SU1583710A1 - Method and apparatus for constructing a secondary lining in tunnel - Google Patents
Method and apparatus for constructing a secondary lining in tunnel Download PDFInfo
- Publication number
- SU1583710A1 SU1583710A1 SU874185515A SU4185515A SU1583710A1 SU 1583710 A1 SU1583710 A1 SU 1583710A1 SU 874185515 A SU874185515 A SU 874185515A SU 4185515 A SU4185515 A SU 4185515A SU 1583710 A1 SU1583710 A1 SU 1583710A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- formwork
- concrete
- tunnel
- interval
- length
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 8
- 238000009415 formwork Methods 0.000 claims abstract description 53
- 239000004567 concrete Substances 0.000 claims abstract description 27
- 230000007246 mechanism Effects 0.000 claims abstract description 4
- 238000009434 installation Methods 0.000 claims description 3
- 230000001447 compensatory effect Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 3
- 239000004570 mortar (masonry) Substances 0.000 abstract 1
- 230000001144 postural effect Effects 0.000 abstract 1
- 101100148823 Streptomyces halstedii schA gene Proteins 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000011010 flushing procedure Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Изобретение относитс к подземному строительству, а именно к способам возведени вторичной отделки в тоннел х. Оно позвол ет исключить осевую неуравновешенность опалубок и повысить качество возводимой отделки путем повышени давлени нагнетани . В тоннеле с первичной отделкой 1 размещают комплект из двух самоходных опалубок 2, 3, перва из которых предыдуща , а втора - последующа . Бетонируют заходки через одну при помощи первой опалубки. Заопалубочное пространство перекрывают съемными торцовыми уплотнительными шандорами. Бетон подают по бетоноводу. Осевую передвижку опалубки 2 с одной заходки на другую производ т после твердени бетона. Шаг передвижки превышает собственную длину опалубки 2 на длину интервала между заходками. Интервал между заходками, меньше длины второй опалубки 3 на величину, достаточную дл опирани концевых участков опалубки 3. Опалубку 3 перемещают по тоннелю вслед за опалубкой 2, перекрывают ее интервал и бетонируют его. Опалубку 3 устанавливают, опира на концевые участки ранее забетонированных заходок. Съемные торцовые уплотнительные шандоры на опалубке 3 не устанавливают. Дл удержани раствора используют торцовые поверхности 10, 11 ранее забетонированных заходок. Бетонирование опалубок 3, 2 осуществл ют с небольшим разрывом по времени от одного бетоннонасоса. Опалубки 2, 3 состо т из шарнирно-складывающихс сегментов, механизма складывани , транспортного моста, ссыпных торцовых шандор и компенсационных накладок по наружным поверхност м сегментов. Толщина передней накладки превышает толщину задних. Это позвол ет использовать опалубки 2, 3 по отдельности. 2 с.п. ф-лы, 3 ил.The invention relates to underground construction, and in particular to methods for the erection of secondary finishing in tunnels. It eliminates the axial imbalance of the formwork and improves the quality of the erected finish by increasing the discharge pressure. In a tunnel with a primary finish 1, a set of two self-propelled formwork 2, 3 is placed, the first of which is the previous one, and the second - the next. Concrete entry through one using the first formwork. The postural space is overlapped with removable mechanical seal girders. Concrete is supplied through the concrete line. Axial shifting of formwork 2 from one stopping to another is done after the concrete has hardened. The step of shifting exceeds the own length of formwork 2 by the length of the interval between entries. The interval between the inlets is less than the length of the second formwork 3 by an amount sufficient to support the end sections of the formwork 3. The formwork 3 is moved through the tunnel after the formwork 2, cover its interval and concretes it. Formwork 3 set, based on the end sections of the previously concreted entries. Removable end seals on formwork 3 do not install. To hold the mortar, end surfaces 10, 11 of previously concreted inlets are used. Concreting of the formwork 3, 2 is carried out with a small gap in time from one concrete pump. The formwork 2, 3 consists of hinged-folding segments, a folding mechanism, a transport bridge, a curved end faceplate, and compensation pads along the outer surfaces of the segments. The thickness of the front lining exceeds the thickness of the rear. This allows formwork 2, 3 to be used separately. 2 sec. f-ly, 3 ill.
Description
Изобретение относитс к подземному стро ительству, а именно к способам возведени вторичной обделки в тоннел х, и может быть использовано в городском подземном строительстве .The invention relates to underground construction, in particular to methods for erecting a secondary lining in tunnels, and can be used in urban underground construction.
Цель изобретени - исключение осевой неуравновешенности опалубок, повышение качества обделки путем повышени давлени нагнетани .The purpose of the invention is to eliminate the axial unbalance of formwork, to improve the quality of the lining by increasing the discharge pressure.
На фиг. 1 изображено размещение опалубок в тоннеле и бетонирование предыду- щей,опалубкой первых заходок, исходное положение; на фиг. 2 - установка опалубок в тоннеле дл последовательного бетонировани ; на фиг. 3 - вид А на фиг. 1.FIG. Figure 1 shows the placement of the formwork in the tunnel and the concreting of the previous one, the first formwork of the first approach, the initial position; in fig. 2 — installation of formwork in a tunnel for sequential concreting; in fig. 3 is a view A of FIG. one.
Способ осуществл ют следующим обра- зом.The method is carried out as follows.
В тоннеле с первичной обделкой 1 размещают комплект из двух самоходных опалубок 2 и 3, перва из которых предыдуIn the tunnel with the primary lining 1 place a set of two self-propelled formwork 2 and 3, the first of which the previous
ща , а втора schA, and the second
последующа .the following.
На начальном участке тоннел первые за ходки 4 и 5 бетонируют при помощи первой опалубки 2, устанавливаемой поэтапно на каждой из этих заходок на первичной обделке 1 внутри тоннел . Торцы заопалубочного пространства опалубки 2 перекрывают съемными торцевыми уплотни- тельными шандорами б и 7. Бетон подают по бетоноводу 8 от наход щегос на поверхности или в шахте бетононасоса. Осевую передвижку опалубки 2 с заходки 4 на заходку 5 производ т после твердени бетона и ее складывани , причем шаг передвижки превышает собственную длину первой опалубки на длину интервала 9 между заходками 4 и 5, который оставл ют меньше длины второй опалубки 3 на величину, достаточную дл опирани кон- цевых участков второй опалубки 3.In the initial section of the tunnel, the first passes for 4 and 5 are concreted using the first formwork 2, which is installed in stages at each of these entries on the primary lining 1 inside the tunnel. The ends of the bottom-up space of the formwork 2 are overlapped with removable end seal seals b and 7. Concrete is supplied through the concrete line 8 from the concrete pump that is located on the surface or in the mine. The axial movement of the formwork 2 from step 4 to step 5 is made after the concrete has hardened and folded, and the step of shifting exceeds the original length of the first formwork by the length of the interval 9 between steps 4 and 5, which is less than the length of the second formwork 3 supporting the end plots of the second formwork 3.
После твердени бетона на заходке 5 первую опалубку 2 перемещают по тоннелю на очередную заходку, оставл такой же интервал 9, а вторую опалубку 3 перемещают по тоннелю вслед за первой опалубкой 2 и устанавливают на вторичной обделке , опира на концевые участки ранее забетонированных заходок 4 и 5 и перекрыва интервал 9 между ними. При этом съемные торцовые уплотнительные шандоры 6 и 7 на второй опалубке 3 не устанавливают, а дл удержани раствора бетон по торцам ее заопалубочного пространства используют торцовые поверхности 10 и И ранее забетонированных заходок 4 и 5. Производ т бетонирование за вторую опалубку 3 в интерва- лах 9 между заходками 4 и 5, после чего наращивают длину бетоновода 8 до первой опалубки 2 и бетонируют ее заопалубочное пространство, а затем отсоедин ют и промывают бетоновод 8. Указанные операции по бетонированию заопалубочного прост- ранства обеих опалубок выполн ют с небольшим разрывом по времени от одного и того же бетононасоса, поэтому надобность в проAfter hardening of concrete at gate 5, the first formwork 2 is moved through the tunnel to the next stop, leaving the same interval of 9, and the second formwork 3 is moved through the tunnel after the first formwork 2 and is installed on the secondary lining, resting on the end sections of previously cast concrete 4 and 5 steps and overlapping the interval 9 between them. At the same time, removable face sealing bolts 6 and 7 are not installed on the second formwork 3, but to hold the concrete along the ends of its co-fi lling space, use face surfaces 10 and and previously cast concrete 4 and 5. Concreting for the second formwork 3 is performed in intervals 9 between entries 4 and 5, after which they increase the length of the betonovod 8 to the first formwork 2 and concrete its filing space, and then disconnect and wash the concrete flow conduit 8. The specified concreting operations of the filing space are of formwork is performed with a small gap in time from the same concrete pump, so the need for pro
00
5 0 5 5 0 5
5 0 5 5 0 5
межуточной промывке бетоновода 8 отсутствует .interstitial flushing betonovod 8 is missing.
Устройство дл осущствленн способа состоит из двух последовательно установленных опалубок 2 и 3, которые включают шарнирноскладывающиес сегменты 12-16, механизмы 17 складывани , транспортные мосты 18 и 19, съемные торцовые уплотнительные шандоры 6 и 7 и компенсационные накладки 20-22 по наружным поверхност м сегмантов 12-16. При этом компенсационные накладки 20 и 21 монтированы соответственно со стороны переднего и заднего торцов предыдущей опалубки 2, а накладка 22 - со стороны заднего торца последующей опалубки 3. Толщина передней накладки 20 превышает толщину задних накладок 21 и 22.The device for implementing the method consists of two successively installed forms 2 and 3, which include swivel segments 12-16, folding mechanisms 17, transport bridges 18 and 19, removable end seals 6 and 7 and compensation pads 20-22 on the outer surfaces of the segents 12-16. When this compensation pads 20 and 21 are mounted respectively from the front and rear ends of the previous formwork 2, and the lining 22 from the rear end of the subsequent formwork 3. The thickness of the front lining 20 exceeds the thickness of the rear pads 21 and 22.
Установку второй опалубки 3 производ т так, что ее передн часть без наружной компенсационной накладки размещаетс на заходке 5 в бетонном отпечатке 23 от задней накладки 21 первой опалубки 2, а хвостова часть с накладкой 22 - на заходке 4 в бетонном отпечатке 24 от передней накладки 20 первой опалубки 2.The second formwork 3 is installed in such a way that its front part without an external compensation pad is placed at gate 5 in the concrete footprint 23 from the rear lining 21 of the first formwork 2, and tail section with plate 22 - at gate 4 in the concrete footprint 24 from the front plate 20 first formwork 2.
После набора прочности бетоном производ т демонтаж торцовых уплотнительных шандор 6 и 7, складывание опалубок 2 и 3 при помощи соответствующих механизмов 17 складывани , перемещение обеих опалубок при помощи транспортных мостов 18 и 19, которые обеспечивают возможность перемещени опалубки как вперед, так и назад, на очередной шаг бетонировани , раскрытие и установку обеих опалубок на новых заход- ках. Накладки 20-22 компенсируют точности изготовлени поперечных сечений переднего и заднего концов каждой опалубки, а также первой и второй опалубок одна относительно другой.After curing with concrete, the end seals 6 and 7 are disassembled, the formwork 2 and 3 are folded using appropriate folding mechanisms 17, and both forms are moved using transport bridges 18 and 19, which allow the formwork to be moved both forward and backward. the next step of concreting, opening and installation of both formwork in new entries. The pads 20-22 compensate for the accuracy of the manufacture of cross sections of the front and rear ends of each formwork, as well as the first and second formwork one relative to the other.
Превышение размеров поперечного сечени каждой опалубки со стороны одного из их торцов по сравнению с размерами другого торца, достигаемое установкой компенсационных накладок 20-22, позвол ет при необходимости использовать опалубки по отдельности по известному способу при продолжении бетонировани вторичной обделки только с помощью предыдущей опалубки 2 после вывода последующей опалубки 3 назад в шахтный ствол дл ремонта.Exceeding the cross section of each formwork on the side of one of their ends compared to the size of the other end, achieved by installing compensation linings 20-22, allows, if necessary, to use the formwork separately by a known method while continuing to concrete the secondary lining only with the previous formwork 2 after bringing the subsequent formwork 3 back into the shaft for repair.
Применение предлагаемого способа позвол ет увеличить суточный темп возведени вторичной обделки в тоннеле и повысить эффективность использовани бетононасоса, а также за счет устранени одностороннего осевого давлени бетона на опалубки ликвидировать осевую неуравновешенность обеих опалубок в момент бетонировани , что обеспечивает повышение давлени бетонировани и улучшение качества готовой обделки без дополнительного вибрировани бетона.The application of the proposed method allows to increase the daily rate of erection of the secondary lining in the tunnel and to increase the efficiency of using the concrete pump, as well as eliminating the axial unbalance of both forms at the time of concrete casting, which increases the pressure of concrete and improves the quality of the finished lining additional vibrating concrete.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874185515A SU1583710A1 (en) | 1987-01-21 | 1987-01-21 | Method and apparatus for constructing a secondary lining in tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU874185515A SU1583710A1 (en) | 1987-01-21 | 1987-01-21 | Method and apparatus for constructing a secondary lining in tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1583710A1 true SU1583710A1 (en) | 1990-08-07 |
Family
ID=21282115
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU874185515A SU1583710A1 (en) | 1987-01-21 | 1987-01-21 | Method and apparatus for constructing a secondary lining in tunnel |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1583710A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107144490A (en) * | 2017-07-03 | 2017-09-08 | 中南大学 | Tunnel Second Lining pours monitoring system and monitoring method |
RU2833228C1 (en) * | 2024-05-30 | 2025-01-15 | Айрат Абдулович Миннуллин | Reinforced concrete culvert reinforcement method |
-
1987
- 1987-01-21 SU SU874185515A patent/SU1583710A1/en active
Non-Patent Citations (1)
Title |
---|
Авторское свидетельство СССР № 1259022, кл. Е 21 D 11/10, 1985. Разработка и внедрение более совершенных технических и технологических решений и конструкторской крепи применительно к различным способам городского подземного строительства. Отчет МГИ. Шифр ПС-1-152, ВНИТИ, 1973, с. 10-13. Опалубка тоннельна ОТП-3.6. Рабочие чертежи СКТБ ГМИС, проект № 2009- ЬО.00.000. 1984. * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107144490A (en) * | 2017-07-03 | 2017-09-08 | 中南大学 | Tunnel Second Lining pours monitoring system and monitoring method |
CN107144490B (en) * | 2017-07-03 | 2023-08-15 | 中南大学 | Tunnel secondary lining pouring monitoring system and monitoring method |
RU2833228C1 (en) * | 2024-05-30 | 2025-01-15 | Айрат Абдулович Миннуллин | Reinforced concrete culvert reinforcement method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4314775A (en) | Method of site casting tunnels, culverts, pressure pipes with minimum forming | |
JPH0821196A (en) | Structure of floor system for segment type tunnel, and construction of segment type tunnel with precast floor system | |
SU1583710A1 (en) | Method and apparatus for constructing a secondary lining in tunnel | |
RU2692518C1 (en) | Method for constructing a three-span subway station of an open method of performing works with a lateral arrangement of passenger platforms and a double-track still tunnel | |
JPS6254959B2 (en) | ||
US1823757A (en) | Subway and tunnel | |
SU574504A2 (en) | Column-tyre subway station | |
SU969900A1 (en) | Method of erecting prestressed tunnel lining | |
SU1583520A1 (en) | Method and apparatus for constructing a solid lining of a canal | |
SU1164425A1 (en) | Method of constructing the station complex of deep underground railway | |
RU2825811C1 (en) | Method of constructing deep underground station on operating underground line without interrupting train traffic | |
SU1065608A1 (en) | Mobile forms for erecting monolithic roof support | |
SU619560A1 (en) | Method of erecting monolithic reinforced concrete span of bridge by pushing | |
SU1073385A1 (en) | Underground electric railway station | |
SU531913A1 (en) | The method of construction of buildings of reinforced concrete | |
SU1427041A1 (en) | Apparatus for concreting solid ferroconcrete pipeline | |
RU2044836C1 (en) | Underground structure and method for erecting the same | |
SU1566033A1 (en) | Method of joining underground tunnel sections | |
SU876941A1 (en) | Flue erecting method | |
SU1129278A1 (en) | Method and apparatus for rendering monolithic a massive concrete structure | |
CN108532627B (en) | Temporary plugging method for pipe gallery port of bolt-fixed prefabricated plate | |
JP2001090487A (en) | Tunnel lining work | |
SU926303A1 (en) | Reinforced concrete lining for walls of underground structure | |
SU1511316A1 (en) | Method of making a key in expansion joints of hydraulic structures | |
SU1096363A1 (en) | Forms for constructing a cylindrical tunnel |