CN105937244A - Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof - Google Patents
Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof Download PDFInfo
- Publication number
- CN105937244A CN105937244A CN201610344037.5A CN201610344037A CN105937244A CN 105937244 A CN105937244 A CN 105937244A CN 201610344037 A CN201610344037 A CN 201610344037A CN 105937244 A CN105937244 A CN 105937244A
- Authority
- CN
- China
- Prior art keywords
- column
- wall
- retaining wall
- steep slope
- toe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 14
- 238000009412 basement excavation Methods 0.000 claims abstract description 13
- 210000000481 breast Anatomy 0.000 claims 3
- 238000005266 casting Methods 0.000 claims 2
- 230000002787 reinforcement Effects 0.000 claims 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 abstract description 6
- 238000009415 formwork Methods 0.000 abstract description 6
- 239000010959 steel Substances 0.000 abstract description 6
- 230000000694 effects Effects 0.000 abstract description 3
- 239000002689 soil Substances 0.000 description 22
- 230000005484 gravity Effects 0.000 description 8
- 238000000034 method Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0266—Retaining or protecting walls characterised by constructional features made up of preformed elements
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
Abstract
一种陡坡地基上的梁柱板式路堤挡土墙及其构筑方法。挡土墙的结构特点是:立柱的下端与横向的地梁在墙趾处连接,地梁之间通过墙趾处的纵向的连接梁相互连接,连接梁与立柱所包围的空间内安装有挡土板。其构筑方法为:A、在挡墙墙趾位置纵向开挖连接梁槽;并在接梁槽内向陡坡内侧开挖横向的地梁槽;B、在连接梁槽和地梁槽中同时搭建模板,绑扎钢筋,浇筑混凝土,构筑形成固定连接的地梁和连接梁;C、在地梁的墙趾位置搭建立柱模板,绑扎钢筋,浇筑混凝土,构筑形成与地梁固定连接的立柱;D、将预制的挡土板安装在连接梁与立柱所包围的空间内。该挡墙抗倾覆力矩大,支挡效果好、适合陡坡地基的路堤支挡;且其开挖方便、开挖量小,工程造价低。
A beam-column-slab type embankment retaining wall on a steep slope foundation and a construction method thereof. The structural characteristics of the retaining wall are: the lower end of the column is connected to the horizontal ground beam at the toe of the wall, the ground beams are connected to each other through the longitudinal connecting beam at the toe of the wall, and a retaining wall is installed in the space surrounded by the connecting beam and the column. Dirt board. The construction method is as follows: A. Longitudinal excavation of the connecting beam groove at the toe position of the retaining wall; excavation of the horizontal ground beam groove to the inner side of the steep slope in the connecting beam groove; B. Simultaneous construction of the connecting beam groove and the ground beam groove Formwork, binding steel bars, pouring concrete, and constructing ground beams and connecting beams that are fixedly connected; C, erecting column formwork at the wall toe of the ground beams, binding steel bars, pouring concrete, and constructing columns that are fixedly connected to the ground beams; D, Install prefabricated retaining panels in the space enclosed by connecting beams and columns. The retaining wall has a large anti-overturning moment, good retaining effect, and is suitable for embankment retaining on steep slope foundations; it is convenient to excavate, has a small excavation volume, and has low engineering cost.
Description
技术领域technical field
本发明涉及一种陡坡地基上的梁柱板式路堤挡土墙及其构筑方法。The invention relates to a beam-column slab embankment retaining wall on a steep slope foundation and a construction method thereof.
背景技术Background technique
在工程建设中,地面横坡大于1:2.5地段的边坡称为陡坡。在陡坡地基下,由于地面横坡较陡、基底地质地形条件变化不均,在荷载、水等作用下,陡坡路堤极易产生下滑等破坏。为防止边坡的坍滑以保持其稳定,需要在陡坡外侧构筑边坡的支挡结构。挡土墙是工程建设中最常用的一类边坡支挡结构,主要用于支承路堤填土或自然边坡土体,防止填土或土体变形失稳,承受土体侧向土压力。In engineering construction, the slope with a ground cross slope greater than 1:2.5 is called a steep slope. Under the steep slope foundation, due to the steep cross slope of the ground and the uneven variation of the base geological and topographical conditions, under the action of load and water, the steep slope embankment is very prone to slide and other damages. In order to prevent the slope from collapsing and keep it stable, it is necessary to build a retaining structure for the slope on the outside of the steep slope. Retaining wall is the most commonly used slope retaining structure in engineering construction. It is mainly used to support embankment filling or natural slope soil, prevent filling or soil deformation and instability, and bear the lateral soil pressure of soil.
常用于陡坡地基路堤的挡土墙主要有重力式挡土墙和桩板式挡土墙。重力式挡土墙是以挡土墙自身重力来维持挡土墙在土压力作用下的稳定,需要承载力高的基础进行支承,因此需要大面积连续开挖宽深基坑,圬工量大,工程的经济性差。桩板式挡土墙是由竖向植入地基桩孔的锚固桩与桩间挡土板组成,桩露出地表部分称为悬臂段,植入地基内部分称为锚固段。利用桩锚固段与地基土的抗力来抵抗土的侧向压力从而保证墙内侧土体稳定。对陡坡地基路堤的支挡,桩锚固段一般需要达到悬臂段的两倍,挖孔深度大对陡坡地基土体扰动大,桩孔的挖孔施工难度大,安全隐患高,工程的造价也大幅增加。The retaining walls commonly used in steep slope foundation embankments mainly include gravity retaining walls and pile-slab retaining walls. The gravity retaining wall maintains the stability of the retaining wall under the action of earth pressure by the gravity of the retaining wall itself, and requires a foundation with high bearing capacity for support. Therefore, a large area of continuous excavation of wide and deep foundation pits is required, and the amount of masonry is large. , The economy of the project is poor. The pile-slab retaining wall is composed of anchor piles vertically implanted into the pile holes of the foundation and a retaining plate between the piles. The part of the pile exposed to the surface is called the cantilever section, and the part embedded in the foundation is called the anchor section. Use the resistance of the pile anchorage section and the foundation soil to resist the lateral pressure of the soil to ensure the stability of the soil inside the wall. For the support and retaining of embankment on steep slope foundation, the pile anchorage section generally needs to be twice as long as the cantilever section. The large excavation depth will cause great disturbance to the steep slope foundation soil, the excavation construction of pile holes is difficult, the safety hazard is high, and the cost of the project is also greatly increased. Increase.
发明内容Contents of the invention
本发明的第一目的是提供一种陡坡地基上的梁柱板式路堤挡土墙,该种挡墙的抗倾覆力矩大,支挡效果好、适合陡坡地基的路堤支挡;且其开挖方便、开挖量小,工程造价低。The first object of the present invention is to provide a beam-column slab type embankment retaining wall on a steep slope foundation. This kind of retaining wall has a large anti-overturning moment, good support effect, and is suitable for embankment support on steep slope foundations; and its excavation is convenient. , The excavation volume is small, and the project cost is low.
本发明为实现其第一目的采用的技术方案是:一种陡坡地基上的梁柱板式路堤挡土墙,包括立柱、挡土板,其特征在于:所述的立柱的下端与横向的地梁在墙趾处固定连接,地梁之间通过墙趾处的纵向的连接梁相互固定连接,连接梁与立柱所包围的空间内安装有挡土板。The technical solution adopted by the present invention to achieve its first purpose is: a beam-column slab type embankment retaining wall on a steep slope foundation, including a column and a soil retaining plate, characterized in that: the lower end of the column and the horizontal ground beam Fixedly connected at the toe of the wall, the ground beams are fixedly connected to each other through the longitudinal connecting beam at the toe of the wall, and a soil retaining board is installed in the space surrounded by the connecting beam and the column.
本发明的第二目的是提供一种上述的陡坡地基上的梁柱板式路堤挡土墙的构筑方法,该种方法能快速、方便的构筑出上述的梁柱板式挡土墙,且构筑施工时对开挖量小,对土体扰动少,支挡效果好。The second object of the present invention is to provide a method for constructing the above-mentioned beam-column-slab type embankment retaining wall on the steep slope foundation. This method can quickly and conveniently build the above-mentioned beam-column-slab type retaining wall. The excavation volume is small, the soil disturbance is small, and the supporting and retaining effect is good.
本发明实现其第二目的所采用的技术方案是,一种上述的陡坡地基上的梁柱板式路堤挡土墙的构筑方法,其步骤为:The technical solution adopted by the present invention to realize its second purpose is, a kind of construction method of the beam-column slab type embankment retaining wall on the above-mentioned steep slope foundation, its steps are:
A、在挡墙墙趾位置纵向开挖连接梁槽;并在接梁槽内向陡坡内侧开挖横向的地梁槽;A. Excavate the connecting beam groove longitudinally at the toe of the retaining wall; and excavate the horizontal ground beam groove to the inner side of the steep slope in the connecting beam groove;
B、在连接梁槽和地梁槽中同时搭建模板,绑扎钢筋,浇筑混凝土,构筑形成固定连接的地梁和连接梁;B. Simultaneously build the formwork in the connecting beam groove and the ground beam groove, bind the steel bars, pour concrete, and construct the ground beam and the connecting beam to form a fixed connection;
C、在地梁的墙趾位置搭建立柱模板,绑扎钢筋,浇筑混凝土,构筑形成与地梁固定连接的立柱;C. Set up a column formwork at the wall toe of the ground beam, bind steel bars, pour concrete, and form a column fixedly connected to the ground beam;
D、将预制的挡土板安装在连接梁与立柱所包围的空间内。D. Install the prefabricated retaining board in the space surrounded by the connecting beam and the column.
与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:
一、使用时将挡土板4背面(面向陡坡内侧一面)分层填筑土体并设置反滤层即可。陡坡土体作用在挡土板上会产生倾覆力矩;而横向深入至陡坡内侧稳定土体的地梁,与内侧稳定土体相互作用则会产生的强大的抗倾覆力,该抗倾覆力通过地梁、连接梁与立柱的整体L型结构能形成强大的弯矩即抗倾覆力矩,有效阻止土体的倾覆,维持挡墙与墙后土体的稳定。总之本发明的抗倾覆力矩强,适合陡坡地基的路堤支挡。1. When in use, fill the soil body layer by layer on the back side of the retaining board 4 (facing the inner side of the steep slope) and set the anti-filter layer. The action of the steep slope soil on the retaining plate will generate an overturning moment; while the ground beam that penetrates horizontally into the stable soil inside the steep slope and interacts with the stable soil inside will generate a strong anti-overturning force. The overall L-shaped structure of beams, connecting beams and columns can form a strong bending moment, that is, an anti-overturning moment, which can effectively prevent the overturning of the soil and maintain the stability of the retaining wall and the soil behind the wall. In a word, the anti-overturning moment of the present invention is strong, and is suitable for embankment support on steep slope foundations.
二、现有的重力式挡土墙仅以挡土墙自身重力产生抗倾覆力,挡土墙的自身重力大,对地基基础的承载力要求高。本发明由横向深入的地梁,与内侧稳定土体相互作用产生抗倾覆力,挡墙本身的重力小,降低了对地基基础的承载力要求。2. The existing gravity retaining wall only generates anti-overturning force by the gravity of the retaining wall itself. The gravity of the retaining wall is large, and the bearing capacity of the foundation is required to be high. In the present invention, the horizontally deep ground beam interacts with the inner stable soil body to generate anti-overturning force, and the gravity of the retaining wall itself is small, which reduces the requirement on the bearing capacity of the foundation.
三、重力式挡墙基础需纵向沿坡面连续开挖深、宽基坑,以构筑大体积、大重量的挡墙。本发明只需要沿坡面纵向开挖连接梁槽、间隔横向开挖地梁槽,其开挖量大大减少,既减少了对土体的扰动,也降低了施工量。同时,纵向、横向挖槽较之桩板墙锚固桩的竖向深孔开挖,明显降低了施工难度和安全隐患,也降低了工程造价低。3. The foundation of the gravity retaining wall needs to excavate deep and wide foundation pits longitudinally along the slope to build a large-volume and heavy-weight retaining wall. The invention only needs to excavate the connecting beam grooves longitudinally along the slope surface and excavate the ground beam grooves horizontally at intervals, the excavation amount is greatly reduced, the disturbance to the soil body is reduced, and the construction amount is also reduced. At the same time, compared with the vertical deep hole excavation of the pile plate wall anchor pile, the vertical and horizontal grooves obviously reduce the construction difficulty and safety hazards, and also reduce the construction cost.
下面结合附图和具体实施方式对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
附图说明:Description of drawings:
图1是本发明的梁柱板式挡土墙的三维结构示意图。Fig. 1 is a three-dimensional structural schematic diagram of a beam-column slab retaining wall of the present invention.
图2是图1的俯视图。FIG. 2 is a top view of FIG. 1 .
图3是本发明使用于陡坡地基上的使用状态侧视(剖视)示意图。Fig. 3 is a schematic side view (sectional view) of the present invention used on a steep slope foundation.
图3中,5是陡坡土体,6是填筑土体。In Fig. 3, 5 is a steep slope soil body, and 6 is a filling soil body.
具体实施方式:detailed description:
实施例Example
图1、图2、图3示出,本发明的一种具体实施方式是,一种陡坡地基上的梁柱板式路堤挡土墙,包括立柱3、挡土板4,其特征在于:所述的立柱3的下端与横向的地梁1在墙趾处固定连接,地梁1之间通过墙趾处的纵向的连接梁2相互固定连接,连接梁2与立柱3所包围的空间内安装有挡土板4。Fig. 1, Fig. 2, Fig. 3 show, a kind of embodiment of the present invention is, a kind of beam-column slab type embankment retaining wall on steep slope foundation, comprises column 3, retaining plate 4, is characterized in that: The lower end of the column 3 is fixedly connected to the horizontal ground beam 1 at the toe of the wall, and the ground beams 1 are fixedly connected to each other through the longitudinal connecting beam 2 at the toe of the wall, and the space surrounded by the connecting beam 2 and the column 3 is installed with Soil retaining board4.
本例的陡坡地基上的梁柱板式路堤挡土墙的构筑方法,其步骤为:The construction method of the beam-column slab type embankment retaining wall on the steep slope foundation of this example, its steps are:
A、在挡墙墙趾位置纵向开挖连接梁槽;并在接梁槽内向陡坡内侧开挖横向的地梁槽;A. Excavate the connecting beam groove longitudinally at the toe of the retaining wall; and excavate the horizontal ground beam groove to the inner side of the steep slope in the connecting beam groove;
B、在连接梁槽和地梁槽中同时搭建模板,绑扎钢筋,浇筑混凝土,构筑形成固定连接的地梁1和连接梁2;B. Build formwork in the connecting beam groove and the ground beam groove at the same time, bind the steel bars, pour concrete, and construct the ground beam 1 and the connecting beam 2 that form a fixed connection;
C、在地梁1的墙趾位置搭建立柱模板,绑扎钢筋,浇筑混凝土,构筑形成与地梁1固定连接的立柱3;C. Set up the column formwork at the wall toe position of the ground beam 1, bind the steel bars, pour concrete, and form the column 3 fixedly connected with the ground beam 1;
D、将预制的挡土板4安装在连接梁2与立柱3所包围的空间内。D. Install the prefabricated retaining board 4 in the space surrounded by the connecting beam 2 and the column 3 .
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610344037.5A CN105937244A (en) | 2016-05-20 | 2016-05-20 | Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610344037.5A CN105937244A (en) | 2016-05-20 | 2016-05-20 | Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105937244A true CN105937244A (en) | 2016-09-14 |
Family
ID=57152078
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610344037.5A Pending CN105937244A (en) | 2016-05-20 | 2016-05-20 | Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105937244A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638673A (en) * | 2016-09-22 | 2017-05-10 | 石家庄铁道大学 | Construction method of combined supporting and retaining structure |
CN106759469A (en) * | 2017-01-12 | 2017-05-31 | 兰州理工大学 | Detachable cantilever retaining wall and construction and recovery method |
CN106759402A (en) * | 2017-02-10 | 2017-05-31 | 陈启品 | A kind of prefabricated section of multidimensional Ecological Retaining Wall system and making wall system |
CN107700424A (en) * | 2017-11-15 | 2018-02-16 | 中船第九设计研究院工程有限公司 | A kind of yacht wharf pontoon bridge pile holding structure |
CN108049421A (en) * | 2017-09-29 | 2018-05-18 | 山西省交通科学研究院 | A kind of H type pile plate wall for reinforcing unstable slope |
CN108343084A (en) * | 2018-04-04 | 2018-07-31 | 广东盖特奇新材料科技有限公司 | A kind of preparation method of assembled ecological permeable concrete retaining wall and its wall |
CN109440561A (en) * | 2018-11-09 | 2019-03-08 | 中铁二院工程集团有限责任公司 | A kind of the light shock-proof road structure and its construction method of rapid construction |
CN109778903A (en) * | 2019-01-25 | 2019-05-21 | 中国一冶集团有限公司 | A kind of detachable assembling type reinforced concrete retaining wall structure and construction method |
CN110117965A (en) * | 2018-02-07 | 2019-08-13 | 山东大学 | A kind of pin-connected panel anchor draws retaining wall and method |
CN110258623A (en) * | 2019-05-29 | 2019-09-20 | 中铁第四勘察设计院集团有限公司 | Retaining structure |
CN110644509A (en) * | 2019-11-01 | 2020-01-03 | 四川省交通勘察设计研究院有限公司 | A kind of vertical anchor and balance weight type pile-slab wall and its construction method |
CN111576455A (en) * | 2020-06-23 | 2020-08-25 | 中煤科工重庆设计研究院(集团)有限公司 | Umbrella-shaped supporting structure for slope prevention and control and construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011231466A (en) * | 2010-04-23 | 2011-11-17 | Hirose & Co Ltd | Retaining wall earth-retaining structure and method of installing the same |
GB2458270B (en) * | 2008-03-10 | 2012-08-01 | Francis & Lewis Internat Ltd | Retaining wall system and support |
CN103334450A (en) * | 2013-07-03 | 2013-10-02 | 中国科学院亚热带农业生态研究所 | Construction method of pile precast slab retaining wall with drainage ditch |
CN103572775A (en) * | 2012-07-30 | 2014-02-12 | 深圳市工勘岩土工程有限公司 | Semi-assembly type retaining wall of soil filling slope and construction method for semi-assembly type retaining wall |
-
2016
- 2016-05-20 CN CN201610344037.5A patent/CN105937244A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2458270B (en) * | 2008-03-10 | 2012-08-01 | Francis & Lewis Internat Ltd | Retaining wall system and support |
JP2011231466A (en) * | 2010-04-23 | 2011-11-17 | Hirose & Co Ltd | Retaining wall earth-retaining structure and method of installing the same |
CN103572775A (en) * | 2012-07-30 | 2014-02-12 | 深圳市工勘岩土工程有限公司 | Semi-assembly type retaining wall of soil filling slope and construction method for semi-assembly type retaining wall |
CN103334450A (en) * | 2013-07-03 | 2013-10-02 | 中国科学院亚热带农业生态研究所 | Construction method of pile precast slab retaining wall with drainage ditch |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638673A (en) * | 2016-09-22 | 2017-05-10 | 石家庄铁道大学 | Construction method of combined supporting and retaining structure |
CN106638673B (en) * | 2016-09-22 | 2017-10-31 | 西南交通大学 | A kind of construction method of compound retaining structure |
CN106759469A (en) * | 2017-01-12 | 2017-05-31 | 兰州理工大学 | Detachable cantilever retaining wall and construction and recovery method |
CN106759402A (en) * | 2017-02-10 | 2017-05-31 | 陈启品 | A kind of prefabricated section of multidimensional Ecological Retaining Wall system and making wall system |
CN108049421A (en) * | 2017-09-29 | 2018-05-18 | 山西省交通科学研究院 | A kind of H type pile plate wall for reinforcing unstable slope |
CN107700424A (en) * | 2017-11-15 | 2018-02-16 | 中船第九设计研究院工程有限公司 | A kind of yacht wharf pontoon bridge pile holding structure |
CN110117965A (en) * | 2018-02-07 | 2019-08-13 | 山东大学 | A kind of pin-connected panel anchor draws retaining wall and method |
CN108343084A (en) * | 2018-04-04 | 2018-07-31 | 广东盖特奇新材料科技有限公司 | A kind of preparation method of assembled ecological permeable concrete retaining wall and its wall |
CN109440561A (en) * | 2018-11-09 | 2019-03-08 | 中铁二院工程集团有限责任公司 | A kind of the light shock-proof road structure and its construction method of rapid construction |
CN109778903A (en) * | 2019-01-25 | 2019-05-21 | 中国一冶集团有限公司 | A kind of detachable assembling type reinforced concrete retaining wall structure and construction method |
CN110258623A (en) * | 2019-05-29 | 2019-09-20 | 中铁第四勘察设计院集团有限公司 | Retaining structure |
CN110644509A (en) * | 2019-11-01 | 2020-01-03 | 四川省交通勘察设计研究院有限公司 | A kind of vertical anchor and balance weight type pile-slab wall and its construction method |
CN111576455A (en) * | 2020-06-23 | 2020-08-25 | 中煤科工重庆设计研究院(集团)有限公司 | Umbrella-shaped supporting structure for slope prevention and control and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105937244A (en) | Beam column plate type embankment earth-retaining wall on steep slope foundation and construction method thereof | |
CN103485363B (en) | Three-dimensional continuous frame formula reinforced concrete structure retaining wall | |
CN104453274B (en) | Method for supporting existing building underground with support structure and underpinning structure | |
CN104988948B (en) | A kind of construction method of fin-plate type retaining wall | |
CN106522270A (en) | Pile foundation and retaining wall anti-earthquake retaining structure comprising EPS buffer layers and construction method | |
CN202280075U (en) | Combined type retaining wall of prefabricated part | |
JP2011236571A (en) | Retaining wall and construction method of the same | |
CN104389315B (en) | Consolidation grouting drilled pile wall and construction method thereof | |
CN111749288B (en) | Load-reducing heightening structure of existing retaining wall and construction method thereof | |
JP5259510B2 (en) | Retaining wall and its construction method | |
CN206752667U (en) | A kind of basement barrier wall structure | |
CN114319435B (en) | Underground passage supporting structure with large-section shallow buried pipe gallery in underpass and construction method | |
CN204780991U (en) | Floor formula retaining wall | |
CN203741848U (en) | Steel tube plate type retaining structure | |
CN203498863U (en) | Three-dimensional continuous-frame-type reinforced concrete structural retaining wall | |
CN206625243U (en) | Rectangular deep foundation pit large-span steel-reinforced concrete inner supporting structure | |
CN218346137U (en) | Foundation with strong bearing capacity | |
KR101262631B1 (en) | Prefab type land-side protection wall device | |
CN206337566U (en) | Foundation ditch vertical prestressing anchor pole supporting construction | |
CN210946864U (en) | Landscape structure foundation for soft stratum | |
CN204401556U (en) | A kind of high-piled slab & girder wharf rear connects the soil-baffling structure of bank | |
CN212223781U (en) | A frame type retaining wall structure that can also be used as the foundation of buildings along the river | |
CN210507517U (en) | Combined member suitable for retaining wall heightening | |
CN114991809A (en) | Mountain-climbing bias tunnel back-pressure supporting structure and construction method thereof | |
CN210117724U (en) | Garage foundation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160914 |