CN105257309B - In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method - Google Patents

In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method Download PDF

Info

Publication number
CN105257309B
CN105257309B CN201510730729.9A CN201510730729A CN105257309B CN 105257309 B CN105257309 B CN 105257309B CN 201510730729 A CN201510730729 A CN 201510730729A CN 105257309 B CN105257309 B CN 105257309B
Authority
CN
China
Prior art keywords
soil
grouting
shield machine
clock
bin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510730729.9A
Other languages
Chinese (zh)
Other versions
CN105257309A (en
Inventor
刘方
沈水龙
张宁
吴怀娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiao Tong University
Original Assignee
Shanghai Jiao Tong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiao Tong University filed Critical Shanghai Jiao Tong University
Priority to CN201510730729.9A priority Critical patent/CN105257309B/en
Publication of CN105257309A publication Critical patent/CN105257309A/en
Application granted granted Critical
Publication of CN105257309B publication Critical patent/CN105257309B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明提供了一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,所述方法步骤包括:第一步、向土仓内注膨润土泥浆;第二步、空气置换土仓内的渣土泥浆;第三步、带压充填空隙;第四步、回填土仓;第五步、清仓换刀;第六步、恢复掘进。本发明针对砂层中无地面加固条件下土压平衡盾构机填仓换刀问题,避免了困难的超前注浆施工作业,明确了注浆施工作业方式,防止了螺旋输送机内的水泥砂浆硬化造成设备破坏,有效地减少了施工作业量;本发明施工时间短,效率高,安全性强。

The invention provides a construction method for grouting and tool change in the earth pressure balance shield machine chamber in the sand layer. The steps of the method include: the first step, injecting bentonite mud into the soil chamber; the second step, replacing the soil with air The muck slurry in the bin; the third step, filling the void under pressure; the fourth step, backfilling the soil bin; the fifth step, clearing the bin and changing the tool; the sixth step, resuming the excavation. The invention aims at the problem of earth pressure balance shield machine filling bin and tool change under the condition of no ground reinforcement in the sand layer, avoids the difficult advanced grouting construction operation, clarifies the grouting construction operation mode, and prevents the cement mortar in the screw conveyor Hardening causes equipment damage, which effectively reduces the construction workload; the invention has short construction time, high efficiency and strong safety.

Description

一种砂层中土压平衡盾构机仓内注浆换刀的施工方法A construction method for grouting and tool change in the chamber of earth pressure balance shield tunneling machine in sand layer

技术领域technical field

本发明涉及一种隧道工程技术领域的施工方法,具体地,涉及一种砂层中土压平衡盾构机仓内注浆换刀的施工方法。The invention relates to a construction method in the technical field of tunnel engineering, in particular to a construction method for grouting and tool change in an earth pressure balance shield machine chamber in a sand layer.

背景技术Background technique

近年来,随着中国城市化进程的不断推进,城市交通的拥堵问题也越来越严重。地铁隧道的建设可以解决或改善城市交通现状,因此得到了广泛的应用。这些地铁隧道需要用盾构法来建造。土压平衡盾构法是盾构法施工中常用的一种全机械施工方法,它采用土压平衡盾构机,通过盾构机前方的刀盘切削土体,并将碴土通过螺旋输送机输送出隧道外,盾构机在外壳和管片的支护下推进。在盾构推进过程中,需要不断地切割岩土,当切割的为坚硬岩层时,刀具会产生过度磨损、炸裂和卡死等破坏刀盘结构,影响正常施工作业,需及时更换刀具。由于各城市所处的地质条件和周围环境的不同,需要在各种地质条件下进行盾构机刀具更换。传统的常压换刀法、带压换刀法和地面加固后换刀法已在盾构法施工过程中得到了广泛应用。但当盾构机处于砂层,盾构机开挖面上部地面无法进行加固施工作业,且砂层自稳能力差、漏气严重时,盾构机刀具更换施工仍存在多方面的技术困难和严重的安全隐患。传统的盾构机刀具更换施工方法难于在砂层中无地面加固条件采用,产生盾构机换刀困难,施工效率低、工期长的不利局面。In recent years, with the continuous advancement of China's urbanization process, the problem of urban traffic congestion has become more and more serious. The construction of subway tunnels can solve or improve the current situation of urban traffic, so it has been widely used. These subway tunnels need to be constructed using the shield method. The earth pressure balance shield method is a fully mechanical construction method commonly used in shield tunneling construction. It uses an earth pressure balance shield machine to cut the soil through the cutter head in front of the shield machine and pass the muck through the screw conveyor. After being transported out of the tunnel, the shield machine is pushed forward under the support of the casing and segments. During the shield tunneling process, it is necessary to continuously cut rock and soil. When cutting hard rock formations, the cutter will cause excessive wear, bursting and jamming, which will damage the structure of the cutter head, affecting normal construction operations, and the cutter needs to be replaced in time. Due to the different geological conditions and surrounding environments of each city, it is necessary to replace the shield machine tool under various geological conditions. The traditional normal pressure tool change method, under pressure tool change method and ground reinforcement tool change method have been widely used in the shield tunneling construction process. However, when the shield machine is in the sand layer, the ground above the excavation surface of the shield machine cannot be reinforced, and the sand layer has poor self-stabilization ability and serious air leakage, there are still many technical difficulties and problems in the construction of shield machine tool replacement. Serious safety hazard. The traditional construction method of shield machine tool replacement is difficult to adopt in the sand layer without ground reinforcement conditions, resulting in the unfavorable situation of difficult tool change of shield machine, low construction efficiency and long construction period.

经对现有技术的文献检索发现,发明专利“[申请号为201210268682.5],发明名称:铁路股道下富水粉土粉砂地层盾构带压换刀的施工方法”,上述专利盾构机换刀施工需要采用高压旋喷桩对换刀处土体进行加固,在无地面加固条件下应用受到限制。发明专利“[申请号为201010554969.5],发明名称:一种隧道施工用盾构机换刀施工方法”,该专利虽然提出了在土仓上壁注浆口利用盾构机的注浆系统进行土仓置换填充,但未提及具体的置换填充方式和具体的置换填充施工操作方法。该专利在土仓内注水泥砂浆与输出渣土同步进行,采用水泥砂浆置换土仓内渣土过程中,无法防止螺旋输送机内的水泥砂浆硬化,造成设备破坏。该专利采用超前注浆加固盾构机上部土体,但超前注浆工序复杂,操作困难,施工速度缓慢。因此亟需一种无地面加固条件下砂层中快速、安全的土压平衡盾构机换刀施工方法。After searching the literature of the prior art, it was found that the invention patent "[application number is 201210268682.5], the name of the invention: the construction method of shield tunneling tool change under pressure in water-rich silt and silt strata under the railway track", the above-mentioned patent shield machine replacement Knife construction requires the use of high-pressure rotary grouting piles to reinforce the soil at the knife change site, and its application is limited without ground reinforcement. Invention patent "[Application No. 201010554969.5], title of the invention: a method for changing the tool of a shield machine for tunnel construction". warehouse replacement filling, but did not mention the specific replacement filling method and specific replacement filling construction operation method. In this patent, the injection of cement mortar in the soil bin and the output of muck are carried out simultaneously. During the process of replacing the muck in the soil bin with cement mortar, it is impossible to prevent the cement mortar in the screw conveyor from hardening, resulting in equipment damage. This patent uses advanced grouting to reinforce the upper soil of the shield machine, but the advanced grouting process is complicated, the operation is difficult, and the construction speed is slow. Therefore, there is an urgent need for a fast and safe method for tool change of the earth pressure balance shield machine in the sand layer without ground reinforcement.

发明内容Contents of the invention

针对现有技术中的缺陷,本发明的目的是提供一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,克服了现有技术中地面无法加固、砂层保气能力差、注浆口易堵塞、注浆施工作业方式不明确、超前注浆加固施工困难且工作量大等缺点和不足,实现砂层中无地面加固条件下土压平衡盾构机的安全换刀施工。Aiming at the defects in the prior art, the purpose of the present invention is to provide a construction method for grouting and tool change in the earth pressure balance shield machine cabin in the sand layer, which overcomes the inability of the ground to be reinforced and the gas retention capacity of the sand layer in the prior art. Poor, easy to block the grouting port, unclear grouting construction operation method, difficult construction of advance grouting reinforcement and heavy workload and other shortcomings and shortcomings, to realize the safe tool change of the earth pressure balance shield machine under the condition of no ground reinforcement in the sand layer construction.

为实现以上目的,本发明提供一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,所述施工方法包括如下步骤:In order to achieve the above object, the present invention provides a construction method for grouting and tool change in the earth pressure balance shield machine cabin in the sand layer, and the construction method includes the following steps:

第一步、向土仓内注膨润土泥浆:The first step is to inject bentonite mud into the soil bin:

通过土仓内位于3点位和12点位的球阀向土仓内注入膨润土泥浆,膨润土泥浆注入量为土仓体积的10%~15%;Inject bentonite mud into the soil bin through the ball valves located at 3 o'clock and 12 o'clock in the soil bin, and the injection amount of bentonite mud is 10% to 15% of the volume of the soil bin;

第二步、空气置换土仓内的渣土泥浆:The second step is to replace the dregs and mud in the soil bin with air:

转动螺旋输送机输出土仓内的渣土泥浆,直至渣土泥浆完全排出,即螺旋输送机不再输出渣土泥浆;输出渣土泥浆过程中,保持土仓内压力稳定在第一设定值;Turn the screw conveyor to output the muck slurry in the soil bin until the muck mud is completely discharged, that is, the screw conveyor will no longer output the muck mud; during the process of outputting the muck mud, keep the pressure in the soil bin stable at the first set value ;

第三步、带压充填空隙:The third step is to fill the gap under pressure:

土仓内压力保持在所述第一设定值,用棉絮将刀盘切口环处前盾与土体之间的缝隙塞紧,并采用堵漏灵进行封堵;The pressure in the soil bin is kept at the first set value, and the gap between the front shield at the incision ring of the cutter head and the soil body is plugged tightly with cotton wool, and the leakage sealing is used for sealing;

第四步、回填土仓:The fourth step, backfilling the soil bin:

(1)将袖阀管通过土仓壁上的球阀连接至土仓内,各球阀和袖阀管的布置如下:12点位球阀注水泥砂浆;10点位球阀接袖阀管,袖阀管固定在11点位和12点位吊耳上,注水泥浆;2点位球阀用于检验10点位球阀的注浆情况;(1) Connect the sleeve valve tube to the soil silo through the ball valve on the wall of the soil silo. The arrangement of each ball valve and sleeve valve tube is as follows: the 12-point ball valve is injected with cement mortar; the 10-point ball valve is connected to the sleeve valve tube, and the sleeve valve tube Fix it on the lugs at 11 o'clock and 12 o'clock, and inject grout; the ball valve at 2 o'clock is used to check the grouting of the ball valve at 10 o'clock;

(2)注水泥砂浆:将水泥砂浆从12点位球阀向土仓内加注;同时打开3点位和9点位球阀缓慢释放空气,直至排出水泥砂浆;关闭3点位和9点位球阀,继续加注水泥砂浆,采用1点位球阀缓慢释放空气;用水泥砂浆置换空气过程中,将土仓内压力保持在第二设定值,水泥砂浆填满土仓后,停止注水泥砂浆,关闭1点位球阀;填水泥砂浆过程中间隔一段时间后反转螺旋输送机,防止螺旋输送机卡死;(2) Cement mortar injection: fill the cement mortar from the 12 o'clock ball valve into the soil bin; simultaneously open the 3 o'clock and 9 o'clock ball valves to slowly release the air until the cement mortar is discharged; close the 3 o'clock and 9 o'clock ball valves , continue to add cement mortar, and use the 1-point ball valve to slowly release the air; during the process of replacing the air with cement mortar, keep the pressure in the soil bin at the second set value, and stop injecting cement mortar after the cement mortar fills the soil bin. Close the 1-point ball valve; reverse the screw conveyor after a period of time during the cement mortar filling process to prevent the screw conveyor from getting stuck;

(3)注水泥浆:待土仓内注入的水泥砂浆初凝后,从10点位球阀向土仓加注水泥浆;注水泥浆过程中,打开人闸泄压孔,缓慢释放仓内空气;待2点位球阀流出水泥浆后,停止注水泥浆;(3) Grout injection: after the initial setting of the cement mortar injected into the soil bin, add cement slurry to the soil bin from the ball valve at 10 o'clock; during the grout injection process, open the pressure relief hole of the man gate to slowly release the air in the bin; After the cement slurry flows out of the 2-point ball valve, stop injecting the slurry;

第五步、清仓换刀:The fifth step, clearing the warehouse and changing the tool:

回填土仓完成后第24小时开始,每隔2小时通过人闸泄压孔处判断土仓内浆液凝固强度,待土仓内浆液凝固,用风镐由下往上凿除凝固的水泥砂浆和水泥浆,把土仓清理干净,此时不凿刀盘开口;保证刀盘面完整性并从下往上进行刀具更换,换刀时稳固安装台面,拆开螺栓和自锁螺母,移除旧刀,更换新刀,上紧螺栓;From the 24th hour after the completion of backfilling the soil silo, judge the solidification strength of the grout in the soil silo through the pressure relief hole of the man gate every 2 hours. For cement slurry, clean the soil bin and do not chisel the opening of the cutter head at this time; ensure the integrity of the cutter head surface and replace the tool from bottom to top. When changing the tool, install the table firmly, disassemble the bolts and self-locking nuts, and remove the old tool , replace with a new knife, and tighten the bolts;

第六步、恢复掘进:The sixth step, resume excavation:

待盾构机刀盘上全部刀具更换完成后,盾构机恢复掘进。After all the cutters on the cutter head of the shield machine are replaced, the shield machine resumes tunneling.

优选地,第一步中,所述膨润土泥浆为化学泥浆,配浆材料为钙基膨润土和水,钙基膨润土与水的体积比为1:3。Preferably, in the first step, the bentonite slurry is chemical slurry, and the mixing materials are calcium-based bentonite and water, and the volume ratio of calcium-based bentonite to water is 1:3.

优选地,第一步中,所述点位为时钟表盘刻度上时针指向的方位。Preferably, in the first step, the point is the azimuth pointed by the hour hand on the dial scale of the clock.

优选地,第一步中,所述球阀为球体启闭件由阀杆带动,并绕球阀轴线作旋转运动的阀门。Preferably, in the first step, the ball valve is a valve in which the opening and closing member of the ball is driven by the valve stem and rotates around the axis of the ball valve.

优选地,第三步中,所述刀盘切口环为位于盾构机最前段部分带有刃口的环状结构,起开挖和挡土作用。Preferably, in the third step, the cutting ring of the cutter head is a ring-shaped structure with a cutting edge located at the frontmost part of the shield machine, which plays the role of excavation and soil retaining.

优选地,第三步中,所述前盾位于盾构前部,为圆筒形钢结构,其内部安装有用于支撑刀盘主驱动装置和螺旋输送机。Preferably, in the third step, the front shield is located at the front of the shield, and is a cylindrical steel structure, inside which is installed a main driving device for supporting the cutter head and a screw conveyor.

优选地,第三步中,所述堵漏灵为一种快速堵漏的水泥混合物,具有速凝、早强、抗渗、微膨胀、无毒无害的特点。Preferably, in the third step, the plugging spirit is a cement mixture for rapid plugging, which has the characteristics of quick setting, early strength, impermeability, micro-expansion, and non-toxic and harmless.

优选地,第四步(1)中,所述袖阀管为一种只能向管外出浆、不能向管内返浆的单向闭合装置,其由PVC外管、6分镀锌注浆内管、橡皮套、密封圈组成。Preferably, in the fourth step (1), the sleeve valve pipe is a one-way closing device that can only discharge slurry to the outside of the pipe and cannot return slurry to the inside of the pipe. It is composed of a PVC outer pipe, a 6-point galvanized grouting inner Tube, rubber sleeve, sealing ring.

优选地,第四步(1)中,所述水泥砂浆的质量配合比为水泥:砂:水=1:a:b,其中:0.5≤a≤1.5,1≤b≤2。Preferably, in the fourth step (1), the mass ratio of the cement mortar is cement:sand:water=1:a:b, wherein: 0.5≤a≤1.5, 1≤b≤2.

优选地,第四步(1)中,所述水泥浆的质量配合比为水泥:水=1:1。Preferably, in the fourth step (1), the mass ratio of the cement slurry is cement:water=1:1.

优选地,第四步(3)中,所述人闸泄压孔为能根据压力大小开闭的阀门,其布置在土仓隔板的上部。Preferably, in the fourth step (3), the pressure relief hole of the man gate is a valve that can be opened and closed according to the pressure, and it is arranged on the upper part of the earth bin partition.

优选地,第五步中,换刀过程中如有漏水,采用棉絮和堵漏灵进行封堵。Preferably, in the fifth step, if there is water leakage during the tool change process, it is blocked with cotton wool and leak blocking spirit.

优选地,第五步中,所述刀盘开口为刀盘上的空口,用于实现切削渣土排屑。Preferably, in the fifth step, the opening of the cutter head is an opening on the cutter head, which is used to realize chip removal of cutting muck.

优选地,第五步中,所述自锁螺母为一种靠摩擦力自锁防松、防振的螺母。Preferably, in the fifth step, the self-locking nut is a self-locking, anti-loosening and anti-vibration nut relying on frictional force.

优选地,第二步和第三步中:所述保持土仓内压力稳定在第一设定值,第一设定值是0.06MPa。Preferably, in the second step and the third step: said keeping the pressure in the soil bin stable at a first set value, the first set value is 0.06MPa.

优选地,第四步中:所述将土仓内压力保持在第二设定值,第二设定值是0.06~0.07MPa。Preferably, in the fourth step: maintaining the pressure in the soil bin at a second set value, the second set value is 0.06-0.07 MPa.

与现有技术相比,本发明具有如下的有益效果:Compared with the prior art, the present invention has the following beneficial effects:

本发明针对砂层中无地面加固条件下土压平衡盾构机填仓换刀问题,提供一种适用于砂层中进行无地面加固条件下的土压平衡盾构机仓内注浆换刀的施工方法,相比现有专利技术,避免了困难的超前注浆施工作业,明确了注浆施工作业方式,防止了螺旋输送机内的水泥砂浆硬化造成设备破坏,有效地减少了施工作业量;本发明施工时间短,效率高,安全性强。The invention aims at the problem of earth pressure balance shield machine filling and changing tools under the condition of no ground reinforcement in the sand layer, and provides a grouting tool change in the earth pressure balance shield machine chamber suitable for the condition of no ground reinforcement in the sand layer Compared with the existing patented technology, the advanced construction method avoids the difficult advanced grouting construction operation, clarifies the grouting construction operation method, prevents the cement mortar in the screw conveyor from hardening and causes equipment damage, and effectively reduces the construction workload. ; The present invention has short construction time, high efficiency and strong safety.

附图说明Description of drawings

通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明的其它特征、目的和优点将会变得更明显:Other characteristics, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

图1为本发明实施例中的输出渣土泥浆过程中的土压平衡盾构机示意图;Fig. 1 is a schematic diagram of an earth pressure balance shield machine in the process of outputting dregs and mud in an embodiment of the present invention;

图2为本发明实施例中的水泥砂浆置换步骤中球阀和袖阀管布置示意图;Fig. 2 is the schematic diagram of arrangement of ball valve and sleeve valve pipe in the cement mortar replacement step in the embodiment of the present invention;

图3为本发明实施例中的刀盘开口位置示意图。Fig. 3 is a schematic diagram of the opening position of the cutter head in the embodiment of the present invention.

具体实施方式Detailed ways

下面结合具体实施例对本发明进行详细说明。以下实施例将有助于本领域的技术人员进一步理解本发明,但不以任何形式限制本发明。应当指出的是,对本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进。这些都属于本发明的保护范围。The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.

如图1-3所示,本实施例提供一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,用于广州某隧道;盾构机刀盘底部深度为地下14m,停机位置上部地面为交叉路口,为防止因刀具的过度磨损、炸裂和卡死等破坏刀盘结构,影响正常施工作业,需采用填仓换刀的施工方法,保证换刀施工安全有效地进行,具体施工步骤简述如下:As shown in Figure 1-3, this embodiment provides a construction method for grouting and tool change in the earth pressure balance shield machine chamber in the sand layer, which is used in a tunnel in Guangzhou; the bottom depth of the shield machine cutter head is 14m underground, The ground above the stop position is an intersection. In order to prevent the structure of the cutter head from being damaged due to excessive wear, bursting and jamming of the cutter, which will affect the normal construction work, it is necessary to adopt the construction method of filling the warehouse and changing the tool to ensure the safe and effective construction of the tool change. The specific construction steps are briefly described as follows:

第一步、施工现场地质调查:The first step, construction site geological survey:

通过查阅地质勘查报告确定盾构机刀盘底部所处位置以下6m至上部地面的地层分布情况;调查盾构机刀盘上部地面状况(即从盾构机刀盘底面45°斜线传到地表范围上部已有建筑物或构筑物条件状况),确定是否有地面加固条件;Determine the stratum distribution from 6m below the bottom of the shield machine cutter head to the upper ground by consulting the geological survey report; investigate the ground conditions on the upper part of the shield machine cutter head (that is, from the 45° oblique line on the bottom surface of the shield machine cutter head to the surface conditions of existing buildings or structures in the upper part of the range), determine whether there are ground reinforcement conditions;

本实施例盾构机刀盘底部所处位置以下6m至上部地面的地层分布为厚度为5m的粘土层、厚度为10.5m的砂层和厚度为4.5m的素填土层,盾构机刀盘处于砂层中;粘土层的渗透系数为1.5m/d,砂层的渗透系数为10m/d;素填土层的渗透系数为0.4m/d。盾构机上部地面为交叉路口,无地面加固条件。In this embodiment, the strata from 6m below the bottom of the shield machine cutter head to the upper ground are distributed as a clay layer with a thickness of 5m, a sand layer with a thickness of 10.5m, and a plain fill layer with a thickness of 4.5m. The pan is in the sand layer; the permeability coefficient of the clay layer is 1.5m/d, the permeability coefficient of the sand layer is 10m/d; the permeability coefficient of the plain fill layer is 0.4m/d. The upper ground of the shield machine is an intersection without ground reinforcement conditions.

第二步、确定换刀方法:The second step is to determine the tool change method:

确定盾构机位于砂层中,且无地面加固条件,本条件下不能对盾构机进行常压换刀,同时砂层保气能力差,不能在砂层中进行带压换刀。所以确定采用砂层中土压平衡盾构机仓内注浆换刀的施工方法。It is determined that the shield machine is located in the sand layer and there is no ground reinforcement condition. Under this condition, the shield machine cannot be changed under normal pressure. At the same time, the gas retention capacity of the sand layer is poor, and the tool change under pressure cannot be performed in the sand layer. Therefore, it is determined to adopt the construction method of grouting and tool change in the earth pressure balance shield machine chamber in the sand layer.

第三步、向土仓内注膨润土泥浆:The third step is to inject bentonite mud into the soil bin:

通过土仓内位于3点位和12点位的球阀向土仓内注入膨润土泥浆,膨润土泥浆注入量为土仓体积的15%,即4.5m3Inject bentonite mud into the soil bin through the ball valves located at 3 o'clock and 12 o'clock in the soil bin. The amount of bentonite mud injected is 15% of the volume of the soil bin, that is, 4.5m 3 .

第四步,空气置换土仓内的渣土泥浆The fourth step is to replace the dregs and mud in the soil bin with air

转动螺旋输送机输出土仓内的渣土泥浆,直至渣土泥浆完全排出,即螺旋输送机不再输出渣土泥浆;输出渣土泥浆过程中,保持土仓内压力稳定在0.06MPa,输出渣土泥浆过程如图1所示。Turn the screw conveyor to output the muck slurry in the soil bin until the muck mud is completely discharged, that is, the screw conveyor will no longer output the muck mud; during the process of outputting the muck mud, keep the pressure in the soil bin stable at 0.06MPa, and output the dregs The soil mud process is shown in Figure 1.

第五步、带压充填空隙:The fifth step, filling the gap under pressure:

土仓内压力保持在0.06MPa,用棉絮将刀盘切口环处前盾与土体之间的缝隙塞紧,并采用堵漏灵进行封堵。The pressure in the soil bin is kept at 0.06MPa, and the gap between the front shield at the incision ring of the cutter head and the soil body is tightly plugged with cotton wool, and sealed with the leak-stopping spirit.

第六步、回填土仓,具体的:The sixth step is to backfill the soil bin, specifically:

(1)将袖阀管通过土仓壁上的球阀连接至土仓内,各球阀和袖阀管的布置如下:12点位球阀注水泥砂浆;10点位球阀接袖阀管,袖阀管固定在11点位和12点位吊耳上,注水泥浆;2点位球阀用于检验10点位球阀的注浆情况;球阀和袖阀管的布置如图2所示。(1) Connect the sleeve valve tube to the soil silo through the ball valve on the wall of the soil silo. The arrangement of each ball valve and sleeve valve tube is as follows: the 12-point ball valve is injected with cement mortar; the 10-point ball valve is connected to the sleeve valve tube, and the sleeve valve tube Fix it on the lugs at 11 o’clock and 12 o’clock, and inject grout; the ball valve at 2 o’clock is used to check the grouting of the ball valve at 10 o’clock; the arrangement of the ball valve and sleeve valve pipe is shown in Figure 2.

(2)注水泥砂浆:水泥砂浆中砂与水泥质量之比a取值为0.75,水与水泥质量之比b取值为1.18,将水泥砂浆从12点位球阀向土仓内加注;同时打开3点位和9点位球阀缓慢释放空气,直至排出水泥砂浆;关闭3点位和9点位球阀,继续加注水泥砂浆,采用1点位球阀缓慢释放空气;用水泥砂浆置换空气过程中,将土仓内压力保持在0.06MPa,水泥砂浆填满土仓后,停止注水泥砂浆,关闭1点位球阀;填水泥砂浆过程中间隔20分钟反转螺旋输送机,防止螺旋输送机卡死。(2) Cement mortar: the ratio a of sand to cement mass in the cement mortar is 0.75, the ratio b of water to cement mass is 1.18, and the cement mortar is injected into the soil bin from the ball valve at 12 o'clock; at the same time Open the 3 o'clock and 9 o'clock ball valves to slowly release the air until the cement mortar is discharged; close the 3 o'clock and 9 o'clock ball valves, continue to add cement mortar, and use the 1 o'clock ball valve to slowly release the air; replace the air with cement mortar , keep the pressure in the soil silo at 0.06MPa. After the cement mortar fills the soil silo, stop injecting cement mortar and close the 1-point ball valve; reverse the screw conveyor at intervals of 20 minutes during the cement mortar filling process to prevent the screw conveyor from getting stuck .

(3)注水泥浆:土仓内注入的水泥砂浆4小时后完成初凝,从10点位球阀向土仓加注水泥浆;注水泥浆过程中,打开人闸泄压孔,缓慢释放仓内空气;待2点位球阀流出水泥浆后,停止注水泥浆。(3) Grout injection: The cement mortar injected into the soil bin will complete the initial setting after 4 hours, and the cement mortar will be injected into the soil bin from the ball valve at 10 o'clock; during the grout injection process, the man gate pressure relief hole will be opened to slowly release the air in the bin ; After the cement slurry flows out of the ball valve at 2 o'clock, stop injecting the slurry.

第七步、清仓换刀:The seventh step, clearing the warehouse and changing the tool:

回填土仓完成后第24小时开始,每隔两小时通过人闸泻压孔处判断土仓内浆液凝固强度,回填土仓完成72小时后,土仓内浆液完全凝固;用风镐由下往上凿除凝固的水泥砂浆和水泥浆,把土仓清理干净,此时不凿刀盘开口;保证刀盘面完整性并从下往上进行刀具更换,换刀时稳固安装台面,拆开螺栓和自锁螺母,移除旧刀,更换新刀,上紧螺栓。对上部刀具进行更换时,下部已换好刀具处有水滴渗出,采用棉絮堵住下部刀具渗水处缝隙后,采用堵漏灵进行封堵,止水效果良好。清仓换刀过程中,掌子面稳定,无水位上涨现象。刀盘开口为刀盘上的空口,用于实现切削渣土排屑,其位置如图3所示。From the 24th hour after the backfilling of the soil silo, judge the solidification strength of the grout in the soil silo through the pressure relief hole of the man gate every two hours. After 72 hours of backfilling the soil silo, the slurry in the earth silo will completely solidify; Remove the solidified cement mortar and cement slurry from the top, and clean the soil bin. At this time, do not chisel the opening of the cutterhead; ensure the integrity of the cutterhead surface and replace the cutter from bottom to top. When changing the cutter, install the table firmly, remove the bolts and Self-locking nut, remove the old knife, replace with a new one, tighten the bolt. When the upper cutter was replaced, there was water seepage from the lower cutter. After using cotton wool to block the water seepage gap of the lower cutter, it was sealed with the plugging spirit, and the water-stopping effect was good. During the process of clearing the warehouse and changing the tool, the face of the pocket is stable, and there is no phenomenon of rising water level. The opening of the cutter head is an opening on the cutter head, which is used to realize the chip removal of cutting muck, and its position is shown in Figure 3.

第八步、恢复掘进:The eighth step, resume excavation:

盾构机刀盘上全部刀具更换完成后,试转螺旋输送机,螺旋输送机运行正常,盾构机恢复掘进。After all the cutters on the cutter head of the shield tunneling machine have been replaced, the screw conveyor is tested, and the screw conveyor operates normally, and the shield tunneling machine resumes excavation.

本发明针对砂层中无地面加固条件下土压平衡盾构机填仓换刀问题,提供一种适用于砂层中进行无地面加固条件下的土压平衡盾构机仓内注浆换刀的施工方法,相比现有专利技术,该方法避免了困难的超前注浆施工作业,明确了注浆施工作业方式,防止了螺旋输送机内的水泥砂浆硬化造成设备破坏,有效地减少了施工作业量;本发明施工时间短,效率高,安全性强。The invention aims at the problem of earth pressure balance shield machine filling and changing tools under the condition of no ground reinforcement in the sand layer, and provides a grouting tool change in the earth pressure balance shield machine chamber suitable for the condition of no ground reinforcement in the sand layer Compared with the existing patented technology, this method avoids the difficult advance grouting construction operation, clarifies the grouting construction operation mode, prevents the cement mortar in the screw conveyor from hardening and causes equipment damage, and effectively reduces the construction cost. Amount of work; the invention has short construction time, high efficiency and strong safety.

以上对本发明的具体实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,本领域技术人员可以在权利要求的范围内做出各种变形或修改,这并不影响本发明的实质内容。Specific embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the specific embodiments described above, and those skilled in the art may make various changes or modifications within the scope of the claims, which do not affect the essence of the present invention.

Claims (10)

1.一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,所述施工方法包括如下步骤:1. a kind of construction method of grouting in the earth pressure balance shield machine storehouse of sand layer and changing tool, it is characterized in that, described construction method comprises the steps: 第一步、向土仓内注膨润土泥浆:The first step is to inject bentonite mud into the soil bin: 通过土仓内位于3点位和12点位的球阀向土仓内注入膨润土泥浆,膨润土泥浆注入量为土仓体积的10%~15%;Inject bentonite mud into the soil bin through the ball valves located at 3 o'clock and 12 o'clock in the soil bin, and the injection amount of bentonite mud is 10% to 15% of the volume of the soil bin; 第二步、空气置换土仓内的渣土泥浆:The second step is to replace the dregs and mud in the soil bin with air: 转动螺旋输送机输出土仓内的渣土泥浆,直至渣土泥浆完全排出,即螺旋输送机不再输出渣土泥浆;输出渣土泥浆过程中,保持土仓内压力稳定在第一设定值;Turn the screw conveyor to output the muck slurry in the soil bin until the muck mud is completely discharged, that is, the screw conveyor will no longer output the muck mud; during the process of outputting the muck mud, keep the pressure in the soil bin stable at the first set value ; 第三步、带压充填空隙:The third step is to fill the gap under pressure: 土仓内压力保持在所述第一设定值,用棉絮将刀盘切口环处前盾与土体之间的缝隙塞紧,并采用堵漏灵进行封堵;The pressure in the soil bin is kept at the first set value, and the gap between the front shield at the incision ring of the cutter head and the soil body is plugged tightly with cotton wool, and the leakage sealing is used for sealing; 第四步、回填土仓:The fourth step, backfilling the soil bin: (1)将袖阀管通过土仓壁上的球阀连接至土仓内,各球阀和袖阀管的布置如下:12点位球阀注水泥砂浆;10点位球阀接袖阀管,袖阀管固定在11点位和12点位吊耳上,注水泥浆;2点位球阀用于检验10点位球阀的注浆情况;(1) Connect the sleeve valve tube to the soil silo through the ball valve on the wall of the soil silo. The arrangement of each ball valve and sleeve valve tube is as follows: the 12-point ball valve is injected with cement mortar; the 10-point ball valve is connected to the sleeve valve tube, and the sleeve valve tube Fix it on the lugs at 11 o'clock and 12 o'clock, and inject grout; the ball valve at 2 o'clock is used to check the grouting of the ball valve at 10 o'clock; (2)注水泥砂浆:将水泥砂浆从12点位球阀向土仓内加注;同时打开3点位和9点位球阀缓慢释放空气,直至排出水泥砂浆;关闭3点位和9点位球阀,继续加注水泥砂浆,采用1点位球阀缓慢释放空气;用水泥砂浆置换空气过程中,将土仓内压力保持在第二设定值,水泥砂浆填满土仓后,停止注水泥砂浆,关闭1点位球阀;填水泥砂浆过程中间隔一段时间后反转螺旋输送机,防止螺旋输送机卡死;(2) Cement mortar injection: fill the cement mortar from the 12 o'clock ball valve into the soil bin; simultaneously open the 3 o'clock and 9 o'clock ball valves to slowly release the air until the cement mortar is discharged; close the 3 o'clock and 9 o'clock ball valves , continue to add cement mortar, and use the 1-point ball valve to slowly release the air; during the process of replacing the air with cement mortar, keep the pressure in the soil bin at the second set value, and stop injecting cement mortar after the cement mortar fills the soil bin. Close the 1-point ball valve; reverse the screw conveyor after a period of time during the cement mortar filling process to prevent the screw conveyor from getting stuck; (3)注水泥浆:待土仓内注入的水泥砂浆初凝后,从10点位球阀向土仓加注水泥浆;注水泥浆过程中,打开人闸泄压孔,缓慢释放仓内空气;待2点位球阀流出水泥浆后,停止注水泥浆;(3) Grout injection: after the initial setting of the cement mortar injected into the soil bin, add cement slurry to the soil bin from the ball valve at 10 o'clock; during the grout injection process, open the pressure relief hole of the man gate to slowly release the air in the bin; After the cement slurry flows out of the 2-point ball valve, stop injecting the slurry; 第五步、清仓换刀:The fifth step, clearing the warehouse and changing the tool: 回填土仓完成后第24小时开始,每隔2小时后通过人闸泄压孔处判断土仓内浆液凝固强度,待土仓内浆液凝固后,用风镐由下往上凿除凝固的水泥砂浆和水泥浆,把土仓清理干净,此时不凿刀盘开口;保证刀盘面完整性并从下往上进行刀具更换,换刀时稳固安装台面,拆开螺栓和自锁螺母,移除旧刀,更换新刀,上紧螺栓;From the 24th hour after the completion of backfilling the soil silo, judge the solidification strength of the grout in the soil silo through the pressure relief hole of the man gate every 2 hours. Mortar and cement slurry, clean the soil bin, do not chisel the opening of the cutter head at this time; ensure the integrity of the cutter head surface and replace the tool from bottom to top. When changing the tool, install the table firmly, disassemble the bolts and self-locking nuts, remove Replace the old knife with a new one and tighten the bolts; 第六步、恢复掘进:The sixth step, resume excavation: 待盾构机刀盘上全部刀具更换完成后,盾构机恢复掘进。After all the cutters on the cutter head of the shield machine are replaced, the shield machine resumes tunneling. 2.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第一步中,所述膨润土泥浆为化学泥浆,配浆材料为钙基膨润土和水,钙基膨润土与水的体积比为1:3。2. the construction method of grouting in the earth pressure balance shield machine chamber of a kind of sand layer according to claim 1, is characterized in that, in the first step, described bentonite mud is chemical mud, and grouting material Calcium-based bentonite and water, the volume ratio of calcium-based bentonite to water is 1:3. 3.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第一步中:3. the construction method of grouting in the earth pressure balance shield machine chamber of a kind of sand layer according to claim 1, is characterized in that, in the first step: 所述点位为时钟表盘刻度上时针指向的方位;The point is the position pointed by the hour hand on the scale of the clock dial; 所述球阀为球体启闭件由阀杆带动,并绕球阀轴线作旋转运动的阀门。The ball valve is a valve in which the opening and closing part of the ball is driven by the valve stem and rotates around the axis of the ball valve. 4.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第三步中:4. the construction method of grouting and tool change in the earth pressure balance shield machine chamber in a kind of sand layer according to claim 1, is characterized in that, in the third step: 所述刀盘切口环为位于盾构机最前段部分带有刃口的环状结构;The cutting ring of the cutter head is a ring structure with a cutting edge at the frontmost part of the shield machine; 所述前盾位于盾构前部,为圆筒形钢结构,其内部安装有用于支撑刀盘主驱动装置和螺旋输送机。The front shield is located at the front of the shield, and is a cylindrical steel structure, inside which is installed a main drive device for supporting the cutter head and a screw conveyor. 5.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第四步(1)中:5. the construction method of grouting tool change in a kind of earth pressure balance shield machine cabin in sand layer according to claim 1, it is characterized in that, in the 4th step (1): 所述水泥砂浆的质量配合比为水泥:砂:水=1:a:b,其中:0.5≤a≤1.5,1≤b≤2;The mass ratio of the cement mortar is cement:sand:water=1:a:b, wherein: 0.5≤a≤1.5, 1≤b≤2; 所述水泥浆的质量配合比为水泥:水=1:1。The mass mixing ratio of the cement slurry is cement:water=1:1. 6.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第四步(1)中,所述袖阀管为一种只能向管外出浆、不能向管内返浆的单向闭合装置,其由PVC外管、6分镀锌注浆内管、橡皮套、密封圈组成。6. The construction method of grouting and tool change in the earth pressure balance shield machine cabin in a kind of sand layer according to claim 1, characterized in that, in the fourth step (1), the sleeve valve pipe is a A one-way closing device that can only discharge slurry to the outside of the tube and cannot return slurry to the inside of the tube. It is composed of a PVC outer tube, a 6-point galvanized grouting inner tube, a rubber sleeve, and a sealing ring. 7.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第四步(3)中,所述人闸泄压孔为能根据压力大小开闭的阀门,其布置在土仓隔板的上部。7. the construction method of grouting tool change in the earth pressure balance shield machine cabin in a kind of sand layer according to claim 1, it is characterized in that, in the 4th step (3), described man gate pressure relief hole is The valve that can be opened and closed according to the pressure is arranged on the upper part of the earth bin partition. 8.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第五步中,换刀过程中如有漏水,采用棉絮和堵漏灵进行封堵。8. The construction method of grouting tool change in the earth pressure balance shield machine cabin in a kind of sand layer according to claim 1, it is characterized in that, in the fifth step, if there is water leakage during the tool change process, use cotton wool and Plugging spirit is used for sealing. 9.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第五步中,所述刀盘开口为刀盘上的空口,用于实现切削渣土排屑;第五步中,所述自锁螺母为一种靠摩擦力自锁防松、防振的螺母。9. The construction method of grouting and tool change in the earth pressure balance shield machine chamber in a sand layer according to claim 1, characterized in that, in the fifth step, the opening of the cutter head is an opening on the cutter head , used to realize chip removal of cutting slag; in the fifth step, the self-locking nut is a self-locking, anti-loosening and anti-vibration nut relying on frictional force. 10.根据权利要求1所述的一种砂层中土压平衡盾构机仓内注浆换刀的施工方法,其特征在于,第二步和第三步中:所述保持土仓内压力稳定在第一设定值,第一设定值是0.06MPa;10. The construction method of grouting and tool change in the earth pressure balance shield machine chamber in a sand layer according to claim 1, characterized in that, in the second step and the third step: said maintaining the pressure in the earth chamber Stable at the first set value, the first set value is 0.06MPa; 第四步中:所述将土仓内压力保持在第二设定值,第二设定值是0.06~0.07MPa。In the fourth step: maintaining the pressure in the soil bin at the second set value, the second set value is 0.06-0.07 MPa.
CN201510730729.9A 2015-10-30 2015-10-30 In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method Expired - Fee Related CN105257309B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510730729.9A CN105257309B (en) 2015-10-30 2015-10-30 In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510730729.9A CN105257309B (en) 2015-10-30 2015-10-30 In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method

Publications (2)

Publication Number Publication Date
CN105257309A CN105257309A (en) 2016-01-20
CN105257309B true CN105257309B (en) 2018-02-09

Family

ID=55097199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510730729.9A Expired - Fee Related CN105257309B (en) 2015-10-30 2015-10-30 In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method

Country Status (1)

Country Link
CN (1) CN105257309B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105952461B (en) * 2016-06-17 2017-12-29 西南交通大学 A kind of experimental rig and method for being used to simulate earth pressure balanced shield, EPBS construction sediment improvement
CN106837360A (en) * 2017-02-13 2017-06-13 中铁十九局集团轨道交通工程有限公司 Upper-soft lower-hard ground shield machine open a position tool changing when mud film construct mechanism and construction method
CN108266195A (en) * 2018-01-11 2018-07-10 中铁工程装备集团机电工程有限公司 A kind of shield machine soil storehouse ball valve slag cleaning device
CN108571327B (en) * 2018-05-16 2023-11-17 华东交通大学 Rapid compensation device for dregs in shield machine soil cabin and working method thereof
CN111742626B (en) * 2020-07-10 2022-04-12 无锡市东生建设工程有限公司 Municipal works underground soil layer equipment of changing soil

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4222677B2 (en) * 1999-04-05 2009-02-12 中部電力株式会社 Cutter pull-in mechanism of shield machine
CN102052079B (en) * 2010-11-19 2013-03-13 中铁一局集团有限公司 Method for exchanging tool of shield machine for tunnel construction
CN102168565B (en) * 2011-03-21 2013-01-23 广东水电二局股份有限公司 Soil reinforcing method for realizing normal-pressure cabin opening of shield machine
CN102536253B (en) * 2011-12-30 2014-11-12 广州轨道交通建设监理有限公司 Construction method of earth cabin back filling and cabin entering operation during earth pressure shielding
CN204000876U (en) * 2014-07-23 2014-12-10 常州市奥达电子有限公司 Resistance to distortion sleeve valve pipe

Also Published As

Publication number Publication date
CN105257309A (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN105257308B (en) Native storehouse mortar mixes the shield machine tool changing construction method of bentonite mud film in a kind of layer of sand
CN105257309B (en) In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method
CN103291325B (en) The preventing control method of Coal-mining Above Confined-water floor strata gushing water
CN108049878B (en) A kind of powder land floor shield cuts the construction method that stake is crossed the river
CN105736004B (en) Shield is opened a position pressurize panelling construction method with weighing apparatus shield mud air pressure
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
CN112664221A (en) Pipe jacking construction method for complex geological formation
CN105569665B (en) Balancing earth-pressure shielding machine soil mass consolidation tool changing construction method outside the native storehouse in layer of sand
CN105626086B (en) A method of the Shield Construction Method Used in boulder bed
CN103089276A (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN205260041U (en) Method of freezing supporting construction is spouted soon to level
CN106437796A (en) Rock stratum shield tunnel end reinforcing structure and reinforcing method
CN105257306B (en) A kind of tool changing construction method of filling in barn reinforced in shield cabin
CN110985016B (en) Quick receiving method of shield machine suitable for hard rock stratum in mine tunnel
CN217518646U (en) A Wrecker Tunnel Structure Underpassing an Existing Station
CN108979646B (en) Method for replacing soil bin medium of shield tunneling machine in freezing process
CN204099720U (en) The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used
CN107829747B (en) Construction method suitable for shallow-buried underground excavation tunnel in expansive soil area
CN113756841A (en) A kind of advance grouting method in the tunnel for shield construction in upper soft and lower hard stratum
CN115875038A (en) A horizontal freezing reinforcement structure and construction method in a shield tunnel
CN115012963A (en) An excavation method based on pressure relief and water stop of the stratum with fractured fissure water development in the section
Sturk et al. Summary of the first TBM drive at the Hallandsås project
Schmall et al. Ground freezing—a viable and versatile construction technique
Qi et al. Risk mitigation and construction control for effective underwater recovery of an EPB shield: a case study of the first metro tunnel in Tel Aviv
CN205260039U (en) Wall reinforced structure is freezed to shield tunnel end hemisphere

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant