[go: up one dir, main page]

KR20100030724A - Method for constructing wall block - Google Patents

Method for constructing wall block Download PDF

Info

Publication number
KR20100030724A
KR20100030724A KR1020080089575A KR20080089575A KR20100030724A KR 20100030724 A KR20100030724 A KR 20100030724A KR 1020080089575 A KR1020080089575 A KR 1020080089575A KR 20080089575 A KR20080089575 A KR 20080089575A KR 20100030724 A KR20100030724 A KR 20100030724A
Authority
KR
South Korea
Prior art keywords
group
groups
blocks
backfill
binding rods
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
KR1020080089575A
Other languages
Korean (ko)
Other versions
KR100995097B1 (en
Inventor
연철수
연훈모
Original Assignee
(합)강산건업
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (합)강산건업 filed Critical (합)강산건업
Priority to KR1020080089575A priority Critical patent/KR100995097B1/en
Publication of KR20100030724A publication Critical patent/KR20100030724A/en
Application granted granted Critical
Publication of KR100995097B1 publication Critical patent/KR100995097B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0075Textiles
    • E02D2300/0076Textiles non-woven

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

본 발명은 블록(B) 쌓기의 지반 면적을 최대한 줄이면서 더욱 견고하고 튼튼하게 시공될 수 있도록 1군의 결속봉(P1) 내지 4군의 결속봉(P4)에 1군의 그리드(G1) 내지 4군의 그리드(G4)를 각각 결속시키면서 블록(B) 쌓기의 중간 중간에 펼쳐지도록 하여 전체적으로 1군 내지 4군의 결속봉(P1∼P4)에 결속된 1군 내지 4군의 그리드(G1∼G4)들이 서로 맞물리면서 짜여져 블록(B)의 무너짐을 철저하게 방지할 수 있도록 한 옹벽 블록 시공방법에 관한 것이다.The present invention is to reduce the ground area of the stacking block (B) as much as possible to be more robust and robust construction of one group of binding rods (P1) to four groups of binding rods (P4) from the group of grid (G1) to Group 1 to group 4 of grids G1 to 4 that are bound to the group 1 to group 4 of the binding rods P1 to P4 so as to unfold in the middle of the stacking of blocks B while binding the group 4 of grids G4 to each other. It relates to a retaining wall block construction method in which G4) are interwoven with each other to prevent the collapse of the block (B).

Description

옹벽 블록 시공방법{METHOD FOR CONSTRUCTING WALL BLOCK}Retaining wall block construction method {METHOD FOR CONSTRUCTING WALL BLOCK}

본 발명은 옹벽 블록 시공방법에 관한 것으로, 더욱 상세하게는 블록 쌓기의 지반 면적을 최대한 줄이면서 더욱 견고하고 튼튼하게 시공될 수 있도록 1군의 결속봉 내지 4군의 결속봉에 1군의 그리드 내지 4군의 그리드를 각각 결속시키면서 블록 쌓기의 중간 중간에 펼쳐지도록 하여 전체적으로 1군 내지 4군의 결속봉에 결속된 1군 내지 4군의 그리드가 서로 맞물리면서 짜여져 블록의 무너짐을 철저하게 방지할 수 있는 옹벽 블록 시공방법에 관한 것이다.The present invention relates to a retaining wall block construction method, and more specifically, to a group of binding rods to a group of four to one group of grids so as to be more robust and robust while reducing the ground area of the stacking block as much as possible. The four groups of grids are bound together to unfold in the middle of the block stacking, so that the grids of groups 1 to 4, which are tied to the grouping rods of groups 1 to 4, are interwoven together to prevent the collapse of the blocks. It relates to a retaining wall block construction method.

일반적으로 옹벽(擁壁)은 토압력에 저항하여 토사가 무너지지 않도록 하기 위한 구조물로서 표고 차이를 유지시키기 위하여 경사진 지반 또는 절개지의 한쪽 면에 토사를 억누르는 블록을 쌓아 완성된다.In general, the retaining wall is a structure for preventing soil from collapsing by resisting soil pressure and is completed by stacking blocks for suppressing soil on one side of inclined ground or incision in order to maintain the difference in elevation.

본원 출원인은 2008.04.08.자로 옹벽 블록 시공방법을 선 출원(10-2008-32460)한 바 있고, 그 내용은 다음과 같다.The applicant of the present application filed a retaining wall block construction method (10-2008-32460) as of 2008.04.08. The contents are as follows.

도 1a는 선 출원에 따른 옹벽 블록 시공방법에 적용된 블록을 나타내는 사시 도이고, 도 1b는 선 출원에 따른 옹벽 블록을 나타내는 사시도이다.Figure 1a is a perspective view showing a block applied to the retaining wall block construction method according to the line application, Figure 1b is a perspective view showing a retaining wall block according to the line application.

선 출원에 따른 옹벽 블록 시공방법에 적용된 블록(B)은 도 1a에 도시된 바와 같이 전광후협(前廣後狹)으로 이루어질 수 있고, 중앙에 중공부(B1) 및 상부에 걸림돌기(B2)를 각각 지닌 구조로 이루어지며, 이때 도 1b에 도시된 바와 같이 중공부(B1)와 걸림돌기(B2)의 맞물림으로 상호 견고한 조립을 이룰 수 있고, 나아가 이렇게 블록(B)을 쌓으면서 중공부(1)에 쇄석 또는 흙을 포설하여 상호간의 지지력을 증진시킬 수 있으며, 나아가 들여쌓기시 외부로 드러난 중공부(B1)에 조경용 화초를 식생할 수 있음은 물론이다.Block (B) applied to the retaining wall block construction method according to the pre-application may be made of an all-optical narrow view (front) as shown in Figure 1a, the hollow portion (B1) in the center and the locking projection (B2) in the upper portion It is made of a structure having each, and at this time, as shown in Figure 1b by the engagement of the hollow portion (B1) and the engaging projection (B2) can be achieved a solid assembly with each other, furthermore by stacking the block (B) in this way 1) by laying crushed stone or soil can enhance mutual support, and furthermore, it is of course possible to plant a landscape flower on the hollow portion (B1) exposed to the outside when stacked.

도 2a 내지 도 2f는 선 출원에 따른 옹벽 블록 시공방법을 나타내는 공정도이다.2a to 2f is a process chart showing a retaining wall block construction method according to the line application.

선 출원에 따른 옹벽 블록 시공방법은 도 2a 내지 도 2f에 도시된 바와 같이 먼저 경사진 지반(60)의 앞쪽 지면을 터파기하여 잡석 기초(70)를 다지고(a), 이 잡석 기초(70) 위에 1군의 블록(11)을 적층시키면서 그 뒤쪽에 1군의 배수용 잡석(12; 우수의 배수를 용이하게 함) 및 보강토(13)를 차례로 쌓는다(b).Retaining wall block construction method according to the preliminary application is to dig the front surface of the inclined ground 60 as shown in Figs. 2a to 2f to compact the rubble foundation 70 (a), on the rubble foundation 70 While stacking a group of blocks 11, one group of rubble for drainage 12 (which facilitates drainage of rainwater) and reinforcement soil 13 are sequentially stacked (b).

그리고, 1군의 블록(11) 상위층의 배면으로부터 경사진 지반(60)을 향하여 제 1 콘크리트층(14)을 타설 및 양생시키고(c), 다시 1군의 블록(11)의 상위층 위에 2군의 블록(21)을 적층시키면서 그 뒤쪽에 2군의 배수용 잡석(22; 우수의 배수를 용이하게 함) 및 보강토(23)를 차례로 쌓는다(d).Then, the first concrete layer 14 is poured and cured toward the ground 60 inclined from the rear of the upper layer of the block 11, and (c) again, the second group is placed on the upper layer of the block 11 of the group 1 While stacking the blocks 21, two groups of rubble for drainage 22 (to facilitate drainage of rainwater) and reinforcement soil 23 are sequentially stacked (d).

이어서, 2군의 블록(21) 상위층의 배면으로부터 경사진 지반(60)을 향하여 제 2 콘크리트층(24)을 타설 및 양생시키고(e), 2군의 블록(21)의 상위층 위에 3군 의 블록(31)을 적층시키면서 그 뒤쪽에 3군의 배수용 잡석(32; 우수의 배수를 용이하게 함) 및 보강토(33)를 차례로 쌓는다(f).Subsequently, the second concrete layer 24 is poured and cured toward the inclined ground 60 from the back of the upper layer of the two groups of blocks 21 (e), and the three groups of blocks are placed on the upper layers of the two groups of blocks 21. While stacking the blocks 31, three groups of drainage rubble 32 (which facilitates drainage of rainwater) and reinforcement soil 33 are sequentially stacked (f).

이때, 제 1 콘크리트층(14) 및 제 2 콘크리트층(24)은 경사진 지반(60)으로부터 전방으로 향할수록 미세하게 경사지게 시공되도록 하여 빗물이 1군 내지 3군의 보강토(13, 23, 33) 및 경사진 지반(60)을 경유하여 스며들 경우 제 1 콘크리트층(14) 및 제 2 콘크리트층(24)에 의해 전방으로 자연스럽게 흐를 수 있도록 하여 1군 내지 3군의 배수용 잡석(12, 22, 32)을 경유하여 지하로 흘러갈 수 있도록 함으로써 우수에 의한 지반약화 내지는 지반의 무너짐을 미연에 방지할 수 있도록 한다.At this time, the first concrete layer 14 and the second concrete layer 24 are constructed to be inclined finely toward the front from the inclined ground (60) so that the rainwater reinforcement soil (13, 23, 33 of group 1 to 3) 1) and 3 groups of drainage rubble (12,) so as to flow naturally forward by the first concrete layer (14) and the second concrete layer (24) when seeping through the inclined ground (60). 22, 32) to be able to flow underground to prevent ground weakness or collapse of the ground due to rainwater.

그리고, 1군 내지 3군의 배수용 잡석(12, 22, 32)에 묻혀진 제 1 콘크리트층(14) 및 제 2 콘크리트층(24)에 상하방향으로 배수공(40)을 관통 형성시켜 빗물이 스며들 경우 자연스럽게 배수공(40)을 경유하여 하측방향으로 흘러갈 수 있도록 한다.In addition, the first concrete layer 14 and the second concrete layer 24 buried in the rubble for drainage (12, 22, 32) of the group 1 to 3 through the drain hole 40 in the vertical direction through the rain water soaked In the case of natural flow through the drain hole 40 to allow to flow downward.

나아가, 선 출원에 따른 옹벽 블록 시공방법은 1군 내지 3군의 블록(11, 21, 31)과, 1군 내지 3군의 배수용 잡석(12, 22, 32) 및 보강토(13, 23, 33) 사이에 합성수지 메쉬[MESH(50); 예를 들면 지오그리드]를 교번적으로 수평지게 펼쳐 상호간의 견인력 및 지지력을 높일 수 있도록 하며, 나아가 2군 및 3군의 블록(21, 31)을 경사진 지반(60)의 기울기에 맞추어 선택적으로 들여쌓기를 하여 외부로 노출되는 중공(B1)에 화초를 식생할 수 있도록 한다.Furthermore, the retaining wall block construction method according to the pre-application is a block (11, 21, 31) of groups 1 to 3, rubble (12, 22, 32) and reinforcement soil (13, 23, 33) a synthetic resin mesh (MESH 50); For example, the geogrid] alternately horizontally spread to increase mutual traction and support, and furthermore, the second and third groups of blocks 21 and 31 are selectively placed in accordance with the inclination of the inclined ground 60. By stacking the flowers to the hollow (B1) exposed to the outside to allow vegetation.

도 3은 선 출원에 따른 옹벽 블록 시공방법을 설명하기 위한 부분 단면을 포 함한 측면도이다.Figure 3 is a side view including a partial cross section for explaining the retaining wall block construction method according to the line application.

선 출원은 도 3에 도시된 바와 같이 경사진 지반(60)의 기울기에 맞추어 들여쌓기로 이루어진 블록(B)의 중공부(B1)에 흙(H)을 포설하여 화초의 식생을 가능케 하고, 이렇게 흙(H)이 포설된 블록(B)과 접하는 하위 블록(B), 제 1 콘크리트층(14), 2군의 배수용 잡석(22), 제 2 콘크리트층(24), 3군의 배수용 잡석(32) 사이에 부직포(V)를 개재하여 흙(H)의 누출을 방지하며, 다른 한편으로 흙(H)이 포설된 블록(B) 이외의 블록(B)의 중공부(B1)에 쇄석(S)을 포설하여 상호간의 견고함을 증진시킬 수 있도록 한다.Preliminary application is to install the soil (H) in the hollow portion (B1) of the block (B) consisting of the stacking in accordance with the inclination of the inclined ground 60 as shown in FIG. Lower block (B) in contact with the block (B) on which soil (H) is placed, first concrete layer (14), rubble for drainage of two groups (22), second concrete layer (24), for drainage of three groups The nonwoven fabric V is interposed between the rubble 32 to prevent leakage of the soil H. On the other hand, the hollow portion B1 of the block B other than the block B in which the soil H is placed is placed. Crushing stones (S) can be installed to promote mutual strength.

그리고, 도 1a 및 도 1b에 도시된 바와 같이 블록(B)의 중공부(B1) 전방 내측으로부터 후방을 향하여 돌기부(B3)를 돌출시켜 블록(B)의 수직방향 적층시 잡초의 자생을 미연에 방지토록 하는 것이 바람직하다.As shown in FIGS. 1A and 1B, the protrusion B3 protrudes from the inner side of the hollow portion B1 toward the rear side of the block B to prevent rearing of the weeds in the vertical stacking of the block B. It is desirable to prevent it.

즉, 도 1a 및 도 1b에 도시된 바와 같이 블록(B)을 들여쌓기를 하지 않고 수직방향으로 쌓을 때 하위의 블록(B) 상측의 중심으로부터 양측방향으로 놓여지는 상위의 블록(B)들 사이로 돌기부(B3)가 존재토록 하여 잡초의 자생을 미연에 방지할 수 있도록 하는 것이다.That is, as shown in FIGS. 1A and 1B, when the blocks B are stacked in the vertical direction without stacking, the blocks B between the upper blocks B placed in both directions from the center of the upper side of the lower blocks B. Projection portion (B3) is to be present so that the native growth of weeds can be prevented in advance.

그런데, 선 출원에 따른 옹벽 블록 시공방법은 경사진 지반(60)의 앞쪽 지면의 면적이 넓을 경우 1군의 블록 내지 3군의 블록(11, 21, 31)을 비롯한 1군의 배수용 잡석 내지 3군의 배수용 잡석(12, 22, 32) 그리고 1군의 보강토 내지 3군의 보강토(13, 23, 33)를 여유롭게 적층 및 쌓을 수 있어 바람직하지만 경사진 지반(60)의 앞쪽 지면의 면적이 좁을 경우 그 시공이 극히 어렵고, 설령 시공을 완성 하더라도 블록(B)이 쉽게 무너져 버리는 문제점을 안고 있다.By the way, the retaining wall block construction method according to the prior application is a group of drainage rubble, including one group of blocks to three groups of blocks 11, 21, and 31 when the area of the front surface of the inclined ground 60 is large. Three groups of drainage rubble (12, 22, 32) and 1 group of reinforcement soils to 3 groups of reinforcement soils (13, 23, 33) can be easily stacked and stacked, but the area of the front surface of the inclined ground (60) If it is narrow, the construction is extremely difficult, even if the construction is complete, the block (B) has a problem that easily collapses.

본 발명의 목적은 블록 쌓기의 지반 면적을 최대한 줄이면서 더욱 견고하고 튼튼하게 시공될 수 있도록 한 옹벽 블록 시공방법을 제공함에 있다.SUMMARY OF THE INVENTION An object of the present invention is to provide a retaining wall block construction method which allows a more solid and robust construction while reducing the ground area of a block stack as much as possible.

상기 목적을 달성하기 위한 본 발명에 따른 옹벽 블록 시공방법은,Retaining wall block construction method according to the present invention for achieving the above object,

사면의 앞쪽 지면을 터파기하여 제 1 기초콘크리트층을 타설 및 양생시키는 스텝과,Digging the ground in front of the slope to pour and cure the first foundation concrete layer,

상기 사면을 따라 1군의 결속봉을 등간격으로 세우는 스텝과,A step of setting up a group of binding rods at equal intervals along the slope;

상기 제 1 기초콘크리트층 위에 1군의 블록을 적층시키면서 그 뒤쪽에 1군의 바닥 골재 및 1군의 뒷채움 골재를 전후 차례로 쌓는 스텝과,Stacking one group of floor aggregates and one group of backfill aggregates in front and back while stacking one group of blocks on the first basic concrete layer;

상기 1군의 결속봉에 결속시키면서 상기 1군의 블록, 1군의 바닥 골재 및 1군의 뒷채움 골재 위에 1군의 그리드를 펼치는 스텝과,Step of spreading the grid of the group 1 on the block of the group 1, the floor aggregate of the group 1 and the backfill aggregate of the group 1 while binding to the binding rod of the group 1,

상기 1군의 결속봉에 2군의 결속봉을 각각 소켓 결합시켜 연장시키는 스텝과,And coupling the two groups of binding rods to the first group of binding rods to extend the sockets;

상기 1군의 그리드 위에 2군의 블록, 2군의 뒷채움 토사 및 2군의 뒷채움 골재를 전후 차례로 쌓으면서 그 중간에 2군의 그리드를 상기 2군의 결속봉에 결속시 켜 펼치는 스텝과,Stacking two groups of blocks, two groups of backfilled soil, and two groups of backfilled aggregates in front and back on the grid of group 1 and binding the two groups of grids to the binding rods of the group 2 in the middle;

상기 2군의 블록 및 2군의 뒷채움 토사 위에 제 2 보강콘크리트층을 타설 및 양생시키는 스텝과,Placing and curing the second reinforcement concrete layer on the blocks of group 2 and the backfill soil of group 2,

상기 2군의 결속봉에 3군의 결속봉을 각각 소켓 결합시켜 연장시키는 스텝과,And coupling the three groups of rods to the two groups of rods to extend the sockets;

상기 제 2 보강콘크리트층 및 2군의 뒷채움 골재 위에 3군의 블록, 3군의 뒷채움 토사 및 3군의 뒷채움 골재를 전후 차례로 쌓으면서 그 중간에 3군의 그리드를 상기 3군의 결속봉에 결속시켜 펼치는 스텝과,Stacking three groups of blocks, three groups of backfilled soil, and three groups of backfilled aggregates in front and back on the second reinforcement concrete layer and the two groups of backfilled aggregates, and binding three groups of grids to the three groups of tie rods in the middle. And spread out the steps,

상기 3군의 블록 및 3군의 뒷채움 토사 위에 제 3 보강콘크리트층을 타설 및 양생시키는 스텝과,Placing and curing the third reinforcement concrete layer on the block of the group 3 and the backfill soil of the group 3,

상기 3군의 결속봉에 4군의 결속봉을 각각 소켓 결합시켜 연장시키는 스텝과,And coupling the four groups of binding rods to the three groups of binding rods to extend the sockets;

상기 제 3 보강콘크리트층 및 3군의 뒷채움 골재 위에 4군의 블록, 4군의 뒷채움 토사 및 4군의 뒷채움 골재를 전후 차례로 쌓으면서 그 중간에 4군의 그리드를 상기 4군의 결속봉에 결속시켜 펼치는 스텝(S12)과,4 groups of blocks, 4 groups of backfill soils, and 4 groups of backfill aggregates are stacked in front and back on the third reinforcement concrete layer and 3 groups of backfill aggregates, and the 4 groups of grids are tied to the 4 bars of the binding rod in the middle. Step (S12) to spread out,

상기 4군의 블록, 4군의 뒷채움 토사 및 4군의 뒷채움 골재 위에 제 4 보강콘크리트층을 타설 및 양생시키는 스텝(S13)을 포함하여 이루어지는 것을 그 기술적 방법상의 기본 특징으로 한다.And a step (S13) of placing and curing the fourth reinforcement concrete layer on the blocks of the 4 groups, the backfill soils of the 4 groups, and the backfill aggregates of the 4 groups.

본 발명은 사면의 앞쪽 지면의 면적이 극히 좁을 경우 블록 쌓기의 지반 면적을 최대한 줄이면서 더욱 견고하고 튼튼하게 시공될 수 있도록 1군의 결속봉 내지 4군의 결속봉에 1군의 그리드 내지 4군의 그리드를 결속시키면서 블록 쌓기의 중간 중간에 펼쳐지도록 하여 전체적으로 1군 내지 4군의 결속봉에 결속된 1군 내지 4군의 그리드가 서로 맞물리면서 짜여져 블록의 무너짐을 철저하게 방지할 수 있는 탁월한 효과가 있다.In the present invention, when the area of the front surface of the slope is extremely narrow, the group of the first to four groups of four to four groups of binding rods to the four groups of binding rods to be more robust and robust construction while reducing the ground area of block stacking as much as possible The grids of 1 to 4 groups, which are tied to the 1 to 4 groups of binding rods, are woven together to form a grid, while the grids of the 1 to 4 groups bind to each other to form a grid. have.

본 발명에 따른 옹벽 블록 시공방법의 바람직한 실시예를 도면을 참조하여 설명하면 다음과 같다.Referring to the drawings a preferred embodiment of the retaining wall block construction method according to the invention as follows.

도 4a 및 도 4b는 본 발명에 따른 옹벽 블록 시공방법에 적용된 블록을 상측 및 하측에서 각각 바라본 사시도이다.Figures 4a and 4b is a perspective view of the block applied to the retaining wall block construction method according to the present invention from the top and bottom, respectively.

본 발명에 따른 옹벽 블록 시공방법에 적용된 블록(B)은 도 4a 및 도 4b에 도시된 바와 같이 전광후협(前廣後狹)으로 이루어질 수 있고, 중앙에 제 1 홀(12)을 지닌 제 1 중공홈(11) 및 제 2 홀(14)을 지닌 제 2 중공홈(13)으로 구획됨과 동시에 상부에 걸림돌기(15)를 구비할 수 있다.Block B applied to the retaining wall block construction method according to the present invention may be made of an all-optical narrow view as shown in Figs. 4a and 4b, the first having a first hole 12 in the center The second hollow groove 13 having the hollow groove 11 and the second hole 14 may be partitioned and at the same time, the locking protrusion 15 may be provided.

이때, 블록(B)의 제 1 중공홈(11)에 속채움 토사(60)가 채워지고, 블록(B)의 제 2 중공홈(13)에 속채움 골재(70)가 채워진다.At this time, the filling soil 60 is filled in the first hollow groove 11 of the block (B), the filling aggregate 70 is filled in the second hollow groove 13 of the block (B).

블록(B)의 들여쌓기시 제 1 중공홈(11)에 채워진 속채움 토사(60)에는 화초를 식생할 수 있고, 이때 제 1 홀(12)은 배수구멍의 역할을 하게 되며, 제 2 중공 홈(13)에는 속채움 골재(70)가 채워져 하중에 의한 견고한 틀을 유지토록 하고, 이때 제 2 홀(14) 역시 배수구멍의 역할을 하게 된다.When stacking the block (B) can be planted in the stuffed soil 60 filled in the first hollow groove 11, the first hole 12 serves as a drainage hole, the second hollow The groove 13 is filled with the filling aggregate 70 to maintain a rigid frame by the load, the second hole 14 also serves as a drain hole.

도 5a 내지 도 5m은 본 발명에 따른 옹벽 블록 시공방법을 나타내는 공정도이다.5a to 5m is a process chart showing a retaining wall block construction method according to the present invention.

본 발명에 따른 옹벽 블록 시공방법은 도 5a 내지 도 5m에 도시된 바와 같이, 사면(斜面; S)의 앞쪽 지면을 터파기하여 제 1 기초콘크리트층(C1)을 타설 및 양생시키고(S1), 사면(S)을 따라 1군의 결속봉(P1)을 등간격으로 세운 후(S2), 제 1 기초콘크리트층(C1) 위에 1군의 블록(B1)을 적층시키면서 그 뒤쪽에 1군의 바닥 골재(T1) 및 1군의 뒷채움 골재(K1)를 전후 차례로 쌓는다[S3; 이때 1군의 블록(B1) 대신 골재를 다질 수도 있음은 물론이다].In the retaining wall block construction method according to the present invention, as shown in FIGS. 5A to 5M, the first ground concrete layer C1 is poured and cured by digging the front surface of the slope S (S1), and the slope After setting the group of binding rods P1 at equal intervals along (S) (S2), the first group of concrete aggregates (B1) on the first foundation concrete layer (C1) while laminating the group of floor aggregates behind it (T1) and the backfill aggregate (K1) of the first group is stacked one after another [S3; At this time, instead of the block (B1) of the group 1 may be aggregate.

그리고, 1군의 결속봉(P1)에 결속시키면서 1군의 블록(B1), 1군의 바닥 골재(T1) 및 1군의 뒷채움 골재(K1) 위에 1군의 그리드(G1)를 펼치고(S4), 1군의 결속봉(P1)에 2군의 결속봉(P2)을 각각 소켓(20) 결합시켜 연장시킨 후(S5), 다시 1군의 그리드(G1) 위에 2군의 블록(B2), 2군의 뒷채움 토사(T2) 및 2군의 뒷채움 골재(K2)를 전후 차례로 쌓으면서 그 중간에 2군의 그리드(G2)를 2군의 결속봉(P2)에 결속시켜 펼친다(S6).Then, while binding to the first group of binding rods P1, the first group of grids (B1), the first group of aggregate aggregates (T1) and the first group of back aggregate aggregates (K1) of the first group of grid (G1) to spread (S4) ), The two groups of binding rods (P2) to the first group of binding rods (P1) to each of the sockets 20 to extend (S5), and then again the second group of blocks (B2) on the first group of grids (G1) While stacking the backfill soils (T2) of the two groups and backfill aggregates (K2) of the two groups in front and rear in turn, the two groups of grids (G2) are bound to the two groups of binding rods (P2) in the middle and unfolded (S6).

이어서, 2군의 블록(B2) 및 2군의 뒷채움 토사(T2) 위에 제 2 보강콘크리트층(C2)을 타설 및 양생시키고(S7), 2군의 결속봉(P2)에 3군의 결속봉(P3)을 각각 소켓(20) 결합시켜 연장시킨 후(S8), 제 2 보강콘크리트층(C2) 및 2군의 뒷채움 골재(K2) 위에 3군의 블록(B3), 3군의 뒷채움 토사(T3) 및 3군의 뒷채움 골재(K3)를 전후 차례로 쌓으면서 그 중간에 3군의 그리드(G3)를 3군의 결속봉(P3)에 결속시켜 펼친다(S9).Subsequently, the second reinforcement concrete layer C2 is poured and cured on the block B2 of the group 2 and the backfilling soil T2 of the group 2 (S7), and the group of binding rods of the group 2 to the binding rod P2 of the group 2 After coupling (P3) and extending the sockets 20, respectively (S8), on the second reinforcement concrete layer (C2) and the second group of backfill aggregates K2, three groups of blocks (B3), three groups of backfill soil ( T3) and the backfill aggregates K3 of group 3 are stacked one after another in the middle, and the grid of group 3 (G3) is bound to the group 3 binding rods (P3) in the middle (S9).

나아가, 3군의 블록(B3) 및 3군의 뒷채움 토사(T3) 위에 제 3 보강콘크리트층(C3)을 타설 및 양생시키고(S11), 3군의 결속봉(P3)에 4군의 결속봉(P4)을 각각 소켓(20) 결합시켜 연장시킨 후(S10), 제 3 보강콘크리트층(C3) 및 3군의 뒷채움 골재(K3) 위에 4군의 블록(B4), 4군의 뒷채움 토사(T4) 및 4군의 뒷채움 골재(K4)를 전후 차례로 쌓으면서 그 중간에 4군의 그리드(G4)를 4군의 결속봉(P4)에 결속시켜 펼친다(S12).Furthermore, the third reinforcement concrete layer C3 is poured and cured on the block B3 of the group 3 and the backfilled soil T3 of the group 3 (S11), and the group of 4 binding rods to the group 3 of the binding rods P3. After coupling (P4) and extending the socket 20, respectively (S10), on the third reinforcement concrete layer (C3) and the third group of backfill aggregates (K3) of the four groups of blocks (B4), four groups of backfill soil ( T4) and four groups of backfill aggregates K4 are stacked one after another in the middle, and the grid G4 of the four groups is bound to the four groups of binding rods P4 in the middle and unfolded (S12).

다음으로, 4군의 블록(B4), 4군의 뒷채움 토사(T4) 및 4군의 뒷채움 골재(K4) 위에 제 4 보강콘크리트층(C4)을 타설 및 양생시켜(S13) 옹벽 블록 시공을 완성한다.Next, the fourth reinforcement concrete layer (C4) is poured and cured on the block B4 of the four groups, the backfill soil of the four groups (T4) and the backfill aggregates of the four groups (S13) to complete the retaining wall block construction. do.

여기서, 본 발명의 가장 큰 핵심 기술은 사면(S)의 앞쪽 지면의 면적이 극히 좁을 경우 블록(B) 쌓기의 지반 면적을 최대한 줄이면서 더욱 견고하고 튼튼하게 시공될 수 있도록 1군의 결속봉(P1) 내지 4군의 결속봉(P4)에 1군의 그리드(G1) 내지 4군의 그리드(G4)를 각각 결속시키면서 블록(B) 쌓기의 중간 중간에 펼쳐지도록 하여 전체적으로 1군 내지 4군의 결속봉(P1∼P4)에 결속된 1군 내지 4군의 그리드(G1∼G4)가 서로 맞물리면서 짜여져 블록(B)의 무너짐을 철저하게 방지할 수 있도록 하는 것이며, 사면(S)의 높이에 따라 블록(B) 쌓기 등의 층수는 자유롭게 가감될 수 있음은 당업자의 이해의 범주로 한다.Here, the greatest core technology of the present invention is a group of binding rods so that when the area of the front surface of the slope (S) is extremely narrow, the ground area of the stacking block (B) can be reduced to the maximum, and the construction can be made more robust and robust. P1) to 4 groups of binding rods (P4) to each group of grids (G1) to 4 groups of grids (G4) to bind to each other in the middle of the stacking of the block (B) so as to expand the overall group 1-4 The grids G1 to G4 of groups 1 to 4, which are bound to the binding rods P1 to P4, are interwoven together so as to thoroughly prevent the collapse of the block B, and according to the height of the slope S It is within the scope of understanding of those skilled in the art that the number of floors such as stacking of blocks (B) can be freely added or subtracted.

한편, 사면(S)을 따라 부직포(30)를 씌워 시공 중 사면(S)으로부터 토사가 무너져 공사를 방해하는 현상을 미연에 방지하고, 나아가 시공 완료 후 우수의 침투로 인한 사면(S)의 미세한 토사가 1군의 뒷채움 골재(K1) 내지 4군의 뒷채움 골재(K4) 속으로 유입되는 현상을 방지하여 1군 내지 4군의 뒷채움 골재(K1∼K4)에 의한 우수의 통로를 보장할 수 있도록 한다.On the other hand, by covering the non-woven fabric 30 along the slope (S) to prevent the soil from collapsing from the slope (S) during construction in advance to prevent the phenomenon, further after the completion of construction fine slope of the slope (S) due to the penetration of rainwater To prevent the soil from entering into the backfill aggregates (K1) of the first group (K1) to the backfill aggregates (K4) of the fourth group to ensure the passage of rainwater by the backfill aggregates (K1 to K4) of groups 1 to 4 do.

또한, 1군의 결속봉(P1) 내지는 4군의 결속봉(P4)을 잡아주면서 부직포(30)를 경유하여 사면(S)에 소일 네일(40; Soil Nail)을 박아 1군의 그리드(G1) 내지는 4군의 그리드(G4)와 더불어 1군 내지 4군의 결속봉(P1∼P4)의 전체적인 지지력과 결속력을 함께 증진시킬 수 있도록 한다.Further, while holding the binding rods P1 of the first group or the binding rods P4 of the fourth group, the Soil Nail 40 is put on the slope S via the nonwoven fabric 30, and the grid G1 of the first group is applied. ) And four groups of grids (G4) to improve the overall support and binding force of the binding rods (P1 to P4) of groups 1 to 4 together.

그리고, 제 1 기초코트리트층 위의 1군의 바닥 골재(T1) 속에 횡방향으로 유공관[50; 다수의 구멍들이 타공된 파이프]을 세팅시켜 1군의 뒷채움 골재(K1) 내지 4군의 뒷채움 골재(K4)로부터 유입되는 우수를 신속히 받아들이면서 횡방향으로 내보내 별도의 배수로에 배출시킬 수 있도록 하여 블록(B)의 무너짐을 미연에 방지토록 한다.And, the perforated pipe in the transverse direction in the first group of aggregate aggregate (T1) on the first foundation coat layer [50; Multiple holes are perforated pipes] to set the block so that it can be discharged to a separate drainage channel to quickly receive the rainwater flowing from the backfill aggregates (K1) of the first group to the backfill aggregates (K4) of the 4th group to be sent laterally Prevent collapse of (B) beforehand.

나아가, 1군의 블록(B1) 내지 4군의 블록(B4)은 사면(S)의 경사각도에 맞추어 들여쌓기 또는 수직쌓기로 이루어질 수 있으며 낱개의 블록(B)들이 군을 이루어 완성되고, 더욱 구체적으로 블록(B)은 전광후협으로 이루어지며 중앙에 제 1 홀(12)을 지닌 제 1 중공홈(11) 및 제 2 홀(14)을 지닌 제 2 중공홈(13)으로 구획됨과 동시에 상부에 걸림돌기(15)를 구비하여 서로 축조될 수 있도록 설계된다.Further, the group of blocks (B1) to the group of blocks (B4) of the group 4 can be made by stacking or vertical stacking in accordance with the inclination angle of the slope (S), the individual blocks (B) is completed by forming a group, more Specifically, the block B is formed of an all-optical narrow view and is divided into a first hollow groove 11 having a first hole 12 in the center and a second hollow groove 13 having a second hole 14 and at the same time. It is designed to be constructed with each other by having a locking projection (15) to.

한편, 1군의 블록(B1) 앞에 노출된 제 1 기초콘크리트층(C1) 위에 앞채움 토사(80)를 주변 지형에 맞추어 쌓아 최종 마무리토록 한다.Meanwhile, the front filling soil 80 is stacked on the first foundation concrete layer C1 exposed in front of the group B1 in accordance with the surrounding topography to be finally finished.

그리고, 본 발명은 사면(S)의 기울기에 맞추어 들여쌓기로 이루어진 블록(B)의 제 1 중공홈(11)에 속채움 토사(60)를 채워 화초의 식생을 가능케 하고, 제 2 중공홈(13)에는 속채움 골재(70)를 채워 하중에 의한 중력으로 더욱 견고한 축조를 가능케 할 수 있다.In addition, the present invention fills the filling soil 60 in the first hollow groove 11 of the block (B) made of the stack according to the slope of the slope (S) to enable the vegetation of the flower, the second hollow groove ( 13) filling the filling aggregate 70 may enable more robust construction by gravity due to the load.

본 발명은 사면의 무너짐을 방지하면서 외관의 미려함을 함께 증진시킬 수 있도록 한 옹벽 블록 시공 분야에 활용된다.The present invention is utilized in the field of the retaining wall block construction to improve the beauty of the appearance while preventing the collapse of the slope.

도 1a는 선 출원된 옹벽 블록 시공방법에 적용된 블록을 나타내는 사시도.Figure 1a is a perspective view showing a block applied to the retaining wall block construction method previously applied.

도 1b는 선 출원된 옹벽 블록을 나타내는 사시도.Figure 1b is a perspective view showing a pre-retained retaining wall block.

도 2a 내지 도 2f는 선 출원된 옹벽 블록 시공방법을 나타내는 공정도.Figure 2a to 2f is a process chart showing a pre-applying retaining wall block construction method.

도 3은 선 출원된 옹벽 블록 시공방법을 설명하기 위한 부분 단면을 포함한 측면도.Figure 3 is a side view including a partial cross-sectional view for explaining the pre-applying retaining wall block construction method.

도 4a 및 도 4b는 본 발명에 따른 옹벽 블록 시공방법에 적용된 블록을 상측 및 하측에서 각각 바라본 사시도.Figure 4a and Figure 4b is a perspective view of the block applied to the retaining wall block construction method according to the present invention from the top and bottom, respectively.

도 5a 내지 도 5m은 본 발명에 따른 옹벽 블록 시공방법을 나타내는 공정도.5a to 5m is a process chart showing a retaining wall block construction method according to the present invention.

* 도면의 주요 부분에 대한 부호의 설명 *       Explanation of symbols on the main parts of the drawings

B : 블록 11 : 제 1 중공홈B: block 11: first hollow groove

12 : 제 1 홀 13 : 제 2 중공홈12: first hole 13: second hollow groove

14 : 제 2 홀 15 : 걸림돌기14: the second hole 15: the protrusion

16 : 돌기부 20 : 소켓16 protrusion 20 socket

30 : 부직포 40 : 소일 네일30: nonwoven fabric 40: soil nail

50 : 유공관 60 : 속채움 토사50: Merit Hall 60: Stuffed Tosa

70 : 속채움 골재 80 : 앞채움 토사70: stuffing aggregate 80: front filling soil

S : 사면 C1 : 제 1 기초콘크리트층S: slope C1: first basic concrete layer

C2 : 제 2 보강콘크리트층 C3 : 제 3 보강콘크리트층C2: Second Reinforced Concrete Layer C3: Third Reinforced Concrete Layer

C4 : 제 4 보강콘크리트층 P1 : 1군의 결속봉C4: 4th reinforced concrete layer P1: Bind rod of 1 group

P2 : 2군의 결속봉 P3 : 3군의 결속봉P2: Bins of Group 2 P3: Bins of Group 3

P4 : 4군의 결속봉 B1 : 1군의 블록P4: Bonding Rod of Group 4 B1: Block of Group 1

B2 : 2군의 블록 B3 : 3군의 블록B2: Group 2 block B3: Group 3 block

B4 : 4군의 블록 T1 : 1군의 바닥 골재B4: Block 4 in group T1: Floor aggregate in group 1

T2 : 2군의 뒷채움 토사 T3 : 3군의 뒷채움 토사T2: backfill soil of group 2 T3: backfill soil of group 3

T4 : 4군의 뒷채움 토사 K1 : 1군의 뒷채움 골재T4: backfill of 4 groups Tosa K1: backfill of 1 group

K2 : 2군의 뒷채움 골재 K3 : 3군의 뒷채움 골재K2: Backfill aggregates from Group 2 K3: Backfill aggregates from Group 3

K4 : 4군의 뒷채움 골재 G1 : 1군의 그리드K4: Backfill aggregate of 4 groups G1: Grid of 1 group

G2 : 2군의 그리드 G3 : 3군의 그리드G2: Grid of Group 2 G3: Grid of Group 3

G4 : 4군의 그리드G4: grid of 4 groups

Claims (8)

사면(S)의 앞쪽 지면을 터파기하여 제 1 기초콘크리트층(C1)을 타설 및 양생시키는 스텝(S1)과,(S1) for pouring and curing the first foundation concrete layer (C1) by breaking the ground in front of the slope (S); 상기 사면(S)을 따라 1군의 결속봉(P1)을 등간격으로 세우는 스텝(S2)과,Step (S2) for setting the group of binding rods (P1) at equal intervals along the slope (S), 상기 제 1 기초콘크리트층(C1) 위에 1군의 블록(B1)을 적층시키면서 그 뒤쪽에 1군의 바닥 골재(T1) 및 1군의 뒷채움 골재(K1)를 전후 차례로 쌓는 스텝(S3)과,Step (S3) of stacking the first group of blocks (B1) on the first base concrete layer (C1) while stacking one group of bottom aggregate (T1) and one group of backfill aggregate (K1) in front and rear sequentially, 상기 1군의 결속봉(P1)에 결속시키면서 상기 1군의 블록(B1), 1군의 바닥 골재(T1) 및 1군의 뒷채움 골재(K1) 위에 1군의 그리드(G1)를 펼치는 스텝(S4)과,Step of unfolding the first group of grids G1 on the first group of blocks B1, the first group of bottom aggregates T1 and the first group of backfill aggregates K1 while binding to the first group of binding rods P1 ( S4), 상기 1군의 결속봉(P1)에 2군의 결속봉(P2)을 각각 소켓(20) 결합시켜 연장시키는 스텝(S5)과,Step (S5) for coupling the two groups of binding rods (P2) to each of the binding rods (P1) of the first group to extend the socket (20), 상기 1군의 그리드(G1) 위에 2군의 블록(B2), 2군의 뒷채움 토사(T2) 및 2군의 뒷채움 골재(K2)를 전후 차례로 쌓으면서 그 중간에 2군의 그리드(G2)를 상기 2군의 결속봉(P2)에 결속시켜 펼치는 스텝(S6)과,2 groups of blocks (B2), 2 groups of backfilled soil (T2) and 2nd group of backfill aggregate (K2) on the grid of the first group (G2) while stacking back and forth in turn in the middle of the two groups of grid (G2) Step (S6) to bind to the two groups of binding rods (P2) and expand, 상기 2군의 블록(B2) 및 2군의 뒷채움 토사(T2) 위에 제 2 보강콘크리트층(C2)을 타설 및 양생시키는 스텝(S7)과,Step (S7) of pouring and curing the second reinforcement concrete layer (C2) on the two groups of blocks (B2) and the two groups of backfilled soil (T2); 상기 2군의 결속봉(P2)에 3군의 결속봉(P3)을 각각 소켓(20) 결합시켜 연장시키는 스텝(S8)과,Step (S8) of coupling the three groups of binding rods (P3) to the socket 20 of the two groups of binding rods (P2) and extending (S8), 상기 제 2 보강콘크리트층(C2) 및 2군의 뒷채움 골재(K2) 위에 3군의 블 록(B3), 3군의 뒷채움 토사(T3) 및 3군의 뒷채움 골재(K3)를 전후 차례로 쌓으면서 그 중간에 3군의 그리드(G3)를 상기 3군의 결속봉(P3)에 결속시켜 펼치는 스텝(S9)과,While stacking three blocks (B3), three groups of backfill soil (T3) and three groups of backfill aggregates (K3) on the second reinforcement concrete layer (C2) and the second group of backfill aggregates (K2) in front and rear in sequence. Step S9 of binding the three groups of grids G3 to the three groups of binding rods P3 in the middle thereof and expanding them; 상기 3군의 블록(B3) 및 3군의 뒷채움 토사(T3) 위에 제 3 보강콘크리트층(C3)을 타설 및 양생시키는 스텝(S10)과,Step (S10) of pouring and curing the third reinforcement concrete layer (C3) on the three groups of blocks (B3) and three groups of backfilled soil (T3); 상기 3군의 결속봉(P3)에 4군의 결속봉(P4)을 각각 소켓(20) 결합시켜 연장시키는 스텝(S11)과,Step (S11) for coupling the four groups of binding rods (P4) to each of the three groups of binding rods (P3) by extending the socket (20), 상기 제 3 보강콘크리트층(C3) 및 3군의 뒷채움 골재(K3) 위에 4군의 블록(B4), 4군의 뒷채움 토사(T4) 및 4군의 뒷채움 골재(K4)를 전후 차례로 쌓으면서 그 중간에 4군의 그리드(G4)를 상기 4군의 결속봉(P4)에 결속시켜 펼치는 스텝(S12)과,While stacking four blocks (B4), four groups of backfill soil (T4) and four groups of backfill aggregate (K4) on the third reinforcement concrete layer (C3) and the third group of backfill aggregate (K3), Step S12 of binding the four groups of grids G4 to the four groups of binding rods P4 in the middle and expanding them; 상기 4군의 블록(B4), 4군의 뒷채움 토사(T4) 및 4군의 뒷채움 골재(K4) 위에 제 4 보강콘크리트층(C4)을 타설 및 양생시키는 스텝(S13)을 포함하여 이루어지는 것을 특징으로 하는 옹벽 블록 시공방법.And a step S13 of pouring and curing the fourth reinforcement concrete layer C4 on the four groups of blocks B4, four groups of backfilled soils T4, and four groups of backfilled aggregates K4. A retaining wall block construction method. 제 1 항에 있어서,The method of claim 1, 상기 사면(S)을 따라 부직포(30)가 씌워지는 것을 특징으로 하는 옹벽 블록 시공방법.Retaining wall block construction method characterized in that the nonwoven fabric 30 is covered along the slope (S). 제 1 항에 있어서,The method of claim 1, 상기 1군의 결속봉(P1) 내지는 4군의 결속봉(P4)을 잡아주면서 상기 부직포(30)를 경유하여 상기 사면(S)에 소일 네일(40; Soil Nail)이 박혀지는 것을 특징으로 하는 옹벽 블록 시공방법.Soil nail 40 is embedded in the slope S via the nonwoven fabric 30 while holding the binding rods P1 of the first group or the four binding rods P4 of the group. Retaining wall block construction method. 제 1 항에 있어서,The method of claim 1, 상기 제 1 기초코트리트층 위의 상기 1군의 바닥 골재(T1) 속에 횡방향으로 유공관(50)이 놓여지는 것을 특징으로 하는 옹벽 블록 시공방법.Retaining wall block construction method characterized in that the perforated pipe (50) is placed in the transverse direction in the bottom aggregate (T1) of the first group on the first foundation coat layer. 제 1 항에 있어서,The method of claim 1, 상기 1군의 블록(B1) 내지 4군의 블록(B4)은 상기 사면(S)의 경사각도에 맞추어 들여쌓기 또는 수직쌓기로 이루어지는 것을 특징으로 옹벽 블록 시공방법.Retaining wall block construction method, characterized in that the first group of blocks (B1) to the fourth group of blocks (B4) is made of the stacking or vertical stacking in accordance with the inclination angle of the slope (S). 제 1 항 내지 제 5 항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 5, 상기 1군 내지 4군의 블록(B1∼B4)은 낱개의 블록(B)들이 군을 이루어 완성되며,Blocks B1 to B4 of the group 1 to 4 are completed by forming a group of blocks (B), 상기 블록(B)은 중앙에 제 1 홀(12)을 지닌 제 1 중공홈(11) 및 제 2 홀(14)을 지닌 제 2 중공홈(13)으로 구획됨과 동시에 상부에 걸림돌기(15)를 구비하는 것을 특징으로 하는 옹벽 블록 시공방법.The block B is partitioned into a first hollow groove 11 having a first hole 12 and a second hollow groove 13 having a second hole 14 at the center thereof, and at the same time, a protrusion 15 at the top thereof. Retaining wall block construction method comprising the. 제 6 항에 있어서,The method of claim 6, 상기 블록(B)의 제 1 중공홈(11)에 속채움 토사(60)가 채워지고, 상기 블록(B)의 제 2 중공홈(13)에 속채움 골재(70)가 채워지는 것을 특징으로 하는 옹벽 블록 시공방법.The filling hollow sand 60 is filled in the first hollow groove 11 of the block B, and the filling aggregate 70 is filled in the second hollow groove 13 of the block B. Retaining wall block construction method. 제 1 항 내지 도 5 항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 5, 상기 1군의 블록(B1) 앞에 노출된 상기 제 1 기초콘크리트층(C1) 위에 앞채움 토사(80)를 주변 지형에 맞추어 쌓는 것을 특징으로 하는 옹벽 블록 시공방법.Retaining wall block construction method characterized in that the front-filled soil (80) is stacked on the first foundation concrete layer (C1) exposed in front of the first group of blocks (B1) according to the surrounding terrain.
KR1020080089575A 2008-09-11 2008-09-11 Retaining Wall Block Construction Method Active KR100995097B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080089575A KR100995097B1 (en) 2008-09-11 2008-09-11 Retaining Wall Block Construction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080089575A KR100995097B1 (en) 2008-09-11 2008-09-11 Retaining Wall Block Construction Method

Publications (2)

Publication Number Publication Date
KR20100030724A true KR20100030724A (en) 2010-03-19
KR100995097B1 KR100995097B1 (en) 2010-11-19

Family

ID=42180565

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080089575A Active KR100995097B1 (en) 2008-09-11 2008-09-11 Retaining Wall Block Construction Method

Country Status (1)

Country Link
KR (1) KR100995097B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102498033B1 (en) * 2022-04-19 2023-02-10 주식회사 천윤 A method of constructing a soil bag using a bundle tube binding material to maintain drainage function and prevent soil loss
CN116180802A (en) * 2022-12-07 2023-05-30 国网福建省电力有限公司经济技术研究院 Modular fort construction method for blocking waste soil in power transmission and transformation engineering tower foundation construction
KR102666790B1 (en) * 2023-07-17 2024-05-17 주식회사 코리아그린텍 bunker structure and the method of construction thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1129929A (en) 1997-07-09 1999-02-02 Kumagai Gumi Co Ltd Reinforced filling method
KR200242168Y1 (en) 2001-05-10 2001-10-15 강승문 An Assembly for Segmental Retaining Wall
KR100660574B1 (en) 2005-05-24 2006-12-22 이정수 Retaining Wall Construction Block

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102498033B1 (en) * 2022-04-19 2023-02-10 주식회사 천윤 A method of constructing a soil bag using a bundle tube binding material to maintain drainage function and prevent soil loss
CN116180802A (en) * 2022-12-07 2023-05-30 国网福建省电力有限公司经济技术研究院 Modular fort construction method for blocking waste soil in power transmission and transformation engineering tower foundation construction
KR102666790B1 (en) * 2023-07-17 2024-05-17 주식회사 코리아그린텍 bunker structure and the method of construction thereof

Also Published As

Publication number Publication date
KR100995097B1 (en) 2010-11-19

Similar Documents

Publication Publication Date Title
KR100924933B1 (en) Construction method of natural friendly retaining wall using vegetation ton and fixing member and its installation structure
KR200185875Y1 (en) Reinforced earth retaining-wall for using sand-bag
KR102666680B1 (en) self standing gravity retaining wall block
KR100679873B1 (en) Construction method of greening retaining wall
KR100995097B1 (en) Retaining Wall Block Construction Method
KR100959828B1 (en) Vegetation slope composition method and the vegetation slope structure by using the method
KR20090019591A (en) Retaining wall construction block and its construction method
KR100660379B1 (en) Plantable reinforced earth wall and its block and construction method of reinforced earth wall
KR100889257B1 (en) Prefabricated earth retaining wall using greening of front wall
KR20020076530A (en) Afforestation Retaining-Wall laying Concrete-block
KR200345937Y1 (en) Precast concrete block for retaining wall
KR102194293B1 (en) Breast wall structure
KR102263958B1 (en) the Method of Construction of Prefabricated Block for Retaining Wall Bulwark
KR100780216B1 (en) Method to install honeycomb mat
KR100750702B1 (en) Embankment Construction Method Using Ecological Block
KR101566794B1 (en) Vertical Round Gabion Box, Retaining Wall Structures and the Construction Methods using Gabion Box
CN110984192B (en) Highway reconstruction excavated slope reinforcing structure and reinforcing method
KR100451429B1 (en) Combination system of block type reinforced retaining wall used waste concrete and waste limestone and constructing method thereof
KR102184291B1 (en) Pavement Block Part for Temporary Reconstructing of Road
CN207062983U (en) A kind of prefabricated frame posture retaining wall
KR101508591B1 (en) Retaining wall frame and construction method of retaining wall
KR20100003166U (en) Retaining Wall Block Construction Grid
KR100992076B1 (en) Structure of raising the ground level and excecution method thereof
KR100885909B1 (en) Self-supporting temporary retaining wall using geotextile network and its construction method
KR20050043552A (en) Wall structure with gabion

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20080911

PA0201 Request for examination
PG1501 Laying open of application
E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20101025

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20101111

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20101112

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20131112

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20131112

Start annual number: 4

End annual number: 4

FPAY Annual fee payment

Payment date: 20141211

Year of fee payment: 5

PR1001 Payment of annual fee

Payment date: 20141211

Start annual number: 5

End annual number: 5

FPAY Annual fee payment

Payment date: 20160512

Year of fee payment: 6

PR1001 Payment of annual fee

Payment date: 20160512

Start annual number: 6

End annual number: 6

FPAY Annual fee payment

Payment date: 20161111

Year of fee payment: 7

PR1001 Payment of annual fee

Payment date: 20161111

Start annual number: 7

End annual number: 7

FPAY Annual fee payment

Payment date: 20171113

Year of fee payment: 8

PR1001 Payment of annual fee

Payment date: 20171113

Start annual number: 8

End annual number: 8

FPAY Annual fee payment

Payment date: 20181112

Year of fee payment: 9

PR1001 Payment of annual fee

Payment date: 20181112

Start annual number: 9

End annual number: 9

PR1001 Payment of annual fee

Payment date: 20200511

Start annual number: 10

End annual number: 10

PC1903 Unpaid annual fee

Termination category: Default of registration fee

Termination date: 20210811

PR0401 Registration of restoration

Patent event code: PR04011E01D

Patent event date: 20210811

Comment text: Registration of Restoration

PR1001 Payment of annual fee

Payment date: 20210811

Start annual number: 11

End annual number: 11

R401 Registration of restoration
PR1001 Payment of annual fee

Payment date: 20211214

Start annual number: 12

End annual number: 12

PC1903 Unpaid annual fee

Termination category: Default of registration fee

Termination date: 20240812

Termination category: Default of registration fee

Termination date: 20230811

Termination category: Default of registration fee

Termination date: 20210811

PR0401 Registration of restoration

Patent event code: PR04011E01D

Patent event date: 20240812

Comment text: Registration of Restoration

PR1001 Payment of annual fee

Payment date: 20240813

Start annual number: 14

End annual number: 14

R401 Registration of restoration