CN108104869A - A kind of continuous stoping method of mining by the way of filling of gently inclined medium thick orebody - Google Patents
A kind of continuous stoping method of mining by the way of filling of gently inclined medium thick orebody Download PDFInfo
- Publication number
- CN108104869A CN108104869A CN201711293513.6A CN201711293513A CN108104869A CN 108104869 A CN108104869 A CN 108104869A CN 201711293513 A CN201711293513 A CN 201711293513A CN 108104869 A CN108104869 A CN 108104869A
- Authority
- CN
- China
- Prior art keywords
- stope
- mining
- ramp
- back production
- ore
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/06—Filling-up mechanically
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明提供一种缓倾斜中厚矿体的连续回采充填采矿法,属于采矿技术领域。该方法将缓倾斜中厚矿体沿垂直方向划分分段,将矿体划分为回采单元,回采单元内的矿体沿走向划分为条带,相邻条带沿矿体走向上留有间柱,在间柱中掘进斜坡道,沿斜坡道分别掘进采场联络巷。将同一回采单元内条带分为6个一步骤采场和6个二步骤采场,在相同回采单元内的采场间隔回采,先采一步骤采场,并对其进行充填,当充填体养护达到规定的时间后,再回采二步骤采场。相邻几个回采单元矿体全部开采完毕且采场进行充填后,再对回采单元之间的间柱、顶部保安矿柱和底部保安矿柱进行回采。本发明机械化程度高、生产能力大、矿石回采率大、贫损率低和安全性好。
The invention provides a continuous mining and filling mining method for a gently inclined medium-thick ore body, which belongs to the technical field of mining. In this method, the gently inclined medium-thick ore body is divided into segments along the vertical direction, and the ore body is divided into mining units. The ore body in the mining unit is divided into strips along the strike, and the adjacent strips are left with intercolumns along the strike of the ore body. , excavate a ramp in the intercolumn, and excavate the stope roadway respectively along the ramp. The strip in the same mining unit is divided into 6 one-step stopes and 6 two-step stopes, and the stopes in the same recovery unit are mined at intervals, and the first-step stope is mined first, and it is filled. After the maintenance reaches the specified time, the second-step stope is recovered. After all the ore bodies of several adjacent mining units have been mined and the stope is filled, the inter-pillars, top security pillars and bottom security pillars between the recovery units are mined. The invention has high mechanization degree, large production capacity, high ore recovery rate, low loss rate and good safety.
Description
技术领域technical field
本发明涉及采矿技术领域,特别是指一种缓倾斜中厚矿体的连续回采充填采矿法。The invention relates to the technical field of mining, in particular to a continuous back mining and filling mining method of a gently inclined medium-thick ore body.
背景技术Background technique
随着矿产资源的逐渐消耗,矿山逐渐向深部开采方向发展,深部开采面临着高井深、高温和高压等条件,其开采成本会大大增加。为了提高矿山的开采水平,越来越多的矿山开始朝着智能化采矿方向发展,要求矿体进行规模化高效开采,以减小开采成本;而缓倾斜中厚矿体为难采矿体,因此,需寻求一种缓倾斜中厚矿体的连续回采充填采矿法,以实现矿山的安全、经济和高效开采。With the gradual consumption of mineral resources, mines are gradually developing towards deep mining. Deep mining is faced with conditions such as high well depth, high temperature and high pressure, and its mining costs will greatly increase. In order to improve the mining level of mines, more and more mines have begun to develop towards intelligent mining, requiring large-scale and efficient mining of ore bodies to reduce mining costs; and gently inclined medium-thick ore bodies are difficult to mine. Therefore, It is necessary to seek a continuous stop and fill mining method for gently inclined medium-thick ore bodies in order to realize safe, economical and efficient mining of mines.
大量缓倾斜中厚矿体的开采方法主要采用分层充填法、分段空场嗣后充填法和房柱法等。采用分层充填法对缓倾斜中厚矿体进行开采时,无法同时进行凿岩、爆破和出矿,作业战线长、生产能力低,且设备利用率低。分段空场嗣后充填法具有生产能力大的优势,但矿体的开采边界难以控制,贫损率高,且需掘进大量的出矿进路,其采切工程量较大。房柱法为较为传统的采矿方法,当采用房柱法对缓倾斜中厚矿体进行开采时,生产能力低,需留设有大量的无法回收的矿柱,矿石损失率较高,顶板易发生垮塌,对矿山的安全生产不利。The mining methods of a large number of gently inclined medium-thick ore bodies mainly adopt the layered filling method, the segmented empty field and subsequent filling method, and the room-and-pillar method. When the layered filling method is used to mine gently inclined medium-thick ore bodies, rock drilling, blasting and ore extraction cannot be performed at the same time. The operation front is long, the production capacity is low, and the utilization rate of equipment is low. The segmented open-field and subsequent filling method has the advantage of large production capacity, but the mining boundary of the ore body is difficult to control, the loss rate is high, and a large number of ore exit routes need to be excavated, and the mining and cutting engineering volume is relatively large. The room-and-pillar method is a relatively traditional mining method. When the room-and-pillar method is used to mine gently inclined medium-thick ore bodies, the production capacity is low, and a large number of unrecoverable ore pillars need to be left, the ore loss rate is high, and the roof is easy to Collapse occurs, which is detrimental to the safe production of mines.
为了提高缓倾斜中厚矿体的开采效率,改善井下生产安全工作环境,发明了一种缓倾斜中厚矿体的连续回采充填采矿法,其生产能力大、机械化程度高、矿石回采率高、贫损率低和安全性好,可实现缓倾斜中厚矿体的连续回采与充填。In order to improve the mining efficiency of gently inclined medium-thick ore bodies and improve the safe working environment for underground production, a continuous backfilling mining method for gently inclined medium-thick ore bodies has been invented, which has large production capacity, high degree of mechanization, and high ore recovery rate. With low loss rate and good safety, it can realize continuous mining and filling of gently inclined medium-thick ore bodies.
发明内容Contents of the invention
本发明要解决的技术问题是提供一种缓倾斜中厚矿体的连续回采充填采矿法,该方法针对倾角为20~30°的缓倾斜中厚矿体,具有生产能力大、机械化程度高、贫损率低、生产效率高和安全性好的特点。The technical problem to be solved by the present invention is to provide a continuous mining and filling mining method for gently inclined medium-thick ore bodies. The method has the advantages of large production capacity, high degree of mechanization, and It has the characteristics of low loss rate, high production efficiency and good safety.
该方法具体包括如下步骤:The method specifically includes the following steps:
(一)采准与切割:(1) Acquisition and cutting:
将缓倾斜中厚矿体划分为回采单元,将回采单元内的矿体沿走向划分为条带,沿矿体走向上相邻的两条带之间留设有间柱,其中同一回采单元内条带划分为一步骤采场和二步骤采场,每12个采场作为一个回采单元,在间柱中掘进斜坡道弯道和斜坡道直道,沿斜坡道弯道和斜坡道直道分别掘进采场联络巷,采场联络巷分别与一步骤采场和二步骤采场进行相连,且采场联络巷分别连接间柱左侧条带的上分层采场和间柱右侧条带的下分层采场;在斜坡道弯道部分掘进斜坡道与溜井联络巷,在螺旋斜坡道弯道中间掘进溜井,溜井下部连通穿脉与溜井联络巷,穿脉与溜井联络巷再连通穿脉巷道,穿脉巷道与中段运输巷相连通;在回采单元的顶部和底部分别留设顶部保安矿柱和底部保安矿柱;The gently inclined medium-thick ore body is divided into mining units, and the ore body in the mining unit is divided into strips along the strike, and inter-pillars are left between two adjacent belts along the strike of the ore body. The strip is divided into one-step stope and two-step stope, and every 12 stopes are used as a recovery unit, and the slope bend and the slope straight are excavated in the intercolumn, and the mining is excavated along the slope bend and the slope straight respectively. The stope connecting roadway is connected with the first-step stope and the second-step stope respectively, and the stope connecting roadway connects the upper stratified stope of the left strip of the intercolumn and the lower stratified stope of the right strip of the intercolumn respectively. Stratified stope; excavate the ramp and the chute connecting roadway in the curved part of the ramp, and excavate the chute in the middle of the spiral ramp bend. , the vein-piercing roadway is connected with the middle transportation roadway; the top security ore pillar and the bottom security ore pillar are respectively reserved at the top and bottom of the mining unit;
(二)回采与充填:(2) Mining and filling:
同一回采单元内的一步骤采场和二步骤采场分别由下而上进行间隔回采,待回采单元内的一步骤采场均回采完毕进行充填,当充填体终凝后,达到自立时间,再依次对回采单元内的二步骤采场进行回采,当同一回采单元内的一步骤采场和二步骤采场均回采完毕,充填体均达到终凝后,再回收相邻回采单元中间的间柱;The one-step stope and the second-step stope in the same mining unit are respectively mined at intervals from bottom to top. After the first-step stope in the recovery unit has been mined, the filling will be completed. When the filling body finally sets and reaches the self-supporting time, then The two-step stopes in the recovery unit are recovered sequentially. When the first-step stope and the second-step stope in the same recovery unit are all recovered, and the filling body reaches the final setting, the inter-column in the middle of the adjacent recovery unit is recovered. ;
每个采场的回采分为两个分层进行,上分层为切顶层,斜坡道弯道和斜坡道直道分别连接上分层采场和下分层采场,自上分层切顶层开始进行切顶,采用自动化铲运机进行出矿,矿石从采场联络巷运输到斜坡道弯道或斜坡道直道,再经斜坡道弯道或斜坡道直道到斜坡道与溜井联络巷运输到采区溜井,然后对采场顶板进行锚杆和锚索支护;上分层回采完毕后,在条带的顶端用深孔拉切割槽,切割槽形成后,在上分层采场凿向下的中深孔,然后对中深孔进行装药和爆破,通过采场联络巷、斜坡道弯道和斜坡道直道、斜坡道与溜井联络巷将矿石运输到采区溜井,矿石经过溜井下放到穿脉巷道上的电机车,再通过中段运输巷运输到矿区主溜井;The mining of each stope is divided into two layers, the upper layer is the cut top layer, and the slope bend and the slope straightway connect the upper layer stope and the lower layer stope respectively, starting from the upper layer to cut the top layer The roof is cut, and the ore is extracted by an automatic scraper. The ore is transported from the stope contact roadway to the slope bend or the slope straightway, and then transported to the slope road and the chute connection roadway to the mining area through the slope bend or the slope straightway. Then the roof of the stope is supported by bolts and anchor cables; after the mining of the upper layer is completed, the cutting groove is drawn with a deep hole at the top of the strip. After the cutting groove is formed, the upper layer stope is cut downward The middle and deep holes are then charged and blasted, and the ore is transported to the mining area through the stope connecting roadway, the slope bend and the slope straight road, the slope road and the slip shaft connection roadway, and the ore is lowered into the mining area through the slip shaft The electric locomotive on the piercing roadway is transported to the main shaft of the mining area through the middle transportation roadway;
当相邻几个回采单元的采场全部回采完毕,对其进行充填,充填体终凝后再进行间柱回采,当某一分段采场全部回采完毕,最后对顶部保安矿柱和底部保安矿柱进行回收。When the stopes of several adjacent mining units are all mined, they will be filled, and the filling body will be finally set and then the inter-column mining will be carried out. The ore pillars are recycled.
其中,间柱采用房柱法进行回收,首先通过留设点柱支护空区,最后回采结束时对空区进行统一封闭,再用灰砂比为1:20~1:24的膏体充填体进行充填;在对顶部保安矿柱和底部保安矿柱进行回收时,首先在宽度方向上刷大分段巷道,然后以分段巷道作为凿岩巷,施工上向扇形中深孔,顶板稳定性不好时,间隔施工锚索,后退式进行爆破,分段砌筑充填挡墙进行充填。Among them, the inter-pillars are recovered by the room-and-pillar method. First, point columns are set to support the void area. Finally, the void area is uniformly closed at the end of mining, and then filled with a paste with a lime-sand ratio of 1:20 to 1:24. When reclaiming the top security pillar and the bottom security pillar, first brush a large segmented roadway in the width direction, and then use the segmented roadway as a rock drilling roadway to construct a fan-shaped medium-deep hole with a stable roof When the performance is not good, the anchor cables are constructed at intervals, the blasting is carried out in a backward manner, and the retaining wall is filled by masonry in sections.
一步骤采场和二步骤采场的宽度为8~12m,长度为100~160m,间柱宽度为30~50m。The width of the first-step stope and the second-step stope is 8-12m, the length is 100-160m, and the width of the inter-column is 30-50m.
斜坡道弯道和斜坡道直道均为螺旋形布置,斜坡道弯道和斜坡道直道的坡度为10~20%,斜坡道弯道的转弯半径为15m。The ramp curve and the ramp straight are arranged in a spiral shape, the slope of the ramp curve and the ramp straight is 10-20%, and the turning radius of the ramp is 15m.
不同回采单元同时回采,同一回采单元采场的回采与充填同时连续作业。Different mining units are mined at the same time, and the mining and filling of the stope of the same mining unit are continuously operated at the same time.
采场联络巷、斜坡道与溜井联络巷和斜坡道弯道、斜坡道直道的宽和高均为4.5m的三心拱巷道。A three-core arch roadway with a width and height of 4.5m for the connecting roadway of the stope, the connecting roadway between the ramp and the chute, the bend of the ramp, and the straight road of the ramp.
每个采区溜井服务1个回采单元。Each production area chute serves 1 recovery unit.
本发明的上述技术方案的有益效果如下:The beneficial effects of above-mentioned technical scheme of the present invention are as follows:
本发明将缓倾斜中厚矿体划分为回采单元,且回采单元沿矿体倾向布置,每个回采单元再划分为条带,沿矿体走向上相邻的条带间留设有间柱,在回采单元内将条带分为一步骤采场和二步骤采场;在同一个回采单元内的条带需进行间隔回采,可同时对多个一步骤采场进行连续回采;可对不同的回采单元的条带同时进行回采,且回采与充填可同时进行,互不干扰,可进行连续出矿或充填,机械化程度高,生产能力大。In the present invention, the gently inclined medium-thick ore body is divided into mining units, and the mining units are arranged along the ore body tendency, and each mining unit is further divided into strips, and inter-columns are left between adjacent strips along the ore body trend. In the recovery unit, the strip is divided into one-step stope and two-step stope; the strips in the same recovery unit need to be mined at intervals, and multiple one-step stopes can be continuously mined at the same time; different The strips of the mining unit are mined at the same time, and the mining and filling can be carried out at the same time without interfering with each other. Continuous mining or filling can be carried out, with a high degree of mechanization and large production capacity.
本发明将采场分为上下两个分层,上分层采用大型凿岩设备进行掘进,并采用锚杆和锚索等形式对顶板进行支护,下分层采用中深孔爆破,大型铲运机出矿,可实现回采单元内矿体的机械化连续回采,其生产能力大,生产作业安全性好。The invention divides the stope into upper and lower layers. The upper layer adopts large-scale rock drilling equipment for excavation, and adopts bolts and anchor cables to support the roof. The lower layer adopts medium and deep hole blasting. The ore is transported out of the machine, which can realize the mechanized continuous mining of the ore body in the mining unit. It has a large production capacity and good production safety.
本发明将回采单元内的采场分为一步骤采场和二步骤采场,采场回采后,采用膏体充填技术对采空区进行充填,一步骤采场充填体的水泥含量相对较高,二步骤采场充填体的水泥含量相对较低,充填接顶效果好,充填成本低。The invention divides the stope in the mining unit into a one-step stope and a two-step stope. After the stope is recovered, the goaf is filled with paste filling technology, and the cement content of the first-step stope filling body is relatively high , The cement content of the stope filling body in the second step is relatively low, the filling effect is good, and the filling cost is low.
本发明分段巷道、采区斜坡道、采场联络巷等大部分都布置在矿体中,铲运机在采场中出矿,不需要掘进一系列的出矿进路,采切工程量少。Most of the segmented roadways, mining area slopes, and stope connecting roadways of the present invention are arranged in the ore body, and the scraper excavates the ore in the stope, and there is no need to dig a series of ore-exiting routes. few.
本发明对上分层顶板进行支护,采场顶板较为稳定,采场开采边界控制好,回采单元矿石回采完毕后,再对间柱、顶部保安矿柱和底部保安矿柱进行回收,其贫损率低和矿石回采率高。The invention supports the roof of the upper layer, the roof of the stope is relatively stable, and the mining boundary of the stope is well controlled. After the ore recovery of the mining unit is completed, the inter-column, the top security pillar and the bottom security pillar are recovered. Low loss rate and high ore recovery rate.
因此,本发明具有机械化程度高、生产能力大、采切工程量少、矿石回采率高、贫损率低和安全性好的特点,适用于矿体倾角为20~30°、厚度为10~16m缓倾斜中厚矿体的开采。Therefore, the present invention has the characteristics of high degree of mechanization, large production capacity, less mining and cutting engineering, high ore recovery rate, low loss rate and good safety. Mining of 16m gently inclined medium-thick ore body.
附图说明Description of drawings
图1为本发明的缓倾斜中厚矿体的连续回采充填采矿法应用于某一回采单元示意图;Fig. 1 is a schematic diagram of the application of the continuous mining and filling mining method of the gently inclined medium-thick ore body of the present invention to a certain mining unit;
图2为图1中A-A向的剖面示意图;Fig. 2 is a schematic sectional view of A-A direction in Fig. 1;
图3为图1中B-B向的剖面示意图。Fig. 3 is a schematic cross-sectional view along the direction B-B in Fig. 1 .
其中:1—分段巷道;2—采场联络巷;3—斜坡道弯道;4—斜坡道与溜井联络巷;5—溜井;6—间柱;7—斜坡道直道;8—顶部保安矿柱;9—底部保安矿柱;10—二步骤采场;11—一步骤采场;12—上分层采场;13—下分层采场;14—锚杆和锚索支护;15—中深孔;16—穿脉巷道;17—穿脉与溜井联络巷;18—中段运输巷;19—崩落矿体。Among them: 1—segmented roadway; 2—stope connecting roadway; 3—slope bend; 4—connecting roadway between slope and shaft; 5—slope; 6—column; 7—straight slope of slope; Ore pillar; 9—bottom security pillar; 10—two-step stope; 11—one-step stope; 12—upper layer stope; 13—lower layer stope; 14—bolt and anchor cable support; 15—medium-deep hole; 16—piercing roadway; 17—connecting roadway between piercing and chute; 18—transportation roadway in the middle section; 19—caving ore body.
具体实施方式Detailed ways
为使本发明要解决的技术问题、技术方案和优点更加清楚,下面将结合附图及具体实施例进行详细描述。In order to make the technical problems, technical solutions and advantages to be solved by the present invention clearer, the following will describe in detail with reference to the drawings and specific embodiments.
本发明提供一种缓倾斜中厚矿体的连续回采充填采矿法。The invention provides a continuous back mining and filling mining method of a gently inclined medium-thick ore body.
如图1所示,该方法按如下步骤进行:As shown in Figure 1, the method is carried out as follows:
(一)采准与切割:(1) Acquisition and cutting:
将缓倾斜中厚矿体划分为回采单元,将回采单元内的矿体沿走向划分为条带,沿矿体走向上相邻的两条带之间留设有间柱6,其中同一回采单元内条带划分为一步骤采场11和二步骤采场10,每12个采场作为一个回采单元,在间柱6中掘进斜坡道弯道3和斜坡道直道7,沿斜坡道弯道3和斜坡道直道7分别掘进采场联络巷2,采场联络巷2分别与一步骤采场11和二步骤采场10进行相连,且采场联络巷2分别连接间柱6左侧条带的上分层采场12和间柱6右侧条带的下分层采场13;在斜坡道弯道3部分掘进斜坡道与溜井联络巷4,在螺旋斜坡道弯道3中间掘进溜井5,溜井5下部连通穿脉与溜井联络巷17,穿脉与溜井联络巷17再连通穿脉巷道16,穿脉巷道16与中段运输巷18相连通;在回采单元的顶部和底部分别留设顶部保安矿柱8和底部保安矿柱9;The gently inclined medium-thick ore body is divided into mining units, and the ore body in the mining unit is divided into strips along the strike, and a space column 6 is left between two adjacent belts along the strike of the ore body, in which the same mining unit The inner strip is divided into a one-step stope 11 and a two-step stope 10, and every 12 stopes are used as a recovery unit, and the ramp bend 3 and the ramp straight 7 are excavated in the intercolumn 6, along the ramp 3 The stope connecting roadway 2 is respectively excavated with the slope road straight road 7, and the stope connecting roadway 2 is connected with the first-step stope 11 and the second-step stope 10 respectively, and the stope connecting roadway 2 is respectively connected with the left side of the inter-column 6 The upper stratified stope 12 and the lower stratified stope 13 of the strip on the right side of the inter-column 6; excavate the ramp and the chute connecting roadway 4 in the ramp 3 part, and excavate the chute 5 in the middle of the spiral ramp 3, The lower part of the chute 5 is connected to the piercing tunnel and the chute connecting lane 17, and the piercing tunnel and the chute connecting lane 17 are connected to the piercing tunnel 16, and the piercing tunnel 16 is connected to the middle transport tunnel 18; Ore pillar 8 and bottom security ore pillar 9;
(二)回采与充填:(2) Mining and filling:
同一回采单元内的一步骤采场11和二步骤采场10分别由下而上进行间隔回采,待回采单元内的一步骤采场11均回采完毕进行充填,当充填体终凝后,达到自立时间,再依次对回采单元内的二步骤采场10进行回采,当同一回采单元内的一步骤采场11和二步骤采场10均回采完毕,充填体均达到终凝后,再回收相邻回采单元中间的间柱6;The first-step stope 11 and the second-step stope 10 in the same recovery unit are mined at intervals from bottom to top, and the first-step stope 11 in the recovery unit is all backed and filled. When the filling body is finally set, it will reach self-supporting time, and then sequentially recover the two-step stope 10 in the recovery unit, and when the first-step stope 11 and the second-step stope 10 in the same recovery unit are all recovered, and the filling bodies all reach the final setting, then recover the adjacent The intercolumn 6 in the middle of the mining unit;
每个采场的回采分为两个分层进行,上分层为切顶层,斜坡道弯道3和斜坡道直道7分别连接上分层采场12和下分层采场13,自上分层切顶层开始进行切顶,采用自动化铲运机进行出矿,矿石从采场联络巷2运输到斜坡道弯道3或斜坡道直道7,再经斜坡道弯道3或斜坡道直道7到斜坡道与溜井联络巷4运输到采区溜井5,然后对采场顶板进行锚杆和锚索支护14;上分层回采完毕后,在条带的顶端用深孔拉切割槽,切割槽形成后,在上分层采场12凿向下的中深孔15,然后对中深孔15进行装药和爆破,通过采场联络巷2、斜坡道弯道3和斜坡道直道7、斜坡道与溜井联络巷4将矿石运输到采区溜井5,矿石经过溜井5下放到穿脉巷道16上的电机车,再通过中段运输巷18运输到矿区主溜井;The mining of each stope is divided into two layers, the upper layer is the cut top layer, the slope bend 3 and the slope straight 7 connect the upper layer stope 12 and the lower layer stope 13 respectively, from the upper layer The top layer of the layer is cut and the roof is cut, and the ore is extracted by an automatic scraper. The ore is transported from the stope connecting roadway 2 to the ramp bend 3 or the ramp straight 7, and then passes through the ramp bend 3 or the ramp straight 7 to The inclined road and the chute connection roadway 4 are transported to the chute 5 in the production area, and then the stope roof is supported by bolts and anchor cables 14; After forming, cut down the medium-deep hole 15 in the upper stratified stope 12, then charge and blast the medium-deep hole 15, pass through the stope connecting roadway 2, the ramp bend 3 and the ramp straightway 7, the slope The ore is transported to the chute 5 in the mining area through the connecting roadway 4 of the road and the chute, and the ore is lowered to the electric locomotive on the passageway 16 through the chute 5, and then transported to the main chute of the mining area through the middle transportation lane 18;
当相邻几个回采单元的采场全部回采完毕,对其进行充填,充填体终凝后再进行间柱6回采,当某一分段采场全部回采完毕,最后对顶部保安矿柱8和底部保安矿柱9进行回收。When the stopes of several adjacent mining units have all been mined, they will be filled, and after the final setting of the filling body, the intercolumn 6 will be mined. Bottom security pillar 9 reclaims.
实施例Example
谦比希铜矿东南矿体呈层状似层状产出,矿体的倾角为20~30°,厚度为10~16m,矿体沿走向长度为755~890m,属于缓倾斜中厚难采矿体,该矿区上盘和下盘围岩均为石英岩,其稳固性较好,矿体开采受地下水的影响较小,工程地质条件属于简单和中等类型。The ore body in the southeast of the Chambishi Copper Mine is layered and layered. The dip angle of the ore body is 20-30°, the thickness is 10-16m, and the length of the ore body along the strike is 755-890m. The surrounding rocks of the hanging wall and footwall of this mining area are all quartzite, which has good stability, and the mining of the ore body is less affected by groundwater, and the engineering geological conditions are of simple and medium types.
采准与切割:如图1、2和3所示,将缓倾斜中厚矿体划分为回采单元,对同一回采单元内的矿体沿走向划分为条带,即回采单元内条带划分为一步骤采场11和二步骤采场10,每12个采场作为一个回采单元,每个回采单元中间留设有间柱6,在间柱6上布置有斜坡道弯道3、斜坡道直道7和采区溜井5,溜井5下部连通穿脉与溜井联络巷17,再与穿脉巷道16相连,穿脉巷道16与中段运输巷18相连;斜坡道直道7和斜坡道弯道3分别与采场相连;在分段巷的顶部和底部分别留设有顶部保安矿柱8和底部保安矿柱9。Mining standard and cutting: As shown in Figure 1, 2 and 3, the gently inclined medium-thick ore body is divided into mining units, and the ore body in the same mining unit is divided into strips along the strike, that is, the strips in the mining unit are divided into The first-step stope 11 and the second-step stope 10, every 12 stopes are used as a recovery unit, and a spacer 6 is left in the middle of each recovery unit, and a ramp bend 3 and a ramp straightway are arranged on the spacer 6 7 and mining area chute 5, the lower part of chute 5 is connected with piercing vein and chute connecting lane 17, and then connected with piercing tunnel 16, and piercing tunnel 16 is connected with middle transport lane 18; ramp straight road 7 and ramp bend 3 are respectively connected with The stopes are connected; the top security ore pillar 8 and the bottom security ore pillar 9 are respectively reserved at the top and bottom of the section roadway.
回采与充填:如图1和2所示,同一回采单元内的采场分为一步骤采场11和二步骤采场10,先开采一步骤采场11,且一个回采单元内的多个一步骤采场11可同时进行回采,随后对一步骤采场11进行充填(采用高强度的灰砂比充填料对其进行充填),待一步骤采场11充填后并达到终凝,可进行自立,再依次回采回采单元内的二步骤采场10,随后对二步骤采场10进行充填(采用低强度的灰砂比充填料对其进行充填);相邻几个回采单元内的采场均回采和充填完毕,再对回采单元中的间柱6、底部保安矿柱9和顶部保安矿柱8进行回收。Mining and filling: as shown in Figures 1 and 2, the stope in the same mining unit is divided into a one-step stope 11 and a two-step stope 10, and the first-step stope 11 is mined first, and multiple one-step stopes in one recovery unit The step stope 11 can be mined at the same time, and then the first step stope 11 can be filled (it is filled with high-strength lime-sand ratio filling material), and after the first step stope 11 is filled and reaches the final setting, it can be self-supporting , and then sequentially recover the two-step stope 10 in the recovery unit, and then fill the second-step stope 10 (filling it with low-strength lime-sand ratio filling material); the stopes in several adjacent recovery units are averaged After mining and filling are completed, the intercolumn 6, the bottom security ore pillar 9 and the top security ore pillar 8 in the mining unit are recovered.
如图2和3所示,每个采场的回采分为上下两个分层,分别为上分层采场12和下分层采场13,先回采上分层采场12,再回采下分层采场13,采场联络巷2分别与上分层采场12和下分层采场13进行相连,自采场联络巷2开始对上分层采场12进行切顶,崩落矿体19的矿石从采场联络巷2、斜坡道直道7和斜坡道弯道3经斜坡道与溜井联络巷4运输至采区溜井5,并采用锚杆和锚索等形式对顶板进行支护。然后在下分层采场13的顶端拉切割槽,切割槽形成后,采用中深孔台车在上分层凿下向中深孔15,分排对中深孔进行装药和爆破,通过采场联络巷2、斜坡道直道7和斜坡道弯道3经斜坡道与溜井联络巷4运输至采区溜井5。As shown in Figures 2 and 3, the mining of each stope is divided into upper and lower layers, which are respectively the upper layer stope 12 and the lower layer stope 13. The upper layer stope 12 is recovered first, and then the lower layer stope is recovered. The layered stope 13 and the stope connecting roadway 2 are respectively connected with the upper layered stope 12 and the lower layered stope 13, and the top layered stope 12 is cut from the stope connecting roadway 2, and the orebody caving The ore in 19 is transported from the stope connecting roadway 2, the slope straight road 7 and the slope curve 3 to the mining area chute 5 through the slope road and the chute connecting roadway 4, and the roof is supported by bolts and anchor cables. Then pull the cutting groove at the top of the lower stratified stope 13. After the cutting groove is formed, the middle and deep hole jumbo is used to chisel down the middle and deep holes 15 in the upper layer, and the middle and deep holes are charged and blasted in rows. Field connecting lane 2, ramp straight road 7 and ramp bend 3 are transported to mining area chute 5 through ramp and chute connecting lane 4.
当相邻几个回采单元的采场全部回采完毕,并对其进行充填,充填体终凝后再进行间柱6回采,当某一分段采场全部回采完毕,最后对顶部保安矿柱8和底部保安矿柱9进行回收。间柱6主要采用房柱法对其进行回收,首先通过留设点柱支护空区,最后回采结束时对其进行统一封闭,再用低灰砂比的膏体充填体对其进行充填;在对顶部保安矿柱8和底部保安矿柱9进行回收时,首先在宽度方向上刷大分段巷道1,然后以分段巷道1作为凿岩巷,施工上向扇形中深孔,顶板稳定性不好时,间隔施工锚索,后退式进行爆破,分段砌筑充填挡墙进行充填。When the stopes of several adjacent mining units are all mined, and they are filled, the inter-column 6 is mined after the filling body is finally set. Reclaim with bottom security ore pillar 9. The inter-column 6 is mainly recovered by the room-pillar method. First, point columns are set to support the empty area, and finally it is uniformly closed at the end of mining, and then it is filled with a paste filling body with a low lime-sand ratio; When recovering the top security pillar 8 and the bottom security pillar 9, first brush the large segmented roadway 1 in the width direction, and then use the segmented roadway 1 as the rock drilling roadway to construct the upward fan-shaped medium-deep hole with a stable roof When the performance is not good, the anchor cables are constructed at intervals, the blasting is carried out in a backward manner, and the retaining wall is filled by masonry in sections.
其中,一步骤采场11和二步骤采场10的宽度为8~12m,长度为100~160m,间柱的宽度为30~50m。Wherein, the width of the first-step stope 11 and the second-step stope 10 is 8-12m, the length is 100-160m, and the width of the intercolumn is 30-50m.
回采单元与回采单元之间可同时连续回采,同一回采单元采场的回采与充填可同时进行连续作业。The mining unit and the mining unit can be continuously mined at the same time, and the mining and filling of the stope of the same mining unit can be continuously operated at the same time.
每个采场的回采分为两个分层进行,先在上分层进行切顶,采用锚杆和锚索等支护形式对顶板进行护顶,再采用下向中深孔对下分层矿进行回采。The mining of each stope is divided into two layers. First, the roof is cut in the upper layer, and the roof is protected by supporting forms such as anchor rods and anchor cables, and then the lower layer is protected by using downward-facing medium-deep holes. Mine is recovered.
该方法适用于矿体倾角为20~30°,矿体厚度为10~16m的缓倾斜中厚矿体的开采。The method is suitable for the mining of gently inclined medium-thick ore bodies with an ore body dip angle of 20-30° and an ore body thickness of 10-16 m.
本发明针对矿体倾角为20~30°,矿体厚度为10~16m的缓倾斜中厚矿体,难以采用机械化进行连续高效开采,属于难采矿体,通过将矿体划分为回采单元,回采单元内矿体划分为条带,同一回采单元内一步骤采场或二步骤采场可同时进行连续回采,不同回采单元内的采场也可同时进行连续回采与充填,采切巷道少,对上分层采场顶板进行支护,下分层采用中深孔进行爆破,采用大型铲运机进行连续出矿,间柱、顶部保安矿柱和底部保安矿柱可进行回收,具有机械化程度高、生产能力大、采切工程量少、矿石回采率高、贫损率低和安全性好的特点。The present invention aims at the ore body whose inclination angle is 20-30° and the thickness of the ore body is 10-16m. It is difficult to use mechanization for continuous and high-efficiency mining, which belongs to the difficult-to-mining ore body. The ore body in the unit is divided into strips, the one-step stope or the two-step stope in the same recovery unit can be continuously mined at the same time, and the stopes in different recovery units can also be continuously mined and filled at the same time. The roof of the upper layer stope is supported, the lower layer is blasted with medium and deep holes, and large-scale scrapers are used for continuous mining. The inter-pillars, top security pillars and bottom security pillars can be recycled, with a high degree of mechanization. , Large production capacity, less mining and cutting engineering, high ore recovery rate, low loss rate and good safety.
以上所述是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明所述原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above description is a preferred embodiment of the present invention, it should be pointed out that for those of ordinary skill in the art, without departing from the principle of the present invention, some improvements and modifications can also be made, these improvements and modifications It should also be regarded as the protection scope of the present invention.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711293513.6A CN108104869B (en) | 2017-12-08 | 2017-12-08 | A kind of continuous mining and filling mining method of gently inclined medium-thick orebodies |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711293513.6A CN108104869B (en) | 2017-12-08 | 2017-12-08 | A kind of continuous mining and filling mining method of gently inclined medium-thick orebodies |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108104869A true CN108104869A (en) | 2018-06-01 |
CN108104869B CN108104869B (en) | 2019-05-07 |
Family
ID=62208208
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711293513.6A Active CN108104869B (en) | 2017-12-08 | 2017-12-08 | A kind of continuous mining and filling mining method of gently inclined medium-thick orebodies |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108104869B (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109083644A (en) * | 2018-08-16 | 2018-12-25 | 中南大学 | A kind of safe and efficient mining methods of gently inclined medium thick orebody |
CN109339783A (en) * | 2018-11-15 | 2019-02-15 | 中国恩菲工程技术有限公司 | The route open stope afterwards filling mining method of gently inclined medium thick orebody |
CN109979304A (en) * | 2019-04-28 | 2019-07-05 | 湖南科技大学 | A kind of integrated teaching mould of more recovery methods and simulation mining method |
CN110259451A (en) * | 2019-06-20 | 2019-09-20 | 中南大学 | A kind of efficient mining methods of gently inclined medium thick orebody Pre-control roof |
CN110552701A (en) * | 2019-10-10 | 2019-12-10 | 锡林郭勒盟山金阿尔哈达矿业有限公司 | Partitioned combined filling mining method |
CN110656938A (en) * | 2019-08-19 | 2020-01-07 | 西北矿冶研究院 | Subsequent filling mining method suitable for gently inclined medium-thickness broken ore body |
CN110905510A (en) * | 2019-11-13 | 2020-03-24 | 铜陵有色金属集团股份有限公司 | Strip and block stoping method for horizontal ore pillar of metal ore body |
CN111364997A (en) * | 2019-12-31 | 2020-07-03 | 武钢资源集团有限公司 | Upward drift-caving combined mining method |
CN111720120A (en) * | 2020-07-31 | 2020-09-29 | 王有奇 | Method for achieving pre-support by adopting two-step mining stope based on layered filling method |
CN112228072A (en) * | 2020-09-29 | 2021-01-15 | 华南理工大学 | Underground supporting system for loess stud and reserved thin-strip ore pillar and construction method |
CN113266354A (en) * | 2021-06-09 | 2021-08-17 | 山东黄金矿业科技有限公司深井开采实验室分公司 | Two-step stoping upward filling mining method along strike layered approach |
CN117489345A (en) * | 2023-11-28 | 2024-02-02 | 长沙矿山研究院有限责任公司 | A method of quasi-sectioned open field unit mining within veins followed by backfill mining |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU773296A1 (en) * | 1979-04-16 | 1980-10-23 | Предприятие П/Я Г-4693 | Support frame of scraper-type filling-in unit |
SU838096A1 (en) * | 1978-06-22 | 1981-06-15 | Днепропетровский Ордена Трудового Крас-Ного Знамени Горный Институт Им.Aptema | Method of vibration compacting of filling area |
CN85103513A (en) * | 1985-04-30 | 1986-10-29 | 中南工业大学 | Across pitch moves back continuously adopts the sublevel open stoping caved stopes |
CN103590831A (en) * | 2013-11-22 | 2014-02-19 | 北京科技大学 | Novel mining method of gently-inclined thin and medium thickness ore bodies |
-
2017
- 2017-12-08 CN CN201711293513.6A patent/CN108104869B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU838096A1 (en) * | 1978-06-22 | 1981-06-15 | Днепропетровский Ордена Трудового Крас-Ного Знамени Горный Институт Им.Aptema | Method of vibration compacting of filling area |
SU773296A1 (en) * | 1979-04-16 | 1980-10-23 | Предприятие П/Я Г-4693 | Support frame of scraper-type filling-in unit |
CN85103513A (en) * | 1985-04-30 | 1986-10-29 | 中南工业大学 | Across pitch moves back continuously adopts the sublevel open stoping caved stopes |
CN103590831A (en) * | 2013-11-22 | 2014-02-19 | 北京科技大学 | Novel mining method of gently-inclined thin and medium thickness ore bodies |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109083644B (en) * | 2018-08-16 | 2019-08-02 | 中南大学 | A kind of safe and efficient mining methods of gently inclined medium thick orebody |
CN109083644A (en) * | 2018-08-16 | 2018-12-25 | 中南大学 | A kind of safe and efficient mining methods of gently inclined medium thick orebody |
CN109339783A (en) * | 2018-11-15 | 2019-02-15 | 中国恩菲工程技术有限公司 | The route open stope afterwards filling mining method of gently inclined medium thick orebody |
CN109979304A (en) * | 2019-04-28 | 2019-07-05 | 湖南科技大学 | A kind of integrated teaching mould of more recovery methods and simulation mining method |
CN109979304B (en) * | 2019-04-28 | 2024-05-14 | 湖南科技大学 | Multi-mining-method-integrated teaching mould and simulated mine mining method |
CN110259451A (en) * | 2019-06-20 | 2019-09-20 | 中南大学 | A kind of efficient mining methods of gently inclined medium thick orebody Pre-control roof |
CN110656938B (en) * | 2019-08-19 | 2021-05-18 | 西北矿冶研究院 | Subsequent filling mining method suitable for gently inclined medium-thickness broken ore body |
CN110656938A (en) * | 2019-08-19 | 2020-01-07 | 西北矿冶研究院 | Subsequent filling mining method suitable for gently inclined medium-thickness broken ore body |
CN110552701A (en) * | 2019-10-10 | 2019-12-10 | 锡林郭勒盟山金阿尔哈达矿业有限公司 | Partitioned combined filling mining method |
CN110905510B (en) * | 2019-11-13 | 2021-06-08 | 铜陵有色金属集团股份有限公司 | Strip and block stoping method for horizontal ore pillar of metal ore body |
CN110905510A (en) * | 2019-11-13 | 2020-03-24 | 铜陵有色金属集团股份有限公司 | Strip and block stoping method for horizontal ore pillar of metal ore body |
CN111364997A (en) * | 2019-12-31 | 2020-07-03 | 武钢资源集团有限公司 | Upward drift-caving combined mining method |
CN111720120A (en) * | 2020-07-31 | 2020-09-29 | 王有奇 | Method for achieving pre-support by adopting two-step mining stope based on layered filling method |
CN112228072A (en) * | 2020-09-29 | 2021-01-15 | 华南理工大学 | Underground supporting system for loess stud and reserved thin-strip ore pillar and construction method |
CN112228072B (en) * | 2020-09-29 | 2022-04-15 | 华南理工大学 | Underground support system and construction method of loess inter-pillars and reserved thin-strip ore pillars |
CN113266354A (en) * | 2021-06-09 | 2021-08-17 | 山东黄金矿业科技有限公司深井开采实验室分公司 | Two-step stoping upward filling mining method along strike layered approach |
CN117489345A (en) * | 2023-11-28 | 2024-02-02 | 长沙矿山研究院有限责任公司 | A method of quasi-sectioned open field unit mining within veins followed by backfill mining |
CN117489345B (en) * | 2023-11-28 | 2024-12-10 | 长沙矿山研究院有限责任公司 | A mining method for intra-vein accurate segmented empty field unit recovery and subsequent filling |
Also Published As
Publication number | Publication date |
---|---|
CN108104869B (en) | 2019-05-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108104869A (en) | A kind of continuous stoping method of mining by the way of filling of gently inclined medium thick orebody | |
CN104806244B (en) | Filling mining method for slant middle-thick ore body | |
CN105041314B (en) | A kind of combined mining method of deep afterwards rooming-slicing ore pillar | |
CN102678121B (en) | Mining method of layer-controlled roofing and subsequent filling in medium-deep holes without panels | |
CN104847355B (en) | Open field continuous mining method of medium-thick steeply inclined ore body | |
CN103089266B (en) | Drift-pillar-free sublevel barnyard caving mining method of open pit transferred underground transitional period | |
CN107869349A (en) | A kind of mechanized mining method of gently inclined medium thick orebody | |
CN108843382A (en) | Downward subsequent filling method suitable for unstable medium-thickness ore body of gently inclined surrounding rock | |
CN104153780B (en) | Lean ore body sublevel caving stays ore deposit continuous stoping technique | |
CN103437769B (en) | Combination is reproduced structure medium-length hole ore blast and is worked in coordination with cable bolting afterwards filling mining method | |
CN1474032A (en) | Step-by-step extrusion and collapse followed by filling continuous mining method | |
CN103590831A (en) | Novel mining method of gently-inclined thin and medium thickness ore bodies | |
CN112682041B (en) | Filling mining method for broken and slowly-inclined thick and large ore body of upper disc | |
CN102155228A (en) | Fully-segmented presplitting squeezing primary-blasting mining method | |
CN104632220B (en) | Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope | |
CN102168579A (en) | Rib-pillar-free continuous sublevel filling method for mining preparation in medium-thickness slope crushed ore body vein | |
CN110259451A (en) | A kind of efficient mining methods of gently inclined medium thick orebody Pre-control roof | |
CN103147761A (en) | Filling mining method of gently inclined thin mineral deposit with soft roof | |
CN104895566A (en) | Mining method with residual ore recovery function | |
CN103104259A (en) | Inclination fragmentation ore body segment top board reconstruction middle-deep hole ore break down filling mining method | |
CN105201506B (en) | The mining methods of afterwards filling are reinforced before a kind of heir | |
CN105626071A (en) | Mining method for gently inclined thin ore body | |
CN105927226A (en) | Medium-length hole ore-breaking continuous sectional horizontal filling mining method | |
CN114592867B (en) | Combined mining method of temporary top pillar induced caving and pillarless sublevel caving | |
CN103437768A (en) | Pre-set space filling mining method without top column and bottom column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |