[go: up one dir, main page]

CN113605389B - Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile - Google Patents

Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile Download PDF

Info

Publication number
CN113605389B
CN113605389B CN202111014058.8A CN202111014058A CN113605389B CN 113605389 B CN113605389 B CN 113605389B CN 202111014058 A CN202111014058 A CN 202111014058A CN 113605389 B CN113605389 B CN 113605389B
Authority
CN
China
Prior art keywords
pipe
pile head
cutting
tube
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111014058.8A
Other languages
Chinese (zh)
Other versions
CN113605389A (en
Inventor
李虎
叶建军
陈伟明
王冠海
彭庆波
张红玉
王鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
First Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
Hubei University of Technology
First Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology, First Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Hubei University of Technology
Priority to CN202111014058.8A priority Critical patent/CN113605389B/en
Publication of CN113605389A publication Critical patent/CN113605389A/en
Application granted granted Critical
Publication of CN113605389B publication Critical patent/CN113605389B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a green dismantling method for a pile head pre-buried pipe and a rope saw cutting of a reinforced concrete cast-in-place pile, which adopts a mode of arranging 4 pre-buried pipes, namely a waist pipe, a rope penetrating pipe, a sleeve and a hoisting pipe, on a cast-in-place pile head and using the rope saw to cut, thereby realizing the dismantling of the green pile head without drilling, stripping, vibration, dust and noise; the invention has the advantages of less used equipment, mechanical completion of main operation, high cutting precision, flat cut, less workload of manual leveling and scabbling, low labor intensity and high safety; the operation provided by the invention has no damage to the pile body concrete and the steel bars, the construction quality is high, and compared with other construction methods, the method also has the advantages of low construction cost and short construction period.

Description

钢筋混凝土灌注桩桩头预埋管和绳锯切割绿色拆除方法Green demolition method of reinforced concrete cast-in-place pile head embedded pipe and wire saw cutting

技术领域technical field

本发明涉及钢筋混凝土结构拆除领域,具体地讲涉及一种钢筋混凝土灌注桩桩头预埋管和绳锯切割绿色拆除方法。The invention relates to the field of dismantling of reinforced concrete structures, in particular to a green dismantling method for cutting a reinforced concrete cast-in-place pile head embedded pipe and a wire saw.

背景技术Background technique

工程建设中,钢筋混凝土灌注桩是在土质地基上的常见基础。为了保证桩身质量,通常都会超灌。混凝土硬化后,需要破除超灌的桩头。常见的破桩头工艺有人工破除法,该法需要大量人工,具有劳动强度高、生产效率低的明显缺点,随着人工费用的逐步提高,将会彻底失去市场。另外,使用挖机配合破碎锤施工,也是之前较为常见的工法,但由于该法噪声和振动很大,对桩身混凝土质量有较大影响,也基本被市场淘汰了;源自2012年“法国国际工程机械展览会”的液压破桩机被引入国内,该技术具备施工效率高,噪音较小,对桩身损伤较小的优点,已经得到较大面积的应用。但该技术也有一些缺点:如不能处理尺寸不规整(如桩身局部突出)的桩头,对纵筋密布、尺寸较大的桩头破碎效率下降;四周强大压力也会对混凝土和钢筋有一定损伤,特别是钢筋与混凝土的锚固力产生不利影响;为保护桩身混凝土不受破坏,要留较长的保护段。该保护段还需人工或机械凿毛或修平处理,这增加了费用和工期,削弱了该技术的优势。2018年,陕西省交通建设集团公司的马佳和张建光在《公路交通科技》2018年第9期的论文《环切法破桩头在桩基础工程中的应用》提出一种新工法,本工法是将事先加工好的脱松套直接套入钢筋笼外露承台、系梁外端的主筋和声测管表面,使桩头混凝土和主筋不发生握裹,再用双刀环切法,两次环切桩基,桩头切除位置采用风镐垂直桩身方向钻孔,将分离楔子插入钻孔中,并采用外力进行敲击,直至桩头与桩身完全分离,然后利用起吊设备吊出上部桩头。本工艺缩短了作业工序与时间,相对于人工破碎工法减少了人工费和水费,确保主筋少受损伤、桩基完整性及操作工人的健康和环保施工。 但该法需要风镐钻孔,噪音较大,仍有粉尘污染,采用人工打击楔子的办法劈裂桩身混凝土劳动强度较大,效率较低。为了克服这个缺点,2020年,中铁市政环境建设有限公司的刘克亮在《建筑施工》期刊2020年12期上发表的论文《钻孔灌注桩免剥离免环切截桩头新工艺》一文中,提出一种新的免剥离免环工法,该工法的特点是将事先加工好的套管直接套入钢筋笼端部的主筋和声测管外端表面并固定,将桩头部位的混凝土与主筋、声测管有效隔离,隔断混凝土与钢筋、声测管间的握裹力及摩擦力;将复合脱松套箍在桩顶处主筋外围,形成裂缝诱发槽;采用水钻在复合脱松套形成的裂缝诱发槽内钻孔,用液压劈裂枪插入孔洞内截断桩头混凝土;最后利用起吊设备将桩头吊出。该工法在吸取了马佳和张建光提出工法的优点的基础上,改进了钻孔方式和劈裂方法,取得降低粉尘和提高劈裂效率、降低劈裂劳动强度的技术进步。但该法也存在缺点:需要三种机械:钻机、液压劈裂机和吊车,对设备要求较高,同时,由于劈裂形成的裂口可能不平齐,需要留较长保护段(10cm以上),该段需要人工和机械凿毛或修平,增加了成本。另外,上述两种工法在声测管外套上套管,对声测检测结果也有影响。为了克服这些的缺点,需要在上述技术的基础上加以改进,开发一种新的免剥离免钻孔的少用设备的桩头绿色拆除工法。In engineering construction, reinforced concrete cast-in-place piles are common foundations on soil foundations. In order to ensure the quality of the pile body, it is usually overfilled. After the concrete has hardened, the overfilled pile heads need to be removed. The common method of breaking pile head is manual breaking method. This method requires a lot of labor and has obvious shortcomings of high labor intensity and low production efficiency. With the gradual increase of labor costs, it will completely lose the market. In addition, the use of excavators and breakers for construction is also a relatively common construction method before, but due to the large noise and vibration of this method, which has a great impact on the quality of the concrete of the pile body, it has also been basically eliminated by the market; The hydraulic pile breaker of "International Construction Machinery Exhibition" was introduced into China. This technology has the advantages of high construction efficiency, less noise and less damage to the pile body, and has been applied in a large area. However, this technology also has some disadvantages: if it cannot handle pile heads with irregular dimensions (such as partial protruding of the pile body), the crushing efficiency of pile heads with dense longitudinal reinforcement and larger size will decrease; the strong surrounding pressure will also have a certain effect on concrete and steel bars Damage, especially the anchoring force of steel bars and concrete, has an adverse effect; in order to protect the concrete of the pile body from damage, a longer protection section should be reserved. The protection section also needs manual or mechanical chiseling or smoothing, which increases the cost and construction period and weakens the advantages of this technology. In 2018, Ma Jia and Zhang Jianguang of Shaanxi Provincial Communications Construction Group Co., Ltd. proposed a new construction method in the paper "Application of Circumcision Method for Pile Head Breaking in Pile Foundation Engineering" in the 9th issue of "Highway Transportation Science and Technology" in 2018. This construction method It is to directly insert the pre-processed release sleeve into the exposed cap of the steel cage, the main reinforcement at the outer end of the tie beam and the surface of the acoustic tube, so that the concrete at the pile head and the main reinforcement do not get caught, and then use the double-knife ring cutting method, twice. Circumcising the pile foundation, the cutting position of the pile head is drilled in the direction of the vertical pile body with a pneumatic pick, insert the separating wedge into the drill hole, and use external force to strike until the pile head and the pile body are completely separated, and then use the lifting equipment to lift the upper part. pile head. This process shortens the operation procedure and time, reduces labor costs and water costs compared with the manual crushing method, and ensures less damage to the main reinforcement, integrity of the pile foundation, and the health and environmental protection of the operators. However, this method requires an air pick to drill holes, which is noisy and still polluted by dust. The method of manually hitting the wedge to split the concrete of the pile body is labor-intensive and low-efficiency. In order to overcome this shortcoming, in 2020, Liu Keliang of China Railway Municipal Environmental Construction Co., Ltd. published the paper "New Technology of Peel-free and Circumcision-free Pile Heads for Bored Cast-in-place Pile" published in the 12th issue of the "Construction" journal in 2020. A new peel-free and ring-free construction method is characterized in that the pre-processed casing is directly inserted into the main reinforcement at the end of the reinforcement cage and the outer end surface of the acoustic tube and fixed, and the concrete at the pile head is connected with the main reinforcement. , The acoustic measuring tube is effectively isolated, and the gripping force and friction between the concrete and the steel bar and the acoustic measuring tube are separated; The crack-inducing groove is drilled, and the hydraulic splitting gun is inserted into the hole to cut off the pile head concrete; finally, the pile head is lifted out by lifting equipment. Based on the advantages of the method proposed by Ma Jia and Zhang Jianguang, the method improves the drilling method and splitting method, and achieves technological progress in reducing dust, improving splitting efficiency and reducing splitting labor intensity. However, this method also has disadvantages: three types of machinery are needed: drilling rig, hydraulic splitting machine and crane, which require high equipment. At the same time, since the cracks formed by splitting may not be flush, it is necessary to leave a long protection section (above 10cm), This section requires manual and mechanical chipping or trimming, adding to the cost. In addition, the above two construction methods are sleeved on the outer casing of the acoustic measuring tube, which also affects the acoustic measuring result. In order to overcome these shortcomings, it is necessary to improve on the basis of the above-mentioned technology, and develop a new green demolition method for pile heads that is free of stripping and drilling, and uses less equipment.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于克服上述不足,提供一种钢筋混凝土灌注桩桩头预埋管和绳锯切割绿色拆除方法,在混凝土灌注桩设计施工之初就考虑拆除超灌桩头的问题,通过在桩头布置多种预埋管,达成免剥离免钻孔少用机械设备的使用绳锯切割、低成本、低环境影响的绿色桩头拆除目的。The object of the present invention is to overcome the above-mentioned deficiencies, provide a reinforced concrete cast-in-place pile head pre-embedded pipe and a wire saw cutting green dismantling method, at the beginning of the design and construction of the concrete cast-in-place pile, the problem of removing the super-cast pile head is considered, A variety of pre-embedded pipes are arranged at the head to achieve the purpose of green pile head removal with no peeling, no drilling, less mechanical equipment, wire saw cutting, low cost and low environmental impact.

本发明为解决上述技术问题,所采用的技术方案是:一种钢筋混凝土灌注桩桩头预埋管,它包括在钢筋混凝土灌注桩施工期便预埋于其桩头内的腰管、穿绳管、套管和吊装管,所述腰管和穿绳管布置在桩顶设计标高以上区域的同一水平面内,该平面即为切割平面,切割平面以上部分即为桩头的切除部分,桩头的纵筋在切割平面以上部分套有套管,桩头切割平面以上部分的同一水平面内预埋有吊装管,吊装管的纵轴指向所在水平面的圆心。In order to solve the above-mentioned technical problems, the technical scheme adopted in the present invention is: a reinforced concrete cast-in-place pile head pre-embedded pipe, which comprises a waist pipe, a wire rope that are pre-buried in the pile head during the construction period of the reinforced concrete cast-in-place pile Pipe, casing and hoisting pipe, the waist pipe and the rope-piercing pipe are arranged in the same horizontal plane of the area above the design elevation of the pile top, this plane is the cutting plane, and the part above the cutting plane is the excised part of the pile head, the pile head The longitudinal rib of the pile head is covered with a casing above the cutting plane, and a hoisting pipe is pre-buried in the same horizontal plane of the part above the cutting plane of the pile head, and the longitudinal axis of the hoisting pipe points to the center of the horizontal plane.

优选地,所述腰管和穿绳管布置在桩顶设计标高以上3-6 cm的同一水平面内。Preferably, the waist tube and the rope threading tube are arranged in the same horizontal plane 3-6 cm above the design elevation of the pile top.

优选地,所述腰管紧贴纵筋外侧,围成一个完整的圈;穿绳管中间部分紧贴纵筋内侧,两端伸至腰管内侧,两端离最近纵筋直线距离大于3 cm。Preferably, the waist tube is close to the outside of the longitudinal rib to form a complete circle; the middle part of the rope-passing tube is close to the inside of the longitudinal rib, both ends extend to the inside of the waist tube, and the linear distance between the two ends is greater than 3 cm from the nearest longitudinal rib .

优选地,所述桩头的切除部分的上半部分在同一水平面内预埋有多根吊装管,该水平面离切除部分顶部的距离大于切除部分总高度的四分之一,吊装管与桩身表面交点均匀分布在圆周上,吊装管外端与混凝土保护层平齐或伸出混凝土保护层表面1-2 cm。Preferably, a plurality of hoisting pipes are pre-buried in the upper half of the cut part of the pile head in the same horizontal plane, and the distance between the horizontal plane and the top of the cut part is greater than one quarter of the total height of the cut part, and the hoisting pipes are connected to the pile body. The surface intersection points are evenly distributed on the circumference, and the outer end of the hoisting pipe is flush with the concrete protective layer or protrudes 1-2 cm from the surface of the concrete protective layer.

优选地,所述腰管采用PVC塑料管或橡胶管预埋形成;穿绳管和套管采用PVC塑料管预埋形成;所述腰管直径等于或大于桩身混凝土保护层厚度;穿绳管内径为15-25 mm;套管内径大于纵筋直径4-20 mm。Preferably, the waist pipe is formed by pre-embedding a PVC plastic pipe or a rubber pipe; the rope threading pipe and the casing are formed by pre-buying a PVC plastic pipe; the diameter of the waist pipe is equal to or greater than the thickness of the concrete protection layer of the pile body; the rope threading pipe The inner diameter is 15-25 mm; the inner diameter of the casing is 4-20 mm larger than the longitudinal rib diameter.

优选地,所述腰管用一根PVC塑料管或橡胶管的两端对接而成,对接处缠绕胶带宽度大于5cm;穿绳管两端用木塞或石膏堵塞;套管上下两端用石膏堵塞;吊装管两端用木塞堵塞。Preferably, the waist tube is formed by butting two ends of a PVC plastic tube or rubber tube, and the width of the wrapping tape at the joint is greater than 5cm; the two ends of the rope-passing tube are blocked with corks or gypsum; the upper and lower ends of the casing are blocked with gypsum ; Both ends of the hoisting pipe are blocked with wooden plugs.

优选地,所述腰管和穿绳管均用绑扎铁丝绑扎在纵筋上,所有与纵筋接触处均绑扎;每根套管上端管壁钻孔,穿过铁丝后绑扎在该根套管套住的纵筋上端。Preferably, the waist tube and the rope-piercing tube are both bound on the longitudinal bars with binding iron wires, and all the places in contact with the longitudinal bars are bound; the upper end wall of each casing is drilled and tied to the casing after passing through the wire. Cover the upper end of the longitudinal rib.

优选地,所述桩头中沿纵向还布置有多根声测管,声测管在切割平面处向桩心弯曲,在纵筋和声测管之间留出间隙供穿绳管穿过,声测管在其它高度紧贴纵筋或箍筋,并绑扎在纵筋或箍筋上。Preferably, a plurality of acoustic pipes are arranged in the longitudinal direction of the pile head, the acoustic pipes are bent towards the pile core at the cutting plane, and a gap is left between the longitudinal bars and the acoustic pipes for the rope-passing pipes to pass through, The acoustic tube is close to the longitudinal bars or stirrups at other heights, and is bound to the longitudinal bars or stirrups.

另外,本发明还公开上述钢筋混凝土灌注桩桩头预埋管对桩头进行绳锯切割的方法,包括以下步骤:In addition, the present invention also discloses a method for cutting the pile head with a wire saw by the pre-buried pipe at the pile head of the reinforced concrete cast-in-place pile, comprising the following steps:

1)找到腰管,破坏包裹腰管的混凝土保护层,解除缠绕胶带和绑扎铁丝后取出腰管;1) Find the waist tube, destroy the concrete protective layer that wraps the waist tube, remove the waist tube after unwinding the tape and binding iron wire;

2)清理穿绳管两端堵塞物,并从穿绳管两端开口穿过绳锯锯条;2) Clean the blockages at both ends of the rope threading pipe, and pass the wire saw blade through the openings at both ends of the rope threading pipe;

3)开动绳锯沿切割平面切割混凝土和声测管,切割至边界线为止;切割时,采用水管对准穿绳管的一端开口,输入润滑用水至切割面的绳锯锯条上,随着切割深度增大,逐步加大水压和水量;3) Start the wire saw to cut the concrete and the acoustic tube along the cutting plane until the boundary line; when cutting, use the water pipe to align the opening of one end of the wire pipe, and input the lubricating water to the wire saw blade on the cutting surface, and follow the cutting. As the depth increases, gradually increase the water pressure and water volume;

4)解开套管上端铁丝,破除切割平面上的穿绳管外侧的混凝土;沿切割平面剪开穿绳管;4) Untie the wire at the upper end of the casing to break the concrete on the outside of the rope-passing pipe on the cutting plane; cut the rope-passing pipe along the cutting plane;

5)用扁头钢钎插入切割平面的切割面,撬起钢钎使保留混凝土沿切割平面断开;5) Insert the flat head steel drill into the cutting surface of the cutting plane, and pry up the steel drill so that the reserved concrete is broken along the cutting plane;

6)打开吊装管外端木塞,插入长度大于吊装管深度10-15cm的圆钢,并在圆钢与吊装管之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe, insert a round steel with a length greater than the depth of the hoisting pipe 10-15cm, and insert a wedge-shaped wooden bar in the gap between the round steel and the hoisting pipe to fix it, tie a steel wire rope on the round steel, and hoist it with a crane Pile head cut off part.

优选地,所述步骤3)具体为:开动绳锯沿切割平面切割混凝土和声测管,切割至边界线为止;切割初期润滑用水采用水管对准穿绳管的一端开口,输入到切割平面的切割面上;切割深度大于5cm后,在穿绳管中点处剪除2cm长管道,改从该处插入水管,将润滑用水输入到切割面的锯条上,随着切割深度增大,逐步深插水管以接近绳锯锯条或加大水压和水量。Preferably, the step 3) is specifically as follows: start the wire saw to cut the concrete and the acoustic tube along the cutting plane, and cut to the boundary line; use a water pipe for the lubrication water in the early stage of cutting to align the opening of one end of the wire pipe, and input it into the cutting plane. On the cutting surface; after the cutting depth is greater than 5cm, cut off the 2cm long pipe at the midpoint of the rope-passing pipe, insert the water pipe from this place, and input the lubricating water to the saw blade on the cutting surface, and gradually insert it deeply as the cutting depth increases. Water hose to get close to the wire saw blade or increase the water pressure and water volume.

本发明具有以下有益效果:The present invention has the following beneficial effects:

(1)本发明通过巧妙布置多种类型预埋管和将绳锯工艺引入灌注桩桩头拆除中,实现了灌注桩桩头的免钻孔、免剥离、无振动、少粉尘、噪音小的绿色拆除过程;(1) The present invention realizes the drilling-free, peeling-free, vibration-free, less dust and low noise of the cast-in-place pile head by ingeniously arranging various types of pre-embedded pipes and introducing the wire sawing process into the demolition of the cast-in-place pile head. green demolition process;

(2)本发明提供的技术方案,所用设备较少,主要操作都是机械完成,人工劳动强度低,安全性高;(2) The technical solution provided by the present invention uses less equipment, the main operations are completed mechanically, the labor intensity is low, and the safety is high;

(3)本发明提供的技术方案,由于绳锯切割精度高,切口平整,只需要少量人工修平和凿毛工作,对混凝土和钢筋都无损伤,施工质量高;(3) In the technical solution provided by the present invention, due to the high cutting precision of the wire saw and the smooth incision, only a small amount of manual leveling and chiseling work is required, and the concrete and steel bars are not damaged, and the construction quality is high;

(4)本发明提供的技术方案,由于不需要在声测管外套管,声测管之间混凝土中没有布置预埋管件,不影响声测管对桩基的检测结果;(4) In the technical solution provided by the present invention, since the outer casing of the acoustic measuring pipe is not required, there is no pre-embedded pipe fittings arranged in the concrete between the acoustic measuring pipes, which does not affect the detection result of the acoustic measuring pipe on the pile foundation;

(5)本发明避免了剥离混凝土保护层,绳锯切割时又避开了纵筋,施工效率高,预计是人工破桩头工艺的2-3倍效率;由于比刘克亮等的破桩头工艺减少人工修平工作,效率上有10-20%的优势,因此,本发明比已有技术有较大的造价和工期优势;(5) The present invention avoids peeling off the concrete protective layer, and avoids the longitudinal bars when the wire saw is cut, and the construction efficiency is high, which is expected to be 2-3 times the efficiency of the artificial pile head breaking process; The manual leveling work is reduced, and the efficiency has an advantage of 10-20%. Therefore, the present invention has greater advantages in cost and construction period than the prior art;

(6)本发明通过预埋腰管,可以在破除桩头时实现精确定位切割平面,免除破碎或切割混凝土保护层;通过预埋穿绳管可以让绳锯避开钢筋,加快切割进度;通过在纵筋上布置套管,可避免了传统破桩头作业中的混凝土剥离操作,也避免了对纵筋的损伤;通过预埋吊装管,方便了切割桩头的吊装作业,也避免了钻孔作业。(6) In the present invention, by pre-embedding the waist tube, the cutting plane can be accurately positioned when the pile head is broken, avoiding crushing or cutting the concrete protective layer; by pre-embedding the wire tube, the wire saw can avoid the steel bars and speed up the cutting progress; Arranging the casing on the longitudinal reinforcement can avoid the concrete stripping operation in the traditional pile head breaking operation, and also avoid the damage to the longitudinal reinforcement; by pre-embedding the hoisting pipe, the hoisting operation of the cutting pile head is convenient, and the drilling operation is avoided. hole work.

附图说明Description of drawings

图1是钢筋混凝土灌注桩桩头的A-A纵截面结构示意图;Fig. 1 is the A-A longitudinal section structure schematic diagram of reinforced concrete cast-in-place pile head;

图2是钢筋混凝土灌注桩桩头未拆除时的B-B横截面示意图;Fig. 2 is the B-B cross-sectional schematic diagram when the reinforced concrete cast-in-place pile head is not removed;

图3是钢筋混凝土灌注桩桩头用绳锯拆除时的B-B横截面示意图;Fig. 3 is the B-B cross-sectional schematic diagram when the reinforced concrete cast-in-place pile head is removed with a wire saw;

图4是钢筋混凝土灌注桩桩头的C-C横截面示意图;Fig. 4 is the C-C cross-sectional schematic diagram of reinforced concrete cast-in-place pile head;

图中,1-桩头,2-纵筋,3-箍筋,4-腰管,5-穿绳管,6-套管,7-吊装管,8-绑扎铁丝,9-缠绕胶带,10-绳锯锯条,11-声测管,12-边界线,13-切割面,14-保留混凝土,15-水管。In the figure, 1-pile head, 2-longitudinal reinforcement, 3-stirrup, 4-waist pipe, 5-rope pipe, 6-casing, 7-hoisting pipe, 8-binding iron wire, 9-winding tape, 10 - Wire saw blade, 11- Acoustic tube, 12- Boundary line, 13- Cutting face, 14- Retain concrete, 15- Water pipe.

具体实施方式Detailed ways

下面结合附图和具体实施例对本发明作进一步的详细描述。The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

如图1至4所示,一种钢筋混凝土灌注桩桩头预埋管,它包括在钢筋混凝土灌注桩施工期便预埋于其桩头1内的腰管4、穿绳管5、套管6和吊装管7,所述腰管4和穿绳管5布置在桩顶设计标高以上区域的同一水平面内,该平面即为切割平面,切割平面以上部分即为桩头1的切除部分,桩头1的纵筋2在切割平面以上部分套有套管6,桩头1切割平面以上部分的同一水平面内预埋有吊装管7,吊装管7的纵轴指向所在水平面的圆心。As shown in Figures 1 to 4, a reinforced concrete cast-in-place pile head pre-embedded pipe includes a waist pipe 4, a rope threading pipe 5 and a casing that are embedded in the pile head 1 during the construction period of the reinforced concrete cast-in-place pile. 6 and the hoisting pipe 7, the waist pipe 4 and the rope-piercing pipe 5 are arranged in the same horizontal plane of the area above the design elevation of the pile top, this plane is the cutting plane, and the part above the cutting plane is the excision part of the pile head 1, the pile The longitudinal rib 2 of the head 1 is covered with a casing 6 above the cutting plane, and a hoisting pipe 7 is pre-embedded in the same horizontal plane of the part above the cutting plane of the pile head 1, and the longitudinal axis of the hoisting pipe 7 points to the center of the horizontal plane.

优选地,所述腰管4和穿绳管5布置在桩顶设计标高以上3-6 cm的同一水平面内。Preferably, the waist tube 4 and the rope threading tube 5 are arranged in the same horizontal plane 3-6 cm above the design elevation of the pile top.

优选地,所述腰管4紧贴纵筋2外侧,围成一个完整的圈;穿绳管5中间部分紧贴纵筋2内侧,两端伸至腰管4内侧,两端离最近纵筋2直线距离大于3 cm。Preferably, the waist tube 4 is close to the outer side of the longitudinal rib 2 to form a complete circle; the middle part of the rope threading tube 5 is close to the inner side of the longitudinal rib 2, the two ends extend to the inner side of the waist tube 4, and the two ends are away from the nearest longitudinal rib. 2 The straight-line distance is greater than 3 cm.

优选地,所述桩头1的切除部分的上半部分在同一水平面内预埋有多根吊装管7,该水平面离切除部分顶部的距离大于切除部分总高度的四分之一,吊装管7与桩身表面交点均匀分布在圆周上,吊装管7外端与混凝土保护层平齐或伸出混凝土保护层表面1-2 cm。Preferably, a plurality of hoisting pipes 7 are pre-embedded in the upper half of the cut part of the pile head 1 in the same horizontal plane, and the distance from the horizontal plane to the top of the cut part is greater than a quarter of the total height of the cut part. The hoisting pipes 7 The intersection points with the surface of the pile body are evenly distributed on the circumference, and the outer end of the hoisting pipe 7 is flush with the concrete protective layer or protrudes 1-2 cm from the surface of the concrete protective layer.

优选地,所述腰管4采用PVC塑料管或橡胶管预埋形成;穿绳管5和套管6采用PVC塑料管预埋形成;所述腰管4直径等于或大于桩身混凝土保护层厚度;穿绳管5内径为15-25mm;套管6内径大于纵筋2直径4-20 mm。Preferably, the waist tube 4 is formed by pre-embedding a PVC plastic tube or a rubber tube; the rope threading tube 5 and the sleeve 6 are formed by pre-embedding a PVC plastic tube; the diameter of the waist tube 4 is equal to or greater than the thickness of the concrete protective layer of the pile body ; The inner diameter of the rope threading pipe 5 is 15-25 mm; the inner diameter of the casing 6 is larger than the diameter of the longitudinal rib 2 by 4-20 mm.

优选地,所述腰管4用一根PVC塑料管或橡胶管的两端对接而成,对接处缠绕胶带9宽度大于5cm;穿绳管5两端用木塞或石膏堵塞;套管6上下两端用石膏堵塞;吊装管7两端用木塞堵塞。Preferably, the waist tube 4 is formed by butting two ends of a PVC plastic tube or rubber tube, and the width of the wrapping tape 9 at the butt joint is greater than 5 cm; the two ends of the rope-passing tube 5 are blocked with wooden plugs or plaster; the upper and lower casings 6 are up and down Both ends are blocked with gypsum; both ends of the hoisting pipe 7 are blocked with wooden plugs.

优选地,所述腰管4和穿绳管5均用绑扎铁丝8绑扎在纵筋2上,所有与纵筋2接触处均绑扎;每根套管6上端管壁钻孔,穿过铁丝后绑扎在该根套管6套住的纵筋2上端。Preferably, both the waist tube 4 and the rope threading tube 5 are bound on the longitudinal bars 2 with binding iron wires 8, and all the places in contact with the longitudinal bars 2 are bound; It is bound on the upper end of the longitudinal rib 2 covered by the sleeve 6 .

优选地,所述桩头1中沿纵向还布置有多根声测管11,声测管11在切割平面处向桩心弯曲,在纵筋2和声测管11之间留出间隙供穿绳管5穿过,声测管11在其它高度紧贴纵筋2或箍筋3,并绑扎在纵筋2或箍筋3上。Preferably, a plurality of acoustic tubes 11 are also arranged in the pile head 1 along the longitudinal direction, and the acoustic tubes 11 are bent toward the pile core at the cutting plane, leaving a gap between the longitudinal bars 2 and the acoustic tubes 11 for passing through. The rope tube 5 is passed through, and the acoustic tube 11 is close to the longitudinal bar 2 or the stirrup 3 at other heights, and is bound on the longitudinal bar 2 or the stirrup 3.

另外,本发明还公开上述钢筋混凝土灌注桩桩头预埋管对桩头进行绳锯切割的方法,包括以下步骤:In addition, the present invention also discloses a method for cutting the pile head with a wire saw by the pre-buried pipe at the pile head of the reinforced concrete cast-in-place pile, comprising the following steps:

1)找到腰管4,破坏包裹腰管4的混凝土保护层,解除缠绕胶带9和绑扎铁丝8后取出腰管4;1) Find the waist tube 4, destroy the concrete protective layer that wraps the waist tube 4, remove the wrapping tape 9 and the binding iron wire 8, and then take out the waist tube 4;

2)清理穿绳管5两端堵塞物,并从穿绳管5两端开口穿过绳锯锯条10;2) Clear the blockages at both ends of the rope threading pipe 5, and pass the wire saw blade 10 from the openings at both ends of the rope threading pipe 5;

3)开动绳锯沿切割平面切割混凝土和声测管11,切割至边界线12为止;切割时,采用水管对准穿绳管5的一端开口,输入润滑用水至切割面13的绳锯锯条10上,随着切割深度增大,逐步加大水压和水量;3) Start the wire saw to cut the concrete and the acoustic tube 11 along the cutting plane until the boundary line 12; when cutting, use a water pipe to align the opening of one end of the wire pipe 5, and input lubricating water to the wire saw blade 10 of the cutting surface 13 As the cutting depth increases, gradually increase the water pressure and water volume;

4)解开套管6上端铁丝,破除切割平面上的穿绳管5外侧的混凝土;沿切割平面剪开穿绳管5;4) Untie the iron wire at the upper end of the casing 6 to break the concrete on the outside of the rope threading pipe 5 on the cutting plane; cut the rope threading pipe 5 along the cutting plane;

5)用扁头钢钎插入切割平面的切割面13,撬起钢钎使保留混凝土14沿切割平面断开;5) Insert the flat head steel drill into the cutting surface 13 of the cutting plane, and pry up the steel drill so that the reserved concrete 14 is broken along the cutting plane;

6)打开吊装管7外端木塞,插入长度大于吊装管7深度10-15cm的圆钢,并在圆钢与吊装管7之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe 7, insert a round steel whose length is 10-15cm greater than the depth of the hoisting pipe 7, and insert a wedge-shaped wooden strip in the gap between the round steel and the hoisting pipe 7 to fix it, and fasten the steel wire rope on the round steel. Lift the excised part of the pile head with a crane.

优选地,所述步骤3)具体为:开动绳锯沿切割平面切割混凝土和声测管11,切割至边界线12为止;切割初期润滑用水采用水管对准穿绳管5的一端开口,输入到切割平面的切割面13上;切割深度大于5cm后,在穿绳管5中点处剪除2cm长管道,改从该处插入水管15,将润滑用水输入到切割面13的锯条10上,随着切割深度增大,逐步深插水管15以接近绳锯锯条10或加大水压和水量。Preferably, the step 3) is specifically: start the wire saw to cut the concrete and the acoustic tube 11 along the cutting plane, and cut to the boundary line 12; use a water pipe for the lubricating water in the early stage of cutting to align the opening of one end of the wire pipe 5, and input it into the On the cutting surface 13 of the cutting plane; after the cutting depth is greater than 5cm, cut off a 2cm long pipe at the midpoint of the rope threading pipe 5, and insert the water pipe 15 from this place, and input the lubricating water to the saw blade 10 of the cutting surface 13. As the cutting depth increases, gradually insert the water pipe 15 deeply to approach the wire saw blade 10 or increase the water pressure and water volume.

本发明附图只展示了圆形截面桩的情形,当截面是矩形(含正方形)时,本发明所有技术特征均相同,上述方案同样成立,只增加一个技术特征,即穿绳管5的4个转角处布置圆弧形倒角,以利于绳锯锯条穿孔和初期切割操作。The accompanying drawings of the present invention only show the situation of a circular section pile. When the cross section is a rectangle (including a square), all the technical features of the present invention are the same, and the above solution is also established, only one technical feature is added, that is, the 4 Arc-shaped chamfers are arranged at each corner to facilitate the perforation of the wire saw blade and the initial cutting operation.

实施例1Example 1

钢筋混凝土灌注桩直径1.2 m,配20根直径Ф22纵筋,桩身混凝土强度C25,保护层厚度40mm,超灌桩头高度1 m。The diameter of the reinforced concrete cast-in-place pile is 1.2 m, with 20 longitudinal bars of diameter Ф22, the concrete strength of the pile body is C25, the thickness of the protective layer is 40 mm, and the height of the super-cast pile head is 1 m.

腰管和穿绳管布置在桩顶设计标高以上3 cm的同一平面内,该平面即为切割平面,切割平面以上部分为桩头切除部分;腰管紧贴纵筋外侧,围成一个完整的圆圈;穿绳管中间部分紧贴15根纵筋内侧,两端伸至腰管内侧,与腰管接触点到相邻两根纵筋距离相等;纵筋在切割平面以上部分套有套管;桩头切除部分的上半部分在同一水平平面上预埋3根吊装管,吊装管纵轴指向圆心,吊装管与桩身表面交点均匀分布在圆周上,吊装管外端与混凝土保护层平齐。 The waist tube and the rope threading tube are arranged in the same plane 3 cm above the design elevation of the pile top. This plane is the cutting plane, and the part above the cutting plane is the excised part of the pile head; Circle; the middle part of the rope threading tube is close to the inside of the 15 longitudinal bars, and the two ends extend to the inner side of the waist tube, and the distance from the contact point of the waist tube to the two adjacent longitudinal bars is equal; the longitudinal bars are sleeved above the cutting plane; The upper half of the excised part of the pile head is pre-buried with three hoisting pipes on the same horizontal plane. The longitudinal axis of the hoisting pipes points to the center of the circle. The intersection points of the hoisting pipes and the surface of the pile body are evenly distributed on the circumference, and the outer ends of the hoisting pipes are flush with the concrete protective layer. .

所述的腰管采用橡胶管,直径45 mm;穿绳管和套管采用PVC塑料管,穿绳管、套管和吊装管的直径都为32mm,壁厚3mm;吊装管长度15cm。The waist tube is a rubber tube with a diameter of 45 mm; the rope threading pipe and the casing are PVC plastic pipes, the diameter of the rope threading pipe, the casing and the hoisting pipe are all 32mm, and the wall thickness is 3mm; the length of the hoisting pipe is 15cm.

所述的腰管对接处缠绕胶带宽度6cm;穿绳管两端用石膏堵塞;套管上下两端用石膏堵塞;吊装管两端用木塞堵塞;所有预埋管完整无渗漏。The width of the wrapping tape at the joint of the waist pipe is 6 cm; the two ends of the rope-piercing pipe are blocked with gypsum; the upper and lower ends of the casing are blocked with gypsum; the two ends of the hoisting pipe are blocked with wooden plugs;

所述的腰管和穿绳管都用绑扎铁丝绑扎在纵筋上,所有与纵筋接触处均绑扎;每根套管上端管壁钻孔,穿过铁丝后绑扎在该根套管套住的纵筋上端。The waist tube and the rope-piercing tube are all bound on the longitudinal bars with binding iron wires, and all the places in contact with the longitudinal bars are bound; the upper end pipe wall of each casing is drilled, and after passing through the wire, it is bound on the casing to cover it. the upper end of the longitudinal ribs.

所述的桩头中沿纵向还布置有3根声测管(声测管均匀分布在同一水平圆环上,且都与腰管接触),声测管在切割平面处微微向桩心弯曲,在纵筋和声测管之间留出间隙供穿绳管穿过,声测管在其它高度紧贴纵筋或箍筋,并绑扎在纵筋或箍筋上。In the pile head, there are also 3 acoustic measuring tubes arranged in the longitudinal direction (the acoustic measuring tubes are evenly distributed on the same horizontal ring, and all are in contact with the waist tube), and the acoustic measuring tubes are slightly bent towards the pile center at the cutting plane, Leave a gap between the longitudinal bar and the acoustic tube for the rope-passing tube to pass through, and the acoustic tube is close to the longitudinal bar or stirrup at other heights, and is bound to the longitudinal bar or stirrup.

所述的吊装管采用直径32,壁厚3mm的PVC塑料管,所在平面位于桩头切除部分的上半部,该平面离桩头切除部分顶部的距离为35 cm。The hoisting pipe is a PVC plastic pipe with a diameter of 32 mm and a wall thickness of 3 mm.

利用上述钢筋混凝土灌注桩桩头预埋管对桩头进行绳锯切割的方法,包括以下步骤:The method for cutting the pile head with a wire saw using the above-mentioned reinforced concrete cast-in-place pile head embedded pipe includes the following steps:

1)找到腰管,破坏包裹腰管的混凝土保护层,解除缠绕胶带和绑扎铁丝后取出腰管;1) Find the waist tube, destroy the concrete protective layer that wraps the waist tube, remove the waist tube after unwinding the tape and binding iron wire;

2)清理穿绳管两端堵塞物,并从穿绳管两端开口穿过绳锯锯条;2) Clean the blockages at both ends of the rope threading pipe, and pass the wire saw blade through the openings at both ends of the rope threading pipe;

3)开动绳锯沿切割平面切割混凝土和声测管,切割至边界线为止(距离保留混凝土中纵筋5cm以上);切割时,采用水管对准穿绳管的一端开口,输入润滑用水至切割面的锯条上,随着切割深度增大,逐步加大水压和水量;3) Start the wire saw to cut the concrete and the acoustic tube along the cutting plane, and cut to the boundary line (more than 5cm away from the longitudinal bars in the reserved concrete); when cutting, use the water pipe to align the opening of one end of the wire pipe, and input lubricating water until the cutting On the saw blade on the surface, as the cutting depth increases, the water pressure and water volume are gradually increased;

4)解开套管上端铁丝,破除切割平面上的穿绳管外侧的混凝土;沿切割平面剪开穿绳管;4) Untie the wire at the upper end of the casing to break the concrete on the outside of the rope-passing pipe on the cutting plane; cut the rope-passing pipe along the cutting plane;

5)用扁头钢钎插入切割平面的切割面,撬起钢钎使保留混凝土沿切割平面断开;5) Insert the flat head steel drill into the cutting surface of the cutting plane, and pry up the steel drill so that the reserved concrete is broken along the cutting plane;

6)打开吊装管外端木塞,插入长度25cm的直径为20 mm圆钢,并在圆钢与吊装管之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe, insert a round steel with a length of 25cm and a diameter of 20 mm, and insert a wedge-shaped wooden bar into the gap between the round steel and the hoisting pipe to fix it, tie a steel wire rope to the round steel, and hoist the pile head with a crane Cut off part.

实施例2Example 2

钢筋混凝土灌注桩直径2 m,配28根直径Ф24纵筋,桩身混凝土强度C25,保护层厚度40mm,超灌桩头高度1.2 m。The diameter of the reinforced concrete cast-in-place pile is 2 m, equipped with 28 longitudinal bars of diameter Ф24, the concrete strength of the pile body is C25, the thickness of the protective layer is 40 mm, and the height of the super-cast pile head is 1.2 m.

腰管和穿绳管布置在桩顶设计标高以上6 cm的同一平面内,该平面即为切割平面,切割平面以上部分为桩头切除部分;腰管紧贴纵筋外侧,围成一个完整的圆圈;穿绳管中间部分紧贴22纵筋内侧,两端伸至腰管内侧,两端离最近纵筋直线距离5 cm;纵筋在切割平面以上部分套有套管;桩头切除部分的上半部分在同一水平平面上预埋4根吊装管,吊装管纵轴指向圆心,吊装管与桩身表面交点均匀分布在圆周上,吊装管外端伸出混凝土保护层表面2 cm。 The waist tube and the threading tube are arranged in the same plane 6 cm above the design elevation of the pile top. This plane is the cutting plane, and the part above the cutting plane is the excised part of the pile head; Circle; the middle part of the rope-passing tube is close to the inner side of the 22 longitudinal bars, the two ends extend to the inner side of the waist tube, and the two ends are 5 cm away from the nearest longitudinal bar; the longitudinal bars are sleeved above the cutting plane; Four hoisting pipes are pre-buried in the upper part on the same horizontal plane. The longitudinal axis of the hoisting pipes points to the center of the circle. The intersections of the hoisting pipes and the surface of the pile body are evenly distributed on the circumference. The outer ends of the hoisting pipes protrude 2 cm from the surface of the concrete protective layer.

所述的腰管采用直径40 mm的 PVC塑料管,壁厚3.7 mm;穿绳管采用直径25mm的PVC塑料管,壁厚2.3mm;套管选用采用直径40 mm PVC塑料管,壁厚3.7 mm。吊装管采用直径32mm的 PVC塑料管,壁厚3 mm,长度20 cm。The waist tube adopts a PVC plastic tube with a diameter of 40 mm and a wall thickness of 3.7 mm; the rope threading tube adopts a PVC plastic tube with a diameter of 25 mm and a wall thickness of 2.3 mm; the casing adopts a PVC plastic tube with a diameter of 40 mm and a wall thickness of 3.7 mm. . The hoisting pipe adopts a PVC plastic pipe with a diameter of 32mm, a wall thickness of 3 mm and a length of 20 cm.

所述的腰管用一根塑料管两端对接而成,对接处缠绕胶带宽度7cm;穿绳管两端用木塞堵塞;套管上下两端用石膏堵塞;吊装管两端用木塞堵塞;所有预埋管完整无渗漏。The waist tube is formed by butting two ends of a plastic tube, and the width of the wrapping tape is 7cm at the butt joint; the two ends of the rope threading tube are blocked with wooden plugs; the upper and lower ends of the casing are blocked with gypsum; the two ends of the hoisting pipe are blocked with wooden plugs; All embedded pipes are intact and leak-free.

所述的腰管和穿绳管都用绑扎铁丝绑扎在纵筋上,所有与纵筋接触处均绑扎;每根套管上端管壁钻孔,穿过铁丝后绑扎在该根套管套住的纵筋上端。The waist tube and the rope-piercing tube are all bound on the longitudinal bars with binding iron wires, and all the places in contact with the longitudinal bars are bound; the upper end pipe wall of each casing is drilled, and after passing through the wire, it is bound on the casing to cover it. the upper end of the longitudinal ribs.

所述的桩头中沿纵向还布置有4根声测管(声测管均匀分布在同一水平圆环上,且都与腰管接触),声测管在切割平面处微微向桩心弯曲,在纵筋和声测管之间留出间隙供穿绳管穿过,声测管在其它高度紧贴纵筋或箍筋,并绑扎在纵筋或箍筋上。There are also 4 acoustic measuring tubes arranged in the longitudinal direction in the pile head (the acoustic measuring tubes are evenly distributed on the same horizontal ring, and all are in contact with the waist tube), and the acoustic measuring tubes are slightly bent towards the pile center at the cutting plane, Leave a gap between the longitudinal bar and the acoustic tube for the rope-passing tube to pass through, and the acoustic tube is close to the longitudinal bar or stirrup at other heights, and is bound to the longitudinal bar or stirrup.

所述的吊装管所在平面位于桩头切除部分的上半部分,该平面离桩头切除部分顶部的距离为40 cm。The plane where the hoisting pipe is located is located in the upper half of the cut-out portion of the pile head, and the distance between the plane and the top of the cut-out portion of the pile head is 40 cm.

利用上述的钢筋混凝土灌注桩桩头预埋管对桩头进行绳锯切割的方法,包括以下步骤:Utilize the above-mentioned reinforced concrete cast-in-place pile head pre-embedded pipe to wire saw cutting the pile head, comprising the following steps:

1)找到腰管,破坏包裹腰管的混凝土保护层,解除缠绕胶带和绑扎铁丝后取出腰管;1) Find the waist tube, destroy the concrete protective layer that wraps the waist tube, remove the waist tube after unwinding the tape and binding iron wire;

2)清理穿绳管两端堵塞物,并从穿绳管两端开口穿过绳锯锯条;2) Clean the blockages at both ends of the rope threading pipe, and pass the wire saw blade through the openings at both ends of the rope threading pipe;

3)开动绳锯沿切割平面切割混凝土和声测管,切割至边界线为止(边界线距离最近纵筋大于5cm);切割初期润滑用水采用水管对准穿绳管的一端开口,输入到切割平面的切割面(13)上;切割深度大于5cm后,在穿绳管中点处剪除2cm长管道,改从该处插入水管,将润滑用水输入到切割面的锯条上,随着切割深度增大,逐步深插水管以接近锯条。3) Start the wire saw to cut the concrete and acoustic tube along the cutting plane until the boundary line (the distance between the boundary line and the nearest longitudinal bar is greater than 5cm); in the early stage of cutting, use a water pipe to align the opening of one end of the rope passing pipe and input it to the cutting plane On the cutting surface (13) of the cutting surface; after the cutting depth is greater than 5 cm, cut off the 2 cm long pipe at the midpoint of the rope-passing pipe, insert the water pipe from this place, and input the lubricating water to the saw blade on the cutting surface, as the cutting depth increases , and gradually insert the water pipe deeply to get close to the saw blade.

4)解开套管上端铁丝,破除切割平面上的穿绳管外侧的混凝土;沿切割平面剪开穿绳管;4) Untie the wire at the upper end of the casing to break the concrete on the outside of the rope-passing pipe on the cutting plane; cut the rope-passing pipe along the cutting plane;

5)用扁头钢钎插入切割平面的切割面,撬起钢钎使保留混凝土沿切割平面断开;5) Insert the flat head steel drill into the cutting surface of the cutting plane, and pry up the steel drill so that the reserved concrete is broken along the cutting plane;

6)打开吊装管外端木塞,插入长度大于35 cm的直径22mm圆钢,并在圆钢与吊装管之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe, insert a 22mm diameter round steel with a length of more than 35 cm, and insert a wedge-shaped wooden bar into the gap between the round steel and the hoisting pipe to fix it, tie a steel wire rope to the round steel, and hoist the pile head with a crane Cut off part.

实施例3Example 3

钢筋混凝土灌注桩直径0.8 m,配16根直径Ф16纵筋,桩身混凝土强度C25,保护层厚度35mm,超灌桩头高度1 m。The diameter of the reinforced concrete cast-in-place pile is 0.8 m, with 16 longitudinal bars of diameter Ф16, the concrete strength of the pile body is C25, the thickness of the protective layer is 35 mm, and the height of the super-cast pile head is 1 m.

腰管和穿绳管布置在桩顶设计标高以上4 cm的同一平面内,该平面即为切割平面,切割平面以上部分为桩头切除部分;腰管紧贴13根纵筋外侧,围成一个完整的圆圈;穿绳管中间部分紧贴纵筋内侧,两端伸至腰管内侧,两端离最近纵筋直线距离大于5 cm;纵筋在切割平面以上部分套有套管;桩头切除部分的上半部分在同一水平平面上预埋2根吊装管,吊装管纵轴指向圆心,吊装管与桩身表面交点均匀分布在圆周上,吊装管外端伸出混凝土保护层表面1cm。 The waist tube and the threading tube are arranged in the same plane 4 cm above the design elevation of the pile top. This plane is the cutting plane, and the part above the cutting plane is the excised part of the pile head; the waist tube is close to the outside of the 13 longitudinal bars, forming a A complete circle; the middle part of the rope-passing tube is close to the inner side of the longitudinal bar, both ends extend to the inner side of the waist tube, and the linear distance between the two ends is greater than 5 cm from the nearest longitudinal bar; the longitudinal bar is covered with a casing above the cutting plane; the pile head is removed The upper part of the part is embedded with two hoisting pipes on the same horizontal plane. The longitudinal axis of the hoisting pipes points to the center of the circle. The intersections of the hoisting pipes and the surface of the pile body are evenly distributed on the circumference, and the outer ends of the hoisting pipes protrude 1cm from the surface of the concrete protective layer.

所述的腰管采用橡胶管,直径35 mm;穿绳管采用直径25mm的PVC塑料管,套管和吊装管都采用PVC塑料管,直径25mm,管壁后2.3mm;吊装管长度10cm。The waist tube adopts a rubber tube with a diameter of 35 mm; the rope threading tube adopts a PVC plastic tube with a diameter of 25 mm, and the casing and the hoisting tube are both PVC plastic tubes, with a diameter of 25 mm and a rear wall of 2.3 mm; the length of the hoisting tube is 10 cm.

所述的腰管用一根橡胶管两端对接而成,对接处缠绕胶带宽度6 cm;穿绳管两端用木塞堵塞;套管上下两端用石膏堵塞;吊装管两端用木塞堵塞;所有预埋管完整无渗漏。The waist tube is formed by butting two ends of a rubber tube, and the width of the wrapping tape is 6 cm; ; All embedded pipes are complete without leakage.

所述的腰管和穿绳管都用绑扎铁丝绑扎在纵筋上,所有与纵筋接触处均绑扎;每根套管上端管壁钻孔,穿过铁丝后绑扎在该根套管套住的纵筋上端。The waist tube and the rope-piercing tube are all bound on the longitudinal bars with binding iron wires, and all the places in contact with the longitudinal bars are bound; the upper end pipe wall of each casing is drilled, and after passing through the wire, it is bound on the casing to cover it. the upper end of the longitudinal ribs.

所述的桩头中沿纵向还布置有2根声测管(声测管均匀分布在同一水平圆环上,且都与腰管接触),声测管在切割平面处微微向桩心弯曲,在纵筋和声测管之间留出间隙供穿绳管穿过,声测管在其它高度紧贴纵筋或箍筋,并绑扎在纵筋或箍筋上。The pile head is also arranged with 2 acoustic measuring tubes along the longitudinal direction (the acoustic measuring tubes are evenly distributed on the same horizontal ring, and both are in contact with the waist tube), and the acoustic measuring tubes are slightly bent towards the pile center at the cutting plane, Leave a gap between the longitudinal bar and the acoustic tube for the rope-passing tube to pass through, and the acoustic tube is close to the longitudinal bar or stirrup at other heights, and is bound to the longitudinal bar or stirrup.

所述的吊装管所在平面位于桩头切除部分的上半部分,该平面离桩头切除部分顶部的距离为30 cm。The plane where the hoisting pipe is located is located in the upper half of the cut-out portion of the pile head, and the distance between the plane and the top of the cut-out portion of the pile head is 30 cm.

利用权利上述钢筋混凝土灌注桩桩头预埋管对桩头进行绳锯切割的方法,包括以下步骤:The method of wire saw cutting the pile head by utilizing the above-mentioned reinforced concrete cast-in-place pile head pre-embedded pipe comprises the following steps:

1)找到腰管,破坏包裹腰管的混凝土保护层,解除缠绕胶带和绑扎铁丝后取出腰管;1) Find the waist tube, destroy the concrete protective layer that wraps the waist tube, remove the waist tube after unwinding the tape and binding iron wire;

2)清理穿绳管两端堵塞物,并从穿绳管两端开口穿过绳锯锯条;2) Clean the blockages at both ends of the rope threading pipe, and pass the wire saw blade through the openings at both ends of the rope threading pipe;

3)开动绳锯沿切割平面切割混凝土和声测管,切割至边界线为止;切割时,采用水管对准穿绳管的一端开口,输入润滑用水至切割面的锯条上,随着切割深度增大,逐步加大水压和水量;3) Start the wire saw to cut the concrete and the acoustic tube along the cutting plane until the boundary line; when cutting, use the water pipe to align the opening of one end of the wire pipe, and input lubricating water to the saw blade on the cutting surface. Large, gradually increase the water pressure and water volume;

4)解开套管上端铁丝,破除切割平面上的穿绳管外侧的混凝土;沿切割平面剪开穿绳管;4) Untie the wire at the upper end of the casing to break the concrete on the outside of the rope-passing pipe on the cutting plane; cut the rope-passing pipe along the cutting plane;

5)用扁头钢钎插入切割平面的切割面,撬起钢钎使保留混凝土沿切割平面断开;5) Insert the flat head steel drill into the cutting surface of the cutting plane, and pry up the steel drill so that the reserved concrete is broken along the cutting plane;

6)打开吊装管外端木塞,插入长度20 cm的直径18mm圆钢,并在圆钢与吊装管之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe, insert a round steel with a length of 20 cm and a diameter of 18 mm, and insert a wedge-shaped wooden bar into the gap between the round steel and the hoisting pipe to fix it, tie a steel wire rope on the round steel, and use a crane to hoist the pile head and cut it off. part.

上述的实施例仅为本发明的优选技术方案,而不应视为对于本发明的限制,本申请中的实施例及实施例中的特征在不冲突的情况下,可以相互任意组合。本发明的保护范围应以权利要求记载的技术方案,包括权利要求记载的技术方案中技术特征的等同替换方案为保护范围。即在此范围内的等同替换改进,也在本发明的保护范围之内。The above-mentioned embodiments are only the preferred technical solutions of the present invention, and should not be regarded as limitations of the present invention. The embodiments and features in the present application may be arbitrarily combined with each other without conflict. The protection scope of the present invention shall take the technical solutions described in the claims, including the equivalent alternatives of the technical features in the technical solutions described in the claims, as the protection scope. That is, equivalent replacements and improvements within this scope are also within the protection scope of the present invention.

Claims (5)

1.一种利用钢筋混凝土灌注桩桩头预埋管对桩头绳锯切割的方法,所述钢筋混凝土灌注桩桩头预埋管包括在钢筋混凝土灌注桩施工期便预埋于其桩头(1)内的腰管(4)、穿绳管(5)、套管(6)和吊装管(7),所述腰管(4)和穿绳管(5)布置在桩顶设计标高以上区域的同一水平面内,该平面即为切割平面,切割平面以上部分即为桩头(1)的切除部分,桩头(1)的纵筋(2)在切割平面以上部分套有套管(6),桩头(1)切割平面以上部分的同一水平面内预埋有吊装管(7),吊装管(7)的纵轴指向所在水平面的圆心;所述腰管(4)紧贴纵筋(2)外侧,围成一个完整的圈;穿绳管(5)中间部分紧贴纵筋(2)内侧,两端伸至腰管(4)内侧,两端离最近纵筋(2)直线距离大于3 cm;所述腰管(4)用一根PVC塑料管或橡胶管的两端对接而成,对接处缠绕胶带(9)宽度大于5cm;穿绳管(5)两端用木塞或石膏堵塞;套管(6)上下两端用石膏堵塞;吊装管(7)两端用木塞堵塞;所述腰管(4)和穿绳管(5)均用绑扎铁丝(8)绑扎在纵筋(2)上,所有与纵筋(2)接触处均绑扎;每根套管(6)上端管壁钻孔,穿过铁丝后绑扎在该根套管(6)套住的纵筋(2)上端;所述桩头(1)中沿纵向还布置有多根声测管(11),声测管(11)在切割平面处向桩心弯曲,在纵筋(2)和声测管(11)之间留出间隙供穿绳管(5)穿过,声测管(11)在其它高度紧贴纵筋(2)或箍筋(3),并绑扎在纵筋(2)或箍筋(3)上;其特征在于:它包括如下步骤:1. a method of utilizing a reinforced concrete cast-in-place pile head embedded pipe to cut a wire saw to the pile head, the reinforced concrete cast-in-place pile head embedded pipe is included in the reinforced concrete cast-in-place pile construction period and is pre-buried in its pile head (1. ), the rope threading pipe (5), the casing (6) and the hoisting pipe (7), the waist pipe (4) and the rope threading pipe (5) are arranged in the area above the design elevation of the pile top In the same horizontal plane of the pile head (1), the plane is the cutting plane, and the part above the cutting plane is the excised part of the pile head (1). , a hoisting pipe (7) is pre-buried in the same horizontal plane of the part above the cutting plane of the pile head (1), and the longitudinal axis of the hoisting pipe (7) points to the center of the horizontal plane; ) outside, forming a complete circle; the middle part of the rope threading tube (5) is close to the inside of the longitudinal rib (2), the two ends extend to the inside of the waist tube (4), and the linear distance between the two ends from the nearest longitudinal rib (2) is greater than 3 cm; the waist tube (4) is formed by butting two ends of a PVC plastic tube or rubber tube, and the width of the tape (9) around the butt joint is greater than 5 cm; the two ends of the rope-piercing tube (5) are made of wooden plugs or plaster Blocking; the upper and lower ends of the casing (6) are blocked with gypsum; the two ends of the hoisting pipe (7) are blocked with wooden plugs; the waist pipe (4) and the rope-piercing pipe (5) are tied with binding iron wires (8) in the longitudinal direction. On the rib (2), all the contact points with the longitudinal rib (2) are bound; the upper pipe wall of each casing (6) is drilled, and after passing through the wire, it is bound to the longitudinal rib ( 2) The upper end; a plurality of acoustic measuring tubes (11) are also arranged in the longitudinal direction in the pile head (1), and the acoustic measuring tubes (11) are bent towards the pile core at the cutting plane, and the longitudinal bars (2) and the acoustic measuring tubes (11) are bent towards the core of the pile at the cutting plane. Leave a gap between the pipes (11) for the rope threading pipe (5) to pass through, and the acoustic measuring pipe (11) is close to the longitudinal reinforcement (2) or stirrup (3) at other heights, and is bound to the longitudinal reinforcement (2). or stirrup (3); it is characterized in that: it comprises the following steps: 1)找到腰管(4),破坏包裹腰管(4)的混凝土保护层,解除缠绕胶带(9)和绑扎铁丝(8)后取出腰管(4);1) Find the waist tube (4), destroy the concrete protective layer that wraps the waist tube (4), remove the wrapping tape (9) and the binding iron wire (8), and then take out the waist tube (4); 2)清理穿绳管(5)两端堵塞物,并从穿绳管(5)两端开口穿过绳锯锯条(10);2) Clear the blockages at both ends of the rope threading pipe (5), and pass the wire saw blade (10) from the openings at both ends of the rope threading pipe (5); 3)开动绳锯沿切割平面切割混凝土和声测管(11),切割至边界线(12)为止;切割时,采用水管对准穿绳管(5)的一端开口,输入润滑用水至切割面(13)的绳锯锯条(10)上,随着切割深度增大,逐步加大水压和水量;3) Start the wire saw to cut the concrete and the acoustic tube (11) along the cutting plane until the boundary line (12); when cutting, use a water pipe to align the opening of one end of the wire pipe (5), and input lubricating water to the cutting surface On the wire saw blade (10) of (13), as the cutting depth increases, the water pressure and water volume are gradually increased; 4)解开套管(6)上端铁丝,破除切割平面上的穿绳管(5)外侧的混凝土;沿切割平面剪开穿绳管(5);4) Untie the wire at the upper end of the casing (6), and break the concrete on the outside of the rope threading pipe (5) on the cutting plane; cut the rope threading pipe (5) along the cutting plane; 5)用扁头钢钎插入切割平面的切割面(13),撬起钢钎使保留混凝土(14)沿切割平面断开;5) Insert the flat head steel drill into the cutting surface (13) of the cutting plane, and pry up the steel drill so that the retained concrete (14) is broken along the cutting plane; 6)打开吊装管(7)外端木塞,插入长度大于吊装管(7)深度10-15cm的圆钢,并在圆钢与吊装管(7)之间间隙中插入楔形木条固定,在圆钢上系上钢丝绳,用吊车吊装桩头切除部分。6) Open the wooden plug at the outer end of the hoisting pipe (7), insert a round steel whose length is 10-15cm longer than the depth of the hoisting pipe (7), and insert a wedge-shaped wooden bar into the gap between the round steel and the hoisting pipe (7) to fix it. A steel wire rope is tied to the steel, and the cut off part of the pile head is hoisted by a crane. 2.根据权利要求1所述的利用钢筋混凝土灌注桩桩头预埋管对桩头绳锯切割的方法,其特征在于:所述腰管(4)和穿绳管(5)布置在桩顶设计标高以上3-6 cm的同一水平面内。2. The method for cutting the pile head wire saw by using the reinforced concrete cast-in-place pile head embedded pipe according to claim 1, characterized in that: the waist pipe (4) and the rope threading pipe (5) are arranged on the pile top design Within the same horizontal plane 3-6 cm above the elevation. 3.根据权利要求2所述的利用钢筋混凝土灌注桩桩头预埋管对桩头绳锯切割的方法,其特征在于:所述桩头(1)的切除部分的上半部分在同一水平面内预埋有多根吊装管(7),该水平面离切除部分顶部的距离大于切除部分总高度的四分之一,吊装管(7)与桩身表面交点均匀分布在圆周上,吊装管(7)外端与混凝土保护层平齐或伸出混凝土保护层表面1-2cm。3 . The method for cutting the pile head with a wire saw using a reinforced concrete cast-in-place pile head embedded pipe according to claim 2 , wherein the upper half of the cut part of the pile head ( 1 ) is pre-cut in the same horizontal plane. 4 . A plurality of hoisting pipes (7) are buried, and the distance from the horizontal plane to the top of the cut part is greater than a quarter of the total height of the cut part. The intersection points of the hoisting pipes (7) and the surface of the pile body are evenly distributed on the circumference, and the hoisting pipes (7) The outer end is flush with the concrete cover or protrudes 1-2cm from the surface of the concrete cover. 4.根据权利要求1所述的利用钢筋混凝土灌注桩桩头预埋管对桩头绳锯切割的方法,其特征在于:所述腰管(4)采用PVC塑料管或橡胶管预埋形成;穿绳管(5)和套管(6)采用PVC塑料管预埋形成;所述腰管(4)直径等于或大于桩身混凝土保护层厚度;穿绳管(5)内径为15-25 mm;套管(6)内径大于纵筋(2)直径4-20 mm。4. The method for cutting the pile head with a wire saw using a reinforced concrete cast-in-place pile head embedded pipe according to claim 1, characterized in that: the waist pipe (4) is formed by pre-embedding a PVC plastic pipe or a rubber pipe; The rope pipe (5) and the casing (6) are formed by pre-embedding PVC plastic pipes; the diameter of the waist pipe (4) is equal to or greater than the thickness of the concrete protection layer of the pile body; the inner diameter of the rope pipe (5) is 15-25 mm; The inner diameter of the casing (6) is 4-20 mm larger than the diameter of the longitudinal rib (2). 5.根据权利要求1所述的利用钢筋混凝土灌注桩桩头预埋管对桩头绳锯切割的方法,其特征在于:5. the method that utilizes reinforced concrete cast-in-place pile head embedded pipe to cut the pile head wire saw according to claim 1, it is characterized in that: 所述步骤3)具体为:开动绳锯沿切割平面切割混凝土和声测管(11),切割至边界线(12)为止;切割初期润滑用水采用水管对准穿绳管(5)的一端开口,输入到切割平面的切割面(13)上;切割深度大于5cm后,在穿绳管(5)中点处剪除2cm长管道,改从该处插入水管(15),将润滑用水输入到切割面(13)的绳锯锯条(10)上,随着切割深度增大,逐步深插水管(15)以接近绳锯锯条(10)或加大水压和水量。The step 3) is as follows: start the wire saw to cut the concrete and the acoustic tube (11) along the cutting plane, and cut to the boundary line (12); use a water pipe to align the opening of one end of the wire pipe (5) with water for initial lubrication , and input it to the cutting surface (13) of the cutting plane; after the cutting depth is greater than 5cm, cut off a 2cm long pipe at the midpoint of the rope threading pipe (5), and insert the water pipe (15) from there, and input the lubricating water to the cutting On the wire saw blade (10) on the surface (13), as the cutting depth increases, gradually insert the water pipe (15) deeply to approach the wire saw blade (10) or increase the water pressure and water volume.
CN202111014058.8A 2021-08-31 2021-08-31 Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile Active CN113605389B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111014058.8A CN113605389B (en) 2021-08-31 2021-08-31 Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111014058.8A CN113605389B (en) 2021-08-31 2021-08-31 Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile

Publications (2)

Publication Number Publication Date
CN113605389A CN113605389A (en) 2021-11-05
CN113605389B true CN113605389B (en) 2022-08-30

Family

ID=78342425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111014058.8A Active CN113605389B (en) 2021-08-31 2021-08-31 Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile

Country Status (1)

Country Link
CN (1) CN113605389B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114875931B (en) * 2022-06-08 2024-08-16 中铁七局集团郑州工程有限公司 Enclosure structure, construction method and removal method of enclosure structure

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385686A (en) * 2018-03-02 2018-08-10 中铁上海工程局集团有限公司 A kind of cast-in-situ bored pile exempts from stripping and exempts from ring cutting to cut pile crown technique
CN110258561A (en) * 2019-06-21 2019-09-20 中铁三局集团广东建设工程有限公司 A kind of constructing device and its construction method cutting off building enclosure
CN212956527U (en) * 2020-05-23 2021-04-13 北京城建中南土木工程集团有限公司 Structure is cut fast to bored concrete pile head
CN112813977A (en) * 2020-12-24 2021-05-18 中交第三航务工程局有限公司江苏分公司 Construction method for cutting off ultrahigh concrete pipe pile by using rope saw

Also Published As

Publication number Publication date
CN113605389A (en) 2021-11-05

Similar Documents

Publication Publication Date Title
CN102425159B (en) Pile cutting construction method of bored concrete pile
CN110820742A (en) Construction method for breaking underwater cast-in-place pile head
CN102587380A (en) Construction method for wholly removing drilling pile head
CN105297729A (en) Bridge pile foundation pile head breaking device and method
CN106592591A (en) Drilling pile head overall removal construction method
CN111005378A (en) Construction method for breaking pile head of cast-in-situ bored pile through static spalling
CN113250186B (en) A cast-in-place concrete pile head separation device and pile head breaking method
CN113605389B (en) Green dismantling method for pile head embedded pipe and rope saw cutting of reinforced concrete cast-in-place pile
CN106284187A (en) Face Slab of Concrete of Rock-fill Dam destroys the quick method for dismounting in district
CN110593255B (en) Full-casing secant pile construction method suitable for sandy gravel soil layer
CN113668529A (en) Construction method for breaking and removing pile head with template based on steel wedge-shaped gap
CN109537592A (en) The anchor cable invaded within the scope of interlocking pile cuts off construction method
TWM660364U (en) Underground obstacle lifting system
CN109403326B (en) Method for taking out reinforcement cage based on serious hole collapse of drilled pile
CN108468337B (en) Recyclable foundation pit supporting pile, dismounting device and using method
CN110387875A (en) Connector cutting device and its construction method
CN217078745U (en) Integral pile head breaking device for concrete cast-in-place pile
CN212956527U (en) Structure is cut fast to bored concrete pile head
JP2004131923A (en) Underground existing structure extraction method
CN114657974A (en) Method for quickly splicing cast-in-place pile under complex geological condition
CN210066752U (en) Water cutting vibrations immersed tube pile pulling device
CN221608843U (en) Bored pile device
CN211080209U (en) Cast-in-situ bored pile
CN210031806U (en) Broken stake pre-buried device of high efficiency
CN219508546U (en) Auxiliary structure for pile head wedge fracture of filling pile and filling pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant