CN106017410B - The safety monitoring assembly and application method of a kind of tunnel arch top settlement - Google Patents

The safety monitoring assembly and application method of a kind of tunnel arch top settlement Download PDF

Info

Publication number
CN106017410B
CN106017410B CN201610406518.4A CN201610406518A CN106017410B CN 106017410 B CN106017410 B CN 106017410B CN 201610406518 A CN201610406518 A CN 201610406518A CN 106017410 B CN106017410 B CN 106017410B
Authority
CN
China
Prior art keywords
lasso
rod piece
testing stand
tunnel
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610406518.4A
Other languages
Chinese (zh)
Other versions
CN106017410A (en
Inventor
金玲玲
宋文利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201610406518.4A priority Critical patent/CN106017410B/en
Publication of CN106017410A publication Critical patent/CN106017410A/en
Application granted granted Critical
Publication of CN106017410B publication Critical patent/CN106017410B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B7/00Measuring arrangements characterised by the use of electric or magnetic techniques
    • G01B7/16Measuring arrangements characterised by the use of electric or magnetic techniques for measuring the deformation in a solid, e.g. by resistance strain gauge

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of safety monitoring assemblies of tunnel arch top settlement, the safety monitoring assembly includes testing stand, energy-saving bulb, supporting rod, tunnel vault, and the testing stand is made of connector, head protector, poling, assembled rod piece, pedestal, card slot, assembly rod piece a;Assembled rod piece is vertically installed on the pedestal, the upper end of the assembly rod piece is equipped with connector, the connector left and right directions is set with poling, the top of the testing stand is equipped with assembled rod piece a, the centre position of the assembly rod piece a is provided with card slot, the rod piece with lasso is set on the card slot, lasso is provided on the rod piece with lasso, spring card is provided on four wall of inside of the lasso, the upper end of the lasso is provided with mounting head part, the upper end of the mounting head part is provided with triangle and is inserted into head, the triangle is inserted into head and is provided with multiple supporting rods, the upper end top pressure of the supporting rod is in the lower surface of tunnel vault.

Description

The safety monitoring assembly and application method of a kind of tunnel arch top settlement
Technical field
The present invention relates to a kind of construction detection device and application method, more specifically, being to be related to a kind of tunnel arch Push up the safety monitoring assembly to sink and application method.
Background technology
Deformation observation and monitoring measurement are the quality of work progress and the emphasis of security control during constructing tunnel, in tunnel In road construction, the deformation and displacement of periphery displacement, vault sinking, ground settlement and surrounding building and pipeline are monitoring measurements It must survey project, wherein vault sinking conventional observation method is that tape measure link is suspended to vault sinking to measure on hook, using spirit level, It measures elevation and obtains vault elevation numerical value.Such method by tape measure link hang up monitoring hook the step for take it is too long, 24 Monitoring point, took close to 4 hours, and efficiency is low.The effect of vault sinking numerical value is when vault sinking rate of change is very fast, It is possible that constructing tunnel is just faced with the danger that vault caves in.When vault sinking cumulative amount is excessive, then need at the beginning of changing tunnel Branch supporting parameter carrys out strengthening supporting, ensures construction in later period safety;Also have and paste total powerstation reflecting piece using on vault sinking hook, make With total station survey elevation, by the comparison of height difference, the rate of deformation is determined;It, by spirit level and total powerstation observation procedure The measurement of people repeatedly is measured, it is longer to expend the time;In recent years, also had using sensor method, and be digitized observation deformation values, this The control of kind of method is more convenient, but sensor economy is not strong, consider in most constructing tunnels economic benefit do not use generally or It is not high using frequency, it is impossible to reach the requirement of safety and quality management.When tunnel vault happen suddenly displacement it is larger when, because use The unpredictable emergency situations of traditional measuring method in construction personnel constructs at the scene, face very big safety problem, so as to It is difficult to predict be the problem that technical staff and safety quality management personnel explore all the time.
Invention content
The present invention is directed to the deficiency of existing product, and provides safety monitoring assembly and the user of a kind of tunnel arch top settlement Method.
A kind of safety monitoring assembly of tunnel arch top settlement of the present invention, the safety monitoring assembly include testing stand, section Energy light bulb, supporting rod, tunnel vault, the testing stand is by connector, head protector, poling, assembled rod piece, pedestal, card slot, assembled bar Part a is formed;Assembled rod piece is vertically installed on the pedestal, the upper end of the assembly rod piece is equipped with connector, the connection Part left and right directions is set with poling, and the top of the testing stand is equipped with assembled rod piece a, the centre position of the assembly rod piece a Card slot is provided with, the rod piece with lasso is set on the card slot, lasso is provided on the rod piece with lasso, it is described Spring card is provided on four wall of inside of lasso, the upper end of the lasso is provided with mounting head part, the mounting head part Upper end be provided with triangle and be inserted into head, the triangle is inserted into head and is provided with multiple supporting rods, the upper end top pressure of the supporting rod In the lower surface of tunnel vault;Conductive metal circle is provided with below the lasso, the conductive metal circle and energy-saving bulb connect It connects, the top setting conductive sheet of the conductive metal circle, the conductive sheet sets mounting head portion lower surface;The conductive sheet leads to Conducting wire is crossed to connect with accumulator.
The mounting distance of the conductive sheet and conductive metal circle in-between is 1-10mm.
Four corners of the pedestal are provided with jacking screw rod.
A kind of application method of the safety monitoring assembly of tunnel arch top settlement, the application method include the following steps;
Step 1, the height of tunnel vault and bottom surface is measured, testing stand is made according to height;The testing stand passes through assembly Rod piece is connected with pedestal, then increases different height assembly rod piece by connector, and testing stand is made to reach requirement for height;
Step 2, assembled rod piece a is transversely mounted in the upper end of testing stand, the centre position of assembled rod piece a is provided with card slot, Rod piece of the installation with lasso in card slot, is provided with lasso on the rod piece with lasso, is placed on four walls inside the lasso Spring card;
Step 3, in the upper end of lasso setting mounting head part, the upper end of mounting head part is provided with triangle and is inserted into head, Triangle is inserted into head and is installed with multiple supporting rods, and the upper end top pressure of supporting rod is in the lower surface of tunnel vault;
Step 4, conductive metal circle is provided with below lasso, conductive metal circle is connected with energy-saving bulb, conductive metal circle Top setting conductive sheet, conductive sheet setting mounting head portion lower surface;Conductive sheet is connected by conducting wire with accumulator;
Step 5, the height of testing stand is finely tuned by the jacking screw rod of four corners of pedestal, is in each supporting rod Stress;
Step 6, when tunnel vault sinks, supporting rod acts on triangle and is inserted on head, so as to which triangle be made to be inserted into head It breaks through the constraint of spring card and declines, when the displacement of sinking reaches setting value, conductive sheet is formed back with conductive metal circle Road, light bulb light monitoring and finish.
The beneficial effects of the invention are as follows:Using visual light bulb by the deformation of testing stand, make light bulb glittering, display peace Full early warning so as to which personnel and equipment be made to be shifted faster or reminded to constructor, prevents and possible trouble, takes effectively Measure big landslide and accident is avoided to occur.
Description of the drawings
Fig. 1 is the overall structure diagram of the present invention;
Fig. 2 is the side view of the testing stand of the present invention;
Fig. 3 is the front view of the testing stand of the present invention;
Fig. 4 is the structure diagram of the lasso of the present invention;
Fig. 5 is that the triangle of the present invention is inserted into the structure diagram of head;
Fig. 6 is the spring card mounting structure schematic diagram of the present invention;
In figure:Connector 1, head protector 2, poling 3, assembled rod piece 4, pedestal 5, card slot 6, assembled rod piece a7, spring card 7- 1st, the rod piece 8 with lasso, lasso 9, conductive sheet 10, conductive metal circle 10-1, mounting head part 11, triangle are inserted into head 12, section It can light bulb 13, supporting rod 14, tunnel vault 15.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings.
A kind of safety monitoring assembly of tunnel arch top settlement of the invention is mainly by connector 1, head protector 2, poling in the figure 3rd, assembled rod piece 4, pedestal 5, card slot 6, assembled rod piece a7, spring card 7-1, the rod piece 8 with lasso, lasso 9, conductive sheet 10th, conductive metal circle 10-1, mounting head part 11, triangle are inserted into head 12, energy-saving bulb 13, supporting rod 14,15 groups of tunnel vault Into.
A kind of safety monitoring assembly of tunnel arch top settlement of the present invention, the safety monitoring assembly include testing stand, energy saving Light bulb 13, supporting rod 14, tunnel vault 15, the testing stand is by connector 1, head protector 2, poling 3, assembled rod piece 4, pedestal 5, card Slot 6, assembled rod piece a7 compositions;Assembled rod piece 4 is vertically installed on the pedestal 5, the upper end of the assembly rod piece 4 is equipped with company Fitting 1,1 left and right directions of connector are set with poling 3, and the top of the testing stand is equipped with assembled rod piece a7, the spelling The centre position of dress rod piece a7 is provided with card slot 6, be set with the rod piece 8 with lasso on the card slot 6, described with lasso Lasso 9 is provided on rod piece 8, spring card 7-1, the upper end setting of the lasso 9 are provided on four wall of inside of the lasso 9 There is mounting head part 11, the upper end of the mounting head part 11 is provided with triangle and is inserted into head 12, and the triangle is inserted into head 12 and sets Multiple supporting rods 14 are equipped with, the upper end top pressure of the supporting rod 14 is in the lower surface of tunnel vault 15;The lower section of the lasso 9 is set Conductive metal circle 10-1 is equipped with, the conductive metal circle 10-1 and energy-saving bulb 13 connect, and the conductive metal circle 10-1's is upper Side's setting conductive sheet 10, the conductive sheet 10 set 11 lower surface of mounting head part;The conductive sheet 10 passes through conducting wire and electric power storage Pond connects.
The mounting distance of the conductive sheet 10 and conductive metal circle 10-1 in-between is 1-10mm.
Four corners of the pedestal 5 are provided with jacking screw rod.
A kind of application method of the safety monitoring assembly of tunnel arch top settlement, the application method include the following steps;
Step 1, the height of tunnel vault 15 and bottom surface is measured, testing stand is made according to height;The testing stand passes through spelling Dress rod piece 4 and pedestal 5 connect, then increase different height assembly rod piece 4 by connector 1, and testing stand is made to reach requirement for height;
Step 2, assembled rod piece a7 is transversely mounted in the upper end of testing stand, the centre position of assembled rod piece a7 is provided with card slot 6, the rod piece 8 with lasso in card slot 6 is installed, lasso 9 is provided on the rod piece 8 with lasso, on 9 four walls of inside of lasso It is placed with spring card 7-1;
Step 3, in the upper end of lasso 9 setting mounting head part 11, the upper end of mounting head part 11 is provided with triangle insertion First 12, it is inserted into head 12 in triangle and is installed with multiple supporting rods 14, the upper end top pressure of supporting rod 14 is in tunnel vault 15 Lower surface;
Step 4, the lower section of lasso 9 is provided with conductive metal circle 10-1, conductive metal circle 10-1 and energy-saving bulb 13 connects, The top setting conductive sheet 10 of conductive metal circle 10-1, conductive sheet 10 set 11 lower surface of mounting head part;Conductive sheet 10 passes through Conducting wire is connected with accumulator;
Step 5, the height of testing stand is finely tuned by the jacking screw rod of four corners of pedestal 5, makes each supporting rod 14 It is in stress;
Step 6, when tunnel vault 15 sinks, supporting rod 14 acts on triangle and is inserted on head 12, so as to make triangle Head 12 is inserted into break through the constraint of spring card 7-1 and decline, when the displacement of sinking reaches setting value, conductive sheet 10 and conduction Quoit 10-1 is formed into a loop, and light bulb lights monitoring and finishes.
The present invention uses deformation of the visual light bulb by testing stand, makes light bulb glittering, safe early warning is shown, so as to make Personnel and equipment are shifted or are reminded to constructor faster, are prevented and possible trouble, take effective measures avoid it is big Landslide and accident occur.
The foregoing is merely the embodiment of the present invention, are not intended to limit the scope of the invention, every to utilize this hair The equivalent structure or equivalent flow shift that bright description is made directly or indirectly is used in other relevant technology necks Domain is included within the scope of the present invention.

Claims (4)

1. a kind of safety monitoring assembly of tunnel arch top settlement, it is characterized in that, the safety monitoring assembly includes testing stand, energy saving Light bulb(13), supporting rod(14), tunnel vault(15), the testing stand is by connector(1), head protector(2), poling(3), assembled bar Part(4), pedestal(5), card slot(6), assembled rod piece a(7)Composition;The pedestal(5)On be vertically installed with assembled rod piece(4), institute State assembled rod piece(4)Upper end connector is installed(1), the connector(1)Left and right directions is set with poling(3), the inspection The top of test aircraft is equipped with assembled rod piece a(7), the assembly rod piece a(7)Centre position be provided with card slot(6), the card slot (6)On be set with the rod piece with lasso(8), the rod piece with lasso(8)On be provided with lasso(9), the lasso(9) Four wall of inside on be provided with spring card(7-1), the lasso(9)Upper end be provided with mounting head part(11), the peace Fill head point(11)Upper end be provided with triangle be inserted into head(12), the triangle insertion head(12)Inside it is provided with multiple supporting rods (14), the supporting rod(14)Upper end top pressure in tunnel vault(15)Lower surface;The lasso(9)Lower section be provided with and lead Electric metal circle(10-1), the conductive metal circle(10-1)And energy-saving bulb(13)Connection, the conductive metal circle(10-1)'s Top sets conductive sheet(10), the conductive sheet(10)Mounting head part is set(11)Lower surface;The conductive sheet(10)Pass through Conducting wire is connected with accumulator.
2. a kind of safety monitoring assembly of tunnel arch top settlement according to claim 1, it is characterized in that, the conductive sheet (10)With conductive metal circle(10-1)Mounting distance in-between is 1-10mm.
3. a kind of safety monitoring assembly of tunnel arch top settlement according to claim 1, it is characterized in that, the pedestal(5) Four corners be provided with jacking screw rod.
4. a kind of application method of the safety monitoring assembly of tunnel arch top settlement, it is characterized in that, the application method includes following Step;
Step 1, tunnel vault is measured(15)With the height of bottom surface, testing stand is made according to height;The testing stand passes through assembly Rod piece(4)And pedestal(5)Connection, then pass through connector(1)Increase different height assembly rod piece(4), testing stand is made to reach height It is required that;
Step 2, assembled rod piece a is transversely mounted in the upper end of testing stand(7), assembled rod piece a(7)Centre position be provided with card slot (6), in card slot(6)Interior rod piece of the installation with lasso(8), the rod piece with lasso(8)On be provided with lasso(9), in lasso (9)Spring card is placed on internal four walls(7-1);
Step 3, in lasso(9)Upper end setting mounting head part(11), mounting head part(11)Upper end be provided with triangle and insert Enter head(12), head is inserted into triangle(12)Inside it is installed with multiple supporting rods(14), supporting rod(14)Upper end top pressure in tunnel Road vault(15)Lower surface;
Step 4, lasso(9)Lower section be provided with conductive metal circle(10-1), conductive metal circle(10-1)And energy-saving bulb(13) Connection, conductive metal circle(10-1)Top setting conductive sheet(10), conductive sheet(10)Mounting head part is set(11)Lower surface; Conductive sheet(10)It is connected by conducting wire with accumulator;
Step 5, pass through pedestal(5)Four corners jacking screw rod fine tuning testing stand height, make each supporting rod(14) It is in stress;
Step 6, work as tunnel vault(15)When sinking, supporting rod(14)It acts on triangle and is inserted into head(12)On, so as to make three Head is inserted at angle(12)Break through spring card(7-1)Constraint and decline, when the displacement of sinking reaches setting value, conductive sheet (10)With conductive metal circle(10-1)Forming circuit, light bulb light monitoring and finish.
CN201610406518.4A 2016-06-12 2016-06-12 The safety monitoring assembly and application method of a kind of tunnel arch top settlement Active CN106017410B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610406518.4A CN106017410B (en) 2016-06-12 2016-06-12 The safety monitoring assembly and application method of a kind of tunnel arch top settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610406518.4A CN106017410B (en) 2016-06-12 2016-06-12 The safety monitoring assembly and application method of a kind of tunnel arch top settlement

Publications (2)

Publication Number Publication Date
CN106017410A CN106017410A (en) 2016-10-12
CN106017410B true CN106017410B (en) 2018-06-26

Family

ID=57090159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610406518.4A Active CN106017410B (en) 2016-06-12 2016-06-12 The safety monitoring assembly and application method of a kind of tunnel arch top settlement

Country Status (1)

Country Link
CN (1) CN106017410B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100009902A (en) * 2008-07-21 2010-01-29 (주)성진지오텍 Surveying target for measuring displacement and settlement
CN102914282A (en) * 2012-10-18 2013-02-06 中铁隧道集团有限公司 Monitoring and measuring method using displacement sensor to measure tunnel deformation
CN104697495A (en) * 2015-03-03 2015-06-10 江西飞尚科技有限公司 On-line monitoring method for settlement and convergence in building construction and operation periods
CN104931006A (en) * 2015-05-05 2015-09-23 中国矿业大学 Dynamic monitoring device for surrounding rock deformation of filling roadway
CN105136100A (en) * 2015-04-29 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Tunnel convergence deformation monitoring method and device
CN204851268U (en) * 2015-07-27 2015-12-09 重庆大学 Efficient tunnel vault monitoring point erection equipment
CN205228375U (en) * 2015-12-19 2016-05-11 长安大学 Experimental lining deformation monitoring devices of tunnel model

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100009902A (en) * 2008-07-21 2010-01-29 (주)성진지오텍 Surveying target for measuring displacement and settlement
CN102914282A (en) * 2012-10-18 2013-02-06 中铁隧道集团有限公司 Monitoring and measuring method using displacement sensor to measure tunnel deformation
CN104697495A (en) * 2015-03-03 2015-06-10 江西飞尚科技有限公司 On-line monitoring method for settlement and convergence in building construction and operation periods
CN105136100A (en) * 2015-04-29 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Tunnel convergence deformation monitoring method and device
CN104931006A (en) * 2015-05-05 2015-09-23 中国矿业大学 Dynamic monitoring device for surrounding rock deformation of filling roadway
CN204851268U (en) * 2015-07-27 2015-12-09 重庆大学 Efficient tunnel vault monitoring point erection equipment
CN205228375U (en) * 2015-12-19 2016-05-11 长安大学 Experimental lining deformation monitoring devices of tunnel model

Also Published As

Publication number Publication date
CN106017410A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
CN103422890B (en) A kind of novel anchor rod withdrawal resistance alarm and using method thereof
CN104457590A (en) Conductor sag monitoring device based on laser distance measurement and monitoring methods
CN106546219A (en) Electrical substation monitoring device, method and system
CN104834012A (en) Electromagnetic radiation monitoring early warning method of mine roof water inrush
CN106017410B (en) The safety monitoring assembly and application method of a kind of tunnel arch top settlement
CN205607483U (en) Dedicated simple and easy water level alarm controls flood
CN104655001A (en) Automatic monitoring device for high side slope deformation key position and application method of automatic monitoring device
CN105910577B (en) A kind of tunnel arch top settlement plumb bob observation device and application method
CN201429408Y (en) Extra-high voltage transmission line tilt angle monitoring device
CN210344919U (en) Environmental monitoring is with monitoring devices who has safeguard function
CN204241529U (en) A kind of convenient and practical bar of checking meter
CN207295994U (en) A kind of shaped steel fire prevention structure structure of steel building
CN212158555U (en) A kind of power line wire height measuring glasses
CN109141351A (en) The measurement method of transmission pressure and lower section obstacle spacing
CN202757989U (en) Anti-electric-shock probe rod
CN214169186U (en) Foundation pit horizontal displacement and vertical settlement monitoring device
CN202559399U (en) Transformer substation monitoring system
CN206940149U (en) A kind of construction elevator intelligent anchoring device
CN207297095U (en) Coal mine U-shaped steel support force monitoring warning device
CN216524008U (en) Outdoor infrared detector with reinforced fixation
CN218679661U (en) High and steep dangerous rock crack monitoring and mounting assembly
CN204286439U (en) A kind of combined type monitoring identity device
CN217132164U (en) Novel building settlement detection device
CN109444679A (en) A kind of 170mm insulator chain windage yaw distance calculating method
CN208907821U (en) A kind of electronic detecting device of structural fire protection equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant