Nguyen, 2023 - Google Patents
Analysis the Causes of the Slip Embankment Protecting the Slope of Lien Chieu Aviation Petroleum DepotNguyen, 2023
View PDF- Document ID
- 14861444100792510957
- Author
- Nguyen H
- Publication year
- Publication venue
- International Conference on Civil Engineering
External Links
Snippet
The slope protection embankment of Lien Chieu aviation petroleum depot was built in 2001. The embankment is responsible for ensuring safety for the oil tank area and dispensing area, with the capacity of dispensing 13,800 m3 of fuel serving airports in the central region …
- 238000004458 analytical method 0 title abstract description 13
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealing or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; construction methods therefor
- E02B2017/0056—Platforms with supporting legs
- E02B2017/0073—Details of sea bottom engaging footing
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
- E01C23/06—Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
- E01C23/10—Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for raising or levelling sunken paving; for filling voids under paving; for introducing material into substructure
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Cubrinovski | Liquefaction-Induced Damage in The2010-2011 Christchurch (New Zealand) Earthquakes | |
Tan et al. | Review of cave-in failures of urban roadways in China: A database | |
Waltham | Sinkhole hazard case histories in karst terrains | |
Zumrawi et al. | Importance of deep excavation support and its influence on adjacent buildings | |
Tafreshi et al. | Expanded polystyrene geofoam | |
Mohri et al. | Damage to agricultural facilities | |
Terzaghi et al. | Mission Dam an Earth and Rockfill Dam on a Highly Compressible Foundation | |
Bromhead | The Treatment of Landslides. | |
Khomenko | Suffosion hazard: today’s and tomorrow’s problem for cities | |
Nguyen | Analysis the Causes of the Slip Embankment Protecting the Slope of Lien Chieu Aviation Petroleum Depot | |
Luehring et al. | Liquefaction mitigation of a silty dam foundation using vibro-stone columns and drainage wicks: a case history at salmon lake dam | |
Lambrechts et al. | Soil mixing to stabilize organic clay for I-95 widening, Alexandria, VA | |
Adamo et al. | Dam safety: Technical problems of aging embankment dams | |
MINES | REPOR | |
Bromhead | Geotechnical structures for landslide risk reduction | |
Doulala-Rigby | Celebrating Reinforced Soil Structures: A Historic Review from the Mid-60’s Original Concept to Today’s Design and GOOD Construction Practice Using Site-Won and Other Non-‘Standard’Reinforced Soil Fills | |
Doulala-Rigby | A Historic Review from the Mid-60's Original Concept to Today's Design and GOOD Construction Practice Using Site-Won and Other Non-‘Standard'Reinforced Soil Fills | |
Hearn et al. | C3 Soil slope stabilization | |
Zhang et al. | Excavation Failure Cases and Analysis | |
Fergason et al. | Mitigation Strategies and Engineering Solutions for Infrastructure at Risk from Earth Fissures | |
Davis | Liquefaction impacts on lifeline systems: Christchurch, New Zealand, examples | |
Hou et al. | Practical Solutions for Mountainous Pipeline Construction: Mechanically Stabilized Earth Retaining Walls on a Western Canadian Transmission Pipeline Project | |
French et al. | Reinforced soil technique for temporary slope stabilisation in loose saturated ground | |
Blower | 10. Managing Groundwater in the Engineering Design & Construction of Surface Works | |
Tudor et al. | Considerations regarding the risk of land degradation induced by mining operations in coal open pits |