CN101736746A - Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting - Google Patents
Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting Download PDFInfo
- Publication number
- CN101736746A CN101736746A CN200910199900A CN200910199900A CN101736746A CN 101736746 A CN101736746 A CN 101736746A CN 200910199900 A CN200910199900 A CN 200910199900A CN 200910199900 A CN200910199900 A CN 200910199900A CN 101736746 A CN101736746 A CN 101736746A
- Authority
- CN
- China
- Prior art keywords
- stake
- pile
- steel sleeve
- grouting
- pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 238000009424 underpinning Methods 0.000 title claims abstract description 15
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 38
- 239000010959 steel Substances 0.000 claims abstract description 38
- 239000002689 soil Substances 0.000 claims abstract description 24
- 238000000034 method Methods 0.000 claims description 16
- 238000007569 slipcasting Methods 0.000 claims description 14
- 239000010883 coal ash Substances 0.000 claims description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 8
- 239000004576 sand Substances 0.000 claims description 7
- 239000007921 spray Substances 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 5
- 239000010881 fly ash Substances 0.000 claims description 5
- 239000002002 slurry Substances 0.000 claims description 5
- 238000009412 basement excavation Methods 0.000 claims description 4
- 239000011230 binding agent Substances 0.000 claims description 4
- 239000000203 mixture Substances 0.000 claims description 3
- 230000002093 peripheral effect Effects 0.000 abstract description 5
- 230000008030 elimination Effects 0.000 abstract 1
- 238000003379 elimination reaction Methods 0.000 abstract 1
- 238000005553 drilling Methods 0.000 description 5
- 238000009527 percussion Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000012467 final product Substances 0.000 description 2
- 239000002956 ash Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting, which is characterized by comprising the following steps: vibrating and sinking a steel sleeve; grouting and stripping a pile body and peripheral soil body; extracting the pile; and grouting and underpinning. Compared with the prior art, the construction method has the advantages of small pile extracting force by only considering the self-weight of the pile body, low vibration noise, complete elimination of underground obstacles, and no hidden dangers remaining in subsequent pile foundation construction, great improvement on the bearing capacity of the foundation soil, and no influence on the peripheral environment. Meanwhile, the construction method has convenient construction and high working efficiency, and is a resource-saving and environment-friendly construction method.
Description
Technical field
The present invention relates to the pile foundation of building structure, especially a kind of job practices that is used for the vibrator pipe sinking high-pressure grouting underpinning pile extracting of old structure, buildings pile dismounting.
Background technology
At present, in the ground and foundation construction of old building transformation project, the pile foundation of structure, building is removed, mainly adopt percussion and grabbing method, hang method by force and the immersed tube water flood is pulled out preformed pile, castinplace pile, piling bar and timber etc.Percussion and grabbing method: adopt weight to smash underground obstacle (pile body), grab out chip with grab bucket then, the shortcoming of percussion and grabbing method construction is: vibrating noise is big, long in time limit, cost is high.Hang method by force: crane gears such as employing large tonnage crane lift by crane by force to be extracted, and the shortcoming of hanging the method construction by force is: often pull off underground obstacle, can't thoroughly remove underground pile body, giving later on, construction stays hidden danger.Immersed tube water flood: adopt the machine power pressurization to sink to steel pipe, the soil body of water filling displacement pile foundation periphery, play the wire rope lifting to treat pile pulling then, this job practices adopts the soil body on water underpinned pile primitive period limit, chips such as the sand grains in the soil body are because at the bottom of the deadweight effect sinks down into, cause hoisting wirerope can't transfer to design attitude, pile pulling is failed easily.
Above several method construction behind the rid, is generally adopted dregs filling perforation hole back and forth, because backfill is loose than closely knit naturally soil, thereby influences the bearing capacity of foundation soil and follow-up pile foundation construction, causes pile position deviation easily.
Summary of the invention
The job practices that a kind of vibrator pipe sinking high-pressure grouting underpinning pile extracting of providing at the deficiencies in the prior art is provided, it is little that it has pile pulling power, only need to consider that the pile body deadweight gets final product, and vibrating noise is little, underground obstacle is removed thoroughly, and follow-up pile foundation construction is not stayed hidden danger, has improved the supporting capacity of foundation soil greatly, surrounding enviroment there is not influence, easy construction, high efficiency, real is a kind of resources conservation, eco-friendly job practices.
The object of the present invention is achieved like this: a kind of job practices of vibrator pipe sinking high-pressure grouting underpinning pile extracting, be characterized in that this method comprises: the pile body periphery soil body, pile pulling and grouting underpinning are peeled off in the heavy steel sleeve of vibration, slip casting, and its concrete construction comprises the steps:
A, the heavy steel sleeve of vibration
Utilize transit that stake is positioned, the soil body of excavation preformed pile periphery also exposes pile crown, adopts the vibration sinking tube method that steel sleeve is sink to the design elevation of stake, and the steel sleeve diameter should be greater than circle stake diameter 500mm or side's stake diagonal 200mm, and length is greater than the long 1.0m of stake;
The pile body periphery soil body is peeled off in b, slip casting
Adopt the high-pressure rotary-spray rig along the design elevation that gets into stake between steel sleeve inwall and pile lining down, high pressure injects coal ash pulp 300mm to the stake in the time of trip-out, and the soil body of pile foundation periphery in the steel sleeve is all peeled off, and the water/binder ratio of coal ash pulp is 1: 1 weight ratio;
C, pile pulling
Is main hanging with the wire rope hoisting ring along the 500mm place, top that pile lining is transferred at the bottom of the stake, it is auxilliary hanging that another wire rope hoisting ring is located at stake long 1/2 downward 1 meter, adopting pile pulling equipment to lift wire rope holds pile body tightly, begin pile pulling then, when stake hangs out ground 1.5m, strain with the pile body binding and by crane with wire rope, when having continued to winch to overhead 5m then, cut stake, repeat this step, all extract until stake;
D, grouting underpinning
After treating that stake is extracted, the stake hole adopts a high-pressure slip-casting filling to underpin, and slurry is that cement, flyash, sand mix by 1: 2: 7 weight ratio, high-pressure slip-casting by the hole in stake hole at the bottom of from bottom to top grouting filling underpin to ground, extract steel sleeve then.
Be provided with the locator of wedge in the described steel sleeve, locator is that four inwalls that evenly are arranged on interior lower end of steel sleeve and steel sleeve are affixed.
It is little that the present invention compared with prior art has pile pulling power, only need to consider that the pile body deadweight gets final product, vibrating noise is little, underground obstacle is removed thoroughly, follow-up pile foundation construction is not stayed hidden danger, improved the supporting capacity of foundation soil greatly, surrounding enviroment have not been had influence, and easy construction, high efficiency, real is a kind of resources conservation, environmentally friendly job practices.
Description of drawings
Fig. 1 is a structural representation of the present invention
Fig. 2 is Fig. 1 vertical view
Fig. 3 is the invention process illustration
The specific embodiment
Consult accompanying drawing 1, accompanying drawing 2, construction sequence of the present invention comprises: the pile body periphery soil body, pile pulling and grouting underpinning are peeled off in the heavy steel sleeve of vibration, slip casting.Excavate treat pile pulling 1 the stake roof construction and the stake 1 periphery the soil body and expose pile crown, adopt the vibration sinking tube method steel sleeve 2 to be sink to the design elevation of stake 1, be provided with the locator 3 of wedge in the steel sleeve 2, locator 3 is that four inwalls that evenly are arranged on lower end in the steel sleeve 2 and steel sleeve 2 are affixed, locator 3 mainly is the spacing that guarantees steel sleeve 2 and stake 1, bores and transfer wire rope hoisting ring 45 times to make things convenient for drilling rod.Then with high-pressure rotary-spray drilling rod 5 along the design elevation that is drilled into stake 1 under steel sleeve 2 inwalls and stake 1 the sidewall, high-pressure rotary-spray injects coal ash pulp when drilling rod 5 rises, the peripheral soil body of stake 1 is all peeled off, the water/binder ratio of coal ash pulp is 1: 1 weight ratio, the main effect of the pulverized fuel ash slurry chips such as sand grains in the soil body that are to suspend, make wire rope hoisting ring 4 can transfer to design attitude, adopt two-point method lifting stake 1 then, when certain altitude is hung in stake 1, cut stake, extract fully up to stake 1, after stake 1 is extracted the high-pressure slip-casting filling is carried out in the stake hole and underpined, slurry is a cement, flyash, sand mixes by 1: 2: 7 weight ratio.
Consulting accompanying drawing 3, is example with the pile pulling engineering, and the present invention is further elaborated:
(1), location excavation pile crown
Utilize transit that stake 1 is positioned, the peripheral soil body of excavation preformed pile 1 also exposes pile crown.
