[go: up one dir, main page]

CN103089276A - Deep-shallow hole and high-low pressure coupling grouting technology - Google Patents

Deep-shallow hole and high-low pressure coupling grouting technology Download PDF

Info

Publication number
CN103089276A
CN103089276A CN2013100301536A CN201310030153A CN103089276A CN 103089276 A CN103089276 A CN 103089276A CN 2013100301536 A CN2013100301536 A CN 2013100301536A CN 201310030153 A CN201310030153 A CN 201310030153A CN 103089276 A CN103089276 A CN 103089276A
Authority
CN
China
Prior art keywords
hole
grouting
shallow
deep
low pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100301536A
Other languages
Chinese (zh)
Other versions
CN103089276B (en
Inventor
韩立军
孟庆彬
宗义江
董亚宁
杨灵
范加冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201310030153.6A priority Critical patent/CN103089276B/en
Publication of CN103089276A publication Critical patent/CN103089276A/en
Application granted granted Critical
Publication of CN103089276B publication Critical patent/CN103089276B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种深浅孔与高低压耦合注浆工艺,适用于矿山巷道,隧道等地下工程的注浆加固,尤其适用于巷道软弱破碎围岩的注浆加固。耦合注浆工艺先用钻头在围岩体上进行钻孔,先钻出一浅孔;然后在所述浅孔内插入孔口管,并进行封孔,所述孔口管靠近岩面端连接球形阀门,球形阀门与注浆装置连接;在所述孔口管安设完成后,并对围岩岩面进行复喷;通过孔口管进行低压浅孔注浆;低压浅孔注浆后,卸掉注浆装置,采用钻头在上述孔口管内进行扫孔,形成深孔;再通过孔口管进行高压深孔注浆;注浆完成后对围岩进行再次喷浆,以形成对孔口管的保护。其工艺简单、安全、成本低、加固效果显著。

Figure 201310030153

The invention discloses a grouting technology coupled with deep and shallow holes and high and low pressure, which is suitable for grouting reinforcement of mine roadways, tunnels and other underground projects, and is especially suitable for grouting reinforcement of weak and broken surrounding rocks in roadways. In the coupling grouting process, a drill bit is used to drill a hole in the surrounding rock mass, and a shallow hole is first drilled; then an orifice pipe is inserted into the shallow hole, and the hole is sealed, and the orifice pipe is connected near the rock surface Spherical valve, the spherical valve is connected with the grouting device; after the orifice pipe is installed, respray the surrounding rock surface; perform low-pressure shallow hole grouting through the orifice pipe; after low-pressure shallow hole grouting, Remove the grouting device, use the drill bit to sweep the hole in the above-mentioned orifice pipe to form a deep hole; then perform high-pressure deep hole grouting through the orifice pipe; after the grouting is completed, spray the surrounding rock again to form a pair of orifice tube protection. The process is simple, safe, low in cost and remarkable in reinforcing effect.

Figure 201310030153

Description

深浅孔与高低压耦合注浆工艺Deep and shallow holes and high and low pressure coupling grouting technology

技术领域 technical field

本发明涉及一种注浆工艺,尤其是一种适用于巷道软弱破碎围岩的注浆加固的深浅孔与高低压耦合注浆工艺。属矿山巷道,隧道等地下工程注浆加固技术领域。 The invention relates to a grouting process, in particular to a deep and shallow hole and high and low pressure coupling grouting process suitable for grouting reinforcement of weak and broken surrounding rocks in roadways. It belongs to the technical field of grouting reinforcement for underground engineering such as mine roadways and tunnels.

背景技术 Background technique

随着大规模的矿山开采和采深的加大,软弱破碎围岩巷道支护问题日益突出,如淮北、淮南、龙口、徐州、铁法、肥城、枣庄等地区的矿区。软岩巷道一般具有围岩松软破碎、流变性大; 来压时间快、初期变形量大、持续时间长; 围岩遇水易于崩解、强度急剧降低等特点。如采用不适当的维护措施,巷道围岩变形愈加剧烈,最终将导致巷道破坏,探索软岩巷道合理支护方式成为亟待解决的重大问题。  With the increase of large-scale mining and mining depth, the problem of weak and broken surrounding rock roadway support has become increasingly prominent, such as mining areas in Huaibei, Huainan, Longkou, Xuzhou, Tiefa, Feicheng, Zaozhuang and other regions. Soft rock roadways generally have the characteristics of soft and broken surrounding rocks, large rheology; fast pressure time, large initial deformation, and long duration; surrounding rocks are easy to disintegrate when exposed to water, and their strength decreases sharply. If inappropriate maintenance measures are adopted, the deformation of the surrounding rock of the roadway will become more severe, which will eventually lead to the destruction of the roadway. Exploring a reasonable support method for soft rock roadways has become a major problem that needs to be solved urgently. the

砌碹、金属支架等均属于被动支护,若仅依靠支护本身强度,很难承受高地应力的作用。锚杆、锚索虽被认为是主动支护,但因锚固的岩体为一些破碎或松散岩体,围岩的可锚性较差,很难满足深部软岩巷道的支护要求。此外,砌碹、金属支架成本高,施工速度慢、变形或破坏后维修较为困难,而大直径长锚杆、长锚索等支护方式既需专用设备,且大量使用时支护成本高,施工速度慢,不能大量用于我国软岩巷道支护。 The masonry and metal supports are all passive supports, and it is difficult to withstand the high ground stress if only relying on the strength of the support itself. Anchor rods and anchor cables are considered active support, but because the anchored rock mass is some broken or loose rock mass, the anchorability of the surrounding rock is poor, and it is difficult to meet the support requirements of deep soft rock roadways. In addition, the cost of masonry and metal supports is high, the construction speed is slow, and it is difficult to maintain after deformation or damage. Support methods such as large-diameter long anchor rods and long anchor cables require special equipment, and support costs are high when used in large quantities. The construction speed is slow, and it cannot be widely used in soft rock roadway support in my country.

传统注浆加固采用浅孔注浆,或浅孔与深孔注浆管间隔布置,打孔、安装注浆管的数量多,浅孔与深孔注浆时压力难以把握,若注浆压力太小,则向破碎围岩中注入的浆液太小,就不能有效地将破碎围岩胶结起来,若注浆压力太大,往往造成对岩体的劈裂破碎,在围岩周边形成裂隙,造成浆液从围岩表面溢出。 Traditional grouting reinforcement adopts shallow hole grouting, or shallow hole and deep hole grouting pipes are arranged at intervals, the number of drilling and installation of grouting pipes is large, and the pressure is difficult to control during shallow hole and deep hole grouting. If the grouting pressure is too high If the injection pressure is too small, the grout injected into the broken surrounding rock is too small, and the broken surrounding rock cannot be cemented effectively. If the grouting pressure is too high, the rock mass will often be split and broken, and cracks will be formed around the surrounding rock, resulting in The slurry spilled from the surface of the surrounding rock.

综上所述,开发一种高效、可操作、经济的,针对巷道等地下工程软弱破碎围岩进行加固的注浆工艺很有必要。 To sum up, it is necessary to develop an efficient, operable, and economical grouting process for reinforcing weak and broken surrounding rock in underground engineering such as roadways.

发明内容 Contents of the invention

技术问题:本发明的目的是克服已有技术中的不足,提供一种工艺简单、安全、成本低、加固效果显著的深浅孔与高低压耦合注浆工艺。  Technical problem: The purpose of the present invention is to overcome the deficiencies in the prior art, and provide a simple, safe, low-cost, and remarkable reinforcement effect coupling grouting process for deep and shallow holes and high and low pressure. the

技术方案:本发明的深浅孔与高低压耦合注浆工艺,包含以下步骤: Technical solution: The deep and shallow hole and high and low pressure coupling grouting process of the present invention includes the following steps:

a、首先在围岩体内钻一个浅孔; a. First drill a shallow hole in the surrounding rock body;

b、在浅孔内插入孔口,并进行封孔,将孔口管外露端与注浆管相连接; b. Insert the orifice in the shallow hole, seal the hole, and connect the exposed end of the orifice pipe with the grouting pipe;

c、向孔口周围的岩面喷射混凝土,使孔口周围的岩面对孔口管形成封闭层; c. Spray concrete to the rock surface around the orifice, so that the rock surface around the orifice forms a sealing layer for the orifice pipe;

d、打开注浆控制阀门,通过孔口管向浅孔内进行压力控制在2MPa~3MPa的低压浅孔注浆,使浆液充分渗入到浅孔周围的岩土体内; d. Open the grouting control valve, and carry out low-pressure shallow hole grouting with pressure controlled at 2MPa~3MPa into the shallow hole through the orifice pipe, so that the grout can fully penetrate into the rock and soil around the shallow hole;

e、低压浅孔注浆完成后,低压浅孔注浆3~7天后,卸掉注浆管,采用钻头经孔口管向内进行扫孔,将浅孔改变为一个深孔;深孔的深度根据围岩松动圈大小及围岩破碎程度确定; e. After the low-pressure shallow hole grouting is completed, 3 to 7 days after the low-pressure shallow hole grouting, remove the grouting pipe, use the drill bit to sweep the hole inward through the orifice pipe, and change the shallow hole into a deep hole; the deep hole The depth is determined according to the size of the surrounding rock loose circle and the degree of fragmentation of the surrounding rock;

f、深孔注浆完成后退钻,连接注浆管,通过孔口管向深孔内进行浆液压力控制在3MPa~5MPa的高压深孔注浆,使浆液充分渗入到深孔周围的岩土体内,并与浅孔周围的浆液耦合,加固岩土体,注浆材料以稀水泥浆液为主,若围岩裂隙较小,采用超细水泥或化学浆液; f. After the deep hole grouting is completed, drill back, connect the grouting pipe, and carry out high-pressure deep hole grouting with the grout pressure controlled at 3MPa~5MPa into the deep hole through the orifice pipe, so that the grout can fully penetrate into the rock and soil around the deep hole , and coupled with the grout around the shallow hole to strengthen the rock and soil mass, the grouting material is mainly dilute cement grout, if the cracks in the surrounding rock are small, use ultra-fine cement or chemical grout;

g、深孔注浆完成3~7天后,卸掉注浆管,对围岩进行再次复喷混凝土,复喷混凝土的厚度为30mm~50mm,对围岩进行封闭,防止注入孔内的浆液渗出,并保证孔口管(6)的外露长度不少于30 mm。 g. After 3~7 days after the deep hole grouting is completed, the grouting pipe is removed, and the surrounding rock is resprayed with concrete. The thickness of the resprayed concrete is 30mm~50mm, and the surrounding rock is sealed to prevent the grout in the injection hole from seeping out, and ensure that the exposed length of the orifice pipe (6) is not less than 30 mm.

所述的浅孔深度为2000mm~3000mm,浅孔直径为40mm~60mm; The depth of the shallow hole is 2000mm~3000mm, and the diameter of the shallow hole is 40mm~60mm;

所述的孔口管长度为500mm~1000mm,直径为30mm~40mm; The length of the orifice tube is 500mm~1000mm, and the diameter is 30mm~40mm;

所述喷射混凝土的强度等级为C25~C30; The strength grade of the shotcrete is C25~C30;

所述低压浅孔注浆浆液采用水泥浆液或水泥-水玻璃复合浆液; The low-pressure shallow hole grouting slurry adopts cement slurry or cement-water glass composite slurry;

所述深孔的深度为5000mm~6000mm,钻孔直径为20mm~30mm。 The depth of the deep hole is 5000mm~6000mm, and the drilling diameter is 20mm~30mm.

有益效果:本发明针对破碎松软围岩、大松动圈围岩注浆效果尤为显著,首先,通过低压浅孔与高压深孔分次注浆的有效结合,采用低压浅孔与高压深孔同管分次注浆,对破碎严重的松动圈外围进行加固,先通过低压浅孔充填注浆,采用较小的注浆压力,保证喷层不破裂防止浆液溢出,将浅部围岩中的裂隙、缝隙充填起来,相当于形成一个较厚的止浆墙,可为深孔高压注浆提供保证;之后再采用较高的注浆压力,进行高压深孔注浆,通过高压深孔注浆对深部围岩细微裂隙进行注浆加固,扩大注浆加固体的范围,将松动圈范围内的破碎围岩体都胶结起来,提供围岩的固有强度与稳定性。从根本上改变破碎围岩的力学特性,提高其自承能力;另外,在结合锚杆(索)加固后,将锚杆压缩拱、锚索深部承载圈等形成的内外圈承载结构有效地组合在一起,最终形成一个高强度、高刚度的多层锚壳组合拱结构,扩大了支护体系的承载范围,共同维持了巷道软弱破碎围岩的长期稳定与安全。 Beneficial effects: the present invention has a particularly remarkable grouting effect on broken soft surrounding rocks and large loose surrounding rocks. First, through the effective combination of low-pressure shallow holes and high-pressure deep holes for grouting in stages, low-pressure shallow holes and high-pressure deep holes are used in the same pipe The grouting is carried out in stages to reinforce the periphery of the severely broken loose circle. First, fill the grouting through low-pressure shallow holes, and use a small grouting pressure to ensure that the sprayed layer does not break and prevent the grout from overflowing. The cracks in the shallow surrounding rock, Filling the gap is equivalent to forming a thicker grouting wall, which can provide guarantee for deep hole high-pressure grouting; then use higher grouting pressure to carry out high-pressure deep-hole grouting, and use high-pressure deep-hole grouting to repair the deep hole. The fine cracks in the surrounding rock are reinforced by grouting, the scope of the grouting reinforcement is expanded, and the broken surrounding rock bodies within the loosening circle are cemented together to provide the inherent strength and stability of the surrounding rock. Fundamentally change the mechanical properties of the broken surrounding rock and improve its self-supporting capacity; in addition, after strengthening with the anchor rod (cable), the inner and outer ring bearing structures formed by the compression arch of the anchor rod and the deep bearing ring of the anchor cable are effectively combined Together, a high-strength, high-rigidity multi-layer anchor-shell composite arch structure is finally formed, which expands the bearing range of the support system and jointly maintains the long-term stability and safety of the weak and broken surrounding rock of the roadway.

附图说明:Description of drawings:

图1为本发明的钻孔示意图; Fig. 1 is the drilling schematic diagram of the present invention;

图2为本发明的钻孔安放套管示意图; Fig. 2 is a schematic diagram of a borehole placement casing of the present invention;

图3为本发明的浅孔注浆示意图; Fig. 3 is the shallow hole grouting schematic diagram of the present invention;

图4为本发明的深孔形成示意图; Fig. 4 is a schematic diagram of deep hole formation of the present invention;

图5为本发明的深孔注浆示意图; Fig. 5 is the deep hole grouting schematic diagram of the present invention;

图6为本发明喷射混凝土封孔示意图。 Fig. 6 is a schematic diagram of sprayed concrete hole sealing according to the present invention.

图中:1-钻机,2-钻杆,3-围岩体,4-钻头,5-快速接头,6-孔口管,7-锚固剂,8-混凝土,9-浅孔,10-浆液,11-注浆软管,12-进浆阀,13-泄压阀,14-浆液扩散区域,15-深孔,16-封孔混凝土。 In the figure: 1-drilling machine, 2-drill pipe, 3-surrounding rock mass, 4-drill bit, 5-quick joint, 6-orifice pipe, 7-anchor agent, 8-concrete, 9-shallow hole, 10-slurry , 11-grouting hose, 12-slurry valve, 13-pressure relief valve, 14-slurry diffusion area, 15-deep hole, 16-sealed concrete.

具体实施方式:Detailed ways:

下面结合附图对本发明的一个实施例作进一步的描述: An embodiment of the present invention will be further described below in conjunction with accompanying drawing:

本发明的深浅孔与高低压耦合注浆工艺: The deep and shallow hole and high and low pressure coupling grouting process of the present invention:

a、启动钻机1,使带有钻头4的钻杆2在围岩体3内钻一个浅孔9,钻孔深度根据松动圈大小及围岩破碎程度而定,所述的浅孔9深度为2000mm~3000mm,浅孔直径为40mm~60mm; A, start drilling rig 1, make the drilling rod 2 that has drill bit 4 drill a shallow hole 9 in surrounding rock body 3, drilling depth is determined according to the loose circle size and surrounding rock fragmentation degree, and described shallow hole 9 depth is 2000mm~3000mm, the shallow hole diameter is 40mm~60mm;

b、在浅孔9内插入孔口管6,并进行封孔,采用锚固剂7固定,并用丝绵或快硬水泥等进行封孔,孔口管6的长度为500mm~1000mm,直径为30mm~40mm,采用钢管加工制作,孔口管6的外露端连接进浆阀12、泄压阀13和快速接头5,且进浆阀12与注浆软管11连接; b. Insert the orifice pipe 6 into the shallow hole 9, and seal the hole, fix it with anchoring agent 7, and seal the hole with silk floss or rapid hardening cement, etc., the length of the orifice pipe 6 is 500mm~1000mm, and the diameter is 30mm~ 40mm, made of steel pipe, the exposed end of the orifice pipe 6 is connected to the grout valve 12, the pressure relief valve 13 and the quick connector 5, and the grout valve 12 is connected to the grouting hose 11;

c、在孔口管6安设完成后,对岩面进行复喷,向孔口周围的岩面喷射混凝土8,使孔口周围的岩面对孔口管6形成封闭层;所述喷射混凝土8的强度等级为C25~C30,复喷混凝土厚度30mm~50mm,并保证孔口管6外露长度不少于30 mm,以便后期进行注浆加固; c. After the orifice pipe 6 is installed, the rock surface is sprayed again, and the rock surface around the orifice is sprayed with concrete 8, so that the rock surface around the orifice forms a sealing layer for the orifice pipe 6; the sprayed concrete The strength grade of 8 is C25~C30, the thickness of the resprayed concrete is 30mm~50mm, and the exposed length of the orifice pipe 6 is not less than 30 mm, so as to facilitate grouting reinforcement in the later stage;

d、进行低压浅孔注浆,连接注浆装置注浆软管11、进浆阀12,然后启动注浆泵,打开进浆阀12,通过孔口管6向浅孔9内进行低压浅孔注浆,注浆压力控制在2MPa~3MPa,使浆液充分渗入到浅孔9周围的围岩体3内;通过浆液10扩散充填裂隙,形成浆液扩散区域14,达到加固围岩体3的目的,所述低压浅孔注浆浆液采用水泥浆液或水泥-水玻璃复合浆液; d. Perform low-pressure shallow hole grouting, connect the grouting device grouting hose 11 and the grouting valve 12, then start the grouting pump, open the grouting valve 12, and carry out low-pressure shallow holes through the orifice pipe 6 into the shallow hole 9 Grouting, the grouting pressure is controlled at 2MPa~3MPa, so that the grout fully penetrates into the surrounding rock mass 3 around the shallow hole 9; the grout 10 is diffused to fill the cracks, forming a grout diffusion area 14, and achieving the purpose of reinforcing the surrounding rock mass 3, The low-pressure shallow hole grouting slurry adopts cement slurry or cement-water glass composite slurry;

e、低压浅孔注浆完成后,待浆液固化3~7天后,卸掉注浆管,采用钻头经孔口管6向内进行扫孔,将浅孔9改变为一个深孔15,深孔15的深度根据围岩松动圈大小及围岩破碎程度确定;所述深孔15的深度为5000mm~6000mm,钻孔直径为20mm~30mm; e. After the low-pressure shallow hole grouting is completed, after the grout has solidified for 3 to 7 days, remove the grouting pipe, use the drill bit to sweep the hole inward through the orifice pipe 6, and change the shallow hole 9 into a deep hole 15, and the deep hole The depth of 15 is determined according to the size of the surrounding rock loose circle and the degree of fragmentation of the surrounding rock; the depth of the deep hole 15 is 5000mm ~ 6000mm, and the borehole diameter is 20mm ~ 30mm;

f、深孔注浆完成后退钻,连接注浆管,通过孔口管6向深孔15内进行浆液压力控制在3MPa~5MPa的高压深孔注浆,使浆液充分渗入到深孔15周围的围岩体3内,并与浅孔9周围的浆液耦合,形成浆液扩散区域14,注浆材料以稀水泥浆液为主,若围岩裂隙较小,采用超细水泥或化学浆液; f. After the deep hole grouting is completed, drill back, connect the grouting pipe, and carry out high-pressure deep hole grouting with the grout pressure controlled at 3MPa~5MPa into the deep hole 15 through the orifice pipe 6, so that the grout can fully penetrate into the surroundings of the deep hole 15. In the surrounding rock body 3, it is coupled with the grout around the shallow hole 9 to form a grout diffusion area 14. The grouting material is mainly dilute cement grout. If the cracks in the surrounding rock are small, use ultra-fine cement or chemical grout;

g、深孔15注浆完成3 ~7天后,卸掉注浆管,对围岩进行再次复喷混凝土8,复喷混凝土的厚度为30mm~50mm,对围岩进行封闭,防止注入孔内的浆液渗出,并保证孔口管6的外露长度不少于30 mm。 g. After 3 to 7 days after the grouting of the deep hole 15 is completed, the grouting pipe is removed, and the surrounding rock is re-sprayed with concrete 8. The thickness of the re-sprayed concrete is 30mm~50mm, and the surrounding rock is sealed to prevent the injection hole. The slurry seeps out, and the exposed length of the orifice pipe 6 is guaranteed to be no less than 30 mm.

以上所述仅是本发明的优选实施方式,应当指出,对于在本技术领域的技术工人来说,在不脱离本发明技术原理前提下,还可以做出若干改进或替换,这些改进或替换也应视为本发明的保护范围。 The above description is only a preferred embodiment of the present invention, and it should be pointed out that for skilled workers in this technical field, without departing from the technical principle of the present invention, some improvements or replacements can also be made, and these improvements or replacements can also be made. It should be regarded as the protection scope of the present invention.

Claims (6)

1. a depth hole and high-low pressure coupling grouting process, is characterized in that, comprises following steps:
A, at first bore a shallow bore hole (9) in country rock body (3);
B, at shallow bore hole (9) interpolation man-hole opening pipe (6), and carry out sealing of hole, orifice tube (6) exposed junction is connected with Grouting Pipe;
C, the scar sprayed mortar (8) around to the aperture make the scar around the aperture form confining bed to orifice tube (6);
D, open the slip casting by-pass valve control, carry out the low pressure Shallow hole grouting that pressure is controlled at 2MPa ~ 3MPa by orifice tube (6) in shallow bore hole (9), slurries are fully penetrated in shallow bore hole (9) Rock And Soil (14) on every side;
After e, low pressure Shallow hole grouting are completed, after slurries solidify 3 ~ 7 days, lay down Grouting Pipe, adopt drill bit inwardly to carry out cleaning bottom of hole through orifice tube (6), shallow bore hole (9) is changed into a deep hole (15), and the degree of depth of deep hole (15) is determined according to wall rock loosening ring size and rock crusher degree;
F, deep hole grouting are completed and are retreated brill, connect Grouting Pipe, carry out the high pressure deep hole grouting that slurries pressure is controlled at 3MPa ~ 5MPa by orifice tube (6) in deep hole (15), slurries are fully penetrated in deep hole (15) Rock And Soil (14) on every side, and be coupled with shallow bore hole (9) slurries on every side, reinforce Rock And Soil (14), injecting paste material is take cement water grout liquid as main, if wall-rock crack is less, adopt superfine cement or chemical grout;
After g, deep hole (15) slip casting are completed 3 ~ 7 days, lay down Grouting Pipe, country rock is carried out again pneumatically placed concrete (8) again, the thickness of multiple pneumatically placed concrete is 30mm ~ 50mm, country rock is sealed, prevent that the slurries in injection hole from oozing out, and guarantee that the protruded length of orifice tube (6) is no less than 30 mm.
Depth hole according to claim 1 and high-low pressure the coupling grouting process, it is characterized in that: described shallow bore hole (9) degree of depth is 2000mm ~ 3000mm, and the shallow bore hole diameter is 40mm ~ 60mm.
Depth hole according to claim 1 and high-low pressure the coupling grouting process, it is characterized in that: described orifice tube (6) length is 500mm ~ 1000mm, and diameter is 30mm ~ 40mm.
Depth hole according to claim 1 and high-low pressure the coupling grouting process, it is characterized in that: the strength grade of described sprayed mortar (8) is C25 ~ C30.
5. depth hole according to claim 1 and high-low pressure coupling grouting process, is characterized in that: described low pressure Shallow hole grouting slurries employing cement grout or cement-sodium silicate compound slurry.
Depth hole according to claim 1 and high-low pressure the coupling grouting process, it is characterized in that: the degree of depth of described deep hole (15) is 5000mm ~ 6000mm, bore diameter is 20mm ~ 30mm.
CN201310030153.6A 2013-01-28 2013-01-28 Deep-shallow hole and high-low pressure coupling grouting technology Active CN103089276B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310030153.6A CN103089276B (en) 2013-01-28 2013-01-28 Deep-shallow hole and high-low pressure coupling grouting technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310030153.6A CN103089276B (en) 2013-01-28 2013-01-28 Deep-shallow hole and high-low pressure coupling grouting technology

Publications (2)

Publication Number Publication Date
CN103089276A true CN103089276A (en) 2013-05-08
CN103089276B CN103089276B (en) 2015-04-29

Family

ID=48202345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310030153.6A Active CN103089276B (en) 2013-01-28 2013-01-28 Deep-shallow hole and high-low pressure coupling grouting technology

Country Status (1)

Country Link
CN (1) CN103089276B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437787A (en) * 2013-09-18 2013-12-11 山东黄金矿业(莱州)有限公司焦家金矿 Special device for deep hole grouting at surrounding rock breaking section and grouting method
CN103758533A (en) * 2014-01-06 2014-04-30 中国矿业大学 High-low pressure integrated roadway grouting reinforcement method
CN104594914A (en) * 2014-08-18 2015-05-06 河南理工大学 Coal mine tunnel broken surrounding rock layering grouting technology and method
CN104895595A (en) * 2015-04-18 2015-09-09 山东大学 Injection slurry diffusion range and rule determining method during anchor rod slurry injection
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A three-dimensional three-dimensional grouting support method for roadway in fault broken area
CN110454200A (en) * 2019-09-06 2019-11-15 贵州桥梁建设集团有限责任公司 A kind of double-walled grouting with small pipe device and its construction method
CN111411983A (en) * 2020-03-30 2020-07-14 中煤新集能源股份有限公司 Repair process for improving compressive strength of underground coal mine roadway surrounding rock loosening ring
CN112065404A (en) * 2020-09-15 2020-12-11 中国矿业大学(北京) A stress-lithology-structure three-factor spatiotemporal coupling regulation and support method
CN114439001A (en) * 2022-01-28 2022-05-06 山东大学 Grouting reinforcement material for in-service pile foundation and directional grouting reinforcement method for pile side

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006046062A (en) * 2004-06-30 2006-02-16 Taiheiyo Material Kk Spray device and spraying method
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Layer-by-layer grouting reinforcement method for soft rock roadway with high ground pressure
CN102230382A (en) * 2011-05-20 2011-11-02 中国矿业大学 Progressive shielding booster-type grouting and reinforcing technology for baseboard
CN102278130A (en) * 2011-09-05 2011-12-14 中铁隧道集团有限公司 Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN102322273A (en) * 2011-05-20 2012-01-18 中国矿业大学 A kind of roadway floor anchor is annotated integrated reinforcement means
CN102733821A (en) * 2012-06-19 2012-10-17 浙江大学 Secondary double-liquid slurry re-grouting method capable of effectively controlling surface deformation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006046062A (en) * 2004-06-30 2006-02-16 Taiheiyo Material Kk Spray device and spraying method
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Layer-by-layer grouting reinforcement method for soft rock roadway with high ground pressure
CN102230382A (en) * 2011-05-20 2011-11-02 中国矿业大学 Progressive shielding booster-type grouting and reinforcing technology for baseboard
CN102322273A (en) * 2011-05-20 2012-01-18 中国矿业大学 A kind of roadway floor anchor is annotated integrated reinforcement means
CN102278130A (en) * 2011-09-05 2011-12-14 中铁隧道集团有限公司 Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN102733821A (en) * 2012-06-19 2012-10-17 浙江大学 Secondary double-liquid slurry re-grouting method capable of effectively controlling surface deformation

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437787A (en) * 2013-09-18 2013-12-11 山东黄金矿业(莱州)有限公司焦家金矿 Special device for deep hole grouting at surrounding rock breaking section and grouting method
CN103758533A (en) * 2014-01-06 2014-04-30 中国矿业大学 High-low pressure integrated roadway grouting reinforcement method
CN103758533B (en) * 2014-01-06 2015-12-30 中国矿业大学 A kind of high-low pressure integratedization roadway grouting reinforcement means
CN104594914A (en) * 2014-08-18 2015-05-06 河南理工大学 Coal mine tunnel broken surrounding rock layering grouting technology and method
CN104895595A (en) * 2015-04-18 2015-09-09 山东大学 Injection slurry diffusion range and rule determining method during anchor rod slurry injection
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A three-dimensional three-dimensional grouting support method for roadway in fault broken area
CN110454200A (en) * 2019-09-06 2019-11-15 贵州桥梁建设集团有限责任公司 A kind of double-walled grouting with small pipe device and its construction method
CN111411983A (en) * 2020-03-30 2020-07-14 中煤新集能源股份有限公司 Repair process for improving compressive strength of underground coal mine roadway surrounding rock loosening ring
CN112065404A (en) * 2020-09-15 2020-12-11 中国矿业大学(北京) A stress-lithology-structure three-factor spatiotemporal coupling regulation and support method
CN114439001A (en) * 2022-01-28 2022-05-06 山东大学 Grouting reinforcement material for in-service pile foundation and directional grouting reinforcement method for pile side

Also Published As

Publication number Publication date
CN103089276B (en) 2015-04-29

Similar Documents

Publication Publication Date Title
CN103089276B (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN102121395B (en) Method for integrated comprehensive management of gas in low-permeability single coal bed
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN102493821B (en) A Supporting Method for High Stress Roadway Coal and Rock Mass
CN104533452B (en) A kind of underground coal mine crushes coal body stagewise grouting strengthening method
CN202866826U (en) Shield tunnel working well outer end socket stratum reinforced structure
CN105200978B (en) A forward-type localized double-fluid grouting device and construction method
CN103899323B (en) A kind of construction method of shield crossing rail yard
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN104747075A (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN101929340A (en) Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN103277120A (en) Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft
CN103993902B (en) A kind of mash gas pumping drilling two step slip-casting hole-sealing method
CN105909287B (en) A kind of coal mine fully-mechanized mining working lead abutment pressure area deep hole grouting technique and method
CN102278130A (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN103573280B (en) Method for supporting porous ooze invasion compound roof roadway
CN103557012B (en) A kind of roadway with large deformation wall rock grouting fastening carrying structure and construction method
CN201310362Y (en) Installing device of high pressure water burst drill hole bore pipe
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN104775787A (en) Hydraulic fracturing crossing hole pitchup hole sealing method of broken surrounding rock
CN102226375A (en) Easy-to-collapse hole drilling and forming method
CN203035203U (en) Pressure-isolating, permeating and cementing grouting device of borehole casing for roadway water-surrounded broken rock
CN110700842A (en) An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant