KR100679873B1 - Construction method of greening retaining wall - Google Patents
Construction method of greening retaining wall Download PDFInfo
- Publication number
- KR100679873B1 KR100679873B1 KR1020060042207A KR20060042207A KR100679873B1 KR 100679873 B1 KR100679873 B1 KR 100679873B1 KR 1020060042207 A KR1020060042207 A KR 1020060042207A KR 20060042207 A KR20060042207 A KR 20060042207A KR 100679873 B1 KR100679873 B1 KR 100679873B1
- Authority
- KR
- South Korea
- Prior art keywords
- greening
- soil
- geogrid
- pack
- retaining wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 71
- 239000002689 soil Substances 0.000 claims abstract description 106
- 238000000034 method Methods 0.000 claims abstract description 23
- 238000000465 moulding Methods 0.000 claims abstract description 10
- 238000005452 bending Methods 0.000 claims abstract description 8
- 239000000463 material Substances 0.000 claims abstract description 8
- 229920003002 synthetic resin Polymers 0.000 claims abstract description 4
- 239000000057 synthetic resin Substances 0.000 claims abstract description 4
- 239000004927 clay Substances 0.000 claims abstract description 3
- 230000002787 reinforcement Effects 0.000 abstract description 24
- 230000003014 reinforcing effect Effects 0.000 abstract description 4
- 230000002265 prevention Effects 0.000 abstract description 3
- 239000004576 sand Substances 0.000 description 18
- 238000005056 compaction Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 229920000728 polyester Polymers 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000001965 increasing effect Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 239000004743 Polypropylene Substances 0.000 description 2
- 230000009471 action Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000003628 erosive effect Effects 0.000 description 2
- 239000000835 fiber Substances 0.000 description 2
- 230000035784 germination Effects 0.000 description 2
- 239000003365 glass fiber Substances 0.000 description 2
- 239000008187 granular material Substances 0.000 description 2
- 230000001939 inductive effect Effects 0.000 description 2
- 230000035699 permeability Effects 0.000 description 2
- -1 polypropylene Polymers 0.000 description 2
- 229920001155 polypropylene Polymers 0.000 description 2
- 229920005989 resin Polymers 0.000 description 2
- 239000011347 resin Substances 0.000 description 2
- 239000012209 synthetic fiber Substances 0.000 description 2
- 229920002994 synthetic fiber Polymers 0.000 description 2
- 238000009941 weaving Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 239000004746 geotextile Substances 0.000 description 1
- 238000003475 lamination Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000012779 reinforcing material Substances 0.000 description 1
- 230000003252 repetitive effect Effects 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0225—Retaining or protecting walls comprising retention means in the backfill
- E02D29/0241—Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0225—Retaining or protecting walls comprising retention means in the backfill
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/205—Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/025—Retaining or protecting walls made up of similar modular elements stacked without mortar
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0283—Retaining or protecting walls characterised by constructional features of mixed type
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0084—Geogrids
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
본 발명은 시공되는 위치에 합성수지 재질의 지오그리드를 포설하는 단계와; 상기 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 적층하고, 지오그리드를 상측으로 수직절곡하고 녹화팩이나 녹화마대 상면에 위치시키는 단계와; 상기 지오그리드 상면에서 상기 녹화팩이나 녹화마대와 면접되게 상하단이 개방된 사각통체 또는 사각틀체인 성형틀을 위치시키고, 성형틀 내측에 상단이 개방된 사각통체인 흙부대를 셋팅하여 그 내부에 토사를 충진시켜 다지는 단계와; 상기 성형틀을 흙부대 외측면에서 제거하고, 흙부대 후방측에 인근까지 흙부대의 중간높이로 토사를 1차로 포설하여 다지는 단계와; 상기 지오그리드 전방측에서 수직절곡하여 흙부대를 감싸고 일단을 후방측으로 연장시키고, 상기 녹화팩이나 녹화마대를 지오그리드와 체결고정시키며, 흙부대의 후방측에서 흙부대의 상단까지 토사를 2차로 포설하여 다지는 단계와; 다시 그 상면에 지오그리드를 포설하고, 지오그리드 하부의 녹화팩이나 녹화마대의 상면에 다시 녹화팩이나 녹화마대를 상부로 적층하며, 상기 성형틀과 흙부대를 하부 흙부대의 상면에서 약간 후방측으로 셋팅하여 전단계를 순차적으로 반복 수행함으로써 필요한 녹화 옹벽의 높이를 설정하여 이루어지는 녹화 옹벽의 시공방법에 관한 것이다.The present invention comprises the steps of laying a geogrid of a synthetic resin material at the construction site; Stacking a green pack or a recording rod under the front side of the geogrid, vertically bending the geogrid upwards, and placing the green pack on the upper surface of the recording pack or recording rod; Place a rectangular cylinder or rectangular frame chain forming mold on the top of the geogrid to be interviewed with the greening pack or greening rod, and set the soil bag of the rectangular cylinder with an open top at the inside of the mold to fill the soil. Chopping; Removing the mold from the outer surface of the soil bag, and laying soil at the middle height of the soil bag to the vicinity of the soil bag rear side first to compact the soil; The geogrid is bent vertically on the front side to surround the soil bag and extend one end to the rear side. Steps; The geogrid is laid on the upper surface again, and the green pack or the greening rod is laminated on the upper side of the greening pack or greening rod under the geogrid, and the molding frame and the soil bag are set slightly rearward from the upper surface of the lower clay bag. The present invention relates to a method for constructing a greening retaining wall by setting the required height of the greening retaining wall by sequentially repeating the previous steps.
이러한 본 발명은 보강재가 외부로 노출되지 않아 파손으로 인한 염려가 전혀 없을 뿐만 아니라 손상이 억제되며, 랩핑이 매우 손쉬워 시공이 간편하며, 시공 후, 녹화율이 매우 뛰어나고, 콘크리트 및 철근을 사용하지 않고도 옹벽의 구조적 인 기능과 강도를 지속적으로 유지할 수 있어 하천 유역 및 유수지역의 유실방지공사에 매우 적합한 환경친화적인 효과가 있다.In the present invention, the reinforcement is not exposed to the outside, there is no fear of damage as well as the damage is suppressed, the wrapping is very easy, easy to install, after construction, very excellent greening rate, without using concrete and reinforcing bar The structural function and strength of the retaining wall can be maintained continuously, which is very suitable for the prevention of loss in river basins and runoff areas.
Description
도 1은 본 발명 실시 예인 녹화 옹벽의 시공방법에 따른 녹화 옹벽의 시공된 모습을 보인 사시도, 1 is a perspective view showing a construction of a greening retaining wall according to the construction method of the greening retaining wall according to an embodiment of the present invention;
도 2는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드가 포설되는 모습을 보인 요부확대 측단면도,Figure 2 is an enlarged side cross-sectional view showing the main portion enlarged geogrid in the installation method of the greening retaining wall according to an embodiment of the present invention,
도 3은 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도,Figure 3 is a side cross-sectional view showing the location of the greening pack or greening rod on the lower front side of the geogrid of the construction method of the greening retaining wall according to an embodiment of the present invention,
도 4는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 녹화팩의 후방선단에 성형틀과 흙부대를 셋팅하고 흙부대 내측에 토사를 충진시키는 모습을 보인 측단면도,Figure 4 is a side cross-sectional view showing a state in which the mold and soil bag is set to the rear end of the greening pack in the construction method of the greening retaining wall according to an embodiment of the present invention and the soil is filled inside the soil bag,
도 5는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 성형틀을 흙부대 외측면에서 제거하는 과정을 보인 측단면도,Figure 5 is a side cross-sectional view showing a process of removing the mold from the soil bag outer surface of the construction method of the greening retaining wall is an embodiment of the present invention,
도 6은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도,Figure 6 is a side cross-sectional view showing a state in which the first stage of the earth and sand is completed by the construction method of the greening retaining wall according to the present invention,
도 7은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형 성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도,FIG. 7 is a side cross-sectional view showing a state in which geogrids are stacked on top of the green packs in order to form the soil layer of the second stage by the construction method of the greening retaining wall according to the embodiment of the present invention; FIG.
도 8은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도,8 is a side cross-sectional view showing a state in which the second stage is completed on top of the first stage by the construction method of the greening retaining wall according to an embodiment of the present invention;
도 9는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법에 따른 녹화 옹벽의 시공된 모습을 보인 사시도, 9 is a perspective view showing the construction of the greening retaining wall according to the construction method of the greening retaining wall according to another embodiment of the present invention;
도 10은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 지오그리드가 포설되는 모습을 보인 요부확대 측단면도, 10 is an enlarged side cross-sectional view showing a main portion of the geogrid in the construction method of the greening retaining wall according to another embodiment of the present invention;
도 11은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도, 11 is a side cross-sectional view showing a greening pack or greening rod placed on the lower front side of the geogrid in the construction method of the greening retaining wall according to another embodiment of the present invention;
도 12는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 녹화팩이나 녹화마대 후방측에 토사를 1차로 충진시키는 모습을 보인 측단면도, 12 is a side cross-sectional view showing a state of filling the soil first in the rear side of the green pack or greening rod in the construction method of the greening retaining wall according to another embodiment of the present invention;
도 13은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도, Figure 13 is a side cross-sectional view showing the first stage of the earth and sand completed by the construction method of the greening retaining wall according to another embodiment of the present invention,
도 14는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도, 14 is a side sectional view showing a state in which a green pack is laminated and geogrids are installed on the upper surface of the greening retaining wall according to another embodiment of the present invention to form a soil layer of the second stage;
도 15는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도.15 is a side cross-sectional view showing a state in which the second stage is completed on top of the first stage by the construction method of the greening retaining wall according to another embodiment of the present invention.
*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *
1,1a : 녹화 옹벽 10 : 흙부대1,1a: Greening retaining wall 10: Earth bag
11 : 토사 20 : 성형틀11: earth and sand 20: mold
30 : 지오그리드 40 : 첫째단30: geogrid 40: first stage
41 : 1차토사 42 : 2차토사41: 1st earth and sand 42: 2nd earth and sand
40a : 둘째단 50 : 녹화팩40a: second stage 50: recording pack
본 발명은 녹화 옹벽의 시공방법에 관한 것으로서, 보다 상세하게는 보강재가 외부로 노출되지 않아 파손으로 인한 염려가 전혀 없을 뿐만 아니라 손상이 억제되며, 랩핑이 매우 손쉬워 시공이 간편하며, 시공 후, 녹화율이 매우 뛰어나고, 콘크리트 및 철근을 사용하지 않고도 옹벽의 구조적인 기능과 강도를 지속적으로 유지할 수 있어 하천 유역 및 유수지역의 유실방지공사에 매우 적합한 환경친화적인 녹화 옹벽의 시공방법에 관한 것이다.The present invention relates to a method for constructing a greening retaining wall, and more particularly, since the reinforcement is not exposed to the outside, there is no worry of damage, and damage is suppressed. This method is about construction of environmentally friendly green retaining wall which is very suitable for the prevention of loss of river basin and flowing water because it has excellent rate and can keep the structural function and strength of retaining wall without using concrete and rebar.
보강토 공법은 오래전부터 흙을 주체로 한 성토층 속에 인장력이 큰 스트립 형태 혹은 판 상의 보강재를 일정한 간격 또는 전체적으로 해당하는 부위를 포설하고, 흙 메움으로 이들을 매설하여 하나의 새로운 복합구조체를 형성시키는 공법으 로서, 그 큰 목적으로서는 흙을 사용한 토질 구조물을 기계적으로 안정화시키기 위한 목적으로 널리 이용되는 공법이다.The reinforcement soil method is a method of laying a part of a strip-like or plate-like reinforcement with high tensile force at regular intervals or as a whole in a fill layer mainly composed of soil, and embedding them with soil filling to form a new composite structure. As a large object, the method is widely used for the purpose of mechanically stabilizing soil structures using soil.
이런 보강토 공법을 이용한 시공에는 연직벽체를 구축하기 위한 보강토 옹벽(MSEW, Mechanically Stabilized Earth Walls)과, 보강사면(RSS, Reinforced Steep Slopes, 또는 Reinforced Soil Slopes)을 그 예로 둘 수 있는바, 옹벽과 같은 기능을 하는 보강토 옹벽을 시공하기 위한 경사각은 지역에 따라서 대략 80°이상의 직경사도로부터 90°의 수직을 이루고, 보강사면은 설계경사도에 따라서 70°이하의 경사도를 이루도록 구축한다.Construction using this reinforcement soil method may include reinforcement retaining walls (MSEW) for building vertical walls, and reinforcement slopes (RSS, Reinforced Steep Slopes, or Reinforced Soil Slopes) as examples. The inclination angle for constructing the functioning retaining wall retaining wall is perpendicular to 90 ° from the diameter slope of more than 80 ° depending on the area, and the reinforcement slope is constructed to be less than 70 ° according to the design slope.
상기 보강토 옹벽시공은 연직벽체의 수직도, 보강사면시공은 경사도를 유지하기 위해 기초 시공 전 상태와 시공단계에서의 규준틀(Leading Frame 또는 Better Board)이 설치된다.The reinforcement soil retaining wall construction is perpendicular to the vertical wall, the reinforcement slope construction is installed before the basic construction state and the construction frame (Leading Frame or Better Board) in order to maintain the slope.
상기 규준틀은 토층시공에 따른 각도를 기준하기 위한 것으로, 완경사부터 급경사에 이르는 지점의 최초 지반으로부터 설치되고, 토층이 연속적으로 시공되는 상태에서는 토층의 전면측 높이를 따라 설치되어 사용된다.The scaffold frame is for reference to the angle according to the soil construction, and is installed from the initial ground from the point of gentle slope to steep slope, and is installed along the front side height of the soil layer when the soil layer is continuously constructed.
한편, 연직벽체나 사면의 시공에 따른 토층의 형성은 시공되는 위치로부터 전면부에 목재 또는 철망(Wire Mesh) 및 철근 등의 재질을 이용하여 가이드 프레임(Guide Frame)을 설치하고, 토체에 저항할 수 있는 보강재가 설치된 상태에서 프레임의 배면측으로는 토공(채움 및 다지기)을 실시하여 토층을 형성할 수 있도록 한다.On the other hand, the formation of the soil layer according to the construction of the vertical wall or slope is to install the guide frame (Guide Frame) using materials such as wood or wire mesh (wire wire) and reinforcement on the front part from the construction position, and to resist the soil body In the state where the reinforcement can be installed to the back side of the frame by the earthwork (filling and compacting) to be able to form a soil layer.
상기 토층의 형성은, 기초지반으로 설정된 위치에 규준틀을 세우고, 규준틀 을 토대로 성토부분의 지면으로는 가이드 프레임이 설치된다. 또한, 가이드 프레임은 철근을 격자형태로 엮거나, 또는 목재를 이용하여 형틀을 만든 것으로, 규준틀의 경사각을 갖도록 형성시킨 것이며, 시공하고자 하는 사면의 시작점에 횡으로 설치된다.In the formation of the soil layer, a scaffold frame is placed at the position set as the foundation ground, and a guide frame is installed on the ground of the fill portion based on the scaffold frame. In addition, the guide frame is formed by weaving the reinforcing bar in the form of a lattice, or using a timber, formed to have an inclination angle of the scaffold frame, and is installed laterally at the starting point of the slope to be constructed.
상기 가이드 프레임이 놓이는 지면으로부터는 보강재가 설치되며, 상기 보강재는 지오그리드(Geogrid)나 지오텍스타일(Geotextile)을 토층에 포설하거나, 보강재 전면을 감싸서 시공할 경우는, 상기 가이드 프레임의 상부로 보강재 일부분을 제쳐 둔 상태에서 가이드 프레임의 배면으로는 흙을 채우고 다져주며, 토체의 상부측, 즉 가이드 프레임의 전면측으로 제쳐둔 보강재를 보강토체 측으로 보내어 그 위에 일정량(두께 8∼15㎝정도)의 토공을 실시하여 토층을 형성시켜 준다.The reinforcement is installed from the ground on which the guide frame is placed, and the reinforcement is provided with a geogrid or a geotextile on the ground layer, or when the construction is wrapped around the front of the reinforcement. In the state of aside, the back of the guide frame is filled with soil and compacted, and the reinforcement placed aside from the upper side of the soil, that is, the front side of the guide frame, is sent to the reinforcement soil, and a certain amount (about 8 to 15 cm thick) is applied to the earth. To form a soil layer.
상기 토층을 형성한 상태에서의 그 상면으로는 또 다른 가이드 프레임과 보강재를 설치하여 상술한 바와 같이 토공의 반복적인 작업으로 수직 또는 경사도를 갖는 보강토체를 연속적으로 시공하면 된다.In the state in which the soil layer is formed, another guide frame and a reinforcing material may be installed to construct reinforcement soils having vertical or inclined soil continuously by repetitive work of earthwork as described above.
상기와 같은 방법에 의해 연속적으로 실시되는 보강토체의 시공에 있어, 시공되는 보강토체의 소정 높이에 별도의 소정길이를 갖는 다른 규준틀을 경사도와 동일한 방향이 되게 결속하여 이를 보고서 시공의 각도를 측정하면서 시공한다.In the construction of the reinforcement soil continuously carried out by the above method, while binding the other standard frame having a predetermined length to the predetermined height of the reinforcement soil to be constructed in the same direction as the slope, while measuring the angle of construction Construct
이후 상기와 같이 가이드 프레임과 보강재의 설치로서 토공을 실시하여 시공을 완성할 수 있다.Thereafter, the construction can be completed by carrying out earthwork as installation of the guide frame and the reinforcement as described above.
한편, 분리형 보강토 옹벽을 시공하기 위한 연직벽체의 시공에 대한 규준틀은 토층의 전면에 대해 수직으로 규준틀을 설치하고, 철근을 직각으로 엮어 제작한 가이드 프레임을 설치하여 가면서 상기와 같이 보강재와 토공으로서 지면으로부터 수직되는 벽체를 구현할 수 있다. On the other hand, the scaffold frame for the construction of the vertical wall for the construction of the separate type reinforced soil retaining wall is installed vertically with respect to the front surface of the soil layer, and the guide frame made by weaving the bars at right angles is installed. It is possible to implement a wall vertically from.
그러나, 상기와 같은 종래의 녹화 옹벽은 보강재가 외부로 노출되어 화재시 또는 외부에서 칼이나 기타 날카로운 장비로 인한 파손시 옹벽구조물 자체에 심각한 붕괴위험을 유발시키는 문제점이 있었다.However, the conventional greening retaining wall as described above has a problem that the reinforcement is exposed to the outside causing a serious risk of collapse in the retaining wall structure itself in case of fire or damage caused by a knife or other sharp equipment from the outside.
또한, 블록식의 경우에는 횡방향 토압을 어느 정도 지지할 수 있으나, 랩핑(wrapping)이 매우 어려워 일반적으로 스틸 메쉬를 이용하는 실정이며, 녹화율이 매우 떨어지는 문제점이 있었다.In addition, in the case of the block type, but can support the lateral earth pressure to some extent, wrapping is very difficult, and the situation is generally using a steel mesh, there was a problem that the recording rate is very low.
본 발명은 상기와 같은 문제점을 해결하기 위한 것으로서, 보강재가 외부로 노출되지 않아 파손으로 인한 염려가 전혀 없을 뿐만 아니라 손상이 억제되며, 랩핑이 매우 손쉬워 시공이 간편하며, 시공 후, 녹화율이 매우 뛰어나고, 콘크리트 및 철근을 사용하지 않고도 옹벽의 구조적인 기능과 강도를 지속적으로 유지할 수 있어 하천 유역 및 유수지역의 유실방지공사에 매우 적합한 환경친화적인 녹화 옹벽의 시공방법을 제공함에 그 목적이 있다.The present invention is to solve the above problems, the reinforcement is not exposed to the outside, there is no fear of damage, as well as damage is suppressed, easy to wrap and easy to install, after construction, the rate of recording is very The purpose is to provide an environmentally friendly green retaining wall construction method that is excellent for the prevention of loss in river basins and runoff areas because it is excellent and can maintain the structural function and strength of retaining walls without using concrete and reinforcing bars.
이와 같은 목적을 달성하기 위하여, 본 발명은 시공되는 위치에 합성수지 재 질의 지오그리드를 포설하는 단계와;In order to achieve the above object, the present invention comprises the steps of laying a geogrid of the resin material in the construction site;
상기 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 적층하고, 지오그리드를 상측으로 수직절곡하고 녹화팩이나 녹화마대 상면에 위치시키는 단계와;Stacking a green pack or a recording rod under the front side of the geogrid, vertically bending the geogrid upwards, and placing the green pack on the upper surface of the recording pack or recording rod;
상기 지오그리드 상면에서 상기 녹화팩이나 녹화마대와 면접되게 상하단이 개방된 사각통체 또는 사각틀체인 성형틀을 위치시키고, 성형틀 내측에 상단이 개방된 사각통체인 흙부대를 셋팅하여 그 내부에 토사를 충진시켜 다지는 단계와;Place a rectangular cylinder or rectangular frame chain forming mold on the top of the geogrid to be interviewed with the greening pack or greening rod, and set the soil bag of the rectangular cylinder with an open top at the inside of the mold to fill the soil. Chopping;
상기 성형틀을 흙부대 외측면에서 제거하고, 흙부대 후방측에 인근까지 흙부대의 중간높이로 토사를 1차로 포설하여 다지는 단계와; Removing the mold from the outer surface of the soil bag, and laying soil at the middle height of the soil bag to the vicinity of the soil bag rear side first to compact the soil;
상기 지오그리드 전방측에서 수직절곡하여 흙부대를 감싸고 일단을 후방측으로 연장시키고, 상기 녹화팩이나 녹화마대를 지오그리드와 체결고정시키며, 흙부대의 후방측에서 흙부대의 상단까지 토사를 2차로 포설하여 다지는 단계와;Wrap the soil bag by vertical bending at the front side of the geogrid and extend one end to the rear side, and fasten and fix the greening pack or greening rod with the geogrid, and install the soil from the rear side of the soil bag to the top of the soil bag. Steps;
다시 그 상면에 지오그리드를 포설하고, 지오그리드 하부의 녹화팩이나 녹화마대의 상면에 다시 녹화팩이나 녹화마대를 상부로 적층하며, 상기 성형틀과 흙부대를 하부 흙부대의 상면에서 약간 후방측으로 셋팅하여 전단계를 순차적으로 반복 수행함으로써 필요한 녹화 옹벽의 높이를 설정하여 이루어지는 특징이 있다.The geogrid is laid on the upper surface again, and the green pack or the greening rod is laminated on the upper side of the greening pack or greening rod under the geogrid, and the molding frame and the soil bag are set slightly rearward from the upper surface of the lower clay bag. It is characterized by setting the required height of the green retaining wall by repeatedly performing the previous step sequentially.
또한, 시공되는 위치에 합성수지 재질의 지오그리드를 포설하는 단계와;In addition, the step of laying a geogrid of synthetic resin material at the construction site;
상기 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 적층하고, 지오그리드를 상측으로 수직절곡하고 녹화팩이나 녹화마대 상면에 위치시키는 단계와;Stacking a green pack or a recording rod under the front side of the geogrid, vertically bending the geogrid upwards, and placing the green pack on the upper surface of the recording pack or recording rod;
상기 녹화팩이나 녹화마대의 중간높이로 토사를 1차로 포설하여 다지는 단계와; Laying and laying soil first with the middle height of the recording pack or recording rod;
상기 지오그리드 전방측에서 수직절곡하여 1차토사를 감싸고 일단을 후방측으로 연장시키고, 상기 녹화팩이나 녹화마대를 지오그리드와 체결고정시키며, 녹화팩이나 녹화마대의 후방측에서 상단까지 토사를 2차로 포설하여 다지는 단계와;Wrap the primary soil by vertical bending at the front side of the geogrid, extend one end to the rear side, fasten and fix the green pack or greening rod with the geogrid, and install the earth and sand from the rear side to the upper end of the greening pack or greening rod. Chopping;
다시 그 상면에 지오그리드를 포설하고, 지오그리드 하부의 녹화팩이나 녹화마대의 상면에 다시 녹화팩이나 녹화마대를 상부로 적층하며, 상기 녹화팩이나 녹화마대를 하부 녹화팩이나 녹화마대의 상면에서 약간 후방측으로 셋팅하여 전단계를 순차적으로 반복 수행함으로써 필요한 녹화 옹벽의 높이를 설정하여 이루어지는 특징을 갖는다.Lay the geogrid on the upper surface again, stack the recording pack or recording rod on top of the recording pack or recording rod under the geogrid, and place the recording pack or recording rod slightly behind the upper recording pack or recording rod. It is characterized by setting the height of the green retaining wall required by setting the side to repeat the previous step sequentially.
이하, 본 발명을 첨부된 도면에 의해 보다 상세하게 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.
참고로 본 고안을 설명함에 있어 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 고안의 요지를 불필요하게 흐릴 수 있다고 판단될 경우에는 그 상세한 설명을 생략하였다.For reference, in describing the present invention, when it is determined that a detailed description of related known functions or configurations may unnecessarily obscure the subject matter of the present invention, the detailed description thereof is omitted.
또한, 후술되는 용어들은 본 고안에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운영자의 의도 또는 관례 등에 따라 달라질 수 있다.In addition, terms to be described later are terms defined in consideration of functions in the present invention, which may vary according to the intention or custom of a user or an operator.
그러므로, 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것임은 물론이다.Therefore, the definition should be made based on the contents throughout the specification.
도 1은 본 발명 실시 예인 녹화 옹벽의 시공방법에 따른 녹화 옹벽의 시공된 모습을 보인 사시도이고, 도 2는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드가 포설되는 모습을 보인 요부확대 측단면도이며, 도 3은 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도이고, 도 4는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 녹화팩의 후방선단에 성형틀과 흙부대를 셋팅하고 흙부대 내측에 토사를 충진시키는 모습을 보인 측단면도이며, 도 5는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 성형틀을 흙부대 외측면에서 제거하는 과정을 보인 측단면도이고, 도 6은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도이며, 도 7은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도이고, 도 8은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도이다.1 is a perspective view showing the construction of the greening retaining wall according to the construction method of the greening retaining wall according to an embodiment of the present invention, Figure 2 is a side enlarged cross-sectional side view showing the geogrid of the construction method of the greening retaining wall according to the embodiment of the present invention. Figure 3 is a side cross-sectional view showing the location of the greening pack or the recording rod on the lower front side of the geogrid of the construction method of the greening retaining wall according to an embodiment of the present invention, Figure 4 is a greening pack of the greening retaining wall construction method according to an embodiment of the present invention A side cross-sectional view showing a state of setting the mold and the soil bag at the rear end of the filling and the soil filling inside the soil bag, Figure 5 is removed from the outer surface of the soil bag mold during the construction method of the greening retaining wall according to an embodiment of the present invention Figure 6 is a side cross-sectional view showing a process, Figure 6 is a side cross-sectional view showing the first stage of the earth and sand completed by the construction method of the greening retaining wall according to an embodiment of the present invention, Figure 7 Fig. 8 is a side cross-sectional view showing a state in which a green pack is laminated and a geogrid is installed on the upper surface to form a second soil layer by the method of constructing the retaining wall according to the embodiment of the present invention. This is a side cross-sectional view showing the completion of the second stage on top of the first stage.
본 발명 녹화 옹벽(1)의 시공방법은, 녹화율을 보다 증대시킴으로써 녹화 옹벽의 구조를 더욱 견고하게 지속적으로 유지시키기 위한 시공방법으로, 도 2는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드가 포설되는 모습을 보인 요부확대 측단면도로, 시공되는 위치의 바닥면에 전면적으로 합성수지 재질의 격자형상 또는 반복되는 수평면 형상의 지오그리드(30)를 포설시켜서 불안정한 사면구간에서 활동저항 증대를 보강시키며, 토사(41,42)와의 상호 결속으로 마찰력을 증대시키고, 하부의 하중을 균등하게 분포시켜 부등침하를 방지시킨다. The construction method of the greening retaining wall 1 of the present invention is a construction method for maintaining the structure of the greening retaining wall more steadily by increasing the greening ratio, and FIG. 2 shows a geogrid of the greening retaining wall construction method according to the embodiment of the present invention. This is an enlarged side cross-sectional view showing the laid state, by installing a grid of geosynthetic resin or a horizontal
도 3은 본 발명 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도로, 상기 지오그리드(30)의 전방측 하부에 녹화팩(50)이나 녹화마대를 적층하고, 녹화팩(50)의 후방선단에서 지오그리드(30)는 상측으로 수직절곡하여 녹화팩(50) 상면에 위치된다. 상기 녹화팩(50)은 초본류 발아가 적절하게 이루어지도록 폴리에스터(polyester)나 플리프로필렌과 같은 합성섬유 재질 또는 유리섬유 등의 토목섬유로, 내부에는 토사(11)가 충진되어 대략 40∼55kg의 무게를 갖는다. 물은 자유로이 유,출입되는 반면, 녹화팩(50) 내부에 채워진 토립자의 유출은 방지되고, 투수를 유도하여 침식작용은 방지된다. Figure 3 is a side cross-sectional view showing the position of the greening pack or greening rod on the front lower portion of the geogrid in the construction method of the green retaining wall according to an embodiment of the present invention, the
도 4는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 녹화팩의 후방선단에 성형틀과 흙부대를 셋팅하고 흙부대 내측에 토사를 충진시키는 모습을 보인 측단면도로, 상기 지오그리드(30) 상면에서 상기 녹화팩(50)이나 녹화마대와 면접되게 상,하단이 개방된 사각통체 또는 사각틀체인 성형틀(20)을 위치시키고, 성형틀(20) 내측에 상단이 개방된 사각통체인 흙부대(10)를 셋팅하여 흙부대(10) 내부에 토사(11)를 충진시킨 후 다진다. 이때, 사각통체 또는 사각틀체인 성형틀(20)과 사각통체인 흙부대(10)는 설치 토압과 그리드 설치를 용이하게 하는 것으로, 전면측의 녹화팩(50)이 그 역할을 대신할 수 있기 때문에 흙부대(10)는 제외시킬 수도 있다. 또한, 성형틀(20)이나 흙부대(10)는 사각이 아니라 원통형상으로 형성시킬 수도 있음은 물론이다.Figure 4 is a side cross-sectional view showing the shape of the molding frame and the soil bag is set in the rear end of the greening pack and the soil filling in the soil bag in the construction method of the greening retaining wall according to an embodiment of the present invention, the
도 5는 본 발명 실시 예인 녹화 옹벽의 시공방법 중 성형틀을 흙부대 외측면 에서 제거하는 과정을 보인 측단면도로, 상기 성형틀(20)을 흙부대(10) 외측면에서 제거하고, 흙부대(10) 후방측에 인근까지 흙부대(10)의 중간높이로 토사(41)를 1차로 포설하여 다짐으로써 토사(41,42)의 첫째단(40) 쌓기를 준비한다. Figure 5 is a side cross-sectional view showing a process of removing the molding frame from the soil bag outer surface of the construction method of the greening retaining wall according to an embodiment of the present invention, removing the
도 6은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도로, 상기 지오그리드(30)의 선단을 전방측에서 후방측으로 수직절곡함으로써, 흙부대(10)의 하면과 정면 및 상면을 감싸면서 일단이 후방측으로 연장되고, 상기 녹화팩(50)이나 녹화마대를 지오그리드(30)와 체결클립이나 체결고리 등의 체결수단으로 체결고정시키며, 흙부대(10)의 후방측에서 흙부대(10)의 상단까지 토사(42)를 2차로 포설하여 다짐으로써 토사(41,42)의 첫째단(40) 쌓기를 완성한다. 이때, 매 단마다 별도의 다짐장비를 이용하여 다짐을 해주어야 함은 물론이다. 6 is a side cross-sectional view showing the first stage of the earth and sand is completed by the construction method of the greening retaining wall according to an embodiment of the present invention, by vertically bending the front end of the geogrid 30 from the front side to the rear side, One end is extended to the rear side while wrapping the lower surface and the front and the upper surface, and fastening and fixing the
도 7은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도로, 다시 첫째단(40)의 상면에 지오그리드(30)를 포설하고, 첫째단(40)의 녹화팩(50) 상부에 다시 녹화팩(50)을 적층시킨다. FIG. 7 is a side cross-sectional view showing a lamination of greening packs and laying a geogrid on an upper surface thereof to form a second soil layer by a method of constructing a greening retaining wall according to an embodiment of the present invention. 30 is laid, and the
도 8은 본 발명 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도로, 상기 성형틀(20)과 흙부대(10)를 하부 흙부대(10)의 상면에서 약간 후방측으로 셋팅하여 상기한 방법과 같이, 지오그리드(30)를 후방측으로 절첩하고 흙부대(10) 후방측으로 토사를 매립하여 다짐으로써 둘째단(40a)을 완성시키는 방법으로 다수개의 단을 필요한 녹화 옹벽(1)의 높이를 설정하여서 본 발명의 녹화 옹벽(1)이 완성된다. 8 is a side cross-sectional view showing a state in which the second stage is completed on the top of the first stage by the construction method of the greening retaining wall according to an embodiment of the present invention, the
도 9는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법에 따른 녹화 옹벽의 시공된 모습을 보인 사시도이고, 도 10은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 지오그리드가 포설되는 모습을 보인 요부확대 측단면도이며, 도 11은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도이고, 도 12는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 녹화팩이나 녹화마대 후방측에 토사를 1차로 충진시키는 모습을 보인 측단면도이며, 도 13은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도이고, 도 14는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도이고, 도 15는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도이다.9 is a perspective view showing the construction of the green retaining wall according to the construction method of the greening retaining wall according to another embodiment of the present invention, Figure 10 is a main portion enlarged side showing the geogrid of the construction method of the greening retaining wall according to another embodiment of the
본 발명 녹화 옹벽의 다른 시공방법은, 보다 저렴한 비용으로 녹화율을 보다 증대시킴으로써 녹화 옹벽의 구조를 더욱 견고하게 지속적으로 유지시키기 위한 시공방법이다.Another construction method of the greening retaining wall of the present invention is a construction method for maintaining the structure of the greening retaining wall more firmly by increasing the greening ratio at a lower cost.
먼저, 도 10과 같이, 시공되는 위치의 바닥면에 전면적으로 합성수지 재질의 격자형상 또는 반복되는 수평면 형상의 지오그리드(30)를 포설시켜서 불안정한 사 면구간에서 활동저항 증대를 보강시키며, 토사(41,42)와의 상호 결속으로 마찰력을 증대시키고, 하부의 하중을 균등하게 분포시켜 부등침하를 방지시킨다. First, as shown in Figure 10, by laying the
도 11은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 지오그리드의 전방측 하부에 녹화팩이나 녹화마대를 위치시키는 모습을 보인 측단면도로, 상기 지오그리드(30)의 전방측 하부에 녹화팩(50)이나 녹화마대를 적층하고, 녹화팩(50)의 후방선단에서 지오그리드(30)는 상측으로 수직절곡하여 녹화팩(50) 상면에 위치된다. 상기 녹화팩(50)은 초본류 발아가 적절하게 이루어지도록 폴리에스터(polyester)나 플리프로필렌과 같은 합성섬유 재질 또는 유리섬유 등의 토목섬유로, 내부에는 토사(11)가 충진되어 대략 40∼55kg의 무게를 갖는다. 물은 자유로이 유,출입되는 반면, 녹화팩(50) 내부에 채워진 토립자의 유출은 방지되고, 투수를 유도하여 침식작용은 방지된다. FIG. 11 is a side cross-sectional view showing the location of the greening pack or the greening rod under the front side of the geogrid in the construction method of the greening retaining wall according to another embodiment of the present invention, and the
도 12는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법 중 녹화팩의 후방선단에 토사를 1차로 충진시키는 모습을 보인 측단면도로, 상기 지오그리드(30) 상면에서 상기 녹화팩(50)이나 녹화마대 후방측에 인근까지 녹화팩(50)이나 녹화마대의 중간높이로 토사(41)를 1차로 포설하여 다짐으로써 토사(41,42)의 첫째단(40) 쌓기를 준비한다. 12 is a side cross-sectional view showing a state in which soil is firstly filled in the rear end of the greening pack in the construction method of the greening retaining wall according to another embodiment of the present invention, and the rear of the
도 13은 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 토사의 첫째단이 완성된 모습을 보인 측단면도로, 상기 지오그리드(30)의 선단을 전방측에서 후방측으로 수직절곡함으로써, 토사(42) 전방측의 하면과 정면 및 상면을 감싸면서 일단이 후방측으로 연장되고, 상기 녹화팩(50)이나 녹화마대를 지오그리드(30)와 체결 클립이나 체결고리 등의 체결수단으로 체결고정시키며, 녹화팩(50)이나 녹화마대의 후방측에서 녹화팩(50) 상단까지 토사(42)를 2차로 포설하여 다짐으로써 토사(41,42)의 첫째단(40) 쌓기를 완성한다. 이때, 매 단마다 별도의 다짐장비를 이용하여 다짐을 해주어야 함은 물론이다. FIG. 13 is a side cross-sectional view showing the first stage of the earth and sand completed by the method of constructing the greening retaining wall according to another embodiment of the present invention, wherein the front end of the
도 14는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 둘째단의 토사층을 형성하기 위해 녹화팩을 적층하고 그 상면에 지오그리드를 포설시킨 모습을 보인 측단면도로, 다시 첫째단(40)의 상면에 지오그리드(30)를 포설하고, 첫째단(40)의 녹화팩(50) 상부에 다시 녹화팩(50)을 적층시킨다. FIG. 14 is a side cross-sectional view illustrating a method of installing a retaining wall according to another embodiment of the present invention, in which a greening pack is stacked and a geogrid is installed on an upper surface thereof to form a soil layer of a second stage.
도 15는 본 발명 다른 실시 예인 녹화 옹벽의 시공방법으로 첫째단의 상부에 둘째단을 완성시킨 모습을 보인 측단면도로, 상기 녹화팩(50)이나 녹화마대를 하부 녹화팩(50)이나 녹화마대의 상면에서 약간 후방측으로 셋팅하여 상기한 방법과 같이, 지오그리드(30)를 후방측으로 절첩하고 녹화팩(50)이나 녹화마대 후방측으로 토사를 매립하여 다짐으로써 둘째단(40a)을 완성시키는 방법으로 다수개의 단을 필요한 녹화 옹벽(1)의 높이를 설정하여서 본 발명의 다른 실시 에인 녹화 옹벽(1a)이 완성된다. 15 is a side cross-sectional view showing a second stage completed on the top of the first stage by the construction method of the greening retaining wall according to another embodiment of the present invention. By setting the rear side slightly on the upper side of the method, the
이렇게 완성된 본 발명의 시공방법에 따른 녹화 옹벽(1)에는 시드 스프레이(seed spray)와 관수 및 방제를 하여 녹화팩(50)의 식생이 보다 원활하게 진행되도록 하면 된다. The greening retaining wall 1 according to the construction method of the present invention thus completed may be seed sprayed and watered and controlled to allow the vegetation of the
이렇게 이루어진 본 발명의 시공방법에 따른 녹화 옹벽(1a)은 콘크리트 및 철근을 사용하지 않고도 녹화팩(50)이나 녹화마대가 옹벽의 구조적인 기능과 강도를 지속적으로 유지할 수 있어 하천 유역 및 유수지역의 토사유실을 보다 효과적으로 방지할 수 있게 된다.Greening retaining wall (1a) according to the construction method of the present invention made so that the
이와 같이, 본 발명은 보강재가 외부로 노출되지 않아 파손으로 인한 염려가 전혀 없을 뿐만 아니라 손상이 억제되며, 랩핑이 매우 손쉬워 시공이 간편하며, 시공 후, 녹화율이 매우 뛰어나고, 콘크리트 및 철근을 사용하지 않고도 옹벽의 구조적인 기능과 강도를 지속적으로 유지할 수 있어 하천 유역 및 유수지역의 토사유실 방지공사에 매우 적합한 환경친화적인 효과가 있다.As described above, the present invention is not exposed to the outside of the reinforcement is not exposed to the damage at all, as well as damage is suppressed, the wrapping is very easy, easy construction, after construction, very excellent greening rate, using concrete and rebar It is possible to maintain the structural function and strength of retaining walls without the need for environmentally friendly effect.
본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형 실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by those skilled in the art without departing from the gist of the present invention as claimed in the claims. Of course, such changes will fall within the scope of the claims.
Claims (3)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060042207A KR100679873B1 (en) | 2006-05-11 | 2006-05-11 | Construction method of greening retaining wall |
PCT/KR2007/002270 WO2007133001A1 (en) | 2006-05-11 | 2007-05-09 | Construction method of breast wall for tree planting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060042207A KR100679873B1 (en) | 2006-05-11 | 2006-05-11 | Construction method of greening retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100679873B1 true KR100679873B1 (en) | 2007-02-07 |
Family
ID=38105659
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020060042207A Expired - Fee Related KR100679873B1 (en) | 2006-05-11 | 2006-05-11 | Construction method of greening retaining wall |
Country Status (2)
Country | Link |
---|---|
KR (1) | KR100679873B1 (en) |
WO (1) | WO2007133001A1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100929861B1 (en) | 2009-06-17 | 2009-12-04 | 허원석 | Construction method of cut slope reinforcement structure using articulated anchor |
KR101070701B1 (en) * | 2009-01-21 | 2011-10-07 | 주식회사 제이에이치 | Retaing wall for planting using frame structure |
KR101073972B1 (en) * | 2009-01-12 | 2011-10-17 | 주식회사 제이에이치 | External member, retaing wall for planting using the same and construction method thereof |
CN104452667A (en) * | 2014-11-26 | 2015-03-25 | 禹顺生态建设有限公司 | River channel reinforced retaining wall structure and construction method thereof |
CN113152319A (en) * | 2021-05-11 | 2021-07-23 | 安徽省交通规划设计研究总院股份有限公司 | Assembly type flexible drainage structure and construction method thereof |
CN113668598A (en) * | 2020-05-14 | 2021-11-19 | 中冶南方城市建设工程技术有限公司 | Green reinforced earth retaining wall structure and construction method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008062820B4 (en) * | 2008-12-23 | 2014-02-27 | Andreas Herold | inclined structure |
WO2017052473A1 (en) * | 2015-09-25 | 2017-03-30 | Housing And Development Board | A bag, system and method for using the same |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050066393A (en) * | 2003-12-26 | 2005-06-30 | 한국철도기술연구원 | Monofilament fiber compounded retaining wall and manufacture thereof |
KR20050110996A (en) * | 2004-05-20 | 2005-11-24 | 강수용 | Reinforced geotextile mat and reinforcement of earth slopes and embankments using the same |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
IT1290702B1 (en) * | 1997-02-25 | 1998-12-10 | Maccaferri Spa Off | ELEMENT FOR THE CONSTRUCTION OF STRUCTURES FOR COVERING, CONTAINMENT AND REINFORCEMENT OF LAND, IN PARTICULAR FOR |
US6893193B2 (en) * | 2002-01-30 | 2005-05-17 | B. Lanka Santha | Self-anchoring fiber block system |
-
2006
- 2006-05-11 KR KR1020060042207A patent/KR100679873B1/en not_active Expired - Fee Related
-
2007
- 2007-05-09 WO PCT/KR2007/002270 patent/WO2007133001A1/en active Application Filing
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050066393A (en) * | 2003-12-26 | 2005-06-30 | 한국철도기술연구원 | Monofilament fiber compounded retaining wall and manufacture thereof |
KR20050110996A (en) * | 2004-05-20 | 2005-11-24 | 강수용 | Reinforced geotextile mat and reinforcement of earth slopes and embankments using the same |
Non-Patent Citations (2)
Title |
---|
1020050066393 * |
1020050110996 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101073972B1 (en) * | 2009-01-12 | 2011-10-17 | 주식회사 제이에이치 | External member, retaing wall for planting using the same and construction method thereof |
KR101070701B1 (en) * | 2009-01-21 | 2011-10-07 | 주식회사 제이에이치 | Retaing wall for planting using frame structure |
KR100929861B1 (en) | 2009-06-17 | 2009-12-04 | 허원석 | Construction method of cut slope reinforcement structure using articulated anchor |
CN104452667A (en) * | 2014-11-26 | 2015-03-25 | 禹顺生态建设有限公司 | River channel reinforced retaining wall structure and construction method thereof |
CN113668598A (en) * | 2020-05-14 | 2021-11-19 | 中冶南方城市建设工程技术有限公司 | Green reinforced earth retaining wall structure and construction method |
CN113152319A (en) * | 2021-05-11 | 2021-07-23 | 安徽省交通规划设计研究总院股份有限公司 | Assembly type flexible drainage structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
WO2007133001A1 (en) | 2007-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100679873B1 (en) | Construction method of greening retaining wall | |
KR100924933B1 (en) | Construction method of natural friendly retaining wall using vegetation ton and fixing member and its installation structure | |
KR100752152B1 (en) | Construction method of greening retaining wall | |
US20070036615A1 (en) | Freestanding wall structures made using sandbags | |
KR100870150B1 (en) | Multifunctional reinforced earth retaining wall block and its construction method | |
KR20120021670A (en) | Reinforcement mattress gabion for afforestation environment and construction method | |
JP2012144937A (en) | Banking-reinforcing soil wall construction method and temporary holding material for banking-reinforcing soil wall for use in the same | |
JP5868352B2 (en) | How to lay a road on the slope | |
KR100815837B1 (en) | Construction method of eco-friendly reinforcement soil retaining wall using eco-friendly block with lower part open and inclined side plate rear part | |
KR100874961B1 (en) | Reinforced earth retaining wall wire mesh | |
KR101963362B1 (en) | Reinforced gabion retaining wall capable of completely drainage and construction method thereof | |
KR100889257B1 (en) | Prefabricated earth retaining wall using greening of front wall | |
KR102116085B1 (en) | A Eco-friendly retain wall structure | |
JP7109840B1 (en) | Embankment reinforced wall and construction method of embankment reinforced wall | |
KR101149038B1 (en) | Reinforcement construction method of poor subsoil by horizontal geogrid and vertical geogrid | |
KR100995097B1 (en) | Retaining Wall Block Construction Method | |
KR20190142927A (en) | Breast wall structure | |
JP2750363B2 (en) | Steep embankment | |
KR101288888B1 (en) | Restoration method of slope using geogrid and nail | |
KR100794669B1 (en) | Reinforced earth retaining wall wire mesh and construction method of reinforced earth retaining wall using the same | |
JPH0369721A (en) | Steep gradient banking | |
KR20080000510U (en) | Construction reinforcement rod | |
KR102549947B1 (en) | Eco-friendly vegetation wire mesh composite mat for reinforcement and restoration of slopes and its construction method | |
KR101252133B1 (en) | Construction structure and its method for geogrid of reinforced soil retaining wall | |
JPH0359222A (en) | Steep slope banking |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20060511 |
|
PA0201 | Request for examination | ||
N231 | Notification of change of applicant | ||
PN2301 | Change of applicant |
Patent event date: 20060615 Comment text: Notification of Change of Applicant Patent event code: PN23011R01D |
|
A302 | Request for accelerated examination | ||
PA0302 | Request for accelerated examination |
Patent event date: 20060619 Patent event code: PA03022R01D Comment text: Request for Accelerated Examination Patent event date: 20060511 Patent event code: PA03021R01I Comment text: Patent Application |
|
N231 | Notification of change of applicant | ||
PN2301 | Change of applicant |
Patent event date: 20060913 Comment text: Notification of Change of Applicant Patent event code: PN23011R01D |
|
E902 | Notification of reason for refusal | ||
PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20060926 Patent event code: PE09021S01D |
|
E701 | Decision to grant or registration of patent right | ||
PE0701 | Decision of registration |
Patent event code: PE07011S01D Comment text: Decision to Grant Registration Patent event date: 20070130 |
|
GRNT | Written decision to grant | ||
PR0701 | Registration of establishment |
Comment text: Registration of Establishment Patent event date: 20070201 Patent event code: PR07011E01D |
|
PR1002 | Payment of registration fee |
Payment date: 20070201 End annual number: 3 Start annual number: 1 |
|
PG1601 | Publication of registration | ||
PR1001 | Payment of annual fee |
Payment date: 20100126 Start annual number: 4 End annual number: 4 |
|
PR1001 | Payment of annual fee |
Payment date: 20110131 Start annual number: 5 End annual number: 5 |
|
FPAY | Annual fee payment |
Payment date: 20120202 Year of fee payment: 6 |
|
PR1001 | Payment of annual fee |
Payment date: 20120202 Start annual number: 6 End annual number: 6 |
|
LAPS | Lapse due to unpaid annual fee | ||
PC1903 | Unpaid annual fee |
Termination category: Default of registration fee Termination date: 20140109 |