JPS6041165B2 - Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. - Google Patents
Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.Info
- Publication number
- JPS6041165B2 JPS6041165B2 JP51147203A JP14720376A JPS6041165B2 JP S6041165 B2 JPS6041165 B2 JP S6041165B2 JP 51147203 A JP51147203 A JP 51147203A JP 14720376 A JP14720376 A JP 14720376A JP S6041165 B2 JPS6041165 B2 JP S6041165B2
- Authority
- JP
- Japan
- Prior art keywords
- truss
- superstructure
- concrete
- construction
- overhang
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
- E01D21/105—Balanced cantilevered erection
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】
本発明は上部に設けられ、側方に張出した車道板を有し
、特に閉塞した箱型横断面をもつ鉄筋コンクリートまた
はプレストレストコンクリート製橋梁構造を区分毎に片
持張出架設するための装置で、上部工の下側に設けられ
、既に完成した部分の上部工を越えて張出し、上部工の
ための型枠を支保し、相互に結合された縦桁及び建設す
べき袋出架設区分の下側にある榛桁上に静止していて且
つ走行装置によって、縦桁の両外側面に沿って配置され
、かつ既に完成した部分の上部工に固定されているレー
ルに沿って走行しうるように支持されている装置に関す
るものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a bridge structure made of reinforced concrete or prestressed concrete having a roadway plate provided on the upper part and extending laterally, and having a closed box-shaped cross section. A device for erection, provided on the underside of the superstructure, extending beyond the superstructure in already completed sections, supporting the formwork for the superstructure, and supporting the interconnected longitudinal girders and the structures to be erected. Along the rails that are stationary on the girder at the bottom of the blank erection section and are placed by means of running devices along both external sides of the longitudinal girder and fixed to the superstructure of the already completed section. It relates to a device that is supported so that it can be moved.
区分毎の片持張出架設による橋梁構造を建設するための
、いわゆる張出架設作業車と言い表わされており、橋梁
構造の既に完成した部分に対して支持され、この橋梁部
分から前方に張出し、そしてこの張出した部分において
橋梁上部工の下側に配置された作業用足場上に〜次のコ
ンクリート打ちする張出架設区分を建設するための型枠
を支持している装置は知られている。It is described as a so-called overhang construction work vehicle for constructing bridge structures by cantilever overhang erection for each section, and is supported on the already completed part of the bridge structure, and is used to construct bridge structures from this bridge part forward. The equipment supporting the formwork for constructing the overhang and the next concreting on the working scaffold placed on the underside of the bridge superstructure in this overhang is known. There is.
この種の張出架設作業車はなかんずく橋脚からそれぞれ
両側に張出し、最後にこれら片持梁を連結することによ
って橋梁構造として閉合することができるT型片持梁の
建設に適している。このような張出架設作業車の使用に
当っての欠点は、1本のT型片持梁を建設する2台の張
出架設作業車の内、常に一合は橋梁の一方の張出架設方
向で、他の一合はこの張出架設方向の反対方向に向って
作業しなければならないと言うことである。A projecting construction vehicle of this type is particularly suitable for the construction of T-shaped cantilevers which can extend from the piers on each side and which can finally be closed as a bridge structure by connecting these cantilevers. The disadvantage of using such overhang construction vehicles is that of the two overhang construction vehicles that are constructing one T-shaped cantilever, one of the vehicles is always used to construct one of the bridges. The other case is that you have to work in the opposite direction to this overhang erection direction.
橋梁上部工の下側に作業足場があり、そこで型枠が支保
されているという、この張出架設作業車の特殊な構造は
、この作業用足場によって橋梁の下側の空間が閉塞され
、そのためにこの張出架設作業車は多径間橋梁の橋脚を
通過することができないという事実を必然的に伴なつて
くる。更に〜既に完成した橋梁部分の上に支持され、次
の張出架設区分の建設のために張出すこの張出架設作業
車は、橋脚の直上に設けられる上部工部分及び少なくと
も当該の張出架設方向の最初の張出架設区分が既にコン
クリート打設されてはじめて、その橋脚部に梶付けるこ
とができる。この作業を実施するためには橋脚に取付け
られているか「地表に支持されていなければならない適
切な型枠を必要とする。橋梁上部工の既に完成した部分
に対するこの種張出架設作業車の支持は、上部工の上側
の車道板、車道板の下側または一部は車道板の上側、一
部は車道板の下側で行なうことができる。The special structure of this projecting construction vehicle is that the work scaffolding is located under the bridge superstructure, and the formwork is supported there. This entails the fact that this overhanging construction vehicle cannot pass over the piers of multi-span bridges. In addition, this overhang construction vehicle, which is supported on an already completed bridge section and is projected for the construction of the next overhang section, is capable of supporting at least the superstructure section provided directly above the piers and at least the corresponding overhang section. Only when the first overhang section in the direction has already been concreted can it be rammed onto its piers. Carrying out this work requires suitable formwork, which must be attached to the piers or supported on the ground surface. This can be done on the roadway board above the superstructure, below the roadway board, or partially above the roadway board, and partially below the roadway board.
そこで、プレストレストコンクリート橋梁を区分毎に片
持張出架設する工法の場合、車道板の下側に設けられ、
型枠を支持する張出架設用装置で、走行装置を所有し、
外側の腹板の外面に固定されているレール上を走行する
ものは知られている。橋梁構造の各側面には、夫々2基
の走行装置が配置されており「 コンクリート打設用足
場の張出している部分を介し、その前方のものに引張が
、その後方のものに圧縮が作用する。(ドイツ特許出願
公告公報第1152124号参照)桁橋の区分毎の片持
張出架設に対する他の公知の装置の場合、既に建設され
た上部工部分の上にトラス状支保工を設置し、これが片
持梁の先端を越えて張出し、この張出した部分で吊り村
により懸垂式のコンクリート打設用足場を支持する。Therefore, in the case of a construction method in which prestressed concrete bridges are constructed by cantilevering each section,
This is an overhanging erection device that supports the formwork and has a traveling device.
