CN107451357A - A kind of balcony construction method of ground based on BIM - Google Patents
A kind of balcony construction method of ground based on BIM Download PDFInfo
- Publication number
- CN107451357A CN107451357A CN201710630543.5A CN201710630543A CN107451357A CN 107451357 A CN107451357 A CN 107451357A CN 201710630543 A CN201710630543 A CN 201710630543A CN 107451357 A CN107451357 A CN 107451357A
- Authority
- CN
- China
- Prior art keywords
- construction
- bim
- ground
- gradient
- waterproof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
- E04F15/182—Underlayers coated with adhesive or mortar to receive the flooring
- E04F15/183—Underlayers coated with adhesive or mortar to receive the flooring for areas prone to frost damage, e.g. for balconies or terraces
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F2290/00—Specially adapted covering, lining or flooring elements not otherwise provided for
- E04F2290/04—Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computer Hardware Design (AREA)
- General Engineering & Computer Science (AREA)
- Evolutionary Computation (AREA)
- Water Supply & Treatment (AREA)
- Computational Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Public Health (AREA)
- Hydrology & Water Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Floor Finish (AREA)
Abstract
The invention discloses a kind of balcony construction method of ground based on BIM, including following steps:(1), based on construction drawing, threedimensional model is established;(2), the dynamic analog based on BIM, the dynamic analog of waterproof construction and the dynamic analog of tile work construction are carried out;(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain the gradient difference data between lastrow floor tile and next line floor tile;(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.The related data that the present invention is obtained by BIM, has positive booster action for site operation, the preferred plan of draining has just been obtained before construction, avoids the deviation for the influence draining parameter being likely to occur in construction.
Description
Technical field
The present invention relates to building field, and in particular to a kind of balcony construction method of ground based on BIM.
Background technology
BIM is the new tool of architecture, engineering science and civil engineering.BIM (Building
Information Modeling, abbreviation BIM), it is defined as by being formed completely with insufficient information to support life cycle management,
And can be by building or architectural engineering information model that computer applied algorithm is directly explained.In short, i.e. digital technology support
Life cycle management to architectural environment.Existing building construction is aided in using BIM technology, is that the one of construction becomes greatly
Gesture.
The meeting that existing balcony ground construction has just has CAD two dimension drawings to be constructed, but more be then according to skill
The experience of art work is constructed, and these modes can only all pinpoint the problems when side is constructed and solve the problems, such as, it is impossible to improves construction
Efficiency.
The content of the invention
It is an object of the invention to provide a kind of balcony construction method of ground based on BIM, present invention BIM technology is to applying
Associated components during work carry out three-dimensional modeling, then carry out dynamic analog and data analysis again, obtain in construction simulation
Beneficial to the Gradient of draining during waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain lastrow floor tile
Gradient difference data between next line floor tile, data and architectural drawing, arrangement and method for construction is recycled to carry out site operation.The present invention
The related data obtained by BIM, has positive booster action for site operation, draining has just been obtained before construction
Preferred plan, avoid construction in be likely to occur influence draining parameter deviation.
The present invention is achieved through the following technical solutions:
A kind of balcony construction method of ground based on BIM, including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic of waterproof construction is carried out
Morphotype is intended, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, i.e. cement layer is laid on waterproof layer, floor tile arrangement
It is laid on into multirow on cement layer, when waterproof construction and tile work are constructed, is required to carry out the slope on ground to the face between floor drain
Degree arrangement;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain when tile work is constructed beneficial to the Gradient of draining
And obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
During waterproof construction, gradient 3-5%.
, it is necessary to coat primer during waterproof construction, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, polyurethane first and second
The mass ratio of material and dimethylbenzene is 1:2.
Dry solidification 4h-6h after primer coating.
The present invention compared with prior art, has the following advantages and advantages:
The related data that the present invention is obtained by BIM, has positive booster action for site operation, before construction
The preferred plan of draining has just been obtained, has avoided the deviation for the influence draining parameter being likely to occur in construction.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment, the present invention is made
Further to describe in detail, exemplary embodiment of the invention and its explanation are only used for explaining the present invention, are not intended as to this
The restriction of invention.
Embodiment 1
A kind of balcony construction method of ground based on BIM, including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic of waterproof construction is carried out
Morphotype is intended, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, i.e. cement layer is laid on waterproof layer, floor tile arrangement
It is laid on into multirow on cement layer, when waterproof construction and tile work are constructed, is required to carry out the slope on ground to the face between floor drain
Degree arrangement;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain when tile work is constructed beneficial to the Gradient of draining
And obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
Embodiment 2
During waterproof construction, gradient 3-5%.
, it is necessary to coat primer during waterproof construction, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, polyurethane first and second
The mass ratio of material and dimethylbenzene is 1:2.
Dry solidification 4h-6h after primer coating.
Above-described embodiment, the purpose of the present invention, technical scheme and beneficial effect are carried out further
Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention
Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc., all should include
Within protection scope of the present invention.
Claims (4)
1. a kind of balcony construction method of ground based on BIM, it is characterised in that including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic analog of waterproof construction is carried out
Intend, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, be i.e. cement layer is laid on waterproof layer, and floor tile is arranged in more
Row is laid on cement layer, when waterproof construction and tile work are constructed, is required to carry out the gradient row on ground to the face between floor drain
Row;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain
Obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
2. the balcony construction method of ground according to claim 1 based on BIM, it is characterised in that during waterproof construction, the gradient
For 3-5%.
3. the balcony construction method of ground according to claim 1 based on BIM, it is characterised in that during waterproof construction, it is necessary to
Coat primer, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, and the mass ratio of the material of polyurethane first and second and dimethylbenzene is 1:
2。
4. the balcony construction method of ground according to claim 3 based on BIM, it is characterised in that dried after primer coating
Solidify 4h-6h.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710630543.5A CN107451357A (en) | 2017-07-28 | 2017-07-28 | A kind of balcony construction method of ground based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710630543.5A CN107451357A (en) | 2017-07-28 | 2017-07-28 | A kind of balcony construction method of ground based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107451357A true CN107451357A (en) | 2017-12-08 |
Family
ID=60489562
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710630543.5A Pending CN107451357A (en) | 2017-07-28 | 2017-07-28 | A kind of balcony construction method of ground based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107451357A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110206313A (en) * | 2019-06-20 | 2019-09-06 | 浙江华汇装饰工程股份有限公司 | A kind of construction method of the mixed paving of flooring plate dry method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1072435A (en) * | 1992-08-27 | 1993-05-26 | 化学工业部海洋涂料研究所 | Building water-proof paint |
CN101191364A (en) * | 2006-11-28 | 2008-06-04 | 贵阳铝镁设计研究院 | Planting zoology roofing for topping laying floor brick |
CN101949207A (en) * | 2010-09-10 | 2011-01-19 | 中建七局第四建筑有限公司 | Method for constructing subsided rest room |
US20130013265A1 (en) * | 2011-07-07 | 2013-01-10 | Autodesk, Inc. | Direct manipulation of composite terrain objects with intuitive user interaction |
CN105781064A (en) * | 2016-03-04 | 2016-07-20 | 上海宝冶集团有限公司 | Floor tile laying construction method based on building information modeling (BIM) |
CN206158102U (en) * | 2016-10-31 | 2017-05-10 | 浙江铭品装饰工程有限公司 | Balcony construction site layout structure |
CN106886654A (en) * | 2017-03-14 | 2017-06-23 | 中国建筑第八工程局有限公司 | A kind of row's of building by laying bricks or stones brick method based on BIM technology |
-
2017
- 2017-07-28 CN CN201710630543.5A patent/CN107451357A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1072435A (en) * | 1992-08-27 | 1993-05-26 | 化学工业部海洋涂料研究所 | Building water-proof paint |
CN101191364A (en) * | 2006-11-28 | 2008-06-04 | 贵阳铝镁设计研究院 | Planting zoology roofing for topping laying floor brick |
CN101949207A (en) * | 2010-09-10 | 2011-01-19 | 中建七局第四建筑有限公司 | Method for constructing subsided rest room |
US20130013265A1 (en) * | 2011-07-07 | 2013-01-10 | Autodesk, Inc. | Direct manipulation of composite terrain objects with intuitive user interaction |
CN105781064A (en) * | 2016-03-04 | 2016-07-20 | 上海宝冶集团有限公司 | Floor tile laying construction method based on building information modeling (BIM) |
CN206158102U (en) * | 2016-10-31 | 2017-05-10 | 浙江铭品装饰工程有限公司 | Balcony construction site layout structure |
CN106886654A (en) * | 2017-03-14 | 2017-06-23 | 中国建筑第八工程局有限公司 | A kind of row's of building by laying bricks or stones brick method based on BIM technology |
Non-Patent Citations (3)
Title |
---|
张道真: "《建筑防水》", 31 August 2014 * |
花草游戏编辑部: "《庭院屋顶种花与景观设计》", 30 November 2010 * |
赵永任: "《工程项目管理》", 31 August 2016 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110206313A (en) * | 2019-06-20 | 2019-09-06 | 浙江华汇装饰工程股份有限公司 | A kind of construction method of the mixed paving of flooring plate dry method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104850709B (en) | Building decoration engineering construction three-dimensional simulation method | |
Bednarz et al. | Strengthening and long-term monitoring of the structure of an historical church presbytery | |
CN105781064A (en) | Floor tile laying construction method based on building information modeling (BIM) | |
CN106544961A (en) | A kind of distress in concrete blocking method | |
CN107299762A (en) | A kind of concrete pouring procedure based on BIM | |
CN111177824A (en) | Aluminum alloy formwork construction method based on BIM technology | |
CN113129427A (en) | Building model processing method and device, computer equipment and readable storage medium | |
CN107292060A (en) | Basement roadway applications method based on BIM technology | |
CN110879905A (en) | A method of roof deepening based on BIM virtual construction | |
CN111456279A (en) | Brick wall building method and device, computer equipment and storage medium | |
Jesus et al. | The potential of 3D printing in building pathology: rehabilitation of cultural heritage | |
CN107451357A (en) | A kind of balcony construction method of ground based on BIM | |
CN111324922B (en) | Method, device, computer equipment and storage medium for generating floor tile model | |
CN104373138B (en) | The construction method that waterproof layer is reinvented when a kind of tunnel lining structure is repaired | |
CN107292058A (en) | A kind of brickwork method based on BIM technology | |
CN103774696A (en) | Construction process of cement-based permeable-crystallization type waterproof material | |
CN107436984A (en) | A kind of wine cellar construction method based on BIM | |
CN111524225B (en) | Construction method of manual hole digging cast-in-place pile based on BIM technology | |
CN107451356A (en) | A kind of outer-wall building method based on BIM | |
CN108086712A (en) | A kind of ancient architecture walling center pillar safeguard structure and construction method | |
CN107313518A (en) | A kind of toilet warterproof technique based on BIM | |
CN107436985A (en) | A kind of toilet ground tile paving method based on BIM | |
CN104058694B (en) | A kind of concrete material for pavement patching and constructional method thereof | |
CN108265746A (en) | A kind of method of back-grouting in Equipment Foundations work progress | |
CN110147607A (en) | Three-dimensional simulation method for building decoration engineering construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171208 |
|
RJ01 | Rejection of invention patent application after publication |