[go: up one dir, main page]

CN115897600A - Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area - Google Patents

Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area Download PDF

Info

Publication number
CN115897600A
CN115897600A CN202211203417.9A CN202211203417A CN115897600A CN 115897600 A CN115897600 A CN 115897600A CN 202211203417 A CN202211203417 A CN 202211203417A CN 115897600 A CN115897600 A CN 115897600A
Authority
CN
China
Prior art keywords
construction
foundation pit
concrete
pile
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211203417.9A
Other languages
Chinese (zh)
Inventor
张自光
尤雪苹
王雪峰
毛瑞金
张梦晴
张�成
张猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Jianzhu University
Original Assignee
Anhui Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Jianzhu University filed Critical Anhui Jianzhu University
Priority to CN202211203417.9A priority Critical patent/CN115897600A/en
Publication of CN115897600A publication Critical patent/CN115897600A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种新建基坑紧临既有地铁车站深基坑近接区施工方法,包括新建基坑场地处理、近接区斜撑支座桩施工、共用围护桩腰梁施工、施作支座桩承台、近接区斜撑施工、近接区土方开挖、新建基坑近接区地下结构施工、近接区斜撑下方素砼回填、地下结构内部斜撑割除、支座桩用做地下结构抗拔桩及近接区回填土至设计标高等步骤。本发明通过借用现有地铁基坑围护桩,形成新基坑的围护桩,并通过设置承台‑斜撑‑腰梁的支撑结构,避免新基坑开挖对地铁工程及其他周边地下建筑的结构影响;整个支护体系在确保基坑整体稳定安全的基础上,对基坑的位移变形以及周边建筑和环境的变形影响也起到了很好的控制作用;本发明有效控制工程投资,大大缩短工期。

Figure 202211203417

The invention discloses a construction method for a new foundation pit adjacent to an existing deep foundation pit approach area of an existing subway station, which includes site treatment of a new foundation pit, construction of diagonally braced support piles in the proximity area, construction of a shared enclosure pile waist beam, and construction of supports Pile caps, oblique bracing construction in the adjacent area, earthwork excavation in the adjacent area, construction of underground structures in the adjacent area of the new foundation pit, backfilling of plain concrete under the oblique braces in the adjacent area, removal of oblique bracing inside the underground structure, and support piles used as anti-corrosion structures for underground structures. Steps such as pile extraction and backfilling of the adjacent area to the design elevation. The present invention forms the surrounding protection piles of the new foundation pit by borrowing the existing surrounding protection piles of the foundation pit of the subway, and by setting the supporting structure of the cap-slant bracing-waist beam, it avoids the impact of the excavation of the new foundation pit on the subway project and other surrounding underground The impact of the structure of the building; on the basis of ensuring the overall stability and safety of the foundation pit, the entire support system also plays a very good role in controlling the displacement deformation of the foundation pit and the deformation effects of surrounding buildings and the environment; the invention effectively controls engineering investment, Greatly shorten the construction period.

Figure 202211203417

Description

一种新建基坑紧临既有地铁车站深基坑近接区施工方法A construction method for a new foundation pit adjacent to the deep foundation pit adjacent area of an existing subway station

技术领域technical field

本发明涉及基坑围护桩施工技术领域,尤其涉及新建基坑紧临既有基坑近接区施工方法。The invention relates to the technical field of foundation pit surrounding protection pile construction, in particular to a construction method for a newly built foundation pit adjacent to an existing foundation pit.

背景技术Background technique

受城市规划土地资源受限的影响,一些新建项目必须紧邻既有地铁站进行施工,既有地铁车站基坑在开挖时会对近接区土体产生影响,使近接区土体的原始应力产生变化。同样新建项目基坑在开挖时为防止近接区受扰动的土体发生坍塌对两基坑稳定性造成影响,因此,在新建基坑开挖时必须将近接区受扰动的土体全部开挖完,并采取一定的支护措施,防止新建基坑在开始产生过大位移。对于一般的深基坑的支护方式多采用围护桩、锚索、内支撑,对于两基坑近接区的施工方式可采取在共用原有地体站基坑围护桩并施作钢支撑进行支护,保证近接区的稳定性。Affected by the limited land resources of urban planning, some new projects must be constructed in close proximity to existing subway stations. Excavation of foundation pits of existing subway stations will have an impact on the soil in the adjacent area, resulting in the original stress of the soil in the adjacent area. Variety. Similarly, when excavating the foundation pit of a new project, in order to prevent the collapse of the disturbed soil in the adjacent area from affecting the stability of the two foundation pits, it is therefore necessary to excavate all the disturbed soil in the adjacent area when excavating a new foundation pit After completion, certain support measures shall be taken to prevent excessive displacement of the new foundation pit at the beginning. For the support methods of general deep foundation pits, surrounding protection piles, anchor cables, and internal supports are mostly used. For the construction method of the adjacent area of the two foundation pits, the surrounding protection piles of the foundation pit of the shared original ground station and steel support can be used for support. protection to ensure the stability of the proximity zone.

发明内容Contents of the invention

本发明的目的是为了解决现有技术中存在的缺点,而提出的新建基坑紧临既有基坑近接区施工方法。The purpose of the present invention is to solve the shortcomings in the prior art, and proposes a construction method for a new foundation pit adjacent to an existing foundation pit approach area.

为了实现上述目的,本发明采用了如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

新建基坑紧临既有基坑近接区施工方法,包括以下步骤:The construction method of the new foundation pit adjacent to the existing foundation pit adjacent area includes the following steps:

一、新建基坑场地处理1. New foundation pit site treatment

工程因其特殊的地理位置和特定的地区影响力,使本工程从基坑支护、土方开挖到斜撑施工的各个阶段都十分重要,基坑开挖是本工程实施的第一阶段,尤为重要,根据定位桩测放出边线的各拐角点,按操作面宽度和排水沟宽度再测放出基坑的内边线或坡底线。开挖第一层土方至共用围护桩腰梁设计标高底部位置(地表以下1500mm)。Due to the special geographical location and specific regional influence of the project, all stages of the project from foundation pit support, earthwork excavation to diagonal brace construction are very important. Foundation pit excavation is the first stage of the project implementation. It is especially important to measure and release the corner points of the side line according to the positioning piles, and then measure and release the inner side line or slope bottom line of the foundation pit according to the width of the operation surface and the width of the drainage ditch. Excavate the first layer of earthwork to the bottom position of the design elevation of the waist beam of the shared enclosure pile (1500mm below the ground surface).

二、近接区斜撑支座桩施工2. Construction of diagonally braced piles in the proximity area

支座桩采用跳挖施工:先施工1、3、5、7、9号桩,再施工2、4、6、8、10号桩,以此类推跳挖钻孔施工。该支座桩顶端位置位于地表以下8750mm,桩底端位于地表以下12750mm,桩长4000mm,桩径800mm。支座桩施工完毕后会,为防止工人从支座桩洞口坠入,采用土体进行回填,待施作支座桩承台时再进行开挖。The support piles are constructed by skip-digging: first construct No. 1, 3, 5, 7 and 9 piles, and then construct No. 2, 4, 6, 8 and 10 piles, and so on. The top of the support pile is located 8750mm below the surface, the bottom of the pile is 12750mm below the surface, the pile length is 4000mm, and the pile diameter is 800mm. After the support pile construction is completed, in order to prevent workers from falling into the hole of the support pile, the soil is used for backfilling, and the excavation will be carried out when the support pile cap is constructed.

1)定位放线1) Positioning and setting out

根据建筑物定位轴线,由专职测量人员按支护桩平面图准确无误地将支护桩桩位放样到现场,现场桩位放样采用木制短桩作为支护桩桩位标识;According to the positioning axis of the building, the full-time surveyors will accurately stake out the positions of the supporting piles to the site according to the plan of the supporting piles, and the wooden short piles will be used as the identification of the supporting piles for the stakes on site;

2)桩位成孔2) Pile position into hole

桩位验收后,钻机就位并调整机身,应用钻机塔身的前后垂直标杆检查导杆,校正位置,使钻杆垂直对准桩位中心,以保证桩身垂直度偏差不得大于允许偏差;After the pile position is accepted, the drilling rig is in place and the fuselage is adjusted. The front and rear vertical benchmarks of the drilling rig tower are used to check the guide rod, and the position is corrected so that the drill rod is vertically aligned with the pile center to ensure that the vertical deviation of the pile body is not greater than the allowable deviation;

3)钢筋笼安放3) Reinforcement cage placed

为了确保钢筋笼在吊装、下放过程中不变形,在钢筋笼中每隔2m加设一道φ20焊接加强筋,加劲箍与主筋采用焊接,桩四周钢筋保护层厚度根据桩孔大小来确定,但不小于5cm;钢筋笼采用长螺旋钻机副卷扬进行吊装,钢筋笼在起吊前检查场地无高压线及障碍物,保证钢筋笼起吊安全施工,钢筋笼利用井口对接安装,钢筋笼入孔后,要牢固定位,定位标高允许误差±5cm,钢筋笼长度锚入承台的长度不小于35d;In order to ensure that the reinforcement cage is not deformed during hoisting and lowering, a φ20 welded reinforcement is added every 2m in the reinforcement cage. The reinforcement hoop and the main reinforcement are welded. Less than 5cm; the steel cage is hoisted by a long auger drilling rig auxiliary winch. Before lifting the steel cage, check that there are no high-voltage lines and obstacles on the site to ensure safe construction of the steel cage. The steel cage is installed by docking the wellhead. Positioning, the allowable error of the positioning elevation is ±5cm, and the length of the reinforcement cage anchored into the cap is not less than 35d;

4)混凝土浇筑4) Concrete pouring

灌注混凝土时,应测定混凝土塌落度,要求塌落度为16~18cm,混凝土要有良好的和易性;为保证混凝土桩身质量,灌注过程中,应不断上下串动导管,使混凝土密实。必要时,需使用振动棒进行振捣;为确保桩顶质量,灌注结束时应缓慢将导管拔出混凝土,防止形成空洞。When pouring concrete, the concrete slump should be measured, and the slump is required to be 16-18cm, and the concrete should have good workability; in order to ensure the quality of the concrete pile body, during the pouring process, the conduit should be continuously moved up and down to make the concrete dense . When necessary, vibrating rods should be used for vibration; in order to ensure the quality of the pile top, the pipe should be slowly pulled out of the concrete at the end of pouring to prevent the formation of cavities.

