[go: up one dir, main page]

CN117386444A - Simultaneous post-filling and recovery process of ore collapse in small sections of roof and bottom pillar residual ore resources - Google Patents

Simultaneous post-filling and recovery process of ore collapse in small sections of roof and bottom pillar residual ore resources Download PDF

Info

Publication number
CN117386444A
CN117386444A CN202311617034.0A CN202311617034A CN117386444A CN 117386444 A CN117386444 A CN 117386444A CN 202311617034 A CN202311617034 A CN 202311617034A CN 117386444 A CN117386444 A CN 117386444A
Authority
CN
China
Prior art keywords
ore
filling
small
roadway
vein
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202311617034.0A
Other languages
Chinese (zh)
Other versions
CN117386444B (en
Inventor
刘志军
刘泽洲
曾令义
王磊
温辉少
彭斌
李坤
王栋栋
方贤辉
熊鹏
廖九波
李运胜
鄂玉强
李昕蔚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Institute of Mining Research Co Ltd
Original Assignee
Changsha Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Institute of Mining Research Co Ltd filed Critical Changsha Institute of Mining Research Co Ltd
Priority to CN202311617034.0A priority Critical patent/CN117386444B/en
Publication of CN117386444A publication Critical patent/CN117386444A/en
Application granted granted Critical
Publication of CN117386444B publication Critical patent/CN117386444B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/22Methods of underground mining; Layouts therefor for ores, e.g. mining placers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/04Transport of mined material in gravity inclines; in staple or inclined shafts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Remote Sensing (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Road Signs Or Road Markings (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

本申请公开了一种顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺;涉及采矿技术领域,其包括如下步骤,S1:将矿体中段划分为顶柱和底柱:S2:对顶柱下方采空区进行全尾砂胶结充填;S3:在本中段距矿体下盘一定距离处布置脉外巷,在脉外巷旁布置连通下中段的溜井,从脉外巷间柱处布置采场联络道,再布置与脉内巷平行的顶柱凿岩巷;S4:将顶底柱在立面上划分为2个小分段,分别在2个小分段巷内钻凿上向扇形浅孔;S5:对顶底柱进行爆破、回采和出矿,然后对空区进行充填;本申请方案辅助工程量较少且可共用,且上下2个小分段顶底柱回收浅孔爆破同步进行,提高了爆破回采效率,利于区分矿石和充填体、为选矿作业节省成本。

This application discloses a small-section synchronous collapse and subsequent filling and recovery process of top and bottom pillar residual ore resources; it relates to the field of mining technology and includes the following steps, S1: Divide the middle section of the ore body into top pillars and bottom pillars: S2: The goaf area below the top pillar is fully cemented and filled with tailings; S3: Arrange an external vein tunnel at a certain distance from the footwall of the ore body in the middle section, and arrange a slide shaft connecting the lower and middle section next to the vein external tunnel. Arrange the stope connection road, and then arrange the top pillar drilling tunnel parallel to the tunnel in the vein; S4: Divide the top and bottom pillars into 2 small sections on the facade, and drill the top and bottom pillars in the two small section tunnels respectively. Sector-shaped shallow hole; S5: Blast, mine and mine the top and bottom pillars, and then fill the empty area; the auxiliary engineering volume of this application plan is small and can be shared, and the recovery of the upper and lower small sections of the top and bottom pillars is shallow Hole blasting is carried out simultaneously, which improves the efficiency of blasting and mining, helps distinguish ore and filling bodies, and saves costs for mineral processing operations.

Description

顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺The subsequent filling and recovery process of small-section synchronous ore collapse of roof and bottom pillar residual ore resources

技术领域Technical field

本申请涉及采矿技术领域,尤其是涉及一种顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺。This application relates to the field of mining technology, and in particular to a small-section synchronous collapse ore subsequent filling and recovery process for roof and bottom pillar residual ore resources.

背景技术Background technique

在国内外金属矿山中已熟练使用浅孔留矿法采矿工艺多年,该采矿方法适用于矿岩稳固性较好,矿体倾角较大的薄-中厚矿体开采,由此开采留下了大量的采场顶底柱和间柱,且较之于间柱而言,顶底柱因分布均匀、连续性较好而具有较好的回采可能。近年来,随着选矿技术的提高,因历史开采遗留下的顶底高价值矿柱变得具有较大的回采价值。而安全可靠经济可行的残矿回收工艺将变得举足轻重,不仅能在保证安全前提下提高采矿效率,而且能大幅提高矿山企业经济效益。The shallow hole ore retention method has been used proficiently in metal mines at home and abroad for many years. This mining method is suitable for the mining of thin to medium-thick ore bodies with good rock stability and large ore body inclination angles. This mining method leaves behind There are a large number of top and bottom pillars and inter-pillars in the stope. Compared with inter-pillars, the top and bottom pillars have better mining possibilities due to their even distribution and better continuity. In recent years, with the improvement of mineral processing technology, the top and bottom high-value ore pillars left over from historical mining have become of greater mining value. The safe, reliable, and economically feasible residual ore recovery process will become very important, which can not only improve mining efficiency while ensuring safety, but also significantly improve the economic benefits of mining enterprises.

矿山使用浅孔留矿法开采多年,近年来已建成全尾砂胶结充填系统,熟练使用全尾砂胶结充填开采工艺,矿石品位价值较高,浅孔留矿法开采留下的采空区急需治理,在治理采空区的同时回收残矿资源,可获得一举两得事半功倍之成效,因此亟需研发出一种安全高效经济的顶底柱资源回收的工艺。The mine has been mining using the shallow hole ore retention method for many years. In recent years, a full tailings cemented and filling system has been built. The full tailings cemented and filling mining technology is skillfully used. The ore grade is of high value. The goaf area left by the shallow hole ore retention method is urgently needed. Treatment, by treating goafs and recovering residual ore resources at the same time, can achieve the effect of killing two birds with half the effort. Therefore, there is an urgent need to develop a safe, efficient and economical top and bottom pillar resource recovery process.

发明内容Contents of the invention

为了安全高效经济的进行顶底柱回收,本申请提供了一种顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺。In order to recycle the top and bottom pillars safely, efficiently and economically, this application provides a small-section synchronous ore collapse and subsequent filling and recovery process of the top and bottom pillar residual ore resources.

本申请提供一种顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺,采用如下的技术方案:This application provides a small-section synchronous collapse ore subsequent filling and recovery process for roof and bottom pillar residual ore resources, adopting the following technical solution:

一种顶底柱残矿资源小分段同步崩矿嗣后充填回收工艺,包括如下步骤,A small-section synchronous collapse ore subsequent filling and recovery process for top and bottom pillar residual ore resources, including the following steps:

S1:将矿体中段划分为顶柱和底柱:S1: Divide the middle section of the ore body into top pillar and bottom pillar:

S2:对顶柱下方采空区进行全尾砂胶结充填;S2: Carry out full tailings cementing and filling of the goaf area below the top pillar;

S3:在本中段距矿体下盘指定距离处布置脉外巷,在脉外巷旁布置连通下中段的溜井,从脉外巷间柱处布置采场联络道,再布置与脉内巷平行的顶柱凿岩巷;S3: Arrange an external vein roadway at a specified distance from the footwall of the ore body in the middle section, arrange a slide shaft connected to the lower middle section next to the vein external tunnel, arrange a stope connection road from the outer vein tunnel pillar, and then arrange it parallel to the vein internal tunnel The pillar drilling alley;

S4:将顶底柱在立面上划分为2个小分段,分别在2个小分段巷内钻凿上向扇形浅孔;S4: Divide the top and bottom columns into two small sections on the facade, and drill upward fan-shaped shallow holes in the two small sections;

S5:对顶底柱进行爆破、回采和出矿,然后对空区进行充填。S5: Blast, mine and mine the top and bottom pillars, and then fill the empty area.

进一步的,在步骤S1之前,还有步骤S0:在间柱内布置人行天井、在天井内每隔2m~3m往两端布置采场联络道,在矿体内布置脉内运输巷,采用电耙出矿底部结构。Further, before step S1, there is step S0: arrange a pedestrian patio in the intercolumn, arrange stope connection roads at both ends every 2m to 3m in the patio, arrange intra-vein transportation lanes in the ore body, and use electric rake Mine bottom structure.

进一步的,步骤S1具体为,以本中段已有的脉内巷为界,依次划分为脉内巷上方的本中段3m厚底柱和脉内巷下方的下中段3m~6m厚顶柱。Further, step S1 specifically involves taking the existing intra-vein lane in this middle section as a boundary and dividing it into a 3m-thick bottom column of this middle section above the intra-vein lane and a 3m-6m thick top column in the lower middle section below the intra-vein lane.

进一步的,步骤S2具体为,残矿回采前对顶柱下方采空区进行全尾砂胶结充填,充填作业保证充填体与顶柱的接顶质量和接顶率,顶部0.5m范围内充填体强度不低于4MPa,底柱上方采空区稳固性较好时可暂时不进行充填,若采空区稳固性较差时,应嗣前采用废石充填25%以上空区,用外覆岩层确保顶底柱回收作业的安全。Further, step S2 specifically includes filling the goaf area below the top pillar with full tailings cement before mining the residual ore. The filling operation ensures the top connection quality and top connection rate between the filling body and the top pillar. The filling body is within 0.5m of the top. The strength is not less than 4MPa. If the stability of the goaf above the bottom column is good, filling may not be performed temporarily. If the stability of the goaf is poor, more than 25% of the empty area should be filled with waste rock and the overlying rock layer should be used. Ensure the safety of top and bottom column recovery operations.

进一步的,步骤S3具体为,在本中段距矿体下盘20m~30m处布置3.0m×3.0m脉外运输巷,在脉外巷旁布置连通下中段的φ1.5m溜井,从脉外巷间柱处以一定坡度往下朝矿体方向布置3.0m×3.0m采场联络道通达顶柱下方,再沿矿体走向与脉内巷平行布置2.4m×2.6m的顶柱凿岩巷。Further, step S3 specifically includes: arranging a 3.0m×3.0m external vein transport lane in the middle section 20m to 30m away from the footwall of the ore body, and arranging a φ1.5m slide shaft connecting the lower and middle sections next to the vein external tunnel, and starting from the vein external tunnel. A 3.0m × 3.0m stope connection channel is arranged at a certain slope downward toward the ore body at the intercolumn to lead to the bottom of the top pillar, and then a 2.4m × 2.6m top pillar rock drilling tunnel is arranged along the direction of the ore body parallel to the inner vein tunnel.

进一步的,步骤S4具体为,以已有的脉内巷及新构筑的凿岩巷为界,将顶底柱在立面上划分为2个小分段,顶底柱起始回采点以原浅孔留矿法间柱内人行天井作为切割天井,分别在2个小分段巷内用凿岩机以相同的孔网参数钻凿上向扇形浅孔。Further, step S4 specifically involves dividing the top and bottom pillars into two small sections on the facade with the existing vein tunnel and the newly constructed rock drilling tunnel as boundaries. The starting mining point of the top and bottom pillars is based on the original mining tunnel. In the shallow hole ore retaining method, the pedestrian patio within the pillars is used as the cutting patio, and the upward fan-shaped shallow holes are drilled with the same hole network parameters using a rock drill in two small sub-lanes.

进一步的,在步骤S4中,顶底柱回收所用的浅孔,设计所用孔网参数如下:炮孔长度3m~6m、炮孔直径40mm、炮孔间距1.0m~1.2m、炮孔排距0.8~1.0m。Further, in step S4, the shallow holes used for top and bottom column recovery are designed as follows: blast hole length 3m~6m, blast hole diameter 40mm, blast hole spacing 1.0m~1.2m, blast hole row spacing 0.8 ~1.0m.

进一步的,在步骤S4中,先施工上分段脉内巷的上向扇形浅孔,后施工下分段凿岩巷的上向扇形浅孔。若下分段凿岩巷对应顶柱大于5m时,也可采用中深孔凿岩机施工。Further, in step S4, the upward fan-shaped shallow hole of the upper segmented vein tunnel is constructed first, and then the upward fan-shaped shallow hole of the lower segmented rock drilling tunnel is constructed. If the corresponding top column of the lower section rock drilling tunnel is larger than 5m, medium and deep hole rock drills can also be used for construction.

进一步的,在步骤S4中,急倾斜薄-中厚浅孔留矿法顶底柱回收浅孔爆破时,采用人工装填φ32mm卷装药,自顶底柱切割天井处开始,以后退式开采顺序进行顶底柱残矿回收爆破。Further, in step S4, when the steeply inclined thin-medium-thick shallow hole ore retention method is used to recover the shallow hole blasting of the top and bottom pillars, the φ32mm roll charge is manually loaded, starting from the top and bottom pillar cutting patio, in a backward mining sequence Carry out top and bottom pillar residual ore recovery and blasting.

进一步的,在步骤S5中,顶底柱回采首茬炮孔爆破时以切割天井为自由面,在2个小分段同步进行装药连线侧向爆破形成垂直切割立槽,后续炮孔以垂直立槽为自由面,两分段同步爆破将矿石崩落至充填体上方;Further, in step S5, when blasting the first shot hole of the top and bottom pillars, the cutting patio is used as the free surface, and the charge connection is simultaneously blasted sideways in two small sections to form a vertical cutting vertical groove, and the subsequent shot holes are The vertical vertical groove is a free surface, and the two segments are blasted simultaneously to collapse the ore to the top of the filling body;

随后以步骤S3形成的脉外巷、采场联络道为出矿通道,采用遥控铲运机将充填体上的崩落矿石铲运至脉外巷旁的溜井进行出矿,出矿完成后,及时构筑充填挡墙,采用全尾砂胶结充填完成本中段空区充填任务。Then, the outer vein tunnel and stope connection road formed in step S3 are used as the ore exit channels, and a remote-controlled scraper is used to shovel the collapsed ore on the filling body to the slide shaft next to the vein outer tunnel for mining. After the ore extraction is completed, the mine is Construct a filling retaining wall and use full tailings cement filling to complete the filling task of the empty area in the middle section.

综上所述,本申请包括以下有益技术效果:To sum up, this application includes the following beneficial technical effects:

(1)辅助工程量较少且可共用,在顶柱下方新构筑凿岩巷、矿体下盘布置脉外巷和溜矿井,由脉外巷往矿体方向掘进下向倾斜采场联络道,且以上工程可多个矿块共同利用,又可为深部开拓工程。(1) The amount of auxiliary works is small and can be shared. A new rock drilling tunnel is constructed under the top pillar, an external vein tunnel and a mine shaft are arranged on the footwall of the ore body. A downward inclined stope connection road is dug from the external vein tunnel toward the ore body. , and the above projects can be used together by multiple ore blocks, and can also be used as deep development projects.

(2)上下2个小分段顶底柱回收浅孔爆破同步进行,极大减少了爆破次数,提高了爆破回采效率,有效控制崩落矿石块度,利于区分矿石和充填体、为选矿作业节省成本。(2) Shallow hole blasting for the upper and lower small segmented roof and bottom pillars is carried out simultaneously, which greatly reduces the number of blasts, improves the efficiency of blasting and mining, effectively controls the size of the caving ore, facilitates the differentiation of ore and filling bodies, and saves money for mineral processing operations. cost.

附图说明Description of the drawings

图1为本发明小分段同步崩矿嗣后充填采矿工艺矿房横剖面图;Figure 1 is a cross-sectional view of the mine room of the small-section synchronous mine collapse and subsequent filling mining process according to the present invention;

图2为图1中Ⅱ-Ⅱ的剖面图;Figure 2 is a cross-sectional view of II-II in Figure 1;

图3为图1中Ⅲ-Ⅲ的剖面图。Figure 3 is a cross-sectional view of III-III in Figure 1.

附图标记说明:Explanation of reference symbols:

1、顶柱;2、底柱;3、间柱;4、脉外巷;5、采场联络道;6、凿岩巷;7、溜井;8、人行通风天井;9、充填体;10、采下矿石;11、脉内运输巷;12、采空区;13、浅孔。1. Top pillar; 2. Bottom pillar; 3. Between pillars; 4. Lane outside the vein; 5. Stope connection road; 6. Drilling lane; 7. Slide shaft; 8. Pedestrian ventilation patio; 9. Filling body; 10 , mined ore; 11. In-vein transportation lane; 12. Goaf area; 13. Shallow hole.

具体实施方式Detailed ways

以下结合附图1-3对本申请作进一步详细说明。The present application will be further described in detail below in conjunction with Figures 1-3.

本申请实施例公开一种浅孔13留矿法残矿资源分段同步崩矿嗣后充填法采矿工艺,包括如下步骤,The embodiment of the present application discloses a shallow hole 13-hole ore retention method and residual ore resources segmented synchronous collapse and subsequent filling method mining process, which includes the following steps:

S0:在间柱3内布置人行天井、在天井内每隔2m~3m往两端布置采场联络道5,在矿体内布置脉内运输巷11,采用电耙出矿底部结构。S0: A pedestrian patio is arranged in the intercolumn 3, stope connection roads 5 are arranged at both ends every 2m to 3m in the patio, intra-vein transportation lanes 11 are arranged in the ore body, and an electric rake is used to extract the bottom structure of the ore.

S1.设计回采的顶底柱2残矿矿体平均水平厚度3m左右,开采条件定义为夹制性大的嗣后充填采矿工艺,在过程上划分为先空场后充填的时间顺序。该残矿回采工艺以本中段已有的2.4m×2.6m脉内巷为界,依次划分为脉内巷上方的本中段3m厚底柱2和脉内巷下方的下中段3m~6m厚顶柱1。S1. The average horizontal thickness of the top and bottom pillar 2 residual ore bodies designed to be mined is about 3m. The mining conditions are defined as a highly restrictive subsequent filling mining process. The process is divided into a time sequence of emptying first and then filling. The residual ore mining process is bounded by the existing 2.4m×2.6m intra-vein lane in this middle section, and is divided into a 3m-thick bottom column 2 in this middle section above the intra-vein lane and a 3m-6m thick top column in the lower middle section below the intra-vein lane. 1.

S2.残矿回采前对顶柱1下方采空区12进行全尾砂胶结充填,充填作业保证充填体9与顶柱1的接顶质量和接顶率,顶部0.5m范围内充填体9强度不低于4MPa,底柱2上方采空区12稳固性较好时可暂时不进行充填,若采空区12稳固性较差时,应嗣前采用废石充填25%以上空区,用外覆岩层确保顶底柱2回收作业的安全。S2. Before mining the remaining ore, the goaf area 12 below the top pillar 1 is filled with all tailings cement. The filling operation ensures the top connection quality and top connection rate between the filling body 9 and the top pillar 1, and the strength of the filling body 9 within the top 0.5m range. Not less than 4MPa. When the stability of the goaf 12 above the bottom pillar 2 is good, filling may not be carried out temporarily. If the stability of the goaf 12 is poor, more than 25% of the empty area should be filled with waste rock beforehand. The overlying rock layer ensures the safety of the top and bottom pillar 2 recovery operations.

S3.在本中段距矿体下盘20m~30m处布置3.0m×3.0m脉外运输巷,在脉外巷4旁布置连通下中段的φ1.5m溜井7,从脉外巷4间柱3处以一定坡度往下朝矿体方向布置3.0m×3.0m采场联络道5通达顶柱1下方,再沿矿体走向与脉内巷平行布置2.4m×2.6m的顶柱1凿岩巷6。S3. Arrange a 3.0m × 3.0m outer vein transport lane 20m to 30m away from the footwall of the ore body in this middle section. Arrange a φ1.5m slip shaft 7 connecting the lower and middle sections next to the vein outer lane 4. Columns 3 from the vein outer lane 4 A 3.0 m .

S4.以已有的脉内巷及新构筑的凿岩巷6为界将顶底柱2在立面上划分为2个小分段,顶底柱2起始回采点以原浅孔13留矿法间柱3内人行天井作为切割天井,分别在2个小分段巷内用YSP45凿岩机以相同的孔网参数钻凿上向扇形浅孔13。S4. Divide the roof and bottom pillars 2 into two small sections on the facade with the existing vein tunnel and the newly constructed rock drilling tunnel 6 as boundaries. The starting mining point of the roof and bottom pillars 2 is the original shallow hole 13. The pedestrian patio in the mining method pillar 3 is used as a cutting patio, and the YSP45 rock drill is used to drill upward fan-shaped shallow holes 13 in two small section tunnels with the same hole network parameters.

S5.顶底柱2回采首茬炮孔爆破时以切割天井为自由面,在2个小分段同步进行装药连线侧向爆破形成垂直切割立槽,后续炮孔以垂直立槽为自由面,两分段同步爆破将矿石崩落至充填体9上方。S5. When blasting the first batch of blast holes in the top and bottom pillars 2, the cutting patio is used as the free surface, and the charging line is simultaneously blasted sideways in two small sections to form a vertical cutting vertical trough. The subsequent blast holes use the vertical vertical trough as the free surface. On the surface, the two sections are simultaneously blasted to collapse the ore to the top of the filling body 9.

以步骤S3形成的脉外巷4、采场联络道5为出矿通道,采用遥控铲运机将步骤S2胶结充填体9上的崩落矿石铲运至脉外巷4旁的φ1.5m溜井7。出矿完成后,及时构筑充填挡墙,采用全尾砂胶结充填完成本中段空区充填任务。Using the outer vein lane 4 and the stope connection road 5 formed in step S3 as the ore exit channels, use a remote control scraper to shovel the caving ore on the cemented filling body 9 in step S2 to the φ1.5m slide shaft 7 next to the vein outer lane 4 . After the mining is completed, a filling retaining wall shall be constructed in time, and all tailings cemented filling shall be used to complete the filling task of the empty area in the middle section.

本申请实施例一种浅孔13留矿法残矿资源分段同步崩矿嗣后充填法采矿工艺的实施原理为:顶底柱2残矿资源为急倾斜中厚矿体,矿岩稳固性中等以上。原矿房回采所用浅孔13留矿法采场沿矿体走向布置,矿房长50m,宽与矿体厚度一致,留8m厚间柱3、3m厚顶柱1、3m~6m厚底柱2,在间柱3内布置1.5m×1.5m人行天井、在天井竖直方向上每隔2m~3m往两端布置采场联络道5,在矿体内布置脉内运输巷11,采用电耙出矿底部结构。The implementation principle of the shallow hole 13 ore-retaining method and residual ore resource segmented synchronous collapse and subsequent filling method mining process in the embodiment of the present application is: the top and bottom pillar 2 residual ore resources are sharply inclined medium-thick ore bodies, and the ore rock stability is medium. above. The shallow hole 13-retaining stope used in the mining of the original ore house is arranged along the direction of the ore body. The ore house is 50m long and has a width consistent with the thickness of the ore body. There are 8m thick inter-pillars 3, 3m-thick top pillars 1, 3m-6m thick bottom pillars 2. Arrange a 1.5m×1.5m pedestrian patio in the intercolumn 3, arrange stope connection roads 5 at both ends every 2m to 3m in the vertical direction of the patio, arrange an intra-vein transportation lane 11 in the ore body, and use an electric rake to extract the ore. Bottom structure.

在顶底柱2回收前视空区稳定情况,对底柱2上方的采空区12暂不处理,或采用废石充填25%以上空区体积,形成一定保护厚度的上覆岩层;对顶柱1下方的采空区12采用全尾砂胶结充填至与顶柱1接顶,待上层0.5m厚充填体9强度达到4MPa时,在矿体下盘20m~30m处布置脉外运输巷,在脉外巷4旁布置连通下中段的φ1.5m溜井7,从间柱3位置处的脉外巷4以一定坡度往下朝矿体方向布置3.0m×3.0m采场联络道5通达顶柱1下方,再沿矿体走向与脉内巷平行布置3.0m×3.0m的顶柱1凿岩巷6,至此,便在已有脉内巷与新掘顶柱1凿岩巷6将顶底柱2划分为2个小分段。Before recycling the top and bottom pillars 2, check the stability of the empty area, temporarily leave the goaf 12 above the bottom pillar 2 unprocessed, or use waste rock to fill more than 25% of the empty area volume to form an overlying rock layer with a certain protective thickness; The goaf 12 below the column 1 is filled with all tailings cement until it reaches the top of the top column 1. When the strength of the upper 0.5m thick filling body 9 reaches 4MPa, an extra-vein transportation tunnel is arranged at 20m to 30m in the footwall of the ore body. A φ1.5m slip shaft 7 connected to the lower middle section is arranged next to the outer lane 4 of the vein. From the outer lane 4 of the vein 3 at the position of the intervening pillar 3, a 3.0m×3.0m stope connection channel 5 is arranged downward toward the ore body at a certain slope to reach the top. Below the pillar 1, a 3.0m×3.0m roof pillar 1 drilling tunnel 6 is then arranged along the direction of the ore body parallel to the vein tunnel. At this point, the roof pillar 1 drilling tunnel 6 will be installed between the existing vein tunnel and the newly dug roof tunnel 1. Bottom column 2 is divided into 2 small segments.

利用顶底柱2一侧间柱3内人行天井作为切割天井,为顶底柱2残矿回收首茬炮孔爆破提供补偿空间,在2个小分段内采用YSP-45浅孔13凿岩机以相同的孔网参数施工上向扇形浅孔13。采用2个小分段同时装药连线的爆破方式,实现小分段同步崩矿的回采工艺,崩落后的矿石采用遥控铲运机经采场联络道5运输至脉外巷4卸入中段φ1.5m溜井7内。待顶底柱2回采出矿完成后,构筑充填挡墙对采空区12进行嗣后充填。The pedestrian patio in the column 3 on one side of the top and bottom pillars 2 is used as a cutting patio to provide compensation space for the first shot hole blasting of the top and bottom pillars 2 residual ore recovery. The YSP-45 shallow hole 13 rock drill is used in 2 small sections. Construct upward fan-shaped shallow holes 13 using the same hole network parameters. The blasting method of two small sections being charged simultaneously and connected in line is used to realize the mining process of synchronous collapse of small sections. The ore after collapse is transported by a remote control scraper through the stope connection road 5 to the outer lane 4 of the vein and unloaded into the middle section. φ1.5m slide shaft 7. After the mining of the top and bottom pillars 2 is completed, a filling retaining wall will be constructed to subsequently fill the goaf 12.

以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。The above are all preferred embodiments of the present application, and are not intended to limit the scope of protection of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application shall be covered by the scope of protection of the present application. Inside.

Claims (10)

1. A technology for synchronously ore-breaking and subsequent filling and recycling of residual ore resources of a top column and a bottom column in small segments is characterized in that: comprises the following steps of the method,
s1: dividing the middle section of the ore body into a top column and a bottom column:
s2: performing full tailing cemented filling on the goaf below the top column;
s3: an extra-vein roadway is arranged at a specified distance from the lower disc of the ore body at the middle section, a drop shaft communicated with the lower middle section is arranged beside the extra-vein roadway, a stope connecting channel is arranged at a pillar between the extra-vein roadway, and then a rock drilling roadway parallel to the intra-vein roadway is arranged;
s4: dividing the top and bottom columns into 2 small sections on the vertical surface, and drilling upward sector shallow holes in 2 small section lanes respectively;
s5: and (5) blasting, stoping and ore extracting the top and bottom columns, and then filling the empty area.
2. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that:
before step S1, there is also step S0: a manway is arranged in the stud, stope connecting channels are arranged in the manway from every 2m to 3m to two ends, and a vein conveying roadway is arranged in the ore body to form a rake ore-drawing bottom structure.
3. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that: the step S1 is specifically divided into a bottom column with the thickness of 3 m-6 m at the middle section above the intra-pulse lane and a top column with the thickness of 3 m-6 m at the lower middle section below the intra-pulse lane by taking the existing intra-pulse lane at the middle section as a boundary.
4. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that: step S2 is specifically that full tailing cemented filling is carried out on a goaf below a jack post before stoping of a residual ore, filling operation guarantees the top connection quality and the top connection rate of a filling body and the jack post, the strength of the filling body within the range of 0.5m at the top is not lower than 4MPa, filling can be temporarily not carried out when the goaf above a bottom post is good in stability, if the goaf is poor in stability, more than 25% of goaf should be filled by adopting waste rock before subsequent steps, and safety of top and bottom post recovery operation is guaranteed by using an overburden stratum.
5. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that: the step S3 is that a 3.0mX3.0mO conveying roadway is arranged at the position 20 m-30 m away from the lower plate of the ore body, phi 1.5mO wells communicated with the lower middle section are arranged beside the outer roadway, a stope connecting roadway of 3.0mX3.0mO is downwards arranged from the outer roadway column to the direction of the ore body with a certain gradient to reach the lower part of the top column, and then a rock drilling roadway of 2.4mX2.6m is arranged along the direction of the ore body and parallel to the inner roadway.
6. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that: the step S4 is to divide the top and bottom columns into 2 small segments on the vertical plane by taking the existing intra-pulse roadway and newly constructed rock drilling roadway as boundaries, taking a pedestrian raise in the original shallow hole ore-retaining method as a cutting raise at the initial stoping point of the top and bottom columns, and drilling upward sector shallow holes in the 2 small segment roadways by using a rock drill with the same hole network parameters.
7. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 6, which is characterized in that: in step S4, shallow holes for top and bottom column recovery are designed, and the parameters of the hole network used are as follows: the length of the blast hole is 3 m-6 m, the diameter of the blast hole is 40mm, the distance between the blast holes is 1.0 m-1.2 m, and the row distance of the blast holes is 0.8-1.0 m.
8. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 6, which is characterized in that: in the step S4, an upward sector shallow hole of the upper segment intra-pulse roadway is constructed, and then an upward sector shallow hole of the lower segment rock drilling roadway is constructed. If the corresponding top column of the lower segmented rock drilling lane is larger than 5m, the construction of the medium-length hole rock drill can be adopted.
9. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 6, which is characterized in that: in the step S4, when shallow hole blasting is recovered by a steep thin-medium thick shallow hole ore-retaining method, manual filling of coiled charges with phi 32mm is adopted, and top and bottom column residual ore recovery blasting is carried out in a backward mining sequence from a top and bottom column cutting courtyard.
10. The roof and bottom pillar residual ore resource small-section synchronous ore caving subsequent filling and recycling process according to claim 1, which is characterized in that: in the step S5, when the top and bottom column stoping first stubble blastholes are blasted, a cutting courtyard is used as a free surface, charging connecting line lateral blasting is synchronously carried out on 2 small sections to form vertical cutting vertical grooves, the subsequent blastholes use the vertical grooves as the free surface, and the two sections of synchronous blasting collapse ores above the filling body;
and then taking the outer drift and stope connecting channel formed in the step S3 as an ore discharging channel, adopting a remote control scraper to shovel the caving ore on the filling body to an ore pass beside the outer drift for ore discharging, constructing a filling retaining wall in time after ore discharging is completed, and adopting full tailing cemented filling to complete the filling task of the middle section empty area.
CN202311617034.0A 2023-11-29 2023-11-29 Small-section synchronous ore-caving subsequent filling recovery process for residual ore resources of top and bottom columns Active CN117386444B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311617034.0A CN117386444B (en) 2023-11-29 2023-11-29 Small-section synchronous ore-caving subsequent filling recovery process for residual ore resources of top and bottom columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311617034.0A CN117386444B (en) 2023-11-29 2023-11-29 Small-section synchronous ore-caving subsequent filling recovery process for residual ore resources of top and bottom columns

Publications (2)

Publication Number Publication Date
CN117386444A true CN117386444A (en) 2024-01-12
CN117386444B CN117386444B (en) 2024-12-17

Family

ID=89470456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311617034.0A Active CN117386444B (en) 2023-11-29 2023-11-29 Small-section synchronous ore-caving subsequent filling recovery process for residual ore resources of top and bottom columns

Country Status (1)

Country Link
CN (1) CN117386444B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727820A (en) * 2015-04-07 2015-06-24 长沙有色冶金设计研究院有限公司 Two-step sublevel open-stop and delayed filling mining method
CN106677780A (en) * 2017-02-21 2017-05-17 中冶北方(大连)工程技术有限公司 Upward and downward staged rock drilling, sublevel bottom cutting and ore removal subsequent backfilling mining method
CN111779485A (en) * 2020-07-01 2020-10-16 长沙矿山研究院有限责任公司 Combined hole segmented open stope subsequent filling mining method
WO2022247176A1 (en) * 2021-05-28 2022-12-01 鞍钢集团矿业有限公司 Filling caving mining method
CN116556949A (en) * 2023-06-13 2023-08-08 紫金矿业集团股份有限公司 Small-section empty-field and caving subsequent filling combination method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727820A (en) * 2015-04-07 2015-06-24 长沙有色冶金设计研究院有限公司 Two-step sublevel open-stop and delayed filling mining method
CN106677780A (en) * 2017-02-21 2017-05-17 中冶北方(大连)工程技术有限公司 Upward and downward staged rock drilling, sublevel bottom cutting and ore removal subsequent backfilling mining method
CN111779485A (en) * 2020-07-01 2020-10-16 长沙矿山研究院有限责任公司 Combined hole segmented open stope subsequent filling mining method
WO2022247176A1 (en) * 2021-05-28 2022-12-01 鞍钢集团矿业有限公司 Filling caving mining method
CN116556949A (en) * 2023-06-13 2023-08-08 紫金矿业集团股份有限公司 Small-section empty-field and caving subsequent filling combination method

Also Published As

Publication number Publication date
CN117386444B (en) 2024-12-17

Similar Documents

Publication Publication Date Title
CN104806244B (en) Filling mining method for slant middle-thick ore body
CN105041314B (en) A kind of combined mining method of deep afterwards rooming-slicing ore pillar
CN102635356B (en) Medium-length hole mining method in multiple blasting free faces of high dipping thin veins
CN108104869A (en) A kind of continuous stoping method of mining by the way of filling of gently inclined medium thick orebody
CN102518438B (en) Roof regeneration medium-length hole ore blast backfill mining method
CN107869349A (en) A kind of mechanized mining method of gently inclined medium thick orebody
CN104100270B (en) A kind of low-angle dip mineral ore Truckless mining method
CN104632220B (en) Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN108843382A (en) Downward subsequent filling method suitable for unstable medium-thickness ore body of gently inclined surrounding rock
CN110905512B (en) Open stope mining method for gently inclined medium-thickness ore body
CN103590831A (en) Novel mining method of gently-inclined thin and medium thickness ore bodies
CN102678121A (en) Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN112682041B (en) Filling mining method for broken and slowly-inclined thick and large ore body of upper disc
CN108625855B (en) Mining method under filling body
CN104895566A (en) Mining method with residual ore recovery function
CN105927226A (en) Medium-length hole ore-breaking continuous sectional horizontal filling mining method
CN105804748B (en) A kind of method of block mining Wall ore under open air transport system
CN115263311B (en) Combined mining method of suspended top pillar induced caving and vertical deep hole ore dropping with bottom pillar sublevel caving
CN115110955B (en) An improved technology for mining steeply inclined lens-shaped ore bodies using a staged chamber method
CN106837335A (en) Truck cooperates with ore removal sill pillars sublevel caving method
CN105422102B (en) A kind of vertical medium-length hole ore blast subsection access back-filling method
CN105822307A (en) Downward subsection open stope mining method
CN106640080B (en) Under a kind of deep high stress environment mining methods are arranged from steady gallery shape stope
CN119195771A (en) Mechanized pre-cut top medium-deep hole blasting top and bottom pillar efficient mining technology method
CN115288684B (en) A downward sub-divided filling mining method suitable for thick and broken ore bodies

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant