CN209723033U - Pipe jacking working well applicable to desert waterless sand layer area - Google Patents
Pipe jacking working well applicable to desert waterless sand layer area Download PDFInfo
- Publication number
- CN209723033U CN209723033U CN201920399744.3U CN201920399744U CN209723033U CN 209723033 U CN209723033 U CN 209723033U CN 201920399744 U CN201920399744 U CN 201920399744U CN 209723033 U CN209723033 U CN 209723033U
- Authority
- CN
- China
- Prior art keywords
- working well
- pile
- inner lining
- well
- pipe jacking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 239000004576 sand Substances 0.000 title claims abstract description 31
- 239000004567 concrete Substances 0.000 claims description 51
- 230000002787 reinforcement Effects 0.000 claims description 27
- 238000009415 formwork Methods 0.000 claims description 15
- 238000010276 construction Methods 0.000 abstract description 62
- 238000000034 method Methods 0.000 abstract description 16
- 238000009412 basement excavation Methods 0.000 abstract description 15
- 239000002689 soil Substances 0.000 abstract description 13
- 238000006243 chemical reaction Methods 0.000 abstract description 5
- 229910000831 Steel Inorganic materials 0.000 description 45
- 239000010959 steel Substances 0.000 description 45
- 239000010410 layer Substances 0.000 description 33
- 230000003014 reinforcing effect Effects 0.000 description 14
- 238000013461 design Methods 0.000 description 11
- 239000011241 protective layer Substances 0.000 description 5
- 238000003466 welding Methods 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 239000011083 cement mortar Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000007921 spray Substances 0.000 description 2
- 230000001133 acceleration Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 238000012790 confirmation Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 239000011120 plywood Substances 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000007586 pull-out test Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000005204 segregation Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 238000009966 trimming Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型提供一种适用于沙漠无水砂层地区顶管工作井,多个钻孔灌注桩沿工作井周向均匀布置,多个钻孔灌注桩绕工作井的圆心构成工作井主要围护和受力结构,钻孔灌注桩体的上方设有冠梁,圆形的冠梁与工作井为同心圆结构,内衬位于钻孔灌注桩的内侧,内衬竖向沿工作井深度方向布置,暗梁嵌于内衬且沿内衬长度方向自上而下间隔布置,底板位于工作井井底,底板下方设置有井底加固旋喷桩,工作井钻孔灌注桩外侧在顶管管节进出洞口位置设置有洞口加固旋喷桩。本实用新型的钻孔灌注桩能够保证开挖过程土体稳定性,并承受顶管施工所需的较大反力;本实用新型的内衬能够增加桩间砂土稳定性,并将水平荷载均匀传递给钻孔灌注桩。
The utility model provides a pipe jacking working well suitable for the desert anhydrous sand layer area. A plurality of bored cast-in-place piles are evenly arranged along the circumference of the working well, and the plurality of bored cast-in-place piles surround the center of the working well to form the main enclosure of the working well. There is a crown beam above the bored pile body. The circular crown beam and the working well are concentric structures. The inner lining is located inside the bored pile, and the inner lining is arranged vertically along the depth direction of the working well. The hidden beams are embedded in the lining and are arranged at intervals from top to bottom along the length of the lining. The bottom plate is located at the bottom of the working well. The bottom of the bottom plate is provided with a bottom-reinforcing rotary jetting pile. At the entrance and exit positions, there are reinforced rotary jet piles at the entrance. The bored pile of the utility model can ensure the stability of the soil body during the excavation process, and can bear the large reaction force required for the pipe jacking construction; the inner lining of the utility model can increase the stability of the sand between the piles, and reduce the horizontal load Evenly pass to bored piles.
Description
技术领域technical field
本实用新型属于顶管施工技术领域,具体涉及一种适用于沙漠无水砂层地区顶管工作井。The utility model belongs to the technical field of pipe jacking construction, and in particular relates to a pipe jacking working well suitable for an anhydrous sand layer in the desert.
背景技术Background technique
顶管施工是一种不开挖或者少开挖的管道设施施工技术。顶管施工是继盾构施工之后而发展起来的一种地下管道施工方法,它不需要开挖面层,并且能够穿越公路、铁道、河川、地面建筑物、地下构筑物以及各种地下管线等。随着城市化进程的进一步加快,我国的地下管线的需求量也在逐年增加。加之人们对环境保护意识的增强,顶管技术在我国地下管线的施工中起到越来越重要的作用。Pipe jacking construction is a pipeline facility construction technology with no or less excavation. Pipe jacking construction is an underground pipeline construction method developed after shield construction. It does not require excavation of the surface layer, and can cross roads, railways, rivers, ground buildings, underground structures and various underground pipelines. With the further acceleration of the urbanization process, the demand for underground pipelines in my country is also increasing year by year. Coupled with the enhancement of people's awareness of environmental protection, pipe jacking technology plays an increasingly important role in the construction of underground pipelines in my country.
在顶管施工的过程中为降低顶管的施工顶力,大多是采用分段施工的方法,在分段施工过程中需要设立竖向工作井和接收井。顶管竖井除提供机械和人员所需的施工空间外,还应提供顶管顶进时所需的反力,因此顶管竖井井壁常承受较大的水平顶力作用。当顶管施工位于沙漠无水砂层中时,顶管顶进所需顶力很大,给竖井设计和施工带来很大难度。但是现行工作井的自身结构和施工方法并不能满足沙漠无水砂层中顶管施工要求。In the process of pipe jacking construction, in order to reduce the construction jacking force of the pipe jacking, the method of segmented construction is mostly adopted, and vertical working wells and receiving wells need to be set up during the segmented construction process. In addition to providing the construction space required by machinery and personnel, the pipe jacking shaft should also provide the reaction force required for the jacking of the pipe, so the wall of the pipe jacking shaft often bears a large horizontal jacking force. When the pipe jacking construction is located in the desert anhydrous sand layer, the jacking force required for the pipe jacking is very large, which brings great difficulties to the design and construction of the shaft. However, the structure and construction method of the current working well cannot meet the requirements of pipe jacking in the desert anhydrous sand layer.
因此,需要提供一种针对上述现有技术不足的改进技术方案。Therefore, it is necessary to provide an improved technical solution for the deficiencies of the above-mentioned prior art.
实用新型内容Utility model content
本实用新型的目的是克服上述现有技术中的沙漠无水砂层地区的顶管施工时需要较大的水平顶力作用,但是现行的工作井结构和施工方法并不能满足这方面的要求。The purpose of this utility model is to overcome the need for large horizontal jacking force during the pipe jacking construction in the desert anhydrous sand layer area in the prior art, but the current working well structure and construction method cannot meet this requirement.
为了实现上述目的,本实用新型提供如下技术方案:In order to achieve the above object, the utility model provides the following technical solutions:
一种适用于沙漠无水砂层地区顶管工作井,所述工作井包括:A pipe-jacking working well suitable for desert anhydrous sand layer areas, the working well comprises:
钻孔灌注桩,多个所述钻孔灌注桩沿工作井的周向均匀布置,多个所述钻孔灌注桩绕工作井的圆心构成第一井壁体,用于工作井的主要围护和受力;A plurality of bored cast-in-place piles are evenly arranged along the circumference of the working well, and a plurality of the bored cast-in-place piles form a first well wall around the center of the working well, which is used for the main enclosure of the working well and force;
冠梁,所述第一井壁体的上方设有冠梁,圆形的所述冠梁与工作井为同心圆结构;A crown beam, a crown beam is arranged above the first well wall body, and the circular crown beam and the working well are concentric circle structures;
内衬,所述内衬位于钻孔灌注桩的内侧,内衬竖向沿工作井深度方向布置构成第二井壁体,用于工作井的辅助围护和受力;an inner lining, the inner lining is located on the inner side of the bored cast-in-place pile, and the inner lining is vertically arranged along the depth direction of the working well to form a second well wall body, which is used for the auxiliary enclosure and stress of the working well;
暗梁,所述暗梁嵌于内衬上且沿内衬的深度方向自上而下间隔布置;Concealed beams, the concealed beams are embedded on the inner lining and are arranged at intervals from top to bottom along the depth direction of the inner lining;
底板,所述底板位于内衬的下方,底板的周边与钻孔灌注桩的内侧壁相连;a bottom plate, the bottom plate is located below the inner lining, and the periphery of the bottom plate is connected with the inner side wall of the bored pile;
井底加固旋喷桩,所述底板的下方设置有井底加固旋喷桩,井底加固旋喷桩采用格栅状满堂布置;The bottom reinforced rotary jet piles are arranged below the bottom plate, and the bottom reinforced rotary jet piles are arranged in a grid-like full house;
洞口加固旋喷桩,所述钻孔灌注桩的外侧设置有洞口加固旋喷桩,洞口加固旋喷桩位于工作井顶管管节进出洞口处。The hole-reinforced rotary jetting pile is provided with a hole-reinforced rotary jetting pile on the outer side of the bored cast-in-place pile, and the hole-reinforced rotary jetting pile is located at the entrance and exit of the pipe jacking pipe section of the working well.
如上所述适用于沙漠无水砂层地区顶管工作井,优选地,所述内衬的厚度为0.5m~0.8m,内衬内部自上而下每间隔4m~6m设置暗梁。As mentioned above, it is suitable for pipe jacking working wells in desert anhydrous sand areas. Preferably, the thickness of the lining is 0.5m-0.8m, and the interior of the lining is provided with dark beams at intervals of 4m-6m from top to bottom.
如上所述适用于沙漠无水砂层地区顶管工作井,优选地,所述井底加固旋喷桩的厚度为2m~6m,搭接范围为0.2m~0.4m。As mentioned above, it is suitable for pipe jacking working wells in desert anhydrous sand layers. Preferably, the thickness of the bottom reinforced rotary jetting pile is 2m-6m, and the overlap range is 0.2m-0.4m.
如上所述适用于沙漠无水砂层地区顶管工作井,优选地,所述暗梁的宽度与内衬的厚度相同,该暗梁的高为0.5m~0.9m。As mentioned above, it is applicable to the pipe jacking working well in the desert anhydrous sand layer. Preferably, the width of the concealed beam is the same as the thickness of the inner lining, and the height of the concealed beam is 0.5m-0.9m.
如上所述适用于沙漠无水砂层地区顶管工作井,优选地,所述内衬与冠梁的连接处还设置有第一垫层,第一垫层为厚度100mm~200mm的素混凝土垫层。As mentioned above, it is suitable for pipe jacking working wells in desert anhydrous sand layers. Preferably, a first cushion layer is also provided at the connection between the inner lining and the crown beam, and the first cushion layer is a plain concrete cushion with a thickness of 100mm to 200mm. Floor.
如上所述适用于沙漠无水砂层地区顶管工作井,优选地,所述底板与井底加固旋喷桩之间还设置有第二垫层,第二垫层的厚度为100mm~200mm,所述第二垫层用于支撑底板模板。As mentioned above, it is suitable for pipe jacking working wells in desert anhydrous sand layers. The second cushion layer is used to support the bottom plate formwork.
如上所述1~6任一项适用于沙漠无水砂层地区顶管工作井的施工方法,优选地,所述施工方法包括如下步骤:Any one of the above 1 to 6 is applicable to the construction method of the pipe jacking working well in the desert anhydrous sand layer area, preferably, the construction method comprises the following steps:
S1,进行钻孔灌注桩的施工;S1, carry out the construction of bored piles;
S2,在步骤S1中钻孔灌注桩的混凝土强度达到设计强度后进行冠梁的施工;S2, the construction of the crown beam is carried out after the concrete strength of the bored pile reaches the design strength in step S1;
S3,步骤S2中冠梁的混凝土强度达到设计强度后进行工作井内土体的开挖,并进行暗梁和内衬的施工;S3, in step S2, after the concrete strength of the crown beam reaches the design strength, the excavation of the soil body in the working well is carried out, and the construction of the concealed beam and the inner lining is carried out;
S4,进行井底加固旋喷桩、底板、洞口加固旋喷桩的施工。S4, carry out the construction of the bottom-reinforcing rotary jetting pile, the bottom plate, and the hole-hole reinforcing rotary jetting pile.
如上所述适用于沙漠无水砂层地区顶管工作井的施工方法,优选地,所述步骤S1包括如下步骤:As mentioned above, it is applicable to the construction method of the pipe jacking working well in the desert anhydrous sand layer area. Preferably, the step S1 includes the following steps:
S101,采用泥浆护壁或钢管护壁法施作钻孔灌注桩的桩孔;S101, using mud retaining wall or steel pipe retaining wall method to apply the pile hole of bored pile;
S102,向步骤S101的桩孔内吊放桩基钢筋笼;S102, hoist the pile foundation reinforcement cage into the pile hole of step S101;
S103,向步骤S102的桩基钢筋笼浇筑桩基混凝土。S103, pour the pile foundation concrete into the pile foundation reinforcement cage of step S102.
如上所述适用于沙漠无水砂层地区顶管工作井的施工方法,优选地,所述步骤S2具体包括如下步骤:As mentioned above, it is applicable to the construction method of the pipe jacking working well in the desert anhydrous sand layer area. Preferably, the step S2 specifically includes the following steps:
S201,开挖冠梁处土体;S201, excavating the soil at the crown beam;
S202,在开挖好的冠梁基坑内绑扎冠梁配筋;S202, tie the crown beam reinforcement in the excavated crown beam foundation pit;
S203,在冠梁配筋上施工冠梁模板;S203, construct the crown beam formwork on the crown beam reinforcement;
S204,浇筑冠梁混凝土。S204, pouring the crown beam concrete.
