CN107700527A - Add the cantilever retaining wall and construction method of pilaster and anchor pole - Google Patents
Add the cantilever retaining wall and construction method of pilaster and anchor pole Download PDFInfo
- Publication number
- CN107700527A CN107700527A CN201711081527.1A CN201711081527A CN107700527A CN 107700527 A CN107700527 A CN 107700527A CN 201711081527 A CN201711081527 A CN 201711081527A CN 107700527 A CN107700527 A CN 107700527A
- Authority
- CN
- China
- Prior art keywords
- anchor
- wall
- retaining wall
- pilasters
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Retaining Walls (AREA)
Abstract
加壁柱与锚杆的悬臂式挡土墙及施工方法,锚杆(4)由锚固段(9)和自由段(11)组成,锚杆(4)通过锚具(10)与壁柱(5)固定连接。方法的步骤为:(1)放线及定位,用测量仪器定位挡土墙墙踵板(3)的位置;(2)施工墙踵板(3)与墙趾板(2):支模然后浇筑混凝土形成悬臂式挡土墙的底板;(3)施工墙身板(1);(4)施工壁柱(5):在设计加锚杆(4)的位置处预留孔洞,再浇筑混凝土形成壁柱(5);(5)施工锚杆(4):在坡体中钻孔,将锚杆(4)置于钻孔中,并注入锚固浆体形成锚固段(9)和自由段(11);(6)固定锚杆(4):将锚杆(4)与壁柱(5)固定连接。
A cantilever retaining wall with a pilaster and an anchor rod and its construction method, the anchor rod (4) is composed of an anchor segment (9) and a free segment (11), and the anchor rod (4) passes through the anchor (10) and the pilaster ( 5) Fixed connection. The steps of the method are: (1) setting out and positioning, using a measuring instrument to locate the position of the wall heel plate (3) of the retaining wall; (2) constructing the wall heel plate (3) and the wall toe plate (2): formwork and then Pouring concrete to form the bottom slab of the cantilever retaining wall; (3) construction wall body (1); (4) construction pilaster (5): reserve holes at the positions where anchor rods (4) are designed to be added, and then pour concrete to form Wall column (5); (5) construction anchor rod (4): drill a hole in the slope body, place the anchor rod (4) in the drill hole, and inject anchor slurry to form the anchor segment (9) and the free segment ( 11); (6) Fix the anchor rod (4): connect the anchor rod (4) to the pilaster (5) fixedly.
Description
技术领域technical field
本发明涉及挡土墙施工技术,属于岩土工程领域。The invention relates to the construction technology of retaining walls and belongs to the field of geotechnical engineering.
背景技术Background technique
在现代基础工程建设中,遇到了越来越多需要支护的边坡工程。而悬臂式挡土墙以其构造简单、施工方便,能适应松软地基而受到广泛的应用。一般形式的悬臂式挡土墙由墙趾板、墙踵板和墙身板构成,主要依靠底板上的填土自重来抵抗边坡土压力并维持边坡稳定。因此当坡高较大时,墙身板下端所受弯矩较大,挡土墙稳定性较差,这就严重限制了悬臂式挡土墙的应用范围。本发明通过在悬臂式挡土墙的墙身板的设计位置加锚杆,使悬臂式挡土墙和锚杆共同承担上部荷载和墙后土压力,并在施加锚杆的墙身位置设置壁柱,可避免墙身板上的应力集中。这不仅进一步保证了支护边坡的稳定性,而且扩大了悬臂式挡土墙的使用范围。In the construction of modern foundation engineering, more and more slope projects needing support are encountered. The cantilever retaining wall is widely used because of its simple structure, convenient construction, and ability to adapt to soft ground. The general form of cantilever retaining wall is composed of wall toe plate, wall heel plate and wall body plate, mainly relying on the self-weight of the fill on the bottom plate to resist the soil pressure of the slope and maintain the stability of the slope. Therefore, when the slope height is high, the bending moment at the lower end of the wall panel is large, and the stability of the retaining wall is poor, which seriously limits the application range of the cantilever retaining wall. In the present invention, by adding anchor rods at the designed positions of the wall panels of the cantilever retaining wall, the cantilever retaining wall and the anchor rods jointly bear the upper load and the earth pressure behind the wall, and a pilaster is set at the wall body where the anchor rods are applied , to avoid stress concentration on the wall panel. This not only further ensures the stability of the supporting slope, but also expands the application range of the cantilever retaining wall.
在实际工程中,遇到的边坡高度大多是起伏不定的。一般悬臂式挡土墙适用于6m~9m的边坡,当边坡高度过高时,选用一般形式的悬臂式挡土墙便会存在一定的安全问题。此时可通过在墙身板的设计位置处加一排或多排锚杆来保证边坡的稳定性。若直接将锚杆用锚具固定在墙身板上,则会在锚杆处产生应力集中现象,会导致墙身板因应力集中而提早破坏。因此可通过在设计加锚杆处加一壁柱,将锚杆用锚具固定在所加壁柱上,这样便可以解决应力集中问题。加壁柱和锚杆的悬臂式挡土墙不仅具有一般悬臂式挡土墙构造简单、施工方便,经济合理的特点,而且可用于支护较高高度的边坡,在边坡支护中可得到更加广泛的应用。In actual engineering, most of the encountered slope heights are undulating. The general cantilever retaining wall is suitable for slopes of 6m to 9m. When the height of the slope is too high, there will be certain safety problems in choosing the general form of cantilever retaining wall. At this time, the stability of the slope can be ensured by adding one or more rows of anchor rods at the design positions of the wall panels. If the anchor rod is directly fixed to the wall panel with an anchor, stress concentration will occur at the anchor rod, which will lead to early failure of the wall panel due to stress concentration. Therefore, by adding a pilaster at the place where the anchor is designed, the anchor can be fixed on the added pilaster with an anchor, so that the problem of stress concentration can be solved. The cantilever retaining wall with pilasters and anchors not only has the characteristics of simple structure, convenient construction, and economical rationality of general cantilever retaining walls, but also can be used to support high slopes. be more widely applied.
发明内容Contents of the invention
本发明的目的在于提供了一种加壁柱与锚杆的悬臂式挡土墙及施工方法。The object of the present invention is to provide a cantilever retaining wall with wall columns and anchor rods and its construction method.
本发明是加壁柱与锚杆的悬臂式挡土墙及施工方法,加壁柱与锚杆的悬臂式挡土墙,包括墙身板1,墙趾板2,墙踵板3,锚杆4,壁柱5,泄水孔6,锚杆4由锚固段9和自由段11组成,锚杆4通过锚具10与壁柱5固定连接。The invention relates to a cantilever retaining wall with a wall column and an anchor rod and a construction method thereof. The cantilever retaining wall with a wall column and an anchor rod includes a wall body board 1, a wall toe board 2, a wall heel board 3, and an anchor rod 4 , pilaster 5, drain hole 6, anchor rod 4 is composed of anchor segment 9 and free segment 11, anchor rod 4 is fixedly connected with pilaster 5 through anchorage 10.
加壁柱与锚杆的悬臂式挡土墙的施工方法,其施工步骤为:The construction method of the cantilever retaining wall with pilasters and anchor rods, the construction steps are:
(1)放线及定位:首先根据工程设计图用测量仪器进行放线,其次平整场地,用测量仪器定位挡土墙墙踵板3的位置;(1) Setting out and positioning: Firstly, use measuring instruments to set out the lines according to the engineering design drawings, and then level the site, and use measuring instruments to locate the position of the wall heel plate 3 of the retaining wall;
(2)施工墙踵板3与墙趾板2:根据墙踵板3与墙趾板2的设计尺寸在所确定的施工位置支模,然后浇筑混凝土形成悬臂式挡土墙的底板;(2) Construction of the wall heel plate 3 and the wall toe plate 2: set up the formwork at the determined construction position according to the design dimensions of the wall heel plate 3 and the wall toe plate 2, and then pour concrete to form the bottom plate of the cantilever retaining wall;
(3)施工墙身板1:根据设计要求,在墙身板的设计位置支模,并在设计的锚杆4的位置处预留孔洞,然后浇筑混凝土,形成墙身板1;(3) Construction wall panel 1: According to the design requirements, set up the formwork at the design position of the wall panel, and reserve a hole at the position of the designed anchor rod 4, and then pour concrete to form the wall panel 1;
(4)施工壁柱5:根据锚杆4的水平间距,确定壁柱5的位置,然后在需设置壁柱5的位置支模,并在设计放置锚杆4的位置处预留孔洞,再浇筑混凝土形成壁柱5;(4) Construction of the pilaster 5: Determine the position of the pilaster 5 according to the horizontal spacing of the anchor rod 4, then set up the formwork at the position where the pilaster 5 needs to be installed, and reserve a hole at the position where the anchor rod 4 is designed to be placed, and then Pouring concrete to form pilasters 5;
(5)施工锚杆4:按照锚杆4的设计长度和倾斜角度,在坡体中钻孔,将锚杆4置于钻孔中,并注入锚固浆体形成锚固段9和自由段11;(5) Construction anchor 4: according to the design length and inclination angle of the anchor 4, drill holes in the slope body, place the anchor 4 in the drill hole, and inject anchor slurry to form the anchor section 9 and the free section 11;
(6)固定锚杆4:使用锚具10将锚杆4与壁柱5固定连接;(6) Fix the anchor rod 4: use the anchor 10 to fix the anchor rod 4 and the pilaster 5;
(7)重复以上步骤,施工相邻的下一段悬臂式挡土墙。(7) Repeat the above steps to construct the next adjacent cantilever retaining wall.
本发明的有益效果:悬臂式挡土墙施工方便、构造简单,能适应承载力较低的地基,墙高一般在6m~9m,在边坡支护中应用较为广泛。但当坡高较大时,墙身板1下部弯矩大,混凝土及钢材用量剧增,影响其经济效益。而本发明通过在墙身板1的设计位置加锚杆4,使挡土墙和锚杆4共同承担上部荷载和墙后土压力,因此可用于高度较高边坡的支护,且具有良好的抗震性能。并且本发明通过沿纵向在加锚杆4的位置处加壁柱5,将锚杆5通过锚具10固定在壁柱5上,可避免在墙身板1上产生应力集中造成墙身板1的过早破坏。Beneficial effects of the invention: the cantilever retaining wall is convenient in construction and simple in structure, and can adapt to foundations with low bearing capacity. The wall height is generally 6m to 9m, and it is widely used in slope support. But when the slope height is large, the bending moment at the lower part of the wall panel 1 is large, and the consumption of concrete and steel increases sharply, which affects its economic benefits. However, the present invention makes the retaining wall and the anchor rod 4 jointly bear the upper load and the earth pressure behind the wall by adding the anchor rod 4 at the design position of the wall body plate 1, so it can be used for the support of a higher slope, and has good Anti-seismic performance. And the present invention adds the pilaster 5 at the position where the anchor 4 is added in the longitudinal direction, and the anchor 5 is fixed on the pilaster 5 through the anchor 10, which can avoid stress concentration on the wall panel 1 and cause the wall panel 1 to be overwhelmed. Early destruction.
