WO2007053895A1 - Structural cavity - Google Patents
Structural cavity Download PDFInfo
- Publication number
- WO2007053895A1 WO2007053895A1 PCT/AU2006/001674 AU2006001674W WO2007053895A1 WO 2007053895 A1 WO2007053895 A1 WO 2007053895A1 AU 2006001674 W AU2006001674 W AU 2006001674W WO 2007053895 A1 WO2007053895 A1 WO 2007053895A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- cavity
- structural cavity
- settable material
- structural
- stabilised
- Prior art date
Links
- 239000000463 material Substances 0.000 claims abstract description 69
- 238000000034 method Methods 0.000 claims abstract description 29
- 239000008187 granular material Substances 0.000 claims abstract description 11
- 238000005507 spraying Methods 0.000 claims description 3
- 239000003381 stabilizer Substances 0.000 claims description 3
- 239000004035 construction material Substances 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 13
- 239000002184 metal Substances 0.000 description 8
- 239000004567 concrete Substances 0.000 description 4
- 239000004568 cement Substances 0.000 description 3
- -1 for example Substances 0.000 description 2
- 239000011378 shotcrete Substances 0.000 description 2
- 230000006641 stabilisation Effects 0.000 description 2
- 229920001732 Lignosulfonate Polymers 0.000 description 1
- 239000004117 Lignosulphonate Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000007717 exclusion Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 235000019357 lignosulphonate Nutrition 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 239000011236 particulate material Substances 0.000 description 1
- 239000011120 plywood Substances 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
Definitions
- the present invention relates to a structural cavity.
- the invention has been devised particularly, although not solely, as a structural cavity in the form of a tunnel.
- a tunnel in accordance with the invention is particularly suitable as an in- ground tunnel.
- In-ground tunnels are constructed for various purposes.
- a tunnel can be constructed to provide an overpass above a location.
- a tunnel may also be constructed in the establishment of a material loading system involving a stockpile of particulate material above the tunnel, with provision for loading material from the stockpile into load carrying vehicles located at a loading zone within the tunnel.
- a tunnel is constructed at ground level and earth material built up around the tunnel structure thereby forming an in-ground tunnel.
- One construction method involves use of a robust metal arch to define the interior profile of the tunnel and form a supporting frame over which select material is backfilled.
- the select backfill typically comprises a sand or other granular material which must match strict quality and specifications.
- Another method involves a heavy duty metal arch which acts as formwork against which a load supporting concrete structure can be constructed.
- the present invention seeks to address these problems through construction of a stable structure using relatively lightweight and readily available materials. Further, safety problems are overcome or at least reduced because construction personnel can work on a solid ground surface at all times.
- the form preferably remains as a permanent feature of the structural cavity, in which the inner surface of the structural cavity is defined by the form.
- the form may be removed such that the inner surface of the structural cavity is defined by the inner surface of the settable material.
- a continuous arch of metal sheeting is particularly convenient for constructing the form, although a range of materials may be used, for example, plywood.
- the metal sheeting extends continuously between opposite sides of the cavity.
- the form is anchored at the ends thereof. Where the structural cavity is constructed on the ground, the ends of the form are typically anchored to footings in the ground.
- the settable material preferably comprises a conglomerate construction material, for example, concrete.
- the concrete is applied by spraying, in which case it may comprise shot-crete.
- the settable material is reinforced, typically by means of metal reinforcement such as mesh.
- the settable material is applied in a layer.
- the layer formed by the settable material is preferably of adequate thickness to provide either the required stability for the structural cavity, or such that the strength of the layer of settable material is at least 15MPa.
- the stabilised granular material may be of any grade or specification, making earth material quite suitable for this purpose, whereby the earth material is stabilised by a suitable stabilising agent, for example, cement or lignosulphonates.
- a suitable stabilising agent for example, cement or lignosulphonates.
- the quantity of stabilising agent required is variable, depending on the type of earth material and the desired design strength upon stabilisation. Construction of the structural cavity by the addition of both the settable material and the stabilised granular material is preferably conducted in stages, building from the ground up.
- the cavity comprises a tunnel
- a structural cavity comprising;
- a load supporting structure establishing the profile of at least the upper portion of the cavity
- the load supporting structure may comprise a layer of settable material which has set.
- the load supporting structure preferably comprises a form to which the settable material was applied during construction of the tunnel.
- the form comprises metal sheeting extending continuously between two opposed sides of the cavity.
- the structural cavity may be constructed on mine sites underneath ore stockpiles.
- chutes are preferably incorporated into the upper portion of the cavity to allow access to the stockpile from the cavity.
- Figure 1 is a cross sectional view of the structural cavity in accordance with the first embodiment
- Figures 2 to 9 are a sequence of diagrams showing the stages of construction of the structural cavity.
- Figure 10 is a cross sectional view of the structural cavity in accordance with the second embodiment.
- FIGs 1 to 9 there is shown a first embodiment of a structural cavity 10, in accordance with the present invention, in the form of an in-ground tunnel.
- the structural cavity 10 comprises a form 12 establishing the profile of the structural cavity 10, a layer of settable material 16, and an overlay of stabilised earth material 18. Retention of the stabilised earth material is aided by backfilling using a compacted backfill material 20.
- the form 12 is supported by a temporary support structure 14 (as shown in Figures 4 to 9) prior to placement of the settable material 16, the stabilised earth material 18 and the backfill material 20.
- the form 12 is initially established from durable material, such a sheet metal, anchored at its ends to the ground using concrete footings 22.
- the sheet metal can be fitted as one continuous sheet, or by connecting pieces together in sections to form an arch.
- the settable material 16 comprises a construction conglomerate material, such as shot-crete and is sprayed onto the upper surface of the form 12 and allowed to set.
- the thickness of the layer of settable material 16 is adjusted such that the strength is adequate to support the height of the arch. Preferably, the strength of the settable material exceeds 15MPa.
- the settable material 16 is reinforced by attaching mesh 24 to the upper surface of the form 12 and spraying the settable material 16 thereon.
- the overlay of stabilised granular material 18, such as earth stabilised with cement, is applied to the form 12 and settable material 16.
- Construction is typically performed in stages as shown in Figures 2 to 9.
- the form 12 is constructed and anchored to cement footings 22 as shown in Figure 2.
- the reinforcing mesh 24 is attached to the upper surface of the form 12 ( Figure 3) and the settable material 16 is then applied in sections close to ground level and allowed to set according to Figure 4.
- Stabilised earth material 18 is then laid around the upper surface of the settable material 16, such that the stabilised earth material 18 extends outwards from the layer of settable material 16.
- the stabilised earth material 18 is then backfilled with compacted backfill material 20 ( Figure 5).
- the stabilised earth material 18 gains enough strength when stabilisation is complete such that construction personnel can stand on it, thus allowing access to the upper portion of the form 12 without the requirement for scaffolding.
- the first section of stabilised earth material 18 as shown in Figure 6 therefore provides a ground surface upon which construction personnel can stand in order to apply the next section of settable material 16.
- the process as hereinbefore described is repeated, as shown in Figures 7 and 8, until the entire form 12 is covered in settable material 16 and encompassed in stabilised earth material 18, to form a tunnel as seen in Figure 9.
- the temporary support structure 14 can then be removed once the tunnel 10 has gained its own strength.
- the form 12 remains in place to form part of the completed tunnel 10, as shown in Figure 1.
- the form 12 can also be removed, leaving the settable material 16 as a load supporting structure.
- FIG 10 there is shown a cross sectional view of a structural cavity 30 according to a second embodiment.
- the structural cavity 30 is of a construction similar to the structural cavity 10 according to the first embodiment and corresponding reference numbers are used to identify similar parts.
- the structural cavity 30 may be fitted with one or more loading chutes 26, which allow for efficient loading of ore from the stockpile onto trucks and/or trains.
- a truck may pass into the structural cavity 30, pausing underneath the chute 26.
- the chute 26 is then opened and ore 28 allowed to pass through and land in the vehicle.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
Claims
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2006313000A AU2006313000A1 (en) | 2005-11-09 | 2006-11-09 | Structural cavity |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU2005906209A AU2005906209A0 (en) | 2005-11-09 | Structural Cavity | |
AU2005906209 | 2005-11-09 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2007053895A1 true WO2007053895A1 (en) | 2007-05-18 |
Family
ID=38022894
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/AU2006/001674 WO2007053895A1 (en) | 2005-11-09 | 2006-11-09 | Structural cavity |
Country Status (1)
Country | Link |
---|---|
WO (1) | WO2007053895A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101737060B (en) * | 2009-12-28 | 2011-08-10 | 中铁二局股份有限公司 | Beneath-soil through-tunnel superlarge diameter pipe curtain construction method |
US9481993B2 (en) | 2011-03-15 | 2016-11-01 | Lock-Block Ltd. | Formwork for use in the construction of arched structures and a method of constructing arched structures |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000017456A1 (en) * | 1998-09-22 | 2000-03-30 | Societe Civile De Brevets Matiere | Tubular structure |
US6205717B1 (en) * | 2000-04-11 | 2001-03-27 | Freyssinet International (Stup) | Bunker construction |
US6719492B1 (en) * | 2002-03-22 | 2004-04-13 | Bebotech Corporation | Top arch overfilled system |
WO2004085749A1 (en) * | 2003-03-28 | 2004-10-07 | Carlo Chiaves | Process for the construction of a segment of an open-air work by prefabricated structural members, and prefabricated structural member related thereto |
-
2006
- 2006-11-09 WO PCT/AU2006/001674 patent/WO2007053895A1/en active Application Filing
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000017456A1 (en) * | 1998-09-22 | 2000-03-30 | Societe Civile De Brevets Matiere | Tubular structure |
US6205717B1 (en) * | 2000-04-11 | 2001-03-27 | Freyssinet International (Stup) | Bunker construction |
US6719492B1 (en) * | 2002-03-22 | 2004-04-13 | Bebotech Corporation | Top arch overfilled system |
WO2004085749A1 (en) * | 2003-03-28 | 2004-10-07 | Carlo Chiaves | Process for the construction of a segment of an open-air work by prefabricated structural members, and prefabricated structural member related thereto |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101737060B (en) * | 2009-12-28 | 2011-08-10 | 中铁二局股份有限公司 | Beneath-soil through-tunnel superlarge diameter pipe curtain construction method |
US9481993B2 (en) | 2011-03-15 | 2016-11-01 | Lock-Block Ltd. | Formwork for use in the construction of arched structures and a method of constructing arched structures |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101476331B (en) | Closed demolition blasting method for internal concrete reinforcement bracing of basement foundation ditch | |
CN105236275A (en) | Soil lifting system and method for construction of deep foundation pit in narrow area building | |
JP6529378B2 (en) | Invert construction method, tunnel construction method and Teruha crane for tunnel | |
CN102392447A (en) | Given force variable stiffness discrete material pile ramming and expanding machine and application thereof | |
JPH09268888A (en) | Tunnel lining method using composite panels | |
WO2007053895A1 (en) | Structural cavity | |
JP2020002778A (en) | Bridge pier construction method | |
CN104929047A (en) | V-shaped pier outer support construction method | |
CN104563497B (en) | One has beam-slab bracing system construction method | |
KR101845199B1 (en) | Restoration method for relocation and topography of building site remained | |
CN107090772B (en) | Construction method of side span cast-in-place beam bracket of extra-large cable-stayed bridge | |
US20240093444A1 (en) | Vehicle barrier system and method of construction thereof | |
CN105951865B (en) | HDPE double-wall corrugated pipes foundation and its construction technology | |
AU2006313000A1 (en) | Structural cavity | |
JP3037912B2 (en) | Power transmission tower foundation construction method and pillar formwork | |
JP4384771B2 (en) | Artificial ground construction method | |
JP2020041381A (en) | Invert construction method in tunnel | |
JP6475554B2 (en) | Construction method of shaft and construction method of underground storage tank | |
CN205061417U (en) | Soil lifting system for construction of deep foundation pit of building in narrow area | |
CN112663636B (en) | Non-panel reinforced soil ecological slope protection system and construction method thereof | |
JP3226869B2 (en) | Surface ground formation block, surface ground using the same, and method of constructing a plant using the surface ground | |
US20060248847A1 (en) | Method for providing a pad to support heavy equipment | |
JP6527844B2 (en) | Civil engineering building block, civil engineering construction using the same, and method of constructing a civil engineering construction | |
JPH0959935A (en) | Pier construction method | |
JP6402056B2 (en) | Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
WWE | Wipo information: entry into national phase |
Ref document number: 2006313000 Country of ref document: AU |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
ENP | Entry into the national phase |
Ref document number: 2006313000 Country of ref document: AU Date of ref document: 20061109 Kind code of ref document: A |
|
WWP | Wipo information: published in national office |
Ref document number: 2006313000 Country of ref document: AU |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 06804495 Country of ref document: EP Kind code of ref document: A1 |