc. Alternatively, the first post-production process SB1c may be started as soon as the shapes of each of the various components are determined as the structural analysis process SA3 progresses.

本実施形態では、上述した第1製作工程SB1を行うことで、洋上風車WMの完成の早期化に寄与する。なお、第1製作工程SB1において製作される部材は、検討の上適宜決定されることが好ましい。
本実施形態において、第1製作工程SB1では、例えば、海洋構造物1を製作する工程上、律速となる部材を製作する。本実施形態において、律速となるとは、例えば、材料の調達に長期間を要することや、材料の加工及び組み立てに長期間を要することにより、海洋構造物1の製作の工程を短縮する余地があることをいう。
以下、海洋構造物1を製作する工程上律速となる部材について数例説明する。本実施形態では、以下に述べる部材のいずれかについて適宜選択の上、第1製作工程SB1において製作することが好ましい。
In this embodiment, performing the above-mentioned first manufacturing process SB1 contributes to early completion of the offshore wind turbine WM. Note that it is preferable that the members to be manufactured in the first manufacturing process SB1 are appropriately determined after careful consideration.
In this embodiment, the first manufacturing process SB1 manufactures, for example, components that are rate-limiting in the manufacturing process of the marine structure 1. In this embodiment, being rate-limiting means that, for example, it takes a long time to procure materials, or it takes a long time to process and assemble materials, and therefore there is room to shorten the manufacturing process of the marine structure 1.
Below, there will be described several examples of members that are rate-limiting in the manufacturing process of the marine structure 1. In this embodiment, it is preferable to appropriately select any of the members described below and manufacture them in the first manufacturing process SB1.

第1製作工程SB1では、例えば、シアキーが付いている部材を製作する。シアキーは比較的溶接量が多いことから、製作に長期間を要する。このため、第1製作工程SB1においてシアキーが付いている部材を製作してもよい。 In the first manufacturing process SB1, for example, a component with a shear key is manufactured. Since shear keys require a relatively large amount of welding, they take a long time to manufacture. For this reason, a component with a shear key may be manufactured in the first manufacturing process SB1.

第1製作工程SB1では、例えば、付属設備30を製作してもよい。付属設備30は、係船設備31、梯子32、踊場33及び作業床34、通路35のうち少なくとも何れかである。これらの付属設備30は比較的溶接量が多いことから、製作に長期間を要する。このため、第1製作工程SB1においてこれらの付属設備30を製作してもよい。 In the first manufacturing process SB1, for example, the auxiliary equipment 30 may be manufactured. The auxiliary equipment 30 is at least one of the mooring equipment 31, ladder 32, landing 33, work platform 34, and passageway 35. These auxiliary equipment 30 require a relatively large amount of welding, and therefore require a long period of time to manufacture. For this reason, these auxiliary equipment 30 may be manufactured in the first manufacturing process SB1.

第1製作工程SB1では、例えば、インターフェイスフランジIFを製作してもよい。インターフェイスフランジIFは防食加工に手間を要するため、製作に長期間を要する。このため、第1製作工程SB1においてインターフェイスフランジIFを製作してもよい。 In the first manufacturing process SB1, for example, an interface flange IF may be manufactured. The interface flange IF requires time-consuming anti-corrosion processing, and therefore takes a long time to manufacture. For this reason, the interface flange IF may be manufactured in the first manufacturing process SB1.

第1製作工程SB1では、例えば、モノパイル本体10を製作してもよい。上述のように、モノパイル本体10は、単位筒状体11を長手方向に複数接続することで形成されることから、比較的溶接量が多い。また、第1製作工程SB1において、モノパイル本体10の内面及び外面のうち少なくとも一方に、被覆防食されることがある。このことから、モノパイル本体10は製作に長期間を要する。このため、第1製作工程SB1においてモノパイル本体10を製作してもよい。 In the first manufacturing process SB1, for example, the monopile body 10 may be manufactured. As described above, the monopile body 10 is formed by connecting multiple unit cylindrical bodies 11 in the longitudinal direction, and therefore requires a relatively large amount of welding. Also, in the first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 may be coated with anti-corrosion coating. For this reason, the monopile body 10 takes a long time to manufacture. For this reason, the monopile body 10 may be manufactured in the first manufacturing process SB1.

また、第1製作工程SB1では、例えば、モノパイル本体10のうち、特に土中に設置される部分を製作してもよい。上述のように、モノパイル本体10のうち、土中に設置される部分や、特に海底OFの表面(海底面)に近い部分は、その他の部分に比べて比較的大きな曲げモーメントが作用することがあることから、比較的板厚が大きい材料が用いられることがある。このような材料は通常の板厚の材料に対して溶接量が多いことから、加工に長期間を要することがある。このため、第1製作工程SB1において、モノパイル本体10のうち、特に土中に設置される部分を製作してもよい。より具体的には、例えば、モノパイル本体10のうち、特に土中に設置される部分に用いられる材料を先行して調達してもよい。
また、第1製作工程SB1では、モノパイル本体10のうちトランジションピース20と水平方向視で重複する状態で接続される接続部を製作し、モノパイル本体10のうち前記接続部以外の部分を製作しないようにしてもよい。
Also, in the first manufacturing step SB1, for example, the portion of the monopile body 10 that is to be installed underground may be manufactured. As described above, the portion of the monopile body 10 that is to be installed underground, and particularly the portion close to the surface (seabed surface) of the seabed OF, may be subjected to a relatively large bending moment compared to other portions, and therefore a material with a relatively large plate thickness may be used. Such materials require a large amount of welding compared to materials with normal plate thicknesses, and therefore may require a long period of time for processing. For this reason, in the first manufacturing step SB1, the portion of the monopile body 10 that is to be installed underground may be manufactured. More specifically, for example, the material to be used for the portion of the monopile body 10 that is to be installed underground may be procured in advance.
In addition, in the first manufacturing process SB1, a connection portion of the monopile body 10 is manufactured so that it is connected to the transition piece 20 in a state where it overlaps with the transition piece 20 when viewed horizontally, and no portion of the monopile body 10 other than the connection portion is manufactured.

本実施形態において、第1製作工程SB1では、例えば、上述した律速となる部材のほか、構造解析工程SA3の前後で形状の変更が生じにくい部材を製作してもよい。具体的には、例えば、以下の通りである。
すなわち、第1製作工程SB1では、例えば、トランジションピース20を製作してもよい。上述のように、トランジションピース20は、モノパイル本体10の上部に重なるように配置される。このため、トランジションピース20は、相対的に強度が高くなることから、構造解析工程SA3の前後で形状の変更が生じにくい。このため、第1製作工程SB1においてトランジションピース20を製作してもよい。
また、第1製作工程SB1では、トランジションピース20のうちインターフェイスフランジIFを製作せず、トランジションピース20のうちインターフェイスフランジIF以外の部分を製作してもよい。トランジションピース20のうちインターフェイスフランジIF以外の部分とは、例えば、トランジションピース20の側壁部である。
In this embodiment, in the first manufacturing process SB1, in addition to the rate-limiting components described above, a component whose shape is unlikely to change before and after the structural analysis process SA3 may be manufactured. Specifically, for example, the following is performed.
That is, in the first manufacturing process SB1, for example, the transition piece 20 may be manufactured. As described above, the transition piece 20 is disposed so as to overlap the upper part of the monopile body 10. Therefore, the transition piece 20 has a relatively high strength, and is unlikely to change in shape before and after the structural analysis process SA3. Therefore, the transition piece 20 may be manufactured in the first manufacturing process SB1.
In addition, in the first manufacturing process SB1, the interface flange IF of the transition piece 20 may not be manufactured, and a portion of the transition piece 20 other than the interface flange IF may be manufactured. The portion of the transition piece 20 other than the interface flange IF is, for example, a side wall portion of the transition piece 20.

本実施形態において、第1製作工程SB1では、上述した部材のうち少なくともいずれか1つを製作する。また、第1製作工程SB1では、上述した部材のうち複数の部材を製作してもよい。具体的には、例えば、後第1製作工程SB1cにおいて、モノパイル本体10、トランジションピース20及び付属設備30のうち少なくとも何れかを製作してもよい。あるいは、第1製作工程SB1では、上述した各種部材の全てを製作してもよい。 In this embodiment, at least one of the above-mentioned components is manufactured in the first manufacturing process SB1. Also, more than one of the above-mentioned components may be manufactured in the first manufacturing process SB1. Specifically, for example, at least one of the monopile body 10, the transition piece 20, and the auxiliary equipment 30 may be manufactured in the later first manufacturing process SB1c. Alternatively, all of the above-mentioned various components may be manufactured in the first manufacturing process SB1.

ここで、同一の設置場所Aに存在する複数の海洋構造物1は、一つずつ順番に設置されることがある。そこで、本実施形態において、第1製作工程SB1は、同一の設置場所Aに存在する複数の海洋構造物1のうち少なくとも一つについて行われることが好ましい。すなわち、複数の海洋構造物1のうち、最初に設置される1つ、又は初期に設置されるいくつかのみ、第1製作工程SB1が実施されることが好ましい。そして、構造解析工程SA3が完了した後に製作の順番が来る海洋構造物1については、第1製作工程SB1を行うことなく、構造解析工程SA3が完了した後に製作を開始することが好ましい。このことで、例えば、構造解析工程SA3の結果によって海洋構造物1の形状を変更する必要が生じた場合等に、海洋構造物1の製作のやり直しが生じることを抑えることができる。 Here, multiple marine structures 1 present at the same installation location A may be installed one by one in sequence. Therefore, in this embodiment, it is preferable that the first fabrication process SB1 is performed for at least one of the multiple marine structures 1 present at the same installation location A. In other words, it is preferable that the first fabrication process SB1 is performed only for the first one of the multiple marine structures 1 to be installed, or for some of the marine structures 1 to be installed initially. Then, for marine structures 1 whose turn comes for fabrication after the structural analysis process SA3 is completed, it is preferable to start fabrication after the structural analysis process SA3 is completed without performing the first fabrication process SB1. This makes it possible to prevent the need to redo fabrication of the marine structure 1, for example, when it becomes necessary to change the shape of the marine structure 1 based on the results of the structural analysis process SA3.

第2製作工程SB2は、海洋構造物1を構成する部材のうち第1製作工程SB1によって製作されない部材を、構造解析工程SA3の完了後に製作する工程である。第2製作工程SB2では、例えば、材料の調達や製作に長期間を要さない部材が製作されることが好ましい。また、第2製作工程SB2では、例えば、構造解析工程SA3において形状が決定されるのが比較的遅い部材を製作してもよい。このことで、形状の変更による部材の製作のやり直しが生じることを抑え、費用を抑えられるようにすることが好ましい。 The second manufacturing process SB2 is a process for manufacturing the components constituting the marine structure 1 that are not manufactured in the first manufacturing process SB1 after the structural analysis process SA3 is completed. In the second manufacturing process SB2, it is preferable to manufacture components that do not require a long period of time for material procurement and manufacturing, for example. In addition, in the second manufacturing process SB2, it is also possible to manufacture components whose shapes are determined relatively late in the structural analysis process SA3, for example. This is preferable to prevent the need to redo the manufacturing of components due to changes in shape, and to keep costs down.

組立工程SB3は、上述の第1製作工程SB1及び第2製作工程SB2で製作された各種部材を組み立てる工程である。
組立工程SB3は、例えば、第1製作工程SB1及び第2製作工程SB2が行われた工場等の場所で行われてもよい。この場合、海洋構造物1は、組立工程SB3の完了後に設置場所Aまで運搬されて設置されてもよい。
あるいは、組立工程SB3は、海洋構造物1の設置現場で行われてもよい。この場合、海洋構造物1は、組立工程SB3において組み立てると同時に設置場所Aに設置されてもよい。
以上の各工程により、本実施形態に係る工程計画方法は実施される。
The assembly process SB3 is a process for assembling the various members manufactured in the first manufacturing process SB1 and the second manufacturing process SB2 described above.
The assembly process SB3 may be performed, for example, at a location such as a factory where the first manufacturing process SB1 and the second manufacturing process SB2 are performed. In this case, the marine structure 1 may be transported to the installation site A and installed there after the assembly process SB3 is completed.
Alternatively, the assembly process SB3 may be performed at the installation site of the marine structure 1. In this case, the marine structure 1 may be installed at the installation site A at the same time as it is assembled in the assembly process SB3.
The process planning method according to this embodiment is carried out through the above-mentioned steps.

なお、本実施形態に係る工程計画方法は、例えば、コンピュータがプログラムを実施することによって実施されてもよい。このとき、コンピュータの各機能の全て又は一部は、ASIC(Application Specific Integrated Circuit)やPLD(Programmable Logic Device)やFPGA(Field Programmable Gate Array)等のハードウェアを用いて実現されてもよい。プログラムは、コンピュータ読み取り可能な記録媒体に記録されてもよい。コンピュータ読み取り可能な記録媒体とは、例えばフレキシブルディスク、光磁気ディスク、ROM、CD-ROM等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶装置である。プログラムは、電気通信回線を介して送信されてもよい。 The process planning method according to this embodiment may be implemented, for example, by a computer executing a program. In this case, all or part of the functions of the computer may be realized using hardware such as an ASIC (Application Specific Integrated Circuit), a PLD (Programmable Logic Device), or an FPGA (Field Programmable Gate Array). The program may be recorded on a computer-readable recording medium. Examples of computer-readable recording media include portable media such as flexible disks, optical magnetic disks, ROMs, and CD-ROMs, and storage devices such as hard disks built into computer systems. The program may be transmitted via a telecommunications line.

以上説明したように、本実施形態に係る工程計画方法によれば、1回目の構造解析工程SA3に含まれる地震応答解析の完了後であって2回目の構造解析工程SA3に含まれる地震応答解析の完了前に開始される第1製作工程SB1であって、海洋構造物1(モノパイル基礎)を構成する部材のうち少なくとも一部を製作する第1製作工程SB1を備える。これにより、第1製作工程SB1において、部材の製作を先行して開始することができる。よって、例えば、構造解析工程SA3の完了後に海洋構造物1の製作を開始する場合と比較して、海洋構造物1の建設プロジェクトの工程を短縮することができる。よって、洋上風車WMの操業開始を早期化することができる。
また、第1製作工程SB1は、トランジションピース20を製作する。第1製作工程SB1は、トランジションピース20のうちインターフェイスフランジIFを製作せず、トランジションピース20のうちインターフェイスフランジIF以外の部分を製作する。これにより、トランジションピース20のうちインターフェイスフランジIF以外の部分について、完成を待機する期間を短縮し、海洋構造物1の建設プロジェクトの工程を短縮することができる。また、トランジションピース20のうちインターフェイスフランジIFについては、構造解析工程SA3において生じる形状の変更に柔軟に対応しやすくすることができる。
また、第1製作工程SB1は、モノパイル本体10を製作する。第1製作工程SB1は、モノパイル本体10のうちトランジションピース20と水平方向視で重複する状態で接続される接続部を製作し、モノパイル本体10のうち接続部以外の部分を製作しない。これにより、モノパイル本体10のうちの接続部について、完成を待機する期間を短縮し、海洋構造物1の建設プロジェクトの工程を短縮することができる。また、モノパイル本体10のうちの接続部以外の部分については、構造解析工程SA3において生じる形状の変更に柔軟に対応しやすくすることができる。
As described above, the process planning method according to the present embodiment includes a first fabrication process SB1 that is started after completion of the earthquake response analysis included in the first structural analysis process SA3 and before completion of the earthquake response analysis included in the second structural analysis process SA3, and that fabricates at least some of the members that constitute the marine structure 1 (monopile foundation). This allows the fabrication of the members to be started in advance in the first fabrication process SB1. Therefore, for example, the process of the construction project for the marine structure 1 can be shortened compared to the case where the fabrication of the marine structure 1 is started after the structural analysis process SA3 is completed. Therefore, the operation of the offshore wind turbine WM can be started earlier.
Moreover, the first manufacturing process SB1 manufactures the transition piece 20. The first manufacturing process SB1 does not manufacture the interface flange IF of the transition piece 20, but manufactures the portion of the transition piece 20 other than the interface flange IF. This shortens the waiting period for completion of the portion of the transition piece 20 other than the interface flange IF, and shortens the process of the construction project for the marine structure 1. Furthermore, the interface flange IF of the transition piece 20 can easily and flexibly respond to changes in shape that occur in the structural analysis process SA3.
In addition, the first manufacturing process SB1 manufactures the monopile body 10. In the first manufacturing process SB1, a connection portion of the monopile body 10 that is connected to the transition piece 20 in a state where it overlaps with the transition piece 20 in a horizontal view is manufactured, and no portion of the monopile body 10 other than the connection portion is manufactured. This shortens the waiting period for the completion of the connection portion of the monopile body 10, and shortens the process of the construction project for the marine structure 1. In addition, the portion of the monopile body 10 other than the connection portion can be easily and flexibly adapted to changes in shape that occur in the structural analysis process SA3.

また、構造解析工程SA3において、海洋構造物1のモデルを用いて構造解析を行う。そして、第1製作工程SB1において、構造解析工程SA3の完了前に、海洋構造物1を構成する部材のうち少なくとも一部を製作する。これにより、例えば、構造解析工程SA3の完了後に海洋構造物1の製作を開始する場合と比較して、海洋構造物1の建設プロジェクトの工程を短縮することができる。よって、洋上風車WMの操業開始を早期化することができる。 In addition, in the structural analysis process SA3, structural analysis is performed using a model of the marine structure 1. Then, in the first manufacturing process SB1, at least some of the components that make up the marine structure 1 are manufactured before the structural analysis process SA3 is completed. This makes it possible to shorten the process of the construction project for the marine structure 1 compared to, for example, a case in which manufacturing of the marine structure 1 begins after the structural analysis process SA3 is completed. This makes it possible to start operation of the offshore wind turbine WM earlier.

また、第1製作工程SB1は、海洋構造物1を構成する部材の一部を製作する。このように、構造解析工程SA3が行われる前の第1製作工程SB1において、海洋構造物1を構成する部材の一部を製作することで、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The first manufacturing process SB1 also manufactures some of the components that make up the marine structure 1. In this way, by manufacturing some of the components that make up the marine structure 1 in the first manufacturing process SB1 before the structural analysis process SA3 is performed, the process of the construction project for the marine structure 1 can be shortened.

また、構造解析工程SA3は、海洋構造物1のモデルの構造解析を所定の径刻みでしか行わない。このように、海洋構造物1の製作に用いる管の径を、構造解析が行われる径に合わせて所定の径刻みで管理することで、管の在庫を管理しやすくすることができる。具体的には、例えば、予め調達され、構造解析の結果によって海洋構造物1の製作に用いられないこととなった径の管が生じることを抑え、在庫の余剰が生じることを抑えることができる。
また、例えば、海洋構造物1のモデルの構造解析を、想定される全ての径によって行う場合と比較して、構造解析を実施する回数を抑えることができる。よって、構造解析工程SA3を短縮することができる。
Moreover, the structural analysis step SA3 performs structural analysis of the model of the marine structure 1 only at a predetermined diameter increment. In this way, by managing the diameter of the pipes used in the production of the marine structure 1 at a predetermined diameter increment in accordance with the diameter for which the structural analysis is performed, it is possible to easily manage the inventory of pipes. Specifically, for example, it is possible to prevent the occurrence of pipes of a diameter that are procured in advance and then not used in the production of the marine structure 1 due to the results of the structural analysis, and thus prevent the occurrence of surplus inventory.
In addition, for example, the number of times the structural analysis is performed can be reduced compared to the case where the structural analysis of the model of the marine structure 1 is performed for all possible diameters. Therefore, the structural analysis step SA3 can be shortened.

また、構造解析工程SA3は、海洋構造物1のモデルの構造解析を所定の板厚刻みでしか行わない。このように、海洋構造物1の製作に用いる板の板厚を、構造解析が行われる板厚に合わせて所定の板厚刻みで管理することで、板の在庫を管理しやすくすることができる。具体的には、例えば、予め調達され、構造解析の結果によって海洋構造物1の製作に用いられないこととなった板厚の板が生じることを抑え、在庫の余剰が生じることを抑えることができる。
また、例えば、海洋構造物1のモデルの構造解析を、想定される全ての板厚によって行う場合と比較して、構造解析を実施する回数を抑えることができる。よって、構造解析工程SA3を短縮することができる。
Moreover, the structural analysis step SA3 performs structural analysis of the model of the marine structure 1 only in predetermined plate thickness increments. In this way, by managing the plate thickness of the plate used in the production of the marine structure 1 in predetermined plate thickness increments according to the plate thickness for which the structural analysis is performed, it is possible to easily manage the plate inventory. Specifically, for example, it is possible to prevent the occurrence of plates of a plate thickness that are procured in advance and then not used in the production of the marine structure 1 due to the results of the structural analysis, and thus to prevent the occurrence of surplus inventory.
In addition, for example, the number of times the structural analysis is performed can be reduced compared to the case where the structural analysis of the model of the marine structure 1 is performed using all possible plate thicknesses. Therefore, the structural analysis step SA3 can be shortened.

また、第1製作工程SB1は、海洋構造物1を製作する工程上、律速となる部材を製作する。このように、律速となる部材を第1製作工程SB1において先行して製作することで、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The first manufacturing process SB1 also produces the components that are rate-limiting in the manufacturing process of the marine structure 1. In this way, by manufacturing the rate-limiting components in advance in the first manufacturing process SB1, the process of the construction project for the marine structure 1 can be shortened.

ここで、シアキーは比較的溶接量が多く、海洋構造物1の製作において律速となることがある。そこで、第1製作工程SB1は、シアキーが付いている部材を製作する。このように、構造解析工程SA3の前に行われる第1製作工程SB1においてシアキーが付いている部材を製作することで、シアキーが付いている部材の完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 Here, the shear key requires a relatively large amount of welding, which can be a rate-limiting factor in the production of the marine structure 1. Therefore, in the first production process SB1, a component with a shear key is produced. In this way, by producing a component with a shear key in the first production process SB1, which is carried out before the structural analysis process SA3, the waiting period for the completion of the component with the shear key can be shortened (or eliminated), and the process of the construction project for the marine structure 1 can be shortened.

また、海洋構造物1は、付属設備30を有する。付属設備30の溶接量が多い場合、海洋構造物1の製作において律速となることがある。そこで、第1製作工程SB1は、付属設備30を製作する。これにより、付属設備30の完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The marine structure 1 also has auxiliary equipment 30. If the auxiliary equipment 30 requires a large amount of welding, this can become a rate-limiting step in the manufacture of the marine structure 1. Therefore, the first manufacturing process SB1 manufactures the auxiliary equipment 30. This shortens (or eliminates) the waiting period for the completion of the auxiliary equipment 30, and shortens the process of the construction project for the marine structure 1.

また、付属設備30は、係船設備31、梯子32、踊場33及び作業床34、通路35のうち少なくとも何れかである。これにより、係船設備31、梯子32、踊場33及び作業床34、通路35の何れかの完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The auxiliary facilities 30 are at least one of the mooring facilities 31, ladders 32, landings 33, work platforms 34, and passageways 35. This shortens (or eliminates) the waiting period for the completion of any of the mooring facilities 31, ladders 32, landings 33, work platforms 34, and passageways 35, thereby shortening the construction project process for the marine structure 1.

また、海洋構造物1は、トランジションピース20を有する。トランジションピース20は海洋構造物1の上部に重なるように配置されることで、相対的に強度が高くなる。このため、トランジションピース20は、海洋構造物1の解析結果による形状の変更が生じる可能性が比較的低い。そこで、第1製作工程SB1は、トランジションピース20を製作する。これにより、海洋構造物1の製作期間をより短縮しやすくすることができる。あるいは、トランジションピース20の完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The marine structure 1 also has a transition piece 20. The transition piece 20 is arranged so as to overlap the upper part of the marine structure 1, which makes it relatively strong. For this reason, the transition piece 20 is relatively unlikely to have its shape changed due to the analysis results of the marine structure 1. Therefore, the first manufacturing process SB1 manufactures the transition piece 20. This makes it easier to shorten the manufacturing period of the marine structure 1. Alternatively, the waiting period for the completion of the transition piece 20 can be shortened (or eliminated), thereby shortening the process of the construction project of the marine structure 1.

また、トランジションピース20は、インターフェイスフランジIFを有する。インターフェイスフランジIFは防食加工が必要とされることから、海洋構造物1の製作において律速となることがある。そこで、第1製作工程SB1は、インターフェイスフランジIFを製作する。これにより、インターフェイスフランジIFの完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The transition piece 20 also has an interface flange IF. The interface flange IF requires corrosion protection processing, which can be a rate-limiting factor in the production of the marine structure 1. Therefore, the first production process SB1 produces the interface flange IF. This shortens (or eliminates) the waiting period for the interface flange IF to be completed, and shortens the process of the construction project for the marine structure 1.

また、海洋構造物1は、モノパイル基礎である。モノパイル基礎は、モノパイル本体10を有し、第1製作工程SB1は、モノパイル本体10を製作する。これにより、モノパイル本体10の完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The marine structure 1 is a monopile foundation. The monopile foundation has a monopile body 10, and the first manufacturing process SB1 manufactures the monopile body 10. This shortens (or eliminates) the waiting period for the completion of the monopile body 10, and shortens the process of the construction project for the marine structure 1.

ここで、モノパイル本体10のうち土中に設置される部分や、当該部分のうち特に海底OFの表面(海底面)に近い部分には、比較的大きな曲げモーメントが作用することがある。このため、モノパイル本体10のうち土中に設置される部分は、板厚を大きくすることが必要とされることがある。このことで、当該部分に用いられる材料の溶接に要する期間が長くなり、海洋構造物1の製作において律速となることがある。そこで、第1製作工程SB1は、モノパイル本体10のうち土中に設置される部分を製作する。これにより、モノパイル本体10のうち土中に設置される部分の完成を待機する期間を短縮(又は解消)し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 Here, a relatively large bending moment may act on the portion of the monopile body 10 that is installed underground, and on that portion, particularly that portion close to the surface (seabed surface) of the seabed OF. For this reason, it may be necessary to increase the plate thickness of the portion of the monopile body 10 that is installed underground. This may lengthen the time required to weld the material used in that portion, which may become a rate-limiting factor in the manufacture of the marine structure 1. Therefore, the first manufacturing process SB1 manufactures the portion of the monopile body 10 that is installed underground. This shortens (or eliminates) the waiting period for the completion of the portion of the monopile body 10 that is installed underground, and shortens the process of the construction project for the marine structure 1.

また、海洋構造物1を構成する部材のうち第1製作工程SB1によって製作されない部材を、第2製作工程SB2において構造解析工程SA3の完了後に製作する。これにより、例えば、部材の製作途中に形状の変更が生じ、製作のやり直しが発生することを抑えやすくすることができる。また、例えば、構造解析工程SA3の前に予め調達された材料が海洋構造物1の製作に用いられないことで、在庫の余剰が生じることを抑えやすくすることができる。したがって、材料の使用量を減らし、海洋構造物1の製作コストを抑えることができる。 In addition, the components constituting the marine structure 1 that are not produced in the first production process SB1 are produced in the second production process SB2 after the structural analysis process SA3 is completed. This makes it easier to prevent, for example, changes to the shape of the components occurring during production, which may result in redoing the production. Also, for example, it makes it easier to prevent excess inventory from occurring, as materials procured in advance before the structural analysis process SA3 are not used in the production of the marine structure 1. This reduces the amount of material used and the production costs of the marine structure 1.

また、第1製作工程SB1は、海洋構造物1を構成する部材の全部を製作する。これにより、より確実に海洋構造物1の建設プロジェクトの工程を短縮することができる。また、例えば、第1製作工程SB1において海洋構造物1を構成する部材の一部のみを製作する場合と比較して、部材のそれぞれを製作する順番を調整しやすくすることができる。よって、第1製作工程SB1を効率的に行いやすくすることができる。 The first manufacturing process SB1 also manufactures all of the components that make up the marine structure 1. This makes it possible to more reliably shorten the process of the construction project for the marine structure 1. Also, for example, compared to a case in which only some of the components that make up the marine structure 1 are manufactured in the first manufacturing process SB1, it is easier to adjust the order in which each component is manufactured. This makes it easier to carry out the first manufacturing process SB1 efficiently.

ここで、同一の設置場所Aに存在する複数の海洋構造物1が、一つずつ順番に設置されることがある。そこで、第1製作工程SB1は、同一の設置場所Aに存在する複数の海洋構造物1のうち少なくとも一つについて行われる。これにより、例えば、複数の海洋構造物1のうち初期に設置される海洋構造物1について、第1製作工程SB1によって早期に製作を開始することができる。これにより、海洋構造物1の建設プロジェクトの開始から海洋構造物1の設置開始までの期間を短縮しやすくすることができる。 Here, multiple marine structures 1 at the same installation location A may be installed one by one in sequence. Therefore, the first manufacturing process SB1 is performed for at least one of the multiple marine structures 1 at the same installation location A. This allows, for example, early manufacturing to begin for the marine structure 1 that is to be installed first among the multiple marine structures 1 by the first manufacturing process SB1. This makes it easier to shorten the period from the start of a construction project for the marine structure 1 to the start of installation of the marine structure 1.

また、第1製作工程SB1は、構造解析工程SA3の開始前に開始される前第1製作工程SB1a及び中第1製作工程SB1bと、構造解析工程SA3の開始後に開始される後第1製作工程SB1cと、を有する。これにより、例えば、海洋構造物1において、構造解析工程SA3の開始前に形状が確定済である部材について、前第1製作工程SB1a及び中第1製作工程SB1bによって製作を開始し、その他の部材については、後第1製作工程SB1cにおいて製作を開始することができる。よって、不確定な要素を含む部材について、構造解析工程SA3の前に製作を開始することを抑えることができる。よって、海洋構造物1の形状が変更されることによって、部材の製作のやり直しが発生することを抑えやすくすることができる。よって、工程計画を最適なものにすることができる。また、費用が増大することを未然に抑えやすくすることができる。 The first manufacturing process SB1 includes a pre-first manufacturing process SB1a and a middle-first manufacturing process SB1b that are started before the start of the structural analysis process SA3, and a post-first manufacturing process SB1c that is started after the start of the structural analysis process SA3. As a result, for example, in the marine structure 1, for members whose shapes have been determined before the start of the structural analysis process SA3, manufacturing can be started by the pre-first manufacturing process SB1a and the middle-first manufacturing process SB1b, and manufacturing can be started for other members in the post-first manufacturing process SB1c. Therefore, it is possible to prevent the start of manufacturing of members that include uncertain elements before the structural analysis process SA3. Therefore, it is possible to easily prevent the need to redo the manufacturing of members due to changes in the shape of the marine structure 1. Therefore, it is possible to optimize the process plan. It is also possible to easily prevent increases in costs.

また、海洋構造物1は、モノパイル基礎である。モノパイル基礎は、トランジションピース20と、付属設備30と、を有し、後第1製作工程SB1cは、トランジションピース20及び付属設備30のうち少なくとも何れかを製作する。このように、構造解析工程SA3の開始後に開始される後第1製作工程SB1cにおいて、トランジションピース20及び付属設備30のうち少なくとも何れかを製作することで、トランジションピース20及び付属設備30の何れかの製作のやり直しが発生することを抑えやすくすることができる。 The marine structure 1 is a monopile foundation. The monopile foundation has a transition piece 20 and ancillary equipment 30, and the first post-fabrication process SB1c fabricates at least one of the transition piece 20 and the ancillary equipment 30. In this way, by fabricating at least one of the transition piece 20 and the ancillary equipment 30 in the first post-fabrication process SB1c, which is started after the start of the structural analysis process SA3, it is possible to more easily prevent the need to redo the fabrication of either the transition piece 20 or the ancillary equipment 30.

また、海洋構造物1は、モノパイル基礎である。モノパイル基礎は、モノパイル本体10を有し、第1製作工程SB1において、モノパイル本体10の内面及び外面のうち少なくとも一方に、被覆防食される。これにより、モノパイル本体10に被覆防食する作業の完了を待機する期間を短縮し、海洋構造物1の建設プロジェクトの工程を短縮することができる。 The marine structure 1 is a monopile foundation. The monopile foundation has a monopile body 10, and in the first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 is coated and protected from corrosion. This shortens the waiting period for the completion of the work of coating and protecting the monopile body 10 from corrosion, and shortens the process of the construction project for the marine structure 1.

また、海洋構造物1には、本開示に係る工程計画方法が適用される。これにより、海洋構造物1の建設プロジェクトの工程を短縮することができる。よって、洋上風車WMの操業開始を早期化することができる。 The process planning method according to the present disclosure is also applied to the marine structure 1. This makes it possible to shorten the process of the construction project for the marine structure 1. This allows the offshore wind turbine WM to start operation earlier.

(第2実施形態)
次に、本開示に係る第2実施形態の工程計画方法を説明する。
なお、この第2実施形態においては、第1実施形態における構成要素と同一の部分については同一の符号を付し、その説明を省略し、異なる点についてのみ説明する。
Second Embodiment
Next, a process planning method according to a second embodiment of the present disclosure will be described.
In the second embodiment, the same components as those in the first embodiment are denoted by the same reference numerals, and their description will be omitted, with only the differences being described.

第2実施形態において、第1製作工程SB1では、例えば、海洋構造物1を製作する工程上、律速とならない部材を製作しない。本実施形態において、律速とならないとは、例えば、材料の調達や、材料の加工及び組み立てに長期間を要さないことにより、海洋構造物1の製作の工程を短縮する余地が少ないことや、構造解析工程SA3において形状の変更が発生する可能性が相対的に高いことから、形状が決定してから製作を開始することがより好ましいことをいう。
このように、律速とならない部材について、構造解析工程SA3の完了前に行われる第1製作工程SB1で製作しないことで、形状が決定した後に製作を開始できるようにする。このことで、製作途中に形状の変更が発生しないようにすることで、製作のやり直しが発生することを抑えられるようにすることに寄与する。
以下、海洋構造物1を製作する工程上律速とならない部材について数例説明する。本実施形態では、以下に述べる部材のいずれかについて適宜選択の上、第1製作工程SB1において製作しないようにすることが好ましい。
In the second embodiment, in the first manufacturing process SB1, for example, no components are manufactured that are not rate-limiting in the process of manufacturing the marine structure 1. In this embodiment, not being rate-limiting means, for example, that there is little room to shorten the manufacturing process of the marine structure 1 because procuring materials and processing and assembling the materials do not require a long period of time, and that there is a relatively high possibility that changes to the shape will occur in the structural analysis process SA3, so it is more preferable to start manufacturing after the shape is determined.
In this way, for the members that are not rate-limiting, by not manufacturing them in the first manufacturing process SB1 that is performed before the completion of the structural analysis process SA3, manufacturing can be started after the shape is determined. This prevents changes to the shape during manufacturing, which contributes to reducing the need to redo manufacturing.
Below, we will explain several examples of members that are not rate-limiting in the process of manufacturing the marine structure 1. In this embodiment, it is preferable to appropriately select any of the members described below and not manufacture them in the first manufacturing process SB1.

第2実施形態において、第1製作工程SB1では、例えば、トランジションピース20を製作しないようにする。トランジションピース20は、海洋構造物1において、加工費や、用いられる材料(例えば、鋼材)の重量において大きな割合を占める部材である。このため、第1製作工程SB1でトランジションピース20を製作せず、形状が決定された後に製作することで、より製作のやり直しによって費用が生じることを抑えられるようにしてもよい。 In the second embodiment, for example, the transition piece 20 is not manufactured in the first manufacturing process SB1. The transition piece 20 is a component that accounts for a large proportion of the processing cost and the weight of the material (e.g., steel) used in the marine structure 1. For this reason, it is possible to not manufacture the transition piece 20 in the first manufacturing process SB1, but to manufacture it after the shape has been determined, thereby further reducing costs incurred by reworking the manufacturing process.

第2実施形態において、第1製作工程SB1では、例えば、モノパイル本体10を製作しないようにしてもよい。モノパイル本体10は、海洋構造物1において用いられる材料(例えば、鋼材)の重量において大きな割合を占める部材である。このため、第1製作工程SB1でモノパイル本体10を製作せず、形状が決定された後に製作することで、より製作のやり直しによって費用が生じることを抑えられるようにしてもよい。 In the second embodiment, for example, the monopile body 10 may not be manufactured in the first manufacturing process SB1. The monopile body 10 is a component that accounts for a large proportion of the weight of the material (e.g., steel) used in the marine structure 1. For this reason, the monopile body 10 may not be manufactured in the first manufacturing process SB1, but may be manufactured after the shape has been determined, thereby further reducing costs incurred by reworking the manufacturing process.

第2実施形態において、第1製作工程SB1では、例えば、モノパイル本体10の両端部のうち少なくとも一方を製作しないようにしてもよい。上述のように、モノパイル本体10は、単位筒状体11を長手方向に複数接続することで形成される。この時、モノパイル本体10の両端以外に位置する単位筒状体11は両端が溶接されるのに対し、モノパイル本体10の両端に位置する単位筒状体11は一方の端のみが溶接される。したがって、モノパイル本体10の両端部は溶接量が少なく、製作工程上律速になりにくい。このため、第1製作工程SB1でモノパイル本体10の両端部のうち少なくとも一方を製作しないようにすることで、構造解析工程SA3における形状の変更に柔軟に対応しやすくすることができるようにしてもよい。 In the second embodiment, for example, in the first manufacturing process SB1, at least one of both ends of the monopile body 10 may not be manufactured. As described above, the monopile body 10 is formed by connecting multiple unit cylindrical bodies 11 in the longitudinal direction. At this time, the unit cylindrical bodies 11 located at other than both ends of the monopile body 10 are welded at both ends, whereas the unit cylindrical bodies 11 located at both ends of the monopile body 10 are welded only at one end. Therefore, the amount of welding at both ends of the monopile body 10 is small, and it is unlikely to be a rate-limiting factor in the manufacturing process. For this reason, by not manufacturing at least one of both ends of the monopile body 10 in the first manufacturing process SB1, it may be possible to more flexibly respond to changes in shape in the structural analysis process SA3.

第2実施形態において、第1製作工程SB1では、例えば、付属設備30を製作しないようにしてもよい。付属設備30は、係船設備31、梯子32、踊場33及び作業床34、通路35のうち少なくとも何れかである。これらの付属設備30は、海洋構造物1における主要な部材(例えば、トランジションピース20)の設計結果の影響を受けやすいことから、構造解析工程SA3によって形状の変更が発生しやすい。このため、第1製作工程SB1で付属設備30を製作せず、形状が決定された後に製作することで、より製作のやり直しによって費用が生じることを抑えられるようにしてもよい。 In the second embodiment, for example, the auxiliary equipment 30 may not be fabricated in the first fabrication process SB1. The auxiliary equipment 30 is at least one of the mooring equipment 31, ladder 32, landing 33, work platform 34, and passageway 35. These auxiliary equipment 30 are easily affected by the design results of the main components of the marine structure 1 (e.g., transition piece 20), and therefore their shapes are likely to change due to the structural analysis process SA3. For this reason, the auxiliary equipment 30 may not be fabricated in the first fabrication process SB1, but may be fabricated after the shape has been determined, thereby further reducing costs incurred by re-fabrication.

第2実施形態において、第1製作工程SB1では、上述した部材のうち少なくともいずれか1つを製作しないようにする。また、第1製作工程SB1では、上述した部材のうち複数の部材を製作しないようにしてもよい。あるいは、第1製作工程SB1では、上述した各種部材の全てを製作しないようにしてもよい。 In the second embodiment, at least one of the above-mentioned components is not produced in the first manufacturing process SB1. Also, it is possible to avoid producing a plurality of the above-mentioned components in the first manufacturing process SB1. Alternatively, it is possible to avoid producing all of the above-mentioned various components in the first manufacturing process SB1.

以上説明したように、第2実施形態に係る工程計画方法によれば、第1製作工程SB1は、海洋構造物1を製作する工程上、律速とならない部材を製作しない。これにより、製作しない部材について、形状の変更に柔軟に対応しやすくすることができる。 As described above, according to the process planning method of the second embodiment, the first manufacturing process SB1 does not manufacture components that are not rate-limiting in the manufacturing process of the marine structure 1. This makes it easier to flexibly respond to changes in shape for components that are not manufactured.

また、海洋構造物1は、トランジションピース20を有する。トランジションピース20は、用いられる材料の量や、加工の手間が比較的多い。そこで、第1製作工程SB1は、トランジションピース20を製作しない。これにより、トランジションピース20の製作を、トランジションピース20の形状が最適化された後に開始することができる。したがって、製作途中のトランジションピース20に形状の変更が生じること等を抑え、海洋構造物1の製作コストを抑えやすくすることができる。 The marine structure 1 also has a transition piece 20. The transition piece 20 requires a relatively large amount of material and processing effort. Therefore, the first manufacturing process SB1 does not manufacture the transition piece 20. This allows the manufacturing of the transition piece 20 to begin after the shape of the transition piece 20 has been optimized. This prevents the shape of the transition piece 20 from being changed during manufacturing, making it easier to reduce the manufacturing costs of the marine structure 1.

また、海洋構造物1は、モノパイル基礎であり、モノパイル基礎は、モノパイル本体10を有する。モノパイル本体10は、用いられる材料の量が比較的多い。そこで、第1製作工程SB1は、モノパイル本体10を製作しない。これにより、モノパイル本体10の製作を、モノパイル本体10の形状が最適化された後に開始することができる。したがって、製作途中のモノパイル本体10に形状の変更が生じること等を抑え、海洋構造物1の製作コストを抑えやすくすることができる。 The marine structure 1 is a monopile foundation, which has a monopile body 10. The monopile body 10 uses a relatively large amount of material. Therefore, the first manufacturing process SB1 does not manufacture the monopile body 10. This allows the manufacturing of the monopile body 10 to begin after the shape of the monopile body 10 has been optimized. This prevents the shape of the monopile body 10 from being changed during manufacturing, making it easier to reduce the manufacturing costs of the marine structure 1.

ここで、モノパイル本体10は、単位筒状体11を長手方向に複数溶接することで構成される。この時、モノパイル本体10の両端以外に位置する単位筒状体11は両端が溶接されるのに対し、モノパイル本体10の両端に位置する単位筒状体11は一方の端のみが溶接される。したがって、モノパイル本体10の両端部は溶接量が少なく、海洋構造物1の製作において比較的律速となりにくい。そこで、第1製作工程SB1は、モノパイル本体10の両端部のうち少なくとも一方を製作しない。これにより、当該部材において生じる形状の変更に柔軟に対応しやすくすることができる。 The monopile body 10 is constructed by welding multiple unit tubular bodies 11 in the longitudinal direction. At this time, the unit tubular bodies 11 located at positions other than both ends of the monopile body 10 are welded at both ends, whereas the unit tubular bodies 11 located at both ends of the monopile body 10 are welded at only one end. Therefore, the amount of welding at both ends of the monopile body 10 is small, and it is relatively unlikely to be a rate-limiting step in the manufacture of the marine structure 1. Therefore, in the first manufacturing process SB1, at least one of the two ends of the monopile body 10 is not manufactured. This makes it easier to flexibly respond to changes in shape that occur in the member.

また、海洋構造物1は、付属設備30を有する。付属設備30は、海洋構造物1における主要な部材(例えば、トランジションピース20)の設計結果の影響を受けやすいことから、形状の変更が発生しやすい。そこで、第1製作工程SB1は、付属設備30を製作しない。これにより、付属設備30の製作を、付属設備30の形状が最適化された後に開始することができる。したがって、製作途中の付属設備30に形状の変更が生じること等を抑え、海洋構造物1の製作コストを抑えやすくすることができる。 The marine structure 1 also has ancillary equipment 30. The ancillary equipment 30 is easily affected by the design results of the main components of the marine structure 1 (e.g., the transition piece 20), and is therefore prone to changes in shape. Therefore, the first manufacturing process SB1 does not manufacture the ancillary equipment 30. This allows the manufacturing of the ancillary equipment 30 to begin after the shape of the ancillary equipment 30 has been optimized. This prevents the ancillary equipment 30 from being subject to shape changes during manufacturing, making it easier to keep manufacturing costs of the marine structure 1 down.

また、付属設備30は、係船設備31、梯子32、踊場33及び作業床34、通路35のうち少なくとも何れかである。これにより、製作途中の係船設備31、梯子32、踊場33及び作業床34、通路35の何れかに形状の変更が生じること等を抑え、海洋構造物1の製作コストを抑えやすくすることができる。 The auxiliary equipment 30 is at least one of the mooring equipment 31, ladder 32, landing 33, work floor 34, and passageway 35. This prevents changes to the shape of the mooring equipment 31, ladder 32, landing 33, work floor 34, and passageway 35 during production, making it easier to reduce the production costs of the marine structure 1.

なお、本開示の技術的範囲は前記実施形態に限定されるものではなく、本開示の趣旨を逸脱しない範囲において種々の変更を加えることが可能である。
例えば、本実施形態に係る工程計画方法を、海洋構造物1以外の構造物に適用してもよい。
また、構造解析工程SA3において、海洋構造物1のモデルの構造解析を、所定の径刻みあるいは所定の板厚刻みで行わず、任意の径や板厚で行ってもよい。
また、第1製作工程SB1は、シアキーが付いている部材を製作しないようにしてもよい。
また、海洋構造物1は、トランジションピース20を備えなくてもよい。
また、海洋構造物1は、モノパイル基礎でなくてもよい。
また、第1製作工程SB1では、モノパイル本体10のうち土中に設置される部分を製作しないようにしてもよい。
また、第1製作工程SB1では、モノパイル本体10の両端部のうち一方又は両方を製作してもよい。
また、第1製作工程SB1では、海洋構造物1を構成する部材の全部を製作しないようにしてもよい。
また、第1製作工程SB1は、同一の設置場所Aに存在する複数の海洋構造物1の二つ以上について行われてもよいし、全てについて行われてもよい。
また、第1製作工程SB1は、中第1製作工程SB1bと、後第1製作工程SB1cと、を備えなくてもよい。
また、第1製作工程SB1においては、モノパイル本体10の内面及び外面のうち少なくとも一方に被覆防食しなくてもよい。
The technical scope of the present disclosure is not limited to the above-described embodiments, and various modifications can be made without departing from the spirit of the present disclosure.
For example, the process planning method according to this embodiment may be applied to structures other than the marine structure 1.
Furthermore, in the structural analysis step SA3, the structural analysis of the model of the marine structure 1 may be performed at any diameter or thickness instead of at a predetermined diameter or thickness increment.
Also, the first manufacturing process SB1 may be configured not to manufacture any members having shear keys.
Furthermore, the marine structure 1 does not need to be equipped with a transition piece 20.
Furthermore, the marine structure 1 does not have to be a monopile foundation.
In addition, in the first manufacturing process SB1, it is possible not to manufacture the portion of the monopile body 10 that is to be installed underground.
In addition, in the first manufacturing process SB1, one or both of the two end portions of the monopile body 10 may be manufactured.
In addition, in the first manufacturing process SB1, it is possible not to manufacture all of the components that make up the marine structure 1.
Furthermore, the first manufacturing process SB1 may be performed for two or more of the multiple marine structures 1 present at the same installation site A, or may be performed for all of them.
Furthermore, the first manufacturing process SB1 does not necessarily have to include the intermediate first manufacturing process SB1b and the subsequent first manufacturing process SB1c.
Furthermore, in the first manufacturing process SB1, at least one of the inner and outer surfaces of the monopile body 10 does not need to be coated with corrosion protection.

その他、本開示の趣旨に逸脱しない範囲で、前記実施形態における構成要素を周知の構成要素に置き換えることは適宜可能であり、また、前記した変形例を適宜組み合わせてもよい。 In addition, the components in the above embodiment may be replaced with well-known components as appropriate without departing from the spirit of this disclosure, and the above-mentioned modifications may be combined as appropriate.

(付記)
前記実施形態に係る工程計画方法及び海洋構造物は、例えば以下のように把握される。
(Additional Note)
The process planning method and the marine structure according to the embodiment can be understood, for example, as follows.

<1>本開示の一態様に係る工程計画方法は、モノパイル本体と、トランジションピースと、を有し、洋上風車のタワーを支持するモノパイル基礎の建設プロジェクトの工程を計画する工程計画方法であって、前記モノパイル基礎のモデルの構造解析を、コンピュータが複数回行う構造解析工程と、1回目の前記構造解析工程に含まれる地震応答解析の完了後であって2回目の前記構造解析工程に含まれる地震応答解析の完了前に開始される第1製作工程であって、前記モノパイル基礎を構成する部材のうち少なくとも一部を製作する第1製作工程と、を備え、前記第1製作工程は、前記トランジションピースを製作し、前記第1製作工程は、前記トランジションピースのうちインターフェイスフランジを製作せず、前記トランジションピースのうち前記インターフェイスフランジ以外の部分を製作し、前記第1製作工程は、前記モノパイル本体を製作し、前記第1製作工程は、前記モノパイル本体のうち前記トランジションピースと水平方向視で重複する状態で接続される接続部を製作し、前記モノパイル本体のうち前記接続部以外の部分を製作しない。 <1> A process planning method according to one aspect of the present disclosure is a process planning method for planning the process of a construction project of a monopile foundation that has a monopile body and a transition piece and supports the tower of an offshore wind turbine, the process including: a structural analysis process in which a computer performs structural analysis of a model of the monopile foundation multiple times; and a first manufacturing process that is started after completion of an earthquake response analysis included in the first structural analysis process and before completion of an earthquake response analysis included in the second structural analysis process, and that manufactures at least a part of the components that constitute the monopile foundation, the first manufacturing process manufacturing the transition piece, the first manufacturing process not manufacturing an interface flange of the transition piece, and manufacturing a part of the transition piece other than the interface flange, the first manufacturing process manufacturing the monopile body, the first manufacturing process manufacturing a connection part of the monopile body that is connected in a state where it overlaps with the transition piece in a horizontal view, and not manufacturing a part of the monopile body other than the connection part.

上記の工程計画方法によれば、1回目の構造解析工程に含まれる地震応答解析の完了後であって2回目の構造解析工程に含まれる地震応答解析の完了前に開始される第1製作工程であって、モノパイル基礎を構成する部材のうち少なくとも一部を製作する第1製作工程を備える。これにより、第1製作工程において、部材の製作を先行して開始することができる。よって、例えば、構造解析工程の完了後に海洋構造物の製作を開始する場合と比較して、海洋構造物の建設プロジェクトの工程を短縮することができる。よって、洋上風車の操業開始を早期化することができる。
また、第1製作工程は、トランジションピースを製作する。第1製作工程は、トランジションピースのうちインターフェイスフランジを製作せず、トランジションピースのうちインターフェイスフランジ以外の部分を製作する。これにより、トランジションピースのうちインターフェイスフランジ以外の部分について、完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。また、トランジションピースのうちインターフェイスフランジについては、構造解析工程において生じる形状の変更に柔軟に対応しやすくすることができる。
また、第1製作工程は、モノパイル本体を製作する。第1製作工程は、モノパイル本体のうちトランジションピースと水平方向視で重複する状態で接続される接続部を製作し、モノパイル本体のうち接続部以外の部分を製作しない。これにより、モノパイル本体のうちの接続部について、完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。また、モノパイル本体のうちの接続部以外の部分については、構造解析工程において生じる形状の変更に柔軟に対応しやすくすることができる。
According to the above process planning method, a first fabrication process is started after completion of the earthquake response analysis included in the first structural analysis process and before completion of the earthquake response analysis included in the second structural analysis process, and includes a first fabrication process for fabricating at least some of the components that constitute the monopile foundation. This allows the fabrication of the components to be started in advance in the first fabrication process. Therefore, for example, the process of a construction project for an offshore structure can be shortened compared to a case in which fabrication of the offshore structure is started after completion of the structural analysis process. Therefore, the operation of the offshore wind turbine can be started earlier.
Moreover, the first manufacturing process manufactures the transition piece. In the first manufacturing process, the interface flange of the transition piece is not manufactured, but the portion of the transition piece other than the interface flange is manufactured. This shortens the waiting period for the completion of the portion of the transition piece other than the interface flange, and shortens the process of the offshore structure construction project. Furthermore, the interface flange of the transition piece can easily and flexibly respond to changes in shape that occur in the structural analysis process.
In addition, the first manufacturing process manufactures the monopile body. In the first manufacturing process, a connection portion of the monopile body that is connected to the transition piece in a state where it overlaps with the transition piece in a horizontal view is manufactured, and no portion of the monopile body other than the connection portion is manufactured. This shortens the waiting period for the completion of the connection portion of the monopile body, and shortens the process of the marine structure construction project. In addition, the portion of the monopile body other than the connection portion can be easily and flexibly adapted to changes in shape that occur in the structural analysis process.

<2>本開示の一態様に係る工程計画方法は、洋上風車のタワーを支持する海洋構造物の建設プロジェクトの工程を計画する工程計画方法であって、前記海洋構造物のモデルの構造解析を行う構造解析工程と、前記構造解析工程完了前に、前記海洋構造物を構成する部材のうち少なくとも一部を製作する第1製作工程と、を備えることを特徴とする。 <2> A process planning method according to one aspect of the present disclosure is a process planning method for planning the process of a construction project for an offshore structure that supports the tower of an offshore wind turbine, and is characterized by comprising a structural analysis process for performing a structural analysis of a model of the offshore structure, and a first manufacturing process for manufacturing at least a portion of the components that make up the offshore structure before completion of the structural analysis process.

上記の工程計画方法によれば、構造解析工程において、海洋構造物のモデルを用いて構造解析を行う。そして、第1製作工程において、構造解析工程の完了前に、海洋構造物を構成する部材のうち少なくとも一部を製作する。これにより、例えば、構造解析工程の完了後に海洋構造物の製作を開始する場合と比較して、海洋構造物の建設プロジェクトの工程を短縮することができる。よって、洋上風車の操業開始を早期化することができる。 According to the above process planning method, in the structural analysis process, a structural analysis is performed using a model of the marine structure. Then, in the first manufacturing process, at least some of the components that make up the marine structure are manufactured before the structural analysis process is completed. This makes it possible to shorten the process of a construction project for the marine structure, for example, compared to a case in which manufacturing of the marine structure begins after the structural analysis process is completed. This makes it possible to start operation of the offshore wind turbine earlier.

<3>上記<2>に係る工程計画方法では、前記第1製作工程は、前記海洋構造物を構成する部材の一部を製作することを特徴とする構成を採用してもよい。 <3> In the process planning method according to <2> above, the first manufacturing process may be configured to manufacture a portion of a component that constitutes the marine structure.

また、第1製作工程は、海洋構造物を構成する部材の一部を製作する。このように、構造解析工程が行われる前の第1製作工程において、海洋構造物を構成する部材の一部を製作することで、海洋構造物の建設プロジェクトの工程を短縮することができる。 The first manufacturing process also produces some of the components that make up the marine structure. In this way, by producing some of the components that make up the marine structure in the first manufacturing process before the structural analysis process is performed, the process of the marine structure construction project can be shortened.

<4>上記<2>または<3>に係る工程計画方法では、前記構造解析工程は、前記海洋構造物のモデルの構造解析を所定の径刻みでしか行わないことを特徴とする構成を採用してもよい。 <4> In the process planning method according to <2> or <3> above, the structural analysis process may be configured to perform structural analysis of the marine structure model only at predetermined diameter intervals.

また、構造解析工程は、海洋構造物のモデルの構造解析を所定の径刻みでしか行わない。このように、海洋構造物の製作に用いる管の径を、構造解析が行われる径に合わせて所定の径刻みで管理することで、管の在庫を管理しやすくすることができる。具体的には、例えば、予め調達され、構造解析の結果によって海洋構造物の製作に用いられないこととなった径の管が生じることを抑え、在庫の余剰が生じることを抑えることができる。
また、例えば、海洋構造物のモデルの構造解析を、想定される全ての径によって行う場合と比較して、構造解析を実施する回数を抑えることができる。よって、構造解析工程を短縮することができる。
In addition, the structural analysis step performs structural analysis of the marine structure model only at a predetermined diameter interval. In this way, by managing the diameter of the pipes used in the manufacture of the marine structure at a predetermined diameter interval in accordance with the diameter for which the structural analysis is performed, it is possible to easily manage the inventory of pipes. Specifically, for example, it is possible to prevent the occurrence of pipes of a diameter that are procured in advance and then not used in the manufacture of the marine structure due to the results of the structural analysis, and thus prevent the occurrence of surplus inventory.
In addition, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the marine structure model is performed for all possible diameters, thereby shortening the structural analysis process.

<5>上記<2>から<4>のいずれか一態様に係る工程計画方法では、前記構造解析工程は、前記海洋構造物のモデルの構造解析を所定の板厚刻みでしか行わないことを特徴とする構成を採用してもよい。 <5> In the process planning method according to any one of the above <2> to <4>, the structural analysis process may be configured to perform structural analysis of the marine structure model only at a predetermined plate thickness increment.

また、構造解析工程は、海洋構造物のモデルの構造解析を所定の板厚刻みでしか行わない。このように、海洋構造物の製作に用いる板の板厚を、構造解析が行われる板厚に合わせて所定の板厚刻みで管理することで、板の在庫を管理しやすくすることができる。具体的には、例えば、予め調達され、構造解析の結果によって海洋構造物の製作に用いられないこととなった板厚の板が生じることを抑え、在庫の余剰が生じることを抑えることができる。
また、例えば、海洋構造物のモデルの構造解析を、想定される全ての板厚によって行う場合と比較して、構造解析を実施する回数を抑えることができる。よって、構造解析工程を短縮することができる。
In addition, the structural analysis step performs structural analysis of the marine structure model only in predetermined plate thickness increments. In this way, by managing the plate thickness of the plate used in the production of the marine structure in predetermined plate thickness increments according to the plate thickness for which the structural analysis is performed, it is possible to easily manage the plate inventory. Specifically, for example, it is possible to prevent the occurrence of plates of a plate thickness that are procured in advance and then not used in the production of the marine structure due to the results of the structural analysis, and thus prevent the occurrence of excess inventory.
In addition, for example, the number of times the structural analysis is performed can be reduced compared to when the structural analysis of the marine structure model is performed using all possible plate thicknesses, thereby shortening the structural analysis process.

<6>上記<2>から<5>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、前記海洋構造物を製作する工程上、律速となる部材を製作することを特徴とする構成を採用してもよい。 <6> In the process planning method according to any one of the above <2> to <5>, the first manufacturing process may be configured to manufacture a component that is rate-limiting in the manufacturing process of the marine structure.

また、第1製作工程は、海洋構造物を製作する工程上、律速となる部材を製作する。このように、律速となる部材を第1製作工程において先行して製作することで、海洋構造物の建設プロジェクトの工程を短縮することができる。 The first manufacturing process also produces the components that are rate-limiting in the manufacturing process of the marine structure. In this way, by manufacturing the rate-limiting components in advance in the first manufacturing process, the process of the marine structure construction project can be shortened.

<7>上記<2>から<6>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、シアキーが付いている部材を製作することを特徴とする構成を採用してもよい。 <7> In the process planning method according to any one of the above <2> to <6>, the first manufacturing process may be configured to manufacture a component having a shear key.

ここで、シアキーは比較的溶接量が多く、海洋構造物の製作において律速となることがある。そこで、第1製作工程は、シアキーが付いている部材を製作する。このように、構造解析工程の前に行われる第1製作工程においてシアキーが付いている部材を製作することで、シアキーが付いている部材の完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 Here, the shear key requires a relatively large amount of welding, which can be a rate-limiting factor in the production of marine structures. Therefore, in the first production process, components with shear keys are produced. In this way, by producing components with shear keys in the first production process, which is carried out before the structural analysis process, the waiting period for the completion of components with shear keys can be shortened, and the process of marine structure construction projects can be shortened.

<8>上記<2>から<7>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、付属設備を有し、前記第1製作工程は、前記付属設備を製作することを特徴とする構成を採用してもよい。 <8> In the process planning method according to any one of the above <2> to <7>, the marine structure may have auxiliary equipment, and the first manufacturing process may be configured to manufacture the auxiliary equipment.

また、海洋構造物は、付属設備を有する。付属設備の溶接量が多い場合、海洋構造物の製作において律速となることがある。そこで、第1製作工程は、付属設備を製作する。これにより、付属設備の完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 In addition, marine structures have auxiliary equipment. If the auxiliary equipment requires a large amount of welding, this can become a rate-limiting factor in the manufacture of the marine structure. Therefore, the first manufacturing process manufactures the auxiliary equipment. This shortens the waiting period for the completion of the auxiliary equipment, and shortens the process of the marine structure construction project.

<9>上記<8>に係る工程計画方法では、前記付属設備は、係船設備、梯子、踊場及び作業床、通路のうち少なくとも何れかであることを特徴とする構成を採用してもよい。 <9> In the process planning method according to <8> above, the auxiliary equipment may be at least one of a mooring facility, a ladder, a landing, a work platform, and a passageway.

また、付属設備は、係船設備、梯子、踊場及び作業床、通路のうち少なくとも何れかである。これにより、係船設備、梯子、踊場及び作業床、通路の何れかの完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 The auxiliary equipment is at least one of the following: mooring equipment, ladders, landings and work platforms, and gangways. This shortens the waiting period for the completion of the mooring equipment, ladders, landings and work platforms, and gangways, and shortens the process of the marine structure construction project.

<10>上記<2>から<9>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、トランジションピースを有し、前記第1製作工程は、前記トランジションピースを製作することを特徴とする構成を採用してもよい。 <10> In the process planning method according to any one of the above <2> to <9>, the marine structure may have a transition piece, and the first manufacturing process may be configured to manufacture the transition piece.

また、海洋構造物は、トランジションピースを有する。トランジションピースは海洋構造物の上部に重なるように配置されることで、相対的に強度が高くなる。このため、トランジションピースは、海洋構造物の解析結果による形状の変更が生じる可能性が比較的低い。そこで、第1製作工程は、トランジションピースを製作する。これにより、海洋構造物の製作期間をより短縮しやすくすることができる。あるいは、トランジションピースの完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 The marine structure also has a transition piece. The transition piece is placed so as to overlap the upper part of the marine structure, which makes it relatively strong. For this reason, the transition piece is relatively unlikely to undergo changes in shape due to the analysis results of the marine structure. Therefore, the first manufacturing process is to manufacture the transition piece. This makes it easier to shorten the manufacturing period of the marine structure. Alternatively, it is possible to shorten the waiting period for the completion of the transition piece and shorten the process of the marine structure construction project.

<11>上記<10>に係る工程計画方法では、前記トランジションピースは、インターフェイスフランジを有し、前記第1製作工程は、前記インターフェイスフランジを製作することを特徴とする構成を採用してもよい。 <11> In the process planning method according to <10> above, the transition piece may have an interface flange, and the first manufacturing process may be configured to manufacture the interface flange.

また、トランジションピースは、インターフェイスフランジを有する。インターフェイスフランジは防食加工が必要とされることから、海洋構造物の製作において律速となることがある。そこで、第1製作工程は、インターフェイスフランジを製作する。これにより、インターフェイスフランジの完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 The transition piece also has an interface flange. The interface flange requires corrosion protection processing, which can be a time-limiting step in the manufacture of marine structures. Therefore, the first manufacturing process is to manufacture the interface flange. This shortens the waiting period for the interface flange to be completed, and shortens the process of the marine structure construction project.

<12>上記<2>から<11>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、モノパイル基礎であり、前記モノパイル基礎は、モノパイル本体を有し、前記第1製作工程は、前記モノパイル本体を製作することを特徴とする構成を採用してもよい。 <12> In the process planning method according to any one of the above <2> to <11>, the marine structure may be a monopile foundation, the monopile foundation may have a monopile body, and the first manufacturing process may be configured to manufacture the monopile body.

また、海洋構造物は、モノパイル基礎である。モノパイル基礎は、モノパイル本体を有し、第1製作工程は、モノパイル本体を製作する。これにより、モノパイル本体の完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 The marine structure is a monopile foundation. The monopile foundation has a monopile body, and the first manufacturing process is to manufacture the monopile body. This shortens the waiting period for the completion of the monopile body, and shortens the process of the marine structure construction project.

<13>上記<12>に係る工程計画方法では、前記第1製作工程は、前記モノパイル本体のうち土中に設置される部分を製作することを特徴とする構成を採用してもよい。 <13> In the process planning method according to <12> above, the first manufacturing process may be configured to manufacture the portion of the monopile body that is to be installed underground.

ここで、モノパイル本体のうち土中に設置される部分や、当該部分のうち特に海底面に近い部分には、比較的大きな曲げモーメントが作用することがある。このため、モノパイル本体のうち土中に設置される部分は、板厚を大きくすることが必要とされることがある。このことで、当該部分に用いられる材料の溶接に要する期間が長くなり、海洋構造物の製作において律速となることがある。そこで、第1製作工程は、モノパイル本体のうち土中に設置される部分を製作する。これにより、モノパイル本体のうち土中に設置される部分の完成を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 Here, a relatively large bending moment may act on the portion of the monopile body that is installed underground, and on that portion, particularly that portion close to the seabed. For this reason, it may be necessary to increase the plate thickness of the portion of the monopile body that is installed underground. This may lengthen the time required to weld the material used in that portion, which may become a rate-limiting factor in the manufacture of marine structures. Therefore, the first manufacturing process manufactures the portion of the monopile body that is installed underground. This shortens the waiting period for the completion of the portion of the monopile body that is installed underground, and shortens the process of the marine structure construction project.

<14>上記<2>から<13>のいずれか一態様に係る工程計画方法では、前記海洋構造物を構成する部材のうち前記第1製作工程によって製作されない部材を、前記構造解析工程完了後に製作する第2製作工程を備えることを特徴とする構成を採用してもよい。 <14> The process planning method according to any one of the above <2> to <13> may be configured to include a second manufacturing process in which, after completion of the structural analysis process, components constituting the marine structure that are not manufactured by the first manufacturing process are manufactured.

また、海洋構造物を構成する部材のうち第1製作工程によって製作されない部材を、第2製作工程において構造解析工程の完了後に製作する。これにより、例えば、部材の製作途中に形状の変更が生じ、製作のやり直しが発生することを抑えやすくすることができる。また、例えば、構造解析工程の前に予め調達された材料が海洋構造物の製作に用いられないことで、在庫の余剰が生じることを抑えやすくすることができる。したがって、材料の使用量を減らし、海洋構造物の製作コストを抑えることができる。 In addition, the components constituting the marine structure that are not produced in the first production process are produced in the second production process after the structural analysis process is completed. This makes it easier to prevent, for example, changes to the shape of a component occurring during production, which would require redoing production. Also, for example, it makes it easier to prevent excess inventory from occurring, since materials procured in advance before the structural analysis process are not used in the production of the marine structure. This therefore reduces the amount of material used and the production costs of the marine structure.

<15>上記<2>から<14>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、前記海洋構造物を製作する工程上、律速とならない部材を製作しないことを特徴とする構成を採用してもよい。 <15> In the process planning method according to any one of the above <2> to <14>, the first manufacturing process may be configured to not manufacture any components that are not rate-limiting in the manufacturing process of the marine structure.

また、第1製作工程は、海洋構造物を製作する工程上、律速とならない部材を製作しない。これにより、製作しない部材について、形状の変更に柔軟に対応しやすくすることができる。 In addition, the first manufacturing process does not manufacture components that are not rate-limiting in the manufacturing process of the marine structure. This makes it easier to flexibly respond to changes in the shape of the components that are not manufactured.

<16>上記<2>から<15>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、トランジションピースを有し、前記第1製作工程は、前記トランジションピースを製作しないことを特徴とする構成を採用してもよい。 <16> In the process planning method according to any one of the above <2> to <15>, the marine structure may have a transition piece, and the first manufacturing process may be configured not to manufacture the transition piece.

また、海洋構造物は、トランジションピースを有する。トランジションピースは、用いられる材料の量や、加工の手間が比較的多い。そこで、第1製作工程は、トランジションピースを製作しない。これにより、トランジションピースの製作を、トランジションピースの形状が最適化された後に開始することができる。したがって、製作途中のトランジションピースに形状の変更が生じること等を抑え、海洋構造物の製作コストを抑えやすくすることができる。 The marine structure also has a transition piece. The transition piece requires a relatively large amount of material and processing effort. Therefore, the first manufacturing process does not manufacture the transition piece. This allows the manufacturing of the transition piece to begin after the shape of the transition piece has been optimized. This prevents the transition piece from being subject to shape changes during manufacturing, making it easier to reduce the manufacturing costs of the marine structure.

<17>上記<2>から<16>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、モノパイル基礎であり、前記モノパイル基礎は、モノパイル本体を有し、前記第1製作工程は、前記モノパイル本体を製作しないことを特徴とする構成を採用してもよい。 <17> In the process planning method according to any one of the above <2> to <16>, the marine structure may be a monopile foundation, the monopile foundation may have a monopile body, and the first manufacturing process may be configured not to manufacture the monopile body.

また、海洋構造物は、モノパイル基礎であり、モノパイル基礎は、モノパイル本体を有する。モノパイル本体は、用いられる材料の量が比較的多い。そこで、第1製作工程は、モノパイル本体を製作しない。これにより、モノパイル本体の製作を、モノパイル本体の形状が最適化された後に開始することができる。したがって、製作途中のモノパイル本体に形状の変更が生じること等を抑え、海洋構造物の製作コストを抑えやすくすることができる。 The marine structure is a monopile foundation, which has a monopile body. A relatively large amount of material is used in the monopile body. Therefore, the first manufacturing process does not manufacture the monopile body. This allows the manufacture of the monopile body to begin after the shape of the monopile body has been optimized. This prevents the shape of the monopile body from being changed during manufacturing, making it easier to reduce the manufacturing costs of the marine structure.

<18>上記<17>に係る工程計画方法では、前記第1製作工程は、前記モノパイル本体の両端部のうち少なくとも一方を製作しないことを特徴とする構成を採用してもよい。 <18> In the process planning method according to <17> above, the first manufacturing process may be configured such that at least one of the two ends of the monopile body is not manufactured.

ここで、モノパイル本体は、素となる管(素管)を長手方向に複数溶接することで構成される。この時、モノパイル本体の両端以外に位置する素管は両端が溶接されるのに対し、モノパイル本体の両端に位置する素管は一方の端のみが溶接される。したがって、モノパイル本体の両端部は溶接量が少なく、海洋構造物の製作において比較的律速となりにくい。そこで、第1製作工程は、モノパイル本体の両端部のうち少なくとも一方を製作しない。これにより、当該部材において生じる形状の変更に柔軟に対応しやすくすることができる。 The monopile body is constructed by welding multiple basic pipes (blank pipes) in the longitudinal direction. In this case, the blank pipes located at any other end of the monopile body are welded at both ends, whereas the blank pipes located at both ends of the monopile body are welded at only one end. Therefore, the amount of welding at both ends of the monopile body is small, and it is relatively unlikely to be a rate-limiting step in the manufacture of marine structures. Therefore, in the first manufacturing process, at least one of the ends of the monopile body is not manufactured. This makes it easier to flexibly respond to changes in shape that occur in the member.

<19>上記<2>から<18>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、付属設備を有し、前記第1製作工程は、前記付属設備を製作しないことを特徴とする構成を採用してもよい。 <19> In the process planning method according to any one of the above <2> to <18>, the marine structure may have auxiliary equipment, and the first manufacturing process may be configured to not manufacture the auxiliary equipment.

また、海洋構造物は、付属設備を有する。付属設備は、海洋構造物における主要な部材(例えば、トランジションピース)の設計結果の影響を受けやすいことから、形状の変更が発生しやすい。そこで、第1製作工程は、付属設備を製作しない。これにより、付属設備の製作を、付属設備の形状が最適化された後に開始することができる。したがって、製作途中の付属設備に形状の変更が生じること等を抑え、海洋構造物の製作コストを抑えやすくすることができる。 The marine structure also has auxiliary equipment. The auxiliary equipment is easily affected by the design results of the main components of the marine structure (e.g., transition pieces), and so changes in shape are likely to occur. Therefore, the first manufacturing process does not manufacture the auxiliary equipment. This allows the manufacturing of the auxiliary equipment to begin after the shape of the auxiliary equipment has been optimized. This prevents the auxiliary equipment from changing its shape during manufacturing, making it easier to reduce the manufacturing costs of the marine structure.

<20>上記<19>に係る工程計画方法では、前記付属設備は、係船設備、梯子、踊場及び作業床、通路のうち少なくとも何れかであることを特徴とする構成を採用してもよい。 <20> In the process planning method according to <19> above, the auxiliary equipment may be at least one of a mooring facility, a ladder, a landing, a work platform, and a passageway.

また、付属設備は、係船設備、梯子、踊場及び作業床、通路のうち少なくとも何れかである。これにより、製作途中の係船設備、梯子、踊場及び作業床、通路の何れかに形状の変更が生じること等を抑え、海洋構造物の製作コストを抑えやすくすることができる。 The auxiliary equipment is at least one of the mooring equipment, ladders, landings and work platforms, and walkways. This prevents changes to the shape of the mooring equipment, ladders, landings and work platforms, and walkways during construction, making it easier to reduce the manufacturing costs of marine structures.

<21>上記<2>から<20>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、前記海洋構造物を構成する部材の全部を製作することを特徴とする構成を採用してもよい。 <21> In the process planning method according to any one of the above <2> to <20>, the first manufacturing process may be configured to manufacture all of the components that constitute the marine structure.

また、第1製作工程は、海洋構造物を構成する部材の全部を製作する。これにより、より確実に海洋構造物の建設プロジェクトの工程を短縮することができる。また、例えば、第1製作工程において海洋構造物を構成する部材の一部のみを製作する場合と比較して、部材のそれぞれを製作する順番を調整しやすくすることができる。よって、第1製作工程を効率的に行いやすくすることができる。 The first manufacturing process also produces all of the components that make up the marine structure. This makes it possible to more reliably shorten the process of a marine structure construction project. Also, for example, compared to a case in which only some of the components that make up the marine structure are produced in the first manufacturing process, it is easier to adjust the order in which each component is manufactured. This makes it easier to carry out the first manufacturing process efficiently.

<22>上記<2>から<21>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、同一のウインドファーム又は海域に存在する複数の前記海洋構造物のうち少なくとも一つについて行われることを特徴とする構成を採用してもよい。 <22> In the process planning method according to any one of the above <2> to <21>, the first manufacturing process may be performed on at least one of the multiple marine structures present in the same wind farm or sea area.

ここで、同一のウインドファーム又は海域に存在する複数の海洋構造物が、一つずつ順番に設置されることがある。そこで、第1製作工程は、同一のウインドファーム又は海域に存在する複数の海洋構造物のうち少なくとも一つについて行われる。これにより、例えば、複数の海洋構造物のうち初期に設置される海洋構造物について、第1製作工程によって早期に製作を開始することができる。これにより、海洋構造物の建設プロジェクトの開始から海洋構造物の設置開始までの期間を短縮しやすくすることができる。 Here, multiple marine structures that exist in the same wind farm or sea area may be installed one by one in sequence. Thus, the first manufacturing process is performed for at least one of the multiple marine structures that exist in the same wind farm or sea area. This allows, for example, early manufacturing to begin for an marine structure that is to be installed first among the multiple marine structures through the first manufacturing process. This makes it easier to shorten the period from the start of a marine structure construction project to the start of installation of the marine structure.

<23>上記<2>から<22>のいずれか一態様に係る工程計画方法では、前記第1製作工程は、前記構造解析工程開始前に開始される前第1製作工程及び中第1製作工程と、前記構造解析工程開始後に開始される後第1製作工程と、を有することを特徴とする構成を採用してもよい。 <23> In the process planning method according to any one of the above <2> to <22>, the first manufacturing process may be configured to include a pre-first manufacturing process and a middle-first manufacturing process that are started before the structural analysis process begins, and a post-first manufacturing process that is started after the structural analysis process begins.

また、第1製作工程は、構造解析工程の開始前に開始される前第1製作工程及び中第1製作工程と、構造解析工程の開始後に開始される後第1製作工程と、を有する。これにより、例えば、海洋構造物において、構造解析工程の開始前に形状が確定済である部材について、前第1製作工程及び中第1製作工程によって製作を開始し、その他の部材については、後第1製作工程において製作を開始することができる。よって、不確定な要素を含む部材について、構造解析工程の前に製作を開始することを抑えることができる。よって、海洋構造物の形状が変更されることによって、部材の製作のやり直しが発生することを抑えやすくすることができる。よって、工程計画を最適なものにすることができる。また、費用が増大することを未然に抑えやすくすることができる。 The first manufacturing process includes a first pre-manufacturing process and a first intermediate manufacturing process that are started before the start of the structural analysis process, and a first post-manufacturing process that is started after the start of the structural analysis process. This allows, for example, in an offshore structure, the manufacturing of members whose shapes have been determined before the start of the structural analysis process to begin in the first pre-manufacturing process and the first intermediate manufacturing process, and the manufacturing of other members to begin in the first post-manufacturing process. This makes it possible to prevent the manufacturing of members that include uncertain elements from beginning before the structural analysis process. This makes it easier to prevent the need to redo the manufacturing of members due to changes in the shape of the offshore structure. This makes it easier to optimize the process plan. It also makes it easier to prevent increases in costs.

<24>上記<23>に係る工程計画方法では、前記海洋構造物は、モノパイル基礎であり、前記モノパイル基礎は、トランジションピースと、付属設備と、を有し、前記後第1製作工程は、前記トランジションピース及び前記付属設備のうち少なくとも何れかを製作することを特徴とする構成を採用してもよい。 <24> In the process planning method according to <23> above, the marine structure may be a monopile foundation, the monopile foundation may have a transition piece and ancillary equipment, and the first fabrication process may be configured to fabricate at least one of the transition piece and the ancillary equipment.

また、海洋構造物は、モノパイル基礎である。モノパイル基礎は、トランジションピースと、付属設備と、を有し、後第1製作工程は、トランジションピース及び付属設備のうち少なくとも何れかを製作する。このように、構造解析工程の開始後に開始される後第1製作工程において、トランジションピース及び付属設備のうち少なくとも何れかを製作することで、トランジションピース及び付属設備の何れかの製作のやり直しが発生することを抑えやすくすることができる。 The marine structure is a monopile foundation. The monopile foundation has a transition piece and ancillary equipment, and the first post-fabrication process fabricates at least one of the transition piece and the ancillary equipment. In this way, by fabricating at least one of the transition piece and the ancillary equipment in the first post-fabrication process that is started after the start of the structural analysis process, it is possible to more easily prevent the need to redo the fabrication of either the transition piece or the ancillary equipment.

<25>上記<2>から<24>のいずれか一態様に係る工程計画方法では、前記海洋構造物は、モノパイル基礎であり、前記モノパイル基礎は、モノパイル本体を有し、前記第1製作工程において、前記モノパイル本体の内面及び外面のうち少なくとも一方に、被覆防食されることを特徴とする構成を採用してもよい。 <25> In the process planning method according to any one of the above <2> to <24>, the marine structure may be a monopile foundation, the monopile foundation may have a monopile body, and in the first manufacturing process, at least one of the inner and outer surfaces of the monopile body may be coated and protected from corrosion.

また、海洋構造物は、モノパイル基礎である。モノパイル基礎は、モノパイル本体を有し、第1製作工程において、モノパイル本体の内面及び外面のうち少なくとも一方に、被覆防食される。これにより、モノパイル本体に被覆防食する作業の完了を待機する期間を短縮し、海洋構造物の建設プロジェクトの工程を短縮することができる。 The marine structure is a monopile foundation. The monopile foundation has a monopile body, and in the first manufacturing process, at least one of the inner and outer surfaces of the monopile body is coated and protected from corrosion. This shortens the waiting period for the completion of the work of coating and protecting the monopile body from corrosion, and shortens the process of the marine structure construction project.

<26>本開示に一態様に係る海洋構造物は、上記<1>から<25>のいずれか一態様に係る工程計画方法が適用される。 <26> The marine structure according to one embodiment of the present disclosure is applied to a process planning method according to any one of the above <1> to <25>.

また、本開示に係る海洋構造物には、本開示に係る工程計画方法が適用される。これにより、海洋構造物の建設プロジェクトの工程を短縮することができる。よって、洋上風車の操業開始を早期化することができる。 The process planning method according to the present disclosure is also applied to the marine structure according to the present disclosure. This makes it possible to shorten the process of the marine structure construction project. As a result, it is possible to speed up the start of operation of offshore wind turbines.

1 海洋構造物
10 モノパイル本体
11 単位筒状体
11A 板
20 トランジションピース
30 付属設備
31 係船設備
32 梯子
33 踊場
34 作業床
35 通路
A 設置場所
B ボルト
C ケーブル
DC ダビットクレーン
G グラウト
H 孔
IF インターフェイスフランジ
OF 海底
SA 設計検討フロー
SA1 事前調査工程
SA2 形状検討工程
SA3 構造解析工程
SA3a 解析実施ステップ
SA3b 第1確認ステップ
SA3c 第2確認ステップ
SA3d 第3確認ステップ
SA3e 見直しステップ
SB 製作フロー
SB1 第1製作工程
SB1a 前第1製作工程
SB1b 中第1製作工程
SB1c 後第1製作工程
SB2 第2製作工程
SB3 組立工程
T タワー
WM 洋上風車
1 Marine structure 10 Monopile body 11 Unit cylindrical body 11A Plate 20 Transition piece 30 Accessory equipment 31 Mooring equipment 32 Ladder 33 Landing 34 Work floor 35 Passage A Installation location B Bolt C Cable DC Davit crane G Grout H Hole IF Interface flange OF Seabed SA Design review flow SA1 Preliminary investigation process SA2 Shape review process SA3 Structural analysis process SA3a Analysis implementation step SA3b First confirmation step SA3c Second confirmation step SA3d Third confirmation step SA3e Review step SB Production flow SB1 First production process SB1a Front first production process SB1b Middle first production process SB1c Rear first production process SB2 Second production process SB3 Assembly process T Tower WM Offshore wind turbine

Claims (1)

モノパイル本体と、トランジションピースと、を有し、洋上風車のタワーを支持するモノパイル基礎の建設プロジェクトの工程を計画する工程計画方法であって、
前記モノパイル基礎のモデルの構造解析を、コンピュータが複数回行う構造解析工程と、
1回目の前記構造解析工程に含まれる地震応答解析の完了後であって2回目の前記構造解析工程に含まれる地震応答解析の完了前に開始される第1製作工程であって、前記モノパイル基礎を構成する部材のうち少なくとも一部を製作する第1製作工程と、
を備え、
前記第1製作工程は、前記トランジションピースを製作し、
前記第1製作工程は、前記トランジションピースのうちインターフェイスフランジを製作せず、前記トランジションピースのうち前記インターフェイスフランジ以外の部分を製作し、
前記第1製作工程は、前記モノパイル本体を製作し、
前記第1製作工程は、前記モノパイル本体のうち前記トランジションピースと水平方向視で重複する状態で接続される接続部を製作し、前記モノパイル本体のうち前記接続部以外の部分を製作しない工程計画方法。
A process planning method for planning a process for a construction project of a monopile foundation that supports a tower of an offshore wind turbine, the monopile foundation having a monopile body and a transition piece, comprising:
a structural analysis step in which a computer performs a structural analysis of the monopile foundation model multiple times;
a first fabrication process that is started after completion of an earthquake response analysis included in a first structural analysis process and before completion of an earthquake response analysis included in a second structural analysis process, the first fabrication process fabricating at least a part of the members that constitute the monopile foundation;
Equipped with
The first manufacturing step includes manufacturing the transition piece,
The first manufacturing step does not manufacture an interface flange of the transition piece, and manufactures a portion of the transition piece other than the interface flange,
The first manufacturing step includes manufacturing the monopile body,
The first manufacturing process is a process planning method in which a connection portion of the monopile body is manufactured so as to be connected to the transition piece in a state where it overlaps with the transition piece when viewed horizontally, and no portion of the monopile body other than the connection portion is manufactured.
JP2024134423A 2024-08-09 2024-08-09 Process Planning Method Active JP7614434B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2024134423A JP7614434B1 (en) 2024-08-09 2024-08-09 Process Planning Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2024134423A JP7614434B1 (en) 2024-08-09 2024-08-09 Process Planning Method

Publications (1)

Publication Number Publication Date
JP7614434B1 true JP7614434B1 (en) 2025-01-15

Family

ID=94213864

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2024134423A Active JP7614434B1 (en) 2024-08-09 2024-08-09 Process Planning Method

Country Status (1)

Country Link
JP (1) JP7614434B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015071634A1 (en) 2013-11-13 2015-05-21 University Of Dundee Offshore foundation
JP2023139586A (en) 2022-03-22 2023-10-04 五洋建設株式会社 Reinforcement structure and reinforcement method for cylindrical body for underwater installation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015071634A1 (en) 2013-11-13 2015-05-21 University Of Dundee Offshore foundation
JP2023139586A (en) 2022-03-22 2023-10-04 五洋建設株式会社 Reinforcement structure and reinforcement method for cylindrical body for underwater installation

Similar Documents

Publication Publication Date Title
US10745929B2 (en) Structural support system and methods of use
CN113239483B (en) An integrated cost reduction optimization design method for offshore wind turbine support structure
US9725868B2 (en) Offshore support structure
CN218756957U (en) Quick mosaic structure of prefabricated bent cap and prefabricated pier
KR100949567B1 (en) Anchor and anchor chain installation prior art
JP7614434B1 (en) Process Planning Method
Minguez et al. Water Intake Riser WIR–from Design to Installation, an Example of Complex Structure Requiring Multi-Disciplinary Approach
KR20210154142A (en) Structural joints for offshore structures and methods of assembling offshore frame structures and methods of using structural joints
Alonso Castro et al. Removal of Topside Units in a Single Lift: The Repsol Yme Field Case Study
CN116065548B (en) Offshore prefabricated bearing platform construction method
CN112360697A (en) Steel pipe concrete truss combination formula tower section of thick bamboo
JP6826936B2 (en) Floating offshore wind turbine construction method
NL1044403B1 (en) An effective structure and an adjoining installation method for the foundation of an offshore facility
EP4484746A1 (en) A method for structurally designing a flanged connection
CN111379265A (en) Peripherally-stabilized high-precision zero-interference weir-mold integrated structure and construction method thereof
JP5054449B2 (en) Rehabilitation method of pile foundation structure
Pettersson Telescopic Tower Facilitating Installation of≥ 12 MW Offshore Wind Turbines
Broughton et al. EKOFISK 2/4J JACKET FOLLOW-ON ENGINEERING.
RU2373452C2 (en) Method of rising category of stretched linear section of operating pipeline (versions)
Hafez et al. Practical investigation of a monopod fabrication method and the numerical investigation of its up-righting process
De Oliveira Vieira Investigation of the mechanical behaviour of conical cans with large slopes
Parnell Jr et al. Fabrication of the Lena guyed tower jacket
Hauptenbuchner Design and construction of the complex steel structure for the Amager Bakke waste‐to‐energy plant
Heggade Engineering of the National Namaste Signature Bridge Pylon
Ciezarek et al. ACG Jackets Design and Fabrication

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240809

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20240809

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20241105

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20241114

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20241226

R150 Certificate of patent or registration of utility model

Ref document number: 7614434

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150