附图说明Description of drawings
图1是本发明加壁柱与锚杆的悬臂式挡土墙的立面示意图,图2是本发明加壁柱与锚杆的悬臂式挡土墙的剖面示意图,图3是本发明加壁柱与锚杆的悬臂式挡土墙的平面示意图。附图标记说明:挡土墙墙身板1、墙趾板2,墙踵板3,锚杆4,壁柱5,泄水孔6,锚杆的锚固段9、锚杆自由段10、锚具11。Fig. 1 is the elevation schematic view of the cantilever type retaining wall with wall column and anchor rod of the present invention, Fig. 2 is the sectional schematic diagram of the cantilever type retaining wall with wall column and anchor rod of the present invention, Fig. 3 is the wall of the present invention Schematic plan view of a cantilevered retaining wall with columns and anchors. Explanation of reference signs: wall body board 1 of retaining wall, wall toe board 2, wall heel board 3, anchor rod 4, pilaster 5, drain hole 6, anchoring section 9 of anchor rod, free section 10 of anchor rod, anchor 11.
具体实施方式Detailed ways
本发明是加壁柱与锚杆的悬臂式挡土墙及施工方法,加壁柱与锚杆的悬臂式挡土墙,包括墙身板1,墙趾板2,墙踵板3,锚杆4,壁柱5,泄水孔6,锚杆4由锚固段9和自由段11组成,锚杆4通过锚具10与壁柱5固定连接;所述的锚杆4为金属锚杆,或者纤维锚杆,或者复合锚杆;锚杆4与水平方向呈10°~35°的角度,在竖直方向呈一排或多排布置。The invention relates to a cantilever retaining wall with a wall column and an anchor rod and a construction method thereof. The cantilever retaining wall with a wall column and an anchor rod includes a wall body board 1, a wall toe board 2, a wall heel board 3, and an anchor rod 4 , pilaster 5, drain hole 6, anchor rod 4 is made up of anchor section 9 and free section 11, and anchor rod 4 is fixedly connected with pilaster 5 through anchorage 10; Described anchor rod 4 is metal anchor rod, or fiber Anchor rods, or composite anchor rods; the anchor rods 4 form an angle of 10° to 35° with the horizontal direction, and are arranged in one or more rows in the vertical direction.
以上所述的加壁柱与锚杆的悬臂式挡土墙,墙趾板2、墙踵板3为钢筋混凝土材料。For the above-mentioned cantilever retaining wall with pilasters and anchor rods, the wall toe board 2 and the wall heel board 3 are reinforced concrete materials.
以上所述的墙身板1为钢筋混凝土材料;所述的壁柱5为矩形截面钢筋混凝土材料。The wall body panel 1 mentioned above is a reinforced concrete material; the pilaster 5 is a reinforced concrete material with a rectangular cross section.
如图1、图2所示,所述的泄水孔6为Φ100PVC管,水平、竖向间距为2~3m,呈梅花形布置。As shown in Figures 1 and 2, the drain holes 6 are Φ100 PVC pipes with a horizontal and vertical spacing of 2 to 3 m and arranged in a plum blossom shape.
如图1~图3所示,所述的锚杆4的锚固段9用水泥浆填筑。As shown in Figures 1 to 3, the anchoring section 9 of the anchor rod 4 is filled with cement slurry.
如图2、图3所示,锚杆4的自由段11用Φ100PVC管包裹并涂防腐材料防止锚杆(4)锈蚀。As shown in Figures 2 and 3, the free section 11 of the anchor rod 4 is wrapped with a Φ100 PVC pipe and coated with anti-corrosion material to prevent the anchor rod (4) from rusting.
如图2所示,锚具10由混凝土台座、槽钢、垫板和高强螺栓组成。As shown in FIG. 2 , the anchorage 10 is composed of a concrete pedestal, a channel steel, a backing plate and high-strength bolts.
如图1~图3所示,加壁柱与锚杆的悬臂式挡土墙的施工方法,其施工步骤为:As shown in Figures 1 to 3, the construction method of the cantilever retaining wall with pilasters and anchors is as follows:
(1)放线及定位:首先根据工程设计图用测量仪器进行放线,其次平整场地,用测量仪器定位挡土墙墙踵板3的位置;(1) Setting out and positioning: Firstly, use measuring instruments to set out the lines according to the engineering design drawings, and then level the site, and use measuring instruments to locate the position of the wall heel plate 3 of the retaining wall;
(2)施工墙踵板3与墙趾板2:根据墙踵板3与墙趾板2的设计尺寸在所确定的施工位置支模,然后浇筑混凝土形成悬臂式挡土墙的底板;(2) Construction of the wall heel plate 3 and the wall toe plate 2: set up the formwork at the determined construction position according to the design dimensions of the wall heel plate 3 and the wall toe plate 2, and then pour concrete to form the bottom plate of the cantilever retaining wall;
(3)施工墙身板1:根据设计要求,在墙身板的设计位置支模,并在设计的锚杆4的位置处预留孔洞,然后浇筑混凝土,形成墙身板1;(3) Construction wall panel 1: According to the design requirements, set up the formwork at the design position of the wall panel, and reserve a hole at the position of the designed anchor rod 4, and then pour concrete to form the wall panel 1;
(4)施工壁柱5:根据锚杆4的水平间距,确定壁柱5的位置,然后在需设置壁柱5的位置支模,并在设计放置锚杆4的位置处预留孔洞,再浇筑混凝土形成壁柱5;(4) Construction of the pilaster 5: Determine the position of the pilaster 5 according to the horizontal spacing of the anchor rod 4, then set up the formwork at the position where the pilaster 5 needs to be installed, and reserve a hole at the position where the anchor rod 4 is designed to be placed, and then Pouring concrete to form pilasters 5;
(5)施工锚杆4:按照锚杆4的设计长度和倾斜角度,在坡体中钻孔,将锚杆4置于钻孔中,并注入锚固浆体形成锚固段9和自由段11;(5) Construction anchor 4: according to the design length and inclination angle of the anchor 4, drill holes in the slope body, place the anchor 4 in the drill hole, and inject anchor slurry to form the anchor section 9 and the free section 11;
(6)固定锚杆4:使用锚具10将锚杆4与壁柱5固定连接;(6) Fix the anchor rod 4: use the anchor 10 to fix the anchor rod 4 and the pilaster 5;
(7)重复以上步骤,施工相邻的下一段悬臂式挡土墙。(7) Repeat the above steps to construct the next adjacent cantilever retaining wall.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711081527.1A CN107700527A (en) | 2017-11-07 | 2017-11-07 | Add the cantilever retaining wall and construction method of pilaster and anchor pole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711081527.1A CN107700527A (en) | 2017-11-07 | 2017-11-07 | Add the cantilever retaining wall and construction method of pilaster and anchor pole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107700527A true CN107700527A (en) | 2018-02-16 |
Family
ID=61177663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711081527.1A Pending CN107700527A (en) | 2017-11-07 | 2017-11-07 | Add the cantilever retaining wall and construction method of pilaster and anchor pole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107700527A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113127962A (en) * | 2021-04-29 | 2021-07-16 | 辽宁工程技术大学 | Method for determining specification of anchor rod composite L-shaped cantilever type retaining wall in narrow space |
CN114482118A (en) * | 2022-01-17 | 2022-05-13 | 兰州铁道设计院有限公司 | A method for realizing the width of embankment with existing-new combined cantilever retaining wall |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1078518A (en) * | 1993-03-20 | 1993-11-17 | 周茂源 | Method with U-steel, anchor concrete stake supporting deep-foundation side wall |
CN203034478U (en) * | 2012-12-19 | 2013-07-03 | 福建工程学院 | Anchor rod/ cable cantilever type retaining wall |
CN103343532A (en) * | 2013-07-05 | 2013-10-09 | 郭红标 | Pre-stressed anchor cable pile-slab wall |
CN103469814A (en) * | 2013-09-24 | 2013-12-25 | 兰州理工大学 | Novel barricade supporting structure for road or river bank dam and construction method thereof |
CN104074197A (en) * | 2014-03-20 | 2014-10-01 | 温州大学 | Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof |
CN207567808U (en) * | 2017-11-07 | 2018-07-03 | 兰州理工大学 | Add the cantilever retaining wall of pilaster and anchor pole |
-
2017
- 2017-11-07 CN CN201711081527.1A patent/CN107700527A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1078518A (en) * | 1993-03-20 | 1993-11-17 | 周茂源 | Method with U-steel, anchor concrete stake supporting deep-foundation side wall |
CN203034478U (en) * | 2012-12-19 | 2013-07-03 | 福建工程学院 | Anchor rod/ cable cantilever type retaining wall |
CN103343532A (en) * | 2013-07-05 | 2013-10-09 | 郭红标 | Pre-stressed anchor cable pile-slab wall |
CN103469814A (en) * | 2013-09-24 | 2013-12-25 | 兰州理工大学 | Novel barricade supporting structure for road or river bank dam and construction method thereof |
CN104074197A (en) * | 2014-03-20 | 2014-10-01 | 温州大学 | Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof |
CN207567808U (en) * | 2017-11-07 | 2018-07-03 | 兰州理工大学 | Add the cantilever retaining wall of pilaster and anchor pole |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113127962A (en) * | 2021-04-29 | 2021-07-16 | 辽宁工程技术大学 | Method for determining specification of anchor rod composite L-shaped cantilever type retaining wall in narrow space |
CN114482118A (en) * | 2022-01-17 | 2022-05-13 | 兰州铁道设计院有限公司 | A method for realizing the width of embankment with existing-new combined cantilever retaining wall |
CN114482118B (en) * | 2022-01-17 | 2024-03-26 | 兰州铁道设计院有限公司 | Method for realizing embankment width by existing-newly-built combined cantilever retaining wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204419195U (en) | A kind of supporting and protection structure pattern being applicable to tunnel portal section | |
CN108130910B (en) | A support system for actively controlling foundation pit displacement and its design method | |
CN104264688A (en) | Manual hole digging non-uniform pile support construction technology | |
CN102162258B (en) | Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof | |
CN105937244A (en) | Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof | |
CN105970973A (en) | Soft soil foundation pit double-row piles supporting structure considering soil-arch and deformation space effect | |
CN104389315B (en) | Consolidation grouting drilled pile wall and construction method thereof | |
CN106522270A (en) | Pile foundation and retaining wall anti-earthquake retaining structure comprising EPS buffer layers and construction method | |
CN107059882A (en) | Arch anchor net and Anchor-Pile Retaining Structure structure | |
CN103469798A (en) | Pit support structure and construction method thereof | |
CN110397050B (en) | Beam-anchor type light drainage retaining wall and construction method thereof | |
CN207092107U (en) | A kind of anti-subsidence structure using diaphram wall | |
CN104631468A (en) | Supporting method for foundation pit excavation project | |
CN206034454U (en) | Supporting construction | |
CN107700527A (en) | Add the cantilever retaining wall and construction method of pilaster and anchor pole | |
CN205954638U (en) | Half semi -rigid flexible supporting construction of deep basal pit lateral wall | |
CN108316328A (en) | A kind of pressurization sinking device and its construction method for open caisson construction | |
CN108035360A (en) | A kind of method for pattern foundation pit supporting structure | |
CN201991013U (en) | High-piled tower footing structure of tower crane concrete-filled steel tube | |
CN207567808U (en) | Add the cantilever retaining wall of pilaster and anchor pole | |
CN203977432U (en) | Multistage H type soil blocking pile | |
CN206844132U (en) | Superelevation light supporting structure | |
CN206189447U (en) | Partly strut formula retaining wall | |
CN108005086A (en) | A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure | |
CN106988337A (en) | Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |