CN104850709B - Building decoration engineering construction three-dimensional simulation method - Google Patents

Building decoration engineering construction three-dimensional simulation method Download PDF

Info

Publication number
CN104850709B
CN104850709B CN201510270601.9A CN201510270601A CN104850709B CN 104850709 B CN104850709 B CN 104850709B CN 201510270601 A CN201510270601 A CN 201510270601A CN 104850709 B CN104850709 B CN 104850709B
Authority
CN
China
Prior art keywords
dimensional
construction
data
threedimensional model
building decoration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510270601.9A
Other languages
Chinese (zh)
Other versions
CN104850709A (en
Inventor
刘长钦
陈名荣
胡建兵
陆李兵
刘军
顾静芳
杨保忠
王兵
康敬
姚伟勤
金鑫
姜伟
沈虹
吴网萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Gold Mantis Construction Decoration Co Ltd
Original Assignee
Suzhou Gold Mantis Construction Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Gold Mantis Construction Decoration Co Ltd filed Critical Suzhou Gold Mantis Construction Decoration Co Ltd
Priority to CN201510270601.9A priority Critical patent/CN104850709B/en
Publication of CN104850709A publication Critical patent/CN104850709A/en
Application granted granted Critical
Publication of CN104850709B publication Critical patent/CN104850709B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Processing Or Creating Images (AREA)

Abstract

The invention discloses a kind of building decoration engineering construction three-dimensional simulation methods, and based on 3 d modeling software, this method comprises the following steps:1) according to decoration construction drawing and pass through the threedimensional model that 3 d modeling software establishes construction area, establish nodal analysis method data and material depot, form three-dimensional modeling data storehouse;2) three-dimensional modeling data storehouse and decoration construction drawing are subjected to comparing, the error present in adjustment three-dimensional modeling data storehouse and/or decoration construction drawing;3) threedimensional model of node is extracted in three-dimensional modeling data storehouse, is confided a technological secret according to threedimensional model and construction party.Compared with prior art, the present invention having abandoned traditional mode, the quality and efficiency of decoration construction are effectively improved.

Description

Building decoration engineering construction three-dimensional simulation method
Technical field
The present invention relates to computer software technologies used in a kind of building decoration engineering, and in particular to a kind of building decoration Engineering construction three-dimensional simulation method.
Background technology
In recent years, with the fast development of threedimensional model technology, with more in architectural design, building body design Come more extensive, but with less in present indoor decoration project under construction, especially tell somebody what one's real intentions are in construction technology, method On, the personal experience completely by builder, the profile of builder determines integrality and accuracy that Project Technical is told somebody what one's real intentions are, Having no basis can seek, and the process handing-over of site operation can also encounter the interactional situation of process, be delayed project progress, no The accuracy rate of decorative scene construction is only affected, while also contributes to the whole efficiency of construction.
The content of the invention
In order to solve the above technical problem, the present invention provides one kind can effectively improve construction efficiency and construction quality Building decoration engineering construction three-dimensional simulation method.
In order to achieve the above object, technical scheme is as follows:
Building decoration engineering construction three-dimensional simulation method, based on 3 d modeling software, this method comprises the following steps:
1) according to decoration construction drawing and pass through the threedimensional model that 3 d modeling software establishes construction area, establish node mould Type data and material depot form three-dimensional modeling data storehouse;
2) three-dimensional modeling data storehouse and decoration construction drawing are subjected to comparing, adjust three-dimensional modeling data storehouse and/or Error present in decoration construction drawing;
3) threedimensional model of node is extracted in three-dimensional modeling data storehouse, technology friendship is carried out according to threedimensional model and construction party Bottom.
The present invention in 3 d modeling software by establishing three-dimensional modeling data storehouse, first by being compared with construction drawing It is right, in the case where ensuring no error, the threedimensional model of node is reintroduced, and skill is carried out according to the threedimensional model and construction party Art is told somebody what one's real intentions are, and completely instead of the personal experience by builder, the profile of builder determines the mode that Project Technical is told somebody what one's real intentions are, So that items are told somebody what one's real intentions are, data have evidence that can seek so that every process can carry out in an orderly manner so that process handing-over is not affected, and has Improve the accuracy rate and whole efficiency of decorative scene construction in effect ground.
Therefore, compared with prior art, the present invention having abandoned traditional mode, it is effectively improved the quality of decoration construction And efficiency.
Based on the above technical solutions, system of the invention can also be improved as follows:
As preferred scheme, above-mentioned building decoration engineering construction three-dimensional simulation method further includes animation preview step: The animation effect of threedimensional model is edited out according to construction procedure by 3 d modeling software, project construction is previewed, with The problems of discovery in advance before construction party is confided a technological secret.
Using the above preferred scheme, the accuracy of threedimensional model can be effectively improved, so as to develop skill what is told somebody what one's real intentions are Accuracy rate.
As preferred scheme, above-mentioned building decoration engineering construction three-dimensional simulation method further includes ornament materials modeling step Suddenly:The site dimension and sizes of memory data of construction area are scanned, 3 d modeling software establishes scantling according to dimension data Three-dimensional data is inputted in numerical control device and processes required material product by three-dimensional data, material product manufacturer.
Using the above preferred scheme, single mode under traditional artificial material can be abandoned, is avoided under material in single quantity When it is more when few, artificial estimation numerical value inaccurate mode, so as to improve the accuracy and efficiency that material product places an order.
Alternatively, above-mentioned building decoration engineering construction three-dimensional simulation method, which is characterized in that further include dress Exterior material modeling procedure:The size three-dimensional data on ornament materials part, material production are extracted from three-dimensional modeling data storehouse Man of manufacturer, which inputs three-dimensional data in numerical control device, processes required material product.
Using the above preferred scheme, single mode under traditional artificial material can be equally abandoned, avoids odd number under material The inaccurate mode of few when more when in amount, artificial estimation numerical value, so as to improve the accuracy and efficiency that material product places an order.
As preferred scheme, by the three-dimensional data of the good material product of three-dimensional scanning device scanning machining, then with Size three-dimensional data are compared, and correct error between the two.
Using the above preferred scheme, the problem of can finding material product in time before construction, so as to improve The total quality of construction.
As preferred scheme, above-mentioned three-dimensional modeling data storehouse is to be layered to establish according to construction technology.
Using the above preferred scheme, the accuracy of threedimensional model can be improved.
As preferred scheme, above-mentioned 3 d modeling software is Sktechup softwares.
Using the above preferred scheme, the modeling efficiency of threedimensional model and modeling accuracy can be improved.
Description of the drawings
Fig. 1 is the flow chart of the building decoration engineering construction three-dimensional simulation method of the present invention.
Specific embodiment
The preferred embodiment that the invention will now be described in detail with reference to the accompanying drawings.
In order to reach the purpose of the present invention, as shown in Figure 1, in the building decoration engineering construction three-dimensional simulation method of the present invention Some of embodiments in, provide the computer or other mobile computer devices for possessing windows operating systems, so There is provided the 3 d modeling software such as Sketchup, Solidworks in a computer afterwards, this method comprises the following steps:
S101:Be connected to after project under construction, be first one interpreting blueprints process, including Hydroelectric Project Construction figure, installation figure, The drawings such as fire-fighting construction drawing, and understanding is analyzed it, to establish Three-Dimensional Battle electronic sand table model database is commanded to carry out Prepare, introducing Sketchup is workbench, and the threedimensional model of construction area is established according to decoration construction drawing, establishes node mould Type data and material depot form three-dimensional modeling data storehouse;
S102 and S1021:Three-dimensional modeling data storehouse and decoration construction drawing are subjected to comparing, adjust threedimensional model number Can be specifically to construction drawing, Hydroelectric Project Construction figure, installation according to storehouse or decoration construction drawing or both error existing simultaneously The drawings such as construction drawing, fire-fighting construction drawing are analyzed, and can have proofreading function to drawing, can carry out impact test, each to construct The simulated crash integration technology of unit construction content, with reference to the decoration construction drawing, Hydroelectric Project Construction figure, installation to engineering They are presented on the three dimensions of a simulation with threedimensional model technology by the analysis of the drawings such as figure, fire-fighting construction drawing one by one In, and be compared, on the premise of the relevant regulations of country are ensured compliance with, design mistake is reasonably optimized, Adjustment in time is not complete because considering in design phase early period, causes the side to conflict between decoration construction and the construction of other complete units Case.
S103:The threedimensional model of node is extracted in three-dimensional modeling data storehouse, skill is carried out according to threedimensional model and construction party Art is told somebody what one's real intentions are so that is confided a technological secret more intuitive and easy to understand, is improved the efficiency that site technology is told somebody what one's real intentions are, lowers the wind that construction node does wrong Danger.
This method in 3 d modeling software by establishing three-dimensional modeling data storehouse, first by being compared with construction drawing It is right, in the case where ensuring no error, the threedimensional model of node is reintroduced, and skill is carried out according to the threedimensional model and construction party Art is told somebody what one's real intentions are, and completely instead of the personal experience by builder, the profile of builder determines the mode that Project Technical is told somebody what one's real intentions are, So that items are told somebody what one's real intentions are, data have evidence that can seek so that every process can carry out in an orderly manner so that process handing-over is not affected, and has Improve the accuracy rate and whole efficiency of decorative scene construction in effect ground.Therefore, this method compared with prior art, has been abandoned traditional Mode is effectively improved the quality and efficiency of decoration construction.
In order to further optimize the implementation result of the present invention, as shown in Figure 1, the building decoration engineering in the present invention is constructed In other embodiments of three-dimensional simulation method, on the basis of the above, the construction of above-mentioned building decoration engineering is three-dimensional Analogy method further includes animation preview step S1031:Threedimensional model is edited out according to construction procedure by 3 d modeling software The problems of animation effect previews project construction, found in advance before being confided a technological secret with construction party, i.e., After rational arrangement and method for construction is determined, site technology is carried out to teams and groups and is told somebody what one's real intentions are.Using simulation of the threedimensional model to construction, reduce The phenomenon that doing over again.Using the scheme of the embodiment, the accuracy of threedimensional model can be effectively improved, is handed over so as to develop skill The accuracy rate at bottom.
In order to further optimize the implementation result of the present invention, as shown in Figure 1, the building decoration engineering in the present invention is constructed In other embodiments of three-dimensional simulation method, on the basis of the above, the construction of above-mentioned building decoration engineering is three-dimensional Analogy method further includes ornament materials modeling procedure S104:The site dimension and sizes of memory data of construction area are scanned, will be swept The data transmission retouched considers the content of site operation combining the actually measured data in scene, three-dimensional modeling on computer Software establishes scantling three-dimensional data according to dimension data, and three-dimensional data is inputted numerical control device by material product manufacturer Required material product is processed in (such as numerically-controlled machine tool).Using the scheme of the embodiment, traditional people can be abandoned Single mode under work material, the inaccurate mode of few, artificial estimation numerical value when more when avoiding under material in single quantity, so as to improve material The accuracy and efficiency that material product places an order.
Above-mentioned step S104 can also be embodied as:It is extracted from three-dimensional modeling data storehouse on ornament materials part Three-dimensional data is inputted in numerical control device and processes required material product by size three-dimensional data, material product manufacturer.
In order to further optimize the implementation result of the present invention, as shown in Figure 1, the building decoration engineering in the present invention is constructed In other embodiments of three-dimensional simulation method, on the basis of the above, step S105 is further included:Pass through 3-D scanning The three-dimensional data for the material product that device scan processes, then with size three-dimensional data be compared, correct between the two Error is tested, checked, it is ensured that processing dimension and the accurate fit at scene.Using the scheme of the embodiment, Ke Yi The problem of material product is found before construction in time, so as to improve the total quality of construction.
In order to further optimize the implementation result of the present invention, in the building decoration engineering construction three-dimensional simulation side of the present invention In other embodiments of method, on the basis of the above, above-mentioned three-dimensional modeling data storehouse is according to construction technology point Layer is established.Using the scheme of the embodiment, the accuracy of threedimensional model can be improved.
Above-described is only the preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art For, without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to the present invention Protection domain.

Claims (6)

1. building decoration engineering construct three-dimensional simulation method, based on 3 d modeling software, which is characterized in that the described method includes with Lower step:
1) to including the decoration construction drawing reading of Hydroelectric Project Construction figure, installation figure, fire-fighting construction drawing drawing, and it is carried out Analysis and understanding commands electronic sand table model database to be ready to establish Three-Dimensional Battle, and introducing Sketchup is workbench, Nodal analysis method data and material depot are established, forms three-dimensional modeling data storehouse;
2) three-dimensional modeling data storehouse and the decoration construction drawing are subjected to comparing, adjust the three-dimensional modeling data Error present in storehouse and/or decoration construction drawing;
3) threedimensional model of node is extracted in the three-dimensional modeling data storehouse, skill is carried out according to the threedimensional model and construction party Art is told somebody what one's real intentions are
4) site dimension and sizes of memory data of construction area are scanned, the 3 d modeling software is built according to the dimension data Vertical scantling three-dimensional data, material product manufacturer will process required in three-dimensional data input numerical control device Material product.
The three-dimensional simulation method 2. building decoration engineering according to claim 1 is constructed, which is characterized in that it is pre- to further include animation Drill step:The animation effect of the threedimensional model is edited out according to construction procedure by the 3 d modeling software, project is applied The problems of work is previewed, found in advance before being confided a technological secret with construction party.
The three-dimensional simulation method 3. building decoration engineering according to claim 1 is constructed, which is characterized in that further include decoration material Expect modeling procedure:The size three-dimensional data on ornament materials part, material production are extracted from the three-dimensional modeling data storehouse Man of manufacturer, which inputs the three-dimensional data in numerical control device, processes required material product.
The three-dimensional simulation method 4. building decoration engineering according to claim 3 is constructed, which is characterized in that pass through 3-D scanning The three-dimensional data for the material product that device scan processes, then be compared with the size three-dimensional data, correct the two Between error.
The three-dimensional simulation method 5. building decoration engineering according to claim 1 is constructed, which is characterized in that the threedimensional model Database is to be layered to establish according to construction technology.
6. according to any building decoration engineering construction three-dimensional simulation methods of claim 1-3, which is characterized in that described three Dimension modeling software is Sktechup softwares.
CN201510270601.9A 2015-05-25 2015-05-25 Building decoration engineering construction three-dimensional simulation method Active CN104850709B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510270601.9A CN104850709B (en) 2015-05-25 2015-05-25 Building decoration engineering construction three-dimensional simulation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510270601.9A CN104850709B (en) 2015-05-25 2015-05-25 Building decoration engineering construction three-dimensional simulation method

Publications (2)

Publication Number Publication Date
CN104850709A CN104850709A (en) 2015-08-19
CN104850709B true CN104850709B (en) 2018-05-25

Family

ID=53850352

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510270601.9A Active CN104850709B (en) 2015-05-25 2015-05-25 Building decoration engineering construction three-dimensional simulation method

Country Status (1)

Country Link
CN (1) CN104850709B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089247B (en) * 2015-08-27 2017-10-20 苏州金螳螂建筑装饰股份有限公司 The many curved surface arc board mounting structures of facade abnormity and its installation method
CN106639207A (en) * 2016-11-01 2017-05-10 苏州美瑞德建筑装饰有限公司 Complex shared space assembling building decoration construction method based on BIM (building information modeling)
CN106897498B (en) * 2017-01-24 2020-06-12 天津博迈科海洋工程有限公司 Large complex support model correction method
CN107123323A (en) * 2017-07-12 2017-09-01 广州风禾数字科技有限公司 Virtual training teaching system
CN107729609A (en) * 2017-09-14 2018-02-23 北京致臻智造科技有限公司 The display methods and system that a kind of building decoration technology is told somebody what one's real intentions are
CN107580206A (en) * 2017-10-13 2018-01-12 湖北聚注通用技术研究有限公司 A kind of decoration construction scene 3-D imaging system based on multi-view image
CN107808052A (en) * 2017-10-27 2018-03-16 巧夺天宫(深圳)科技有限公司 A kind of plumbing toilet seat engineering design system, design method and electronic equipment
CN107563109A (en) * 2017-10-30 2018-01-09 巧夺天宫(深圳)科技有限公司 A kind of plumbing squatting pan engineering design method, design system and electronic equipment
CN108171786A (en) * 2017-12-12 2018-06-15 上海爱优威软件开发有限公司 A kind of terminal simulation design method and system
CN110206212A (en) * 2019-05-27 2019-09-06 中国十七冶集团有限公司 A kind of curved metal roof construction method based on BIM technology
CN111310333B (en) * 2020-02-12 2022-09-30 上海国太建筑装饰工程有限公司 Building decoration simulation construction method
CN112663885A (en) * 2020-12-10 2021-04-16 深圳中安建工程建设有限公司 Decoration method of interior decoration prefabricated component
CN113343339B (en) * 2021-06-17 2022-04-29 华煜建设集团有限公司 Green and environment-friendly building decoration method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102819621B (en) * 2011-06-10 2015-04-01 上海市电力公司 Device for conducting construction simulation through building information model (BIM)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2851817A (en) * 1956-09-17 1958-09-16 Jr Henry J Faustich Safety fish hook with retractable barbs
CN102235090A (en) * 2010-04-20 2011-11-09 上海市建筑装饰工程有限公司 Method for realizing factory-oriented construction of architectural ornament project based on three-dimensional virtual software platform
CN104573254A (en) * 2015-01-21 2015-04-29 中国十七冶集团有限公司 Pre-construction technical disclosure method based on BIM

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102819621B (en) * 2011-06-10 2015-04-01 上海市电力公司 Device for conducting construction simulation through building information model (BIM)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
基于SketchUp的装饰工程BIM技术应用研究;罗兰 等;《土木建筑工程信息技术》;20150430;第7卷(第2期);37-42 *

Also Published As

Publication number Publication date
CN104850709A (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN104850709B (en) Building decoration engineering construction three-dimensional simulation method
CN104217063B (en) Emulation design method for steel rail rolling pass
CN104252558B (en) A kind of non-standard construction fender member digital control processing preprocess method based on BIM platform
Jiang et al. Frame field singularity correctionfor automatic hexahedralization
CN109583033B (en) Application method and system of BIM adaptive model in special-shaped curtain wall construction
CN104715114B (en) The collision checking method and device of steel truss arched bridge beam are realized using BIM
US9804751B2 (en) Creating and merging two-dimensional floor plans within three-dimensional models
CN105781064A (en) Floor tile laying construction method based on building information modeling (BIM)
CN107299762A (en) A kind of concrete pouring procedure based on BIM
CN106639207A (en) Complex shared space assembling building decoration construction method based on BIM (building information modeling)
US20160328496A1 (en) System and method for editing a model
CN114065357A (en) A Revit-based modeling method and system for segment-assembled bridges
CN113158320B (en) Three-dimensional modeling system based on building plane design
CN107451358A (en) A kind of building method of the curved wall based on BIM
CN107905512A (en) A kind of Wall or floor tile based on BIM becomes more meticulous construction
CN113987627B (en) A solid modeling method for shield universal segment based on Revit secondary development
CN108829954A (en) A kind of reinforcing bar configuration method based on structural model profile features
CN110378039A (en) A kind of aluminum alloy pattern plate design method and system based on Revit
Anderson et al. Surface and hypersurface meshing techniques for space–time finite element methods
CN106114037A (en) A kind of building block engraving process
CN107292058A (en) A kind of brickwork method based on BIM technology
CN102819237B (en) Method for generating simulation target blank in solid milling simulation process
CN109063272B (en) Design method of flexible drilling template
CN115098964B (en) A merging method, device and electronic equipment
CN110147607A (en) Three-dimensional simulation method for building decoration engineering construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant