CN114875931B - Enclosure structure, construction method and removal method of enclosure structure - Google Patents

Enclosure structure, construction method and removal method of enclosure structure Download PDF

Info

Publication number
CN114875931B
CN114875931B CN202210642771.5A CN202210642771A CN114875931B CN 114875931 B CN114875931 B CN 114875931B CN 202210642771 A CN202210642771 A CN 202210642771A CN 114875931 B CN114875931 B CN 114875931B
Authority
CN
China
Prior art keywords
pile
embedded
enclosure
dismantled
pipelines
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210642771.5A
Other languages
Chinese (zh)
Other versions
CN114875931A (en
Inventor
夏锋
李衡
承元涛
王军鹏
许�鹏
张小水
王元灿
赵军磊
王可
李震
梁凤璐
沈彬鑫
郝宇菲
代雅
贾文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority to CN202210642771.5A priority Critical patent/CN114875931B/en
Publication of CN114875931A publication Critical patent/CN114875931A/en
Application granted granted Critical
Publication of CN114875931B publication Critical patent/CN114875931B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种围护结构、围护结构的施工方法及拆除方法,涉及地铁车站施工技术领域,围护结构包括包括围护结构本体和多个预埋管道,围护结构本体包括成行设置的多个钻孔桩,各钻孔桩的内部设置有钢筋笼,围护结构本体具有拆除边界和待拆除围护体,待拆除围护体为围护结构后期需要拆除的部分,拆除边界为待拆除围护体的边界,待拆除围护体上最外侧的两个钻孔桩均为边桩,两个边桩之间的钻孔桩均为中桩,边桩位于待拆除围护体内的部分为待拆除边桩体体,中桩位于待拆除围护体内的部分为待拆除中桩体;各预埋管道分别用于穿入切割绳对待拆除围护体进行切割,减少噪音污染、减少对结构及防水在成损坏,提高了施工效率。

The invention discloses a retaining structure, a construction method of the retaining structure and a demolition method, and relates to the technical field of subway station construction. The retaining structure comprises a retaining structure body and a plurality of pre-buried pipes. The retaining structure body comprises a plurality of bored piles arranged in a row, a steel cage is arranged inside each bored pile, the retaining structure body comprises a demolition boundary and a retaining body to be demolished, the retaining body to be demolished is a part of the retaining structure that needs to be demolished later, the demolition boundary is a boundary of the retaining body to be demolished, the two outermost bored piles on the retaining body to be demolished are both side piles, the bored piles between the two side piles are both middle piles, the part of the side pile located in the retaining body to be demolished is the side pile body to be demolished, and the part of the middle pile located in the retaining body to be demolished is the middle pile body to be demolished; each pre-buried pipe is respectively used for inserting a cutting rope to cut the retaining body to be demolished, thereby reducing noise pollution, reducing damage to the structure and waterproofing, and improving construction efficiency.

Description

围护结构、围护结构的施工方法及拆除方法Enclosure structure, construction method and removal method of enclosure structure

技术领域Technical Field

本发明涉及地铁车站施工技术领域,特别是涉及一种围护结构、围护结构的施工方法及拆除方法。The present invention relates to the technical field of subway station construction, and in particular to a retaining structure, a construction method of the retaining structure and a dismantling method thereof.

背景技术Background Art

目前,在地铁车站预留口贴壁围护结构破除过程中,通常采用炮锤破除,施工前需采用大型吊车将炮锤吊放至基坑内,施工破除时站位困难、噪音大、扬尘大,易对已完成结构及防水造成损坏。At present, blasting hammers are usually used to demolish the wall retaining structures of reserved openings in subway stations. Before construction, a large crane is required to lower the blasting hammer into the foundation pit. During the demolition work, it is difficult to stand, the noise is loud, and a lot of dust is generated, which can easily cause damage to the completed structure and waterproofing.

发明内容Summary of the invention

本发明的目的是提供一种围护结构、围护结构的施工方法及拆除方法,以解决上述现有技术存在的问题,减少噪音污染、减少对结构及防水在成损坏,提高了施工效率。The purpose of the present invention is to provide a protective structure, a construction method of the protective structure and a dismantling method to solve the problems existing in the above-mentioned prior art, reduce noise pollution, reduce damage to the structure and waterproofing, and improve construction efficiency.

为实现上述目的,本发明提供了如下方案:To achieve the above object, the present invention provides the following solutions:

本发明提供一种围护结构,包括:围护结构本体和多个预埋管道,所述围护结构本体包括成行设置的多个钻孔桩,各所述钻孔桩的内部设置有钢筋笼,所述围护结构本体具有拆除边界和待拆除围护体,在所述拆除边界处进行切割能够将所述待拆除围护体拆除,所述待拆除围护体上最外侧的两个所述钻孔桩均为边桩,两个所述边桩之间的所述钻孔桩均为中桩,所述边桩位于所述待拆除围护体内的部分为待拆除边桩体,所述中桩位于所述待拆除围护体内的部分为待拆除中桩体;各所述预埋管道分别用于穿入切割绳对所述待拆除围护体进行切割,各所述待拆除中桩体顶面和底面、各所述待拆除边桩体顶面和底面以及各所述待拆除边桩体背离所述中桩的侧面均设置有预埋管道,各所述待拆除中桩体顶面和底面设置的预埋管道为中桩水平预埋管道,各所述待拆除边桩体顶面和底面的预埋管道为边桩端部预埋管道,各所述待拆除边桩体背离所述中桩的侧面的预埋管道为竖向预埋管道,所述中桩水平预埋管道、所述边桩端部预埋管道和所述竖向预埋管道均位于所述拆除边界上,各所述中桩水平预埋管道呈环形并固定套设于各所述中桩的钢筋笼的外侧,所述边桩端部预埋管道包括第一外预埋管道和第一内预埋管道,所述第一内预埋管道的两端与所述第一外预埋管道连接并连通形成环形,各所述第一内预埋管道穿过各所述边桩的钢筋笼设置于所述边桩的钢筋笼内侧,各所述第一外预埋管道固定设置于各所述边桩的钢筋笼外侧,各所述竖向预埋管道呈环形,各所述竖向预埋管道的上、下两侧边分别穿过各所述边桩的钢筋笼设置于所述待拆除边桩体顶面和底面,所述竖向预埋管道竖向方向上的两侧边分别固定设置于所述钢筋笼外侧。The present invention provides a retaining structure, comprising: a retaining structure body and a plurality of pre-buried pipes, the retaining structure body comprising a plurality of bored piles arranged in a row, a steel cage being arranged inside each of the bored piles, the retaining structure body having a demolition boundary and a retaining body to be demolished, the retaining body to be demolished can be demolished by cutting at the demolition boundary, the two outermost bored piles on the retaining body to be demolished are both side piles, the bored pile between the two side piles is both a middle pile, the portion of the side pile located inside the retaining body to be demolished is the side pile body to be demolished, and the portion of the middle pile located inside the retaining body to be demolished is the middle pile body to be demolished; each of the pre-buried pipes is respectively used to penetrate a cutting rope to cut the retaining body to be demolished, the top surface and bottom surface of each of the middle pile bodies to be demolished, the top surface and bottom surface of each of the side pile bodies to be demolished, and the side surface of each of the side pile bodies to be demolished away from the middle pile are all provided with pre-buried pipes, the pre-buried pipes arranged on the top surface and bottom surface of each of the middle pile bodies to be demolished are horizontal pre-buried pipes of the middle piles, and each of the side pile bodies to be demolished The embedded pipes on the top and bottom surfaces are embedded pipes at the ends of the side piles, the embedded pipes on the sides of the side piles to be removed away from the middle piles are vertical embedded pipes, the horizontal embedded pipes of the middle piles, the embedded pipes at the ends of the side piles and the vertical embedded pipes are all located on the demolition boundaries, the horizontal embedded pipes of the middle piles are annular and fixedly sleeved on the outside of the steel cage of each middle pile, the embedded pipes at the ends of the side piles include a first outer embedded pipe and a first inner embedded pipe, both ends of the first inner embedded pipe are connected to the first An outer pre-buried pipe is connected and communicated to form a ring, each of the first inner pre-buried pipes passes through the steel cage of each side pile and is arranged on the inner side of the steel cage of the side pile, each of the first outer pre-buried pipes is fixedly arranged on the outer side of the steel cage of each side pile, each of the vertical pre-buried pipes is ring-shaped, and the upper and lower side edges of each vertical pre-buried pipe respectively pass through the steel cage of each side pile and are arranged on the top and bottom surfaces of the side pile body to be removed, and the two side edges of the vertical pre-buried pipe in the vertical direction are respectively fixedly arranged on the outer side of the steel cage.

优选的,还包括多个边桩分段预埋管道,各所述边桩分段预埋管道并排设置于位于两个所述边桩端部预埋管道之间的所述待拆除边桩体上,且各所述边桩分段预埋管道与所述边桩端部预埋管道平行,各所述边桩分段预埋管道均包括第二外预埋管道和第二内预埋管道,所述第二内预埋管道的两端与所述第二外预埋管道连接并连通形成环形,各所述第二内预埋管道穿过各所述边桩的钢筋笼设置于所述待拆除边桩体背离所述中桩的侧面,各所述第二外预埋管道固定设置于各所述边桩的钢筋笼外侧。Preferably, it also includes a plurality of side pile segmented pre-buried pipes, each of the side pile segmented pre-buried pipes is arranged side by side on the side pile body to be removed between the two side pile end pre-buried pipes, and each of the side pile segmented pre-buried pipes is parallel to the side pile end pre-buried pipes, each of the side pile segmented pre-buried pipes includes a second outer pre-buried pipe and a second inner pre-buried pipe, both ends of the second inner pre-buried pipe are connected to the second outer pre-buried pipe and communicated to form a ring, each of the second inner pre-buried pipes passes through the steel cage of each side pile and is arranged on the side of the side pile body to be removed away from the middle pile, and each of the second outer pre-buried pipes is fixedly arranged on the outside of the steel cage of each side pile.

优选的,各所述预埋管道的两端端口通过对接热熔封堵使各所述预埋管形成封闭管道。Preferably, both end ports of each pre-buried pipe are sealed by butt-jointing and hot-melting so that each pre-buried pipe forms a closed pipe.

优选的,所述预埋管道为中密度聚乙烯管,直径18~22mm,壁厚1.8~2.2mm,最小弯折半径18~22cm。Preferably, the pre-buried pipeline is a medium-density polyethylene pipe with a diameter of 18 to 22 mm, a wall thickness of 1.8 to 2.2 mm, and a minimum bending radius of 18 to 22 cm.

优选的,各所述预埋管道位于各所述钻孔桩的混凝土层内部,各所述预埋管道的两端端口的对接处设置为外凸的凸起。Preferably, each of the pre-buried pipes is located inside the concrete layer of each of the bored piles, and the butt joints of the two end ports of each of the pre-buried pipes are configured as outwardly convex protrusions.

优选的,所述中桩水平预埋管道两端端口的对接处为第一凸起,所述边桩端部预埋管道两端端口的对接处为第二凸起,所述竖向预埋管道两端端口的对接处为第三凸起,所述第一凸起设置于所述中桩的迎土侧,所述第二凸起设置于所述边桩朝向所述中桩的一侧,所述第三凸起设置于所述边桩的迎土侧。Preferably, the butt joint of the ports at both ends of the horizontal pre-buried pipe of the center pile is a first protrusion, the butt joint of the ports at both ends of the pre-buried pipe at the end of the side pile is a second protrusion, and the butt joint of the ports at both ends of the vertical pre-buried pipe is a third protrusion. The first protrusion is arranged on the soil-facing side of the center pile, the second protrusion is arranged on the side of the side pile facing the center pile, and the third protrusion is arranged on the soil-facing side of the side pile.

本发明还提供了一种如权利要求1-6任一项围护结构的施工方法,包括如下步骤:The present invention also provides a construction method of a retaining structure according to any one of claims 1 to 6, comprising the following steps:

S1:根据地铁的结构图纸,确定所述待拆除围护体和所述拆除边界;S1: Determine the enclosure to be demolished and the demolition boundary according to the structural drawings of the subway;

S2:在所述围护结构的所述钢筋笼绑扎完成后,根据所述拆除边界与所述钢筋笼的相对位置在各所述钢筋笼上安装各所述预埋管道并绑扎牢固;S2: After the steel cages of the enclosure structure are tied, the embedded pipes are installed on the steel cages according to the relative position between the demolition boundary and the steel cages and tied securely;

S3:将所述钢筋笼放入钻孔中并浇筑混凝土形成所述钻孔桩,钻孔桩全部浇筑完成形成所述围护结构。S3: placing the steel cage into the drilled hole and pouring concrete to form the bored piles. After all the bored piles are poured, the retaining structure is formed.

本发明还提供了一种如权利要求1-7任一项围护结构中的待拆除围护体的拆除方法,包括如下步骤:The present invention also provides a method for removing a to-be-removed enclosure in a enclosure structure according to any one of claims 1 to 7, comprising the following steps:

S1:对所述待拆除围护体迎土侧的土进行开挖至露出所述待拆除围护体,根据所述预埋管道的位置凿出所述预埋管道,将所述切割绳穿入到所述预埋管道内;S1: excavating the soil on the soil side of the enclosure to be removed until the enclosure to be removed is exposed, chiseling out the pre-buried pipeline according to the position of the pre-buried pipeline, and inserting the cutting rope into the pre-buried pipeline;

S2:将所述切割绳与绳锯切割机连接,使切割绳对所述待拆除围护体进行切割。S2: Connect the cutting rope to a rope saw cutting machine, so that the cutting rope cuts the enclosure to be removed.

S3:将切割下的所述待拆除围护体运出。S3: transporting the cut enclosure to be dismantled out.

优选的,所述切割绳为金刚绳。Preferably, the cutting rope is a diamond rope.

优选的,所述切割绳为金刚绳。Preferably, the cutting rope is a diamond rope.

本发明相对于现有技术取得了以下技术效果:Compared with the prior art, the present invention has achieved the following technical effects:

本发明提供一种围护结构、围护结构的施工方法及拆除方法,通过安装预埋管道,将切割绳穿入到预埋管道内,将切割绳与绳锯切割机连接切割贴壁的围护结构,解决了紧贴主体结构部分围护结构无法直接切除,采用炮锤破除时站位困难、噪音大、易对已完成结构及防水造成损坏的问题,提高了施工效率,避免了因防水及结构损坏造成结构渗流。The present invention provides a retaining structure, a construction method for the retaining structure and a dismantling method thereof. Preburied pipes are installed, a cutting rope is inserted into the preburied pipes, and the cutting rope is connected to a rope saw cutting machine to cut the retaining structure attached to the wall. The problem that the retaining structure close to the main structure cannot be directly removed, and the problem that a blasting hammer is used to break the retaining structure is difficult to stand in, the noise is loud, and the completed structure and waterproofing are easily damaged is solved. The construction efficiency is improved, and structural seepage caused by waterproofing and structural damage is avoided.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

图1为本发明提供的围护结构的竖向剖视图;FIG1 is a vertical cross-sectional view of a protective structure provided by the present invention;

图2为本发明提供的围护结构水平剖视图;FIG2 is a horizontal cross-sectional view of the enclosure structure provided by the present invention;

图3为本发明提供的围护结构中的中桩的水平剖视图;FIG3 is a horizontal cross-sectional view of a center pile in the enclosure structure provided by the present invention;

图4为本发明提供的围护结构的待拆除边桩体的水平剖视图;FIG4 is a horizontal cross-sectional view of a side pile to be removed of the enclosure structure provided by the present invention;

图中:1、待拆除围护体;2、待拆除中桩体;3、待拆除边桩体;4、钢筋笼;5、中桩水平预埋管道;6、边桩端部预埋管道;7、竖向预埋管道;8、凸起。In the figure: 1. The retaining structure to be removed; 2. The middle pile to be removed; 3. The side pile to be removed; 4. The steel cage; 5. The horizontal pre-buried pipes at the middle pile; 6. The pre-buried pipes at the ends of the side piles; 7. The vertical pre-buried pipes; 8. The protrusions.

具体实施方式DETAILED DESCRIPTION

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

本发明的目的是提供一种围护结构、围护结构的施工方法及拆除方法,以解决上述现有技术存在的问题,避免噪音污染、避免对结构及防水在成损坏,提高了施工效率。The purpose of the present invention is to provide a protective structure, a construction method of the protective structure and a dismantling method thereof, so as to solve the problems existing in the above-mentioned prior art, avoid noise pollution, avoid damage to the structure and waterproofing, and improve construction efficiency.

为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

实施例一Embodiment 1

如图1~4所示,本实施例提供一种围护结构,包括:围护结构本体和多个预埋管道,围护结构本体包括成行设置的多个钻孔桩,各钻孔桩的内部设置有钢筋笼4,围护结构本体具有拆除边界和待拆除围护体1,在拆除边界处进行切割能够将待拆除围护体1拆除,待拆除围护体1上最外侧的两个钻孔桩均为边桩,两个边桩之间的钻孔桩均为中桩,边桩位于待拆除围护体1内的部分为待拆除边桩体3,中桩位于待拆除围护体1内的部分为待拆除中桩体2;各预埋管道分别用于穿入切割绳对待拆除围护体1进行切割,各待拆除中桩体2顶面和底面、各待拆除边桩体3顶面和底面以及各待拆除边桩体3背离中桩的侧面均设置有预埋管道,各待拆除中桩体2顶面和底面设置的预埋管道为中桩水平预埋管道5,各待拆除边桩体3顶面和底面的预埋管道为边桩端部预埋管道6,各待拆除边桩体3背离中桩的侧面的预埋管道为竖向预埋管道7,中桩水平预埋管道5、边桩端部预埋管道6和竖向预埋管道7均位于拆除边界上,各中桩水平预埋管道5呈环形并固定套设于各中桩的钢筋笼4的外侧,边桩端部预埋管道6包括第一外预埋管道和第一内预埋管道,第一内预埋管道的两端与第一外预埋管道连接并连通形成环形,各第一内预埋管道穿过各边桩的钢筋笼4设置于边桩的钢筋笼4内侧,各第一外预埋管道固定设置于各边桩的钢筋笼4外侧,各竖向预埋管道7呈环形,各竖向预埋管道7的上、下两侧边分别穿过各边桩的钢筋笼4设置于待拆除边桩体3顶面和底面,竖向预埋管道7竖向方向上的两侧边分别固定设置于钢筋笼4外侧,首先通过各个预埋管道的设置能够方便使用切割绳对待拆除围护体1进行切割从而能够避免噪音污染、避免对结构及防水在成损坏,另外通过设置中桩水平预埋管道5、边桩端部预埋管道6和竖向预埋管道7,并将预埋管道设置于钢筋笼4的外侧能够提高施工效率。As shown in Figures 1 to 4, this embodiment provides a retaining structure, including: a retaining structure body and a plurality of pre-buried pipes, the retaining structure body includes a plurality of bored piles arranged in a row, each bored pile is provided with a steel cage 4 inside, the retaining structure body has a demolition boundary and a retaining body 1 to be demolished, cutting at the demolition boundary can remove the retaining body 1 to be demolished, the two outermost bored piles on the retaining body 1 to be demolished are both side piles, the bored piles between the two side piles are both middle piles, the part of the side pile located inside the retaining body 1 to be demolished is the side pile body 3 to be demolished, and the middle pile is located at the retaining body to be demolished. 1 is the middle pile body 2 to be removed; each pre-buried pipe is used to penetrate the cutting rope to cut the enclosure 1 to be removed, and the top and bottom surfaces of each middle pile body 2 to be removed, the top and bottom surfaces of each side pile body 3 to be removed, and the side of each side pile body 3 to be removed away from the middle pile are all provided with pre-buried pipes. The pre-buried pipes arranged on the top and bottom surfaces of each middle pile body 2 to be removed are the horizontal pre-buried pipes 5 of the middle pile, the pre-buried pipes on the top and bottom surfaces of each side pile body 3 to be removed are the pre-buried pipes 6 at the end of the side pile, the pre-buried pipes on the side of each side pile body 3 to be removed away from the middle pile are the vertical pre-buried pipes 7, and the middle pile horizontal pre-buried pipes 8 are the vertical pre-buried pipes 9. The embedded pipes 5, the embedded pipes 6 at the ends of the side piles, and the vertical embedded pipes 7 are all located on the demolition boundary. The horizontal embedded pipes 5 of each middle pile are annular and fixedly sleeved on the outside of the steel cage 4 of each middle pile. The embedded pipes 6 at the ends of the side piles include a first outer embedded pipe and a first inner embedded pipe. Both ends of the first inner embedded pipe are connected to the first outer embedded pipe and communicated to form an annular shape. Each first inner embedded pipe passes through the steel cage 4 of each side pile and is arranged on the inner side of the steel cage 4 of the side pile. Each first outer embedded pipe is fixedly arranged on the outer side of the steel cage 4 of each side pile. Each vertical embedded pipe 7 is annular. The steel cage 4 that passes through each side pile on the upper and lower sides of the embedded pipe 7 is arranged on the top and bottom surfaces of the side pile body 3 to be demolished, and the two sides of the vertical embedded pipe 7 in the vertical direction are fixedly arranged on the outside of the steel cage 4. Firstly, through the arrangement of each embedded pipe, it is convenient to use a cutting rope to cut the enclosure 1 to be demolished, thereby avoiding noise pollution and damage to the structure and waterproofing. In addition, by arranging the horizontal embedded pipe 5 of the middle pile, the embedded pipe 6 at the end of the side pile and the vertical embedded pipe 7, and arranging the embedded pipe on the outside of the steel cage 4, the construction efficiency can be improved.

优选的,还包括多个边桩分段预埋管道,各边桩分段预埋管道并排设置于位于两个边桩端部预埋管道6之间的待拆除边桩体3上,且各边桩分段预埋管道与边桩端部预埋管道6平行,各边桩分段预埋管道均包括第二外预埋管道和第二内预埋管道,第二内预埋管道的两端与第二外预埋管道连接并连通形成环形,各第二内预埋管道穿过各边桩的钢筋笼4设置于待拆除边桩体3背离中桩的侧面,各第二外预埋管道固定设置于各边桩的钢筋笼4外侧,将待拆除边桩体3中间设置多道的边桩分段预埋管道方便对待拆除边桩体3进行横向和竖向的切割,提高施工效率。Preferably, it also includes a plurality of side pile segmented pre-buried pipes, each of which is arranged side by side on the side pile body 3 to be removed between the pre-buried pipes 6 at the ends of the two side piles, and each of the side pile segmented pre-buried pipes is parallel to the pre-buried pipes 6 at the ends of the side piles, and each of the side pile segmented pre-buried pipes includes a second outer pre-buried pipe and a second inner pre-buried pipe, both ends of the second inner pre-buried pipe are connected to the second outer pre-buried pipe and communicated to form a ring, each second inner pre-buried pipe passes through the steel cage 4 of each side pile and is arranged on the side of the side pile body 3 to be removed away from the middle pile, and each second outer pre-buried pipe is fixedly arranged on the outside of the steel cage 4 of each side pile, and a plurality of side pile segmented pre-buried pipes are arranged in the middle of the side pile body 3 to be removed, which facilitates the horizontal and vertical cutting of the side pile body 3 to be removed, thereby improving the construction efficiency.

优选的,各预埋管道的两端端口通过对接热熔封堵使各预埋管形成封闭管道,能够避免在钻孔桩浇筑过程中,混凝土进入预埋管道造成预埋管道堵塞,提高施工效率。Preferably, the two end ports of each pre-buried pipe are butt-connected and hot-melt sealed to form a closed pipe, which can prevent concrete from entering the pre-buried pipe during the bored pile casting process and causing blockage of the pre-buried pipe, thereby improving construction efficiency.

优选的,预埋管道为中密度聚乙烯管,直径18~22mm,壁厚1.8~2.2mm,最小弯折半径18~22cm。Preferably, the pre-buried pipeline is a medium-density polyethylene pipe with a diameter of 18 to 22 mm, a wall thickness of 1.8 to 2.2 mm, and a minimum bending radius of 18 to 22 cm.

优选的,各预埋管道位于各钻孔桩的混凝土层内部,各预埋管道的两端端口的对接处设置为外凸的凸起8,凸起8远离钢筋笼4朝向钻孔桩外侧能够使预埋管道接近钻孔桩的外表层,方便后期剔凿找出预埋管道。Preferably, each pre-buried pipe is located inside the concrete layer of each bored pile, and the butt joint of the two end ports of each pre-buried pipe is set as an outward protrusion 8. The protrusion 8 is away from the steel cage 4 toward the outside of the bored pile, which can make the pre-buried pipe close to the outer layer of the bored pile, making it convenient to find the pre-buried pipe by chiseling later.

优选的,中桩水平预埋管道5两端端口的对接处为第一凸起,边桩端部预埋管道6两端端口的对接处为第二凸起,竖向预埋管道7两端端口的对接处为第三凸起,第一凸起设置于中桩的迎土侧,第二凸起设置于边桩朝向中桩的一侧,第三凸起设置于边桩的迎土侧,开挖会开挖待拆除边桩体3的迎土侧,将第三凸起和第一凸起设置在迎土侧方便施工,割除中桩后,就能够方便操出第二凸起8,方便绳锯沿预埋管道进行切割。Preferably, the butt joint of the two end ports of the horizontal pre-buried pipe 5 of the center pile is a first protrusion, the butt joint of the two end ports of the pre-buried pipe 6 at the end of the side pile is a second protrusion, and the butt joint of the two end ports of the vertical pre-buried pipe 7 is a third protrusion. The first protrusion is arranged on the soil-facing side of the center pile, the second protrusion is arranged on the side of the side pile facing the center pile, and the third protrusion is arranged on the soil-facing side of the side pile. Excavation will excavate the soil-facing side of the side pile body 3 to be removed. The third protrusion and the first protrusion are arranged on the soil-facing side for the convenience of construction. After cutting off the center pile, the second protrusion 8 can be easily manipulated to facilitate cutting along the pre-buried pipe with a rope saw.

实施例二Embodiment 2

本实施例提供了实施例一中的围护结构的施工方法,包括如下步骤:This embodiment provides a construction method of the enclosure structure in Embodiment 1, comprising the following steps:

S1:根据地铁的结构图纸,确定待拆除围护体1和拆除边界,将地铁站出入口轮廓线顶部50cm,底部10cm,将地铁站出入口轮廓线两侧10cm的围护桩为围护结构本体的拆除边界;S1: According to the structural drawings of the subway, determine the enclosure 1 to be demolished and the demolition boundary, and take the top 50cm and bottom 10cm of the subway station entrance and exit contour line, and the 10cm retaining piles on both sides of the subway station entrance and exit contour line as the demolition boundary of the enclosure structure body;

S2:在围护结构的钢筋笼4绑扎完成后,根据拆除边界与钢筋笼4的相对位置在各钢筋笼4上安装各预埋管道并使用尼龙扎带与钢筋笼4绑扎牢固,防止管道在钢筋笼4下放过程中变形移位;S2: After the steel cage 4 of the enclosure structure is tied, the pre-buried pipes are installed on each steel cage 4 according to the relative position between the demolition boundary and the steel cage 4 and are firmly tied with the steel cage 4 using nylon tie to prevent the pipes from deforming and shifting during the lowering of the steel cage 4;

S3:将钢筋笼4放入钻孔中并浇筑混凝土形成钻孔桩,钻孔桩全部浇筑完成形成围护结构,钻孔桩桩基直径1m,间距1400mm。S3: Put the steel cage 4 into the borehole and pour concrete to form bored piles. After all the bored piles are poured, a retaining structure is formed. The bored pile foundation has a diameter of 1m and a spacing of 1400mm.

实施例三Embodiment 3

本发明还提供了实施例二中的围护结构的施工方法,包括如下步骤:The present invention also provides a construction method of the enclosure structure in the second embodiment, comprising the following steps:

S1:对待拆除围护体11迎土侧的土进行开挖,根据预埋管道的凸起8的位置凿出预埋管道,采用穿线器将切割绳穿入到预埋管道内;S1: excavate the soil on the soil side of the enclosure 11 to be removed, chisel out the pre-buried pipe according to the position of the protrusion 8 of the pre-buried pipe, and use a threader to pass the cutting rope into the pre-buried pipe;

S2:将切割绳与绳锯切割机连接,使切割绳对待拆除围护体1进行切割,不会损坏主体结构及防水、且破除面平整度容易控制。S2: Connect the cutting rope to the rope saw cutting machine so that the cutting rope can cut the enclosure 1 to be demolished without damaging the main structure and waterproofing, and the flatness of the demolished surface can be easily controlled.

S3:将切割下的待拆除围护体1通过吊机运出。S3: The cut enclosure 1 to be dismantled is transported out by a crane.

优选的,切割绳为金刚绳,便于绳锯沿预埋管道切割围护桩,金刚绳切割具有切割速度快、效率高、体积小和安全系数大的优点。Preferably, the cutting rope is a diamond rope, which facilitates the rope saw to cut the retaining piles along the pre-buried pipeline. Diamond rope cutting has the advantages of fast cutting speed, high efficiency, small size and high safety factor.

本发明中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处。综上所述,本说明书内容不应理解为对本发明的限制。The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims (9)

1. A kind of enclosure structure, which is composed of a frame, characterized by comprising the following steps:
The building enclosure comprises an enclosure body, wherein the enclosure body comprises a plurality of bored piles arranged in rows, a reinforcement cage is arranged in each bored pile, the enclosure body is provided with a dismantling boundary and an enclosure body to be dismantled, the enclosure body to be dismantled can be dismantled by cutting at the dismantling boundary, two bored piles on the outermost side of the enclosure body to be dismantled are side piles, the bored piles between the two side piles are middle piles, the part of the side piles in the enclosure body to be dismantled is the side pile body to be dismantled, and the part of the middle pile in the enclosure body to be dismantled is the middle pile body to be dismantled; and
The embedded pipelines are respectively used for penetrating the cutting ropes to cut the enclosure body to be dismantled, the top surface and the bottom surface of the middle pile body to be dismantled, the top surface and the bottom surface of the side pile body to be dismantled and the side surfaces of the side pile bodies to be dismantled away from the middle pile are all provided with embedded pipelines, the embedded pipelines arranged on the top surface and the bottom surface of the middle pile body to be dismantled are middle pile horizontal embedded pipelines, the embedded pipelines arranged on the top surface and the bottom surface of the side pile body to be dismantled are side pile end embedded pipelines, the embedded pipelines arranged on the side surfaces of the side pile body to be dismantled are vertical embedded pipelines, the middle pile horizontal embedded pipelines, the side pile end embedded pipelines and the vertical embedded pipelines are all located on the dismantling boundary, the middle pile horizontal embedded pipelines are annular and are fixedly sleeved on the outer sides of reinforcement cages of the middle pile, the two ends of the side pile end embedded pipelines comprise first outer embedded pipelines and first inner embedded pipelines, the two ends of the first inner embedded pipelines are connected and communicated with each other to form an annular shape, the first inner embedded pipelines are arranged on the top surface of the side pile body and the two sides of the vertical side pile, the first embedded pipelines are arranged on the side of the side pile body and the side of the vertical side pile body and the vertical side embedded pipelines are arranged on the two sides of the vertical side of the reinforcement cage and the side pile body and the vertical side embedded pipelines are arranged on the side of the vertical side cage and the side pile body.
2. The enclosure of claim 1, wherein: the side pile embedded type pile comprises a middle pile body, and is characterized by further comprising a plurality of side pile segmented embedded pipelines, wherein each side pile segmented embedded pipeline is arranged on the side pile body to be dismantled and positioned between the two side pile end embedded pipelines side by side, each side pile segmented embedded pipeline is parallel to the side pile end embedded pipeline, each side pile segmented embedded pipeline comprises a second outer embedded pipeline and a second inner embedded pipeline, two ends of the second inner embedded pipeline are connected with the second outer embedded pipeline and communicated to form a ring shape, each second inner embedded pipeline penetrates through a reinforcement cage of each side pile to be dismantled and is arranged on the side surface of the side pile body facing away from the middle pile, and each second outer embedded pipeline is fixedly arranged on the outer side of the reinforcement cage of each side pile.
3. The enclosure of claim 1, wherein: and the ports at the two ends of each embedded pipe are plugged by butt joint and hot melting to form a closed pipe for each embedded pipe.
4. The enclosure of claim 3, wherein: the embedded pipeline is a medium-density polyethylene pipe, the diameter is 18-22 mm, the wall thickness is 1.8-2.2 mm, and the minimum bending radius is 18-22 cm.
5. The enclosure of claim 3, wherein: each embedded pipeline is positioned in the concrete layer of each bored pile, and the butt joint of the two end ports of each embedded pipeline is provided with a convex boss.
6. The enclosure of claim 5, wherein: the butt joint department of the two end ports of the horizontal embedded pipeline of the middle pile is a first bulge, the butt joint department of the two end ports of the embedded pipeline of the side pile end is a second bulge, the butt joint department of the two end ports of the vertical embedded pipeline is a third bulge, the first bulge is arranged on the earth facing side of the middle pile, the second bulge is arranged on the side pile facing to one side of the middle pile, and the third bulge is arranged on the earth facing side of the side pile.
7. A method of constructing an enclosure of any of claims 1-6, comprising: the method comprises the following steps:
S1: determining the enclosure to be dismantled and the dismantling boundary according to a structural drawing of the subway;
s2: after the reinforcement cages of the enclosure structure are bound, installing the embedded pipelines on the reinforcement cages according to the relative positions of the dismantling boundaries and the reinforcement cages, and binding firmly;
s3: and placing the reinforcement cage into a drilled hole, pouring concrete to form the drilled pile, and completing pouring of all the drilled piles to form the enclosure structure.
8. A method of demolishing an enclosure of any one of claims 1-6, comprising: the method comprises the following steps:
S1: excavating soil on the earth facing side of the enclosure to be removed until the enclosure to be removed is exposed, chiseling the embedded pipeline according to the position of the embedded pipeline, and penetrating the cutting rope into the embedded pipeline;
S2: connecting the cutting rope with a rope saw cutting machine to enable the cutting rope to cut the enclosure to be removed;
s3: and carrying out the cut enclosure body to be removed.
9. The removal method as claimed in claim 8, wherein: the cutting rope is a diamond rope.
CN202210642771.5A 2022-06-08 2022-06-08 Enclosure structure, construction method and removal method of enclosure structure Active CN114875931B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210642771.5A CN114875931B (en) 2022-06-08 2022-06-08 Enclosure structure, construction method and removal method of enclosure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210642771.5A CN114875931B (en) 2022-06-08 2022-06-08 Enclosure structure, construction method and removal method of enclosure structure

Publications (2)

Publication Number Publication Date
CN114875931A CN114875931A (en) 2022-08-09
CN114875931B true CN114875931B (en) 2024-08-16

Family

ID=82679750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210642771.5A Active CN114875931B (en) 2022-06-08 2022-06-08 Enclosure structure, construction method and removal method of enclosure structure

Country Status (1)

Country Link
CN (1) CN114875931B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258561A (en) * 2019-06-21 2019-09-20 中铁三局集团广东建设工程有限公司 A kind of constructing device and its construction method cutting off building enclosure
CN113654423A (en) * 2021-08-31 2021-11-16 湖北工业大学 Green demolition method of pre-buried holes in reinforced concrete beams and columns by mechanical cutting and off-site blasting

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56131712A (en) * 1980-03-17 1981-10-15 Kensuke Asakura Removing method of defective concrete at upper part of pile when driving pile in site
JP3713006B2 (en) * 2002-09-24 2005-11-02 東日本旅客鉄道株式会社 Cutting method of existing pile and cutting device therefor
FR2888259B1 (en) * 2005-07-08 2007-10-12 Saipem U K Ltd INSTALLATION AND METHOD FOR CUTTING UNDERWATER STRUCTURES ENCLOSED IN THE BOTTOM OF THE SEA
JP4359701B2 (en) * 2005-08-22 2009-11-04 飛島建設株式会社 Steel pipe pile part removal method of earth retaining wall
FI20125395L (en) * 2012-04-11 2013-10-12 Motocut Oy Cutting device and method for cutting a pile
CN110145328B (en) * 2019-05-24 2021-04-09 中铁隧道局集团有限公司 Construction method for underground tunnel entering underground excavation interval tunnel door from vertical shaft
CN213653453U (en) * 2020-11-03 2021-07-09 中国冶金地质总局青岛地质勘查院 Shifting device for static crushing charge pipe of pile head in deep buried engineering
CN113338285B (en) * 2021-05-12 2023-04-14 中国铁建港航局集团有限公司 Pre-embedding dismantling method for supporting piles of offshore deep foundation pit
CN113186920A (en) * 2021-06-06 2021-07-30 化学工业岩土工程有限公司 Pile foundation pile head integral breaking structure
CN113605389B (en) * 2021-08-31 2022-08-30 中铁十六局集团第一工程有限公司 Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile
CN215596553U (en) * 2021-09-13 2022-01-21 北京建工集团有限责任公司 Fixing device capable of positioning vertical embedded pipeline

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258561A (en) * 2019-06-21 2019-09-20 中铁三局集团广东建设工程有限公司 A kind of constructing device and its construction method cutting off building enclosure
CN113654423A (en) * 2021-08-31 2021-11-16 湖北工业大学 Green demolition method of pre-buried holes in reinforced concrete beams and columns by mechanical cutting and off-site blasting

Also Published As

Publication number Publication date
CN114875931A (en) 2022-08-09

Similar Documents

Publication Publication Date Title
GB1561053A (en) Construction of concrete walls
CN105155516B (en) The method of construction drill bored concrete pile before making an overall screening underground obstacle
CN110820742A (en) Construction method for breaking underwater cast-in-place pile head
CN210368983U (en) Supporting construction that bored concrete pile and underground continuous wall combined together
CN106499199A (en) Close on the interim support replacement of subway ultra-deep foundation pit mid-board and its construction method
CN114875931B (en) Enclosure structure, construction method and removal method of enclosure structure
CN114232628A (en) Cutting hoop for integrally breaking pile head of cast-in-situ bored pile and construction method
CN104047607A (en) Construction method for lifting out shield tunneling machine under condition of envelop enclosure
CN111794243B (en) Assembled building enclosure for foundation pit and construction method thereof
CN112813969A (en) Steel pipe pile foundation and construction method thereof
CN210343347U (en) Assembled pipe jacking back wall
CN110629757A (en) A kind of SMW engineering method pile steel extraction method
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
CN110965584A (en) Access and exit earthwork excavation and passage opening concrete breaking synchronous construction method
CN216640561U (en) Novel combined type enclosure structure
CN113605389B (en) Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile
KR101049514B1 (en) Ready-made reinforced concrete pile with detachable upper pile
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN213625548U (en) Multi-combination mode ground is wall joint construction equipment even
CN212375877U (en) Biting pile construction device
CN109653193B (en) Reverse construction method for underground continuous wall
JP3091859B2 (en) Piling method for shafts with openings at the top
CN213869893U (en) Reserved structure for long-term construction of subway station end
CN113529693B (en) Construction method for penetrating pipeline through cutter-suction type corner amplitude diaphragm wall
CN221256773U (en) Construction structure for half reverse construction method of large-diameter shield tunnel originating well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant