[go: up one dir, main page]

CN104074197A - Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof - Google Patents

Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof Download PDF

Info

Publication number
CN104074197A
CN104074197A CN201410102546.8A CN201410102546A CN104074197A CN 104074197 A CN104074197 A CN 104074197A CN 201410102546 A CN201410102546 A CN 201410102546A CN 104074197 A CN104074197 A CN 104074197A
Authority
CN
China
Prior art keywords
pile
construction
anchor
foundation pit
duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410102546.8A
Other languages
Chinese (zh)
Other versions
CN104074197B (en
Inventor
王军
叶强
蔡袁强
丁光亚
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Group Northwest Geotechnical Engineering Co Ltd
Original Assignee
Wenzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou University filed Critical Wenzhou University
Priority to CN201410102546.8A priority Critical patent/CN104074197B/en
Publication of CN104074197A publication Critical patent/CN104074197A/en
Application granted granted Critical
Publication of CN104074197B publication Critical patent/CN104074197B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种大直径薄壁筒桩复合锚杆式基坑围护结构及其施工方法,该围护结构设计主要涉及止水帷幕、薄壁筒桩、被动区加固桩、压顶梁和围檩的连接与构造设计,该围护结构施工过程主要有止水帷幕施工、大直径薄壁筒桩的施工、被动区加固桩施工、第一层锚杆的施工(下挖基坑→钻机成孔→锚杆体入孔→锚固段灌浆→自由端灌浆→安装紧固螺母)、第二层锚杆施工(下挖基坑→钻机成孔→锚杆体入孔→锚固段灌浆→自由端灌浆)和第一层围檩施工(绑扎围檩钢筋→安装围檩模板→浇筑混凝土)。通过特殊的构造设计与施工将传统主要用于地基处理的大直径薄壁筒桩与高强锚杆、围檩复合来围护基坑,达到经济、环保和高效的效果,并为后续基坑施工带来极大的便捷。

The invention discloses a large-diameter thin-walled cylindrical pile composite anchor rod type foundation pit enclosure structure and a construction method thereof. The enclosure structure design mainly involves water-stop curtains, thin-walled cylindrical piles, passive zone reinforcement piles, top beams and The connection and structural design of purlins. The construction process of the enclosure structure mainly includes the construction of water-stop curtain, the construction of large-diameter thin-walled cylindrical piles, the construction of reinforced piles in the passive zone, and the construction of the first layer of anchor rods (digging foundation pit→drilling rig Hole forming → anchor body entry → anchor section grouting → free end grouting → installation of fastening nut), the second layer of anchor construction (digging the foundation pit → drilling rig to form a hole → anchor body entry → anchor section grouting → free end grouting) and purlin construction of the first layer (binding purlin reinforcement → installing purlin formwork → pouring concrete). Through special structural design and construction, the traditional large-diameter thin-walled piles, which are mainly used for foundation treatment, are combined with high-strength anchor rods and purlins to enclose the foundation pit, achieving economical, environmental protection and high-efficiency effects, and laying foundation for the subsequent foundation pit construction. Bring great convenience.

Description

大直径薄壁筒桩复合锚杆式基坑围护结构及其施工方法Large-diameter thin-walled cylindrical pile composite anchor type foundation pit enclosure structure and its construction method

技术领域 technical field

本发明涉及一种建筑物基坑的围护结构,更进一步涉及的是一种软粘土地区基坑围护的新型有效结构设计以及相应的施工方法。 The invention relates to an enclosure structure for a foundation pit of a building, and further relates to a new effective structural design and a corresponding construction method for the enclosure enclosure of a foundation pit in a soft clay area.

背景技术 Background technique

中国的发展主要是经济的发展,经济的发展带来的是建筑业的发展,建筑业的发展方向势必是建筑的更高更大更优更美,而这个方向的保障是为建筑打下坚实的基础,这也就要求在基坑围护方面做得更多。另一方面,由于建筑用地越来越少,越来越多的建筑施工不得不在基础条件稍差的软土地区开展,这也就更具体地提出了如何更好地围护软土地区基坑这样一个技术问题。 The development of China is mainly the development of the economy. The development of the economy brings the development of the construction industry. The development direction of the construction industry is bound to be taller, bigger, better and more beautiful. The guarantee of this direction is to lay a solid foundation for the construction. Foundation, which also requires doing more in foundation pit enclosure. On the other hand, due to less and less construction land, more and more building construction has to be carried out in soft soil areas with poor foundation conditions, which also puts forward more specifically how to better protect foundation pits in soft soil areas Such a technical problem.

目前在软土地区的基坑围护结构主要有:土钉墙、地下连续墙、SMW工法以及灌注桩加内支撑等。土钉墙通过在土体内设置一定长度和密度的土钉,与土共同作用,形成了以增强边坡稳定能力为主要目的的复合土体,是一种主动制约机制,土钉与土的相互作用,形成了能提高原状土强度和刚度的复合土体,改变了土坡的变形与破坏形式,显著提高了土坡的整体稳定性。然而,土钉墙存在缺乏合理的控制位移计算理论的缺点,对于有严格位移要求的软土基坑并不适应。地下连续墙是在地面上采用一种挖槽机械,沿着深开挖工程的周边轴线,在泥浆护壁条件下,开挖出一条狭长的深槽,清槽后,在槽内吊放钢筋,然后用导管法灌筑水下混凝土筑成一个单元槽段,如此逐段进行,在地下筑成一道连续的钢筋混凝土墙壁,作为截水、防渗、承重、挡水的基坑围护结构。地下连续墙围护结构存在对施工过程中产生的废泥浆处理困难,挖槽以后的槽壁容易坍塌,造价较高,对施工单位操作水平要求也较高的问题。SMW工法围护结构(劲性水泥土连续墙)是采用专用多轴搅拌机,就地钻进切削土体,同时从其钻头前端将水泥浆液注入土体,经反复搅拌和充分混合后,再将H型钢或其它芯材插入搅拌体内,形成地下连续墙体,它主要的缺点是围护刚度较小,开挖后的变形较大。灌注桩加内支撑是指用钻孔灌注桩作为围护桩,围护桩顶设置压顶梁,在基坑外侧设置止水帷幕以及在基坑内侧设置排水措施,然后在基坑内侧设置一层或多层围檩并在相应的围檩处设置内支撑的围护结构。这种围护结构存在泥浆污染严重,泥浆后续处理困难,钻孔耗能较大,围护桩质量难以保证以及基坑内施工不便等缺点。2014年3月18日。 At present, the foundation pit enclosure structures in soft soil areas mainly include: soil nail wall, underground diaphragm wall, SMW construction method, and cast-in-place pile plus internal support. The soil nail wall forms a composite soil with the main purpose of enhancing the stability of the slope by setting soil nails of a certain length and density in the soil and interacting with the soil. It is an active control mechanism. The interaction between soil nails and soil As a result, a composite soil body that can improve the strength and stiffness of the undisturbed soil is formed, the deformation and failure form of the soil slope are changed, and the overall stability of the soil slope is significantly improved. However, the soil nail wall has the disadvantage of lacking a reasonable control theory for displacement calculation, and it is not suitable for soft soil foundation pits with strict displacement requirements. The underground diaphragm wall adopts a kind of trenching machine on the ground, along the peripheral axis of the deep excavation project, under the condition of mud retaining wall, excavates a narrow and long deep groove, after clearing the groove, hang steel bars in the groove, Then use the conduit method to fill the underwater concrete to build a unit tank section, and then build a continuous reinforced concrete wall underground as a foundation pit enclosure structure for water interception, seepage prevention, load bearing, and water retention. The enclosure structure of the underground diaphragm wall is difficult to deal with the waste mud generated during the construction process, the trench wall is easy to collapse after the trench is excavated, the cost is high, and the operation level of the construction unit is also required to be high. The SMW construction method enclosure structure (stiff cement-soil continuous wall) uses a special multi-shaft mixer to drill and cut the soil on the spot, and at the same time inject the cement slurry into the soil from the front end of the drill bit. H-shaped steel or other core materials are inserted into the mixing body to form an underground continuous wall. Its main disadvantage is that the enclosure rigidity is small and the deformation after excavation is large. Cast-in-situ pile plus internal support refers to the use of bored piles as surrounding protection piles, top pressure beams are set on the top of the surrounding piles, water-stop curtains are set on the outside of the foundation pit and drainage measures are set on the inside of the foundation pit, and then a layer is set on the inside of the foundation pit. Or multi-layer purlins and set up an inner support enclosure structure at the corresponding purlins. This enclosure structure has the disadvantages of serious mud pollution, difficulty in subsequent mud treatment, high energy consumption for drilling, difficulty in ensuring the quality of enclosure piles, and inconvenient construction in the foundation pit. March 18, 2014.

发明内容 Contents of the invention

本发明主要解决的技术问题是,为软土地区的基坑提供一种安全、环保、高效、经济以及能为后续基坑开挖施工提供便捷的大直径薄壁筒桩围护结构的设计及其施工方法。 The technical problem mainly solved by the present invention is to provide a safe, environment-friendly, efficient, economical design and design of a large-diameter thin-walled cylindrical pile enclosure structure that is convenient for subsequent foundation pit excavation construction for foundation pits in soft soil areas. its construction method.

本发明的技术解决方案是:大直径薄壁筒桩复合锚杆式基坑围护结构,其特征是:包括水泥搅拌桩止水帷幕、大直径薄壁筒桩、第一层锚杆和第二层锚杆、压顶梁、围檩和被动区加固桩,所述止水帷幕处于基坑围护结构的外围,且由沿基坑周围分布的多个单排水泥搅拌桩构成;所述大直径薄壁筒桩为现浇式薄壁筒桩,且处于止水帷幕内侧,大直径薄壁筒桩包括薄壁桩身和桩头,桩头带有桩头通孔,所述桩顶浇筑有增强各围护桩整体稳定性的压顶梁,在所述薄壁桩身上沿深度方向依次开设第一孔道和第二孔道,所述第一孔道和第二孔道均包括处于桩身的桩身孔和处于土体中的土体孔,所述第一层锚杆插入第一孔道并到达土体孔中,第一孔道与第一层锚杆之间灌注有水泥浆,所述第一层锚杆插入的第一孔道口浇筑锚固有托板,紧固螺母与第一层锚杆的一端螺纹连接并将托板压紧在薄壁桩身上,所述第二层锚杆插入第二孔道并到达土体孔中,第二孔道与第二层锚杆之间灌注有水泥浆,所述第二层锚杆预留一定长度的杆体钢筋在第二孔道外,围檩内部钢筋与杆体钢筋绑扎,围檩由混凝土构成;所述被动区加固桩处于大直径薄壁筒桩内侧,且由打设于土体内的水泥搅拌桩构成。 The technical solution of the present invention is: a large-diameter thin-walled cylindrical pile composite anchor-type foundation pit enclosure structure, which is characterized in that it includes a cement mixing pile water-stop curtain, a large-diameter thin-walled cylindrical pile, the first layer of anchor rods and the second The second layer of anchor rods, top beams, surrounding purlins and reinforcement piles in the passive area, the water-stop curtain is located at the periphery of the foundation pit enclosure structure, and is composed of a plurality of single-row cement mixing piles distributed around the foundation pit; the large The diameter thin-walled cylindrical pile is a cast-in-place thin-walled cylindrical pile, and is located inside the water-stop curtain. The large-diameter thin-walled cylindrical pile includes a thin-walled pile body and a pile head. The pile head has a pile head through hole. The pile top is poured There is a top beam that enhances the overall stability of each surrounding protection pile, and a first tunnel and a second tunnel are sequentially opened on the thin-walled pile body along the depth direction, and the first tunnel and the second tunnel both include the pile body in the pile body Holes and soil holes in the soil, the first layer of anchors are inserted into the first tunnel and reach the soil hole, cement slurry is poured between the first tunnel and the first layer of anchors, the first layer The first hole where the anchor rod is inserted is poured and anchored with a supporting plate, the fastening nut is threaded with one end of the first layer of anchor rod and the supporting plate is pressed against the thin-walled pile, and the second layer of anchor rod is inserted into the second hole And reach the soil hole, cement slurry is poured between the second tunnel and the second layer of anchor rods, the second layer of anchor rods reserves a certain length of rod body reinforcement outside the second tunnel, and the internal reinforcement of the surrounding purlin and the rod body reinforcement Binding, the surrounding purlins are made of concrete; the reinforcement piles in the passive area are located inside the large-diameter thin-walled cylindrical piles, and are made of cement mixing piles driven in the soil.

上述大直径薄壁筒桩复合锚杆式基坑围护结构的施工方法包括以下施工步骤: The construction method of the above-mentioned large-diameter thin-walled cylindrical pile composite anchor rod type foundation pit enclosure structure includes the following construction steps:

(1)止水帷幕施工 (1) Waterstop curtain construction

     止水帷幕处于基坑围护结构的外围,采用沿基坑周围分布的数量较多的单排水泥搅拌桩包围形成; The water-stop curtain is located on the periphery of the foundation pit enclosure structure, and is surrounded by a large number of single-row cement mixing piles distributed along the foundation pit;

(2)大直径薄壁筒桩施工 (2) Construction of large-diameter thin-walled cylindrical piles

    ①将大直径薄壁筒桩的预制桩头嵌入内钢筒模板和外钢筒模板之间; ① Embed the prefabricated pile head of the large-diameter thin-walled cylindrical pile between the inner steel cylinder formwork and the outer steel cylinder formwork;

    ②在刚筒模板顶部安装夹振器,用来固定高频振动器,高频振动器调整就位后,将内钢筒模板和外钢筒模板及预制桩头压入土内至预制桩头达到设计深度; ②Install a vibration clamp on the top of the rigid cylinder formwork to fix the high-frequency vibrator. After the high-frequency vibrator is adjusted in place, press the inner steel cylinder formwork, the outer steel cylinder formwork and the prefabricated pile head into the soil until the prefabricated pile head reaches design depth;

    ③松开模板顶部的夹振器,将预制好的钢筋笼放入环形模板腔内,通过外钢筒模板上的混凝土浇注口浇注混凝土,并同时起吊钢筒模板; ③ Loosen the vibration clamp on the top of the formwork, put the prefabricated reinforcement cage into the annular formwork cavity, pour concrete through the concrete pouring port on the outer steel cylinder formwork, and lift the steel cylinder formwork at the same time;

    ④重复上述步骤,施工下一个大直径薄壁筒桩直至基坑所需的所有围护用大直径薄壁筒桩施工完毕; ④ Repeat the above steps to construct the next large-diameter thin-walled cylindrical pile until all the large-diameter thin-walled cylindrical piles required for the enclosure of the foundation pit are completed;

⑤待围护桩混凝土达到设计强度后,清除基坑围护桩顶部的杂土,浇筑增强各围护桩整体稳定性的压顶梁。 ⑤ After the concrete of the retaining piles reaches the design strength, remove the miscellaneous soil on the top of the retaining piles in the foundation pit, and pour the top beams to enhance the overall stability of the retaining piles.

(3)被动区加固桩施工 (3) Construction of reinforcement piles in the passive zone

     被动区加固桩处于大直径薄壁筒桩内侧,且由打设于土体内的水泥搅拌桩构成。 The reinforced piles in the passive zone are located inside the large-diameter thin-walled cylindrical piles, and are composed of cement mixing piles driven in the soil.

(4)第一层锚杆施工 (4) The first layer of anchor rod construction

    ①下挖基坑至第一层锚杆设计标高以下1m处; ①Dig the foundation pit down to 1m below the design elevation of the first layer of anchor bolts;

    ②按照施工设计图采用全站仪进行测量放样确定锚杆设计孔位及锚孔方位角,并在围护桩身上标记; ②According to the construction design drawing, use a total station to measure and set out to determine the design hole position and anchor hole azimuth of the anchor bolt, and mark it on the enclosure pile;

    ③钻机就位,在标记孔位进行钻孔; ③The drilling rig is in place, and the hole is drilled at the marked hole position;

    ④将锚杆用力一致地推送进入孔道,推送过程中不得转动杆体;采用压力活塞式注浆泵对孔道进行灌浆,将水泥浆经注浆管推入孔内,然后进行灌浆,并在锚杆孔道口浇筑锚固托板并安装紧固螺母。 ④Push the anchor rod into the tunnel forcefully and consistently, and do not rotate the rod body during the pushing process; use a pressure piston type grouting pump to grout the tunnel, push the cement slurry into the hole through the grouting pipe, and then grout, and install it on the anchor rod Anchor supporting plates are poured at the opening of the tunnel and fastening nuts are installed.

(5)第二层锚杆施工 (5) Construction of the second layer of anchor rods

    ①下挖基坑至第二层锚杆设计标高以下1m处; ①Dig the foundation pit down to 1m below the design elevation of the second floor anchor;

    ②按照施工设计图采用全站仪进行测量放样确定锚杆设计孔位及锚孔方位角,并在围护桩身上标记; ②According to the construction design drawing, use a total station to measure and set out to determine the design hole position and anchor hole azimuth of the anchor bolt, and mark it on the enclosure pile;

    ③钻机就位,在标记孔位进行钻孔; ③The drilling rig is in place, and the hole is drilled at the marked hole position;

    ④将锚杆用力一致地推送进入孔道,推送过程中不得转动杆体;采用压力活塞式注浆泵对孔道进行灌浆,将水泥浆经注浆管推入孔内,然后进行灌浆;预留一定长度的锚杆的杆体钢筋在孔道外; ④Consistently push the bolt into the hole, and do not rotate the rod body during the pushing process; use the pressure piston type grouting pump to grout the hole, push the cement slurry into the hole through the grouting pipe, and then grout; reserve a certain length The rod body reinforcement of the anchor rod is outside the tunnel;

(6)第一层围檩施工 (6) Purlin construction on the first layer

    ①将第二层锚杆预留的第二孔道外的杆体钢筋与第一层围檩钢筋绑扎; ① Bind the rod body reinforcement outside the second channel reserved for the second layer of anchor rods with the first layer of purlin reinforcement;

②安装第一层围檩的模板,并浇筑混凝土; ②Install the formwork for the first layer of purlins and pour concrete;

4、根据权利要求书1所述的大直径薄壁筒桩复合锚杆式基坑围护结构的施工方法,其特征是:施工步骤(2)的分步骤③中的预制钢筋笼预留了锚杆孔道所需的孔洞,为锚杆能在对筒桩破坏最小的情况下穿过筒桩与其复合;施工步骤(2)—③中的混凝土浇注为分段浇注分段振实,钢模板分段起吊。 4. According to the construction method of large-diameter thin-walled cylindrical pile composite anchor-type foundation pit enclosure structure according to claim 1, it is characterized in that: the prefabricated steel cage in the sub-step ③ of the construction step (2) has reserved The hole required for the anchor channel is that the anchor can pass through the cylindrical pile and compound it with the minimum damage to the cylindrical pile; the concrete pouring in the construction steps (2)-③ is segmental pouring and segmental vibration, and the steel formwork is segmented lift.

本发明大直径薄壁筒桩复合锚杆式基坑围护结构及施工方法与现有的技术相比,具有以下显著优点和有益效果: Compared with the existing technology, the large-diameter thin-walled cylindrical pile composite anchor type foundation pit enclosure structure and construction method of the present invention have the following significant advantages and beneficial effects:

从宏观角度来说,本发明的基坑围护结构及施工过程主要突出了安全、环保、经济以及便捷等几个方面的优点。首先,本发明通过为筒桩钢筋笼预留锚杆孔洞来使锚杆能在对筒桩破坏最小的情况下穿过筒桩,并进一步利用预留锚杆杆体钢筋作为桥梁来实现能在不破坏筒桩薄壁的情况下连接筒桩、锚杆和围檩,形成整体稳定性非常好且抗侧向变形能力强的围护结构,具有较好的安全性,同时这种围护结构中不设置内支撑,可以节约大量资源的浪费(内支撑一般后续拆除浪费)并且为基坑内的后续施工带来极大的方便,体现了本发明的环保、经济和便捷性。其次,利用大直径薄壁筒桩作为围护桩施工过程中不需要利用钻孔机和打桩机等大型机械,不需要大量的泥浆护壁,不需要开挖大量的场地土,从而能减少施工过程中的噪音污染,降低安全隐患,避免泥浆及土方的后续运输和处理问题,体现了本发明的安全环保性;最后,该围护桩虽然直径大(具有很好的整体稳定性和抗侧向变形性),但是所需的混凝土和钢筋用量却远远小于相近直径的其它种类围护桩,体现了本发明的经济性。 From a macro point of view, the foundation pit enclosure structure and construction process of the present invention mainly highlight the advantages of safety, environmental protection, economy and convenience. First of all, the present invention makes the anchor rod pass through the cylindrical pile with minimum damage to the cylindrical pile by reserving the hole of the anchor rod for the reinforcement cage of the cylindrical pile, and further utilizes the reserved anchor rod body reinforcement as a bridge to realize the When the thin wall of the cylindrical pile is destroyed, the cylindrical pile, the anchor rod and the purlin are connected to form an enclosure structure with very good overall stability and strong resistance to lateral deformation, which has good safety. At the same time, this enclosure structure The absence of internal support can save a lot of waste of resources (the internal support is generally a waste of subsequent dismantling) and brings great convenience to the subsequent construction in the foundation pit, which embodies the environmental protection, economy and convenience of the present invention. Secondly, the use of large-diameter thin-walled cylindrical piles as enclosure piles does not require the use of large-scale machinery such as drilling machines and pile drivers, does not require a large amount of mud wall protection, and does not need to excavate a large amount of site soil, thereby reducing the construction process. Noise pollution in the environment, reduce potential safety hazards, avoid follow-up transportation and treatment of mud and earthwork, embodies the safety and environmental protection of the present invention; finally, although the enclosure pile has a large diameter (has good overall stability and lateral resistance Deformability), but the required amount of concrete and reinforcement is far less than other types of enclosure piles with similar diameters, reflecting the economy of the present invention.

附图说明 Description of drawings

    图1是本发明所涉及的基坑围护结构的围护桩、锚杆与围檩复合结构局部正视图。 Fig. 1 is a partial front view of the compound structure of the enclosure pile, anchor rod and enclosure purlin of the foundation pit enclosure structure involved in the present invention.

    图2是本发明所涉及的基坑围护结构的侧剖面局部结构示意图。 Fig. 2 is a schematic diagram of a side section partial structure of the foundation pit enclosure structure involved in the present invention.

    图3是本发明所涉及的基坑围护结构的大直径薄壁筒桩结构及施工示意图。 Figure 3 is a schematic diagram of the large-diameter thin-walled cylindrical pile structure and construction of the foundation pit enclosure structure involved in the present invention.

    图4是本发明所涉及的基坑围护结构的第一层锚杆与围护桩复合结构细部示意图。 Figure 4 is a detailed schematic diagram of the composite structure of the first layer of anchor rods and surrounding protection piles of the foundation pit protection structure involved in the present invention.

图5是本发明所涉及的基坑围护结构的第二层锚杆的结构示意图。 Fig. 5 is a structural schematic diagram of the second layer of anchor rods of the foundation pit enclosure structure involved in the present invention.

图6为图5中的第一层围檩与围护桩复合结构细部示意图。 Fig. 6 is a detailed schematic diagram of the composite structure of the first layer of surrounding purlins and surrounding protection piles in Fig. 5 .

    图7是本发明所涉及的基坑围护结构的俯视局部结构示意图。 Fig. 7 is a top view partial structural schematic diagram of the foundation pit enclosure structure involved in the present invention.

    图8是本发明所涉及的基坑围护结构的第一层围檩处俯视局部结构示意图。 Fig. 8 is a schematic diagram of the local structure of the first layer of the surrounding purlins of the foundation pit enclosure structure involved in the present invention.

图中所示:1、大直径薄壁筒桩,2、桩头,3、压顶梁,4、第一层锚杆,5、第二层锚杆,6、第一层围檩,7、外钢筒模板,8、内钢筒模板,9、高频振动器,10、夹振器,11、混凝土浇筑口,12、桩头通孔,13、基坑,14、锚固段,15、自由段,16、锚杆孔道,17、托板,18、紧固螺母,19、注浆管,20、筒桩钢筋笼,21、孔洞,22、杆体钢筋,23、第一层围檩钢筋,24、高强钢丝,25、被动区加固桩,26、止水帷幕。 As shown in the figure: 1. Large-diameter thin-walled cylindrical pile, 2. Pile head, 3. Top beam, 4. The first layer of anchor rods, 5. The second layer of anchor rods, 6. The first layer of purlins, 7. Outer steel cylinder formwork, 8. Inner steel cylinder formwork, 9. High-frequency vibrator, 10. Vibration clamp, 11. Concrete pouring opening, 12. Pile head through hole, 13. Foundation pit, 14. Anchorage section, 15. Free section, 16, anchor hole, 17, supporting plate, 18, fastening nut, 19, grouting pipe, 20, tube pile reinforcement cage, 21, hole, 22, rod body reinforcement, 23, first layer of purlin reinforcement , 24, high-strength steel wire, 25, passive zone reinforcement pile, 26, water-stop curtain.

具体实施方式 Detailed ways

下面结合附图和具体实施例对本发明作进一步说明: The present invention will be further described below in conjunction with accompanying drawing and specific embodiment:

图1~图8只是本发明的一种实施例,所示实施例的基坑围护结构为大直径薄壁筒桩复合一层围檩与两层锚杆。 Figures 1 to 8 are just one embodiment of the present invention, and the enclosure structure of the foundation pit shown in the embodiment is a large-diameter thin-walled cylindrical pile compounded with a layer of purlins and two layers of anchor rods.

它的具体结构设计如下: Its specific structure design is as follows:

参照图1、图2、图3、图4、图5、图6、图7、图8所示,该实施例提供的大直径薄壁筒桩复合锚杆式基坑围护结构,包括水泥搅拌桩止水帷幕26、大直径薄壁筒桩1、第一层锚杆4、第二层锚杆5、压顶梁3、第一层围檩6和被动区加固桩25。所述止水帷幕26处于基坑围护结构的外围,且由沿基坑周围分布的多个单排水泥搅拌桩构成,水泥搅拌桩的直径为500mm,桩间距为350mm,设计深度为8m,水泥为32.5级的硅酸盐水泥,水灰比控制在0.5左右。所述大直径薄壁筒桩1为现浇式薄壁筒桩,且处于止水帷幕26内侧,大直径薄壁筒桩1包括薄壁桩身和桩头2,桩头2带有桩头通孔,大直径薄壁筒桩1的壁厚为200mm,筒桩外径为1000mm,桩间距为1000mm,设计深度为10m,所述桩顶浇筑有增强各围护桩整体稳定性的压顶梁3,大直径薄壁筒桩1桩顶嵌入压顶梁3里,混凝土等级为C30。在所述薄壁桩身上沿深度方向依次开设有两个锚杆孔道16,锚杆孔道16分别为第一孔道和第二孔道,所述第一孔道和第二孔道均包括处于桩身的桩身孔和处于土体中的土体孔,所述第一层锚杆4插入第一孔道并到达土体孔中,第一孔道与第一层锚杆4之间灌注有水泥浆,所述第一层锚杆4插入的第一孔道口浇筑锚固有托板17,紧固螺母18与第一层锚杆4的一端螺纹连接并将托板17压紧在薄壁桩身上,所述第二层锚杆5插入第二孔道并到达土体孔中,第二孔道与第二层锚杆5之间灌注有水泥浆,所述第二层锚杆5预留一定长度的杆体钢筋22在第二孔道外,第一层锚杆4和第二层锚杆5为精轧螺纹钢,锚杆孔道16的钻孔深度为5m,孔径80mm。所述围檩6内部钢筋23与杆体钢筋22绑扎,围檩6由混凝土构成。所述被动区加固桩25处于大直径薄壁筒桩1内侧,且由打设于土体内的水泥搅拌桩构成,具体施工是:被动区每隔3m作为一个加固节点,设置水泥搅拌桩加固,加固桩25设置三排,每排5根桩,桩的直径为500mm,桩间距为350mm,排间距为500mm,设计深度为10m。 Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, and Fig. 8, the large-diameter thin-walled cylindrical pile composite anchor rod foundation pit enclosure structure provided by this embodiment includes cement Stirring pile water-stop curtain 26, large-diameter thin-walled cylindrical pile 1, anchor rod 4 of the first layer, anchor rod 5 of the second layer, top beam 3, purlin 6 of the first layer and reinforcement pile 25 in the passive area. The water-stop curtain 26 is located at the periphery of the foundation pit enclosure structure, and is composed of a plurality of single-row cement mixing piles distributed around the foundation pit. The diameter of the cement mixing piles is 500mm, the pile spacing is 350mm, and the design depth is 8m. The cement is Portland cement of grade 32.5, and the water-cement ratio is controlled at about 0.5. The large-diameter thin-walled cylindrical pile 1 is a cast-in-place thin-walled cylindrical pile and is located inside the water-stop curtain 26. The large-diameter thin-walled cylindrical pile 1 includes a thin-walled pile body and a pile head 2, and the pile head 2 has a pile head Through holes, the wall thickness of the large-diameter thin-walled cylindrical pile 1 is 200mm, the outer diameter of the cylindrical pile is 1000mm, the pile spacing is 1000mm, and the design depth is 10m. The top of the pile is poured with a pressure beam that enhances the overall stability of the surrounding protection piles 3. The top of the large-diameter thin-walled tubular pile 1 is embedded in the top of the top beam 3 miles, and the concrete grade is C30. On the thin-walled pile body, there are two anchor tunnels 16 successively along the depth direction. The anchor tunnels 16 are respectively the first tunnel and the second tunnel, and the first tunnel and the second tunnel all include piles in the pile body. The body hole and the soil hole in the soil, the first layer of anchor rod 4 is inserted into the first tunnel and reaches the soil hole, cement slurry is poured between the first tunnel and the first layer of anchor rod 4, the The first hole in which the first layer of anchor rods 4 is inserted is poured and anchored with a supporting plate 17, and the fastening nut 18 is threadedly connected with one end of the first layer of anchor rods 4 and the supporting plate 17 is pressed against the thin-walled pile body. The second layer of anchor rod 5 is inserted into the second tunnel and reaches the soil hole, cement slurry is poured between the second tunnel and the second layer of anchor rod 5, and a certain length of rod body reinforcement 22 is reserved for the second layer of anchor rod 5. Outside the second channel, the first layer of anchor rods 4 and the second layer of anchor rods 5 are finished rolled rebar, and the drilling depth of the anchor rod channel 16 is 5m and the aperture is 80mm. The internal steel bar 23 of the purlin 6 is bound to the steel bar 22 of the pole body, and the purlin 6 is made of concrete. The reinforcement pile 25 in the passive area is located inside the large-diameter thin-walled cylindrical pile 1, and is composed of cement mixing piles set in the soil body. The specific construction is: every 3m in the passive area is used as a reinforcement node, and cement mixing piles are set for reinforcement. Three rows of reinforcement piles 25 are arranged, each row has 5 piles, the diameter of the piles is 500mm, the pile spacing is 350mm, the row spacing is 500mm, and the design depth is 10m.

它的具体施工方法包括以下步骤: Its specific construction method includes the following steps:

(1)止水帷幕26施工 (1) Waterstop curtain 26 construction

     止水帷幕26处于基坑围护结构的外围,采用沿基坑周围分布的数量较多的单排水泥搅拌桩包围形成,采用二次注浆二次搅拌工艺,第一次搅拌头下沉搅拌至设计深度,接着一边注浆一边提升搅拌头至设计面标高,然后第二次将搅拌头下沉搅拌至设计深度,又第二次一边注浆一边提升搅拌头至设计面标高,形成水泥搅拌桩止水帷幕26。 The water-stop curtain 26 is located on the periphery of the foundation pit enclosure structure, and is surrounded by a large number of single-row cement mixing piles distributed around the foundation pit. The secondary grouting and secondary mixing process is adopted, and the first mixing head sinks and mixes. To the design depth, then raise the mixing head to the design surface elevation while grouting, then sink the mixing head to the design depth for the second time, and raise the mixing head to the design surface elevation while grouting for the second time, forming cement mixing Pile waterstop curtain 26.

(2)大直径薄壁筒桩1施工 (2) Construction of large-diameter thin-walled cylindrical pile 1

    ①将大直径薄壁筒桩1的预制桩头2嵌入内钢筒模板8外钢筒模板7之间,所述的外钢筒模板7设有混凝土浇注口11,所述的预制桩头2为锥形桩头且预制了桩头通孔12来输出下沉过程中的软土; ① Embedding the prefabricated pile head 2 of the large-diameter thin-walled cylindrical pile 1 between the inner steel cylinder formwork 8 and the outer steel cylinder formwork 7, the outer steel cylinder formwork 7 is provided with a concrete pouring port 11, and the prefabricated pile head 2 It is a conical pile head and the pile head through hole 12 is prefabricated to output the soft soil in the subsidence process;

    ②在刚筒模板顶部安装夹振器10,用来固定高频振动器9,高频振动器9调整就位后,将内钢筒模板8外钢筒模板7及预制桩头压入土内至预制桩头达到设计深度,所述下压模板过程需要不断调整桩身竖直; ②Install the vibration clamp 10 on the top of the rigid cylinder formwork to fix the high frequency vibrator 9. After the high frequency vibrator 9 is adjusted in place, press the inner steel cylinder formwork 8, the outer steel cylinder formwork 7 and the prefabricated pile head into the soil until The prefabricated pile head reaches the design depth, and the process of pressing down the formwork needs to continuously adjust the verticality of the pile body;

    ③松开模板顶部的夹振器10,将预制好的钢筋笼20放入环形模板腔内,通过外钢筒模板7上的混凝土浇注口11浇注混凝土,采用分段浇注,并同时起吊钢筒模板,所述的钢筋笼20在各层锚杆设计位置预留了锚杆孔道的孔洞21; ③ Loosen the vibration clamp 10 on the top of the formwork, put the prefabricated steel cage 20 into the annular formwork cavity, pour concrete through the concrete pouring port 11 on the outer steel cylinder formwork 7, adopt segmental pouring, and lift the steel cylinder at the same time Formwork, the steel cage 20 has reserved the hole 21 of the bolt tunnel at the design position of each layer of bolt;

    ④重复上述步骤,施工下一个大直径薄壁筒桩1直至基坑所需的所有围护桩施工完毕; ④Repeat the above steps to construct the next large-diameter thin-walled cylindrical pile 1 until all the surrounding protection piles required for the foundation pit are completed;

    ⑤待围护桩混凝土达到设计强度后,清除基坑围护桩顶部的杂土,浇筑增强各围护桩整体稳定性的压顶梁3。 ⑤ After the concrete of the retaining piles reaches the design strength, remove the miscellaneous soil on the top of the retaining piles in the foundation pit, and pour the top beam 3 to enhance the overall stability of the retaining piles.

(3)被动区加固桩25施工 (3) Construction of reinforcement pile 25 in the passive area

    被动区加固桩25处于大直径薄壁筒桩1内侧,且由打设于土体内的水泥搅拌桩构成,被动区加固桩25分排施工,每排施工如上述水泥土搅拌桩施工方法。 The reinforcement piles 25 in the passive area are located inside the large-diameter thin-walled cylindrical pile 1, and are composed of cement mixing piles driven in the soil. The reinforcement piles in the passive area are constructed in rows, and the construction of each row is as the above-mentioned cement-soil mixing pile construction method.

(4)第一层锚杆4施工 (4) Construction of anchor rod 4 on the first layer

    ①下挖基坑13至第一层锚杆4设计标高以下1m处,清除干净围护桩身上的杂土; ①Dig the foundation pit 13 to the place 1m below the design elevation of the anchor rod 4 of the first layer, and remove the miscellaneous soil on the retaining pile;

    ②按照施工设计图采用全站仪进行测量放样确定锚杆设计孔位及锚孔方位角,并在围护桩1身上标记,所述方位角与筒桩预制钢筋笼上预留孔洞21角度一致; ②According to the construction design drawing, use a total station to measure and set out to determine the design hole position of the anchor rod and the azimuth angle of the anchor hole, and mark it on the enclosure pile 1. The azimuth angle is consistent with the angle of the hole 21 reserved on the prefabricated steel cage of the barrel pile ;

    ③钻机就位,在标记孔位进行钻孔,所述钻孔过程中保持特定的钻孔速度,防止对围护桩的薄壁造成过大破坏; ③ The drilling rig is in place, and the hole is drilled at the marked hole position. During the drilling process, a specific drilling speed is maintained to prevent excessive damage to the thin wall of the surrounding protection pile;

    ④锚杆安装前对钻孔重新进行检查,对塌孔、掉块进行清理; ④Re-inspect the drilled hole before installing the bolt, and clean up the collapsed hole and dropped blocks;

    ⑤将锚杆用力一致地推送进入孔道16,推送过程中不得转动杆体,并确保将锚杆体15推送至预定的深度; ⑤Consistently push the anchor rod into the hole 16, do not rotate the rod body during the pushing process, and ensure that the anchor rod body 15 is pushed to the predetermined depth;

    ⑥采用压力活塞式注浆泵对孔道进行灌浆,将水泥浆经注浆管19推入孔内,然后进行灌浆,所述灌浆过程为两次灌浆,第一次灌浆先灌注锚固段14,必须保持锚固段长度内灌满,在锚固段具备一定强度后对自由段15进行第二次灌浆,最后在孔端注入锚浆; ⑥ Use a pressure piston type grouting pump to grout the tunnel, push the grout into the hole through the grouting pipe 19, and then grout. The grouting process is two grouting. Keep the length of the anchoring section full, and after the anchoring section has a certain strength, perform the second grouting on the free section 15, and finally inject the anchoring grout at the end of the hole;

    ⑦在锚杆孔道口浇筑锚固托板17并安装紧固螺母18; ⑦Concrete the anchor supporting plate 17 at the opening of the anchor hole and install the fastening nut 18;

(5)第二层锚杆5施工 (5) Construction of the second layer anchor rod 5

    ①下挖基坑至第二层锚杆5设计标高以下1m处; ①Dig the foundation pit down to a place 1m below the design level of the anchor rod 5 on the second floor;

    ②按照施工设计图采用全站仪进行测量放样确定锚杆设计孔位及锚孔方位角,并在围护桩1身上标记,所述方位角与筒桩预制钢筋笼上预留孔洞21角度一致; ②According to the construction design drawing, use a total station to measure and set out to determine the design hole position of the anchor rod and the azimuth angle of the anchor hole, and mark it on the enclosure pile 1. The azimuth angle is consistent with the angle of the hole 21 reserved on the prefabricated steel cage of the barrel pile ;

    ③钻机就位,在标记孔位进行钻孔,所述钻孔过程中保持特定的钻孔速度,防止对围护桩的薄壁造成过大破坏; ③ The drilling rig is in place, and the hole is drilled at the marked hole position. During the drilling process, a specific drilling speed is maintained to prevent excessive damage to the thin wall of the surrounding protection pile;

    ④锚杆安装前对钻孔重新进行检查,对塌孔、掉块进行清理; ④Re-inspect the drilled hole before installing the bolt, and clean up the collapsed hole and dropped blocks;

    ⑤将锚杆用力一致地推送进入孔道16,推送过程中不得转动杆体,并确保将锚杆体推送至预定的深度,同时预留一定长度的第二层锚杆5的杆体钢筋22在孔道16外;; ⑤Push the anchor rod into the hole 16 consistently with force, do not rotate the rod body during the pushing process, and ensure that the anchor body is pushed to the predetermined depth, and reserve a certain length of the rod body steel bar 22 of the second layer of anchor rod 5 in the hole 16 outside;;

    ⑥采用压力活塞式注浆泵对孔道进行灌浆,将水泥浆经注浆管19推入孔内,然后进行灌浆,所述灌浆过程为两次灌浆,第一次灌浆先灌注锚固段14,必须保持锚固段14长度内灌满,在锚固段14具备一定强度后对锚杆的自由段15进行第二次灌浆,最后在孔端注入锚浆。 ⑥ Use a pressure piston type grouting pump to grout the tunnel, push the grout into the hole through the grouting pipe 19, and then grout. The grouting process is two grouting. Keep the length of the anchoring section 14 full, and after the anchoring section 14 has a certain strength, carry out the second grouting to the free section 15 of the anchor rod, and finally inject the anchor grout at the end of the hole.

(6)第一层围檩6施工 (6) Construction of purlin 6 on the first floor

    ①将第二层锚杆预留的孔道外的杆体钢筋22与第一层围檩钢筋23绑扎,所述的第二层预留杆体钢筋22设计为全部浇筑在第一层围檩6体内,锚杆与围檩钢筋间绑扎钢筋为高强钢丝24; ① Bind the rod body reinforcement 22 outside the tunnel reserved for the second layer of anchor rods with the first layer of purlin reinforcement 23, and the second layer of reserved rod body reinforcement 22 is designed to be completely poured in the first layer of purlin 6 body, The binding steel bar between the anchor rod and the purlin steel bar is high-strength steel wire 24;

    ②安装第一层围檩6的模板,并浇筑混凝土; ②Install the formwork of purlin 6 on the first layer and pour concrete;

通过以上施工,即成本发明的基坑围护结构。 Through the above construction, the foundation pit enclosure structure of the present invention is obtained.

参见图1~图7。本发明还可以有另外的实施例,即基坑围护结构有多层如三层锚杆5与两层围檩6,其施工方法具体如下: See Figure 1~Figure 7. The present invention can also have other embodiment, promptly foundation pit enclosing structure has multi-layer such as three-layer anchor rod 5 and two-layer enclosing purlin 6, and its construction method is specifically as follows:

(1)水泥搅拌桩止水帷幕26施工 (1) Construction of cement mixing pile water-stop curtain 26

(2)大直径薄壁筒桩1施工 (2) Construction of large-diameter thin-walled cylindrical pile 1

(3)被动区加固桩25施工 (3) Construction of reinforcement pile 25 in the passive area

(4)第一层锚杆4施工 (4) Construction of anchor rod 4 on the first layer

(5)第二层锚杆5施工 (5) Construction of the second layer anchor rod 5

(6)第一层围檩6施工 (6) Construction of purlin 6 on the first floor

[上述(1)~(6)施工步骤同上一个施工例] [The above (1)~(6) construction steps are the same as the previous construction example]

(7)第三层锚杆施工 (7) Construction of the third layer of anchor rods

    ①下挖基坑至第三层锚杆设计标高以下1m处; ①Dig the foundation pit to the point 1m below the design elevation of the anchor bolt on the third floor;

    ②重复上述(2)中②~⑥的施工过程(不需要浇筑托板和安装紧固螺母),预留一定长度的杆体钢筋在孔道外; ②Repeat the construction process of ②~⑥ in (2) above (no need to pour pallets and install fastening nuts), and reserve a certain length of rod body reinforcement outside the tunnel;

(8)第二层围檩施工 (8) Purlin construction on the second floor

    ①将第三层锚杆预留的孔道外的杆体钢筋与围檩钢筋绑扎,所述的第三层预留杆体钢筋设计为全部浇筑在第二层围檩体内,锚杆与围檩钢筋间绑扎钢筋为高强钢丝; ① Bind the rod body reinforcement outside the channel reserved for the third layer of anchor rods with the surrounding purlin reinforcement. The third layer of reserved rod body reinforcement is designed to be poured entirely in the second layer of surrounding purlin body. The gap between the anchor rod and the surrounding purlin reinforcement Binding steel bars are high-strength steel wires;

②安装第二层围檩的模板,并浇筑混凝土; ②Install formwork for the purlins on the second floor and pour concrete;

通过以上施工,即成本发明基坑围护结构的另一实施例。 Through the above construction, another embodiment of the foundation pit enclosure structure of the present invention is obtained.

Claims (4)

1. a large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure, it is characterized in that: comprise cement mixing pile water stopping curtain, the stake of large diameter thin wall cylinder, first floor anchor pole and second layer anchor pole, capping beam, enclose purlin and passive area reinforcing pile, the periphery of described water-stop curtain in foundation pit enclosure structure, and formed by the multiple single cement mixing pile around distributing along foundation ditch, the stake of described large diameter thin wall cylinder is Cast-in-situs type thin-walled cylinder pile, and in water-stop curtain inner side, the stake of large diameter thin wall cylinder comprises thin-walled pile body and pile crown, pile crown is with pile crown through hole, the capping beam that strengthens each fender post resistance to overturning is built in described stake top casting, on described thin-walled pile body, offer successively the first duct and the second duct along depth direction, described the first duct and the second duct include pile body hole in pile body and the soil body hole in the soil body, described first floor anchor pole inserts the first duct and arrives in soil body hole, between the first duct and first floor anchor pole, be perfused with cement paste, the first opening of the channel that described first floor anchor pole inserts is built anchoring supporting plate, clamp nut is connected with the threaded one end of first floor anchor pole and supporting plate is pressed on thin-walled pile body, described second layer anchor pole inserts the second duct and arrives in soil body hole, between the second duct and second layer anchor pole, be perfused with cement paste, the body of rod reinforcing bar of the reserved certain length of described second layer anchor pole is outside the second duct, enclose the inner reinforcing bar of purlin and body of rod reinforcing bar binding, enclosing purlin is made up of concrete, described passive area reinforcing pile is in large diameter thin wall cylinder stake inner side, and is made up of the cement mixing pile being piled in the soil body.
2. large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure, is characterized in that: the diameter that forms the cement mixing pile of described water-stop curtain is that 500mm, pile spacing are that 350mm, projected depth are 8m; The cylinder pile lining of described large diameter thin wall cylinder stake 1 thick for 200mm, a cylinder stake external diameter be that 1000mm, pile spacing are that 1000mm, projected depth are 10m; Described passive area as a reinforcing joint, arranges Reinforcement with Cement-mixed Piles every 3m, and reinforcing pile 25 arranges three rows, every row's 5 piles, and the diameter of stake is 500mm, and pile spacing is 350mm, and row's spacing is 500mm, and projected depth is 10m; The body of rod of described first floor anchor pole and second layer anchor pole is fining twisted steel, and the degree of depth in described the first duct and the second duct is 5m, aperture 80mm.
3. a construction method for large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure, is characterized in that: comprise following construction sequence:
(1) water-stop curtain construction
The periphery of water-stop curtain in foundation pit enclosure structure, adopts a fairly large number of single cement mixing pile distributing along foundation ditch to surround around and forms;
(2) large diameter thin wall cylinder pile driving construction
1. the prefabricated pile crown of large diameter thin wall cylinder stake is embedded between interior steel cylinder template and outer steel cylinder template;
2. at the just tube template top mounting clamp device that shakes, be used for fixing dither, dither adjust in place after, interior steel cylinder template and outer steel cylinder template and prefabricated pile crown are pressed in soil to prefabricated pile crown and reach projected depth;
3. the folder that the unclamps template top device that shakes, puts into annular template chamber by prefabricated reinforcing cage, by the concrete pouring gate fluid concrete in outer steel cylinder template, and hoisting steel tube template simultaneously;
4. repeat above-mentioned steps, the next large diameter thin wall cylinder stake of constructing is until required all the going along with sb. to guard him of foundation ditch uses large diameter thin wall cylinder pile driving construction complete;
5. reach after design strength until fender post concrete, remove the assorted soil at bracing of foundation pit stake top, build the capping beam that strengthens each fender post resistance to overturning;
(3) passive area reinforcing pile construction
Passive area reinforcing pile is in large diameter thin wall cylinder stake inner side, and is made up of the cement mixing pile being piled in the soil body;
(4) first floor anchor bolt construction
1. dig down foundation ditch to the following 1m of first floor Soil Anchor Design absolute altitude place;
2. adopt total powerstation to measure setting-out and determine position, Soil Anchor Design hole and anchor hole azimuth according to design drawing, and with it fender post mark;
3. rig is in place, holes in index aperture position;
4. anchor pole is firmly as one man pushed and enters duct, in propelling movement process, must not rotate the body of rod; Adopt pressure piston formula grouting pump to be in the milk to duct, cement paste, in Grouting Pipe pushes hole, is then in the milk, and builds anchoring supporting plate at bolthole road junction and clamp nut is installed;
(5) second layer anchor bolt construction
1. dig down foundation ditch to the following 1m of second layer Soil Anchor Design absolute altitude place;
2. adopt total powerstation to measure setting-out and determine position, Soil Anchor Design hole and anchor hole azimuth according to design drawing, and with it fender post mark;
3. rig is in place, holes in index aperture position;
4. anchor pole is firmly as one man pushed and enters duct, in propelling movement process, must not rotate the body of rod; Adopt pressure piston formula grouting pump to be in the milk to duct, cement paste, in Grouting Pipe pushes hole, is then in the milk; The body of rod reinforcing bar of the anchor pole of reserved certain length is outside duct;
(6) first floor encloses purlin construction
1. body of rod reinforcing bar and first floor outside the second reserved duct of second layer anchor pole are enclosed to purlin reinforcing bar binding;
2. the template that first floor encloses purlin is installed, and concreting.
4. according to the construction method of the large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure described in claims 1, it is characterized in that: the precast reinforced cage in 3. step by step of construction sequence (2) has been reserved the required hole in anchor pole duct, for anchor pole can be to cylinder, stake destroys minimum in the situation that compound with it through cylinder stake; Pouring concrete in construction sequence (2)-is 3. step pouring segmentation jolt ramming, steel form segmentation lifting.
CN201410102546.8A 2014-03-20 2014-03-20 The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure Active CN104074197B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410102546.8A CN104074197B (en) 2014-03-20 2014-03-20 The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410102546.8A CN104074197B (en) 2014-03-20 2014-03-20 The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure

Publications (2)

Publication Number Publication Date
CN104074197A true CN104074197A (en) 2014-10-01
CN104074197B CN104074197B (en) 2016-05-04

Family

ID=51595773

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410102546.8A Active CN104074197B (en) 2014-03-20 2014-03-20 The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure

Country Status (1)

Country Link
CN (1) CN104074197B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638619A (en) * 2016-12-20 2017-05-10 王志华 Foundation-pit support building structure
CN107700527A (en) * 2017-11-07 2018-02-16 兰州理工大学 Add the cantilever retaining wall and construction method of pilaster and anchor pole
CN112942446A (en) * 2021-02-04 2021-06-11 浙江吉祥建设集团有限公司 Sheet pile foundation waterproof structure
CN112982468A (en) * 2019-12-18 2021-06-18 烟台三维岩土工程技术有限公司 Anchoring technology and construction method for marine large-diameter tubular pile foundation
CN113789802A (en) * 2021-08-10 2021-12-14 罗荣 Clay waterproof curtain wall
CN114541440A (en) * 2022-03-22 2022-05-27 中铁大桥局第九工程有限公司 Cofferdam structure located on bias water-approaching slope and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126241A (en) * 2006-08-15 2008-02-20 吴忠诚 Scattered row piles-brad wall combination supporting method
CN101503878A (en) * 2009-03-02 2009-08-12 杭州萧宏建设集团有限公司 Construction method for building foundation pit enclosure structure with thin-walled cylinder pile as fender post
CN201873997U (en) * 2010-11-24 2011-06-22 温州中城建设集团有限公司 Support structure of foundation pit
CN102425174A (en) * 2011-12-10 2012-04-25 中国建筑西南勘察设计研究院有限公司 Composite supporting structure of drainage pipe pile and soil nailing wall

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1565963A1 (en) * 1987-10-13 1990-05-23 Московский Государственный Трест "Мосоргинжстрой" Главмосинжстроя При Мосгорисполкоме Lining for sinking vertical working

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126241A (en) * 2006-08-15 2008-02-20 吴忠诚 Scattered row piles-brad wall combination supporting method
CN101503878A (en) * 2009-03-02 2009-08-12 杭州萧宏建设集团有限公司 Construction method for building foundation pit enclosure structure with thin-walled cylinder pile as fender post
CN201873997U (en) * 2010-11-24 2011-06-22 温州中城建设集团有限公司 Support structure of foundation pit
CN102425174A (en) * 2011-12-10 2012-04-25 中国建筑西南勘察设计研究院有限公司 Composite supporting structure of drainage pipe pile and soil nailing wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈晨等: "现浇薄壁混凝土筒桩在温州某基坑工程中的应用", 《岩土工程学报》, vol. 32, 31 July 2010 (2010-07-31) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638619A (en) * 2016-12-20 2017-05-10 王志华 Foundation-pit support building structure
CN106638619B (en) * 2016-12-20 2018-12-14 王志华 A kind of pattern foundation pit supporting structure building structure
CN107700527A (en) * 2017-11-07 2018-02-16 兰州理工大学 Add the cantilever retaining wall and construction method of pilaster and anchor pole
CN112982468A (en) * 2019-12-18 2021-06-18 烟台三维岩土工程技术有限公司 Anchoring technology and construction method for marine large-diameter tubular pile foundation
CN112942446A (en) * 2021-02-04 2021-06-11 浙江吉祥建设集团有限公司 Sheet pile foundation waterproof structure
CN112942446B (en) * 2021-02-04 2022-04-19 浙江吉祥建设集团有限公司 Sheet pile foundation waterproof structure
CN113789802A (en) * 2021-08-10 2021-12-14 罗荣 Clay waterproof curtain wall
CN114541440A (en) * 2022-03-22 2022-05-27 中铁大桥局第九工程有限公司 Cofferdam structure located on bias water-approaching slope and construction method

Also Published As

Publication number Publication date
CN104074197B (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN108868778B (en) Non-excavation construction method for large underground structure
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN104074197B (en) The construction method of large diameter thin wall cylinder stake compound anchor rod-type foundation pit enclosure structure
CN205742213U (en) Foundation pit supporting construction
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN108842791A (en) A kind of relief piled anchor multistage support structure and construction method
CN103510510A (en) Reinforced long spiral drilling concrete grouting pile and construction method thereof
CN110847207A (en) Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN104631440A (en) Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN105464128B (en) Prestress anchorage cable assembled pile plate wall protection construction method
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN108118689B (en) Partially recyclable prefabricated underground diaphragm wall, spreader and construction method
CN103790148A (en) Combined treatment construction method for collapsible loess foundation
CN203594023U (en) Enhanced type long auger drilling pressure-grouting concrete pile
CN211547686U (en) Prestressed concrete-filled steel tube pipe curtain structure based on prefabricated concrete-filled steel tube connection
CN210263075U (en) A rear grouting inner anchor and outer water stop support system for grid-type pipe piles
CN108571010B (en) Method for integrating open cut method engineering prefabricated main structure and supporting structure
CN102330430A (en) Construction method for prefabricated building enclosure of deep foundation pit in low-temperature environment construction
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN106337421B (en) A kind of lattice concrete is compound to go along with sb. to guard him piling wall and the construction method based on BIM

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181121

Address after: 518055 No. 2001, Vanke Yunchuang 20 Floor, Block B, Bottom Science Park, Chaguang Road and Chuangke Road, Xili Street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: Wei Zheng Intellectual Property Service Co., Ltd.

Address before: 325000 Dongfang Road 38, Ouhai Economic Development Zone, Wenzhou, Zhejiang (Wenzhou University Science Park)

Patentee before: Wenzhou University

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181127

Address after: 710061 491 Changan South Road, Yanta District, Xi'an, Shaanxi

Patentee after: China Metallurgical Group northwest Geotechnical Engineering Co., Ltd.

Address before: 518055 No. 2001, Vanke Yunchuang 20 Floor, Block B, Bottom Science Park, Chaguang Road and Chuangke Road, Xili Street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: Wei Zheng Intellectual Property Service Co., Ltd.

TR01 Transfer of patent right