如上所述适用于沙漠无水砂层地区顶管工作井的施工方法,优选地,所述步骤S3包括如下步骤:As mentioned above, it is applicable to the construction method of the pipe jacking working well in the desert anhydrous sand layer area. Preferably, the step S3 includes the following steps:
S301,开挖工作井内土体;S301, excavating the soil in the working well;
S302,对开挖土体处工作井的井壁进行植筋;S302, planting reinforcement on the shaft wall of the working well at the excavated soil body;
S303,搭设内衬模板;S303, erecting a lining template;
S304,进行内衬和暗梁的混凝土施工。S304, the concrete construction of the inner lining and the concealed beam is carried out.
与最接近的现有技术相比,本实用新型提供的技术方案具有如下优异效果:Compared with the closest prior art, the technical solution provided by the present utility model has the following excellent effects:
本实用新型的新型顶管竖井,除能满足机械和人员所需的施工空间外,还能提供较大顶管施工水平反力;本实用新型的钻孔灌注桩的内衬能够增加桩间砂土的稳定性,内衬能够增加桩间砂土稳定性,并将水平荷载均匀传递给钻孔灌注桩,内衬内部设置的暗梁能够将钻孔灌注桩连成一个整体,共同受力;本实用新型的高压旋喷桩能够保证施工人员实现在地面对竖井封底,增加了结构安全性和施工便利性。同时钻孔灌注桩的桩径和成桩深度可选范围大,无挤土效应,竖向和水平向承载力较高,采用沿工作井周围均匀布置灌注桩形成的工作井,除满足施工空间外,还可以提供始发工作井顶管顶进所需的较大反力。The new pipe jacking shaft of the utility model can not only meet the construction space required by machinery and personnel, but also provide a large horizontal reaction force for pipe jacking construction; the inner lining of the bored pile of the utility model can increase the sand between the piles The stability of the soil, the inner lining can increase the stability of the sand between the piles, and evenly transmit the horizontal load to the bored piles, and the hidden beams set inside the lining can connect the bored piles into a whole and bear the force together; The high-pressure rotary jet pile of the utility model can ensure that the construction personnel can realize the bottom sealing of the vertical shaft on the ground, thereby increasing the structural safety and the construction convenience. At the same time, the pile diameter and pile depth of the bored piles can be selected in a large range, there is no soil squeeze effect, and the vertical and horizontal bearing capacities are high. In addition, it can also provide a larger reaction force required for the pipe jacking of the starting working well.
附图说明Description of drawings
图1为本实用新型实施例的工作井的结构示意图;1 is a schematic structural diagram of a working well according to an embodiment of the present utility model;
图2为本实用新型实施例的基坑内衬的平面布置图;Fig. 2 is the plan layout drawing of the foundation pit lining of the embodiment of the present utility model;
图3为图1中的冠梁与第一垫层之间的位置关系示意图。FIG. 3 is a schematic diagram of the positional relationship between the crown beam and the first cushion layer in FIG. 1 .
图中:1、冠梁;2、钻孔灌注桩;3、暗梁;4、洞口加固旋喷桩;5、内衬;6、第二垫层;7、井底加固旋喷桩;8、底板;9、第一垫层;10、管节。In the picture: 1. Crown beam; 2. Bored cast-in-place pile; 3. Concealed beam; 4. Reinforced jetting pile at the hole; 5. Inner lining; 6. Second cushion; 7. Reinforced jetting pile at the bottom of the well; 8 , bottom plate; 9, the first cushion; 10, pipe joints.
具体实施方式Detailed ways
下面将对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention belong to the protection scope of the present invention.
下面将参考附图并结合实施例来详细说明本实用新型。需要说明的是,在不冲突的情况下,本实用新型中的实施例及实施例中的特征可以相互组合。The present utility model will be described in detail below with reference to the accompanying drawings and in conjunction with the embodiments. It should be noted that the embodiments of the present invention and the features of the embodiments may be combined with each other under the condition of no conflict.
如图1~3所示,本实用新型提供了一种适用于沙漠无水砂层地区顶管工作井,工作井包括:As shown in Figures 1-3, the utility model provides a pipe jacking working well suitable for desert anhydrous sand layer areas, and the working well includes:
钻孔灌注桩2,多个钻孔灌注桩2沿工作井的周向均匀布置,多个钻孔灌注桩2绕工作井的圆心构成第一井壁体,用于工作井的主要围护和受力,第一井壁体用于承受顶管施工所需反力和保证整个工作井的稳定。Bored piles 2, a plurality of bored piles 2 are evenly arranged along the circumference of the working well, and a plurality of bored piles 2 form a first well wall around the center of the working well, which is used for the main enclosure and the working well. The first well wall body is used to bear the reaction force required by the pipe jacking construction and ensure the stability of the entire working well.
冠梁1,第一井壁体的上方设有冠梁1,圆形的冠梁1与工作井为同心圆结构。Crown beam 1, a crown beam 1 is arranged above the first well wall body, and the circular crown beam 1 is in a concentric structure with the working well.
内衬5,内衬5位于钻孔灌注桩2的内侧,内衬5竖向沿工作井深度方向布置构成第二井壁体,用于工作井的辅助围护和受力,内衬5的厚度为0.5m~0.8m,内衬5内部自上而下每间隔4m~6m设置暗梁3。环形的暗梁3与内衬5形成一个稳定的受力结构,能够极大地增加工作井的整个刚度和承载能力。The inner lining 5 is located on the inner side of the bored pile 2. The inner lining 5 is arranged vertically along the depth direction of the working well to form a second well wall, which is used for the auxiliary enclosure and stress of the working well. The thickness is 0.5m-0.8m, and the inner lining 5 is provided with dark beams 3 at intervals of 4m-6m from top to bottom. The annular dark beam 3 and the inner lining 5 form a stable force-bearing structure, which can greatly increase the overall rigidity and bearing capacity of the working well.
暗梁3,暗梁3内嵌于内衬5且沿内衬5的长度方向自上而下间隔布置,暗梁3的宽度与内衬5的厚度相同,暗梁3的高为0.5m~0.9m,内衬5与冠梁1的连接处还设置有第一垫层9,第一垫层9为厚度100mm~200mm的素混凝土垫层。The hidden beam 3, the hidden beam 3 is embedded in the inner lining 5 and is arranged at intervals from top to bottom along the length direction of the inner lining 5, the width of the hidden beam 3 is the same as the thickness of the inner lining 5, and the height of the hidden beam 3 is 0.5m~ 0.9m, a first cushion layer 9 is also provided at the connection between the inner lining 5 and the crown beam 1, and the first cushion layer 9 is a plain concrete cushion layer with a thickness of 100mm-200mm.
底板8,底板8位于内衬5的下方,底板8周边与钻孔灌注桩2的内侧壁相连。The bottom plate 8 is located below the inner lining 5 , and the periphery of the bottom plate 8 is connected with the inner side wall of the bored pile 2 .
井底加固旋喷桩7,底板8的下方设置有井底加固旋喷桩7,井底加固旋喷桩7采用格栅状满堂布置,即在井底布置满格栅状的井底加固旋喷桩8,底板8与井底加固旋喷桩7之间还设置有第二垫层6,第二垫层6的厚度为100mm~200mm(如100mm,110mm,130mm,140mm,150mm,170mm,180mm,190mm,200mm),用于支撑底板8模板。Bottom reinforced rotary jetting piles 7, bottom reinforced rotary jetting piles 7 are arranged below the bottom plate 8, and the bottom well reinforced rotary jetting piles 7 are arranged in a grid-like full house, that is, a grid-shaped bottom-well reinforced rotary jetting pile is arranged at the bottom of the well. The spray pile 8 is also provided with a second cushion layer 6 between the bottom plate 8 and the bottom reinforced rotary spray pile 7. 180mm, 190mm, 200mm), used to support the bottom plate 8 formwork.
洞口加固旋喷桩4,钻孔灌注桩2的外侧设置有洞口加固旋喷桩4,洞口加固旋喷桩4位于工作井顶管管节10进出洞口处;井底加固旋喷桩7的厚度为2m~6m,搭接范围为0.2m~0.4m。The hole-reinforced rotary jetting pile 4 is provided on the outside of the bored cast-in-place pile 2, and the hole-reinforced rotary jetting pile 4 is located at the entrance and exit of the pipe jacking pipe section 10 of the work well; the thickness of the bottom-well reinforced rotary jetting pile 7 It is 2m to 6m, and the overlap range is 0.2m to 0.4m.
本实用新型还提供了一种适用于沙漠无水砂层地区顶管工作井的施工方法,施工方法包括如下步骤:The utility model also provides a construction method suitable for a pipe jacking working well in an anhydrous sand layer area of the desert, and the construction method comprises the following steps:
S1,进行钻孔灌注桩2的施工,步骤S1包括如下步骤:S1, carry out the construction of the bored pile 2, and step S1 includes the following steps:
S101,采用泥浆护壁或钢管护壁法施作钻孔灌注桩2的桩孔。S101 , the pile holes of the bored cast-in-place pile 2 are formed by the method of mud retaining wall or steel pipe retaining wall.
S102,向步骤S101的桩孔内吊放桩基钢筋笼。S102, the pile foundation reinforcement cage is hoisted into the pile hole of step S101.
S103,向步骤S102的桩基钢筋笼浇筑桩基混凝土。S103, pour the pile foundation concrete into the pile foundation reinforcement cage of step S102.
S2,在步骤S1中钻孔灌注桩2的混凝土强度达到设计强度后进行冠梁1的施工,步骤S2具体包括如下步骤:S2, the construction of the crown beam 1 is carried out after the concrete strength of the bored pile 2 reaches the design strength in step S1, and step S2 specifically includes the following steps:
S201,开挖冠梁1土方,冠梁1基坑深度为地面以下3m,基坑开挖范围内无地下水,基坑周围无其它构、建筑物,冠梁1基坑土层为松散、中密的砂土,坡顶无荷载,开挖深度为3m,采用放坡比例为1:1的方式进行开挖,挖出的土方运至场外指定位置堆放。S201, excavate the earthwork of crown beam 1, the depth of the foundation pit of crown beam 1 is 3m below the ground, there is no groundwater within the excavation range of the foundation pit, there are no other structures and buildings around the foundation pit, and the soil layer of the crown beam 1 foundation pit is loose, medium Dense sandy soil, no load on the top of the slope, the excavation depth is 3m, and the excavation is carried out with a grading ratio of 1:1.
S202,在开挖好的冠梁1基坑内绑扎冠梁1配筋,灌注桩剔凿至设计标高,桩头钢筋调直,外围一圈600mm范围内砂土人工清平至桩顶以下150mm,并浇筑100mm厚C20混凝土垫层。剔凿后的桩头嵌入冠梁1内50mm,灌注桩主筋锚入冠梁1内770mm。冠梁1内侧与内衬5墙连接处预留双排Φ18@100钢筋(衬墙内侧竖向筋,接收井预留Φ16@150钢筋、工作井预留Φ18@100钢筋)并插入砂土内不得少于1m。冠梁1横向主筋采用焊接连接,箍筋采用绑扎连接,保护层厚度为40mm。S202, tie the crown beam 1 reinforcement in the excavated crown beam 1 foundation pit, chisel the cast-in-place pile to the design elevation, straighten the steel bar at the pile head, artificially level the sand and soil within 600mm of the periphery to 150mm below the pile top, and Pour 100mm thick C20 concrete cushion. The chiseled pile head is embedded in the crown beam 1 for 50mm, and the main reinforcement of the cast-in-place pile is anchored into the crown beam 1 for 770mm. Double rows of Φ18@100 steel bars are reserved at the connection between the inner side of the crown beam 1 and the lining 5 wall (the vertical bars on the inner side of the lining wall, the Φ16@150 steel bars are reserved for the receiving well, and the Φ18@100 steel bars are reserved for the working well) and inserted into the sand. Not less than 1m. The transverse main bars of crown beam 1 are connected by welding, and the stirrups are connected by binding, and the thickness of the protective layer is 40mm.
S203,在冠梁1配筋上施工冠梁1模板,在冠梁1配筋上施工冠梁1模板:模板使用木模双面搭设,拼接处用木方钉牢,梁壁用Q235M14型对拉螺栓(带3片3mm止水钢片)间400×400mm加固,螺栓帽套钢管竖楞,钢管横楞三道环绕连接,竖向间距为800mm且在螺栓加固处设置。S203, construct the crown beam 1 template on the crown beam 1 reinforcement, and construct the crown beam 1 template on the crown beam 1 reinforcement: the template is erected on both sides of the wooden mold, the splicing place is nailed with wooden squares, and the beam wall is paired with Q235M14 The bolts (with 3 pieces of 3mm water-stop steel sheets) are reinforced by 400×400mm, the bolt caps cover the vertical corrugation of the steel pipe, and the horizontal corrugation of the steel pipe is connected in three circles, and the vertical spacing is 800mm and is set at the bolt reinforcement.
S204,浇筑冠梁1混凝土,在浇筑冠梁1混凝土前还需要搭设冠梁1脚手架,冠梁1外部采用双排落地脚手架,内部采用满堂式脚手架施工,用扣件式脚手架搭设,其搭设尺寸为:立杆的纵距为1.5m,立杆的横距为1.5m,立杆的步距为1.8m,冠梁1内外脚手架搭设均为高度为3.6m;内排架距离壁板长度为0.35m,大横杆在下,搭接在大横杆上的小横杆根数为2;采用的钢管类型为Φ48.3×3.6;横杆与立杆连接方式为单扣件;扣件抗滑承载力系数为0.8。冠梁1浇筑采用汽车泵输送C35商品混凝土,浇筑期间采用振捣棒密实,冠梁1顶部收光抹平。S204, the crown beam 1 concrete is poured, and the crown beam 1 scaffold needs to be erected before the crown beam 1 concrete is poured. The outside of the crown beam 1 adopts double-row floor-standing scaffolding, and the interior adopts the full-house type scaffolding construction, and the fastener type scaffolding is used for erection. Its erection size It is: the vertical distance of the vertical pole is 1.5m, the horizontal distance of the vertical pole is 1.5m, the step distance of the vertical pole is 1.8m, the height of the inner and outer scaffolding of the crown beam 1 is 3.6m; the length of the inner bent frame from the wall plate is 0.35m, the large crossbar is at the bottom, and the number of small crossbars lapped on the large crossbar is 2; the type of steel pipe used is Φ48.3×3.6; the connection method between the crossbar and the vertical rod is a single fastener; The sliding capacity factor is 0.8. The crown beam 1 is poured by using a truck pump to transport C35 commercial concrete. During the pouring, the vibrating rod is used to compact it, and the top of the crown beam 1 is smoothed and smoothed.
在对冠梁1施工时需要注意以下几个问题:In the construction of crown beam 1, the following issues should be paid attention to:
①冠梁1施工时,基坑内工作面尺寸不够的情况下,需扩大基坑按照1:1.2比例放坡,不能用砂土回填做遮挡面。①When the crown beam 1 is constructed, if the size of the working face in the foundation pit is not enough, the foundation pit needs to be enlarged and grading at a ratio of 1:1.2, and sand backfill cannot be used as a shielding surface.
②钢筋绑扎需等垫层混凝土达到设计强度时才能进行。② Reinforcement binding can only be carried out when the cushion concrete reaches the design strength.
③浇筑混凝土前,首先要检查脚手架搭设、模板支撑必须牢靠,对拉螺栓必须拧紧,模内杂物必须清理干净。混凝土自由下落高度不能超过2m。③ Before pouring concrete, first check that the scaffolding is erected, the formwork support must be firm, the tie bolts must be tightened, and the sundries in the form must be cleaned up. The free fall height of concrete shall not exceed 2m.
④脚手架搭设前,严格按施工方案放线、设置底座、垫板和标定立杆位置,并从中间部位开始向两边交圈搭设,在搭设完该处的立杆、纵向水平杆后,立即设置连墙杆;剪刀撑与脚手架同步搭设,设置在脚手架外侧立面,沿架高连续布置,斜杆与地面夹角为45°至60°,剪刀撑的斜杆除两端用旋转扣件与脚手架的立杆或大横杆扣紧外,在其中间增加2~4个扣结点。所有剪刀撑搭接长度不得小于1m,并最少采用3组扣件固定;脚手架各杆件相交伸出的端头,均大于10cm,以防止杆件滑脱。每一步距内均设置防护栏杆及安全网。④Before the scaffolding is erected, lay out the line strictly according to the construction plan, set the base, the backing plate and the position of the calibration pole, and set up from the middle part to both sides in a circle. Connecting wall rod; scissors braces and scaffolding are erected synchronously, set on the outer facade of the scaffolding, and continuously arranged along the height of the scaffolding, the angle between the inclined rods and the ground is 45° to 60°, and the two ends of the inclined rods of the scissors braces are connected with rotating fasteners. After the vertical pole or large horizontal bar of the scaffold is fastened, add 2 to 4 fastening points in the middle. The overlapping length of all scissor braces shall not be less than 1m, and shall be fixed by at least 3 sets of fasteners; the ends of the intersecting and protruding ends of the scaffolding rods shall be greater than 10cm to prevent the rods from slipping. Protective railings and safety nets are installed within each step distance.
⑤振捣棒使用前必须对各部件进行认真检查,操作者必须戴绝缘手套和穿绝缘鞋;使用时先要试运转,确认无误后才能正式使用;振动棒要自然地沉入和拔出混凝土,不能用力硬插,硬拔。振捣时须将振动棒上下抽动,以保证振捣均匀,每处振捣的时间必须恰当,既要防止振捣不实,又要防止过振后下层的石子与水泥砂浆离析,影响混凝土的质量,每一插点振捣时间保证在20-30秒,以混凝土表面呈水平并出现均匀的水泥浆和不再冒气泡为止,不显著下沉,表示已振实,即停止振捣。⑤ Before using the vibrator, all parts must be carefully checked, and the operator must wear insulating gloves and insulating shoes; when using the vibrator, a trial run must be performed first, and it can be used formally after confirmation; the vibrator must sink into and pull out of the concrete naturally , can not force hard plug, hard pull. When vibrating, the vibrating rod must be twitched up and down to ensure uniform vibrating. The time of each vibrating must be appropriate. It is necessary to prevent the vibrating from being unrealistic, and to prevent the segregation of the stones in the lower layer and the cement mortar after over-vibration, which will affect the performance of the concrete. For quality, the vibrating time of each insertion point is guaranteed to be 20-30 seconds. When the concrete surface is level and there is a uniform grout and no air bubbles, it does not sink significantly, indicating that it has been vibrated, that is, stop vibrating.
S3,步骤S2中冠梁1的混凝土强度达到设计强度后进行暗梁3和内衬5的施工,步骤S3包括如下步骤:S3, in step S2, after the concrete strength of the crown beam 1 reaches the design strength, the construction of the concealed beam 3 and the inner lining 5 is carried out, and the step S3 includes the following steps:
S301,开挖工作井内土体,冠梁1施工完成,待混凝土强度达到设计强度后,进行下方内衬5土方开挖。内衬5结构范围内无地下水,根据现场实际情况,内衬5土方开挖分为两种方式。S301 , excavating the soil in the working well, the construction of the crown beam 1 is completed, and after the concrete strength reaches the design strength, the earthwork excavation of the lower lining 5 is carried out. There is no groundwater within the range of the inner lining 5 structure. According to the actual situation on site, the earth excavation of inner lining 5 is divided into two methods.
方式一:地面以下15m内的基坑土方采用长臂挖机直接开挖,挖出的土方用推土机推至场外。Method 1: The earthwork of the foundation pit within 15m below the ground is directly excavated with a long-arm excavator, and the excavated earthwork is pushed to the off-site with a bulldozer.
方式3二:地面以下深度大于15m的基坑土方采取人工配合小型挖掘机开挖的方式开挖,选用1台WY15液压反铲挖掘机(0.3m3),基坑土方开挖主要采用挖掘机开挖,人工配合挖除机械挖不到的地方。一次性开挖深度控制在1.8m以内,在松散砂层区每节高度不宜大于1m,先从中部开挖,然后向四周开挖。挖出的土方装入钢制土斗中,采用汽车吊吊运到井外,用推土机将土方推至场外。Method 32: The foundation pit with a depth of more than 15m below the ground is excavated by manual excavation with a small excavator, and a WY15 hydraulic backhoe (0.3m 3 ) is selected. The excavator is mainly used for the excavation of the foundation pit. Excavation, manual cooperation to excavate the places that cannot be excavated by machinery. The one-time excavation depth is controlled within 1.8m, and the height of each section in the loose sand layer area should not be greater than 1m. First excavate from the middle, and then excavate to the surrounding areas. The excavated earth is loaded into the steel earth bucket, hoisted out of the well by a truck, and pushed out of the site by a bulldozer.
此外,暗梁3与内衬5为同时施工:内衬5结构每4.5m设置一道高700mm宽500mm的环形暗梁3,在各灌注桩上环梁双排设置8根Φ16横向间距275mm竖向间距500mm的植筋,钢筋锚入桩内长度560mm,外露440mm。植筋抗拔强度达到设计要求后,可进行暗梁3钢筋绑扎,暗梁3钢筋连接形式采用焊接,保护层厚度为40mm。暗梁3预埋铁与冠梁1预埋铁埋设方式相同,且在同一垂线上。暗梁3的厚度与内衬5的厚度相同,钢筋比内衬5增加的纵横向箍筋,其模板安装与内衬5结构模板安装方法相同,混凝土强度为C35。In addition, the concealed beam 3 and the inner lining 5 are constructed at the same time: a ring-shaped concealed beam 3 with a height of 700 mm and a width of 500 mm is arranged every 4.5m of the inner lining 5 structure, and 8 Φ16 horizontally spaced 275 mm vertical For planting bars with a spacing of 500mm, the length of the bars anchored into the pile is 560mm, and the exposed 440mm. After the pull-out strength of the planted bars reaches the design requirements, the concealed beam 3 steel bars can be bound, and the concealed beam 3 steel bars are connected by welding, and the thickness of the protective layer is 40mm. The embedded iron of the hidden beam 3 and the embedded iron of the crown beam 1 are buried in the same way and on the same vertical line. The thickness of the concealed beam 3 is the same as that of the inner lining 5, and the vertical and horizontal stirrups of the reinforcing bars are increased compared with the inner lining 5. The installation method of the template is the same as that of the inner lining 5 structural template, and the concrete strength is C35.
S302,对开挖土体处的工作井的井壁进行植筋,逆作法施工内衬5时,模板为单面模板,加固时不能与一般模板支护一样直接采用螺杆对拉,需在灌注桩桩体上进行植筋作为对拉螺杆的墙内固定端。S302, plant reinforcements on the well wall of the working well at the excavated soil body. When the inner lining 5 is constructed in the reverse method, the formwork is a single-sided formwork. When reinforcing, the screw can not be directly pulled in the same way as the general formwork support. Reinforcing bars are planted on the pile body as the in-wall fixed end of the pull rod.
井内每节内衬5脚手架搭设完成后,清理灌注桩表面杂土,按对拉螺栓间距进行植筋,植筋直径16mm,植筋完成后72小时后,采用拉力机(千斤顶)对所植钢筋进行拉拔试验,试验合格后进行方可进行下到工序。After the completion of the erection of 5 scaffolds for each section of the lining in the well, clean the soil on the surface of the cast-in-place piles, and plant reinforcing bars according to the spacing between the tie bolts. The diameter of the reinforcing bars is 16mm. Carry out the pull-out test and proceed to the next process only after the test is qualified.
S303,搭设内衬5模板:S303, set up lining 5 templates:
1)钢筋加工:①钢筋在钢筋棚加工配料,运至施工现场后绑扎成型。②钢筋加工前,应将钢筋表面油渍、铁锈、漆污、冰块、积雪等杂物清除干净。1) Steel bar processing: ① Steel bars are processed and batched in the steel bar shed, and then bound and formed after being transported to the construction site. ②Before the steel bar is processed, the surface of the steel bar should be cleaned of oil stains, rust, paint stains, ice cubes, snow and other sundries.
2)钢筋连接:钢筋连接分竖向和水平向钢筋接头,均采用单面焊接连接,焊接长度为10d。2) Steel bar connection: The steel bar connection is divided into vertical and horizontal steel bar joints, all of which are connected by single-sided welding, and the welding length is 10d.
3)钢筋安装:①土方开挖人工修整完毕后,立即进行护壁钢筋绑扎。采用预先下料、井下绑扎的施工方法。第一节内衬5的钢筋制作时,预留第二节内衬5竖向钢筋。绑扎时先将竖向钢筋打入砂中,入砂深度不小于两倍竖向钢筋搭接焊长度,并确保垂直。钢筋间距按设计要求,然后绑扎上水平横向钢筋,水平钢筋在外,竖向7钢筋在内,双排钢筋之间设拉筋和钢筋梯进行绑扎就位,竖向钢筋的连接均采用焊接。②钢筋混凝土内衬5开洞时,墙筋应切断,洞口周边设加强筋,其面积不小于被切断钢筋的面积,且每边不小于4根主筋,并超过洞径每边800~1000mm。③用水泥砂浆垫块控制保护层。④在底板8钢筋制作时,预留最后一节井壁的钢筋。⑤修整合模以后,对伸出的墙体钢筋进行修整,并绑一道临时定位筋,发现钢筋位移和变形时要及时进行调整。3) Reinforcement installation: ①After the manual trimming of earthwork excavation is completed, the reinforcement reinforcement for wall protection shall be bound immediately. The construction method of pre-cutting and underground binding is adopted. When the steel bars of the first section of the inner lining 5 are made, the vertical steel bars of the second section of the inner lining 5 are reserved. When binding, first drive the vertical steel bar into the sand, and the depth of the sand is not less than twice the length of the vertical steel bar lap welding, and ensure that it is vertical. The spacing of the reinforcing bars is according to the design requirements, and then the horizontal horizontal reinforcing bars are bound. The horizontal reinforcing bars are outside, and the vertical 7 reinforcing bars are inside. Between the double rows of reinforcing bars, tie bars and reinforcing bar ladders are arranged to bind them in place, and the connections of the vertical reinforcing bars are all welded. ②When the reinforced concrete lining 5 is opened, the wall reinforcement should be cut off, and the reinforcement reinforcement should be set around the opening, the area of which is not less than the area of the cut steel reinforcement, and each side is not less than 4 main reinforcement, and exceeds the hole diameter by 800-1000mm on each side. ③ Use cement mortar pads to control the protective layer. ④ When making the steel bars of the bottom plate 8, reserve the steel bars of the last section of the shaft wall. ⑤ After repairing the formwork, trim the protruding wall steel bars, and tie a temporary positioning bar. When the displacement and deformation of the steel bars are found, they should be adjusted in time.
4)模板工程:①内衬5模板体系由13mm厚七层胶合板、方木、钢管及对拉螺栓等组合成。②模板加固采用竖向木方和水平钢管(Φ48.3×3.6)组成,竖楞方木间距250mm,横楞钢管间距500mm;③采用Φ14对拉螺栓,一端焊接至植入到灌注桩体的植筋上,另一端与水平钢管拉结以加固模板截面,螺杆横向间距为500mm,竖向间距500mm。④内衬5结构为逆作法施工,安装下节内衬5模板时,上节内衬5混凝土已浇筑完毕,所以需对上下接缝做特殊处理,为方便下节混凝土料投入模板内,在接缝处侧模上口设一杯形投料口,高出上下节接缝300mm,宽出井内衬5250mm,混凝土由投料口入料。⑤模板安装流程:模板制作→模板用螺栓初固定→竖楞安装→横楞安装→调模定模。4) Formwork project: ①The lining 5 formwork system is composed of 13mm thick seven-layer plywood, square wood, steel pipe and tension bolts. ②The formwork reinforcement is composed of vertical wooden squares and horizontal steel pipes (Φ48.3×3.6), the distance between vertical corrugated squares is 250mm, and the distance between horizontal corrugated steel pipes is 500mm; On the planting bar, the other end is tied with the horizontal steel pipe to strengthen the section of the template. The horizontal spacing of the screws is 500mm and the vertical spacing is 500mm. ④ The structure of the inner lining 5 is constructed in the reverse way. When installing the lower section of the inner lining 5 formwork, the concrete of the upper section of the inner lining 5 has been poured, so special treatment should be done to the upper and lower joints. The upper mouth of the side mold at the joint is provided with a cup-shaped feeding port, which is 300mm higher than the joint of the upper and lower sections, and the width is 5250mm from the lining of the well. The concrete is fed from the feeding port. ⑤ Template installation process: template making → initial fixing of template with bolts → vertical corrugated installation → horizontal corrugated installation → mold adjustment and mold setting.
S304,进行内衬5和暗梁3的混凝土施工:S304, carry out the concrete construction of the inner lining 5 and the concealed beam 3:
①混凝土运输:为了保证内衬5结构的浇筑质量,内衬5混凝土采用商品混凝土,采用混凝土运输车运送进场,并用混凝土泵车进行内衬5结构浇筑。①Concrete transportation: In order to ensure the pouring quality of the lining 5 structure, commercial concrete is used for the lining 5 concrete, which is transported into the site by a concrete truck, and the lining 5 structure is poured by a concrete pump truck.
②混凝土浇筑:内衬5机构混凝土等级为C35,内衬5壁厚500mm,底板8厚1000mm,由于采用逆作法施工,结构墙体分多次浇筑。施工连接缝的处理,采用斜缝连接。混凝土浇筑及间歇的全部时间不得超过混凝土的初凝时间,同一节井内衬5的混凝土必须连续浇筑,并在底层混凝土初凝之前将上一层混凝土浇筑完毕。②Concrete pouring: The concrete grade of the lining 5 mechanism is C35, the wall thickness of the lining 5 is 500mm, and the thickness of the bottom plate 8 is 1000mm. Due to the reverse construction method, the structural wall is poured in multiple times. The construction joints shall be treated with oblique joints. The total time of concrete pouring and intermittent shall not exceed the initial setting time of concrete. The concrete of the lining 5 of the same section must be continuously poured, and the upper layer of concrete must be poured before the initial setting of the bottom concrete.
③浇筑混凝土时的振捣:振捣时要快插慢拔;墙板采用向振捣,振捣时上层要插入下层≥50mm。振动棒移动间距≤50cm。每一插点的振捣时间为25±5s,同时配合观察(混凝土表面泛出浆、不再显著下沉、不再出现气泡)来确定其振捣时间。振捣器距离模板≤20cm。从施工缝处开始浇筑混凝土时,不能直接靠近缝边下料,振捣时由远而近向施工缝处推进,距离缝边900mm±100mm处停止振捣,改用人工加强对此处混凝土的振捣,使其结合紧密。③ Vibration when pouring concrete: When vibrating, it should be inserted quickly and slowly pulled out; the wall panel should be vibrated in the direction, and the upper layer should be inserted into the lower layer ≥50mm when vibrating. The moving distance of the vibrating rod is less than or equal to 50cm. The vibrating time of each insertion point is 25 ± 5s, and the vibrating time is determined by observing (the concrete surface is swelled with slurry, no longer sinks significantly, and no air bubbles appear). The distance between the vibrator and the template is less than or equal to 20cm. When pouring concrete from the construction joint, do not directly approach the joint edge to unload the material. When vibrating, advance from far to near to the construction joint, stop vibrating at a distance of 900mm±100mm from the joint edge, and manually strengthen the concrete here. Vibrate to bind tightly.
④浇筑混凝土时的注意事项:为保证模板不跑位不变形,混凝土浇筑强度需要严格控制,控制在1.5m/h的浇筑强度。混凝土自高处倾落的自由高度不得超过2m,浇筑的竖向结构高度超过3m时采用振动溜管使混凝土下落。④ Precautions when pouring concrete: In order to ensure that the formwork does not move or deform, the concrete pouring strength needs to be strictly controlled, and the pouring strength should be controlled at 1.5m/h. The free height of the concrete falling from the height shall not exceed 2m, and the vibrating chute shall be used when the vertical structure height of the pouring exceeds 3m. drop the concrete.
⑤混凝土养护:混凝土浇筑完成后12小时内,进行混凝土养护,顶管井施工完成后必须养护3天。用塑料薄膜覆盖并浇水保持湿润状态,保持混凝土湿润状态浇。浇筑完成的混凝土强度≤1.2Mpa(通过同条件实验来确定)前,不得上人和进行其它作业。⑤Concrete curing: Concrete curing shall be carried out within 12 hours after the completion of concrete pouring, and it must be cured for 3 days after the completion of the pipe jacking construction. Cover with plastic wrap and water to keep it moist, keep the concrete wet and pour. Before the finished concrete strength is less than or equal to 1.2Mpa (determined by experiments under the same conditions), no climbing or other operations are allowed.
S4,进行井底加固旋喷桩7、底板8、洞口加固旋喷桩4的施工,暗梁3、内衬5墙施工至管道顶标高以上停止,将井垫层施工完成后再施工底板8与剩余内衬5墙、洞口加固。垫层、底板8,基坑开挖到底后要及时进行封底施工,确保施工安全。S4, carry out the construction of the bottom reinforced rotary jetting pile 7, the bottom plate 8, and the hole reinforced rotary jetting pile 4, the construction of the hidden beam 3 and the inner lining 5 wall is stopped until the top elevation of the pipeline is above, and the bottom plate 8 is constructed after the well cushion construction is completed. Reinforced with remaining lining 5 walls and openings. Cushion, bottom plate 8, and foundation pit shall be closed in time after excavation to the bottom to ensure construction safety.
(1)垫层施工:垫层采用C20素混凝土浇筑,厚度为200mm。施工之前平整并清楚坑底杂物,混凝土浇筑高度控制在设计标高内,施工完成后,人员不能直接踩踏。(1) Cushion construction: The cushion is poured with C20 plain concrete with a thickness of 200mm. Before construction, level and clear the debris at the bottom of the pit. The height of concrete pouring is controlled within the design elevation. After the construction is completed, personnel cannot directly step on it.
(2)底板8、剩余内衬5、洞口加固施工:①底板8钢筋绑扎:底板8钢筋绑扎两层,下层钢筋横纵间距为Φ22@150保护层40mm,钢筋两端90°向上350mm弯钩;上层钢筋横纵间距为Φ22@120(工作井为Φ22@100)保护层35mm,双层钢筋伸入墙内≥12d,且至少到墙中线,钢筋连接形式为绑扎搭接。(2) Bottom plate 8, remaining lining 5, hole reinforcement construction: ① Bottom plate 8 steel bar binding: Bottom plate 8 steel bars are bound in two layers, the horizontal and vertical spacing of the lower steel bars is Φ22@150 protective layer 40mm, and the two ends of the steel bar are 90° upward with 350mm hooks ;The horizontal and vertical spacing of the upper steel bars is Φ22@120 (the working well is Φ22@100), the protective layer is 35mm, the double-layer steel bars extend into the wall for ≥12d, and at least reach the center line of the wall, and the steel bars are connected in the form of binding and lap.
②最后一节内衬5墙、洞口加固钢筋绑扎:最后一节内衬5墙竖向钢筋锚入底板8,内层钢筋90°弯钩锚入底板8长度为36d,与底板8连接处设置4Φ25加强筋横向连接。内衬5墙在设计洞口处加宽800mm,并设置洞口加强钢筋,剩余最后内衬5混凝土浇筑采用预制钢模板加固,浇筑方法与上层内衬5墙施工方法相同。②The last section is lined with 5 walls and the openings are reinforced with steel bars: the last section of the lining 5 wall is anchored with vertical steel bars into the bottom plate 8, and the 90° hook of the inner layer of steel bars is anchored into the bottom plate 8. The length is 36d, and the connection with the bottom plate 8 is set. 4Φ25 reinforcing ribs are connected laterally. The inner lining 5 wall is widened by 800mm at the designed opening, and the reinforcement reinforcement is set at the opening. The remaining final lining 5 concrete is reinforced with prefabricated steel formwork. The pouring method is the same as the construction method of the upper lining 5 wall.
综上所述,本实用新型中的工作井的内衬5与暗梁3间隔位于钻孔灌注桩2的内侧壁上,内衬5与暗梁3形成一个稳固的结构,能够增强工作井内侧壁整体的承压强度,同时内衬5与暗梁3同时施工,便于提升施工的效率。此外,本实用新型的施工方法整体施工效率较高。To sum up, the inner lining 5 and the concealed beam 3 of the working well in the present invention are located on the inner side wall of the bored pile 2 at intervals, and the inner lining 5 and the concealed beam 3 form a stable structure, which can strengthen the inner side of the working well. The compressive strength of the whole wall, and the lining 5 and the concealed beam 3 are constructed at the same time, which is convenient to improve the efficiency of construction. In addition, the overall construction efficiency of the construction method of the present invention is relatively high.
以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均在本实用新型待批权利要求保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention are all within the scope of the present invention. Within the scope of protection of the new type of pending claims.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920399744.3U CN209723033U (en) | 2019-03-27 | 2019-03-27 | Pipe jacking working well applicable to desert waterless sand layer area |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920399744.3U CN209723033U (en) | 2019-03-27 | 2019-03-27 | Pipe jacking working well applicable to desert waterless sand layer area |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209723033U true CN209723033U (en) | 2019-12-03 |
Family
ID=68689040
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920399744.3U Withdrawn - After Issue CN209723033U (en) | 2019-03-27 | 2019-03-27 | Pipe jacking working well applicable to desert waterless sand layer area |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209723033U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797778A (en) * | 2019-03-27 | 2019-05-24 | 中铁四局集团有限公司 | Pipe-jacking working well applicable to desert anhydrous sand layer area and construction method |
CN113027463A (en) * | 2021-03-24 | 2021-06-25 | 山东建筑大学 | Suspension type reverse wall working well supporting structure and construction method |
CN114482079A (en) * | 2022-01-24 | 2022-05-13 | 中铁四局集团有限公司 | Pipe jacking well deep foundation pit construction method |
-
2019
- 2019-03-27 CN CN201920399744.3U patent/CN209723033U/en not_active Withdrawn - After Issue
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797778A (en) * | 2019-03-27 | 2019-05-24 | 中铁四局集团有限公司 | Pipe-jacking working well applicable to desert anhydrous sand layer area and construction method |
CN113027463A (en) * | 2021-03-24 | 2021-06-25 | 山东建筑大学 | Suspension type reverse wall working well supporting structure and construction method |
CN113027463B (en) * | 2021-03-24 | 2022-08-30 | 山东建筑大学 | Suspension type reverse wall working well supporting structure and construction method |
CN114482079A (en) * | 2022-01-24 | 2022-05-13 | 中铁四局集团有限公司 | Pipe jacking well deep foundation pit construction method |
CN114482079B (en) * | 2022-01-24 | 2023-09-19 | 中铁四局集团有限公司 | Construction method for deep foundation pit of pipe jacking well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101914925B (en) | Basement by using optimized composite prefabricated arch wall as external wall | |
CN102031784B (en) | Slope protection pile pouring and cable bolting construction method for deep foundation pit | |
WO2023077552A1 (en) | Construction method for foundation pit enclosure and earth excavation | |
CN111733828A (en) | Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology | |
CN109797778A (en) | Pipe-jacking working well applicable to desert anhydrous sand layer area and construction method | |
CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
CN105804089B (en) | Locally increase deep support system and its construction method after a kind of former deep foundation pit construction | |
CN114439487B (en) | A construction method for opening a connecting passage in an existing shield tunnel | |
CN105201513A (en) | Shaft construction method for rail transit | |
CN207777770U (en) | A kind of precast spliced pipe fitting jacking system | |
CN103343544A (en) | Construction method for large-scale open caisson | |
CN110905523A (en) | Subway vertical shaft construction method | |
CN108612110A (en) | A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting | |
CN111119904A (en) | Construction Method of Tunnel in Karst Section of Weak Surrounding Rock | |
CN109488347B (en) | Excavation construction method for special stratum chamber | |
CN209723033U (en) | Pipe jacking working well applicable to desert waterless sand layer area | |
CN107268634A (en) | Deep basal pit waist rail construction typified form system | |
CN113236259A (en) | Special construction process for excavation and supporting of combined tunnel | |
CN118110193A (en) | The whole process construction method of large diameter caisson in complex geological conditions | |
CN114411756A (en) | Construction method and construction device for open-cut foundation pit of water-rich sand layer subway station without precipitation | |
CN111042569B (en) | Construction method for additionally building linear accelerator machine room in limited space of hospital basement | |
CN113846695B (en) | Reverse construction method basement construction method | |
CN103866982A (en) | Petal artistic framework construction method | |
CN207211188U (en) | Outer wall of underground structure HCMW engineering methods overlap wall | |
CN111379273A (en) | Construction method of corrugated steel comprehensive pipe gallery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20191203 Effective date of abandoning: 20210428 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20191203 Effective date of abandoning: 20210428 |