SU994771A1 - Method of preventing outbursts of coal, rock and gas when driving preparatory workings - Google Patents
Method of preventing outbursts of coal, rock and gas when driving preparatory workings Download PDFInfo
- Publication number
- SU994771A1 SU994771A1 SU813348964A SU3348964A SU994771A1 SU 994771 A1 SU994771 A1 SU 994771A1 SU 813348964 A SU813348964 A SU 813348964A SU 3348964 A SU3348964 A SU 3348964A SU 994771 A1 SU994771 A1 SU 994771A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- gas
- coal
- rock
- outbursts
- preventing
- Prior art date
Links
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Description
Изобретение относитс к горной промышленности и может быть использовано дл предупреждени выбросов угл , породы и газа при взрывных работах.The invention relates to the mining industry and can be used to prevent emissions of coal, rock and gas during blasting operations.
Известен способ предотзвращени внезапных выбросов угл , породы и газа, включающий установку на некотором рассто нии от -забо выработки перемычки, разрушение части порой взрывными работами дл заполнени пространства от забо до перемычки породой, отбойку угл СП.There is a known method for preventing sudden outbursts of coal, rock, and gas, including installing at a distance from the jumper to produce a jumper, sometimes destroying a part with explosives to fill the space from the hole to the jumper with rock, breaking the coal of the joint venture.
Недостатком способа. вл етс снижение темпов проведени выработок из-за необходимости проведени дополнительных работ.по удалению породы из забо выработки и недостаточно высока эффективность способа из-за сложности производства работ.The disadvantage of the method. is a reduction in the rate of excavation due to the need for additional work to remove the rock from the excavation and the efficiency of the method is not high enough due to the complexity of the work.
Наиболее близким по технической сущности и получаемому результату к предлагаемому вл етс способ предотвращени выбросов при взрывных работах; включающий бурение шпуров в призабойном пространстве, их зар жение , установку перемычки, создание в изрлированном пространстве между перемычкой и забоем газового давлени , равного давлению газа в пластеjThe closest in technical essence and the result to the proposed is a way to prevent emissions from blasting; including drilling holes in the wellbore space, their charging, setting the jumper, creating a gas pressure in the diverted space between the jumper and the bottom, equal to the pressure of gas in the reservoir
взрывание ВВ в umypcix по отбойке угл С 2.blasting explosives in umypcix for blasting coal C 2.
Недостатком известного способа вл етс сложность и трудоемкость сооружени прочной герметической перемычки , расчитанной на давлений газа в пласте, достигающего на особо внбросоопасных пластаис 40-100 атм, создание и поддержание в изолированном The disadvantage of the known method is the complexity and laboriousness of constructing a solid hermetic bridge, designed for gas pressures in the reservoir, reaching 40-100 atm for particularly bio-hazardous reservoirs, creating and maintaining in an isolated
10 пространстве высокого давлени газа, и низка эффективность способа из-за неудобства зар жани и взрывани шпуров в стесненных услови х и неустойчивости перемычки при больших 10 space of high pressure gas, and low efficiency of the method due to the inconvenience of charging and blasting holes in cramped conditions and instability of the jumper at large
15 ударных нагрузках.15 shock loads.
Цель изобретени - снижение трудоемкости работ и повьаиение эффективности способа.The purpose of the invention is to reduce the complexity of work and improve the efficiency of the method.
Поставленна цель, достигаетс тем, The goal is achieved by
20 что сс5гласно способу, включающему бурение шпуров в призабойном пространстве , их зар жание,; установку перемычки , создание в изолированном пространстве между.перемычкой и забоем 20 that cc5 according to the method, including drilling holes in the wellbore space, their charging ,; jumper installation, creation in an isolated space between the jumper and the bottom
25 газового.давлени , равного давлению газа в пласте, взрывание ВВ в шпурах по отбойке угл , в призабойном пространстве выработки создают дополнительный объем путем образовани в 25 gas pressure equal to the pressure of the gas in the reservoir, blasting of explosives in boreholes on the coal blasting, in the bottomhole production space creates additional volume by forming in
30 стенкаис выработки скважин или увели-30 wall well production or increase
чени глубины и диаметра шпуров по отбойке угл , размещают в них зар ды ВВ с высоким удельным объемом выделени газов, и производ т их взрывание одновременно с зар дс1ми в шпурах по отбойке угл , при этом перемычку устанавливают на рассто нии от забо выработки равном где Q - обща величина ВВ, кг; п - удельный выход газов при взрыве, л k - коэффициент кг/см S - сечение выработки, р - расчетна величина избыточного давлени за перемЕлчкой кг/см . Способ осуществл етс следук цим образом. В груди забо и стенках выработк одновременно производ т бурение шпуров дл отбойки угл и скважин дл размещени дополнительных зар дов В Создание объемов в призабойном прос ранстве дл размещени дополнительных зар дов ВВ возможно осуществл т и другим способом, а именно увеличе нием глубины шпуров по отбойке угл или их диаметра. Размещамр: в шпурах и скважинах зар ды ВВ и возвод т перемычку на рассто нии от забо , определ емом из зависимости При этом используютс перемычки негерметичного типа,, так как внезапный выброс представл ет собой процесс мгновенного действи и период воздействи противодавлени в изолированном пространстве вл етс кратковременным , что существенно снижает трудоемкость и врем работ на ее сооружение и последук цую разборку. Изменение требовани в части герметичности перелвычки позвол ет перейти от сплошных стационарных перемычек типа наливного бетона к разборным. В качестве последних могут примен ть с составные перемычки из балок металлического профил , пневмобаллонов дерев нных брусьев или в виде передвижных щитов. Производ т взрывание дополнительных зар дов ВВ одновремен но с зар дами по отбойке угл . Сущность предлагаемого способа заключаетс в использовании сил и продуктов взрыва дополнительных зар дов ВВ дл погашени провоцирующего выброс действи взрыва. Пр и м е р 1. Производитс вскрытие выбросоопасного пласта квер , шлагом. Сечение р 12 м, тип ВВ аммонит Т-19 с удельным объемом газовьщелени 0,72 MVKr, заданна The depths and diameters of holes for coal blasting, place explosive charges with a high specific volume of gas evolution into them, and blast them simultaneously with charges in the coal blasting holes, while the jumper is set at a distance from the hole where Q - total value of explosive, kg; n is the specific yield of gases during an explosion, l k is the ratio kg / cm S is the output cross section, and p is the calculated value of the excess pressure after the crossing kg / cm. The method is carried out in the following manner. Drilling holes in the chest of the bottom and walls of the workings at the same time to coal and bore holes to accommodate additional charges. Creating volumes in the wellbore to accommodate additional explosive charges can also be carried out in another way, namely by increasing the depth of coal holes. or their diameter. Placed: in boreholes and boreholes, explosives are charged and the jumper is erected at a distance from the bottom determined from the dependencies. Non-hermetic type jumpers are used, since sudden outburst is a process of instantaneous action and the period of back pressure in an isolated space is short-term, which significantly reduces the complexity and time of work on its construction and subsequent disassembly. Changing the requirement in terms of leaktightness of the liner allows you to go from continuous stationary bridges such as self-leveling concrete to collapsible. As the latter can be used with composite lintels of metal profile beams, pneumatic tubes of wooden bars or in the form of movable shields. Additional charges of explosives are blasting simultaneously with coal blasting charges. The essence of the proposed method consists in using the forces and products of the explosion of additional explosive charges to repay the precipitating effect of the explosion. Ex. 1. An outburst hazardous reservoir is opened, with a barrier. The cross section is p 12 m, type BB ammonite T-19 with a specific gas gap of 0.72 MVKr, given
величина противодавлени на забой ,5 ата (1,5 атм).Величины количества взрывае 4ого ВВ и рассто ние от забо до перемычки - переменные устанавливаютс расчетомthe value of the back pressure to the bottom, 5 at (1.5 atm).
i 1г5.12 i 1g5.12
15 15
25 кг/м. 25 kg / m.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813348964A SU994771A1 (en) | 1981-10-30 | 1981-10-30 | Method of preventing outbursts of coal, rock and gas when driving preparatory workings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813348964A SU994771A1 (en) | 1981-10-30 | 1981-10-30 | Method of preventing outbursts of coal, rock and gas when driving preparatory workings |
Publications (1)
Publication Number | Publication Date |
---|---|
SU994771A1 true SU994771A1 (en) | 1983-02-07 |
Family
ID=20980760
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU813348964A SU994771A1 (en) | 1981-10-30 | 1981-10-30 | Method of preventing outbursts of coal, rock and gas when driving preparatory workings |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU994771A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109707371A (en) * | 2018-11-19 | 2019-05-03 | 太原理工大学 | A device and method for rapidly measuring the drilling depth of coal seam |
-
1981
- 1981-10-30 SU SU813348964A patent/SU994771A1/en active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109707371A (en) * | 2018-11-19 | 2019-05-03 | 太原理工大学 | A device and method for rapidly measuring the drilling depth of coal seam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110966002B (en) | A method of roof cutting and pressure relief based on dense drilling | |
CN107060773B (en) | A kind of underground chamber drilling and blasting method damping excavation method of static(al) explosion presplitting shock insulation | |
CN111043924B (en) | Efficient blasting method for blocking stemming of tunnel soft rock full-section multistage ultra-deep hole double-end stemming | |
SU994771A1 (en) | Method of preventing outbursts of coal, rock and gas when driving preparatory workings | |
RU2270338C1 (en) | Method for preparation and excavation of inclined and steep mineral bed | |
RU2757619C1 (en) | Method for developing low-powered steel ore bodies | |
CN111486760B (en) | A high-stage controlled blasting method for underground mines | |
SU1469137A1 (en) | Roof control method | |
RU2307936C1 (en) | Method for inclined ore deposit development | |
RU2762170C1 (en) | Method for developing thin and low-powered steel-falling ore bodies | |
CN110645854B (en) | Arrangement of pre-split blasting holes and on-line detonation method for hard roof in the initial mining of fully mechanized mining face | |
RU2224891C2 (en) | Method for extracting mined blocks during subterraneous extraction of blind ore bodies | |
RU2011822C1 (en) | Method for roof control | |
RU2078211C1 (en) | Method of mining thick steep coal seams | |
SU1666710A1 (en) | Method for development of mineral deposits | |
RU2193659C2 (en) | Method of mineral deposits mining | |
RU2203419C2 (en) | Process of underground development of thick ore deposits | |
SU1659668A1 (en) | Method of safeguarding entries | |
SU907254A1 (en) | Method of extinguishing voids | |
CN108661638B (en) | A kind of method of ring holes recycling ore pillar | |
RU2089844C1 (en) | Method of blasting of low-stable ore bodies | |
RU2012804C1 (en) | Method for protection of workings from rock pressure | |
SU1125373A1 (en) | Method of mining unstable ores | |
Eremenko et al. | Influence exerted by construction of vertical cylindrical explosive charges increased in diameter on the degree of ore shattering | |
SU883421A1 (en) | Method of explosion-breaking of ore |