NL9000138A - Adjoining dwelling construction method - includes concrete base, support beams and interconnected uprights - Google Patents

Adjoining dwelling construction method - includes concrete base, support beams and interconnected uprights Download PDF

Info

Publication number
NL9000138A
NL9000138A NL9000138A NL9000138A NL9000138A NL 9000138 A NL9000138 A NL 9000138A NL 9000138 A NL9000138 A NL 9000138A NL 9000138 A NL9000138 A NL 9000138A NL 9000138 A NL9000138 A NL 9000138A
Authority
NL
Netherlands
Prior art keywords
floor
supporting
upright
foundation
space
Prior art date
Application number
NL9000138A
Other languages
Dutch (nl)
Other versions
NL189927B (en
NL189927C (en
Original Assignee
Cornelis Spee
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cornelis Spee filed Critical Cornelis Spee
Priority to NL9000138A priority Critical patent/NL189927C/en
Publication of NL9000138A publication Critical patent/NL9000138A/en
Publication of NL189927B publication Critical patent/NL189927B/en
Application granted granted Critical
Publication of NL189927C publication Critical patent/NL189927C/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3572Extraordinary methods of construction, e.g. lift-slab, jack-block using templates or jigs to set out buildings or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Construction e.g. of adjoining dwellings or storage sheds, includes laying an aerated concrete base, on which a rectangular foundation beam arrangement is fitted. Uprights with interconnected rods, rest on the transverse beams. Aerated concrete layer 8(2) supports a longitudinal transverse beam arrangement and provides entry spaces for building material. Vertical upright (8) have threaded blocks, for entry of shoring rods (14). Transver beams 16 (a,b,c) form the supports for completing the buildings frame work.

Description

Korte aanduiding: Werkwijze voor het bouwen van één ofmeerdere aaneengesloten woningen of bedrijfsruimten.Short designation: Method for building one or more contiguous homes or commercial spaces.

De uitvinding heeft betrekking op een werkwijze voor hetbouwen van één of meerdere aaneengesloten woningen.The invention relates to a method for building one or more contiguous homes.

Hoewel tegenwoordig bij de bouw van zowel woningen alsutiliteitsgebouwen in toenemende mate gebruik wordt gemaakt vansteeds betere hulpwerktuigen, materialen en organisatie-technieken wordt in feite nog altijd de traditionelebouwmethode toegepast, ondanks het feit dat deze een grootaantal, algemeen bekende, nadelen en beperkingen heeft.Although today, the construction of both residential and utility buildings is increasingly making use of ever better auxiliary tools, materials and organizational techniques, the traditional construction method is in fact still used, despite the fact that it has a large number of well-known disadvantages and limitations.

De uitvinding beoogt dit patroon te doorbrekenen een werkwijze als boven aangegeven te verschaffen die hetmogelijk maakt een aanzienlijke kostenbesparing te bereiken,de bouwwerkzaamheden niet seizoengebonden te verrichten en meteenvoudige en relatief goedkope produktiemiddelen op eenarbeidsvriendelijke wijze onder gunstige werkomstandighedenniet alleen een grotere produktie doch ook een aanzienlijkekwaliteitsverbetering te realiseren.The object of the invention is to break through this pattern and to provide a method as indicated above which makes it possible to achieve considerable cost savings, not to carry out construction work on a seasonal basis and to provide direct and relatively inexpensive means of production in a labor-friendly manner under favorable working conditions, not only with a larger production but also with a considerable quality improvement. realize.

Dit doel wordt bereikt met de werkwijze zoalsgeformuleerd in de hoofdconclusie, waarbij voorkeursuitvoe¬ringsvormen zijn aangegeven in de volgconclusies.This object is achieved by the method as formulated in the main claim, wherein preferred embodiments are indicated in the subclaims.

Doordat reeds direkt na het optrekken van de draagcon¬structie en het op de horizontale liggers aanbrengen dermetaalplaten een door deze platen tegen weersinvloeden afge¬schermde ruimte is verkregen kan onder vrijwel alle weers¬omstandigheden worden doorgewerkt; door de gunstige werkom¬standigheden zal ook het ziekteverzuim lager zijn. Dezeplaten vormen een direkt beloopbare werkvloer en fungeren ineen later stadium als trekwapening voor de te storten beton-vloeren die tijdens het storten ervan volledig afgeschermdzijn. Doordat de afbouwmaterialen droog kunnen wordenopgeslagen zal het verwerken daarvan droog, sneller enprobleemloos kunnen geschieden wat mede de kwaliteit vanhet werk zal verbeteren. Op het werkterrein zelf behoevennog maar weinig materialen en dan nog slechts tijdelijk, teworden opgeslagen. In het bijzonder wordt het, wanneer men te werk gaat zoals aangegeven in conclusie 5, mogelijk pas ineen zeer laat afbouwstadium over de uiteindelijke indeling vanhet gebouwde te beslissen met de mogelijkheid bij de bouw vaneen aantal aaneengesloten woningen de indeling van deindividuele woningen onderling verschillend en naar wens tekiezen. Voorts is het mogelijk later een bestaande indelingmet betrekkelijk weinig kosten te wijzigen.Because dermetal plates have already been obtained immediately after the construction of the supporting construction and the mounting on the horizontal beams, a space is shielded from these influences by these plates, work can continue under almost all weather conditions; absenteeism due to illness will also be lower due to the favorable working conditions. These plates form a directly walkable work floor and at a later stage function as tensile reinforcement for the concrete floors to be poured, which are completely protected during pouring. Because the finishing materials can be stored dry, processing them can be done dry, faster and without problems, which will also improve the quality of the work. On the work site itself, few materials need to be stored, and only temporarily. In particular, if one proceeds as stated in claim 5, it becomes possible to decide at a very late completion stage about the final layout of the built, with the possibility of dividing the individual dwellings in different ways according to the construction of a number of contiguous dwellings. choose wish. Furthermore, it is possible to change an existing layout at a relatively low cost later.

Men heeft de bouwtijd, doordat onder voorspelbare omstandig¬heden wordt gewerkt, beter in de hand.Construction time is better under control, because working under predictable conditions.

De draagconstructie kan worden opgebouwd uit standaard¬onderdelen die steeds opnieuw kunnen worden gebruikt.The supporting structure can be built from standard parts that can be used over and over again.

De uitvinding wordt toegelicht aan de hand van de tekening.Hierin toont;The invention is elucidated with reference to the drawing, which shows;

Figuur 1 schematisch in perspectief de volgens de uit¬vinding toegepaste draagconstructie; figuur 2 een schematisch zijaanzicht van deze draagcon¬structie en het met behulp daarvan verkregen skelet inverschillende fasen der afbouw; figuur 3 het gedeelte tussen de vlakken I-II in figuur 2op vergrote schaal; figuur 4 het gedeelte tussen de vlakken II-III in figuur2 op vergrote schaal; figuur 5 het gedeelte tussen de vlakken III-IV in figuur2 op vergrote schaal; figuur 6 een eindaanzicht van het met de werkwijzevolgens de uitvinding verkregen woningskelet; figuur 7, 8 en 9 verschillende details uit figuur 2.Figure 1 is a schematic perspective view of the supporting construction applied according to the invention; figure 2 shows a schematic side view of this supporting construction and the skeleton obtained with the aid of it in different phases of the completion; figure 3 shows the part between the planes I-II in figure 2 on an enlarged scale; figure 4 shows the part between the planes II-III in figure 2 on an enlarged scale; figure 5 shows the part between the planes III-IV in figure 2 on an enlarged scale; figure 6 shows an end view of the dwelling skeleton obtained with the method according to the invention; figures 7, 8 and 9 different details from figure 2.

In de figuren is met het verwijzingscijfer 2 aangegeveneen gestorte schuimbetonlaag waarop een fundatie rustbestaande uit langsbalken 4 en dwarsbalken 6; het geheelomsluit de kruipruimten 5. Volgens de door de uitvindingvoorgestelde werkwijze wordt op deze fundatie een draag¬constructie opgericht die bestaat uit een aantal verticalestaanders 8, gevormd door met behulp van de schematischaangegeven schroefdraadverbinding 10 in lengte instelbareschroefstempels; een goed verband wordt verkregen door de met 12 respectievelijk 14 aangegeven, eventueel eveneens inlengte instelbare schoren.In the figures, reference numeral 2 denotes a poured foam concrete layer on which a foundation rests consisting of longitudinal beams 4 and cross beams 6; the whole encloses the crawl spaces 5. According to the method proposed by the invention, a supporting construction is erected on this foundation, which consists of a number of vertical uprights 8, formed by screw punches adjustable in length by means of the schematically indicated threaded connection 10; a good connection is obtained by the braces, which may also be adjustable in length, indicated by 12 and 14, respectively.

De onderste schroefstempels, zoals de schroefstempel 8ain figuur 8 zijn direkt aan een fundatiebalk verankerd, - voorde stempel 8a de fundatiebalk 6a - en elke volgende schroefstempelis opgenomen tussen twee in dwarsdoorsnede E - vormigehorizontale dwarsliggers, in figuur 1 aangegeven met 16a voorde onderste, 16b voor de middelste en 16c voor de bovenste; debevestiging geschiedt bijvoorbeeld door middel van flenzen 18(zie figuur 7 en 8). Dergelijke liggers zijn normaal in dehandel verkrijgbaar. Eventueel kunnen ter beveiliging van dewerklieden nog horizontale afschermingen worden aangebracht,in figuur schematisch aangegeven met 20.The bottom screw punches, such as the screw punch 8 in Figure 8, are anchored directly to a foundation beam, - for the punch 8a, the foundation beam 6a - and each subsequent screw punch is included between two in cross section E - shaped horizontal sleepers, indicated in Figure 1 by 16a for the bottom, 16b for the middle and 16c for the top; the fixing is done, for example, by means of flanges 18 (see figures 7 and 8). Such beams are normally available on the market. If necessary, horizontal shields can also be fitted to protect the workers, indicated schematically by 20 in the figure.

Deze gehele constructie wordt opgebouwd uit hoogwaardigstalen elementen met zodanige afmetingen dat ze nog gemakke¬lijk met de hand hanteerbaar zijn zodat voor het oprichten vandeze constructie gebruik kan worden gemaakt van eenvoudigehulpmiddelen zoals een bouwlift.This entire construction is constructed from high-quality steel elements with dimensions such that they are still easy to handle by hand, so that simple aids such as a construction lift can be used to erect this construction.

Op de dwarsliggers 16 worden vervolgens trapeziumvormiggeprofileerde platen 22 aangebracht en met de liggers respec¬tievelijk de fundatie verbonden, bijvoorbeeld door middel vanschietnagels. Wanneer deze operatie is voltooid is over hethele skelet, dus in figuur tussen de vlakken I-IV de situatieontstaan die op vergrote schaal is getekend in figuur 3 en infiguur 2 is getekend tussen de vlakken I-II. De beplating voorde begane grond vloer kan tegelijk met die voor de andere vloerenworden aangebracht; eventueel kan men echter daarmee wachtentot een later stadium met als voordeel dat de kruipruimte 5langer toegankelijk blijft.Trapezoidal profiled sheets 22 are then applied to the cross beams 16 and connected to the beams and the foundation, for example by means of rivets. When this operation is completed, the situation arises over the whole skeleton, so in figure between planes I-IV, which is drawn on an enlarged scale in figure 3 and figure 2 is drawn between planes I-II. The cladding for the ground floor can be installed at the same time as that for the other floors; if desired, however, it is possible to wait until a later stage with the advantage that the crawl space remains accessible for longer.

Hiermee is de eerste fase van de werkwijze volgens deuitvinding voltooid en is een stabiele draagconstructie verkregenmet uit de platen 22 bestaande werkvloeren die fungeren alsafscherming tegen weersinvloeden en een beschutte en veiligewerkruimte voor de daaronder werkende bouwvakkers geven.This completes the first phase of the method according to the invention and a stable supporting structure has been obtained with work floors consisting of plates 22 that function as weather protection and provide a sheltered and safe working space for the construction workers working underneath.

Vervolgens wordt voor het hele gebouw overgegaan naar fase2 die in figuur 2 is getoond tussen de vlakken II-III en op vergrote schaal is getoond in figuur 4. Deze fase omvattwee bewerkingen: a. het op de vloerplaten storten van een monolitischelichtbetonvloer, daarbij bijvoorbeeld gebruikmakend van eenbetonpomp. De trapeziumvormige vloerplaten fungeren daarbij alswapening voor de gestorte vloer, die in de figuren is aange¬geven met het verwijzingscijfer 24. Zoals figuur 9 toont zal men bij het storten der vloeren de op zich bekendeuitzetvoegen vormen en met isolatiemateriaal opvullen,zoals met 26 is aangegeven in figuur 9. Zoals reeds gezegdkan men er, in verband met het aanbrengen van de ver¬schillende leidingen en kanalen in de door de funderings-balken 4, 6 en de betonlaag 2 bepaalde kruipruimte 5 devoorkeur aan geven de onderste vloer 24a als laatste testorten.Subsequently, for the whole building, phase 2 is shown, which is shown in figure 2 between planes II-III and is shown on an enlarged scale in figure 4. This phase comprises two operations: a. Pouring a monolithic light concrete floor on the floor slabs, using for example of a concrete pump. The trapezoidal floor plates act as reinforcement for the poured floor, which is indicated in the figures with the reference numeral 24. As figure 9 shows, when pouring the floors the expansion joints known per se will be formed and filled with insulating material, as indicated by 26 in figure 9. As already stated, in connection with the provision of the different pipes and channels in the crawl space 5 determined by the foundation beams 4, 6 and the concrete layer 2, it is preferable to test the bottom floor 24a last .

b. het na het uitharden der vloeren 24 opmetselen van de de verschillende woningen scheidende dragende scheidings¬muren die de steunfunctie van de schroefstempels 8 moeten gaanovernemen. Zoals links in figuur 4 aangegeven wordt op defundatiebalk 6b, die ligt naast de fundatiebalk 6a waarop deschroefstempels 8 steunen een muur 26a opgetrokken; evenzowordt naast de stempel 8b en rustend op de vloer 24b een muur26b opgetrokken terwijl naast de schroefstempel 8c en rustendop de muur 24c de muur 26c wordt opgetrokken. Uiteraard wordtvoor het gehele gebouw aldus te werk gegaan. Deze murenworden opgetrokken tot zij de op de schroefstempelsrustende belasting kunnen opnemen en wanneer dit procesis voltooid kunnen de schroefstempels en de dwarsliggers 16worden verwijderd, resulterend in de rechts in figuur 4 aangegevensituatie: er zijn nu nog slechts de nog enkele muren 26cenerzijds en 26a'-26c1 anderzijds en de daartussen, niet aanmuren grenzende, gelegen schroefstempels 8d-8f. Uiteraard geldtdeze situatie niet alleen voor het in figuur 2 tussen devlakken II-III getekende deel van het skelet doch voor hetgehele skelet.b. after the curing of the floors 24, bricklaying of the load-bearing dividing walls separating the various dwellings, which are to take over the support function of the screw dies 8. As shown on the left in Figure 4, on wall beam 6b, which lies next to the foundation beam 6a on which the screw dies 8 support, a wall 26a is erected; likewise a wall 26b is erected next to the punch 8b and resting on the floor 24b, while the wall 26c is pulled up next to the screw punch 8c and resting on the wall 24c. Naturally, the entire building will be operated in this way. These walls are erected until they can take up the load on the screw punch resting load and when this process is completed the screw punches and sleepers 16 can be removed, resulting in the right hand situation in figure 4: there are now only the few walls 26c on the other side and 26a'-26c1 on the other hand and the screw dies 8d-8f located adjacent to them, which do not adjoin the walls. Naturally, this situation applies not only to the part of the skeleton drawn between planes II-III in Figure 2, but to the entire skeleton.

In de beschreven uitvoeringsvorm is ervan uitgegaan dat het woningontwerp voorziet in woningscheidende dubbelebouwmuren. Daarbij wordt er nu overgegaan tot het op de plaatsvan de weggenomen stempels, dus naast elke reeds opgetrokkenbouwmuren onder vorming van een spouw optrekken van een tweedemuur. Tenslotte worden ook de tussengelegen stempels, zoalsde stempels 8d-8f verwijderd en dan ontstaat de situatiedie in figuur 2 is aangegeven tussen de vlakken III-IVen op vergrote schaal is aangegeven in figuur 5. Dedraagconstructie bestaande uit schroefstempels, schoren ensteunbalken is 'geheel verwijderd en er is een zelfdragendeconstructie ontstaan met de op de funderingsbalken 6rustende muren 26 en de vloeren 24.In the described embodiment, it has been assumed that the house design provides for house-separating double-building walls. In doing so, it is now proceeded to erect a second wall at the location of the removed stamps, i.e. next to any building walls already erected, with the formation of a cavity. Finally, the intermediate stamps, such as the stamps 8d-8f, are also removed and then the situation is shown, which is shown in figure 2 between the planes III-IV and is shown on an enlarged scale in figure 5. The supporting construction consisting of screw stamps, braces and support beams has been completely removed and a self-supporting construction has been created with the walls 26 resting on the foundation beams 6 and the floors 24.

Opgemerkt wordt dat het voor het gemakkelijk transportvan afwerk- en bouwmaterialen gewenst is de de woningscheidende muren te voorzien van voorlopige uitsparingenzoals aangegeven met 28a-28c voor de muren 26a-26c in heteindaanzicht volgens figuur 6. Wanneer de woningen geheelzijn afgewerkt worden deze uitsparingen gedicht.It is noted that for the convenient transport of finishing and building materials it is desirable to provide the house-separating walls with provisional recesses as indicated by 28a-28c for the walls 26a-26c in the end view according to figure 6. When these houses are completely finished these recesses are closed.

Voor wat betreft de - niet in de figuur aangegeven -dakconstructie zijn er verschillende mogelijkheden. Wanneermen een plat dak wenst kan men de vloerplaten 22a van debovenste laag met geschikt isolatiemateriaal afwerken endaarna de gebruikelijke dakbedekking aanbrengen. Wanneer mendaarentegen een hellend dak wenst kan men dit, eventueelopgebouwd uit prefab onderdelen op de draagconstructie of hetskelet en de bovenste laag vloerplaten 22a naar wens afwerkenmet bijvoorbeeld een dunne betonvloer of een anderebeloopbare constructie.There are various options with regard to the roof construction - not shown in the figure. If a flat roof is desired, the top layer floor plates 22a can be finished with suitable insulating material and then the usual roofing material applied. If, on the other hand, a sloping roof is desired, this can be finished, optionally built up of prefabricated parts on the supporting construction or the skeleton and the top layer of floor plates 22a, for instance with a thin concrete floor or another walkable construction.

Uiteraard is er binnen het kader van de voorgesteldenieuwe werkwijze voldoende ruimte om het nu verkregen skeletnaar wens af te werken doch binnen de doelstelling deruitvinding een rationele bouwmethode te verschaffen die eengrote vrijheid in uiteindelijke indeling en afwerkingverschaft worden bij voorkeur de volgende maatregelentoegepast:Naturally, within the framework of the proposed new method, there is sufficient space to finish the now obtained skeleton as desired, but within the objective of the invention to provide a rational construction method that provides a great deal of freedom in final layout and finish, the following measures are preferably applied:

Op afstand onder de vloeren 24 worden verlaagde plafonds, zoals aangegeven met 30, aangebracht en de aldusontstane tussenruimten 32 worden gebruikt voor hetonzichtbaar wegwerken van alle noodzakelijke leidingen enkanalen die men laat uitmonden in een tussen de vloeren aan¬gebrachte leidingschacht 34 waarvan de onderste, als aangegevenmet 34a in figuur 6 in verbinding staat met de kruipruimte 5. Doorgebruik te maken van een (op zich bekende) plafondconstructiemet losneembare elementen is elke plek der daarboven gelegenvloer bereikbaar en kan men de doorvoeren door de vloerennaar wens kiezen zodat er een zeer grote flexibiliteitin de woningindeling ontstaat en het niet nodig is deplaats van leidingen en/of montagedozen vooraf tebepalen en in de constructie aan te brengen. Uiteraardleidt dit tot een zeer grote flexibiliteit voor wat betreftde indeling der woningen doch een ander voordeel is datwijziging respectievelijk aanpassing achteraf, zeer gemakkelijkmogelijk is. Dat men pas in een zeer laat afbouwstadium overde definitieve indeling behoeft te besluiten zal door velenals een groot voordeel worden gezien.Suspended ceilings, as indicated by 30, are placed at a distance below the floors 24, and the gaps 32 thus created are used for invisibly concealing all the necessary pipes and channels which are allowed to open into a pipe shaft 34 arranged between the floors, the lower of which, as indicated with 34a in figure 6 communicates with the crawl space 5. By using a (per se known) ceiling construction with detachable elements, every spot of the floor above it is accessible and the passages through the floors can be chosen as desired, so that there is a very great flexibility in the house layout and it is not necessary to predetermine the location of pipes and / or installation boxes and to install them in the construction. Naturally, this leads to a very great flexibility with regard to the layout of the houses, but another advantage is that modification or adaptation afterwards is very easily possible. The fact that one only has to decide on the final classification at a very late completion stage will be seen by many as a great advantage.

Tenslotte worden in het laatste stadium der bouw, dusnadat alle binnenafbouwcomponenten zijn aangebracht of inieder geval op de gewenste werkplek zijn opgeslagen debuitengevelelementen aangebracht. Uiteraard is inmiddels ookhet dak aangebracht en met de noodzakelijke elementenafgewerkt.Finally, at the last stage of construction, after all interior finishing components have been installed or at least at the desired workplace, the exterior wall elements have been installed. The roof has of course also been installed and finished with the necessary elements.

Claims (7)

1. Werkwijze voor het bouwen van één of meerdere aaneen¬gesloten woning(en) of bedrijfsruimten, gekenmerkt door de stappen van het - op een fundering oprichten van een draagconstructiebestaande uit onderling gekoppelde verticale staanders endaardoor ondersteunde, de verdiepingen bepalende horizontaleliggers, - op de horizontale liggers bevestigen van geprofileerdemetaalplaten, - onder gebruikmaking van deze platen als wapeningstorten van monolitische betonvloeren, - beginnend vanaf de fundering optrekken van dragendebouwmuren, - verwijderen van de draagconstructie, - verder afwerken van het aldus gevormde skelet.Method for building one or more contiguous dwelling (s) or commercial spaces, characterized by the steps of - erecting a supporting construction on a foundation consisting of mutually coupled vertical uprights and thereby supporting horizontal beams defining the floors, - on the fastening horizontal beams of profiled metal plates, - using these plates as reinforcement castings of monolithic concrete floors, - starting from the foundation, erecting load-bearing building walls, - removing the supporting structure, - further finishing the skeleton thus formed. 2. Werkwijze volgens conclusie 1, met het kenmerk, dat menbij het optrekken der bouwmuren daarin tijdelijke doorbre¬kingen vrijlaat welke het transport van materiaal daardoormogelijk maken.2. Method as claimed in claim 1, characterized in that temporary openings are released therein when the building walls are erected, which makes it possible to transport material. 3. Werkwijze volgens conclusie 1-2, met het kenmerk, datmen bij het optrekken der draagconstructie een staandersteunt op een funderings- of vloerdeel, aangrenzend daaraaneen draagmuur optrekt tot aan de onderzijde van het daarbovengelegen vloeroppervlak en vervolgens de aan deze muur grenzendestaander en de daardoor ondersteunde horizontale liggerverwijdert.3. Method as claimed in claims 1-2, characterized in that, when the supporting construction is erected, a upright supports on a foundation or floor part, an adjacent supporting wall is raised to the underside of the above floor surface and then the upright adjacent to this wall and the upright thereby supported horizontal beam removes. 4. Werkwijze volgens conclusie 3, met het kenmerk, dat mende staander ondersteunt op een eerste van twee aangrenzendefunderings- of vloerdelen, de draagmuur optrekt op hetaangrenzend deel, en een tweede draagmuur optrekt op het nahet verwijderen der staander vrijgekomen deel.Method according to claim 3, characterized in that the supporting upright supports on a first of two adjacent foundation or floor parts, the supporting wall pulls up on the adjacent part, and a second supporting wall lifts up on the part released after the removal of the upright. 5. Werkwijze volgens conclusie 1-4, met het kenmerk, datmen in althans een aantal staanders schroefstempelsopneemt.A method according to claims 1-4, characterized in that screw stamps are incorporated in at least a number of uprights. 6. Werkwijze volgens conclusie 1-5, met het kenmerk, datmen op afstand onder de verdiepingsvloeren een verlaagdplafond aanbrengt, onder de begane grondvloer een kruipruimtevormt en in elke woning of bedrijfsruimte een de verdiepingenverbindende, met de ruimte tussen vloer en plafond en met dekruipruimte in verbinding staande verticale leidingschachtopneemt, dienst- en sanitaire leidingen in deze ruimte enschachten aanbrengt en in een later afbouwstadium naar wensdoorvoert door in de vloer of het verlaagd plafond gevormdeuitsparingen. \Method according to Claims 1 to 5, characterized in that a false ceiling is arranged below the storey floors, a crawl space is formed under the ground floor and a floor connecting in each house or commercial space, with the space between floor and ceiling and with the crawl space in upright vertical pipe shaft connection, install service and sanitary pipes in this space and shafts and, at a later finishing stage, feed through as desired through recesses formed in the floor or false ceiling. \ 7. Werkwijze volgens conclusie 1-6, met het kenmerk, datmen de buitengevelelementen aanbrengt nadat de voor afbouwvan het gebouw noodzakelijke materialen in het gevormdeskelet zijn gebracht.Method according to claims 1-6, characterized in that the outer facade elements are fitted after the materials necessary for finishing the building have been introduced into the shaped skeleton.
NL9000138A 1990-01-19 1990-01-19 METHOD FOR BUILDING A MULTI-STOREY BUILDING NL189927C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
NL9000138A NL189927C (en) 1990-01-19 1990-01-19 METHOD FOR BUILDING A MULTI-STOREY BUILDING

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL9000138A NL189927C (en) 1990-01-19 1990-01-19 METHOD FOR BUILDING A MULTI-STOREY BUILDING
NL9000138 1990-01-19

Publications (3)

Publication Number Publication Date
NL9000138A true NL9000138A (en) 1991-08-16
NL189927B NL189927B (en) 1993-04-01
NL189927C NL189927C (en) 1993-09-01

Family

ID=19856448

Family Applications (1)

Application Number Title Priority Date Filing Date
NL9000138A NL189927C (en) 1990-01-19 1990-01-19 METHOD FOR BUILDING A MULTI-STOREY BUILDING

Country Status (1)

Country Link
NL (1) NL189927C (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE562773A (en) *
FR968341A (en) * 1947-06-26 1950-11-24 Method of establishing concrete floors especially for high-rise buildings
GB988114A (en) * 1962-06-04 1965-04-07 Siemens Bauunion Gmbh Improvements in the construction of reinforced concrete multi-storey buildings
FR1466046A (en) * 1966-01-27 1967-01-13 Mobile floor, made up of dissociable elements, adjustable both in height and in surface, for the preparation of concrete slabs

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE562773A (en) *
FR968341A (en) * 1947-06-26 1950-11-24 Method of establishing concrete floors especially for high-rise buildings
GB988114A (en) * 1962-06-04 1965-04-07 Siemens Bauunion Gmbh Improvements in the construction of reinforced concrete multi-storey buildings
FR1466046A (en) * 1966-01-27 1967-01-13 Mobile floor, made up of dissociable elements, adjustable both in height and in surface, for the preparation of concrete slabs

Also Published As

Publication number Publication date
NL189927B (en) 1993-04-01
NL189927C (en) 1993-09-01

Similar Documents

Publication Publication Date Title
CA2358747C (en) Ring beam/lintel system
US3678638A (en) Building construction of modular units with settable material therebetween
WO2013019134A1 (en) Building structure of pre-cast monolithic walls and interfloor slabs
US5501055A (en) Method for reinforced concrete construction
US7219474B2 (en) Load bearing building panel
US3364647A (en) Method for erecting tall buildings with balconies
EP0790364A1 (en) Reinforced or prestressed semi-precast concrete structure for building
JP2915897B1 (en) Building construction method
US4294052A (en) Prefabricated load bearing structure
CA2592820A1 (en) Composite floor and composite steel stud wall construction systems
US2379636A (en) Method of making reinforced concrete buildings
JPH05287901A (en) Construction of stairs
GB2543513A (en) Building system
AU2014268276A1 (en) Method of Constructing a Core in Modular Construction
NL9000138A (en) Adjoining dwelling construction method - includes concrete base, support beams and interconnected uprights
JP2002235443A (en) Intermediate story steel frame traveling construction method
CA2625897A1 (en) Reinforced concrete forming system
RU2099482C1 (en) Method of erection of monolithic buildings and structures
AU2003269072B2 (en) In-situ construction of concrete building
US1883192A (en) Concrete floor construction
JP7368671B2 (en) Slab base structure before concrete pouring, reinforced concrete slab structure, construction method for slab base structure before concrete pouring, and construction method for reinforced concrete slab structure
CN110952651B (en) Cantilever building floor slab reinforcing steel structure adopting reinforcing steel truss template and reinforcing steel bar arrangement method
AU2019100434A4 (en) A method of assembling a building
AU648918B2 (en) Building construction method
RU2087650C1 (en) House-building combine

Legal Events

Date Code Title Description
A1C A request for examination has been filed
SNR Assignments of patents or rights arising from examined patent applications

Owner name: PETER CORNELIS SPEE

V1 Lapsed because of non-payment of the annual fee