CN113982004A - Anchor cable-reinforced soil composite retaining member and construction method thereof - Google Patents
Anchor cable-reinforced soil composite retaining member and construction method thereof Download PDFInfo
- Publication number
- CN113982004A CN113982004A CN202111595426.2A CN202111595426A CN113982004A CN 113982004 A CN113982004 A CN 113982004A CN 202111595426 A CN202111595426 A CN 202111595426A CN 113982004 A CN113982004 A CN 113982004A
- Authority
- CN
- China
- Prior art keywords
- reinforced
- anchor cable
- retaining member
- soil
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002689 soil Substances 0.000 title claims abstract description 46
- 238000010276 construction Methods 0.000 title claims abstract description 23
- 239000002131 composite material Substances 0.000 title abstract 2
- 239000000463 material Substances 0.000 claims abstract description 35
- 239000000945 filler Substances 0.000 claims abstract description 17
- 230000003014 reinforcing effect Effects 0.000 claims description 17
- 230000002787 reinforcement Effects 0.000 claims description 14
- 238000007789 sealing Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 2
- 239000012779 reinforcing material Substances 0.000 claims description 2
- 239000013589 supplement Substances 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 description 12
- 239000010959 steel Substances 0.000 description 12
- 230000000694 effects Effects 0.000 description 9
- 230000006378 damage Effects 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 5
- 210000003205 muscle Anatomy 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 241000196324 Embryophyta Species 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 3
- 239000011148 porous material Substances 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 238000009417 prefabrication Methods 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 241000727913 Parthenocissus tricuspidata Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000000452 restraining effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000009331 sowing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0225—Retaining or protecting walls comprising retention means in the backfill
- E02D29/0241—Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种锚索‑加筋土组合挡土构件及其施工方法,属于边坡支护技术领域;包括立柱和墙面模块,立柱设置有插槽,墙面模块插接在两侧立柱的插槽内;墙面模块的内侧面设置有连接构件,连接构件与墙面模块之间形成间隙,加筋材料一端套置在连接构件上并卡在间隙内,上下层的加筋材料之间设置有填料;当土体沉降时,加筋材料可沿连接构件向下移动;本发明使边坡承载能力和抗变形能力显著提高,解决了现有连接结构中加筋材料易被破坏的问题,适用于多种地质情况。
The invention discloses an anchor-cable-reinforced soil composite retaining member and a construction method thereof, belonging to the technical field of slope support. In the slot of the column; the inner side of the wall module is provided with a connecting member, a gap is formed between the connecting member and the wall module, one end of the reinforced material is sleeved on the connecting member and stuck in the gap, and the upper and lower layers of the reinforced material Fillers are arranged between them; when the soil settles, the reinforced material can move down along the connecting member; the invention significantly improves the bearing capacity and anti-deformation ability of the slope, and solves the problem that the reinforced material is easily damaged in the existing connecting structure The problem is applicable to a variety of geological conditions.
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111595426.2A CN113982004B (en) | 2021-12-24 | 2021-12-24 | Anchor cable-reinforced soil combined retaining member and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111595426.2A CN113982004B (en) | 2021-12-24 | 2021-12-24 | Anchor cable-reinforced soil combined retaining member and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113982004A true CN113982004A (en) | 2022-01-28 |
CN113982004B CN113982004B (en) | 2022-05-10 |
Family
ID=79734235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111595426.2A Active CN113982004B (en) | 2021-12-24 | 2021-12-24 | Anchor cable-reinforced soil combined retaining member and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113982004B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117027021A (en) * | 2023-10-08 | 2023-11-10 | 中铁二十二局集团电气化工程有限公司 | Cutting retaining structure and construction method |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB9014990D0 (en) * | 1990-07-06 | 1990-08-29 | Nicolaidis Raphael | A constructional element and a process for its production |
US5836129A (en) * | 1993-09-01 | 1998-11-17 | Jaecklin; Felix Paul | Construction element, in particular supporting or sound insulating construction element capable of being planted, set of construction elements and process for producing the same |
EP2325399A1 (en) * | 2009-11-23 | 2011-05-25 | Furnes-Hamjern SCC AS | Manhole structure |
CN102261053A (en) * | 2011-05-12 | 2011-11-30 | 河海大学 | Aseismatic measure of high earth-rock dam and construction method thereof |
CN102454171A (en) * | 2010-11-02 | 2012-05-16 | 同济大学 | Reinforced earth retaining wall |
CN103088834A (en) * | 2013-02-01 | 2013-05-08 | 河海大学 | Method for improving slope stability of expansive soil and controlling structural damage of expansive soil |
CN105002927A (en) * | 2015-06-15 | 2015-10-28 | 湖北工业大学 | Construction method for excavation slope retaining wall reversed filter layer |
RU2600426C1 (en) * | 2015-07-03 | 2016-10-20 | Харис Касьянович Мухаметдинов | Ground module (versions) |
CN107447775A (en) * | 2017-08-09 | 2017-12-08 | 中国地质环境监测院 | Landslide disaster body makes ground draining reinforced earth retaining wall structure |
CN107524159A (en) * | 2017-01-19 | 2017-12-29 | 湖南大学 | A kind of hybrid reinforced soil retaining wall |
CN108716222A (en) * | 2018-06-26 | 2018-10-30 | 许剑超 | A kind of side slope active defense wall |
CN109371989A (en) * | 2018-10-26 | 2019-02-22 | 华中科技大学 | A combined support structure suitable for slope stabilization support and its construction method |
CN109750689A (en) * | 2019-03-07 | 2019-05-14 | 浙江交工集团股份有限公司 | A greening reinforced embankment retaining member and construction method thereof |
CN210482362U (en) * | 2019-05-24 | 2020-05-08 | 郑州大学 | Assembled rigid and flexible combined elastic anti-seismic reinforced earth retaining wall |
CN111622244A (en) * | 2020-06-30 | 2020-09-04 | 长安大学 | Three-dimensional netted reinforced band flexible retaining structure that can assemble |
-
2021
- 2021-12-24 CN CN202111595426.2A patent/CN113982004B/en active Active
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB9014990D0 (en) * | 1990-07-06 | 1990-08-29 | Nicolaidis Raphael | A constructional element and a process for its production |
US5836129A (en) * | 1993-09-01 | 1998-11-17 | Jaecklin; Felix Paul | Construction element, in particular supporting or sound insulating construction element capable of being planted, set of construction elements and process for producing the same |
EP2325399A1 (en) * | 2009-11-23 | 2011-05-25 | Furnes-Hamjern SCC AS | Manhole structure |
CN102454171A (en) * | 2010-11-02 | 2012-05-16 | 同济大学 | Reinforced earth retaining wall |
CN102261053A (en) * | 2011-05-12 | 2011-11-30 | 河海大学 | Aseismatic measure of high earth-rock dam and construction method thereof |
CN103088834A (en) * | 2013-02-01 | 2013-05-08 | 河海大学 | Method for improving slope stability of expansive soil and controlling structural damage of expansive soil |
CN105002927A (en) * | 2015-06-15 | 2015-10-28 | 湖北工业大学 | Construction method for excavation slope retaining wall reversed filter layer |
RU2600426C1 (en) * | 2015-07-03 | 2016-10-20 | Харис Касьянович Мухаметдинов | Ground module (versions) |
CN107524159A (en) * | 2017-01-19 | 2017-12-29 | 湖南大学 | A kind of hybrid reinforced soil retaining wall |
CN107447775A (en) * | 2017-08-09 | 2017-12-08 | 中国地质环境监测院 | Landslide disaster body makes ground draining reinforced earth retaining wall structure |
CN108716222A (en) * | 2018-06-26 | 2018-10-30 | 许剑超 | A kind of side slope active defense wall |
CN109371989A (en) * | 2018-10-26 | 2019-02-22 | 华中科技大学 | A combined support structure suitable for slope stabilization support and its construction method |
CN109750689A (en) * | 2019-03-07 | 2019-05-14 | 浙江交工集团股份有限公司 | A greening reinforced embankment retaining member and construction method thereof |
CN210482362U (en) * | 2019-05-24 | 2020-05-08 | 郑州大学 | Assembled rigid and flexible combined elastic anti-seismic reinforced earth retaining wall |
CN111622244A (en) * | 2020-06-30 | 2020-09-04 | 长安大学 | Three-dimensional netted reinforced band flexible retaining structure that can assemble |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117027021A (en) * | 2023-10-08 | 2023-11-10 | 中铁二十二局集团电气化工程有限公司 | Cutting retaining structure and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN113982004B (en) | 2022-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2306130C (en) | Reinforced retaining wall | |
CN110158600B (en) | Construction method for synchronous excavation and asynchronous backfilling of adjacent foundation pits | |
US4653962A (en) | Retaining wall construction and method of manufacture | |
US6050749A (en) | Concrete masonry unit for reinforced retaining wall | |
CN111705795B (en) | Prefabricated anchor pier for slope reinforcement and post-cast lattice beam assembly integral construction method | |
US4369004A (en) | Earth retaining method and structure | |
CN109403371A (en) | A kind of Steep Slope Embankment retaining structure and construction method | |
CN110924433A (en) | Design method of subway foundation pit foot-hanging pile enclosure structure in upper-soft lower-hard rock stratum | |
CN109750681B (en) | Filling side slope frame micro-tensioning support anchor plate supporting structure and construction method thereof | |
US20090047075A1 (en) | Modular Block Connecting Techniques | |
CN108468341B (en) | Anti-slide pile-corrugated steel arch-anchor-pulling combined slope protection structure and construction method | |
CN110777806B (en) | Multi-connecting-rod plane frame permanent supporting structure and construction process thereof | |
US7114887B1 (en) | Modular block anchoring techniques | |
US7390146B2 (en) | Modular block structures | |
CN113982004A (en) | Anchor cable-reinforced soil composite retaining member and construction method thereof | |
CN111894026B (en) | Construction method of tunnel type pile foundation bearing platform combined anchorage structure | |
CN111622234B (en) | Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process | |
CN210263073U (en) | Supporting construction that adjacent foundation ditch synchronous excavation was asynchronously backfilled | |
CN113417300A (en) | Slope support system and construction method thereof | |
CN220927867U (en) | Support system for controlling foundation pit displacement | |
CN209722993U (en) | A kind of embankment side slope framework parts La Tuoding anchor slab supporting construction a little | |
CN111206617A (en) | High pile bearing platform retaining wall and construction method | |
CN114319437B (en) | Construction method for constructing retaining wall structure at open cut and added layer vertical shaft by underground excavation | |
US5871307A (en) | Pre-cast concrete panel wall | |
CN213038395U (en) | Side slope retaining structure of high soil slope entrance to a cave |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20230109 Address after: 030006 No. A, 18/F, Block B, Building 1 (Jinmao Building), No. 1, Pingyang Road, Xiaodian District, Taiyuan City, Shanxi Province Patentee after: Shanxi Chenzhi Civil Engineering Technology Co.,Ltd. Address before: 030024 No. 79 West Main Street, Taiyuan, Shanxi, Yingze Patentee before: Taiyuan University of Technology |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20230309 Address after: 032200 Xihe North Road, Fenyang City, Luliang City, Shanxi Province Patentee after: Luliang South Expressway Branch of Shanxi Transportation Holding Group Co.,Ltd. Address before: 030006 No. A, 18/F, Block B, Building 1 (Jinmao Building), No. 1, Pingyang Road, Xiaodian District, Taiyuan City, Shanxi Province Patentee before: Shanxi Chenzhi Civil Engineering Technology Co.,Ltd. |