Snippet
A completed part of the Bolu Tunnel at Elmalık side collapsed during the 1999 Düzce earthquake. In order to by-pass the collapsed section, a new tunnel route was determined. 474 meters of the new route, including two portals and double tubing, crossed through the …
- 238000004458 analytical method 0 title description 44
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/34—Foundations for sinking or earthquake territories
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/48—Chocks or the like
- E21D15/483—Chocks or the like made of flexible containers, e.g. inflatable, with or without reinforcement, e.g. filled with water, backfilling material or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Lay-outs therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Sinha | Underground structures: design and instrumentation | |
Juran et al. | Ground anchors and soil nails in retaining structures | |
Tong et al. | Highway construction across heavily mined ground and steep topography in southern China | |
Shi et al. | Sub-horizontal reinforcement of weathered granite before tunneling beneath a spillway | |
Zhang et al. | Effect of closely spaced twin tunnel construction beneath an existing subway station: A case study | |
Sterpi et al. | Soil nailing at the tunnel face in difficult conditions: A case study | |
Amiri et al. | Comparison of shallow tunneling method with pile and rib method for construction of subway station in soft ground | |
Wen et al. | Factors that affect the stability of roads around rocks | |
Aşçıoğlu | Analysis of support design practice at Elmalık portals of Bolu tunnel | |
di Prisco et al. | Assessment of excavation-related hazards and design of mitigation measures | |
Simon et al. | Restoring RW5 at Yeager Airport: Design and construction of a tall retaining wall on the side of a mountain | |
Tan et al. | Challenges in design and construction of deep excavation for KVMRT in Kuala Lumpur limestone formation | |
Alali | Improvement Of Soil By Nailing | |
Herranz et al. | SEM crossover cavern in Downtown LA | |
Mutton et al. | Design of water holding bulkheads for Coal Mines | |
Bineshian | I-System: Index of ground-structure definition, applications, and utilisation in design/practice | |
Lee et al. | Review and perspective of expressway tunnels in Taiwan, China | |
DA FONSECA et al. | Project and construction of Underground stations and tunnels (TBM and NATM) in heterogeneous masses for Metro do Porto | |
Lu et al. | Tunnel stability and in-situ rock stress | |
Elyasi et al. | Efficiency assessment of l-profiles and pipe fore-poling pre-support systems in difficult geological conditions: A case study | |
Johns et al. | Oahe dam: influence of shale on Oahe power structures design | |
Romani et al. | The design of Venezia station of Rome Line C underground | |
Singh et al. | Challenges and Remedies during Construction of the North-south Corridor of Pune Metro through Deccan Basaltic Rocks-A Case Study | |
Castelli et al. | Connecting Continents: Challenges of the Eurasia Tunnel in Istanbul | |
Baines et al. | DINORWIG PUMPED STORAGE SCHEME. PART 1: DESIGN. PART 2: CONSTRUCTION. |