三、共用围护桩腰梁施工3. Construction of waist beams of shared enclosure piles

土方开挖至围檩高度时,施工斜支撑腰梁及顶力座,要求腰梁的一边壁和承台的一边壁呈平行,以便后续施作斜撑;When excavating the earthwork to the height of the purlin, the construction of the obliquely braced waist beam and the jacking seat requires that the side wall of the waist beam and the side wall of the cap be parallel to facilitate subsequent diagonal bracing;

将地铁共用围护桩上部保护层凿除,露出受力钢筋,将钢筋表面清洗干净,并将腰梁钢筋与原围护桩桩身主筋焊接,随后至模板,浇筑混凝土,进行保养;Remove the protective layer on the upper part of the subway shared retaining pile to expose the reinforced steel bars, clean the surface of the reinforced bars, weld the waist beam reinforcement with the main reinforcement of the original retaining pile body, and then pour concrete into the formwork for maintenance;

腰梁施工过程如下:The waist beam construction process is as follows:

开挖腰梁顶土方→凿除灌注桩浮浆层至桩顶设计标高→垫层混凝土→绑扎配筋→支模板→浇筑腰梁混凝土(C30)→保养;Excavate the earthwork on the top of the waist beam → chisel away the laitance layer of the cast-in-place pile to the design elevation of the pile top → cushion layer concrete → tie reinforcement → formwork support → pouring the waist beam concrete (C30) → maintenance;

四、施作支座桩承台4. Construction of pile caps

待支座桩混凝土达到设计强度时,继续开挖基坑至支座桩顶部,两深基坑近接区放坡留土,施做支座桩承台。When the concrete of the supporting pile reaches the design strength, continue to excavate the foundation pit to the top of the supporting pile, and leave soil in the adjacent area of the two deep foundation pits to make the supporting pile cap.

1)承台钢筋绑扎1) Binding of steel bars on the platform

支护桩施工完毕,绑扎前应搭设钢筋绑扎架,在其顶端预留的锚固筋上方进行绑扎承台钢筋,绑扎时先放置上层主筋,然后放置箍筋,按图纸间距绑扎时箍筋与主筋垂直绑扎,箍筋间距符合设计及规范规定;上层绑扎完成后穿下层主筋并与箍筋及时绑扎;侧向主筋穿入后逐个放置内箍筋及拉结筋并绑扎牢固,主筋搭接采用单面搭接焊,焊接后钢筋长度满足设计要求,钢筋绑扎好后及时绑扎钢筋垫块;After the construction of the support piles is completed, a steel bar binding frame should be set up before binding, and the steel bars of the cap should be bound above the anchor bars reserved at the top. When binding, the upper main bars are placed first, and then the stirrups. Binding vertically, the spacing of stirrups conforms to the design and specifications; after the upper layer is bound, pass through the main reinforcement of the lower layer and tie it with the stirrups in time; after the main reinforcement of the side is penetrated, place the inner stirrups and tie bars one by one and tie them firmly. Surface lap welding, the length of the steel bars after welding meets the design requirements, and the steel bar pads are bound in time after the steel bars are bound;

3)模板支护及混凝土浇筑3) Form support and concrete pouring

混凝土采用商品混凝土,强度等级C30,用混凝土运输车运送至施工现场,浇筑混凝土时应连续进行,如必须间歇,其间歇时间应尽量缩短,浇筑过程中要及时振捣,使用插入式振捣器应快插慢拔,插点要均匀排列,逐点移动,顺序进行,不得遗漏,做到均匀振实,移动间距不大于振捣作用半径的1.5倍(一般为30~40cm),振捣后及时用木抹子将梁面进行初次抹平,在初凝后终凝前用钢抹对梁面进行收光处理,承台浇筑完毕后,用草袋覆盖,并派专人每天浇水保养;The concrete is commercial concrete with a strength grade of C30. It is transported to the construction site by a concrete transport vehicle. The pouring of the concrete should be carried out continuously. If it must be intermittent, the intermittent time should be shortened as much as possible. During the pouring process, it should be vibrated in time and a plug-in vibrator should be used. It should be inserted quickly and pulled out slowly, and the insertion points should be evenly arranged, moved point by point, in sequence, without omission, so as to achieve uniform vibration, and the moving distance should not be greater than 1.5 times the radius of the vibration effect (generally 30-40cm). Use a wooden trowel to smooth the beam surface for the first time in time. After the initial setting and before the final setting, use a steel trowel to finish the beam surface. After the platform is poured, cover it with straw bags and send special personnel to water and maintain it every day;

4)拆模及养护4) Form removal and maintenance

混凝土浇筑完成后12小时内要及时对承台进行浇水养护,养护次数以保持表面湿润为准,24小时后即可对承台进行拆除,拆除时拆除工具不得接触混凝土,避免损坏菱角,以免影响整体观感,拆除后的模板要及时清理干净并堆放整齐,便于下次利用;Within 12 hours after the concrete pouring is completed, the caps should be watered and maintained in time. The number of maintenance is based on keeping the surface moist. The caps can be dismantled after 24 hours. Affect the overall look and feel, the removed formwork should be cleaned up in time and stacked neatly for the next use;

五、近接区斜撑施工5. Diagonal bracing construction in the proximity area

主体的钢支撑采用600×600的钢格构斜撑,钢支撑顶端焊接700×700×16的钢板进行封端;钢支撑底端设有专门的顶力座,顶力座具体是通过锚件与承台斜边壁上预埋钢筋连接,通过千斤顶在均匀施顶;钢支撑与共用围护桩腰梁采用焊接,另一端为活动支座。钢支撑预加轴力依靠两台液压千斤顶完成,千斤顶能力满足设计预加轴力的要求。千斤顶安装在预埋板406和顶力坐303之间。钢支撑安装时,腰梁、端头、千斤顶各轴线保持在同一轴线上,为确保平直,钢支撑上锁紧片应按对角顺序同时拧紧。拼装最终偏心值不大于20mm。斜撑焊死前应顶紧,当顶力达到设计的预加力,在锁紧段安装锁紧片焊死后卸下千斤顶,千斤顶预加轴力必须对称同步,保证支撑轴心受力,斜支撑焊死前,必须施加不小于400KN的预顶力;The steel support of the main body adopts a 600×600 steel lattice diagonal brace, and the top of the steel support is welded with a 700×700×16 steel plate for sealing; It is connected with the pre-embedded steel bars on the sloped side wall of the cap, and the jack is applied evenly through the jack; the steel support is welded to the waist beam of the shared enclosure pile, and the other end is a movable support. The pre-loaded axial force of the steel support is completed by two hydraulic jacks, and the capacity of the jacks meets the requirements of the designed pre-loaded axial force. The jack is installed between the embedded plate 406 and the jacking seat 303 . When the steel support is installed, the axes of the waist beam, the end and the jack are kept on the same axis. In order to ensure straightness, the locking pieces on the steel support should be tightened in diagonal order at the same time. The final eccentric value of assembly is not greater than 20mm. The diagonal brace should be tightened before welding. When the jacking force reaches the designed pre-loading force, install the locking plate on the locking section and remove the jack after welding. The pre-loaded axial force of the jack must be symmetrical and synchronous to ensure that the supporting axis is stressed. Before the oblique support is welded dead, a pre-jacking force of not less than 400KN must be applied;

六、近接区土方开挖6. Earthwork excavation in the proximity area

保留斜撑下土方,进行图书馆地下室结构施工,地下室结构施工完成后,清运保留土方。钢斜撑之间的土方采用挖掘机开挖,靠近钢斜撑部位及斜撑底部的土方采用人工挖土的方式,防止机械开挖造成斜撑失稳破坏。Retain the earthwork under the diagonal braces to carry out the construction of the basement structure of the library. After the construction of the basement structure is completed, the retained earthwork will be cleared and transported. The earthwork between the steel braces is excavated by an excavator, and the earth near the steel braces and the bottom of the braces is manually excavated to prevent mechanical excavation from causing the braces to be unstable and damaged.

七、新建基坑近接区地下结构施工7. Underground structure construction in the vicinity of the new foundation pit

地下室解构在施工时先只施工支座桩承台至共用围护桩部分的结构,绑扎侧墙及底板与侧墙交界处的钢筋并浇筑混凝土,待侧墙混凝土强度达到设计强度时,对侧墙外表面涂抹防水材料。余下部分地下室结构待钢斜撑割除完毕之后继续施工。For the deconstruction of the basement, only the structure from the bearing pile cap to the common retaining pile is constructed first, and the side wall and the steel bars at the junction of the bottom plate and the side wall are bound and concrete is poured. When the concrete strength of the side wall reaches the design strength, the opposite side Apply waterproof material to the outer surface of the wall. The rest of the basement structure will continue to be constructed after the steel diagonal braces are removed.

八、近接区斜撑下方素砼回填8. Plain concrete backfill under the diagonal braces in the adjacent area

地下室结构施工完成后,清运保留土方,割除斜支撑,进行素混凝土回填,在清运保留土方及割除斜支撑时,围护桩完全失去支撑及土方的侧压力,是否会对围护桩及地铁结构产生不利影响,如保留该部分土方,仅回填土方上部混凝土,会对围护桩起到一定保护作用;After the construction of the basement structure is completed, remove and retain the earthwork, cut off the oblique supports, and carry out plain concrete backfill. When the earthwork is removed and the oblique supports are removed, the surrounding protection piles will completely lose the support and the lateral pressure of the earthwork. Will it affect the surrounding protection piles and If the subway structure is adversely affected, if this part of the earthwork is retained and only the concrete on the upper part of the earthwork is backfilled, it will have a certain protective effect on the surrounding retaining piles;

九、地下结构内部斜撑割除及防水9. Removal and waterproofing of diagonal braces inside the underground structure

割除钢格构斜支撑后,需对斜撑穿地下室底板及外墙部分洞口进行封堵并进行防水处理,地下共计斜撑29道,会产生58个渗漏隐患点,由于地下室侧墙与共用围护桩之间采用素砼回填具有一定防水作用,只需对侧墙钢支撑割除洞口采用混凝土封堵即可。地下室底板的钢支撑割除后,先铺设止水片再浇筑混凝土垫层,在混凝土垫层上继续绑扎钢筋,浇筑混凝土,完成未施工完毕的地下室底板结构,对底板墙防水进行补强,以达到杜绝渗漏的效果,即完成全部施工。After cutting off the oblique bracing of the steel lattice, it is necessary to seal and waterproof the openings of the oblique bracing through the basement floor and outer wall. The plain concrete backfill between the retaining piles has a certain waterproof effect, and it is only necessary to use concrete to seal the opening of the steel support on the side wall. After the steel support of the basement floor is cut off, the waterproof sheet is laid first and then the concrete cushion is poured. On the concrete cushion, the steel bars are continuously bound and concrete is poured to complete the unfinished basement floor structure and reinforce the waterproofing of the floor wall to achieve Eliminate the effect of leakage, that is, complete all construction.

十、支座桩用做地下结构抗拔桩10. Bearing piles are used as uplift piles for underground structures

对面地下水较为丰富的地区,地下室结构内部钢斜撑拆除后,可凿除支座桩承台,露出受力钢筋,将受力钢筋与地下室结构底板钢筋焊接并浇筑混凝土,使得支座桩成为地下室底板的整体结构,作为地下室抗浮桩使用,大大节省了施工成本。In the area where the groundwater is relatively abundant, after removing the steel diagonal braces inside the basement structure, the bearing pile caps can be chiseled out to expose the stressed steel bars, and the stressed steel bars are welded to the basement structural bottom plate steel bars and poured with concrete, so that the bearing piles become the basement The overall structure of the bottom plate is used as an anti-floating pile in the basement, which greatly saves the construction cost.

十一、近接区回填土至设计标高。11. Backfill the adjacent area to the design elevation.

待整个地下室结构完成施工,混凝土强度达到设计标高时,回填地下土。室外基坑回填前必须对地下防水层、保护层等进行检查,发现损坏及时修补处理,将基坑底的垃圾等杂物清理干净,回填施工前在室外防水保护板上弹水平线以控制回填土的高度。When the construction of the entire basement structure is completed and the concrete strength reaches the design elevation, the underground soil shall be backfilled. Before backfilling the outdoor foundation pit, it is necessary to check the underground waterproof layer and protective layer, and repair the damage in time, clean up the garbage and other sundries at the bottom of the foundation pit, and bounce the horizontal line on the outdoor waterproof protection plate before backfilling to control the backfill soil. the height of.

优选地,步骤一的施工工序为:场地平整→基坑定位→桩位放线→支护桩施工→压密注浆→腰梁施工→砌砖拱挡土墙施工→土方分层挖运→土钉→挂钢筋网片→喷锚→养护。Preferably, the construction process of step 1 is: site leveling → foundation pit positioning → pile position setting out → support pile construction → compaction grouting → waist beam construction → brick arch retaining wall construction → earthwork layered excavation → Soil nailing→hanging steel mesh→spraying anchor→maintenance.

优选地,步骤一中的砂浆供应与砌筑操作具体为:支护桩砼采用商品砼C30,砂浆采用现场人工拌制,砌筑。Preferably, the mortar supply and masonry operations in Step 1 are as follows: commercial concrete C30 is used for the supporting pile concrete, the mortar is manually mixed on site, and the masonry is constructed.

优选地,步骤一中的桩基施工:采用钻孔灌注施工,下吊钢筋笼,场内土石方转运用挖机进行,外运采用自卸汽车。Preferably, the pile foundation construction in step 1: drilling and grouting construction is adopted, steel cages are hoisted down, earth and stones are transferred in the site by excavators, and dump trucks are used for external transportation.

优选地,步骤二中,钻杆下钻到预定深度,现场施工技术人员根据地质勘察报告以及实际钻孔出土观察分析,是否达到设计要求的土层;如在施工中发现长螺旋干成孔无法施工,将采用长螺旋后置钢筋笼施工方法。Preferably, in step 2, the drill pipe is drilled to a predetermined depth, and the on-site construction technicians check whether the soil layer required by the design is reached according to the geological survey report and the actual drilling unearthed observation analysis; The construction will adopt the construction method of long spiral post reinforcement cage.

优选地,步骤二中,开钻前,封住钻头阀门,使钻杆向下移动至钻头触及地面时,开动钻机旋动钻头;一般应先慢后快,在成孔过程中如发现钻杆摇晃或难钻时,应停机或放慢进尺,遇到障碍物应停止钻进,分析原因,禁止强行钻进。Preferably, in step 2, before drilling, the valve of the drill bit is sealed, and the drill pipe is moved down until the drill bit touches the ground, and the drill rig is started to rotate the drill bit; generally, it should be slow first and then fast. When it is shaking or difficult to drill, stop the machine or slow down the footage, stop drilling when encountering obstacles, analyze the reasons, and prohibit forced drilling.

优选地,步骤二中,砼垫块做的保护层靠孔壁一面做成圆弧形,一般竖向每间隔2m左右布置一道,每道沿圆周对称布置四块。Preferably, in step 2, the protective layer made of concrete pads is made into an arc shape on the side of the hole wall, generally arranged vertically at intervals of about 2m, and each row is symmetrically arranged with four blocks along the circumference.

优选地,砼垫块也可做成圆柱形,中有孔能穿在箍筋上。Preferably, the concrete spacer can also be made into a cylindrical shape, and there are holes in the middle to be worn on the stirrups.

优选地,步骤三中,安放钢筋时,由测量员事先在垫层上放线,钢筋笼紧贴线进行安放,水平误差不得超过3cm,垂直误差不得超过2cm,安放好的钢筋观感应平直。Preferably, in step 3, when placing the steel bars, the surveyor should lay out the wires on the cushion in advance, and the steel cages should be placed close to the wires. The horizontal error should not exceed 3cm, and the vertical error should not exceed 2cm. The installed steel bars should look straight .

优选地,步骤三中,混凝土浇筑前应将模板内的垃圾、泥土等杂物及钢筋上的油污清除干净,并检查钢筋的水泥砂浆垫块是否垫好。Preferably, in step 3, before pouring concrete, the rubbish, soil and other sundries in the formwork and oil stains on the steel bars should be removed, and it is checked whether the cement mortar pads of the steel bars are well placed.

与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:

1.本发明通过借用现有地铁基坑围护桩,形成新基坑的围护桩,并通过设置承台-斜撑-腰梁的支撑结构,避免新基坑开挖对地铁工程及其他周边地下建筑的结构影响。1. The present invention forms the surrounding protection piles of the new foundation pit by borrowing the surrounding protection piles of the existing subway foundation pit, and avoids the impact of the excavation of the new foundation pit on the subway project and others by setting the supporting structure of the cap-slant brace-waist beam. Structural influence of surrounding underground buildings.

2.本发明有效控制工程投资,大大缩短工期。由于施工场地有限,本支护方案的出发点是尽量减小基坑开挖对周边建筑及环境的影响。使得整个支护体系在确保基坑整体稳定安全的基础上,对基坑的位移变形以及周边建筑和环境的变形影响也起到了很好的控制作用,同时也兼顾了经济性。2. The invention effectively controls project investment and greatly shortens the construction period. Due to the limited construction site, the starting point of this support plan is to minimize the impact of foundation pit excavation on surrounding buildings and the environment. On the basis of ensuring the overall stability and safety of the foundation pit, the entire support system also plays a good role in controlling the displacement deformation of the foundation pit and the deformation effects of surrounding buildings and the environment, while also taking into account the economy.

附图说明Description of drawings

图1为本发明提出的新建基坑紧临既有基坑近接区施工方法的流程图;Fig. 1 is the flow chart of the new foundation pit that the present invention proposes next to the existing foundation pit approach area construction method;

图2为本发明的施工方法中刻槽安装斜撑工序的结构图;Fig. 2 is the structural diagram of groove installation diagonal brace operation in the construction method of the present invention;

图3为本发明的施工方法中土方开挖到底工序的结构图;Fig. 3 is the structural diagram of earthwork excavation to the bottom process in the construction method of the present invention;

图4为本发明的施工方法中回填素混凝土工序的结构图;Fig. 4 is the structural diagram of backfill plain concrete operation in construction method of the present invention;

图5为本发明中承台的箍筋(梯形)的结构图;Fig. 5 is the structural diagram of the stirrup (trapezoidal) of the platform in the present invention;

图6为本发明中承台的主筋的结构图;Fig. 6 is the structural diagram of the main reinforcement of the platform in the present invention;

图7为本发明中斜撑的截面结构图;Fig. 7 is a cross-sectional structure diagram of a diagonal brace in the present invention;

图8为本发明中斜撑与腰梁的连接结构图;Fig. 8 is a connection structure diagram of the diagonal brace and the waist beam in the present invention;

图9为本发明中斜撑与承台的连接结构图。Fig. 9 is a structural diagram of the connection between the brace and the cap in the present invention.

图中:地铁基坑围护桩1、腰梁2、预埋板A201、斜撑3、钢支撑301、钢板302、顶力座303、承台4、井字状主筋401、方形封闭箍402、纵向配筋403、梯形封闭箍404、横向配筋405、预埋板B406、预应力筋407、锚件408承台、支护桩5、地下室结构6。In the figure: protection pile 1 for subway foundation pit, waist beam 2, embedded plate A201, diagonal brace 3, steel support 301, steel plate 302, jacking seat 303, bearing platform 4, well-shaped main reinforcement 401, square closed hoop 402 , longitudinal reinforcement 403, trapezoidal closed hoop 404, transverse reinforcement 405, embedded plate B406, prestressed tendon 407, anchor 408 cap, support pile 5, basement structure 6.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention.

本项目:合肥市中心图书馆位于祁门路与翡翠路交口,西侧紧邻翡翠路(地铁三号线),南侧紧邻祁门路(地铁四号线),该处是投入运营后的三四号线的交汇点及换乘点。根据基坑支护设计图纸,图书馆基坑开挖及基坑支护过程中将共用地铁项目原有围护桩,为防止共用围护桩向新开挖基坑一侧倾斜,故提出以下施工方法,参照图1。This project: Hefei Central Library is located at the intersection of Qimen Road and Feicui Road. Line intersections and transfer points. According to the foundation pit support design drawings, the original enclosure piles of the subway project will be shared during the excavation and foundation pit support of the library. In order to prevent the shared enclosure piles from tilting to the side of the newly excavated foundation pit, the following is proposed Construction method, refer to Figure 1.

1.施工斜撑支座桩,参照图2:1. Construction of diagonal support piles, refer to Figure 2:

1.1施工准备1.1 Construction preparation

(1)正式进场前应对整套施工设备进行检查,保证设备状态良好,禁止带故障设备进场。协助甲方作好与支护桩施工相关的水、电管线布置工作,保证进场后可立即投入施工。施工现场内道路、基坑坡道应符合设备运输车辆和汽车吊的行驶要求,保证运输安全。(1) The entire set of construction equipment should be inspected before officially entering the site to ensure that the equipment is in good condition, and it is forbidden to enter the site with faulty equipment. Assist Party A in the layout of water and electricity pipelines related to the construction of support piles, and ensure that they can be put into construction immediately after entering the site. The roads and foundation pit ramps on the construction site should meet the driving requirements of equipment transport vehicles and truck cranes to ensure transportation safety.

(2)设备组装时应设立隔离区,专人指挥,严格按程序组装,非安装人员不得在组装区域内,以杜绝安全事故。(2) When the equipment is assembled, an isolation area should be set up, commanded by a special person, and assembled in strict accordance with the procedures. Non-installation personnel are not allowed in the assembly area to prevent safety accidents.

(3)安排材料进场,按要求进行材料复检和混凝土配比试验。(3) Arrange materials to enter the site, and conduct material re-inspection and concrete proportioning test as required.

(4)开工前进行质量、安全技术交底,并填写《技术交底记录》。(4) Make quality and safety technical disclosure before starting construction, and fill in the "Technical Disclosure Record".

1.2定位放线1.2 Positioning and setting out

建设单位提供建筑物定位轴线后,双方应共同进行核查,双方在《交接检查记录》签字确认。根据建设单位提供的建筑物定位轴线,由专职测量人员按支护桩平面图准确无误地将支护桩桩位放样到现场。现场桩位放样采用木制短桩作为支护桩桩位标识。After the construction unit provides the positioning axis of the building, both parties should conduct a joint inspection, and both parties should sign the "Handover Inspection Record" for confirmation. According to the building positioning axis provided by the construction unit, the full-time surveyors accurately set out the positions of the support piles to the site according to the plan of the support piles. On-site pile position setting out uses wooden short piles as the identification of support pile positions.

经建设单位、监理单位及设计人员共同检验桩位合格并签字后,可进行下道工序。After the construction unit, the supervisory unit and the designer jointly inspect the pile position and sign it, the next process can be carried out.

1.3钻孔1.3 Drilling

桩位验收后,钻机就位并调整机身,应用钻机塔身的前后垂直标杆检查导杆,校正位置,使钻杆垂直对准桩位中心,以保证桩身垂直度偏差不得大于允许偏差。After the pile position is accepted, the drilling rig is in place and the fuselage is adjusted. The front and rear vertical benchmarks of the drilling rig tower are used to check the guide rod, and the position is corrected so that the drill rod is vertically aligned with the center of the pile position to ensure that the vertical deviation of the pile body is not greater than the allowable deviation.

开钻前,封住钻头阀门,使钻杆向下移动至钻头触及地面时,开动钻机旋动钻头。一般应先慢后快,在成孔过程中如发现钻杆摇晃或难钻时,应停机或放慢进尺,遇到障碍物应停止钻进,分析原因,禁止强行钻进。Before drilling, seal the drill bit valve, move the drill pipe down until the drill bit touches the ground, and start the drilling rig to rotate the drill bit. Generally, it should be slow first and then fast. If the drill pipe is found to be shaking or difficult to drill during the hole forming process, stop the machine or slow down the footage. Stop drilling when encountering obstacles, analyze the reasons, and prohibit forced drilling.

根据设计桩长,确定钻孔深度并在钻机塔身相应位置作醒目标注,作为施工时控制桩长的依据,当动力头底面到达标志时,桩长即满足设计要求。According to the design pile length, determine the drilling depth and make eye-catching notes on the corresponding position of the drilling rig tower, as the basis for controlling the pile length during construction. When the bottom surface of the power head reaches the mark, the pile length meets the design requirements.

钻杆下钻到预定深度,现场施工技术人员根据地质勘察报告以及实际钻孔出土观察分析,是否达到设计要求的土层。如遇特殊地质情况,应由支护桩设计人员根据图纸与现场地质实际情况综合确定,并及时通知监理。The drill pipe is drilled to the predetermined depth, and the on-site construction technicians analyze whether the soil layer required by the design is met according to the geological survey report and the observation and analysis of the actual unearthed holes. In case of special geological conditions, the designer of the support pile should comprehensively determine it according to the drawings and the actual geological conditions on site, and notify the supervisor in time.

在施工过程中,应及时、准确地填写《支护桩施工记录》。如在施工中发现长螺旋干成孔无法施工,将采用长螺旋后置钢筋笼施工方法。During the construction process, the "Record of Supporting Pile Construction" should be filled in timely and accurately. If it is found during construction that the long spiral can not be constructed through dry hole formation, the construction method of long spiral post reinforcement cage will be adopted.

1.4钢筋笼制作、安装1.4 Manufacture and installation of reinforcement cage

(1)钢筋笼制作(1) Fabrication of reinforcement cage

a)为了确保钢筋笼在吊装、下放过程中不变形,在钢筋笼中每隔2m加设一道φ20焊接加强筋,加劲箍与主筋采用焊接,桩四周钢筋保护层厚度根据桩孔大小来确定,但不小于5cm。a) In order to ensure that the reinforcement cage does not deform during hoisting and lowering, a φ20 welded reinforcement is added every 2m in the reinforcement cage. The reinforcement hoop and the main reinforcement are welded. The thickness of the reinforcement protection layer around the pile is determined according to the size of the pile hole. But not less than 5cm.

b)钢筋的种类、型号及尺寸规格应符合设计要求,如有代换应按规范要求代换,并经设计、监理签证,并作好计录。b) The types, models and dimensions of steel bars should meet the design requirements. If there is any replacement, it should be replaced according to the specification requirements, and the design and supervision should be approved and recorded.

c)钢筋笼绑扎顺序:先将主筋等间距布置好,待固定住加劲箍后,再按规定的间距安设箍筋。箍筋、加劲箍、主筋之间的接点采用电弧焊接固定。c) Binding sequence of reinforcement cage: first arrange the main reinforcement at equal intervals, and then install the stirrups according to the specified spacing after the stiffening hoops are fixed. The joints between stirrups, stiffening stirrups and main bars are fixed by arc welding.

d)钢筋笼外侧需设混凝土垫块或采用其它有效措施,以确保钢筋保护层的厚度。主筋保护层厚度应≥50mm,承台底部保护层厚度≥100mm。d) Concrete pads or other effective measures shall be adopted on the outside of the reinforcement cage to ensure the thickness of the reinforcement protection layer. The thickness of the protective layer of the main reinforcement should be ≥ 50mm, and the thickness of the protective layer at the bottom of the platform cap should be ≥ 100mm.

(2)钢筋笼堆放(2) Steel cage stacking

a)钢筋笼制作场地可根据现场的实际情况确定,但必须在塔吊覆盖范围内,以便用于钢筋笼的堆放。a) The production site of the reinforcement cage can be determined according to the actual situation of the site, but it must be within the coverage of the tower crane so as to be used for stacking the reinforcement cage.

b)钢筋笼堆放应按安装顺序、先安装的堆放在上层,后安装的堆放要下层,最多只能堆放两层。b) Reinforcement cages should be stacked in the order of installation. Those installed first should be stacked on the upper layer, and those installed later should be stacked on the lower layer. Only two layers can be stacked at most.

c)堆放下层钢筋笼时,应用块石将钢筋笼的侧面垫稳,以防止发生滚动。c) When stacking the reinforcement cage on the lower floor, the sides of the reinforcement cage should be padded with stones to prevent rolling.

(3)钢筋笼就位安装(3) Install the reinforcement cage in place

a)钢筋笼采用长螺旋钻机副卷扬进行吊装,长螺旋钻机副卷扬拉力为20kN(2T),本工程最长桩位钻孔灌注桩Z1,有效桩长15m,单桩重量0.932T,副卷扬机满足其起吊重量。钢筋笼在起吊前检查场地无高压线及障碍物,保证钢筋笼起吊安全施工,钢筋笼利用井口对接安装,钢筋笼入孔后,要牢固定位,定位标高允许误差±5cm,钢筋笼长度锚入承台的长度不小于35d。a) The steel cage is hoisted by the auxiliary winch of the long auger drilling rig. The pulling force of the auxiliary winch of the long auger drilling rig is 20kN (2T). The longest pile position of this project is Z1, the effective pile length is 15m, and the weight of a single pile is 0.932T. The auxiliary hoist meets its lifting weight. Before hoisting the steel cage, check that there are no high-voltage lines and obstacles on the site to ensure the safe construction of the steel cage. The steel cage is installed by docking the wellhead. The length of the platform is not less than 35d.

b、保护层b. Protective layer

①在钢筋笼上下端及中部每隔一定距离(一般2m左右)于同一截面上对称设置四个钢筋“耳环”,钢筋直径一般为10~12mm。①At the upper and lower ends of the reinforcement cage and in the middle, set four steel bar “earrings” symmetrically on the same section at a certain distance (generally about 2m), and the diameter of the steel bar is generally 10-12mm.

②用砼垫块做保护层。靠孔壁一面做成圆弧形,一般竖向每间隔2m左右布置一道,每道沿圆周对称布置四块;砼垫块也可做成圆柱形,中有孔能穿在箍筋上。②Use concrete blocks as protective layer. The side close to the hole wall is made into an arc shape, generally arranged vertically at intervals of about 2m, and each row is symmetrically arranged with four pieces along the circumference; the concrete spacer can also be made into a cylindrical shape, and there are holes in the middle that can be worn on the stirrups.

1.5混凝土浇筑、支护桩检测1.5 Concrete pouring and support pile detection

a)干作业成孔验收合格后,应在1小时内采用导管作为溜槽进行混凝土灌注。导管底距离孔底距离1m左右。a) After the acceptance of the hole formed by the dry operation, the concrete should be poured within 1 hour using the conduit as the chute. The distance between the bottom of the conduit and the bottom of the hole is about 1m.

b)灌注混凝土时,应测定混凝土塌落度,要求塌落度为16~18cm,混凝土要有良好的和易性。b) When pouring concrete, the concrete slump should be measured, and the slump is required to be 16-18cm, and the concrete must have good workability.

c)为保证混凝土桩身质量,灌注过程中,应不断上下串动导管,使混凝土密实。必要时,需使用振动棒进行振捣。c) In order to ensure the quality of the concrete pile body, during the pouring process, the conduit should be continuously moved up and down to make the concrete dense. Vibrate with a vibrator if necessary.

d)为确保桩顶质量,灌注结束时应缓慢将导管拔出混凝土,防止形成空洞。d) In order to ensure the quality of the pile top, the conduit should be slowly pulled out of the concrete at the end of pouring to prevent the formation of voids.

支护桩施工完毕,养护龄期达至强度至70%,进行支护桩完整性检测,设计图纸要求检测桩数不小于支护桩总数量的20%,且不得少于5根,现场要求支护桩完整性检测按100%检测,保证施工安全。检测合格后方可进行下道工序承台施工。After the construction of the support piles is completed, the maintenance age reaches 70% of the strength, and the integrity of the support piles is tested. The design drawings require that the number of test piles should not be less than 20% of the total number of support piles, and not less than 5. The site requires The integrity of the support piles is tested at 100% to ensure construction safety. Only after passing the inspection can the next process cap platform construction be carried out.

2.施工斜撑支座承台,参照5和6,承台4一侧由井字状主筋401,主筋401四周焊接有方形封闭箍402,方形封闭箍402内侧绑扎有纵向配筋403,承台4另一侧内部形成梯形封闭箍404,梯形封闭箍404内侧绑扎有横向配筋405,形成的钢筋笼与支护桩5顶端钢筋绑扎,最后浇注成承台4;2. For the construction of the oblique support bearing platform, refer to 5 and 6. One side of the platform 4 is composed of a well-shaped main reinforcement 401, and the main reinforcement 401 is welded with a square closed hoop 402. The inner side of the square closed hoop 402 is bound with a longitudinal reinforcement 403. 4. A trapezoidal closed hoop 404 is formed inside the other side, and the inner side of the trapezoidal closed hoop 404 is bound with transverse reinforcement 405, and the formed steel cage is tied to the top reinforcement of the support pile 5, and finally cast into the cap 4;

2.1承台施工艺2.1 Platform construction technology

将地铁共用围护桩上部保护层凿除,露出受力钢筋,将钢筋表面清洗干净,并将腰梁钢筋与原围护桩桩身主筋焊接,随后至模板,浇筑混凝土,进行保养。Cut off the upper protective layer of the subway shared retaining piles to expose the stressed steel bars, clean the surface of the steel bars, weld the waist beam reinforcements to the main bars of the original guard piles, and then pour concrete into the formwork for maintenance.

开挖承台顶土方→凿除灌注桩浮浆层至桩顶设计标高→垫层混凝土→绑扎配筋→支模板→浇筑承台混凝土(C30)→保养。Excavate the earthwork on the top of the cap → chisel away the laitance layer of the pouring pile to the design elevation of the pile top → cushion concrete → tie reinforcement → support the formwork → pour the cap concrete (C30) → maintenance.

2.2施工准备2.2 Construction preparation

1)基槽土已开挖至设计标高,桩间土挖除干净。1) The foundation trench soil has been excavated to the design elevation, and the soil between the piles has been excavated clean.

2)用水准仪在桩身标注出桩顶标高位置,并用红漆进行标记。2) Use a level to mark the elevation of the pile top on the pile body, and mark it with red paint.

2.3施工注意事项2.3 Precautions for construction

1)机械使用时应检查并确认电动机、电缆线等均正常,保护接地装置良好,防护装置安全有效后,方可启动机械。1) When using the machine, check and confirm that the motor, cables, etc. are normal, the protective grounding device is in good condition, and the protective device is safe and effective before starting the machine.

2)在进行桩头破除过程中,施工人员应配备相应的劳动保护用品,防止混凝土碎屑飞溅对施工人员造成伤害;与施工无关人员不得接近施工现场。2) During the pile head demolition process, construction personnel should be equipped with corresponding labor protection articles to prevent concrete debris from splashing and causing harm to construction personnel; personnel not related to construction should not approach the construction site.

3)桩头吊离时应用钢丝绳捆扎牢固,待捆扎人员撤离后方可起吊。3) When the pile head is hoisted away, the steel wire rope should be used to bind it firmly, and it can only be hoisted after the tying personnel evacuate.

2.4承台钢筋绑扎2.4 Binding of steel bars for caps

2.4.1主要材料及机具2.4.1 Main materials and tools

钢筋:应有出厂合格证,按规定作力学性能复试,待检测合格后方可投入使用。钢筋应无老锈及油污。Reinforcement: There should be a certificate of conformity from the factory, and a retest of mechanical properties shall be carried out according to the regulations, and it can be put into use only after passing the test. Steel bars should be free from old rust and oil stains.

铁丝:采用20~22号铁丝(火烧丝)或镀锌铁丝(铅丝);Iron wire: No. 20-22 iron wire (fired wire) or galvanized iron wire (lead wire);

混凝土保护层:砂浆垫块Concrete Cover: Mortar Pads

工具:钢筋钩子、撬棍、钢筋扳子、绑扎架、钢丝刷子、手推车、粉笔,尺子等。Tools: rebar hooks, crowbars, rebar spanners, lashing frames, wire brushes, trolleys, chalk, rulers, etc.

2.4.2钢筋加工2.4.2 Steel bar processing

对照图纸正确选择钢筋级别、规格,进行下料加工。纵向筋的接长应优先采用焊接,d≤20的钢筋允许采用搭接(d为钢筋直径),搭接区段长度≥0.7L,且不应小于200mm,同一连接区段内纵向钢筋搭接接头面积百分率应≤50%。正式焊接前先进行试焊,合格后方可进行批量焊接。钢筋搭接区错开,相临两个接头间距不小于1m。同一截面主筋搭接根数不超过钢筋总数的25%,并错开阳角1m以上。盘圆应调直后方可下料加工箍筋,下料尺寸严格按照图纸尺寸进行。箍筋加工应由熟练的工人进行,加工过程中应经常核对加工尺寸,避免因误差过大造成的无法使用。Correctly select the steel bar level and specification according to the drawings, and carry out blanking processing. The length of the longitudinal reinforcement should be preferentially welded, and the reinforcement with d≤20 is allowed to be overlapped (d is the diameter of the reinforcement), and the length of the overlapping section is ≥0.7L, and should not be less than 200mm. The joint area percentage should be ≤ 50%. Trial welding is carried out before formal welding, and batch welding can only be carried out after passing the test. The overlapping areas of steel bars are staggered, and the distance between two adjacent joints is not less than 1m. The number of overlapping main reinforcements in the same section shall not exceed 25% of the total number of reinforcements, and the external angle shall be staggered by more than 1m. The circle should be straightened before blanking can be used to process stirrups, and the blanking size should be strictly in accordance with the drawing size. The processing of stirrups should be carried out by skilled workers, and the processing dimensions should be checked frequently during the processing to avoid unusability due to excessive errors.

2.4.3钢筋绑扎2.4.3 Binding of steel bars

绑扎前应搭设钢筋绑扎架,在灌注桩锚固筋上方进行绑扎,以提高效率。绑扎时先放置承台上层主筋,然后放置箍筋。按图纸间距绑扎时箍筋与主筋垂直绑扎,箍筋间距符合设计及规范规定;上层绑扎完成后穿承台下层主筋并与箍筋及时绑扎;侧向主筋穿入后逐个放置内箍筋及拉结筋并绑扎牢固。主筋搭接采用单面搭接焊,焊接后钢筋长度满足设计要求。钢筋绑扎好后及时绑扎钢筋垫块。Before binding, a reinforcement binding frame should be set up, and binding should be carried out above the anchor bars of cast-in-place piles to improve efficiency. When binding, place the upper main reinforcement of the cap first, and then place the stirrups. When binding according to the spacing of the drawings, the stirrups and the main reinforcement are bound vertically, and the spacing of the stirrups meets the design and specification requirements; after the upper layer is bound, the main reinforcement of the lower layer of the cap is pierced and tied with the stirrups in time; Tie the tendons and tie them securely. The lap of the main reinforcement adopts single-sided lap welding, and the length of the steel bar after welding meets the design requirements. After the steel bars are bound, tie the steel bar pads in time.

2.5承台模板支设2.5 Cap formwork support

先在加工区按设计要求配好承台侧模板2副,在每两桩之间打入1.2m长入土深度500mm的48*3钢管,将配制好的模板放入钢管内侧,接头处用木板连接好,接头内侧接缝处用胶带粘贴以防漏浆,同时垫好保护层垫块,确认钢筋等全部绑扎完毕、垫块垫好后,用横向钢管将桩间钢管用扣件连接,并在距承台顶标高下150mm处用48*3钢管顺模板边横向连接、加强与立柱连接,全部安装好后用斜撑将立柱加固。First prepare 2 sets of cap side formwork in the processing area according to the design requirements, drive 1.2m long 48*3 steel pipes with a depth of 500mm into the soil between every two piles, put the prepared formwork inside the steel pipe, and use wooden boards at the joints After the connection is completed, the inner seam of the joint is pasted with adhesive tape to prevent slurry leakage, and the protective layer pads are placed at the same time. After confirming that all the steel bars have been bound and the pads are well placed, use horizontal steel pipes to connect the steel pipes between the piles with fasteners, and Use 48*3 steel pipes to horizontally connect along the side of the formwork at a place 150mm below the elevation of the cap platform, and strengthen the connection with the columns. After all installations, use diagonal braces to reinforce the columns.

2.6承台混凝土浇筑2.6 Pouring of platform concrete

浇筑前应将模板内的垃圾、泥土等杂物及钢筋上的油污清除干净,并检查钢筋的水泥砂浆垫块是否垫好。Before pouring, the garbage, soil and other sundries in the formwork and the oil stains on the steel bars should be removed, and the cement mortar pads of the steel bars should be checked to see if they are well placed.

混凝土采用商品混凝土,强度等级C30,用混凝土运输车运送至施工现场。浇筑混凝土时应连续进行,如必须间歇,其间歇时间应尽量缩短。浇筑过程中要及时振捣,使用插入式振捣器应快插慢拔,插点要均匀排列,逐点移动,顺序进行,不得遗漏,做到均匀振实。移动间距不大于振捣作用半径的1.5倍(一般为30~40cm)。振捣后及时用木抹子将梁面进行初次抹平,在初凝后终凝前用钢抹对梁面进行收光处理,承台浇筑完毕后,用草袋覆盖,并派专人每天浇水保养。Concrete is commercially available concrete with a strength grade of C30, which will be transported to the construction site with a concrete truck. When pouring concrete, it should be carried out continuously. If it must be intermittent, the intermittent time should be shortened as much as possible. During the pouring process, it is necessary to vibrate in time. When using a plug-in vibrator, it should be inserted quickly and slowly. The moving distance is not greater than 1.5 times of the vibration radius (generally 30-40cm). After vibrating, use a wooden trowel to smooth the beam surface for the first time in time. After the initial setting and before the final setting, use a steel trowel to finish the beam surface. water maintenance.

2.7承台拆模及养护2.7 Formwork removal and maintenance of caps

混凝土浇筑完成后12小时内要及时对梁面进行浇水养护,养护次数以保持承台表面湿润为准。24小时后即可对承台侧模板进行拆除。拆除时拆除工具不得接触混凝土,避免损坏承台菱角,以免影响整体观感。拆除后的模板要及时清理干净并堆放整齐,便于下次利用。Within 12 hours after the concrete pouring is completed, the beam surface should be watered and maintained in time, and the maintenance times should be based on keeping the surface of the cap platform moist. After 24 hours, the side formwork of the platform cap can be removed. During demolition, the demolition tool shall not touch the concrete, so as to avoid damage to the water chestnut of the bearing platform, so as not to affect the overall appearance. The dismantled formwork should be cleaned up in time and stacked neatly for the next use.

3.刻槽安装斜撑,参照图2、7-9,斜撑3由主体的钢支撑301、顶端的钢板302及底端的顶力座303组成,钢支撑301为焊接而成的格构柱;3. Slant braces are installed with grooves, referring to Figure 2, 7-9, the braces 3 are composed of a steel support 301 at the main body, a steel plate 302 at the top and a jacking seat 303 at the bottom, and the steel support 301 is a welded lattice column ;

腰梁2靠近钢支撑301的一侧面经过凿毛,露出预埋板A201且与钢板302满焊连接;The side of the waist beam 2 close to the steel support 301 is chiseled, exposing the embedded plate A201 and fully welded with the steel plate 302;

承台4靠近钢支撑301的一侧面经过凿毛,露出预埋板B406和预应力筋(407),预应力筋(407)穿过顶力座303,顶力座303的一块板与预埋板B406满焊连接,预应力筋(407)张拉后通过锚件408与顶力座303的另一块板锁紧。The side of the platform 4 close to the steel support 301 has been chiseled to expose the pre-embedded plate B406 and the prestressed tendons (407), the prestressed tendons (407) pass through the jacking seat 303, and a plate of the jacking seat 303 is connected to the pre-embedded The plate B406 is fully welded and connected, and the prestressed tendons (407) are stretched and locked with the other plate of the jacking seat 303 through the anchor 408.

土方开挖至围檩高度时,施工斜支撑腰梁及支座,在保留土方上刻槽设置内斜撑。When the earthwork is excavated to the height of the purlins, the waist beams and supports shall be constructed obliquely, and internal oblique braces shall be set on the retained earthwork.

1)钢支撑采用Q235B钢,焊接节点处的焊缝均为满焊,焊缝高度hf≥8,并应符合设计及有关规范要求;1) The steel support is made of Q235B steel, the welds at the welding joints are all fully welded, the weld height hf≥8, and shall meet the requirements of the design and relevant specifications;

2)斜撑位置根据平面图布置,现场须复核,应避开主体结构梁柱等;2) The positions of the diagonal braces are arranged according to the plan, which must be reviewed on site, and beams and columns of the main structure should be avoided;

3)斜撑施工时剖面图中土方必须保留,直到斜撑施工完成方可分层分段挖除,斜撑施工应隔一个施工一个,土方挖开后及时施工斜撑,暴露时间不得超过12小时;3) The earthwork in the cross-section must be retained during the construction of the diagonal braces, and the excavation can be layered and segmented until the construction of the diagonal braces is completed. The diagonal braces should be constructed one by one. Hour;

4)钢格构斜撑穿过主体结构底板、侧墙的部位,可在底板、侧墙处设置一道或多道止水板,止水板的道数根据基础底板、侧墙的防水要求确定。各单肢角钢上的止水板若重叠时应相互错开;4) Where steel lattice braces pass through the bottom plate and side walls of the main structure, one or more water stop plates can be installed at the bottom plate and side walls, and the number of water stop plates is determined according to the waterproof requirements of the foundation bottom plate and side walls . If the water-stop plates on each single-leg angle steel overlap, they should be staggered from each other;

5)地下室基坑回填过以后方可割除地下室内部的钢格构斜撑;5) After the foundation pit of the basement is backfilled, the steel lattice braces inside the basement can be cut off;

6)斜撑焊死前应顶紧。6) The diagonal brace should be tightened before it is welded to death.

斜撑顶紧施工:钢支撑的端部设有专门的顶力座,用千斤顶在均匀施顶。当顶力达到设计的预加力,再锁紧段安装锁紧片焊死后卸下千斤顶。千斤顶预加轴力必须对称同步,保证支撑轴心受力。斜支撑焊死前,必须施加不小于400KN的预顶力。Diagonal brace jacking construction: There is a special jacking seat at the end of the steel brace, and the jacking is applied evenly with a jack. When the jacking force reaches the designed pre-stressing force, install the locking piece on the locking section and weld it dead, then remove the jack. The pre-loaded axial force of the jack must be symmetrical and synchronous to ensure the force on the supporting axis. Before the oblique support is welded, a pre-jacking force of not less than 400KN must be applied.

4.土方开挖到底,参照图3,4. Excavate the earthwork to the bottom, refer to Figure 3,

保留斜撑下土方,进行图书馆地下室结构施工。地下室结构施工完成后,清运保留土方。Keep the earthwork under the diagonal braces, and carry out the construction of the basement structure of the library. After the construction of the basement structure is completed, the retained earth shall be cleared and transported.

5.回填素混凝土,参照图4,5. Backfill plain concrete, refer to Figure 4,

保留斜撑下土方,进行图书馆地下室结构施工。地下室结构施工完成后,清运保留土方,割除斜支撑,进行素混凝土回填。在清运保留土方及割除斜支撑时,围护桩完全失去支撑及土方的侧压力,是否会对围护桩及地铁结构产生不利影响,如保留该部分土方,仅回填土方上部混凝土,会对围护桩起到一定保护作用,研究该方案是否可行。Keep the earthwork under the diagonal braces, and carry out the construction of the basement structure of the library. After the construction of the basement structure is completed, remove and retain the earthwork, cut off the oblique supports, and backfill with plain concrete. When clearing and transporting the retained earthwork and cutting off the oblique supports, the surrounding protection piles will completely lose the support and the lateral pressure of the earthwork. Will it have an adverse impact on the surrounding protection piles and the subway structure? The retaining piles play a certain protective role, and the feasibility of this scheme is studied.

6.支撑内部割除及防水6. Support internal cutting and waterproofing

割除钢格构斜支撑后,需对斜撑穿地下室底板及外墙部分洞口进行封堵并进行防水处理,地下共计斜撑29道,会产生58个渗漏隐患点,拟在先行施工的四处斜撑进行工艺改进,加焊止水片并对外墙防水进行补强,以达到杜绝渗漏的效果。After cutting off the diagonal braces of the steel lattice, it is necessary to seal and waterproof the openings of the diagonal braces passing through the basement floor and the outer wall. There are 29 diagonal braces underground, which will generate 58 hidden leakage points. Improve the technology of the diagonal brace, add welding water-stop sheet and reinforce the waterproofing of the outer wall to achieve the effect of preventing leakage.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, any person familiar with the technical field within the technical scope disclosed in the present invention, according to the technical solution of the present invention Any equivalent replacement or change of the inventive concepts thereof shall fall within the protection scope of the present invention.

Claims (9)

1. 新建基坑紧临既有基坑近接区施工方法,其特征在于,包括以下步骤:1. The new foundation pit is close to the existing foundation pit approach area construction method, it is characterized in that, comprises the following steps: 一、新建基坑场地处理1. New foundation pit site treatment 工程因其特殊的地理位置和特定的地区影响力,使本工程从基坑支护、土方开挖到斜撑施工的各个阶段都十分重要,基坑开挖是本工程实施的第一阶段,尤为重要,根据定位桩测放出边线的各拐角点,按操作面宽度和排水沟宽度再测放出基坑的内边线或坡底线;开挖第一层土方至共用围护桩腰梁设计标高底部位置(地表以下1500mm);Due to the special geographical location and specific regional influence of the project, all stages of the project from foundation pit support, earthwork excavation to diagonal brace construction are very important. Foundation pit excavation is the first stage of the project implementation. It is especially important to measure and release the corner points of the edge line according to the positioning pile, and then measure and release the inner edge line or slope bottom line of the foundation pit according to the width of the operation surface and the width of the drainage ditch; excavate the first layer of earthwork to the bottom of the design elevation of the waist beam of the common enclosure pile Location (1500mm below the surface); 二、近接区斜撑支座桩施工2. Construction of diagonally braced piles in the proximity area 支座桩采用跳挖施工:先施工1、3、5、7、9号桩,再施工2、4、6、8、10号桩,以此类推跳挖钻孔施工;该支座桩顶端位置位于地表以下8750mm,桩底端位于地表以下12750mm,桩长4000mm,桩径800mm;支座桩施工完毕后会,为防止工人从支座桩洞口坠入,采用土体进行回填,待施作支座桩承台时再进行开挖;The support piles are constructed by skip-digging: first construct No. 1, 3, 5, 7, and 9 piles, and then construct No. 2, 4, 6, 8, and 10 piles, and so on. The position is 8750mm below the ground surface, the bottom of the pile is 12750mm below the ground surface, the pile length is 4000mm, and the pile diameter is 800mm. Excavation shall be carried out when the pile cap of the supporting pile is installed; 1)定位放线1) Positioning and setting out 根据建筑物定位轴线,由专职测量人员按支护桩平面图准确无误地将支护桩桩位放样到现场,现场桩位放样采用木制短桩作为支护桩桩位标识;According to the positioning axis of the building, the full-time surveyors will accurately stake out the positions of the supporting piles to the site according to the plan of the supporting piles, and the wooden short piles will be used as the identification of the supporting piles for the stakes on site; 2)桩位成孔2) Pile position into hole 桩位验收后,钻机就位并调整机身,应用钻机塔身的前后垂直标杆检查导杆,校正位置,使钻杆垂直对准桩位中心,以保证桩身垂直度偏差不得大于允许偏差;After the pile position is accepted, the drilling rig is in place and the fuselage is adjusted. The front and rear vertical benchmarks of the drilling rig tower are used to check the guide rod, and the position is corrected so that the drill rod is vertically aligned with the pile center to ensure that the vertical deviation of the pile body is not greater than the allowable deviation; 3)钢筋笼安放3) Reinforcement cage placed 为了确保钢筋笼在吊装、下放过程中不变形,在钢筋笼中每隔2m加设一道φ20焊接加强筋,加劲箍与主筋采用焊接,桩四周钢筋保护层厚度根据桩孔大小来确定,但不小于5cm;钢筋笼采用长螺旋钻机副卷扬进行吊装,钢筋笼在起吊前检查场地无高压线及障碍物,保证钢筋笼起吊安全施工,钢筋笼利用井口对接安装,钢筋笼入孔后,要牢固定位,定位标高允许误差±5cm,钢筋笼长度锚入承台的长度不小于35d;In order to ensure that the reinforcement cage is not deformed during hoisting and lowering, a φ20 welded reinforcement is added every 2m in the reinforcement cage. The reinforcement hoop and the main reinforcement are welded. Less than 5cm; the steel cage is hoisted by a long auger drilling rig auxiliary winch. Before lifting the steel cage, check that there are no high-voltage lines and obstacles on the site to ensure safe construction of the steel cage. The steel cage is installed by docking the wellhead. Positioning, the allowable error of the positioning elevation is ±5cm, and the length of the reinforcement cage anchored into the cap is not less than 35d; 4)混凝土浇筑4) Concrete pouring 灌注混凝土时,应测定混凝土塌落度,要求塌落度为16~18cm,混凝土要有良好的和易性;为保证混凝土桩身质量,灌注过程中,应不断上下串动导管,使混凝土密实;必要时,需使用振动棒进行振捣;为确保桩顶质量,灌注结束时应缓慢将导管拔出混凝土,防止形成空洞;When pouring concrete, the concrete slump should be measured, and the slump is required to be 16-18cm, and the concrete should have good workability; in order to ensure the quality of the concrete pile body, during the pouring process, the conduit should be continuously moved up and down to make the concrete dense ;If necessary, use a vibrating rod to vibrate; in order to ensure the quality of the pile top, the pipe should be slowly pulled out of the concrete at the end of pouring to prevent the formation of cavities; 三、共用围护桩腰梁施工3. Construction of waist beams of shared enclosure piles 土方开挖至围檩高度时,施工斜支撑腰梁及顶力座,要求腰梁的一边壁和承台的一边壁呈平行,以便后续施作斜撑;When excavating the earthwork to the height of the purlin, the construction of the obliquely braced waist beam and the jacking seat requires that the side wall of the waist beam and the side wall of the cap be parallel to facilitate subsequent diagonal bracing; 将地铁共用围护桩上部保护层凿除,露出受力钢筋,将钢筋表面清洗干净,并将腰梁钢筋与原围护桩桩身主筋焊接,随后至模板,浇筑混凝土,进行保养;Remove the protective layer on the upper part of the subway shared retaining pile to expose the reinforced steel bars, clean the surface of the reinforced bars, weld the waist beam reinforcement with the main reinforcement of the original retaining pile body, and then pour concrete into the formwork for maintenance; 腰梁施工过程如下:The waist beam construction process is as follows: 开挖腰梁顶土方→凿除灌注桩浮浆层至桩顶设计标高→垫层混凝土→绑扎配筋→支模板→浇筑腰梁混凝土(C30)→保养;Excavate the earthwork on the top of the waist beam → chisel away the laitance layer of the cast-in-place pile to the design elevation of the pile top → cushion layer concrete → tie reinforcement → formwork support → pouring the waist beam concrete (C30) → maintenance; 四、施作支座桩承台4. Construction of pile caps 待支座桩混凝土达到设计强度时,继续开挖基坑至支座桩顶部,两深基坑近接区放坡留土,施做支座桩承台;When the concrete of the support pile reaches the design strength, continue to excavate the foundation pit to the top of the support pile, and leave soil in the adjacent area of the two deep foundation pits to make the support pile cap; 1)承台钢筋绑扎1) Binding of steel bars on the platform 支护桩施工完毕,绑扎前应搭设钢筋绑扎架,在其顶端预留的锚固筋上方进行绑扎承台钢筋,绑扎时先放置上层主筋,然后放置箍筋,按图纸间距绑扎时箍筋与主筋垂直绑扎,箍筋间距符合设计及规范规定;上层绑扎完成后穿下层主筋并与箍筋及时绑扎;侧向主筋穿入后逐个放置内箍筋及拉结筋并绑扎牢固,主筋搭接采用单面搭接焊,焊接后钢筋长度满足设计要求,钢筋绑扎好后及时绑扎钢筋垫块;After the construction of the support piles is completed, a steel bar binding frame should be set up before binding, and the steel bars of the cap should be bound above the anchor bars reserved at the top. When binding, the upper main bars are placed first, and then the stirrups. Binding vertically, the spacing of stirrups conforms to the design and specifications; after the upper layer is bound, pass through the main reinforcement of the lower layer and tie it with the stirrups in time; after the main reinforcement of the side is penetrated, place the inner stirrups and tie bars one by one and tie them firmly. Surface lap welding, the length of the steel bars after welding meets the design requirements, and the steel bar pads are bound in time after the steel bars are bound; 3)模板支护及混凝土浇筑3) Form support and concrete pouring 混凝土采用商品混凝土,强度等级C30,用混凝土运输车运送至施工现场,浇筑混凝土时应连续进行,如必须间歇,其间歇时间应尽量缩短,浇筑过程中要及时振捣,使用插入式振捣器应快插慢拔,插点要均匀排列,逐点移动,顺序进行,不得遗漏,做到均匀振实,移动间距不大于振捣作用半径的1.5倍(一般为30~40cm),振捣后及时用木抹子将梁面进行初次抹平,在初凝后终凝前用钢抹对梁面进行收光处理,承台浇筑完毕后,用草袋覆盖,并派专人每天浇水保养;The concrete is commercial concrete with a strength grade of C30. It is transported to the construction site by a concrete transport vehicle. The pouring of the concrete should be carried out continuously. If it must be intermittent, the intermittent time should be shortened as much as possible. During the pouring process, it should be vibrated in time and a plug-in vibrator should be used. It should be inserted quickly and pulled out slowly, and the insertion points should be evenly arranged, moved point by point, in sequence, without omission, so as to achieve uniform vibration, and the moving distance should not be greater than 1.5 times the radius of the vibration effect (generally 30-40cm). Use a wooden trowel to smooth the beam surface for the first time in time. After the initial setting and before the final setting, use a steel trowel to finish the beam surface. After the platform is poured, cover it with straw bags and send special personnel to water and maintain it every day; 4)拆模及养护4) Form removal and maintenance 混凝土浇筑完成后12小时内要及时对承台进行浇水养护,养护次数以保持表面湿润为准,24小时后即可对承台进行拆除,拆除时拆除工具不得接触混凝土,避免损坏菱角,以免影响整体观感,拆除后的模板要及时清理干净并堆放整齐,便于下次利用;Within 12 hours after the concrete pouring is completed, the caps should be watered and maintained in time. The number of maintenance is based on keeping the surface moist. The caps can be dismantled after 24 hours. Affect the overall look and feel, the removed formwork should be cleaned up in time and stacked neatly for the next use; 五、近接区斜撑施工5. Diagonal bracing construction in the proximity area 主体的钢支撑采用600×600的钢格构斜撑,钢支撑顶端焊接700×700×16的钢板进行封端;钢支撑底端设有专门的顶力座,顶力座具体是通过锚件与承台斜边壁上预埋钢筋连接,通过千斤顶在均匀施顶;钢支撑与共用围护桩腰梁采用焊接,另一端为活动支座;钢支撑预加轴力依靠两台液压千斤顶完成,千斤顶能力满足设计预加轴力的要求;千斤顶安装在预埋板406和顶力坐303之间;钢支撑安装时,腰梁、端头、千斤顶各轴线保持在同一轴线上,为确保平直,钢支撑上锁紧片应按对角顺序同时拧紧;拼装最终偏心值不大于20mm;斜撑焊死前应顶紧,当顶力达到设计的预加力,在锁紧段安装锁紧片焊死后卸下千斤顶,千斤顶预加轴力必须对称同步,保证支撑轴心受力,斜支撑焊死前,必须施加不小于400KN的预顶力;The steel support of the main body adopts a 600×600 steel lattice diagonal brace, and the top of the steel support is welded with a 700×700×16 steel plate for sealing; It is connected with the pre-embedded steel bars on the sloped side wall of the cap, and the jack is applied evenly through the jack; the steel support is welded to the waist beam of the shared enclosure pile, and the other end is a movable support; the pre-loaded axial force of the steel support is completed by two hydraulic jacks , the capacity of the jack meets the requirements of the design pre-loaded axial force; the jack is installed between the embedded plate 406 and the jacking seat 303; when the steel support is installed, the axes of the waist beam, the end, and the jack are kept on the same axis. Straight, the locking pieces on the steel support should be tightened in diagonal order at the same time; the final eccentricity of the assembly should not be greater than 20mm; the diagonal brace should be tightened before welding, and when the jacking force reaches the designed pre-loading force, install and lock at the locking section After the piece is welded, remove the jack. The pre-loaded axial force of the jack must be symmetrical and synchronized to ensure that the supporting axis is stressed. Before the oblique support is welded, a pre-jacking force of not less than 400KN must be applied; 六、近接区土方开挖6. Earthwork excavation in the proximity area 保留斜撑下土方,进行图书馆地下室结构施工,地下室结构施工完成后,清运保留土方;钢斜撑之间的土方采用挖掘机开挖,靠近钢斜撑部位及斜撑底部的土方采用人工挖土的方式,防止机械开挖造成斜撑失稳破坏;The earthwork under the diagonal braces is reserved for the construction of the basement structure of the library. After the construction of the basement structure is completed, the retained earthwork is removed; the earthwork between the steel braces is excavated by an excavator, and the earthwork near the steel braces and the bottom of the braces is manually excavated. The method of excavation prevents mechanical excavation from causing instability and damage to the diagonal brace; 新建基坑近接区地下结构施工Underground structure construction in the adjacent area of new foundation pit 地下室解构在施工时先只施工支座桩承台至共用围护桩部分的结构,绑扎侧墙及底板与侧墙交界处的钢筋并浇筑混凝土,待侧墙混凝土强度达到设计强度时,对侧墙外表面涂抹防水材料;余下部分地下室结构待钢斜撑割除完毕之后继续施工;For the deconstruction of the basement, only the structure from the bearing pile cap to the common retaining pile is constructed first, and the side wall and the steel bars at the junction of the bottom plate and the side wall are bound and concrete is poured. When the concrete strength of the side wall reaches the design strength, the opposite side Apply waterproof material to the outer surface of the wall; the rest of the basement structure will continue to be constructed after the steel diagonal braces are cut off; 近接区斜撑下方素砼回填Plain concrete backfill under the diagonal braces in the adjacent area 地下室结构施工完成后,清运保留土方,割除斜支撑,进行素混凝土回填,在清运保留土方及割除斜支撑时,围护桩完全失去支撑及土方的侧压力,是否会对围护桩及地铁结构产生不利影响,如保留该部分土方,仅回填土方上部混凝土,会对围护桩起到一定保护作用;After the construction of the basement structure is completed, remove and retain the earthwork, cut off the oblique supports, and carry out plain concrete backfill. When the earthwork is removed and the oblique supports are removed, the surrounding protection piles will completely lose the support and the lateral pressure of the earthwork. Will it affect the surrounding protection piles and If the subway structure is adversely affected, if this part of the earthwork is retained and only the concrete on the upper part of the earthwork is backfilled, it will have a certain protective effect on the surrounding retaining piles; 地下结构内部斜撑割除及防水Removal and waterproofing of diagonal braces inside underground structures 割除钢格构斜支撑后,需对斜撑穿地下室底板及外墙部分洞口进行封堵并进行防水处理,地下共计斜撑29道,会产生58个渗漏隐患点,由于地下室侧墙与共用围护桩之间采用素砼回填具有一定防水作用,只需对侧墙钢支撑割除洞口采用混凝土封堵即可;地下室底板的钢支撑割除后,先铺设止水片再浇筑混凝土垫层,在混凝土垫层上继续绑扎钢筋,浇筑混凝土,完成未施工完毕的地下室底板结构,对底板墙防水进行补强,以达到杜绝渗漏的效果,即完成全部施工;After cutting off the oblique bracing of the steel lattice, it is necessary to seal and waterproof the openings of the oblique bracing through the basement floor and outer wall. The plain concrete backfill between the enclosure piles has a certain waterproof effect, and it is only necessary to use concrete to seal the opening of the steel support on the side wall; On the concrete cushion, continue to bind steel bars, pour concrete, complete the basement floor structure that has not been completed, and reinforce the waterproofing of the floor wall to achieve the effect of preventing leakage, that is, complete the entire construction; 支座桩用做地下结构抗拔桩Bearing piles are used as uplift piles for underground structures 对面地下水较为丰富的地区,地下室结构内部钢斜撑拆除后,可凿除支座桩承台,露出受力钢筋,将受力钢筋与地下室结构底板钢筋焊接并浇筑混凝土,使得支座桩成为地下室底板的整体结构,作为地下室抗浮桩使用,大大节省了施工成本;In the area where the groundwater is relatively abundant, after removing the steel diagonal braces inside the basement structure, the bearing pile caps can be chiseled out to expose the stressed steel bars, and the stressed steel bars are welded to the basement structural bottom plate steel bars and poured with concrete, so that the bearing piles become the basement The overall structure of the bottom plate is used as an anti-floating pile in the basement, which greatly saves construction costs; 十一、近接区回填土至设计标高;11. Backfill the adjacent area to the design elevation; 待整个地下室结构完成施工,混凝土强度达到设计标高时,回填地下土;室外基坑回填前必须对地下防水层、保护层等进行检查,发现损坏及时修补处理,将基坑底的垃圾等杂物清理干净,回填施工前在室外防水保护板上弹水平线以控制回填土的高度。When the construction of the entire basement structure is completed and the concrete strength reaches the design level, backfill the underground soil; before backfilling the outdoor foundation pit, the underground waterproof layer and protective layer must be inspected, and any damage is found to be repaired in time. Clean up, and before backfilling construction, play a horizontal line on the outdoor waterproof protection board to control the height of backfilling. 2.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤一的施工工序为:场地平整→基坑定位→桩位放线→支护桩施工→压密注浆→腰梁施工→砌砖拱挡土墙施工→土方分层挖运→土钉→挂钢筋网片→喷锚→养护。2. The construction method according to claim 1, wherein the new foundation pit is adjacent to the adjacent area of the existing foundation pit, characterized in that the construction process of the first step is: site leveling → foundation pit positioning → pile position setting → support Pile construction→compaction grouting→waist beam construction→brick-laying arch retaining wall construction→earth excavation in layers→soil nailing→hanging steel mesh→spray anchor→maintenance. 3.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤一中的砂浆供应与砌筑操作具体为:支护桩砼采用商品砼C30,砂浆采用现场人工拌制,砌筑。3. The method for constructing a new foundation pit next to an existing foundation pit according to claim 1, characterized in that the mortar supply and masonry operations in the first step are as follows: commercial concrete C30 is used for supporting pile concrete , The mortar is manually mixed and built on site. 4.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤一中的桩基施工:采用钻孔灌注施工,下吊钢筋笼,场内土石方转运用挖机进行,外运采用自卸汽车。4. The new foundation pit according to claim 1 is close to the existing foundation pit approach area construction method, it is characterized in that, the pile foundation construction in the described step 1: adopt borehole perfusion construction, hang the reinforcement cage, in the field Earth and stone transfer is carried out by excavators, and dump trucks are used for external transportation. 5.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤二中,钻杆下钻到预定深度,现场施工技术人员根据地质勘察报告以及实际钻孔出土观察分析,是否达到设计要求的土层;如在施工中发现长螺旋干成孔无法施工,将采用长螺旋后置钢筋笼施工方法。5. The new foundation pit according to claim 1 is close to the existing foundation pit approach area construction method, it is characterized in that, in said step 2, the drill pipe is drilled to a predetermined depth, and the on-site construction technicians are based on the geological survey report and Observation and analysis of the actual borehole unearthed to see if the soil layer required by the design is met; if it is found during construction that the long spiral dry hole cannot be constructed, the construction method of the long spiral post-installed reinforcement cage will be adopted. 6.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤二中,开钻前,封住钻头阀门,使钻杆向下移动至钻头触及地面时,开动钻机旋动钻头;一般应先慢后快,在成孔过程中如发现钻杆摇晃或难钻时,应停机或放慢进尺,遇到障碍物应停止钻进,分析原因,禁止强行钻进。6. The construction method according to claim 1, wherein the new foundation pit is adjacent to the adjacent area of the existing foundation pit, characterized in that, in the second step, before drilling, the drill bit valve is sealed to move the drill pipe down to the drill bit When touching the ground, start the drilling rig to rotate the drill bit; generally, it should be slow first and then fast. If the drill pipe is found to be shaking or difficult to drill during the hole forming process, stop the machine or slow down the footage. When encountering obstacles, stop drilling and analyze the reasons , It is forbidden to force drilling. 7.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤二中,砼垫块做的保护层靠孔壁一面做成圆弧形,一般竖向每间隔2m左右布置一道,每道沿圆周对称布置四块。7. The new foundation pit according to claim 1 is close to the existing foundation pit approach area construction method, it is characterized in that, in the described step 2, the protective layer that the concrete spacer is done is made into an arc shape by one side of the hole wall, Generally, one line is arranged vertically at intervals of about 2m, and each line is symmetrically arranged with four blocks along the circumference. 8.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤三中,安放钢筋时,由测量员事先在垫层上放线,钢筋笼紧贴线进行安放,水平误差不得超过3cm,垂直误差不得超过2cm,安放好的钢筋观感应平直。8. The new foundation pit according to claim 1 is close to the existing foundation pit approach area construction method, it is characterized in that, in described step 3, when laying steel bar, lay out line on cushion layer in advance by surveyor, steel bar cage Place it close to the line, the horizontal error shall not exceed 3cm, the vertical error shall not exceed 2cm, and the installed steel bar will look straight. 9.根据权利要求1所述的新建基坑紧临既有基坑近接区施工方法,其特征在于,所述步骤三中,混凝土浇筑前应将模板内的垃圾、泥土等杂物及钢筋上的油污清除干净,并检查钢筋的水泥砂浆垫块是否垫好。9. The new foundation pit according to claim 1 is close to the existing foundation pit approach area construction method, it is characterized in that, in the described step 3, the rubbish, earth and other sundries in the formwork and the steel bars should be placed on the concrete before pouring. Clean up the oil stains and check whether the cement mortar pads of the steel bars are properly cushioned.
CN202211203417.9A 2022-09-29 2022-09-29 Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area Pending CN115897600A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211203417.9A CN115897600A (en) 2022-09-29 2022-09-29 Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211203417.9A CN115897600A (en) 2022-09-29 2022-09-29 Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area

Publications (1)

Publication Number Publication Date
CN115897600A true CN115897600A (en) 2023-04-04

Family

ID=86485105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211203417.9A Pending CN115897600A (en) 2022-09-29 2022-09-29 Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area

Country Status (1)

Country Link
CN (1) CN115897600A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118207884A (en) * 2024-05-22 2024-06-18 北京建工四建工程建设有限公司 Existing building dismantling and newly-built building foundation pit supporting cross comprehensive construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118207884A (en) * 2024-05-22 2024-06-18 北京建工四建工程建设有限公司 Existing building dismantling and newly-built building foundation pit supporting cross comprehensive construction method

Similar Documents

Publication Publication Date Title
CN107542108B (en) A kind of reverse construction method of building basement structure
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN110485429A (en) A kind of prestressing force fashioned iron assembled combination inner support construction method
CN110952456A (en) Pile type bridge construction process
CN110905523A (en) Subway vertical shaft construction method
CN105236275A (en) Soil lifting system and method for construction of deep foundation pit in narrow area building
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN109488347B (en) Excavation construction method for special stratum chamber
CN111560941A (en) Karst landform cavity treatment method
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
WO2021097863A1 (en) Swirl pool construction method employing semi-reverse construction
CN113266392B (en) A construction method of pipe jacking through existing anchor cable groups
CN111455977A (en) Underground continuous wall construction method
CN114411761A (en) Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method
CN209723033U (en) Pipe jacking working well applicable to desert waterless sand layer area
CN108118689B (en) Partially recyclable prefabricated underground diaphragm wall, spreader and construction method
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN212270945U (en) Existing railway line foundation pit supporting system
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN111218938A (en) Excavation construction method for foundation pit above existing tunnel
CN117385927A (en) Comprehensive construction method for underground comprehensive pipe rack
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
CN217378907U (en) Deep soft soil pool foundation pit support system for complex land storage yard
CN116446915A (en) Entrance Support Structure and Construction Method of Shallow Buried Tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination