[go: up one dir, main page]

CN106968252B - Pile pulling recharging method and pile pulling recharging system - Google Patents

Pile pulling recharging method and pile pulling recharging system Download PDF

Info

Publication number
CN106968252B
CN106968252B CN201710213872.XA CN201710213872A CN106968252B CN 106968252 B CN106968252 B CN 106968252B CN 201710213872 A CN201710213872 A CN 201710213872A CN 106968252 B CN106968252 B CN 106968252B
Authority
CN
China
Prior art keywords
pile
pulled
anchor
hole
pulling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710213872.XA
Other languages
Chinese (zh)
Other versions
CN106968252A (en
Inventor
刘海祥
陈亮
柯敏勇
唐云清
张民
鲁文妍
龙志勇
陈西宁
王凌骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing R & D Tech Group Co ltd
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
Nanjing R & D Tech Group Co ltd
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing R & D Tech Group Co ltd, Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical Nanjing R & D Tech Group Co ltd
Priority to CN201710213872.XA priority Critical patent/CN106968252B/en
Publication of CN106968252A publication Critical patent/CN106968252A/en
Application granted granted Critical
Publication of CN106968252B publication Critical patent/CN106968252B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及一种拔桩回灌方法及拔桩回灌系统,属于水利、公路、铁路、市政、桥梁等工程中桩的撤去技术领域。该拔桩回灌方法包括以下步骤:1)经前处理先使待拔桩的顶部曝露;2)在待拔桩的顶部钻制锚孔和桩体灌浆孔;3)将锚索材料的一端下放至锚孔底部,其另一端露出待拔桩顶部;4)向锚孔灌注第一浆体,将锚索材料固定于待拔桩内形成锚杆;5)通过起吊设备提升锚索材料的另一端以拔起待拔桩,在拔桩过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体。该拔桩回灌方法及拔桩回灌系统可以将桩快速安全拔出,起到降低提升力、防止塌方,提高成功率,以及保护周边建筑物地下结构稳定的作用。

Figure 201710213872

The invention relates to a method for pulling out piles and refilling and a system for pulling out piles and refilling, belonging to the technical field of pile removal in water conservancy, highway, railway, municipal, bridge and other projects. The method for refilling the extracted piles includes the following steps: 1) exposing the top of the piles to be pulled out after pretreatment; 2) drilling anchor holes and grouting holes for the piles on the top of the piles to be pulled out; 3) placing one end of the anchor cable material Lower it to the bottom of the anchor hole, and its other end exposes the top of the pile to be pulled out; 4) Pour the first slurry into the anchor hole, and fix the anchor cable material in the pile to be pulled out to form an anchor rod; 5) Lift the anchor cable material by lifting equipment. The other end is used to pull up the pile to be pulled. During the process of pulling the pile, the second slurry is refilled through the grouting hole of the pile body, so that the second slurry penetrates into the soil around the pile at the bottom of the pile to be pulled, and the soil body and the to-be-pulled pile are separated. The piles are connected as a whole. The pile-pulling refilling method and the pile-pulling refilling system can quickly and safely pull out the piles, thereby reducing the lifting force, preventing landslides, improving the success rate, and protecting the stability of the underground structures of surrounding buildings.

Figure 201710213872

Description

拔桩回灌方法及拔桩回灌系统Pull-out pile re-injection method and pull-out pile re-injection system

技术领域technical field

本发明涉及一种拔桩回灌方法及拔桩回灌系统,属于水利、公路、铁路、市政、桥梁等工程中桩的撤去技术领域。The invention relates to a method for pulling out piles and refilling and a system for pulling out piles and refilling, belonging to the technical field of pile removal in water conservancy, highway, railway, municipal, bridge and other projects.

背景技术Background technique

现有地铁隧洞盾构施工中,需要将影响隧洞施工的整桩提至安全高度,即将影响隧洞施工的整桩完全拔出或者部分拔出。In the shield construction of the existing subway tunnels, it is necessary to raise the whole pile affecting the tunnel construction to a safe height, and the whole pile affecting the tunnel construction is about to be completely or partially pulled out.

但是,据申请人了解,现有国内外的拔桩技术,主要采用以下几种方式:However, according to the applicant's knowledge, the existing domestic and foreign pile pulling technology mainly adopts the following methods:

1)冲击碎桩法与全套管减磨拔除法;这两种拔桩技术主要依赖全套管钻机及大型起重机,故对施工场地要求较高,施工场地面积很大且场地上部无净高限制,但是,实际施工环境是难以达到的。1) Impact crushing method and full casing wear reduction and extraction method; these two pile extraction techniques mainly rely on full casing drilling rigs and large cranes, so they have higher requirements on the construction site, the construction site area is large, and there is no clear height limit on the upper part of the site. However, the actual construction environment is difficult to achieve.

2)全套管静压拔桩的方法,这种方法采用钢套管以及结合喷射高压水及高压膨润土浆对桩的周圈土体进行清除,然后进行拔桩,但是工艺较复杂,实际较长,特别是对于彼此紧邻的多根桩的拔除不能适用。2) The method of full casing static pressure pile pulling, this method uses steel casing and combined with jetting high-pressure water and high-pressure bentonite slurry to remove the surrounding soil of the pile, and then pulls the pile, but the process is more complicated and the actual length is longer. , especially for the extraction of multiple piles that are in close proximity to each other.

3)直接将灌注桩中的桩头钢筋与拔桩设置连接,逐渐施力直至将桩拔出,但是,现有灌注桩中的钢筋强度低、焊接不可靠、受力不均,容易将灌注桩拔断,这是拔桩施工中所不允许的。3) Directly connect the pile head steel bar in the cast-in-place pile with the pulling pile, and gradually apply force until the pile is pulled out. However, the steel bars in the existing cast-in-place pile have low strength, unreliable welding, and uneven stress, which is easy to pour out the cast-in-place pile. The pile is pulled off, which is not allowed in the construction of pulling piles.

同时,据申请人了解,在拔桩过程中,桩的底部将形成由水体代替的空腔,空腔周边松散土体极易坍塌,破坏桩的功能,容易对周边建筑物产生不利影响,现有桩的回灌都是在拔桩后进行的。At the same time, according to the applicant's knowledge, during the process of pulling out the pile, a cavity replaced by a water body will be formed at the bottom of the pile, and the loose soil around the cavity is very easy to collapse, destroying the function of the pile and easily adversely affecting the surrounding buildings. The recharge with piles is carried out after the piles are pulled out.

可见,现有拔桩技术中,设备要求高、占地大、启用大型吊机风险大,快速安全拔桩仍然是一个难题,尤其是在小空间中的大直径桩快速安全拔出。同时,现有桩的回灌不能保证原有桩的功能,不能保护周边建筑物地下结构稳定。It can be seen that in the existing pile pulling technology, the equipment requirements are high, the land occupation is large, and the risk of using a large crane is high. Fast and safe pile pulling is still a difficult problem, especially for large-diameter piles in a small space. At the same time, the recharge of the existing piles cannot guarantee the function of the original piles, and cannot protect the stability of the underground structure of the surrounding buildings.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题是针对现有技术不足,提出一种快速安全拔出不同直径桩并同时保证桩的功能的拔桩回灌方法及拔桩回灌系统。The technical problem to be solved by the present invention is to propose a method and a system for pulling out and refilling piles that can quickly and safely pull out piles of different diameters while ensuring the function of the piles.

本发明为解决上述技术问题提出的技术方案之一是:一种拔桩回灌方法,包括以下步骤:One of the technical solutions proposed by the present invention to solve the above-mentioned technical problems is: a method for pulling out piles and refilling, comprising the following steps:

1)经前处理先使待拔桩的顶部曝露,同时备设多根高强度锚索材料以及起吊设备;1) Expose the top of the pile to be pulled out after pretreatment, and equip multiple high-strength anchor cable materials and lifting equipment at the same time;

2)在待拔桩的顶部钻制向待拔桩内的底部延伸的锚孔,在待拔桩上钻制贯通其顶面和底面的桩体灌浆孔;2) An anchor hole extending toward the bottom of the pile to be pulled is drilled at the top of the pile to be pulled, and a pile grouting hole penetrating the top and bottom surfaces of the pile to be pulled is drilled;

3)将所述锚索材料的一端下放至所述锚孔底部,其另一端露出待拔桩顶部;3) Lower one end of the anchor cable material to the bottom of the anchor hole, and the other end of the anchor material exposes the top of the pile to be pulled;

4)向所述锚孔灌注第一浆体,待所述第一浆体固化并达到设定强度后,将所述锚索材料固定于所述待拔桩内形成锚杆;4) pouring the first slurry into the anchor hole, and after the first slurry is solidified and reaches the set strength, the anchor cable material is fixed in the to-be-pulled pile to form an anchor rod;

5)通过起吊设备提升所述锚索材料的另一端以拔起待拔桩,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体。5) Lift the other end of the anchor cable material by lifting equipment to pull up the pile to be pulled out. During the process of pulling up the pile to be pulled out, refill the second slurry through the grouting hole of the pile body, so that the second slurry penetrates into the to-be-pulled pile. Pull out the soil around the pile at the bottom of the pile, and connect the soil with the pile to be pulled out as a whole.

本发明为解决上述技术问题提出的技术方案之二是:一种拔桩回灌系统,用于上述的拔桩回灌方法中,该拔桩回灌系统设置于固定在土体中并顶部曝露的待拔桩附近,包括多根高强度锚索材料和起吊设备,其特征在于:所述待拔桩的顶部制有向待拔桩内的底部延伸的锚孔,所述待拔桩上制有贯通其顶面和底面的桩体灌浆孔,所述锚索材料的一端设于所述锚孔底部,所述锚索材料的另一端露出待拔桩顶部;所述锚孔内灌注有固化后用于将锚索材料固定于待拔桩内以形成锚杆的第一浆体,所述起吊设备用于提升所述锚索材料的另一端以拔起待拔桩,所述桩体灌浆孔用于在拔桩过程中回灌第二浆体。The second technical solution proposed by the present invention to solve the above-mentioned technical problems is: a pile-pulling refilling system, which is used in the above-mentioned pulling-pile refilling method, and the pile-pulling refilling system is arranged in the soil body and is fixed in the soil body and the top is exposed. The vicinity of the to-be-pulled pile, including a plurality of high-strength anchor cable materials and lifting equipment, is characterized in that: the top of the to-be-pulled pile is provided with anchor holes extending toward the bottom of the to-be-pulled pile, and the to-be-pulled pile is made on the top. There are pile grouting holes penetrating the top surface and bottom surface of the pile body, one end of the anchor cable material is set at the bottom of the anchor hole, and the other end of the anchor cable material is exposed at the top of the pile to be pulled out; the anchor hole is filled with solidified After that, it is used to fix the anchor cable material in the pile to be pulled out to form the first slurry of the anchor rod. The lifting device is used to lift the other end of the anchor cable material to pull up the pile to be pulled out. The pile body is grouted. The holes are used to refill the second grout during pile extraction.

本发明直接在待拔桩的顶部钻制向待拔桩内的底部延伸的锚孔,在待拔桩上钻制贯通其其顶面和底面的桩体灌浆孔,然后将锚索材料的一端下放至所述锚孔底部,其另一端露出待拔桩顶部,再向锚孔灌注第一浆体,将锚索材料固定于待拔桩内形成锚杆,最后通过起吊设备提升所述锚索材料的另一端以拔起待拔桩,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,这样具有如下效果:The invention directly drills an anchor hole extending to the bottom of the pile to be pulled at the top of the pile to be pulled, drills a pile grouting hole through the top surface and the bottom surface of the pile to be pulled, and then drills one end of the anchor cable material. It is lowered to the bottom of the anchor hole, the other end of which is exposed to the top of the pile to be pulled out, the first slurry is poured into the anchor hole, the anchor cable material is fixed in the pile to be pulled out to form an anchor rod, and finally the anchor cable is lifted by lifting equipment The other end of the material is used to pull up the pile to be pulled out. During the process of pulling up the pile to be pulled out, the second slurry is refilled through the grouting hole of the pile body, which has the following effects:

1)巧妙的将现有岩土锚固技术中的锚杆移用到拔桩中,相比于传统拔桩的思维定势是一味在桩的外表固定后进行吊拔,本发明突破了这一思维定势,对待拔桩先钻孔进行锚固再拔除,形成先锚后拔,因此十分出人意料。1) The anchor rod in the existing geotechnical anchoring technology is skillfully transferred to the pulling pile. Compared with the traditional thinking of pulling the pile, the surface of the pile is fixed and lifting and pulling. The present invention breaks through this. The mindset is that when the piles are pulled out, they are first drilled for anchoring and then pulled out, which is very unexpected.

本发明既可以对于不同直径(大、中、小)待拔桩进行锚固提升,同时又对拔桩进行加固,可以有效防止拔桩中的断桩并将大直径桩快速安全拔出,特别是对于小空间中彼此紧邻的多根桩的拔除十分适用,整体非常可靠稳固、安全性大大提高的同时节省大量成本,且提高效率。The invention can not only carry out anchoring and lifting for different diameters (large, medium and small) piles to be pulled out, but also reinforce the pulled piles, which can effectively prevent the broken piles in the pulled piles and quickly and safely pull out the large-diameter piles, especially It is very suitable for the removal of multiple piles that are close to each other in a small space. The whole is very reliable and stable, the safety is greatly improved, and a lot of cost is saved, and the efficiency is improved.

2)通过在待拔桩上钻制贯通其顶面和底面的桩体灌浆孔,在拔起待拔桩的过程中,通过桩体灌浆孔回灌第二浆体,可以确保桩的结构安全,保护周边建筑物地下结构稳定,防止塌方,同时,可以使大气压内外平衡,降低提升力,提高成功率。特别重要的是,在只需要将桩部分拔出的施工要求时,在拔桩过程中,通过桩体灌浆孔回灌第二浆体,使得第二浆体渗入待拔桩底部的桩周土体,并将土体与待拔桩连为整体,这样,未完全拔出的余下的桩还可以进行利用。2) By drilling the pile grouting holes through the top and bottom surfaces of the pile to be pulled out, in the process of pulling up the pile to be pulled, the second slurry is refilled through the grouting hole of the pile to ensure the structural safety of the pile. , to protect the stability of the underground structure of surrounding buildings and prevent landslides. At the same time, it can balance the internal and external atmospheric pressure, reduce the lifting force and improve the success rate. It is particularly important that when only the construction requirements of pulling out the pile are required, in the process of pulling the pile, the second slurry is refilled through the grouting hole of the pile body, so that the second slurry can penetrate into the surrounding soil of the pile at the bottom of the pile to be pulled out. The soil body is connected with the pile to be pulled out as a whole, so that the remaining piles that are not completely pulled out can still be used.

上述技术方案之一的改进是:在所述步骤2)中,在所述待拔桩的顶部钻制向其底部延伸的静态爆破孔;在所述步骤5)中,在通过起吊设备提升所述锚索材料的另一端以拔起桩后,先在静态爆破孔中倒入破碎剂并用快硬性水泥堵住静态爆破孔的孔口12-18小时,然后通过破碎设备进行桩体破碎。The improvement of one of the above technical solutions is: in the step 2), a static blasting hole extending toward the bottom of the pile to be pulled is drilled at the top; in the step 5), the After pulling up the pile at the other end of the anchor cable material, first pour the crushing agent into the static blasting hole and block the orifice of the static blasting hole with fast-hardening cement for 12-18 hours, and then use the crushing equipment to break the pile body.

本发明采用上述技术方案的效果是:通过在待拔桩的顶部钻制向其底部延伸的静态爆破孔,这样在通过起吊设备提升锚索材料的另一端以拔起桩后,先在静态爆破孔中倒入破碎剂并用快硬性水泥堵住静态爆破孔的孔口12-18小时,然后通过破碎设备进行桩体破碎,结合混凝切割以及气割钢筋等办法,可以快速分解混凝土,实现桩的上部拆除,将拔桩工程顺利转向下一工序、下一根桩。The effect of adopting the above technical scheme in the present invention is: by drilling a static blasting hole extending to the bottom of the pile to be pulled out, after the other end of the anchor cable material is lifted by the lifting device to pull up the pile, the static blasting hole is first Pour the crushing agent into the hole and block the orifice of the static blasting hole with fast-hardening cement for 12-18 hours, and then use the crushing equipment to break the pile body. Combined with concrete cutting and gas cutting steel bars, the concrete can be quickly decomposed and the pile is broken. The upper part is removed, and the pile pulling project is smoothly transferred to the next process and the next pile.

上述技术方案之一的完善之一是:在所述步骤1)中,在所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台;在所述步骤5)中,所述起吊设备是设于工作平台上的穿心千斤顶、吊机或卷扬机,所述穿心千斤顶、吊机或卷扬机持续张拉锚索材料的另一端以连续拔起所述待拔桩。One of the improvement of one of the above-mentioned technical solutions is: in the step 1), a working platform is provided on other piles near the pile to be pulled or the soil around the pile to be pulled; in the step 5) Among them, the lifting equipment is a center-through jack, a hoist or a hoist set on the working platform, and the through-core jack, crane or winch continuously stretches the other end of the anchor cable material to continuously pull up the pile to be pulled out .

本发明采用上述技术方案的效果是:本发明通过在待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台,起吊设备采用设于工作平台上的穿心千斤顶、吊机或卷扬机,这样可以通过穿心千斤顶、吊机或卷扬机持续张拉锚索材料的另一端,对桩连续拔起,整体结构简单可靠。The effect of adopting the above technical scheme in the present invention is: the present invention provides a working platform on other piles near the pile to be pulled or on the soil body around the pile to be pulled, and the lifting equipment adopts the through-core jack, hoisting jack, etc. In this way, the other end of the anchor cable material can be continuously tensioned by the through-core jack, crane or hoist, and the pile can be pulled up continuously, and the overall structure is simple and reliable.

上述技术方案之一的完善之一的改进是:所述工作平台是钢筋混凝土平台、钢结构框架平台或组合结构平台;所述穿心千斤顶通过反力架安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上;所述吊机或卷扬机设于钢筋混凝土平台、钢结构框架平台或组合结构平台上。One of the improvements of one of the above-mentioned technical solutions is: the working platform is a reinforced concrete platform, a steel structure frame platform or a composite structure platform; on a platform or a combined structure platform; the crane or hoist is arranged on a reinforced concrete platform, a steel structure frame platform or a combined structure platform.

本发明采用上述技术方案的效果是:本发明通过设置钢筋混凝土平台、钢结构框架平台或组合结构平台,可以对头部位于地表以上或整体位于地表以下的桩,进行连续拔起,整体结构简单可靠。The effect of adopting the above technical solutions in the present invention is: the present invention can continuously pull up the piles whose heads are located above the ground or below the ground as a whole by setting up a reinforced concrete platform, a steel structure frame platform or a composite structure platform, and the overall structure is simple. reliable.

上述技术方案之一的完善之一的改进是:所述工作平台是沉井平台,所述穿心千斤顶固定在沉井平台上。One of the improvements of one of the above technical solutions is that: the working platform is a caisson platform, and the through-core jack is fixed on the caisson platform.

本发明采用上述技术方案的效果是:本发明通过设置沉井平台,特别适用于整体位于地表以下的桩,进行连续拔起,整体结构简单可靠。The effect of adopting the above technical solutions in the present invention is that the present invention is particularly suitable for the piles located below the surface of the earth to be continuously pulled up by setting the caisson platform, and the overall structure is simple and reliable.

上述技术方案之一的完善之二是:所述锚孔的深度和锚杆的长度小于所述待拔桩的长度并大于所述锚杆的最小锚固长度,所述锚杆的最小锚固长度L按下式计算:The second improvement of one of the above technical solutions is: the depth of the anchor hole and the length of the anchor rod are less than the length of the pile to be pulled out and greater than the minimum anchoring length of the anchor rod, and the minimum anchoring length L of the anchor rod. Calculate as follows:

Figure BDA0001261711640000051
Figure BDA0001261711640000051

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

上述技术方案之一的完善之三是:所述锚索材料上设有出口分别位于锚孔底部、中部和上部处的三根灌浆管;采用压力灌浆向锚孔内灌注第一浆体,所述第一浆体是由PO52.5水泥、水泥浆孔道压浆剂和水混合而成的浆体,所述第一浆体的水胶比为0.35~0.45;采用砂浆搅拌机和注浆泵进行压力灌浆。The third improvement of one of the above technical solutions is: the anchor cable material is provided with three grouting pipes whose outlets are located at the bottom, middle and upper parts of the anchor hole; pressure grouting is used to pour the first slurry into the anchor hole, and the The first slurry is a slurry formed by mixing PO52.5 cement, cement slurry pore grouting agent and water, and the water-to-binder ratio of the first slurry is 0.35 to 0.45; a mortar mixer and a grouting pump are used to carry out pressure grout.

上述技术方案之二的改进是:所述待拔桩的顶部制有向待拔桩内的底部延伸的静态爆破孔;所述静态爆破孔中倒入有破碎剂并封堵有快硬性水泥块。The second improvement of the above technical solution is: the top of the pile to be pulled is provided with a static blasting hole extending toward the bottom of the pile to be pulled; the static blasting hole is filled with a crushing agent and blocked with fast-hardening cement blocks. .

上述技术方案之二的改进是:所述待拔桩附近的其它桩上或待拔桩周边的土体上设有工作平台。The improvement of the second technical solution above is that a working platform is provided on other piles near the piles to be pulled out or on the soil around the piles to be pulled out.

附图说明Description of drawings

下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with the accompanying drawings:

图1是本发明实施例一的拔桩回灌方法以及拔桩回灌系统采用的拔桩装置示意图。FIG. 1 is a schematic diagram of the pile pulling device adopted in the method for pulling out the pile and refilling the refilling system according to the first embodiment of the present invention.

图2是图1的左视图。FIG. 2 is a left side view of FIG. 1 .

图3是图1待拔桩上钻制的锚孔、桩体灌浆孔和静态爆破孔的示意图。FIG. 3 is a schematic diagram of the anchor hole, the pile grouting hole and the static blasting hole drilled on the pile to be pulled in FIG. 1 .

具体实施方式Detailed ways

实施例一Example 1

本实施例的拔桩回灌方法,如图1、图2和图3所示,包括以下步骤:As shown in Figure 1, Figure 2 and Figure 3, the method for pulling out piles and refilling in this embodiment includes the following steps:

1)经前处理先使待拔桩1的顶部曝露,同时备设多根高强度锚索材料2以及起吊设备。1) After pretreatment, the top of the pile 1 to be pulled out is exposed, and at the same time, multiple high-strength anchor cable materials 2 and lifting equipment are installed.

本实施例的待拔桩1是埋在在土体中摩擦桩、部分嵌岩的端承桩或是埋于地表以下一定深度的咬合桩、承台桩和打入桩,摩擦桩或端承桩的头部曝露在地表。The pile 1 to be pulled out in this embodiment is a friction pile buried in the soil, a partial rock-socketed end bearing pile, or an occlusal pile, a cap pile and a driven pile buried at a certain depth below the surface, a friction pile or an end bearing pile The head of the pile is exposed to the surface.

本实施例的锚索材料2可以是金属硬质或软质材料制成。金属硬质制成,例如:粘结钢绞束、预应力钢绞线、预应力钢绞束、高强钢丝、高强钢丝绳或高强钢筋,等等;也可以是非金属硬质或软质材料制成,例如:纤维、塑料或尼龙,等等。The anchor cable material 2 in this embodiment can be made of metal hard or soft material. Made of hard metal, such as: bonded strands, prestressed strands, prestressed strands, high-strength steel wires, high-strength steel wire ropes or high-strength steel bars, etc.; also can be made of non-metallic hard or soft materials , for example: fiber, plastic or nylon, etc.

2)在待拔桩1的顶部钻制向待拔桩内的底部延伸的锚孔1-1,在待拔桩1上钻制贯通其顶面和底面的桩体灌浆孔1-2。本实施例的锚孔1-1是位于待拔桩1横截面中心的一个锚孔或沿待拔桩1横截面中心周圈均布的至少两个锚孔。2) An anchor hole 1-1 extending toward the bottom of the pile to be pulled is drilled at the top of the pile 1 to be pulled, and a pile grouting hole 1-2 is drilled on the pile 1 to be pulled through its top and bottom surfaces. The anchor hole 1-1 in this embodiment is one anchor hole located at the center of the cross section of the pile 1 to be pulled or at least two anchor holes evenly distributed along the center circumference of the cross section of the pile 1 to be pulled.

本实施例的锚孔1-1钻孔采用履带式钻机D150,单台功率75kW;同时配15m3,1.3MPa空压机,空压机功率135kW。工作效率为60m/8hr。钻完孔后,运用清水清洗干浆,并抽干其中自由水,下锚索材料2之前,运用塞子堵住孔口,防止异物进入孔内。若待拔桩仍作为工程桩,为避免履带式钻机对桩的损伤,可以采用地质钻机钻孔。如果待拔桩1的顶面在地表以下,可以通过勘察明确桩中心及直径的桩,锚孔1-1和桩体灌浆孔1-2通过套管法钻制。The anchor hole 1-1 in this embodiment is drilled by a crawler drilling rig D150, with a single power of 75kW; and a 15m3, 1.3MPa air compressor with a power of 135kW. The working efficiency is 60m/8hr. After drilling the hole, use clean water to clean the dry slurry and drain the free water. Before lowering the anchor cable material 2, use a plug to block the hole to prevent foreign matter from entering the hole. If the pile to be pulled is still used as an engineering pile, in order to avoid damage to the pile by the crawler drilling rig, a geological drilling rig can be used to drill. If the top surface of the pile 1 to be pulled is below the ground surface, the center and diameter of the pile can be determined through investigation, and the anchor hole 1-1 and the grouting hole 1-2 of the pile body can be drilled by the casing method.

3)将锚索材料2的一端下放至锚孔1-1底部,其另一端露出待拔桩1顶部,或者下放至咬合桩、承台桩或打入桩等等桩中的锚孔的锚索材料2的另一端露出地表。3) Lower one end of the anchor cable material 2 to the bottom of the anchor hole 1-1, and the other end exposes the top of the pile 1 to be pulled out, or lower it to the anchor of the anchor hole in the occlusal pile, the cap pile or the driven pile, etc. The other end of the cable material 2 is exposed to the ground.

4)向锚孔1-1灌注第一浆体,待第一浆体固化并达到设定强度后,将锚索材料2固定于待拔桩1内形成锚杆;4) Pour the first slurry into the anchor hole 1-1, and after the first slurry is solidified and reaches the set strength, the anchor cable material 2 is fixed in the pile to be pulled 1 to form an anchor rod;

本实施例的锚孔1-1的深度和锚杆的长度小于待拔桩1的长度并大于锚杆的最小锚固长度,锚杆的最小锚固长度L按下式计算:The depth of the anchor hole 1-1 and the length of the anchor rod in this embodiment are less than the length of the pile to be pulled 1 and greater than the minimum anchoring length of the anchor rod. The minimum anchoring length L of the anchor rod is calculated as follows:

Figure BDA0001261711640000071
Figure BDA0001261711640000071

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

5)在起拔之前,可以灌注大量的水体,对拔桩1的桩底进行软化、平衡内外大气压等,然后通过起吊设备提升锚索材料2的另一端以拔起待拔桩1,在拔起待拔桩1的过程中(本实施例从拔起产生明显竖向位移后,可定为10cm,当然也可以定为其它尺寸),通过桩体灌浆孔1-2回灌第二浆体,使得第二浆体渗入待拔桩1底部的桩周土体,并将土体与待拔桩1连为整体。5) Before pulling up, a large amount of water can be poured to soften the pile bottom of the pulling pile 1, balance the internal and external atmospheric pressure, etc., and then lift the other end of the anchor cable material 2 through the lifting equipment to pull up the pile 1 to be pulled out. In the process of lifting the pile 1 to be pulled out (in this embodiment, after the obvious vertical displacement is generated from pulling up, it can be set to 10 cm, of course, it can also be set to other sizes), refill the second slurry through the grouting holes 1-2 of the pile body , so that the second slurry penetrates into the soil around the pile at the bottom of the pile 1 to be pulled, and connects the soil body with the pile 1 to be pulled as a whole.

可以将帷幕灌浆方法运用于桩的回灌,提高回灌质量;针对待拔桩1的桩周土体稳定性差的,与周边建筑物近的情况,可以采用边拔边灌,甚至双浆液固结灌浆。The curtain grouting method can be applied to the recharge of the pile to improve the quality of the recharge; for the situation where the soil around the pile to be pulled 1 has poor stability and is close to the surrounding buildings, it can be used while pulling while grouting, or even double-slurry liquid-solid. Knot grouting.

针对待拔桩1相邻的多根桩,为避免灌浆过程中,将体将相邻桩连接起来,影响下一根桩的起拔,需要同桩同桩灌注。For multiple piles adjacent to the pile to be pulled 1, in order to avoid connecting the adjacent piles during the grouting process, which affects the pulling-up of the next pile, it is necessary to cast the same pile with the same pile.

为了避免回灌对周边桩的起拔,可以回灌抗拉、剪强度极低的胶凝材料,仅起到填充作用。In order to avoid the pulling up of the surrounding piles by the refilling, the cementitious material with extremely low tensile and shear strength can be refilled, which only plays the role of filling.

采用商品砂浆,泵车进行回灌,针对灌浆孔,可以放置一根出气、出水管至桩底,桩顶通过漏斗进行快速灌浆,灌浆时桩底水、气通过通气、水孔排出桩顶,实现桩底快速、可靠灌浆。Commercial mortar is used for refilling with a pump truck. For the grouting hole, an air outlet and water outlet pipe can be placed to the bottom of the pile, and the top of the pile can be quickly grouted through a funnel. Realize fast and reliable grouting of the pile bottom.

本实施例的在步骤1)中,在待拔桩1附近的其它桩上或待拔桩周边的土体上设有工作平台3;工作平台3可以是钢筋混凝土平台、钢结构框架平台或组合结构平台,也可以是沉井平台,等等。In step 1) of this embodiment, a working platform 3 is provided on other piles near the pile 1 to be pulled or the soil around the pile to be pulled; the working platform 3 can be a reinforced concrete platform, a steel structure frame platform or a combination of Structural platform, can also be a caisson platform, and so on.

为了快速分解混凝土,实现待拔桩1的上部桩体拆除,将拔桩工程顺利转向下一工序、下一根桩:In order to quickly decompose the concrete and realize the removal of the upper pile body of the pile to be pulled 1, the pile pulling project will be smoothly transferred to the next process and the next pile:

本实施例在步骤2)中,在待拔桩1的顶部钻制向其底部延伸的静态爆破孔1-3。In this embodiment, in step 2), static blasting holes 1-3 extending toward the bottom of the pile 1 to be pulled are drilled at the top.

本实施例在步骤5)中,在通过起吊设备提升锚索材料2的另一端以拔起桩后,先在静态爆破孔1-3中倒入破碎剂并用快硬性水泥堵住静态爆破孔1-3的孔口12-18小时,然后通过破碎设备进行桩体破碎。In this embodiment, in step 5), after the other end of the anchor cable material 2 is lifted by the hoisting equipment to pull up the pile, the crushing agent is poured into the static blasting holes 1-3 and the static blasting hole 1 is blocked with fast-hardening cement -3 orifice for 12-18 hours, and then the pile body is crushed by crushing equipment.

静态爆破孔1-3是在需破除部位提前钻制出,呈“十”字型分布。破碎剂采用SCA-2型(无声破碎剂),适用于10-25℃环境,按每袋5公斤破碎剂与1.5升水调配,搅拌后,保证破碎剂完全溶解到水中成了浆体。浆体必须在搅拌后10-15分钟内倒入静态爆破孔1-3内,装填到离孔口15mm处,将浆体倒入孔中并在孔中搅动,以确保钻孔中没有气孔;填完后用快硬性水泥堵住孔口;12-18小时后可以达到效果。The static blasting holes 1-3 are drilled in advance at the parts to be blasted, and are distributed in a "cross" shape. The crushing agent adopts SCA-2 type (silent crushing agent), which is suitable for the environment of 10-25 °C. It is prepared according to 5 kg of crushing agent per bag and 1.5 liters of water. After stirring, it is ensured that the crushing agent is completely dissolved in the water to form a slurry. The slurry must be poured into the static blasting hole 1-3 within 10-15 minutes after stirring, and filled to 15mm away from the orifice, pour the slurry into the hole and stir in the hole to ensure that there is no air hole in the drilled hole; After filling, plug the orifice with fast-hardening cement; the effect can be achieved after 12-18 hours.

为了简单可靠对待拔桩1连续拔起,本实施例在在步骤5)中,起吊设备是设于工作平台3上的穿心千斤顶5,穿心千斤顶5通过反力架4安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上;当需要对整体位于地表以下的桩进行拔出时,穿心千斤顶5固定在沉井平台上,等等。穿心千斤顶5持续张拉锚索材料2的另一端以连续拔起待拔桩1。In order to simply and reliably pull up the pile 1 continuously, in step 5) in this embodiment, the lifting device is the through-center jack 5 arranged on the working platform 3, and the through-center jack 5 is installed and fixed on the reinforced concrete through the reaction force frame 4 On the platform, steel structure frame platform or composite structure platform; when it is necessary to pull out the piles located below the surface as a whole, the through-core jack 5 is fixed on the caisson platform, and so on. The piercing jack 5 continuously tensions the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled out.

为了确保灌浆密实,本实施例的锚索材料2上设有出口分别位于锚孔1-1底部、中部和上部处的三根灌浆管;采用压力灌浆向锚孔1-1内灌注第一浆体,第一浆体是由PO52.5水泥、水泥浆孔道压浆剂和水混合而成的浆体,第一浆体的水胶比为0.35~0.45;采用砂浆搅拌机和注浆泵进行压力灌浆。压浆前可以进行砂浆块制作试验,确保试块3d强度达到25MPa,10d强度达到30MPa。当然也可以采用常态灌浆管,第一浆体还可以是砂浆或砂,等等。In order to ensure the grouting is dense, the anchor cable material 2 in this embodiment is provided with three grouting pipes whose outlets are located at the bottom, middle and top of the anchor hole 1-1 respectively; pressure grouting is used to pour the first grout into the anchor hole 1-1 , the first slurry is a slurry composed of PO52.5 cement, cement slurry grouting agent and water, and the water-to-binder ratio of the first slurry is 0.35 to 0.45; a mortar mixer and a grouting pump are used for pressure grouting . Before grouting, the mortar block production test can be carried out to ensure that the 3d strength of the test block reaches 25MPa, and the 10d strength reaches 30MPa. Of course, a normal grouting pipe can also be used, and the first slurry can also be mortar or sand, and so on.

采用砂浆搅拌机和注浆泵进行压力灌浆(灌注第一浆体)。灌注第一浆体由底部向上灌浆,当灌至上一个个灌浆管时,开启上一灌浆管,直至灌至设计位置。每次灌浆制作3组水泥浆试块,采用砂浆块,待3d、7d压制试块,待强度达到后可以进行提升。Pressure grouting (priming the first grout) is carried out using a mortar mixer and a grouting pump. The first grout is grouted from the bottom upwards. When grouting to the last grouting pipe, open the last grouting pipe until it reaches the design position. Three groups of cement slurry test blocks were made for each grouting, and mortar blocks were used. After 3d and 7d, the test blocks were pressed, and they could be upgraded after the strength was reached.

如图1、图2和图3所示,本实施例的拔桩回灌系统,用于上述的拔桩回灌方法中,该拔桩回灌系统设置于固定在土体中并顶部曝露的待拔桩1附近,包括多根高强度锚索材料2和起吊设备。As shown in Fig. 1, Fig. 2 and Fig. 3, the pile-pulling refilling system of the present embodiment is used in the above-mentioned pulling-pile refilling method. The vicinity of the pile 1 to be pulled out includes a plurality of high-strength anchor cable materials 2 and lifting equipment.

本实施例的拔桩回灌系统的待拔桩1也是埋在在土体中摩擦桩、部分嵌岩的端承桩或是埋于地表以下一定深度的咬合桩、承台桩和打入桩,摩擦桩或端承桩的头部曝露在地表。The to-be-pulled pile 1 of the pulling-pile-refilling system of the present embodiment is also a friction pile buried in the soil, a partially rock-socketed end bearing pile, or an occlusal pile, a cap pile and a driven pile buried at a certain depth below the surface. , the head of the friction pile or end bearing pile is exposed to the surface.

本实施例的拔桩回灌系统的锚索材料2也可以是金属硬质或软质材料制成,例如:粘结钢绞束、预应力钢绞线、预应力钢绞束、高强钢丝、高强钢丝绳或高强钢筋,等等;也可以是非金属硬质或软质材料制成,例如:纤维、塑料或尼龙,等等。The anchor cable material 2 of the pile-pulling and refilling system in this embodiment can also be made of metal hard or soft materials, such as: bonded steel strands, prestressed steel strands, prestressed steel strands, high-strength steel wires, High-strength steel wire rope or high-strength steel bar, etc.; it can also be made of non-metallic hard or soft materials, such as fiber, plastic or nylon, etc.

待拔桩1的顶部制有向待拔桩内的底部延伸的锚孔1-1,待拔桩1上制有贯通其其顶面和底面的桩体灌浆孔1-2,锚索材料2的一端设于锚孔1-1底部,锚索材料2的另一端露出待拔桩1顶部;本实施例的锚孔1-1是位于待拔桩1横截面中心的一个锚孔或沿待拔桩1横截面中心周圈均布的至少两个锚孔。The top of the pile to be pulled 1 is formed with an anchor hole 1-1 extending toward the bottom of the pile to be pulled, the pile 1 to be pulled is formed with a pile grouting hole 1-2 penetrating its top surface and bottom surface, and the anchor cable material 2 One end is set at the bottom of the anchor hole 1-1, and the other end of the anchor cable material 2 is exposed at the top of the pile 1 to be pulled out; the anchor hole 1-1 in this embodiment is an anchor hole located in the center of the cross section of the pile 1 to be pulled out or along the At least two anchor holes are evenly distributed around the center of the cross section of the pulling pile 1 .

锚孔1-1内灌注有固化后用于将锚索材料2固定于待拔桩1内以形成锚杆的第一浆体,起吊设备用于提升锚索材料2的另一端以拔起待拔桩1,桩体灌浆孔1-2用于在拔桩过程中回灌第二浆体。The anchor hole 1-1 is filled with the first slurry that is used to fix the anchor cable material 2 in the pile 1 to be pulled to form the anchor rod after curing, and the lifting device is used to lift the other end of the anchor cable material 2 to pull up the to-be-pulled pile. Pulling the pile 1, the grouting hole 1-2 of the pile body is used to refill the second slurry during the pulling of the pile.

本实施例的拔桩回灌系统的锚孔1-1的深度和锚杆的长度也小于待拔桩1的长度并大于锚杆的最小锚固长度,锚杆的最小锚固长度L按下式计算:The depth of the anchor hole 1-1 and the length of the anchor rod of the pull-out pile reinjection system of the present embodiment are also smaller than the length of the pile to be pulled 1 and greater than the minimum anchoring length of the anchor rod. The minimum anchoring length L of the anchor rod is calculated by the following formula :

Figure BDA0001261711640000101
Figure BDA0001261711640000101

式中,a为安全系数;σ为锚索材料强度;A为锚索材料截面面积;d为锚孔直径;τ为锚杆与孔壁抗剪强度。In the formula, a is the safety factor; σ is the strength of the anchor cable material; A is the cross-sectional area of the anchor cable material; d is the diameter of the anchor hole; τ is the shear strength of the anchor rod and the hole wall.

本实施例的待拔桩1的顶部制有向待拔桩内的底部延伸的静态爆破孔1-3;静态爆破孔1-3中倒入有破碎剂并封堵有快硬性水泥块。The top of the pile 1 to be pulled in this embodiment is provided with static blasting holes 1-3 extending toward the bottom of the pile to be pulled; the static blasting holes 1-3 are filled with a crushing agent and blocked with fast-hardening cement blocks.

本实施例的待拔桩1附近的其它桩上或待拔桩1周边的土体上设有工作平台3。起吊设备是设于工作平台3上的穿心千斤顶5,工作平台3是钢筋混凝土平台、钢结构框架平台、组合结构平台或沉井平台,等等。In this embodiment, a working platform 3 is provided on other piles near the pile 1 to be pulled out or on the soil body around the pile 1 to be pulled out. The hoisting equipment is a piercing jack 5 provided on the working platform 3, and the working platform 3 is a reinforced concrete platform, a steel structure frame platform, a composite structure platform or a caisson platform, and so on.

穿心千斤顶5通过反力架4安装固定在钢筋混凝土平台、钢结构框架平台或组合结构平台上。当需要对整体位于地表以下的桩进行拔出时,穿心千斤顶5固定在沉井平台上,等等。穿心千斤顶5用于持续张拉锚索材料2的另一端以连续拔起待拔桩1。The through-core jack 5 is installed and fixed on the reinforced concrete platform, the steel structure frame platform or the combined structure platform through the reaction force frame 4 . When it is necessary to pull out the pile which is entirely below the surface, the through-core jack 5 is fixed on the caisson platform, and so on. The through-core jack 5 is used to continuously tension the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled out.

本实施例的拔桩回灌系统的锚索材料2上也设有出口分别位于锚孔1-1底部、中部和上部处的三根灌浆管。The anchor cable material 2 of the pile pulling and refilling system in this embodiment is also provided with three grouting pipes whose outlets are located at the bottom, the middle and the upper part of the anchor hole 1-1 respectively.

实施例二Embodiment 2

本实施例的拔桩回灌方法,是在实施例一基础上的改进,与实施例一的不同之处在于:The method for pulling out piles and refilling in the present embodiment is an improvement on the basis of Embodiment 1, and the difference from Embodiment 1 is:

本实施例需要提升的待拔桩1总长24m,桩径1500mm,该桩需提升高度达7-8m,占该待拔桩1的总长24m的30%。经过计算,拔桩力设计荷载为8000kN,校核荷载为10000kN。The total length of the pile to be pulled 1 to be lifted in this embodiment is 24m, the diameter of the pile is 1500mm, and the height of the pile to be lifted is 7-8m, accounting for 30% of the total length of the pile to be pulled 1 24m. After calculation, the design load of pile pulling force is 8000kN, and the check load is 10000kN.

这样,锚索材料2采用选用4束CPS15A-12型剪力分散型锚索。每束CPS15A-14型剪力分散型锚索采用14-φ15.24高强度、低松弛钢绞线,抗拉强度为1860MPa。In this way, the anchor cable material 2 adopts 4 bundles of CPS15A-12 shear force dispersion anchor cables. Each bundle of CPS15A-14 shear-distributed anchor cables adopts 14-φ15.24 high-strength, low-relaxation steel strands with a tensile strength of 1860MPa.

本实施例的起吊设备还是采用穿心千斤顶5,选用4台4000kN穿心千斤顶5作为提升动力设备,按0.8效率考虑,总提升能力达12800kN。The hoisting equipment in this embodiment still adopts the through-center jacks 5, and four sets of 4000kN through-center jacks 5 are selected as the lifting power equipment. Considering the efficiency of 0.8, the total lifting capacity reaches 12800kN.

放线之前,首先将反力架4位置编制于地坪上,然后根据反力架4可布设位置确定锚孔1-1位置。本实施例的锚孔1-1是中心分布在边长为60cm的正方形四个角点的四个锚孔,锚孔1-1孔径150mm,正方形的边长分别与反力架大梁平行与垂直。Before setting out the line, firstly prepare the position of the reaction force frame 4 on the floor, and then determine the position of the anchor hole 1-1 according to the position of the reaction force frame 4 that can be laid out. The anchor holes 1-1 in this embodiment are four anchor holes whose centers are distributed at the four corners of a square with a side length of 60cm. The hole diameter of the anchor holes 1-1 is 150mm. The side lengths of the square are parallel and perpendicular to the reaction frame beam respectively. .

由于桩周受挡墙、渠壁等连接影响,可以采用履带式钻机D150,将该连接通过钻孔消除。消除该连接时,钻孔范围适当加大、加深,防止强连接以下范围存在较大的扩孔与塌孔。强连接消除选择与锚孔1-1同期进行。Since the pile circumference is affected by the connection of the retaining wall and the canal wall, the crawler drilling rig D150 can be used to eliminate the connection through drilling. When the connection is eliminated, the drilling range should be appropriately enlarged and deepened to prevent large reaming and collapsing in the range below the strong connection. The strong connection elimination selection is performed at the same time as the anchor hole 1-1.

桩周与土层间的摩阻部分消除,是通过在桩周钻制一定数量的孔、适当冲水实现消除桩周磨阻。孔内下直径50PVC花管,一方面防止塌孔,另一方面用于通过桩体灌浆孔1-2回灌第二浆体时,桩体灌浆孔底的水体通过桩体灌浆孔底从桩顶孔口溢出;第二浆体渗入待拔桩1底部的桩周土体,将土体与待拔桩1连为整体,加固桩周土体,恢复待拔桩1的作用。The friction between the pile circumference and the soil layer is partially eliminated by drilling a certain number of holes around the pile and properly flushing the pile to eliminate the friction around the pile. The bottom diameter of the hole is 50 PVC flower tube, on the one hand to prevent the hole from collapsing, on the other hand, when the second slurry is refilled through the pile grouting hole 1-2, the water body at the bottom of the pile grouting hole passes from the pile to the bottom of the pile grouting hole. The top hole overflows; the second slurry penetrates into the soil around the pile at the bottom of the pile 1 to be pulled, connects the soil body with the pile 1 to be pulled as a whole, strengthens the soil around the pile, and restores the function of the pile 1 to be pulled.

可以在建筑物沉降观测的基础上,确定回灌时机、回灌压力。对于建筑物安全,回灌宜早不宜迟,对于相邻桩提升具有挤密效果,宜迟不宜早。回灌压力过大,易造成周边建筑物上升,本次消阻范围相对较小,采用不超过1MPa的低压回灌。The timing and pressure of recharge can be determined based on the observation of building settlement. For the safety of the building, the refilling should be done sooner rather than later, and the adjacent piles have a compacting effect, so it should be sooner rather than later. If the recharge pressure is too large, it is easy to cause the surrounding buildings to rise. This time the resistance range is relatively small, and the low pressure recharge not exceeding 1MPa is used.

拔桩分为以下几个阶段,将预估提升力分为10级,每级观察10钟,每分钟测一次数据,分析桩顶位移随时间变化与随荷载变化关系。同时监测地表沉降位移、结构应力与变形。预估提升力为8000kN,具体荷载分级为800kN、1600kN,2400kN,直至启动荷载。实施例三The pile pulling is divided into the following stages. The estimated lifting force is divided into 10 levels, each level is observed for 10 minutes, and the data is measured every minute, and the relationship between the displacement of the pile top with time and the change with the load is analyzed. Simultaneously monitor surface settlement displacement, structural stress and deformation. The estimated lifting force is 8000kN, and the specific load classification is 800kN, 1600kN, 2400kN, until the starting load. Embodiment 3

本实施例的拔桩回灌方法,是在实施例一和实施例二基础上的改进,与上述实施例的不同之处在于:本实施例在在步骤5)中,起吊设备采用设于工作平台3上的吊机或卷扬机,吊机或卷扬机持续张拉锚索材料2的另一端以连续拔起待拔桩1。吊机或卷扬机设于钢筋混凝土平台、钢结构框架平台或组合结构平台上。The method for pulling out piles and refilling in this embodiment is an improvement on the basis of Embodiments 1 and 2. The difference from the above-mentioned embodiment is that in this embodiment, in step 5), the hoisting equipment adopts a working The crane or hoist on the platform 3 continuously stretches the other end of the anchor cable material 2 to continuously pull up the pile 1 to be pulled. The crane or hoist is installed on the reinforced concrete platform, the steel structure frame platform or the combined structure platform.

本发明不局限于上述实施例。凡采用等同替换形成的技术方案,均落在本发明要求的保护范围。The present invention is not limited to the above-described embodiments. All technical solutions formed by equivalent replacements fall within the protection scope of the present invention.

Claims (10)

1. A pile pulling and recharging method is characterized by comprising the following steps:
1) exposing the top of the pile to be pulled out through pretreatment, and simultaneously preparing a plurality of high-strength anchor cable materials and hoisting equipment;
2) drilling an anchor hole extending to the bottom in the pile to be pulled at the top of the pile to be pulled, and drilling a pile body grouting hole penetrating through the top surface and the bottom surface of the pile to be pulled;
3) one end of the anchor cable material is lowered to the bottom of the anchor hole, and the other end of the anchor cable material is exposed out of the top of the pile to be pulled;
4) pouring first slurry into the anchor hole, and fixing the anchor cable material into the pile to be pulled to form an anchor rod after the first slurry is solidified and reaches a set strength;
5) and lifting the other end of the anchor cable material by using lifting equipment to pull up the pile to be pulled, and recharging the second slurry through the pile body grouting hole in the process of pulling up the pile to be pulled so that the second slurry permeates into the soil body around the pile at the bottom of the pile to be pulled and connects the soil body and the pile to be pulled into a whole.
2. The pile pulling and recharging method of claim 1, wherein: in the step 2), drilling a static blast hole extending to the bottom of the pile to be pulled at the top of the pile to be pulled; in the step 5), after the other end of the anchor cable material is lifted by a lifting device to pull up the pile, firstly, a crushing agent is poured into the static blast hole and the orifice of the static blast hole is blocked by quick-hardening cement for 12-18 hours, and then, the pile body is crushed by a crushing device.
3. A pile pulling and recharging method as defined in claim 1 or 2, wherein: in the step 1), a working platform is arranged on other piles near the pile to be pulled or on soil around the pile to be pulled; in the step 5), the hoisting equipment is a penetrating jack, a crane or a winch which is arranged on the working platform, and the penetrating jack, the crane or the winch continuously stretches the other end of the anchor cable material to continuously pull up the pile to be pulled.
4. The pile pulling and recharging method of claim 3, wherein: the working platform is a reinforced concrete platform, a steel structure frame platform or a combined structure platform; the center-penetrating jack is fixedly arranged on the reinforced concrete platform, the steel structure frame platform or the combined structure platform through a reaction frame; the crane or the winch is arranged on the reinforced concrete platform, the steel structure frame platform or the combined structure platform.
5. The pile pulling and recharging method of claim 3, wherein: the working platform is a sunk well platform, and the center penetrating jack is fixed on the sunk well platform.
6. A pile pulling and recharging method as defined in claim 1 or 2, wherein: the depth of the anchor hole and the length of the anchor rod are smaller than the length of the pile to be pulled and larger than the minimum anchoring length of the anchor rod, and the minimum anchoring length L of the anchor rod is calculated according to the following formula:
Figure FDA0001261711630000021
in the formula, a is a safety factor; sigma is the strength of the anchor cable material; a is the cross-sectional area of the anchor cable material; d is the anchor eye diameter; tau is the shear strength of the anchor rod and the hole wall.
7. A pile pulling and recharging method as defined in claim 1 or 2, wherein: the anchor cable material is provided with three grouting pipes with outlets respectively positioned at the bottom, the middle part and the upper part of the anchor hole; pouring first slurry into the anchor hole by adopting pressure grouting, wherein the first slurry is slurry formed by mixing PO52.5 cement, a cement slurry pore canal grouting agent and water, and the water-cement ratio of the first slurry is 0.35-0.45; and (5) performing pressure grouting by adopting a mortar stirrer and a grouting pump.
8. A pile pulling and recharging system is used in the pile pulling and recharging method of claim 1, and is arranged near a pile to be pulled which is fixed in a soil body and exposed at the top, and comprises a plurality of high-strength anchor cable materials and hoisting equipment, and is characterized in that an anchor hole extending towards the bottom in the pile to be pulled is formed at the top of the pile to be pulled, a pile body grouting hole penetrating through the top surface and the bottom surface of the pile to be pulled is formed in the pile to be pulled, one end of each anchor cable material is arranged at the bottom of the anchor hole, and the other end of each anchor cable material is exposed out of the top of the pile to be pulled; the anchor hole is filled with first slurry which is used for fixing the anchor cable material in the pile to be pulled out after solidification so as to form an anchor rod, the hoisting equipment is used for lifting the other end of the anchor cable material so as to pull up the pile to be pulled out, and the pile body grouting hole is used for recharging second slurry in the pile pulling process.
9. The pile pulling and recharging system of claim 8, wherein: a static blasting hole extending towards the bottom in the pile to be pulled is formed in the top of the pile to be pulled; and a breaking agent is poured into the static blasting hole and a rapid hardening cement block is blocked.
10. The pile pulling and recharging system of claim 8, wherein: and working platforms are arranged on other piles near the pile to be pulled or soil around the pile to be pulled.
CN201710213872.XA 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system Active CN106968252B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710213872.XA CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710213872.XA CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Publications (2)

Publication Number Publication Date
CN106968252A CN106968252A (en) 2017-07-21
CN106968252B true CN106968252B (en) 2022-08-09

Family

ID=59336156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710213872.XA Active CN106968252B (en) 2017-04-01 2017-04-01 Pile pulling recharging method and pile pulling recharging system

Country Status (1)

Country Link
CN (1) CN106968252B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107421816A (en) * 2017-08-10 2017-12-01 北京林业大学 A kind of stratum splitting drag Rapid measuring and its assay method
CN108894224A (en) * 2018-08-03 2018-11-27 中冶沈勘工程技术有限公司 A kind of method for pulling out of static pressure pipe pile
CN113737796A (en) * 2021-09-07 2021-12-03 江苏兴宇建设集团有限公司 Construction method for high-pressure water flushing assisted pile driving and pile pulling synchronous grouting of steel plate pile

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1206421C (en) * 2003-06-12 2005-06-15 上海隧道工程股份有限公司 A drill hole grout pile drag reduction extraction process
CN101886390B (en) * 2010-06-12 2012-06-27 中铁十六局集团有限公司 All casing static pressure pile pulling technology in narrow space
CN204475338U (en) * 2015-02-05 2015-07-15 温州荣强海洋科技有限公司 A kind of single sleeve pipe is without the pile pulling device of water burst no swell mud
CN204662442U (en) * 2015-03-27 2015-09-23 江苏高速公路工程养护有限公司 Highway barrier hydraulic pressure inner bearing type gets an equipment
CN105442605B (en) * 2015-11-20 2017-06-30 常州第一建筑集团有限公司 Extract PHC and be reused in deep foundation pit supporting construction method
CN206902712U (en) * 2017-04-01 2018-01-19 南京瑞迪建设科技有限公司 Pile pulling recharge system

Also Published As

Publication number Publication date
CN106968252A (en) 2017-07-21

Similar Documents

Publication Publication Date Title
CN103924585B (en) The construction method of wind-powered electricity generation socketed pile
CN106948347B (en) Pile pulling method and pile pulling system
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN110106889A (en) A kind of deep basal pit perfusion slope protection pile adds cable bolting construction
CN106968252B (en) Pile pulling recharging method and pile pulling recharging system
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN106930296A (en) A kind of construction method of internal support of foundation pit
CN210766754U (en) Recoverable prestressed anchorage cable stock supporting construction
CN105862862B (en) A kind of large diameter pile buries hammer Refloatation method
CN109024721A (en) A kind of underpinning and improve the method that ability is cut in the bending resistance of existing building rigid foundation
CN205576896U (en) That can effectively reduce engineering cost takes steel reinforcement cage construction hole stake
CN206902712U (en) Pile pulling recharge system
CN107059872B (en) Diagonal cable pile pulling method and diagonal cable pulling pile system
CN206928296U (en) Pile pulling system
CN206902710U (en) Retaining wall and counter-force open caisson platform pile pulling system
CN111042820B (en) Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method
CN205712171U (en) A kind of retaining wall reinforcement structure
CN107023008B (en) Pile pulling method and system for open caisson platform for retaining wall and counterforce
CN206902713U (en) Oblique cord pile pulling system
CN105951874A (en) Retaining wall reinforcing structure and construction method thereof
CN206570811U (en) Existing bridge pile pulling device is passed through in weak soil shield driving area
CN212896321U (en) Backfill structure of ultra-deep major diameter stake hole
CN107447775A (en) Landslide disaster body makes ground draining reinforced earth retaining wall structure

Legal Events

Date Code Title Description
PB01 Publication
CB03 Change of inventor or designer information

Inventor after: Liu Haixiang

Inventor after: Chen Liang

Inventor after: Ke Minyong

Inventor after: Tang Yunqing

Inventor after: Zhang Min

Inventor after: Lu Wenyan

Inventor after: Long Zhiyong

Inventor after: Chen Xining

Inventor after: Wang Lingjun

Inventor before: Liu Haixiang

Inventor before: Chen Liang

Inventor before: Ke Minyong

Inventor before: Tang Yunqing

Inventor before: Lu Wenyan

Inventor before: Long Zhiyong

Inventor before: Chen Xining

Inventor before: Wang Lingjun

CB03 Change of inventor or designer information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant