[go: up one dir, main page]

SU1566025A1 - Method of working pillars - Google Patents

Method of working pillars Download PDF

Info

Publication number
SU1566025A1
SU1566025A1 SU884478719A SU4478719A SU1566025A1 SU 1566025 A1 SU1566025 A1 SU 1566025A1 SU 884478719 A SU884478719 A SU 884478719A SU 4478719 A SU4478719 A SU 4478719A SU 1566025 A1 SU1566025 A1 SU 1566025A1
Authority
SU
USSR - Soviet Union
Prior art keywords
ore
layer
ledge
pillars
compensation space
Prior art date
Application number
SU884478719A
Other languages
Russian (ru)
Inventor
Валентин Михайлович Кучер
Вячеслав Евгеньевич Василенко
Юрий Юрьевич Кривенко
Виктор Александрович Горобец
Original Assignee
Криворожский горнорудный институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Криворожский горнорудный институт filed Critical Криворожский горнорудный институт
Priority to SU884478719A priority Critical patent/SU1566025A1/en
Application granted granted Critical
Publication of SU1566025A1 publication Critical patent/SU1566025A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

Изобретение относитс  к подземной разработке рудных тел. Цель изобретени  - повышение эффективности отработки целиков уступчатой формы за счет роста производительности выемки и снижени  разубоживани  руды. Целик отрезают от массива, образуют выпускные выработки и формируют компенсационное пространство над днищем. Руду отбивают послойно на компенсационное пространство. Первый слой руды отбивают в центральной части целика, а последующие слои - попарно от центра к флангам. Отбойку каждого сло  ограничивают по простиранию плоскост ми проекций уступов целика на днище, а по высоте основани ми уступов и производ т при этом отрезку уступа, соответствующего отбиваемому слою. Выпуск руды из каждого сло  под опускающимс  отрезанным уступом осуществл ют до момента достижени  уступом верхней отметки соседнего с ним нижележащего уступа. Затем производ т указанную парную отбойку слоев руды. 4 ил.This invention relates to the underground mining of ore bodies. The purpose of the invention is to increase the efficiency of working out the substitute pillars by increasing the productivity of the excavation and reducing the dilution of ore. Pillars cut off from the array, form the exhaust workings and form a compensation space above the bottom. Ore beat back in layers to the compensation space. The first layer of ore is fought off in the central part of the pillar, and the subsequent layers - in pairs from the center to the flanks. The stripping of each layer is limited along the strike by the planes of the projections of the backsides of the rear sight on the bottom, and along the height of the bases of the ledges, and at the same time they produce a section of the ledge corresponding to the backing layer. The ore is discharged from each layer under the descending cut-off ledge until the point reaches the upper level of the adjacent lower scarp. Then, the specified ore layer crushing is performed. 4 il.

Description

Изобретение относитс  к горному делу и может быть использовано при подземной разработке мощных крутопадающих рудных тел.The invention relates to mining and can be used in the underground mining of powerful steeply dipping ore bodies.

Цель изобретени  - повышение эффективности отработки целиков уступчатой формы за счет роста производительности выемки и снижени  разубоживани  руды.The purpose of the invention is to increase the efficiency of working out the substitute pillars by increasing the productivity of the excavation and reducing the dilution of ore.

На фиг.1-4 показан целик на различных стади х отработки, вертикальный разрез оFigures 1-4 show the rear sight in various stages of mining, a vertical section about

Способ реализуют следующим образом .The method is implemented as follows.

В днище 1 проход т выпускные дуч- ки 2. Целик 3 отрезают от вис чегоIn the bottom 1 the exhaust gears 2 pass. Rear sight 3 is cut off from hanging

и лежачего боков (не показаны). Над днищем 1 образуют компенсационное пространство 4 (фиг.1), которое ограничивают по простиранию плоскост ми 5 (следы которых показаны пунктиром на фиг.1) проекции верхнего уступа 6 целика 3 на днище 1. Над компенсационным пространством 4 в центральной части целика скважинами 7 разбуривают первый слой руды, расположенный между плоскост ми 5 проекций верхнего уступа 6 на днище 1 и плоскостью основани  верхнего уступа 6 целика 3. Скважины 7 зар жают взрывчатыми веществами и отбивают разбуренный слой руды на компенспционное пространство 4, при этом отрезают уступ над отбиваемым слоем. Отбитую руду через дучки 2 выпускают на откаточный горизонт 8, при этом под действием налегающих пород 9 иand lying sides (not shown). Above the bottom 1 they form a compensation space 4 (FIG. 1), which is limited along strike by planes 5 (whose traces are shown by a dotted line in FIG. 1) the projections of the upper bench 6 of the rear sight 3 on the bottom 1. Over the compensation space 4 in the central part of the rear sight wells 7 the first layer of ore is drilled, located between the planes 5 of the projections of the upper ledge 6 on the bottom 1 and the plane of the base of the upper ledge 6 of the rear sight 3. The wells 7 are charged with explosives and beat the drilled ore layer into the compensation space 4, this cut off the ledge above beating layer. Repulsed ore through duchki 2 is produced on the haulage horizon 8, while under the action of overburden 9 and

собственного веса верхний уступ 6 целика 3 опускаетс . Массовый выпуск отбитой руды прекращают в момент, когда верхний уступ 6 поравн етс  с верхней отметкой нижележащего соседнего с ним уступа 10 (фиг. 2), После чего производ т частичный выпускits own weight, the upper ledge 6 of the rear sight 3 is lowered. The mass production of broken ore is stopped at the moment when the upper ledge 6 is equal to the upper mark of the adjacent neighboring ledge 10 (Fig. 2), after which a partial release is made

руды в центральной по длине части целика 3, образу  компенсационное пространство (не показано). Затем разбуривают от центра к флангам два сло  11, ограниченные по простиранию плоскост ми проекций (показаны пунктиром на фиг.З) уступов 10 на днище 1 , а по высоте - плоскост ми оснований этих уступов, и отбивают разбуренные оба участка руды на компен- сационое пространство (не показано), образованное при частичном выпуске отбитой руды предыдущего сло . Выпускают отбитую руду до момента опускани  уступов 6 и 10 на уровне нижележащих , соседних с уступами 10. И повтор ют операции до момента опускани  всех уступов на уровень нижнегоore in the central part of the pillar 3, forming a compensation space (not shown). Then, two layers 11 are bored from the center to the flanks, bounded along the strike by the planes of projections (shown by dashed lines in FIG. 3) of the ledges 10 on the bottom 1, and in height by the planes of the bases of these ledges, and they beat off the drilled space (not shown), formed by the partial release of broken ore of the previous layer. Released ore is released until the steps 6 and 10 are lowered at the level below, adjacent to the steps 10. And the operations are repeated until all the steps are lowered to the level below.

10ten

1515

1566025415660254

Claims (1)

(фиг.4), который отрабатывают известным способом. Формула изобретени (figure 4), which work out in a known manner. Invention Formula Способ отработки целиков, включающий отрезку целика от массива, образование выпускных выработок, формирование компенсационного пространства над днищем, послойную отбойку руды на компенсационное пространство и выпуск отбитой руды под опускающимс  целиком, отличающийс  тем, что, с целью повышени  эффективности отработки целиков уступчатой формы за счет роста производительности выемки и снижени  разубоживани  руды, первый слой руды отбивают в центральной части целика, а последующие слои отбивают попарно от центра к флангам целика, причем отбойку каждого сло  ограничивают по простиранию плоскост ми проекций уступов целика на днище, а по высоте - основани ми уступа, и производ т при этом отрезку уступа, соответствующего отбиваемому слою, выпуск руды из каждого отбитого сло  под опускающимс  отрезанным уступом осуществл ют до момента достижени  уступом верхней отметки соседнего с ним нижележащего уступа, после чего осуществл ют указанную парную отбойку слоев руды.A method of working out the pillars, which includes the section of the pillar from the massif, the formation of exhaust workings, the formation of the compensation space above the bottom, layering ore to the compensation space and the release of broken ore under the whole lowering, characterized in that, in order to improve the efficiency of working out the substitute form by increasing the performance of the excavation and reduction of ore dilution, the first layer of ore is beaten off in the central part of the rear sight, and the subsequent layers are beaten off in pairs from the center to the flanks of the rear sight, Moreover, the stripping of each layer is limited along the strike by the projection planes of the rear pillars on the bottom, and in height - by the bases of the ledge, and at the same time producing a section of the ledge corresponding to the pitting layer, ore from each broken layer under the descending cut offset is carried out until reaching the ledge of the upper mark of the adjacent lower ledge, after which the said pair breaking of the ore layers is carried out. 2020 2525 30thirty 2/ I/2 / I / Составитель В Черкашенинов Редактор Н. Рогулич Техред М.Ходанич КорректорВ. Гирн к .Compiled by V. Cherkasheninov Editor N. Rogulich Tehred M. Khodanych Corrector. Girn to. Заказ 1206Order 1206 Тираж 397Circulation 397 ВНИИПИ Государственного комитета по изобретени м и открыти м при ГКНТ СССР 113035, Москва, Ж-35, Раушска  наб., д. 4/5VNIIPI State Committee for Inventions and Discoveries at the State Committee on Science and Technology of the USSR 113035, Moscow, Zh-35, Raushsk nab. 4/5 Производственно-издательский комбинат Патент, г. Ужгород, ул. Гагарина, 101Production and Publishing Combine Patent, Uzhgorod, st. Gagarin, 101 ФигЛFy ПодписноеSubscription
SU884478719A 1988-08-29 1988-08-29 Method of working pillars SU1566025A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884478719A SU1566025A1 (en) 1988-08-29 1988-08-29 Method of working pillars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884478719A SU1566025A1 (en) 1988-08-29 1988-08-29 Method of working pillars

Publications (1)

Publication Number Publication Date
SU1566025A1 true SU1566025A1 (en) 1990-05-23

Family

ID=21397571

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884478719A SU1566025A1 (en) 1988-08-29 1988-08-29 Method of working pillars

Country Status (1)

Country Link
SU (1) SU1566025A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Агошков М.И. и др. Разработка рудных и нерудных месторождений. - М.: Недра, 1983, с. 250-251, Авторское свидетельство СССР № 569712, кл. Е 21 С 41/06, 1971. *

Similar Documents

Publication Publication Date Title
SU1566025A1 (en) Method of working pillars
US4216998A (en) Method of underground mining by pillar extraction
RU2154254C1 (en) Method for drilling and blasting operations in open cuts
SU492662A1 (en) Method for developing steeply dipping ore bodies
SU976745A1 (en) Method for breaking rocks in quarry
RU2017959C1 (en) Method for rock blasting
SU720165A1 (en) Method of mining thick ore deposits with chamber mining system
SU611001A1 (en) Method of borehole hydraulic winning
SU1490419A1 (en) Method of moving rock by explosion
SU1344906A1 (en) Method of driving reserved-dome mine workings
SU1638304A1 (en) Method of mining thick ore deposits
SU1025888A1 (en) Method of preventing sudden short-duration shifting of structures built above an excavatied space
SU1546638A1 (en) Method of mining sloping ore deposits
SU1120749A1 (en) Method of underground leaching of minerals
SU1090266A3 (en) Method for recovering components from underground ore deposit
SU619651A1 (en) Method of excavating development workings at excavation of coal seams
SU1525273A1 (en) Method of breaking pillars
SU1518521A1 (en) Method of mining ore deposits
SU711290A1 (en) Method of working thick gently sloping coal beds
RU95119561A (en) METHOD FOR DEVELOPING MINERAL DEPOSITS
SU1205643A1 (en) Blasting method for overburden operations at opencast mining of seam deposits of useful minerals
SU1019075A1 (en) Method of conducting drilling and blasting jobs
SU1670131A1 (en) Method for mining complex ore bodies with steep rock interlayers
SU1125373A1 (en) Method of mining unstable ores
SU362924A1 (en) METHOD OF PREVENTING MOUNTAIN BREEDS