Snippet
Open-pit mine design and long-term planning are crucial parts of the mining industry. It contains the technical plan that must be followed from the beginning of mine development to mine closure. Every deposit can be mined entirely, however, many things need to be …
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/20—Handling natural language data
- G06F17/21—Text processing
- G06F17/24—Editing, e.g. insert/delete
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/20—Handling natural language data
- G06F17/21—Text processing
- G06F17/22—Manipulating or registering by use of codes, e.g. in sequence of text characters
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/50—Computer-aided design
- G06F17/5086—Mechanical design, e.g. parametric or variational design
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING; COUNTING
- G06F—ELECTRICAL DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/30—Information retrieval; Database structures therefor; File system structures therefor
- G06F17/30067—File systems; File servers
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/16—Enhanced recovery methods for obtaining hydrocarbons
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Whittle et al. | Combined optimisation of an open-pit mine outline and the transition depth to underground mining | |
Froyland et al. | The value of additional drilling to open pit mining projects | |
Elahi et al. | A new algorithm for optimum open pit design: Floating cone method III | |
Pourrahimian | Mathematical programming for sequence optimization in block cave mining | |
Javanshirgiv et al. | The selection of an underground mining method using the fuzzy topsis method: A case study in the Kamar Mahdi II fluorine mine | |
US9773075B2 (en) | Underground tactical optimization | |
NZ539421A (en) | System and method(s) of mine planning, design and processing | |
Utili et al. | Optimal pitwall shapes to increase financial return and decrease carbon footprint of open pit mines | |
Erdogan et al. | Application of Three Existing Stope Boundary Optimisation Methods in an Operating Underground Mine | |
Agosti et al. | Design of an open-pit gold mine by optimal pitwall profiles | |
Self et al. | Reducing drilling cost by finding optimal operational parameters using particle swarm algorithm | |
Ugarte Zarate et al. | Optimizing block caving drawpoints over multiple geostatistical models | |
Vlachogiannis et al. | Proposed formulas for pillar stress estimation in a regular room-and-pillar pattern | |
Purevdavaa et al. | Ultimate pit limit optimization by computerized and manual methods for Dadiin Khar Tolgoi–2 Coal Mine–A case study | |
Mariko et al. | Open pit optimisation and design of tabakoto pit at anglogold ashanti sadiola mine using surpac and whittle software | |
Grieco et al. | Grade uncertainty in stope design—improving the optimisation process | |
MacNeil et al. | A stochastic optimization formulation for the transition from open-pit to underground mining within the context of a mining complex | |
Rahimdel | Selection of the Most Proper Underground Mining Method for Kodakan Gold Mine in Iran | |
Shenavar et al. | Evaluation of underground mineable reserve in presence of grade and commodity price uncertainties | |
Shami-Qalandari et al. | Determining a resilient stope boundary for underground mass mining projects | |
Ben-Awuah | Oil sands mine planning and waste management using goal programming | |
Paweł | Simulation possibilites of the post-mining goafs impact on the deformations induced by next underground mining operations with use of the cellular automata method | |
Nguyen et al. | Robust optimization of unconventional reservoirs under uncertainties | |
Chimunhu et al. | Development of Novel Hybrid Intelligent Predictive Models for Dilution Prediction in Underground Sub-level Mining | |
Deressa et al. | Integrated approach to reserve estimation and optimal open pit design for hydrothermal gold deposit |