(2), the heavy steel sleeve of vibration
Adopt the vibration sinking tube method steel sleeve 2 to be sink to the design elevation of stake 1, be provided with the locator 3 of wedge in the steel sleeve 2, locator 3 is that four inwalls that evenly are arranged on lower end in the steel sleeve 2 and steel sleeve 2 are affixed, the diameter of steel sleeve 2 should be greater than circle stake diameter 500mm or side's stake diagonal 200mm, and length is greater than the long 1.0m of stake.
(3), the pile body periphery soil body is peeled off in slip casting
Along the design elevation that is drilled into stake 1 under the sidewall of steel sleeve 2 inwalls and stake 1, high-pressure rotary-spray injects coal ash pulp when promoting drilling rod 5, and the peripheral soil body of stake 1 is all peeled off with high-pressure rotary-spray drilling rod 5, and the water/binder ratio of coal ash pulp is 1: 1 weight ratio.
(4), pile pulling
The lifting of stake 1 is adopted at 2 and is hung method, it is main hanging that one wire rope hoisting ring 4 is transferred to the 500mm place, top of stake 1 bottom along the sidewall of stake 1,1/2 downward 1 meter that another wire rope hoisting ring 4 is located at stake 1 length is auxilliary hanging, and adopts the 150T crane to lift wire rope stake 1 is held tightly, begins pile pulling then, when stake 1 hangs out ground 1.5m, again with wire rope with stake 1 binding and by the crane tension, when having continued to winch to overhead 5m then, cut, repeat this step, all extract until stake 1.
(5), grouting underpinning
After treating that stake 1 is extracted, the stake hole adopts a high-pressure slip-casting filling to underpin, and slurry is that cement, flyash, sand mix by 1: 2: 7 weight ratio, high-pressure slip-casting by the hole in stake hole at the bottom of from bottom to top grouting filling underpin to ground.
After stake was all extracted, the stake hole adopted a grouting filling to underpin, adopt cement, flyash, sand by 1: 2: 7 proportioning employing high-pressure slip-casting by the hole at the bottom of from bottom to top grouting filling underpin to ground.
(6), pull out steel sleeve
After former position backfill is closely knit, adopts pile pulling equipment to rise and pull out steel bushing 2 and clean next stand-by.
More than just the present invention will be further described, is not in order to the restriction this patent, all for the present invention's equivalence enforcement, all should be contained within the claim scope of this patent.
Claims (2)
1. the job practices of a vibrator pipe sinking high-pressure grouting underpinning pile extracting is characterized in that this method comprises: the pile body periphery soil body, pile pulling and grouting underpinning are peeled off in the heavy steel sleeve of vibration, slip casting, and its concrete construction comprises the steps:
A, the heavy steel sleeve of vibration
Utilize transit that stake is positioned, the soil body of excavation preformed pile periphery also exposes pile crown, adopts the vibration sinking tube method that steel sleeve is sink to the design elevation of stake, and the steel sleeve diameter should be greater than circle stake diameter 500mm or side's stake diagonal 200mm, and length is greater than the long 1.0m of stake;
The pile body periphery soil body is peeled off in b, slip casting
Adopt the high-pressure rotary-spray rig along the design elevation that gets into stake under a steel sleeve inwall and the sidewall, high pressure injects coal ash pulp to a beneath 300mm in the time of trip-out, and the soil body of pile body periphery in the steel sleeve is all peeled off, and the water/binder ratio of coal ash pulp is 1: 1 weight ratio;
C, pile pulling
Is main hanging with the wire rope hoisting ring along the 500mm place, top that pile lining is transferred at the bottom of the stake, it is auxilliary hanging that another wire rope hoisting ring is located at stake long 1/2 downward 1 meter, adopting pile pulling equipment to lift wire rope holds pile body tightly, begin pile pulling then, when stake hangs out ground 1.5m, strain with the pile body binding and by crane with wire rope, when having continued to winch to overhead 5m then, cut stake, repeat this step, all extract until stake;
D, grouting underpinning
After stake was extracted, the stake hole adopted a high-pressure slip-casting filling to underpin, and slurry is that cement, flyash, sand mix by 1: 2: 7 weight ratio, high-pressure slip-casting by the hole in stake hole at the bottom of from bottom to top grouting filling underpin to ground, extract steel sleeve then.
2. according to the job practices of the described vibrator pipe sinking high-pressure grouting underpinning pile extracting of claim 1, it is characterized in that being provided with in the described steel sleeve locator of wedge, locator is that four inwalls that evenly are arranged on interior lower end of steel sleeve and steel sleeve are affixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101999002A CN101736746B (en) | 2009-12-04 | 2009-12-04 | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101999002A CN101736746B (en) | 2009-12-04 | 2009-12-04 | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101736746A true CN101736746A (en) | 2010-06-16 |
CN101736746B CN101736746B (en) | 2011-08-17 |
Family
ID=42460732
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009101999002A Active CN101736746B (en) | 2009-12-04 | 2009-12-04 | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101736746B (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102108705A (en) * | 2011-03-07 | 2011-06-29 | 江苏现代造船技术有限公司 | Marine wind driven generator mounting and transporting spud leg mud discharging, air injecting and washing device and method |
CN103046550A (en) * | 2013-01-08 | 2013-04-17 | 上海建工二建集团有限公司 | Pile extractor with vibrating lantern ring and application method thereof |
CN103485344A (en) * | 2013-09-17 | 2014-01-01 | 常熟理工学院 | Method for extracting construction engineering pile foundation |
CN103556641A (en) * | 2013-10-09 | 2014-02-05 | 中铁十三局集团有限公司 | Grooving assisting method for in-pit underground diaphragm wall of existing basement |
CN103669343A (en) * | 2013-11-22 | 2014-03-26 | 河海大学 | Detachable combined pile and detachment construction method thereof |
CN104110027A (en) * | 2013-12-02 | 2014-10-22 | 成都绿迪科技有限公司 | Tool-type uplift pile |
CN104652436A (en) * | 2014-12-24 | 2015-05-27 | 福建工程学院 | Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method |
CN105507321A (en) * | 2015-12-16 | 2016-04-20 | 上海市城市建设设计研究总院 | High-efficiency pile sinking process for existing precast pile |
CN105544544A (en) * | 2015-12-16 | 2016-05-04 | 上海市城市建设设计研究总院 | Method for quickly extracting pile under low clearance condition |
CN108425361A (en) * | 2018-05-09 | 2018-08-21 | 上海建工四建集团有限公司 | Pile pulling device and its application process |
CN108457273A (en) * | 2018-03-17 | 2018-08-28 | 北京工业大学 | A kind of steel pipe slope protection pile pile recovery method |
CN108894224A (en) * | 2018-08-03 | 2018-11-27 | 中冶沈勘工程技术有限公司 | A kind of method for pulling out of static pressure pipe pile |
CN109763489A (en) * | 2019-02-18 | 2019-05-17 | 杭州昂创科技有限公司 | The all casing high pressure water vapor injections of stake lubricate pile-pulling construction method |
CN109930602A (en) * | 2019-04-11 | 2019-06-25 | 江苏楼翔建设有限公司 | A kind of Water Cutting vibration immersed tube pile pulling device |
CN110952555A (en) * | 2019-12-09 | 2020-04-03 | 广州市盾建地下工程有限公司 | Pile pulling method and pile pulling system |
CN115387339A (en) * | 2022-08-15 | 2022-11-25 | 中建八局装饰工程有限公司 | Driving and pulling steel sheet pile matched synchronous grouting obstacle clearing device and obstacle clearing method thereof |
-
2009
- 2009-12-04 CN CN2009101999002A patent/CN101736746B/en active Active
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102108705B (en) * | 2011-03-07 | 2012-11-21 | 江苏现代造船技术有限公司 | Marine wind driven generator mounting and transporting spud leg mud discharging, air injecting and washing device and method |
CN102108705A (en) * | 2011-03-07 | 2011-06-29 | 江苏现代造船技术有限公司 | Marine wind driven generator mounting and transporting spud leg mud discharging, air injecting and washing device and method |
CN103046550A (en) * | 2013-01-08 | 2013-04-17 | 上海建工二建集团有限公司 | Pile extractor with vibrating lantern ring and application method thereof |
CN103046550B (en) * | 2013-01-08 | 2015-11-25 | 上海建工二建集团有限公司 | A kind of vibrations collar pile pulling device and using method thereof |
CN103485344A (en) * | 2013-09-17 | 2014-01-01 | 常熟理工学院 | Method for extracting construction engineering pile foundation |
CN103556641A (en) * | 2013-10-09 | 2014-02-05 | 中铁十三局集团有限公司 | Grooving assisting method for in-pit underground diaphragm wall of existing basement |
CN103669343B (en) * | 2013-11-22 | 2015-07-15 | 河海大学 | Detachable combined pile and detachment construction method thereof |
CN103669343A (en) * | 2013-11-22 | 2014-03-26 | 河海大学 | Detachable combined pile and detachment construction method thereof |
CN104110027B (en) * | 2013-12-02 | 2016-01-13 | 华北水利水电大学 | Tool type uplift pile |
CN104110027A (en) * | 2013-12-02 | 2014-10-22 | 成都绿迪科技有限公司 | Tool-type uplift pile |
CN104652436A (en) * | 2014-12-24 | 2015-05-27 | 福建工程学院 | Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method |
CN105507321A (en) * | 2015-12-16 | 2016-04-20 | 上海市城市建设设计研究总院 | High-efficiency pile sinking process for existing precast pile |
CN105544544A (en) * | 2015-12-16 | 2016-05-04 | 上海市城市建设设计研究总院 | Method for quickly extracting pile under low clearance condition |
CN108457273B (en) * | 2018-03-17 | 2020-02-14 | 北京工业大学 | Piling recovery method for steel pipe slope protection piles |
CN108457273A (en) * | 2018-03-17 | 2018-08-28 | 北京工业大学 | A kind of steel pipe slope protection pile pile recovery method |
CN108425361A (en) * | 2018-05-09 | 2018-08-21 | 上海建工四建集团有限公司 | Pile pulling device and its application process |
CN108425361B (en) * | 2018-05-09 | 2023-09-22 | 上海建工四建集团有限公司 | Pile pulling device and application method thereof |
CN108894224A (en) * | 2018-08-03 | 2018-11-27 | 中冶沈勘工程技术有限公司 | A kind of method for pulling out of static pressure pipe pile |
CN109763489A (en) * | 2019-02-18 | 2019-05-17 | 杭州昂创科技有限公司 | The all casing high pressure water vapor injections of stake lubricate pile-pulling construction method |
CN109930602A (en) * | 2019-04-11 | 2019-06-25 | 江苏楼翔建设有限公司 | A kind of Water Cutting vibration immersed tube pile pulling device |
CN109930602B (en) * | 2019-04-11 | 2024-04-19 | 中桩基础工程有限公司 | Pile pulling device for water cutting vibration immersed tube |
CN110952555A (en) * | 2019-12-09 | 2020-04-03 | 广州市盾建地下工程有限公司 | Pile pulling method and pile pulling system |
CN115387339A (en) * | 2022-08-15 | 2022-11-25 | 中建八局装饰工程有限公司 | Driving and pulling steel sheet pile matched synchronous grouting obstacle clearing device and obstacle clearing method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN101736746B (en) | 2011-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736746B (en) | Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting | |
CN100501011C (en) | Hole drilling mudjack pile construction method | |
CN104929123B (en) | A kind of pile sinking staving press | |
CN111395330B (en) | Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery | |
CN106978807A (en) | Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area | |
CN1963044A (en) | Construction method for withdrawal of waste pile | |
CN106088140A (en) | A kind of batholith sea bed offshore wind turbine embedding rock single-pile foundation construction technique | |
CN101761081A (en) | Construction method and equipment of holding and pressing type static-pressure driven cast-in-place pile | |
CN106869126A (en) | The quick green construction remove device on the waste and old basis in city | |
CN105494212A (en) | Anchoring device suitable for sandy and muddy bottom | |
CN204000830U (en) | Merogenesis take-over type sand drain machine | |
WO2023207250A1 (en) | Construction method for rapidly driving trestle steel pipe pile into sloped bare rock | |
CN105862862B (en) | A kind of large diameter pile buries hammer Refloatation method | |
CN101713201B (en) | Underground hole-forming device of hydraulic grab bucket | |
CN103572770B (en) | A kind of stake case hydraulic structures and construction method thereof | |
CN106948347B (en) | Pile pulling method and pile pulling system | |
CN101691760A (en) | Composite foundation combining anchor rods with excavation and construction method thereof | |
KR101543209B1 (en) | Boring and grouting constructuring method and post with Geo tube | |
CN106968252B (en) | Pile pulling recharging method and pile pulling recharging system | |
CN213952217U (en) | Static pressure pipe pile sinking device with recyclable pile tip | |
CN105951863B (en) | A kind of construction method of the construction equipment of active assembled open caisson | |
CN103334433B (en) | A kind of construction method of pile pulling | |
CN206902710U (en) | Retaining wall and counter-force open caisson platform pile pulling system | |
CN206902712U (en) | Pile pulling recharge system | |
CN206928296U (en) | Pile pulling system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |