JP6402056B2 - Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method - Google Patents

Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method Download PDF

Info

Publication number
JP6402056B2
JP6402056B2 JP2015047847A JP2015047847A JP6402056B2 JP 6402056 B2 JP6402056 B2 JP 6402056B2 JP 2015047847 A JP2015047847 A JP 2015047847A JP 2015047847 A JP2015047847 A JP 2015047847A JP 6402056 B2 JP6402056 B2 JP 6402056B2
Authority
JP
Japan
Prior art keywords
underground
wall
embankment
segment ring
continuous wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015047847A
Other languages
Japanese (ja)
Other versions
JP2016169474A (en
Inventor
祐樹 小林
祐樹 小林
平 山本
平 山本
良亮 鈴木
良亮 鈴木
利秀 木村
利秀 木村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2015047847A priority Critical patent/JP6402056B2/en
Publication of JP2016169474A publication Critical patent/JP2016169474A/en
Application granted granted Critical
Publication of JP6402056B2 publication Critical patent/JP6402056B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

本発明は、地上部外周囲に盛土部を有する立坑、地下式貯槽、立坑の構築方法および地下式貯槽の構築方法に関する。   The present invention relates to a vertical shaft having an embankment portion around the outside of the ground, an underground storage tank, a vertical shaft construction method, and an underground storage tank construction method.

立坑の周囲に盛土を行う場合に、立坑の掘削により発生した掘削残土を盛土材として使用すれば、掘削残土の搬出に要する手間や費用を削減することができる。
例えば、LNG地下タンク(地下貯槽)等では、躯体の構築後、躯体の外周部に掘削残土を盛り立てることにより盛土部を形成する場合がある。
立坑構築時の掘削残土は、立坑の掘削から躯体の構築が完了するまでの間、仮置き場に保管しておく必要があるが、使用可能な敷地が制限されている場合には、仮置き場を確保することができない場合がある。
When embankment is performed around a vertical shaft, if the excavation residual soil generated by excavation of the vertical shaft is used as the embankment material, labor and cost required for carrying out the excavation residual soil can be reduced.
For example, in an LNG underground tank (underground storage tank) or the like, a banking part may be formed by building up excavation residual soil on the outer peripheral part of the chassis after the construction of the chassis.
The remaining excavated soil at the time of shaft construction needs to be stored in a temporary storage area from the time the shaft is excavated until the construction of the frame is completed. There are cases where it cannot be secured.

特許文献1には、掘削残土の仮置き場を不要とする地下タンクの施工方法として、図8に示すように、地中に円筒状の地中連続壁101を構築し、この地中連続壁101の内側から上方に突出するように側壁上部102を構築し、地中連続壁101により囲まれた地盤を掘削するとともに側壁上部102の周囲に掘削残土103を盛り立てた後、地中連続壁101の内面に沿って側壁下部104を構築して側壁上部102と一体化させる方法が開示されている。   In Patent Document 1, as an underground tank construction method that does not require a temporary storage site for excavated soil, a cylindrical underground wall 101 is constructed in the ground as shown in FIG. The side wall upper part 102 is constructed so as to protrude upward from the inside of the wall, the ground surrounded by the underground continuous wall 101 is excavated, and after excavating the remaining excavated soil 103 around the side wall upper part 102, the underground continuous wall 101 A method is disclosed in which a sidewall lower portion 104 is constructed along the inner surface and integrated with the sidewall upper portion 102.

特開2012−036661号公報JP 2012-036661 A

特許文献1の地下タンクの施工方法は、側壁上部102を構築するための型枠や支保部材の設置・撤去に手間がかかる。
また、側壁上部102と地中連続壁101との接合部には、鉛直方向の荷重(せん断力)に加えて、盛土土圧によって引張力が作用するため、側壁上部102と地中連続壁101との接合強度を高める必要がある。すなわち、地中連続壁101の上部(側壁上部102と地中連続壁101との接合部)の施工が煩雑である。
また、側壁上部102は、盛土土圧によって変形が生じるため、側壁上部102の変形量を抑えるための処理が必要となる場合がある。
また、側壁上部102を盛土部形成時の土留壁(仮設部材)として利用しているため、側壁下部104の構築後(側壁完成後)にも残留応力が発生するおそれがある。そのため、側壁上部102の応力状態の管理が困難となる。
また、側壁上部102は、地中連続壁101の内部に沿って形成するため、側壁上部102の施工中は、地中連続壁101の内部の掘削をすることができない。
さらに、所定の高さの側壁上部102を構築することにより、早い段階から視界が遮られることにより、立坑内部の状況を確認しづらい。
The construction method of the underground tank of Patent Document 1 takes time to install and remove the formwork and support members for constructing the upper side wall 102.
In addition to the vertical load (shearing force), a tensile force acts on the joint between the side wall upper part 102 and the underground continuous wall 101 due to the embankment earth pressure. It is necessary to increase the bonding strength. That is, the construction of the upper part of the underground continuous wall 101 (joint part between the sidewall upper part 102 and the underground continuous wall 101) is complicated.
Moreover, since the side wall upper part 102 is deformed by the embankment earth pressure, a process for suppressing the deformation amount of the side wall upper part 102 may be required.
Further, since the side wall upper portion 102 is used as a retaining wall (temporary member) at the time of forming the embankment portion, residual stress may be generated even after the side wall lower portion 104 is constructed (after the side wall is completed). Therefore, it becomes difficult to manage the stress state of the sidewall upper part 102.
Moreover, since the side wall upper part 102 is formed along the inside of the underground continuous wall 101, the inside of the underground continuous wall 101 cannot be excavated during the construction of the side wall upper part 102.
In addition, by constructing the sidewall upper portion 102 having a predetermined height, the field of view is blocked from an early stage, making it difficult to check the situation inside the shaft.

このような観点から、本発明は、地上部外周囲に盛土部を有する場合であっても、簡易に構築することが可能な立坑、地下式貯槽、立坑の構築方法および地下式貯槽の構築方法を提案することを課題とする。   From this point of view, the present invention provides a shaft, an underground storage tank, a shaft construction method, and a method for constructing an underground storage tank that can be easily constructed even when there is a banking portion around the outside of the ground. It is an issue to propose.

前記課題を解決するために、本発明の立坑は、円筒状に形成した地中連続壁と、前記地中連続壁の上端に立設されたセグメントリングと、前記セグメントリングの外周囲に盛り立てられた盛土部とを備えていて、前記盛土部が前記地中連続壁により囲まれた地盤を掘削することにより発生した掘削残土を含む盛土材により形成されていることを特徴としている。
前記盛土部には、補強材が埋め込まれているのが望ましい。
In order to solve the above-mentioned problems, the shaft according to the present invention includes an underground continuous wall formed in a cylindrical shape, a segment ring erected on an upper end of the underground continuous wall, and raised around an outer periphery of the segment ring. And the embankment portion is formed of a embankment material including excavation residual soil generated by excavating the ground surrounded by the underground continuous wall.
It is desirable that a reinforcing material is embedded in the embankment.

また、本発明の立坑の構築方法は、地中連続壁を円筒状に形成する工程と、前記地中連続壁の上端において複数のセグメントを組み立てることによりセグメントリングを形成する工程と、前記地中連続壁により囲まれた地盤を掘削するとともに前記地盤の掘削により発生した掘削残土を含む盛土材を前記地中連続壁の外周囲に盛り立てる工程とを備えることを特徴としている。   The shaft construction method of the present invention includes a step of forming an underground continuous wall in a cylindrical shape, a step of forming a segment ring by assembling a plurality of segments at an upper end of the underground continuous wall, and the underground A step of excavating the ground surrounded by the continuous wall and raising the embankment material including the excavated residual soil generated by the excavation of the ground around the outer periphery of the underground continuous wall.

かかる立坑および立坑の構築方法によれば、プレキャスト部材であるセグメントを利用しているため、施工性に優れている。
また、盛土部の立ち上がりに応じて施工すれば、セグメントを組み立てる際の足場を省略または縮小化することが可能となる。また、セグメントリングを段階的に施工することで、セグメントリングにより視界が遮られることを防止することができる。
また、セグメントリングは、地中連続壁の上端に形成するため、地中連続壁の内部の掘削と干渉することがなく、セグメントリングの施工と掘削作業とを並行して行うことができる。
According to the shaft and the method for constructing the shaft, since the segment which is a precast member is used, the workability is excellent.
Moreover, if construction is performed according to the rising of the embankment, it is possible to omit or reduce the scaffold when assembling the segments. Moreover, it can prevent that a visual field is obstruct | occluded by a segment ring by constructing a segment ring in steps.
Further, since the segment ring is formed at the upper end of the underground continuous wall, the segment ring can be constructed and excavated in parallel without interfering with the excavation inside the underground continuous wall.

また、本発明の地下式貯槽は、円筒状に形成した地中連続壁と、前記地中連続壁の上端に立設されたセグメントリングと、前記セグメントリングの外周囲に盛り立てられた盛土部と、前記地中連続壁および前記セグメントリングの内面に沿って形成されたコンクリート製の側壁とを備えていて、前記盛土部が前記地中連続壁により囲まれた地盤を掘削することにより発生した掘削残土を含む盛土材により形成されていて、前記側壁の上部が前記セグメントリングを外型枠として形成されていることを特徴としている。   Further, the underground storage tank of the present invention is a continuous underground wall formed in a cylindrical shape, a segment ring erected at the upper end of the underground continuous wall, and a banking portion raised around the outer periphery of the segment ring And a concrete side wall formed along the inner surface of the underground continuous wall and the segment ring, and the embankment portion is generated by excavating the ground surrounded by the underground continuous wall It is formed by the embankment material containing excavation residual soil, The upper part of the said side wall is formed using the said segment ring as an outer mold frame, It is characterized by the above-mentioned.

また、本発明の地下式貯槽の構築方法は、地中連続壁を円筒状に形成する工程と、前記地中連続壁の上端において複数のセグメントを組み立てることによりセグメントリングを形成する工程と、前記地中連続壁により囲まれた地盤を掘削するとともに前記地盤の掘削により発生した掘削残土を含む盛土材を前記地中連続壁の外周囲に盛り立てる工程と、前記地中連続壁および前記セグメントリングの内面に沿って側壁を形成する工程とを備えることを特徴としている。   The underground storage tank construction method of the present invention includes a step of forming an underground continuous wall in a cylindrical shape, a step of forming a segment ring by assembling a plurality of segments at the upper end of the underground continuous wall, A step of excavating the ground surrounded by the underground continuous wall and embedding a filling material including excavated residual soil generated by the excavation of the ground around the outer periphery of the underground continuous wall; the underground continuous wall and the segment ring; And a step of forming a side wall along the inner surface.

かかる地下式貯槽および地下式貯槽の構築方法によれば、側壁の外型枠を設置する作業を省略することが可能なため、施工性に優れている。
また、盛土を段階的に施工すれば、土圧管理が容易であるとともに、側壁に作用する土圧および偏土圧を排除することができる。
盛土部の施工後に側壁を構築するため、側壁に残留応力が発生することがなく、また、土圧によって側壁に生じる変形量を抑制することができる。
According to the underground storage tank and the construction method of the underground storage tank, the work of installing the outer mold on the side wall can be omitted, and therefore, the workability is excellent.
Moreover, if the embankment is constructed in stages, earth pressure management is easy, and earth pressure and uneven earth pressure acting on the side wall can be eliminated.
Since the side wall is constructed after the embankment is constructed, no residual stress is generated on the side wall, and the amount of deformation generated on the side wall due to earth pressure can be suppressed.

本発明の立坑、地下式貯槽、立坑の構築方法および地下式貯槽の構築方法によれば、地上部外周囲に盛土部を有する場合であっても、簡易に構築することが可能となる。   According to the vertical shaft, underground storage tank, vertical shaft construction method, and underground storage tank construction method of the present invention, it is possible to easily construct even if there is a banking portion outside the above-ground part.

(a)本発明の実施形態に係る地下式貯槽を示す断面図、(b)は同平面図である。(A) Sectional drawing which shows the underground type storage tank which concerns on embodiment of this invention, (b) is the same top view. 地下式貯槽の構築方法における地中連続壁施工後の初期掘削状況を示す図であって、(a)は断面図、(b)は平面図である。It is a figure which shows the initial excavation state after underground continuous wall construction in the construction method of an underground type storage tank, Comprising: (a) is sectional drawing, (b) is a top view. (a)および(b)は、セグメントリングと地中連続壁との接合部の構造を示す模式図である。(A) And (b) is a schematic diagram which shows the structure of the junction part of a segment ring and an underground continuous wall. 盛土部の一部を示す拡大断面図である。It is an expanded sectional view which shows a part of embankment part. 図2に続く施工状況を示す図であって、(a)は断面図、(b)は平面図である。It is a figure which shows the construction condition following FIG. 2, (a) is sectional drawing, (b) is a top view. (a)は図5に続く施工状況を示す断面図、(b)は(a)に続く施工状況を示す断面図である。(A) is sectional drawing which shows the construction condition following FIG. 5, (b) is sectional drawing which shows the construction condition following (a). セグメント同士の接合部の一例を示す模式図である。It is a schematic diagram which shows an example of the junction part of segments. 従来の地下式貯槽の構築方法を示す断面図である。It is sectional drawing which shows the construction method of the conventional underground storage tank.

本発明の実施形態の地下式貯槽1は、図1(a)および(b)に示すように、底版2と、底版2に立設された側壁3と、側壁3により囲まれた空間の頂部を遮蔽する屋根4と、側壁3の周囲に形成された立坑5と、底版2および側壁3の内面に取り付けられたメンブレン10とを備えている。   As shown in FIGS. 1A and 1B, an underground storage tank 1 according to an embodiment of the present invention includes a bottom plate 2, a side wall 3 standing on the bottom plate 2, and a top portion of a space surrounded by the side wall 3. The roof 4 is shielded, the shaft 5 is formed around the side wall 3, and the membrane 10 is attached to the bottom plate 2 and the inner surface of the side wall 3.

底版2は、図1(a)に示すように、メンブレン10の下面を覆うように形成されたコンクリート構造体である。底版2の内部には、必要に応じて図示しない底部ヒーターを埋設する。
また、底版2の下方には、必要に応じて排水層(図示せず)が形成されている。排水層の構成は限定されるものではないが、例えば、砕石等を敷き詰めることにより形成すればよい。
The bottom plate 2 is a concrete structure formed so as to cover the lower surface of the membrane 10 as shown in FIG. A bottom heater (not shown) is embedded in the bottom plate 2 as necessary.
A drainage layer (not shown) is formed below the bottom plate 2 as necessary. Although the structure of a drainage layer is not limited, For example, what is necessary is just to form by spreading a crushed stone etc.

側壁3は、底版2の周縁部に立設されたコンクリート構造体である。本実施形態の側壁3は、図1(b)に示すように、平面視円形(円筒状)を呈している。また、側壁3の壁厚や壁高は、適宜設定すればよい。   The side wall 3 is a concrete structure erected on the peripheral edge of the bottom slab 2. The side wall 3 of the present embodiment has a circular shape (cylindrical shape) in plan view as shown in FIG. Moreover, what is necessary is just to set the wall thickness and wall height of the side wall 3 suitably.

屋根4は、図1(a)に示すように、側壁3の上端に形成されていて、メンブレン10の上面を覆っている。
屋根4の周縁部は、側壁3の上端部に固定されている。
本実施形態では屋根4が鋼製部材により形成されているが、屋根4は、例えばコンクリート部材により形成されていてもよい。
As shown in FIG. 1A, the roof 4 is formed at the upper end of the side wall 3 and covers the upper surface of the membrane 10.
The peripheral edge of the roof 4 is fixed to the upper end of the side wall 3.
In this embodiment, the roof 4 is formed of a steel member, but the roof 4 may be formed of, for example, a concrete member.

立坑5は、連続地中壁6と、セグメントリング7により形成された地上壁71と、盛土部8とを備えている。
連続地中壁6は、図1(a)および(b)に示すように、側壁3の外周囲を囲うように円筒状に形成されている。
連続地中壁6の下端は底版2の下方の難透水層に到達している。なお、連続地中壁6の高さや深さ方向の位置は限定されない。また、連続地中壁6の壁厚は限定されるものではなく、適宜設定すればよいが、本実施形態では1〜1.5mの範囲内とする。
また、連続地中壁6には、必要に応じて側部ヒーター(図示せず)を配設する。なお、側部ヒーターの構成は限定されない。
The vertical shaft 5 includes a continuous underground wall 6, a ground wall 71 formed by a segment ring 7, and a banking portion 8.
As shown in FIGS. 1A and 1B, the continuous underground wall 6 is formed in a cylindrical shape so as to surround the outer periphery of the side wall 3.
The lower end of the continuous underground wall 6 reaches the poorly permeable layer below the bottom plate 2. The height of the continuous underground wall 6 and the position in the depth direction are not limited. The wall thickness of the continuous underground wall 6 is not limited and may be set as appropriate, but in the present embodiment, the wall thickness is in the range of 1 to 1.5 m.
Further, a side heater (not shown) is disposed on the continuous underground wall 6 as necessary. The configuration of the side heater is not limited.

地上壁71は、図1(a)に示すように、複数段のセグメントリング7,7,7を連続地中壁6の上に積層することにより形成されている。本実施形態では、3段のセグメントリング7が積層されているが、セグメントリング7の段数は限定されるものではなく、盛土部8の設計高さとセグメントリング7の一段当たりの高さ等に応じて適宜設定すればよい。
セグメントリング7は、図1(b)に示すように、複数のプレキャスト製のセグメントを連続地中壁6の周方向に並べることにより円筒状に形成されていて、地中連続壁6の上端に立設されている。なお、左右または上下に隣り合うセグメント同士は、ボルト等により接合する。本実施形態では、セグメントとして、コンクリート製のプレキャスト部材を使用するが、セグメントを構成する材料は限定されるものではなく、例えば、鋼製セグメント、合成セグメント、高強度繊維補強コンクリート製セグメント等を使用してもよい。
As shown in FIG. 1A, the ground wall 71 is formed by laminating a plurality of stages of segment rings 7, 7, 7 on the continuous underground wall 6. In the present embodiment, three segment rings 7 are laminated, but the number of segment rings 7 is not limited, and depends on the design height of the embankment portion 8 and the height per segment ring 7 or the like. May be set as appropriate.
As shown in FIG. 1B, the segment ring 7 is formed in a cylindrical shape by arranging a plurality of precast segments in the circumferential direction of the continuous underground wall 6, and is formed at the upper end of the underground continuous wall 6. It is erected. In addition, the segments adjacent to each other on the left and right or the top and bottom are joined with a bolt or the like. In this embodiment, a concrete precast member is used as a segment, but the material constituting the segment is not limited, and for example, a steel segment, a synthetic segment, a high strength fiber reinforced concrete segment, or the like is used. May be.

本実施形態のセグメントリング7の内面は、連続地中壁6の内面と面一としてもよいし、セグメントリング7の内面と連続地中壁6の内面に段差を有していてもよい。また、各セグメントの高さや部材厚等の寸法は限定されるものではなく、適宜設定すればよいが、本実施形態では、高さが1.5〜15.0mの範囲内、幅が1.5〜15.0mの範囲内、厚さが5cm〜150cmの範囲内とする。さらに、最下段のセグメントリング7として、単体で自立可能な断面L字状のセグメントを使用すれば、セグメントリング7を組み立てる際の仮設支持部材等を省略してもよい。   The inner surface of the segment ring 7 of the present embodiment may be flush with the inner surface of the continuous underground wall 6 or may have a step between the inner surface of the segment ring 7 and the inner surface of the continuous underground wall 6. In addition, the dimensions such as the height and the member thickness of each segment are not limited and may be set as appropriate. In the present embodiment, the height is in the range of 1.5 to 15.0 m and the width is 1. The thickness is in the range of 5 to 15.0 m and the thickness is in the range of 5 to 150 cm. Further, if a segment L-shaped segment that can stand alone is used as the lowermost segment ring 7, a temporary support member or the like when assembling the segment ring 7 may be omitted.

盛土部8は、図1(a)および(b)に示すように、地上壁71の外周囲に、地中連続壁6により囲まれた地盤を掘削することにより発生した掘削残土(盛土材)を盛り立てることにより形成されている。なお、盛土部8は、必ずしも掘削残土(流用土)のみで形成する必要はなく、外部から搬入した材料(発生土や購入土等)を含んでいてもよい。
盛土部8の上面は、地上壁71の上端と同等の高さとなるまで盛り立てられている。また、盛土部8の外周囲(外縁)には安定勾配による法面が形成されていて、原地盤の高さ(地表面GL)にすり付けられている。なお、盛土部8の外周囲は、必ずしも安定勾配による法面が形成されている必要はない。例えば、補強工法や擁壁等を採用することで盛土部8外周囲の勾配を立ててもよい。補強工法としては、例えば、盛土材にセメントを混合した改良土により盛土部を形成すればよい。
As shown in FIGS. 1 (a) and 1 (b), the embankment portion 8 is excavated residual soil (embankment material) generated by excavating the ground surrounded by the underground continuous wall 6 around the outer periphery of the ground wall 71. It is formed by raising. Note that the embankment portion 8 is not necessarily formed only from excavated residual soil (diverted soil), and may include materials carried from the outside (such as generated soil and purchased soil).
The upper surface of the embankment portion 8 is raised until it reaches a height equivalent to the upper end of the ground wall 71. Further, a slope with a stable gradient is formed on the outer periphery (outer edge) of the embankment portion 8, and is rubbed to the height of the original ground (ground surface GL). In addition, the outer periphery of the embankment part 8 does not necessarily need to have a slope with a stable gradient. For example, a gradient around the embankment portion 8 may be established by employing a reinforcement method or a retaining wall. As the reinforcing method, for example, the embankment portion may be formed by improved soil obtained by mixing cement with embankment material.

次に、地下式貯槽1の構築方法について説明する。
地下式貯槽1の構築方法は、地中壁構築工程、地上壁形成工程、盛土工程およびタンク構築工程により行う。
Next, the construction method of the underground storage tank 1 will be described.
The underground storage tank 1 is constructed by an underground wall construction process, a ground wall formation process, a banking process, and a tank construction process.

地中壁構築工程は、連続地中壁6を構築する工程である。
連続地中壁6は、地下式貯槽1の形成予定地の周囲を囲うように円筒状(平面視円形)の溝を形成し、この溝の内部に鉄筋籠を建て込んだ後、コンクリートを打設することにより形成する(図2(a)および(b)参照)。連続地中壁6は、難透水層に到達するように形成する。コンクリートは、トレミー管(図示せず)を利用して、溝の底部から打設する。また、本実施形態では、コンクリートの打設後、上部を除去し(レイタンス除去)、新たにコンクリートを打設することにより連続地中壁6の上部(コーピングコンクリート61)を形成する(図3参照)。
なお、連続地中壁6の構造は限定されるものではなく、例えば鉄筋籠に代えて形鋼材等の芯材を設置してもよい。また、安定液固化連壁工法やソイルセメント連壁工法を採用してもよい。また、コーピングコンクリート61は必要に応じて形成すればよい。
The underground wall construction process is a process of constructing the continuous underground wall 6.
The continuous underground wall 6 is formed with a cylindrical groove (circular in plan view) so as to surround the area where the underground storage tank 1 is to be formed. (See FIGS. 2A and 2B). The continuous underground wall 6 is formed so as to reach the hardly permeable layer. Concrete is cast from the bottom of the groove using a tremy tube (not shown). Moreover, in this embodiment, after placing concrete, the upper part is removed (latency removal) and the concrete is newly placed to form the upper part of the continuous underground wall 6 (coping concrete 61) (see FIG. 3). ).
In addition, the structure of the continuous underground wall 6 is not limited, For example, it may replace with a reinforcing bar rod and may install core materials, such as a shape steel material. Moreover, you may employ | adopt a stable liquid solidification continuous wall method and a soil cement continuous wall method. Moreover, what is necessary is just to form the coping concrete 61 as needed.

連続地中壁6を構築したら、地上壁形成工程と盛土工程とを並行して実施することにより、立坑5を形成する。
すなわち、所定の高さの盛土部8が形成されるまで、セグメントリング7の構築と、セグメントリング7の外周囲への掘削残土の盛り立てを実施する。
まず、連続地中壁6の構築後、図2(a)および(b)に示すように、初期掘削を行う(盛土工程)。なお、初期掘削は、最下段のセグメントリング7の構築作業と並行して行えばよい。
When the continuous underground wall 6 is constructed, the shaft 5 is formed by carrying out the ground wall forming process and the embankment process in parallel.
That is, until the embankment portion 8 having a predetermined height is formed, the segment ring 7 is constructed and the excavation remaining soil around the outer periphery of the segment ring 7 is implemented.
First, after construction of the continuous underground wall 6, as shown in FIGS. 2A and 2B, initial excavation is performed (filling step). The initial excavation may be performed in parallel with the construction work of the lowermost segment ring 7.

初期掘削は、連続地中壁6により囲まれた地盤をバックホウ等の掘削機M1を利用して行う。掘削により発生した掘削残土は、トラック等の搬送車M2を利用して、連続地中壁6の外側に搬出し、連続地中壁6の外周囲に盛り立てる。なお、セグメントリング7が完全な円形になるまで(閉合されるまで)は、セグメントリング7から離れた位置に盛土を行う。このとき、連続地中壁6により囲まれた空間には、掘削底面から連続地中壁6の外周囲の地盤面に至るらせん状の仮設道路11が、搬送車M2が走行可能な縦断勾配により形成されている。   The initial excavation is performed using the excavator M1 such as a backhoe on the ground surrounded by the continuous underground wall 6. The excavated residual soil generated by excavation is carried out to the outside of the continuous underground wall 6 using a transport vehicle M2 such as a truck, and piled up around the outer periphery of the continuous underground wall 6. Note that the banking is performed at a position away from the segment ring 7 until the segment ring 7 is completely circular (closed). At this time, in the space surrounded by the continuous underground wall 6, the spiral temporary road 11 extending from the bottom of the excavation to the ground surface around the outer surface of the continuous underground wall 6 is caused by the longitudinal gradient that the transport vehicle M2 can travel. Is formed.

最下段のセグメントリング7は、図2(b)に示すように、地中連続壁6の上端において複数のセグメント72を組み立てることにより形成する(地上壁形成工程)。
最下段のセグメントリング7は、地中連続壁6の上面に立設させる。なお、セグメントリング7の地中連続壁6への固定方法は限定されるものではない。例えば、地中連続壁6の頂部(コーピングコンクリート61)にセグメントリング7の一部を埋め込んでもよいし(図3(a)参照)、所定の治具74(例えば、アングル材とアンカー)を利用して地中連続壁6の上端に固定してもよい(図3(b)参照)。また、セグメントリング7は、地中連続壁6に対して剛接合やピン接合等により固定してもよい。
最下段のセグメントリング7の組み立ては、セグメントが倒れることがないように、必要に応じて支保部材(頬杖材・斜材等)によってセグメントを支持した状態で行う。
また、最下段のセグメントリング7には、図4に示すように、必要に応じて、盛土部8に浸透した水分を立坑5内に排水するための排水管73を配管しておく。
As shown in FIG. 2B, the lowermost segment ring 7 is formed by assembling a plurality of segments 72 at the upper end of the underground continuous wall 6 (ground wall forming step).
The lowermost segment ring 7 is erected on the upper surface of the underground continuous wall 6. The method for fixing the segment ring 7 to the underground continuous wall 6 is not limited. For example, a part of the segment ring 7 may be embedded in the top portion (coping concrete 61) of the underground continuous wall 6 (see FIG. 3A), or a predetermined jig 74 (for example, an angle material and an anchor) is used. And you may fix to the upper end of the underground continuous wall 6 (refer FIG.3 (b)). Further, the segment ring 7 may be fixed to the underground continuous wall 6 by rigid bonding, pin bonding, or the like.
Assembling of the lowermost segment ring 7 is performed in a state where the segment is supported by a supporting member (cheek cane material, diagonal material, etc.) as necessary so that the segment does not fall down.
In addition, as shown in FIG. 4, a drainage pipe 73 for draining water that has penetrated into the embankment 8 into the shaft 5 is provided in the lowermost segment ring 7 as needed.

最下段のセグメントリング7が完成したら、図5(a)および(b)に示すように、地中連続壁6により囲まれた地盤を掘削するとともに、地盤の掘削により発生した掘削残土をセグメントリング7の外周囲に盛り立てる(盛土工程)。
本実施形態では、地中連続壁6により囲まれた空間内において、掘削機械M1を利用して地盤を掘削し、掘削残土を地中連続壁6の外側の地上部に配置されたクローラクレーン等の揚重機M3を利用して地上部に搬出する。このとき、立坑内(地中連続壁6により囲まれた空間内)では、搬送車M2を利用して掘削機械M1により掘削された掘削残土を揚重機M3の下方に輸送する。なお、立坑内での掘削残土の運搬は、ベルトコンベヤ等の他の輸送手段により行ってもよい。
When the lowermost segment ring 7 is completed, as shown in FIGS. 5A and 5B, the ground surrounded by the underground continuous wall 6 is excavated, and the excavated residual soil generated by the excavation of the ground is segmented. Raise the outer circumference of 7 (filling process).
In the present embodiment, in the space surrounded by the underground continuous wall 6, the ground is excavated by using the excavating machine M <b> 1, and the excavated residual soil is disposed on the ground portion outside the underground continuous wall 6. It is carried out to the ground part using the lifting machine M3. At this time, in the shaft (in the space surrounded by the underground continuous wall 6), the excavation residual soil excavated by the excavating machine M1 using the transport vehicle M2 is transported below the lifting machine M3. In addition, you may perform the conveyance of the excavation residual soil in a shaft by other transport means, such as a belt conveyor.

地上部に搬出された掘削残土は、搬送車M2によってセグメントリング7の外周囲の所定の位置に搬送された後、ブルドーザ等の敷均し機M4によって敷均し、必要に応じて転圧ローラ等によって転圧する。なお、掘削残土は、搬送されたものを直接敷均してもよいし、仮置きした後に敷均してもよい。また、掘削残土にセメント等の固化材を混合した改良土を敷均してもよい。
盛土部8の施工は、図5(b)に示すように、セグメントリング7の周方向に沿って、搬送車M3の走行が可能な縦断勾配を有した状態でらせん状に盛り立てるものとし、盛土部8の上面を仮設道路11として使用可能に構成する。
また、本実施形態の盛土部8は自立した盛土である。盛土部8の内周部には、図4に示すように、所定の高さ毎に補強材(いわゆるジオテキスタイル等)81,81,…を敷設する。
なお、盛土部8の施工は、必ずしもらせん状に盛り立てる必要はない。また、補強材は必要に応じて敷設すればよい。
The excavated residual soil transported to the ground is transported to a predetermined position on the outer periphery of the segment ring 7 by the transport vehicle M2, and then leveled by a leveling machine M4 such as a bulldozer, and if necessary, a rolling roller Compressed by etc. In addition, the excavated residual soil may be spread directly after being conveyed, or may be spread after temporarily placing. Moreover, you may level the improvement soil which mixed solidification materials, such as cement, with excavation residual soil.
As shown in FIG. 5 (b), the construction of the embankment portion 8 is to be spirally raised along the circumferential direction of the segment ring 7 with a longitudinal gradient that allows the transport vehicle M3 to travel. The upper surface of the embankment part 8 is configured to be usable as a temporary road 11.
Moreover, the embankment part 8 of this embodiment is a self-supporting embankment. As shown in FIG. 4, reinforcing materials (so-called geotextiles) 81, 81,... Are laid on the inner peripheral portion of the embankment portion 8 at predetermined heights.
In addition, the construction of the embankment part 8 does not necessarily need to be heaped up spirally. Further, the reinforcing material may be laid as necessary.

なお、盛土部8のセグメントリング7側の端部では蛇籠や土のう等の保護材82を設置することで、セグメントリング7に作用する土圧を最小限に抑えるのが望ましい。保護材82を省略し、盛土部8に法面を形成してもよいし、盛土部8(掘削残土)がセグメントリング7の外周面に接するように形成してもよい。
保護材82とセグメントリング7との隙間には充填材9を充填する。充填材9には、砂や礫等の排水性材料を用いるのが望ましいが、掘削残土を用いてもよいし、購入土を用いてもよい。充填材9の充填は、盛土部8の転圧後に行うのが望ましい。このようにすれば、転圧時はセグメントリング7ご盛土部8との間に隙間が形成されているため、転圧時の圧力がセグメントリング7に作用することがなく、セグメントリング7(セグメント)の小断面化を図ることができる。
In addition, it is desirable to minimize earth pressure acting on the segment ring 7 by installing a protective material 82 such as a gabion or a sandbag at the end of the banking portion 8 on the segment ring 7 side. The protective material 82 may be omitted, and a slope may be formed on the embankment portion 8, or the embankment portion 8 (excavated residual soil) may be formed in contact with the outer peripheral surface of the segment ring 7.
Filler 9 is filled in the gap between the protective material 82 and the segment ring 7. As the filler 9, it is desirable to use a drainage material such as sand or gravel, but excavated residual soil or purchased soil may be used. The filling of the filler 9 is preferably performed after the embankment 8 is rolled. In this way, since a gap is formed between the segment ring 7 and the embankment 8 during rolling, the pressure during rolling does not act on the segment ring 7, and the segment ring 7 (segment ).

盛土部8を所定の高さ(本実施形態では最下段のセグメントリング7の中間付近)まで構築したら、図6(a)に示すように、2段目のセグメントリング7を組み立てる(地上壁形成工程)。2段目のセグメントリング7は、最下段のセグメントリング7の上面に接合する。
セグメントリング7を構成するセグメントは、盛土部8上に形成された仮設道路11を利用して車両により所定の位置(組立箇所)に運搬する。なお、セグメントの運搬方法は限定されない。
When the embankment 8 is constructed to a predetermined height (in the present embodiment, near the middle of the lowermost segment ring 7), the second stage segment ring 7 is assembled as shown in FIG. Process). The second stage segment ring 7 is joined to the upper surface of the lowermost segment ring 7.
The segment constituting the segment ring 7 is transported to a predetermined position (assembly position) by a vehicle using a temporary road 11 formed on the embankment portion 8. In addition, the conveyance method of a segment is not limited.

2段目のセグメントリング7を形成したら、図6(a)に示すように、地中連続壁6により囲まれた地盤を掘削するとともに、地盤の掘削により発生した掘削残土を2段目のセグメントリング7の外周囲に盛り立てる(盛土工程)。
同様に、地上壁形成工程と盛土工程を繰り返すことで、床付け面まで掘削するとともに、所定の高さの地上壁71および盛土部8を形成する。
When the second stage segment ring 7 is formed, as shown in FIG. 6A, the ground surrounded by the underground continuous wall 6 is excavated, and the remaining excavated soil generated by the excavation of the ground is second segmented. Raise the outer circumference of the ring 7 (filling process).
Similarly, by repeating the ground wall forming step and the embankment step, the ground wall 71 and the embankment portion 8 having a predetermined height are formed while excavating to the flooring surface.

なお、セグメントリング7の組立作業と、盛土部8の盛り立て作業は、異なる位置において並行して実施するのが望ましい。
すなわち、例えば、立坑5の中心を挟んで対向する位置にそれぞれ揚重機M3を配置して、その近傍において盛土部8の施工をしている場合(図5(b)参照)、揚重機M3から十分に離れた位置であって、所定の高さまで盛り立てられた位置においてセグメントリング7の組立作業を行えばよい。
It is desirable that the assembly operation of the segment ring 7 and the embedding operation of the embankment portion 8 are performed in parallel at different positions.
That is, for example, when the lifting machines M3 are arranged at positions facing each other across the center of the shaft 5, and the embankment portion 8 is constructed in the vicinity thereof (see FIG. 5B), from the lifting machine M3 The segment ring 7 may be assembled at a position that is sufficiently distant and raised to a predetermined height.

タンク構築工程は、立坑5の内側に底版2、側壁3および屋根4を構築する工程である。
まず、立坑5の床付け面51(図6(b)参照)に砕石等を敷き均し、排水層(図示せず)を形成する。
次に、底版2を形成する(図1参照)。このとき、必要に応じて底部ヒーター(図示せず)を埋設しておく。
The tank construction process is a process of constructing the bottom plate 2, the side wall 3 and the roof 4 inside the shaft 5.
First, crushed stone or the like is spread on the flooring surface 51 (see FIG. 6B) of the shaft 5 to form a drainage layer (not shown).
Next, the bottom plate 2 is formed (see FIG. 1). At this time, a bottom heater (not shown) is embedded as necessary.

続いて、連続地中壁6および地上壁71の内面に沿って側壁3を形成する(図1参照)。
側壁3の施工は、セグメントリング7を外型枠として利用する。すなわち、連続地中壁6および地上壁71の内側に、側壁3の壁厚を確保した隙間をあけて内型枠(図示せず)を設け、当該隙間にコンクリートを打設することにより側壁3を形成する。
Then, the side wall 3 is formed along the inner surface of the continuous underground wall 6 and the ground wall 71 (refer FIG. 1).
The construction of the side wall 3 uses the segment ring 7 as an outer mold. That is, an inner mold frame (not shown) is provided inside the continuous underground wall 6 and the ground wall 71 with a gap ensuring the wall thickness of the side wall 3, and concrete is placed in the gap to form the side wall 3. Form.

側壁3を形成したら、屋根4を形成し、側壁3の上面を遮蔽する(図1参照)。
屋根4は、まず、側壁3に囲まれた空間内において、底版2上で組み立てる。次に、内部の気圧を上昇させることで、屋根4を持ち上げて、側壁3の上端部に固定する。なお、屋根4の施工方法(持ち上げ方法)は限定されるものではなく、例えば、支保工を利用してもよいし、ジャッキを利用してもよい。
なお、屋根4の施工に伴い、底版2および側壁3の内面にメンブレン10を取り付ける。メンブレン10は、図示しない保冷材を介して底版2および側壁3に取り付ける。
If the side wall 3 is formed, the roof 4 is formed and the upper surface of the side wall 3 is shielded (see FIG. 1).
First, the roof 4 is assembled on the bottom plate 2 in a space surrounded by the side walls 3. Next, by raising the internal atmospheric pressure, the roof 4 is lifted and fixed to the upper end of the side wall 3. In addition, the construction method (lifting method) of the roof 4 is not limited, For example, a support work may be utilized and a jack may be utilized.
In addition, the membrane 10 is attached to the inner surface of the bottom plate 2 and the side wall 3 with the construction of the roof 4. The membrane 10 is attached to the bottom plate 2 and the side wall 3 through a cold insulating material (not shown).

本実施形態の地下式貯槽1(立坑5)および地下式貯槽(立坑)の構築方法によれば、プレキャスト部材であるセグメントを利用して地上壁71を形成しているため、現場打ちコンクリートにより形成する壁体に比べて施工性に優れている。
また、セグメントリング7の施工と盛土部8の施工を並行して行うことで、工期短縮化を図ることができる。
According to the construction method of the underground type storage tank 1 (vertical shaft 5) and the underground type storage tank (vertical shaft) of the present embodiment, the ground wall 71 is formed using the segment which is a precast member. Excellent workability compared to wall bodies.
Moreover, the construction period can be shortened by performing the construction of the segment ring 7 and the construction of the embankment portion 8 in parallel.

また、盛土部8をある程度の高さまで形成した後に2段目以降のセグメントリング7を施工することで、セグメントを組み立てる際の足場を省略または縮小化することが可能となる。
また、盛土部8を段階的に施工することで、土圧管理が容易であるとともに、側壁3に作用する土圧、偏土圧および水圧を排除することができる。また、盛土部8に補強材81を敷設して盛土部8を自立させることで、側壁3に作用する土圧および水圧を最小限に抑えている。
In addition, by forming the second and subsequent segment rings 7 after forming the embankment portion 8 to a certain height, it becomes possible to omit or reduce the scaffold when assembling the segments.
Moreover, earth pressure management is easy by constructing the embankment part 8 in steps, and the earth pressure, uneven earth pressure, and water pressure which act on the side wall 3 can be excluded. Moreover, the earth pressure and water pressure which act on the side wall 3 are suppressed to the minimum by laying the reinforcing material 81 in the banking part 8, and making the banking part 8 self-supporting.

掘削残土を盛土部8に使用しているため、排土量を大幅に削減することができ、経済的である。また、掘削残土を仮置きするためのヤードを省略または削減することができるため、使用可能な敷地が限られている場合であっても、施工が可能である。さらに、掘削残土の運搬距離を大幅に削減することができるため、効率的である。
盛土部8の施工は、セグメントリング7の外側で行うため、盛土部8の施工時に立坑5内に盛土材等が落下することを防止することができる。
Since the excavated residual soil is used for the embankment 8, the amount of soil discharged can be greatly reduced, which is economical. In addition, since the yard for temporarily placing the excavated soil can be omitted or reduced, construction is possible even when the usable site is limited. Furthermore, since the transport distance of excavated soil can be significantly reduced, it is efficient.
Since the construction of the embankment portion 8 is performed outside the segment ring 7, it is possible to prevent the embankment material and the like from falling into the shaft 5 during construction of the embankment portion 8.

盛土部8がカウンターウェイトとして機能するため、地下式貯槽1の浮き上がりが防止される。
また、盛土部8により立坑5周囲の地盤の圧密沈下を施工時から促進させることができるため、立坑5の完成後の圧密沈下量を抑制することが可能である。そのため、付帯工事の着手を早めることが可能である。
地中連続壁6およびセグメントリング7は、円形(円筒状)に形成されているため、土圧および地下水圧に対して十分な耐力を発現する。
Since the embankment portion 8 functions as a counterweight, the underground storage tank 1 is prevented from rising.
Moreover, since the settlement of the ground around the shaft 5 can be promoted by the embankment portion 8 from the time of construction, the amount of consolidation settlement after the completion of the shaft 5 can be suppressed. Therefore, it is possible to accelerate the start of incidental work.
Since the underground continuous wall 6 and the segment ring 7 are formed in a circular shape (cylindrical shape), they exhibit sufficient strength against earth pressure and groundwater pressure.

また、セグメントリング7を側壁3の外型枠に利用しているため、別途外型枠を設置する作業を省略することができる。また、コンクリート打設時の端太材等の反力体を省略することができるため、反力体の設置に要する手間や費用を削減することができる。
地上壁71に排水管73が配管されているため、盛土部8内の水分を排水し、側壁3への負担を軽減することができる。
Further, since the segment ring 7 is used for the outer mold of the side wall 3, the work of installing the outer mold can be omitted. Moreover, since a reaction force body such as a thick end material at the time of placing concrete can be omitted, it is possible to reduce labor and cost required for installing the reaction force body.
Since the drain pipe 73 is piped to the ground wall 71, the water in the embankment part 8 can be drained and the burden on the side wall 3 can be reduced.

以上、本発明の実施形態について説明したが、本発明は、前述の実施形態に限られず、前記の各構成要素については、本発明の趣旨を逸脱しない範囲で、適宜変更が可能である。
前記実施形態では、地下式貯槽を構築する場合について説明したが、本発明の立坑の用途は限定されるものではない。例えば、建物や駅等のあらゆる地下構造物を構築する際の土留用の立坑として使用してもよいし、トンネル工事の発進立坑や到達立坑として使用してもよい。
Although the embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and the above-described components can be appropriately changed without departing from the spirit of the present invention.
In the above embodiment, the case of constructing an underground storage tank has been described, but the use of the shaft of the present invention is not limited. For example, it may be used as a shaft for earth retaining when constructing any underground structure such as a building or a station, or may be used as a starting or reaching shaft for tunnel construction.

前記実施形態では、盛土部内に補強材を敷設する場合について説明したが、補強材は省略してもよい。また、補強材は、盛土部の下部のみに配設してもよいし、全高に配設してもよい。
また、立坑内(地中連続壁の内側)の掘削方法、土砂搬出方法等は、前記実施形態で示した方法に限定されるものではない。
初期掘削において、地中連続壁の内面に沿って円環状に原地盤を残置させた状態で中央部のみを掘削すれば、最下段のセグメントリングを形成する際の足場を、セグメントリングの内外に確保することができる。
図7に示すように、セグメントリング7は、セグメント72同士の継手部の外側に継手部を覆う補強材75が固定されていてもよい。こうすることで、セグメントリング7のリングコンプレッションに対する耐力をより高めることができる。
Although the said embodiment demonstrated the case where a reinforcing material was laid in the embankment part, you may abbreviate | omit a reinforcing material. Further, the reinforcing material may be disposed only at the lower part of the embankment part, or may be disposed at the entire height.
Moreover, the excavation method in the shaft (the inside of the underground continuous wall), the sediment transport method, and the like are not limited to the methods shown in the embodiment.
In the initial excavation, if only the central part is excavated with the original ground left in an annular shape along the inner surface of the underground continuous wall, the scaffold for forming the lowest segment ring can be placed inside and outside the segment ring. Can be secured.
As shown in FIG. 7, in the segment ring 7, a reinforcing member 75 that covers the joint portion may be fixed to the outside of the joint portion between the segments 72. By carrying out like this, the proof stress with respect to the ring compression of the segment ring 7 can be raised more.

1 地下式貯槽
10 メンブレン
2 底版
3 側壁
4 屋根
5 立坑
6 地中連続壁
7 セグメントリング
71 地上壁
8 盛土部
DESCRIPTION OF SYMBOLS 1 Underground storage tank 10 Membrane 2 Bottom plate 3 Side wall 4 Roof 5 Vertical shaft 6 Underground continuous wall 7 Segment ring 71 Ground wall 8 Embankment part

Claims (5)

円筒状に形成した地中連続壁と、
前記地中連続壁の上端に立設されたセグメントリングと、
前記セグメントリングの外周囲に盛り立てられた盛土部と、を備える立坑であって、
前記盛土部が、前記地中連続壁により囲まれた地盤を掘削することにより発生した掘削残土を含む盛土材により形成されていることを特徴とする、立坑。
A continuous underground wall formed in a cylindrical shape;
A segment ring erected at the upper end of the underground continuous wall;
A shaft provided with an embankment raised on the outer periphery of the segment ring,
The shaft is characterized in that the embankment portion is formed of an embankment material including excavation residual soil generated by excavating the ground surrounded by the underground continuous wall.
前記盛土部に補強材が埋め込まれていることを特徴とする、請求項1に記載の立坑。   The shaft according to claim 1, wherein a reinforcing material is embedded in the embankment. 円筒状に形成した地中連続壁と、
前記地中連続壁の上端に立設されたセグメントリングと、
前記セグメントリングの外周囲に盛り立てられた盛土部と、
前記地中連続壁および前記セグメントリングの内面に沿って形成された側壁と、を備える地下式貯槽であって、
前記盛土部が、前記地中連続壁により囲まれた地盤を掘削することにより発生した掘削残土を含む盛土材により形成されていて、
前記側壁の上部が、前記セグメントリングを外型枠として形成されていることを特徴とする、地下式貯槽。
A continuous underground wall formed in a cylindrical shape;
A segment ring erected at the upper end of the underground continuous wall;
An embankment raised on the outer periphery of the segment ring;
An underground storage tank comprising: the underground continuous wall and a side wall formed along the inner surface of the segment ring;
The embankment portion is formed of a fill material including excavation residue generated by excavating the ground surrounded by the underground continuous wall;
An underground storage tank, wherein an upper portion of the side wall is formed with the segment ring as an outer mold.
地中連続壁を円筒状に形成する工程と、
前記地中連続壁の上端において複数のセグメントを組み立てることによりセグメントリングを形成する工程と、
前記地中連続壁により囲まれた地盤を掘削するとともに、前記地盤の掘削により発生した掘削残土を含む盛土材を前記地中連続壁の外周囲に盛り立てる工程と、を備えることを特徴とする、立坑の構築方法。
Forming the underground continuous wall into a cylindrical shape;
Forming a segment ring by assembling a plurality of segments at the upper end of the underground continuous wall;
Excavating the ground surrounded by the underground continuous wall, and raising the embankment material including excavation residual soil generated by excavating the ground around the outer periphery of the underground continuous wall, How to build a shaft.
地中連続壁を円筒状に形成する工程と、
前記地中連続壁の上端において複数のセグメントを組み立てることによりセグメントリングを形成する工程と、
前記地中連続壁により囲まれた地盤を掘削するとともに、前記地盤の掘削により発生した掘削残土を含む盛土材を前記地中連続壁の外周囲に盛り立てる工程と、
前記地中連続壁および前記セグメントリングの内面に沿って側壁を形成する工程と、を備えることを特徴とする、地下式貯槽の構築方法。
Forming the underground continuous wall into a cylindrical shape;
Forming a segment ring by assembling a plurality of segments at the upper end of the underground continuous wall;
Excavating the ground surrounded by the underground continuous wall, and raising the embankment material including excavation residual soil generated by excavating the ground around the outer periphery of the underground continuous wall;
Forming a side wall along the underground continuous wall and the inner surface of the segment ring, and a method for constructing an underground storage tank.
JP2015047847A 2015-03-11 2015-03-11 Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method Active JP6402056B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015047847A JP6402056B2 (en) 2015-03-11 2015-03-11 Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015047847A JP6402056B2 (en) 2015-03-11 2015-03-11 Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method

Publications (2)

Publication Number Publication Date
JP2016169474A JP2016169474A (en) 2016-09-23
JP6402056B2 true JP6402056B2 (en) 2018-10-10

Family

ID=56983294

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015047847A Active JP6402056B2 (en) 2015-03-11 2015-03-11 Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method

Country Status (1)

Country Link
JP (1) JP6402056B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112145206A (en) * 2020-09-01 2020-12-29 王文革 Tunnel waterproof device convenient to disassemble and assemble and using method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5848712B2 (en) * 1976-09-01 1983-10-29 石川島播磨重工業株式会社 How to build an underground tank
JPS63117812A (en) * 1986-11-06 1988-05-21 Nagaoka Koichi Continuous vertical conveying device
JPH1161859A (en) * 1997-08-25 1999-03-05 Ohbayashi Corp Construction method and structure for underground structure
US7162844B2 (en) * 2003-01-09 2007-01-16 Chicago Bridge & Iron Company Use of partial precast panels for construction of concrete walls and shells
JP4829870B2 (en) * 2007-11-19 2011-12-07 大成建設株式会社 Underground structure
JP4702674B1 (en) * 2010-08-09 2011-06-15 清水建設株式会社 Construction method of underground tank
JP2012158891A (en) * 2011-01-31 2012-08-23 Shimizu Corp Construction method of pit-in type tank

Also Published As

Publication number Publication date
JP2016169474A (en) 2016-09-23

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
CN101691751B (en) Construction method for making ultra-long artificial excavating pile penetrate cave and ultra-long pile penetrating cave
JP5055249B2 (en) Multiple tunnel construction method and multiple tunnel structure
CN104727302B (en) Board wall cast-in-place construction technique between a kind of friction pile stake
CN110397043A (en) A three-in-one method of foundation pit support internal support system and basement structure system
JP6543176B2 (en) Building method
CN108221528B (en) Roadbed building overlapping structure and construction method
KR101169462B1 (en) Top-down construction method using post member
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
JP7232714B2 (en) how to build a foundation
CN110318403A (en) A kind of deep basal pit inner support assembled support replacement construction tool and construction method
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP6402056B2 (en) Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system
JP6920039B2 (en) How to dismantle the existing underground skeleton
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
KR101658826B1 (en) Method and structure to build underground structures using the border structure
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
CN104846856B (en) Horizontal inclined independent bent frame column pushing correction method
KR20100118000A (en) Using reclamation steel perimeter beam and girder which the basement infrastructure construction method
JP2011241608A (en) Construction method of basement in existing house
JP2021123961A (en) Construction method of pile head reinforcement structure and formwork
KR101058628B1 (en) Retaining wall construction structure using landscape stone
CN111254938B (en) Foundation pit supporting structure based on side wall of underground chamber and reverse construction method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171114

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180725

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180904

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180910

R150 Certificate of patent or registration of utility model

Ref document number: 6402056

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250