It is known to run on rails fixed to the outer surface of the outer belly plate. Two traveling devices are placed on each side of the bridge structure, and ``Through the overhanging part of the concrete casting scaffold, tension is applied to the thing in front of it, and compression is applied to the thing behind it.'' (cf. German Patent Application No. 1 152 124) In the case of other known devices for cantilever erection of sections of girder bridges, truss-like shoring is installed on the already erected superstructure sections; This overhangs beyond the tip of the cantilever beam, and at this overhang, a suspended concrete scaffolding is supported by a hanging village.
(ドイツ特許第973407号明細書)、この公知の装
置は、その前にコンクリート打設された張出架設区分に
ある走行用レールの上に戦っている前部主走行装置によ
って支持され、その後万端では浮き上り1こ対し上部工
に碇着される。最後に、車道板の下側にある上部工の全
てに対する外型枠がそれ自体剛でありかつ自ら支持する
ように構成されており、上部工の側壁に対する型枠の外
側面に取付けてある複数の縦桁で連結されている張出架
設用装置も公知である。(German Patent No. 973 407), this known device is supported by a front main running gear which rests on running rails in an overhanging section which has been concreted in front of it, and which is subsequently Then, one floating boat will be anchored on the superstructure. Finally, the outer formwork for all of the superstructures on the underside of the roadway board is itself rigid and self-supporting, with multiple Devices for overhanging erections which are connected by longitudinal girders are also known.
(DT−OSドイツ出願公開公報第2240678号)
この装置においては、前進の場合のコンクリート打設用
足場の張出している部分に基ずく荷重は、車道板を側方
からはさみ、走行装置を備えている門型ラーメンを介し
て車道板に支持され、一方その縦桁は後方機で下から車
道板の張出した部分に対して押し当てられる。この張出
架設作業車に関連し、桁高が変る橋桁を建設しうるよう
にするため「底型枠を横方向に曲げに剛なるようにし、
その高さを変更しうるように構成することもまた既に知
られているところである。更に、張出架設作業車を橋脚
部を通過させるために橋梁構造の両側に分割し、この分
けられた両部分を、車道の上部に設置されている補助桁
上を走行しうる捲上磯で吊り下げることができるように
縦方向中心軸で分割できるように作ることも知られてい
る。更に、この種の2台の張出架設作業車を用い、橋脚
直上部分の上部工施工区分のコンクリート打設を行なう
こともまた知られている。(DT-OS German Published Application No. 2240678)
In this device, the load based on the overhanging part of the concrete casting scaffold when moving forward is supported by the roadway board through gate-shaped rigid frames that sandwich the roadway board from the sides and are equipped with a traveling device. , while the longitudinal girder is pressed against the overhanging part of the roadway board from below by the rear machine. In connection with this overhanging construction vehicle, in order to be able to construct a bridge girder with varying girder heights, the bottom form was made to be rigid against lateral bending.
It is also already known to configure the device so that its height can be changed. Furthermore, in order to allow the overhang construction work vehicle to pass through the bridge piers, the bridge structure is divided into two parts, and both parts are suspended using hoisting rocks that can run on auxiliary girders installed at the top of the roadway. It is also known to make it so that it can be divided along the longitudinal central axis so that it can be lowered. Furthermore, it is also known to use two overhang construction vehicles of this type to place concrete in the superstructure construction section directly above the bridge piers.
(ドイツ特許出願公告公報第22私斑5号参照)。この
目的のため、この張出架設作業車の後方部分は側方に銚
関できるようになっており、それによってこの2台の張
出架設作業車は、それぞれの後方部分で相互に連結され
うるようになっている。この状態において2台の張出架
設作業車は改めて当該の橋脚の頭部に支持されている補
助桁に吊り下げられている。上記の諸種の張出架設装置
のそれぞれは、或る特定の目的に対して考案されたもの
であり、その目的に対してのみ利点を有している。(See German Patent Application Announcement No. 22 Private Patent No. 5). For this purpose, the rear part of the projector can be laterally connected, so that the two projectors can be interconnected at their respective rear parts. It looks like this. In this state, the two overhang construction vehicles are once again suspended from the auxiliary girder supported by the head of the relevant pier. Each of the various types of overhang construction devices described above has been devised for a specific purpose and has advantages only for that purpose.
最初に記述された様式の「下部を移動する張出架設作業
車は、その簡易な実施形態の結果、個々の張出架設区分
間の目地を鋸歯状に形成する場合に対してのみ適してい
るものであり、それによって、張出架設作業車の荷重を
含めず、その都度建設される張出架設区分の重量の大部
分が既に完成された上部工部分に直接伝達されることが
保証される。上部を移動する張出架設作業車の場合「
コンクリート打設用足場が吊り下げられる費用の高くつ
く支保工構造により「片持梁の先端にある建設場所に至
る通路が広範囲に遮断される。吊り村を用いてコンクリ
ート打設用足場を吊り下げることにより、曲つている橋
梁の建設は困難となる。と言うのは、吊り材は常に垂直
に設けられるからである。他の張出架設装置の場合「型
枠を剛にかつ自体支持するように形成することにより、
張出架設作業車は非常に重いものになる。即ちこの張出
架設作業車は斜めの外側腹板を有する箱桁の場合にのみ
使用され、この場合張出架設作業車を下方に下げるだけ
で既に脱型が行なわれる。本発明の課題は、当初に記載
した様式の張出架設装置を低減した建設経費で普遍的に
使用しうるように構成することにある。As a result of its simple embodiment, the first described type of undercarriage-moving overhanging vehicle is only suitable for creating serrated joints between the individual overhang sections. This ensures that the majority of the weight of each constructed overhang section, not including the loads of the overhang construction vehicle, is transferred directly to the already completed superstructure section. .In the case of an overhanging construction vehicle that moves the upper part,
The expensive shoring structure from which the concrete pouring scaffold is suspended "cuts off a large area of the path leading to the construction site at the end of the cantilever. Hanging villages are used to suspend the concrete pour scaffold. This makes the construction of curved bridges difficult, since the suspension members are always installed vertically. By forming
Overhang construction vehicles are extremely heavy. In other words, this overhanging vehicle is used only for box girders with oblique outer panels, in which case demolding is already carried out simply by lowering the overhanging vehicle. SUMMARY OF THE INVENTION The object of the invention is to design an overhanging installation of the type originally described in such a way that it can be used universally with reduced construction costs.
この課題は、本発明によれば以下のように解決される。According to the present invention, this problem is solved as follows.
即ちコンクリート打設用足場のための縦桁が上部工の縦
桁腹板の両側に設けられた、横桁によって場合によって
は斜補剛材に結合されて立体的な支保工になっている壁
状のトラス桁であり、トラス桁の下部領域にコンクリー
ト打設用足場が固定されており、トラス桁の各々は張出
している領域に垂直部村をもつ少くとも一つのほぼ方形
のトラス面を有し「張出架設方向で後方の範囲に上部の
水平部材をもつ三角形トラスを有し、走行装置が走行レ
ールに対して支承するために三角形トラスの後方の節点
部と、方形トラスと三角形トラスの間の上部結合節点部
とに設置されている。この支保構造は、その各部材が張
出した範囲において垂直部材をもつ少なくとも一個の〜
基本的には正方形のトラス面を、そして張出架設方向に
対して後方の範囲において、上方に節点が設けられ、先
のトラス面に結合する三角形トラスを構成する壁状のト
ラス桁として形成されると好都合である。In other words, a wall in which longitudinal girders for scaffolding for concrete pouring are provided on both sides of the longitudinal girder base plate of the superstructure, and in some cases are connected to diagonal stiffeners by cross girders to form a three-dimensional support. a truss girder with a concrete casting scaffold fixed to the lower area of the truss girder, each truss girder having at least one substantially rectangular truss face with a vertical section in the overhanging area; "It has a triangular truss with an upper horizontal member in the rear range in the overhang construction direction, and the rear node part of the triangular truss, the square truss and the triangular truss are used to support the traveling device against the traveling rail. The support structure comprises at least one ...
Basically, it is formed as a wall-like truss girder with a square truss surface and, in the rear range with respect to the overhang erection direction, a node is provided above and forms a triangular truss that connects to the previous truss surface. It is convenient.
走行用レールに対して支持するための走行装置は、架設
装置のそれぞれの側において三角形トラスの節点及び正
方形トラスと三角形トラスとの間の上部結合接点に設け
ると便利である。三角形トラスにおいては「斜部材が目
的に従ってその両端でヒンジ状に結合されており、一方
この斜部材ならびに水平部材はその長さを変えうるよう
にすることができる。この際、斜部材はテレスコープ状
のパイプとして形成することができ、一方水平部村は上
部の結合節点に取りつけられたガイド中を水平に糟勤し
うるようにすることができる。コンクリート打設用足場
は、支保構造に対し〜その高さを変えようとすることが
できる。Conveniently, running devices for support against the running rails are provided on each side of the erection device at the nodes of the triangular truss and at the upper joint contacts between the square truss and the triangular truss. In a triangular truss, "the diagonal members are hinged at their ends according to the purpose, while the diagonal members as well as the horizontal members can be of variable length. In this case, the diagonal members are telescoped. It can be formed as a shaped pipe, while the horizontal section can be run horizontally in guides attached to the upper connection nodes. ~ You can try to change its height.
ここで、コンクリート打設用足場の横桁を、その両端に
ガイドを取りつけ、垂直なガイド用レールに対し支保構
造に沿って階動するように設置された構成とすることが
できる。ガイド筒はトラスの垂直部材がガイドレールと
して掴まれるような摺動筒として形成されると便利であ
る。全体の装置は「橋脚を越して次に移送するために縦
方向中心軸で分割するようにすることができる。Here, the cross beam of the scaffold for concrete placement can be configured to have guides attached to both ends thereof, and to be installed so as to move step by step along the supporting structure with respect to the vertical guide rail. Conveniently, the guide tube is designed as a sliding tube in which the vertical members of the truss can be gripped as guide rails. The entire device can be split along the central longitudinal axis for subsequent transport across the piers.
コンクリート打設用足場の藤桁は、またガイドにヒンジ
状に結合することもできる。更に、上部工の上方に配置
されている補助桁上を走行する移送装置からの把手に対
し上部工を側方からはさむ門型ラーメンを支保構造に取
付けることができることは、それ自体知られている処で
ある。The rattan girder of the concrete scaffolding can also be hinged to the guide. Furthermore, it is known per se that it is possible to attach to the supporting structure a gate-shaped rigid frame that sandwiches the superstructure from the side against a handle from a transfer device that runs on an auxiliary girder arranged above the superstructure. It is a place.
この発明性のある装置の長所は、先ず橋梁の側方に設け
られ、横桁及び斜葱剛材を有する支保構造が、もっぱら
橋梁上部工の下側に位置して車道上の範囲には侵害しな
い立体的な構造を提示し、その上ならびにその中に上部
工に対する実際的な任意の型枠構成材が設置されうる点
にある。The advantage of this inventive device is that the support structure, which is installed on the side of the bridge and has crossbeams and diagonal stiffeners, is located exclusively under the bridge superstructure and does not interfere with the area above the roadway. The point is that any practical formwork constituent material for the superstructure can be installed on and within the three-dimensional structure.
際立った長所は、支保構造を壁状のトラス桁として形成
することであり、これにより引張弦材、圧縮弦材及び斜
材を大きく拡げる結果コンクリート打設の荷重を受け持
ち、既に完成した上部工部分へ伝達するための非常に軽
量でしかもことのほか剛な構造が得られる。支保構造の
後方部分がテレスコープ状になっていることにより「
2台のかかる装置を後方で相互に結合する可能性が生ず
る。A distinct advantage is the construction of the support structure as a wall-like truss girder, which allows the tension chords, compression chords and diagonals to be widened to a large extent so that they can take on the loads of the concrete pouring and thus extend the already completed superstructure sections. This results in a very lightweight yet exceptionally rigid structure for transmitting signals to the The rear part of the support structure is telescoped, so
The possibility arises of interconnecting two such devices at the rear.
この結合が引張材及び圧縮材ならびに斜補剛材を介して
行なわれるならば「 2台のかかる装鷹は1ッの曲げに
剛な支保横に合体し、補助桁に負担をかけることなくそ
の荷重を直接橋脚に伝えることができ「従って補助桁は
荷の加わっていない張出架設装置の移送に対してのみ役
割を果し、その結果軽量なものにすることができる。こ
の発明性のある装魔の更に詳細なる特長的な有益な性能
は、図面中に示される実施例についての以下の記述によ
って明らかである。If this connection is made through tension and compression members as well as diagonal stiffeners, then two such riggers can be joined together on one side of a rigid support in one bend, without straining the auxiliary girder. Loads can be transferred directly to the piers, so that the auxiliary girder only plays a role in transporting the unloaded overhanging equipment and can therefore be lightweight. Further details, characteristic and advantageous performance of the enchantment will become apparent from the following description of the exemplary embodiments shown in the drawings.
第la図および第lb図においては、多摩間の橋梁構造
の建設進行中の特徴的なこッの建設状態が概観図的に示
されている。In Figures 1a and 1b, the characteristic construction status of the bridge structure between Tama during construction is schematically shown.
第la図は、上部工2の既に建設された部分がその上に
載っている橋脚軍を示す。上部工2は「張出架設作業車
」と称される2台の張出架設装置1及び0の助けをかり
、個々の張出架設区分2a,2b,2c,2dといった
ように順次に建設される。上部工の既に完成した部分に
支持されている2台の張出架設作業車1及び瓜ま、丁度
施工区分2dを建設するための位置にある。第lb図に
おいては、橋梁構造の次の橋脚3での建設開始の状態が
示されている。Figure la shows the pier army on which the already erected part of the superstructure 2 rests. The superstructure 2 is constructed successively into individual overhang sections 2a, 2b, 2c, and 2d with the help of two overhang erection devices 1 and 0 called "overhang erection work vehicles." Ru. The two overhang construction vehicles 1 and the gourd, supported on the already completed part of the superstructure, are just in position for constructing the construction section 2d. In FIG. 1b, the construction of the next pier 3 of the bridge structure is shown starting.
ここにおいては、後程更に説明を加えるが、2台の張出
架設作業車1及び山まその後端部で相互に結合し、橋脚
直上の最初の張出架設区分2aの建設のための役割りを
果す。第2図においては、第la図から判るように張出
架設区分2dを建設する位置にある張出架設作業車1が
拡大した尺度で示されている。Here, although further explanation will be added later, two overhang construction work vehicles 1 are connected to each other at the rear end of the crest, and play a role in the construction of the first overhang construction section 2a directly above the bridge pier. accomplish In FIG. 2, the cantilever construction vehicle 1 is shown on an enlarged scale in the position for constructing the cantilever construction section 2d, as can be seen from FIG.
張出架設作業車1は二ッの壁状をしたトラス桁4a及び
母bからなり、これらは上部工2の外側両側面に設魔さ
れている。(第3図及び第4図)トラス桁4a及び4b
の基本的な支持構成部材はほぼ正方形のトラス面を形成
している前端の垂直部材5及び後端の垂直部材6、下部
の水平部材7、上部の水平部材8及び斜部村9であり、
そしてこれらの後方に接続し、水平部材10及び斜めの
パイプ支裸核11から構成される三角形のトラス面であ
る。パイプ支保材11は後方の上部節点12及び下部の
節点13においてヒンジ状に結合されており、かつこれ
は11a及び11bのニッの部分よりなり、テレスコ−
フ。状に相互に摺り動かすことができるようになってい
る。上部中央のトラス節点14部では橋状のガイド15
が取付けられており、上部後方の水平部村10が水平方
向に摺り動かすことができるようになっている。2個の
トラス桁4a及び4bは上部工藤断面の下側で前方の底
型枠用横桁16及び後方の底型枠用横桁17により相互
に結合されている。The overhang construction vehicle 1 consists of two wall-shaped truss girders 4a and base b, which are installed on both outer sides of the superstructure 2. (Figures 3 and 4) Truss girders 4a and 4b
The basic supporting components are a front end vertical member 5 and a rear end vertical member 6, a lower horizontal member 7, an upper horizontal member 8 and a diagonal village 9 forming a substantially square truss surface;
Connected to the rear of these is a triangular truss surface composed of a horizontal member 10 and an oblique pipe support core 11. The pipe support 11 is hinged at an upper node 12 and a lower node 13 at the rear, and this consists of the gap portions 11a and 11b, and is telescopic.
centre. They can be slid against each other in a shape. A bridge-like guide 15 is installed at the truss node 14 in the upper center.
is attached so that the horizontal part 10 at the rear of the upper part can be slid in the horizontal direction. The two truss girders 4a and 4b are connected to each other at the lower side of the upper Kudo section by a front cross-beam 16 for bottom formwork and a cross-beam 17 for bottom formwork at the rear.
更に追加の橘岡山を行なうために、建設すべき張出架設
区分の前面で垂直部村5によって定められる橋梁横断面
内に斜め支持材(プレーシング)が取付けられる。これ
は図を見やすくするために省略されている。張出架設作
業車の前面、即ち建設すべき橋梁部分の前面には作業用
足場18を備えた作業用支保工がある。種々の補助的小
部材が輪郭だけ示されるが、詳細な説明は必要としない
。トラス桁4a及び4bの上部範囲において、即ち垂直
部材6の上端、筒状のガイド15の部分及び後方の節」
点12部分に走行装置が設けられており、これを用いて
張出架設作業車は走行用レール19に沿って走行しうる
ようになっている。In order to carry out an additional Tachibana Okayama, diagonal supports (placing) are installed in the bridge cross-section defined by the vertical section 5 in front of the overhang section to be constructed. This has been omitted for clarity. At the front of the overhang construction vehicle, that is, at the front of the bridge section to be constructed, there is a work shoring structure equipped with a work scaffold 18. Various auxiliary components are shown only in outline and do not require detailed explanation. In the upper region of the truss girders 4a and 4b, i.e. the upper end of the vertical member 6, the part of the cylindrical guide 15 and the rear node.
A traveling device is provided at the point 12, and the overhang construction work vehicle can travel along the traveling rail 19 using this.
走行用レール19は上部工横断面の外側の側面で車道板
21の張出部分20の下側の位置に固定されている。走
行用レール19の下フランジに沿って走行する走行車輪
22及びそれによって張出架設作業車1が後方の節点1
2の範囲において走行用レール19の下面に対して支持
される支持車輪23による荷重に対応して、これは引張
部材24を介して上部工に吊り下げられかつ油圧ジャッ
キ28を介して車道板21の張出した部分20の下面に
対して支持される。第2図から第4図に示されているコ
ンクリートの打設状態において、狼出架設区分2dの重
量による全荷重が加わる場合、走行用レール19及びそ
れの吊り材24に加わっている荷重を除去するために、
張出架設作業車は一方が後方の底型枠横桁17に固定さ
れ、上部工を貫通して上方に斜めに、そして車道板21
の上面にある短い横桁27に碇着されている引張部材2
6を介して吊り下げられる。The traveling rail 19 is fixed at a position below the overhanging portion 20 of the roadway board 21 on the outer side surface of the cross section of the superstructure. The running wheels 22 run along the lower flange of the running rail 19, and thereby the overhanging construction vehicle 1 moves to the rear node 1.
Corresponding to the load exerted by the support wheels 23 which are supported against the underside of the running rail 19 in the area 2, this is suspended on the superstructure via tension members 24 and is applied to the roadway board 21 via hydraulic jacks 28. It is supported against the lower surface of the overhanging portion 20 of. In the concrete placement state shown in FIGS. 2 to 4, when the full load due to the weight of the exposed construction section 2d is applied, the load applied to the running rail 19 and its hanging material 24 is removed. In order to
The overhanging construction vehicle is fixed at one end to the rear bottom formwork crossbeam 17, passes through the superstructure, diagonally upwards, and then connects to the roadway board 21.
Tension members 2 anchored to short crossbeams 27 on the top surface of
6.
(第4図).油圧ジャッキ28を介し張出架設作業車の
後方の支持の荷重を除去するために引張部材25が上部
工横断面の下緑30に対して緊張される。コンクリート
打設のために底型枠用0足場31上に上部工に対する型
枠の部分が組立てられている。この型枠は基本的には任
意に形成されうるものであり、従ってここでは詳細に記
述する必要はない。張出架設区分のコンクリートが硬化
し、型枠部タ分がコンクリートから剥離した後、次に張
出架設作業車は、張出架設区分の長さだけ新しい施工開
始位置に前進する。(Figure 4). Via a hydraulic jack 28, a tension member 25 is tensioned against the lower green 30 of the superstructure cross section in order to relieve the load of the rear support of the projecting construction vehicle. For concrete pouring, the formwork portion for the superstructure is assembled on the bottom formwork scaffolding 31. This formwork can basically be formed arbitrarily and therefore does not need to be described in detail here. After the concrete in the overhang section has hardened and the formwork section has peeled off from the concrete, the overhang construction vehicle then moves forward by the length of the overhang section to a new construction start position.
この際、張出架設作業車は、走行車輪22を介し、走行
用レール19の下フランジに吊り下げられ、かつ支持車
輪23を介して0走行用レール19の下フランジに対し
て支持される。走行移動は、油圧ジャッキとフックを備
え、その一端は水平部材8に、他端は走行用レール19
に支持されている推進装置32を用いて行なわれる。こ
の推進装置32は逆のやり方で走行用レール19の前進
のためにも使用される。そのためには、上部工に対して
張出架設作業車を固定した後、走行用レール19は支持
車輪23及び走行車輪22の範囲にある図示されていな
い支持車輪上に下げられる。(第2図)第la図に示さ
れている建設状態をこえてその後の建設の進行に対して
稼働していた張出架設作業車0が後方の軽間を閉塞して
終うと直ちに張出架設作業車1及び川ま次の橋脚部に移
しかえられなければならない。At this time, the overhang construction work vehicle is suspended from the lower flange of the running rail 19 via the running wheels 22, and is supported by the lower flange of the zero running rail 19 via the support wheels 23. For traveling movement, a hydraulic jack and a hook are provided, one end of which is attached to the horizontal member 8, and the other end of which is attached to the traveling rail 19.
This is carried out using a propulsion device 32 supported by. This propulsion device 32 is also used for the advancement of the running rail 19 in a reverse manner. To this end, after fixing the overhanging vehicle to the superstructure, the running rail 19 is lowered onto support wheels (not shown) in the area of support wheels 23 and running wheels 22. (Fig. 2) As soon as the construction work vehicle 0, which was in operation after the construction progressed beyond the construction state shown in Fig. It must be moved to the construction vehicle 1 and the pier at Kawamatsugi.
この目的に対してのみトラス桁4a及び4bに、上部工
務断面を側方からはさんでいる門型ラーメン33が設備
されている。縦桁35によって相互に連結されている上
部の腕木状部材34に吊り部材を取り付けることが出来
、これを用いて張出架設作業車を走行台車に吊り下げる
ことができる。この走行台車は図には示されていないが
、上部工2の上側にあって既に完成した片持梁と次の橋
脚間の径闇を跨いで架橋されている補助桁の上を走行し
うるようになっている。それによって各張出架設作業車
は橋脚を通過することができ、2本の底型枠用横桁16
及び17は橋梁縦方向軸X−Xで分割されるようになっ
ている。2本の底型枠用横桁16及び17はそれぞれの
外側の端部においてヒンジ36を用いてトラス桁4a及
び4bに連結されているので、中央の結合を解放するこ
とによって生ずる半分の部分は、このヒンジを中心とし
て外側に聯関させることができる。第lb図に概観図的
に示されている建設状態、即ち橋脚の直上部分の上部工
施工区分2aの建設のために、それらの後方が一体に連
結されている2台の張出架設作業車1及びロが使用され
ている状態は第5図に大きな縮尺で示されている。For this purpose only, the truss girders 4a and 4b are provided with gate-shaped rigid members 33 that sandwich the upper construction section from the sides. Hanging members can be attached to the upper cross-members 34, which are interconnected by the longitudinal beams 35, by means of which the projecting construction vehicle can be suspended from the carriage. Although this traveling bogie is not shown in the diagram, it can run on the auxiliary girder that is located above the superstructure 2 and spans the gap between the already completed cantilever and the next pier. It looks like this. This allows each overhanging construction vehicle to pass through the piers and the two bottom formwork crossbeams 16.
and 17 are divided by the bridge longitudinal axis XX. Since the two bottom formwork cross beams 16 and 17 are connected to the truss beams 4a and 4b by means of hinges 36 at their respective outer ends, the halves created by releasing the central connection are , can be connected to the outside around this hinge. For the construction state schematically shown in Figure lb, that is, for the construction of superstructure section 2a directly above the pier, two overhanging construction vehicles are connected together at their rear ends. 1 and 2 in use are shown on a larger scale in FIG.
この位置では、張出架設作業車の後方の水平部材10は
筒状のガイド16の内側に摺り動かすことによって内部
に押し込まれている。同時にパイプ支持材亀1も短くさ
れ、節点12及び13の範囲内でヒンジを中心として旋
回している。両方の節点13の間には圧縮部村36が取
付けられ、両方の筒状のガィド‘ま引張部材37によっ
て連結される。追加して斜補剛材38が取付けられる。
この状態においては2台の張出架設作業車1及び山ま、
曲げに対して剛に相互に結合される。張出架設作業車は
その垂直力を中央の垂直部材6の下側で橋脚3の頭部に
直接伝達するが、この際垂直部村は橋脚頭の上の座板3
9の上に据置かれる。この位置から、2台の張出架設作
業車1及びロを前進させる場合には、張出架設区分2a
が建設された後、両方の後方にある三角形トラスを形成
する部村10及び11が再び第2図に明示されている位
贋に引伸ばされる。第6図から第9図に示されている張
出架設作業車の施工形態の場合、型枠を支保するコンク
リ−ト打節用足場40はトラス桁4a及び4b、底部横
桁41及び42、及び前面の斜補剛材43から形成され
る張出架設作業車の支保用骨組の内側で高さを変えうる
ように設置されている。In this position, the rear horizontal member 10 of the overhanging vehicle is pushed into the interior of the cylindrical guide 16 by sliding it inside. At the same time, the pipe support 1 is also shortened and pivoted about the hinge within the nodes 12 and 13. A compression section 36 is mounted between the two nodes 13 and is connected to the two cylindrical guides by a tension member 37 . Additionally, diagonal stiffeners 38 are installed.
In this state, two overhang construction work vehicles 1 and a mountain,
They are interconnected rigidly against bending. The overhang construction vehicle transmits its vertical force directly to the head of the pier 3 under the central vertical member 6, and in this case, the vertical member is connected to the seat plate 3 above the pier head.
It is placed on top of 9. When moving the two overhang construction vehicles 1 and 2 forward from this position, the overhang construction section 2a
After this has been erected, the sections 10 and 11 forming the two rear triangular trusses are stretched again to the dimensions shown in FIG. In the case of the construction form of the overhanging construction work vehicle shown in FIGS. 6 to 9, the concrete hammering scaffold 40 supporting the formwork consists of truss girders 4a and 4b, bottom cross beams 41 and 42, and It is installed so that its height can be changed inside the supporting framework of the overhanging construction vehicle, which is formed from the front diagonal stiffener 43.
このようにすることによって桁高の変る橋梁構造を建設
することができる可能性が現われてくる。ここではコン
クリート打設用足場40は、前方の足場用横桁40aと
後方の足場用横桁40bとで支えられている。By doing this, it becomes possible to construct a bridge structure with variable girder height. Here, the concrete casting scaffold 40 is supported by a front scaffold cross beam 40a and a rear scaffold cross beam 40b.
両者ともその織部にガイド44aならびに44bが取付
けられており、これらは前方の垂直部材45及び後方の
垂直部材46を掴み、そしてこの部で滑敷できる。機桁
40a及び40bに、またはガイド44a及び44bに
長さが変えられ、その短縮によってコンクリート打設用
足場40を持ち上げることができる引張部材47が取付
けられる。この種のコンクリート打該用足場40の高さ
の可変性は、上部工より幅広い橋脚部を通過することが
できるという前提の下に生み出されたものである。Both have guides 44a and 44b attached to their weavings, which can grip the front vertical member 45 and the rear vertical member 46 and slide in this area. A tension member 47 is attached to the machine girders 40a and 40b or to the guides 44a and 44b, the length of which can be changed and whose length can be shortened to lift the concrete casting scaffold 40. This type of height variability of the concrete pouring scaffold 40 was created on the premise that it can pass through a bridge pier that is wider than the superstructure.
このような事例はt例えばアウトバーンの橋梁がその例
に該当するが、ーッの連続した橋脚の上に2個の分割し
た上部工横断面が上載するような場合に生ずる。張出架
設作業車に関し、第2図から第4図に従って記述された
ようにコンクリート打設用足場の底部機桁が縦方向中心
軸で分割されるようになっているならば、第6図から第
8図に示した張出架設作業車の場合、コンクリート打設
用足場40の両方に分れた半分の部分はガイド44a及
び44bに取付けられたヒンジ48の図りで隣開し、吊
り材49を用いて側方で上方に引き上げることができる
。この際ガイド44a及び44bは垂直部村45及び4
6に沿ってコンクリート打設用足場40の高さ移動に従
って糟動する(第9図及び第10図)。Such a case occurs, for example, in an autobahn bridge, where two divided superstructure cross sections are placed on top of a continuous bridge pier. Regarding the overhanging construction vehicle, if the bottom machine girder of the concrete casting scaffold is divided along the longitudinal center axis as described according to Figs. 2 to 4, then from Fig. 6 In the case of the overhanging construction vehicle shown in FIG. 8, both halves of the concrete casting scaffold 40 are opened next to each other at the hinges 48 attached to the guides 44a and 44b, and the hanging members 49 It can be pulled up on the sides using the At this time, the guides 44a and 44b are connected to the vertical sections 45 and 4.
6 (FIGS. 9 and 10) according to the height movement of the concrete casting scaffold 40.
第la図及び第lb図は橋梁構造の建設中における二ッ
の特徴的な建設状態の側面図、第2図は本発明による張
出架設装置の最初の施工形態の側面図、第3図は第2図
のm−m線に沿った横断面図、第4図は第2図のN−W
線に沿った横断面図、第6図は橋脚の直上に設けられる
上部工部分の建設中における2台の相互に連結した張出
架設装置、第6図はこの張出架設装置の引き続いた施工
形態の側面図、第7図及び第8図は第6図の肌−脚線及
び風一畑線に沿った部分横断面図、第9図及び第10図
は、幅広い橋脚部を通過する際の張出架設装置の第7図
及び第8図に対応する横断面図。
図中符号は16,17…・・・前方および後方底型枠用
横桁、19・・・・・・走行用レール、22,23・・
・・・・走行車輪。
ガヲ.れ
力9 フあ
ヵ9.2
行9・7
勺9.8
丹9.3
力9.夕
分9.あ
力9.5
カタ‐9
布9.のFigures 1A and 1B are side views of two characteristic construction states during construction of a bridge structure, Figure 2 is a side view of the first construction form of the overhang erection device according to the present invention, and Figure 3 is A cross-sectional view taken along line mm in Figure 2, and Figure 4 is a cross-sectional view along line N-W in Figure 2.
A cross-sectional view along a line, Figure 6 shows two interconnected cantilever construction equipment during the construction of the superstructure section directly above the pier, and Figure 6 shows the subsequent construction of this cantilever construction equipment. Figures 7 and 8 are partial cross-sectional views taken along the skin-leg line and Kazeichibata line in Figure 6. Figures 9 and 10 are cross-sectional views taken when passing through a wide pier. FIG. 8 is a cross-sectional view corresponding to FIGS. 7 and 8 of the overhang construction device. The symbols in the figure are 16, 17... cross beams for front and rear bottom formwork, 19... running rails, 22, 23...
...Running wheels. Gawo. Re force 9 Fuaka 9.2 Line 9.7 庺 9.8 Tan 9.3 Force 9. Evening 9. Atari 9.5 Kata-9 Cloth 9. of
Claims (1)
に閉塞した箱型横断面をもつ鉄筋コンクリートまたはプ
レストレストコンクリート製橋梁構造を区分毎に片持張
出架設するため、上部工の下側に設けられ、上部工の既
に完成した部分を越えて張出し、上部工のための型枠を
支保し、相互に結合された縦桁及び建設すべき張出架設
区分の下側にある横桁上に静止していて且つ走行装置に
よつて、上部工の縦桁腹板の両外側面に沿つて配置され
、かつ上部工の既に完成した部分に固定されている走行
用レールに沿つて走行しうるように支持されているコン
クリート打設用足場から成る装置において、コンクリー
ト打設用足場のための縦桁が上部工の縦桁腹板の両側に
設けられた、横桁16,17;41,42によつて場合
によつては斜補剛材に結合されて立体的な支保工になつ
ている壁状のトラス桁4aと4bであり、トラス桁の下
部領域にコンクリート打設用足場が固定されており、ト
ラス桁の各々は張出している領域に垂直部材5,6;4
5,46をもつ少くとも一つのはゞ方形のトラス面を有
し、張出架設方向で後方の範囲に上部の水平部材10を
もつ三角形トラスを有し、走行装置22,23が走行レ
ール19に対して支承するために三角形トラスの後方の
節点12部と、方形トラスと三角形トラスの間の上部結
合節点14部とに設置されていることを特徴とする装置
。 2 支保構造が壁状のトラス桁4a,4bとして構成さ
れており、その各々が張出している範囲において垂直部
材5,6をもつ少なくとも1個の基本的には正方形のト
ラス面を、そして張出架設方向に対して後方にあたる範
囲において上部に節点14が設けられ先のトラス面に結
合した三角形のトラス面を構成することを特徴とする請
求範囲1に記載の装置。 3 走行用レール19に支持させるために装置の各側面
において三角形トラス面の節点、及び正方形トラスと三
角形トラスとの間の上部結合節点14部に走行装置22
及び23が設置されていることを特徴とする特許請求の
範囲1或いは2に記載の装置。 4 夫々の三角形トラスにおいて斜部材11がその両端
でヒンジ状に結合されており、この斜部材11ならびに
水平部材10がその長さを変えることができるようにな
つていることを特徴とする特許請求範囲1から3までの
いずれかの項に記載の装置。 5 斜部材11がテレスコープ状のパイプで形成されて
いることを特徴とする特許請求範囲4に記載の装置。 6 水平部材10が上部の結合節点14に取りつけられ
ているガイド15中に水平に摺り動かしうることを特徴
とする特許請求範囲4或るいは5に記載の装置。 7 支保構造4a,4bに対してコンクリート打設用足
場がその高さを変えうるようになつていることを特徴と
する特許請求範囲1から6までのいずれかの項に記載の
装置。 8 コンクリート打設用足場40用横桁41,42は、
その両端にガイドが取りつけられており、垂直のガイド
レールに対し支保構造に沿つて滑動するように配置され
ていることを特徴とする特許請求範囲7に記載の装置。 9 ガイドは、摺動筒44a,44bとして形成され、
トラスの垂直部材5,6を、ガイドレールとして掴んで
いることを特徴とする特許請求範囲7或るいは8に記載
の装置。10 全体の装置を橋脚を越えて先に移送する
ために縦方向中心軸で分割することができるようになつ
ていることを特徴とする特許請求の範囲1から9までの
いずれかの項に記載の装置。 11 コンクリート打設用足場40の横桁41,42が
ガイド部でヒンジ状に結合しうるようになつていること
を特徴とする特許請求範囲10に記載の装置。 12 上部工の上方に設置されている補助桁上を走行す
る移送装置からの把手に対し、上部工を側方からはさむ
門型ラーメン34を支保構造に取りつけることを特徴と
する特許請求範囲1から11までのいずれかの項に記載
の装置。[Scope of Claims] 1. For constructing a bridge structure made of reinforced concrete or prestressed concrete with a roadway plate provided at the upper part and extending laterally, and having a particularly closed box-shaped cross section, with a cantilever for each section. , provided on the underside of the superstructure and extending beyond the already completed part of the superstructure, supporting the formwork for the superstructure and under the interconnected longitudinal girders and overhang sections to be constructed. Traveling devices which are stationary on the side transverse beams and which are arranged along both outer sides of the longitudinal girder sides of the superstructure by means of running devices and which are fixed to already completed parts of the superstructure. In a device consisting of a concrete casting scaffold supported so as to be able to run along a rail, a transverse beam in which the longitudinal girders for the concrete casting scaffold are provided on both sides of the longitudinal girder base plate of the superstructure. 16, 17; wall-shaped truss girders 4a and 4b which are sometimes connected to diagonal stiffeners by 41, 42 to form a three-dimensional support, with concrete in the lower area of the truss girder. The pouring scaffold is fixed and each truss girder has vertical members 5, 6; 4 in its overhanging area.
At least one with 5, 46 has a rectangular truss surface and has a triangular truss with an upper horizontal member 10 in the rear region in the direction of the overhang, and the running devices 22, 23 have a running rail 19. A device characterized in that it is installed at the rear node 12 of the triangular truss and at the upper joint node 14 between the square truss and the triangular truss for bearing against the truss. 2. The support structure is constructed as wall-like truss girders 4a, 4b, each of which has at least one essentially square truss surface with vertical members 5, 6 in the extent of its overhang and 2. The device according to claim 1, wherein a node 14 is provided at the upper part of the truss surface in a rear region with respect to the construction direction, forming a triangular truss surface connected to the previous truss surface. 3. A running device 22 is installed at the node of the triangular truss surface on each side of the device and at the upper joint node 14 between the square truss and the triangular truss to be supported by the running rail 19.
3. The apparatus according to claim 1 or 2, wherein: and 23 are installed. 4. A patent claim characterized in that in each triangular truss, a diagonal member 11 is hingedly connected at both ends, and the length of the diagonal member 11 and the horizontal member 10 can be changed. Apparatus according to any one of ranges 1 to 3. 5. The device according to claim 4, wherein the diagonal member 11 is formed of a telescopic pipe. 6. Device according to claim 4 or 5, characterized in that the horizontal member 10 can be slid horizontally into a guide 15 attached to the upper connection node 14. 7. The device according to any one of claims 1 to 6, characterized in that the height of the concrete casting scaffold can be changed with respect to the supporting structures 4a, 4b. 8 Cross beams 41 and 42 for concrete placement scaffolding 40 are:
8. Device according to claim 7, characterized in that it has guides attached to its ends and is arranged to slide along the support structure relative to a vertical guide rail. 9 The guide is formed as sliding tubes 44a and 44b,
9. Device according to claim 7, characterized in that the vertical members 5, 6 of the truss are gripped as guide rails. 10. According to any one of claims 1 to 9, characterized in that the entire device can be divided along the central longitudinal axis in order to be transported beyond the pier. equipment. 11. The device according to claim 10, characterized in that the cross beams 41, 42 of the concrete casting scaffold 40 can be joined together in a hinged manner at a guide portion. 12 From claim 1, characterized in that a gate-shaped rigid frame 34 that sandwiches the superstructure from the side is attached to the supporting structure with respect to a handle from a transfer device that runs on an auxiliary girder installed above the superstructure. 11.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19752555311 DE2555311C3 (en) | 1975-12-09 | 1975-12-09 | Device for the section-by-section, free pre-construction of bridge structures made of reinforced or prestressed concrete |
DE2555311.1 | 1975-12-09 |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5270549A JPS5270549A (en) | 1977-06-11 |
JPS6041165B2 true JPS6041165B2 (en) | 1985-09-14 |
Family
ID=5963888
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP51147203A Expired JPS6041165B2 (en) | 1975-12-09 | 1976-12-09 | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. |
Country Status (4)
Country | Link |
---|---|
JP (1) | JPS6041165B2 (en) |
AT (1) | AT364917B (en) |
DE (1) | DE2555311C3 (en) |
IT (1) | IT1072141B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NO150289C (en) * | 1982-06-01 | 1984-09-19 | Oestlandske Spennbetong As | DEVICE FOR SECTIONAL CASTING OF TENSIONED CONCRETE BRIDGES AFTER THE FRONT BUILDING METHOD |
FR2570112B1 (en) * | 1984-09-12 | 1986-11-21 | Travaux Publics Indl Entrepris | METHOD OF BUILDING A BRIDGE BY SUCCESSIVE CONVEYORS |
JP2001049622A (en) * | 1999-08-05 | 2001-02-20 | Vsl Japan Kk | Bridge erecting apparatus and bridge erecting method |
ES2249649T3 (en) * | 2003-03-12 | 2006-04-01 | Doka Industrie Gmbh | DEVICE AND PROCEDURE FOR MANUFACTURING BY SECTIONS OF A CONCRETE STRUCTURE CONCRETEED OR CONCRETE CONCRETE. |
DE102007047443A1 (en) * | 2007-10-04 | 2009-04-16 | Doka Industrie Gmbh | Formwork arrangement for the cantilever construction of bridges |
JP2016217051A (en) * | 2015-05-25 | 2016-12-22 | 株式会社ピーエス三菱 | Separate overhanging construction method of concrete bridge superstructure and concrete bridge |
CN105603885B (en) * | 2015-12-18 | 2017-06-13 | 广东省基础工程集团有限公司 | A kind of movable hydraulic roof Hanging Basket and its construction method with lifting and cloth function |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5035935A (en) * | 1972-08-18 | 1975-04-04 |
-
1975
- 1975-12-09 DE DE19752555311 patent/DE2555311C3/en not_active Expired
-
1976
- 1976-11-08 AT AT825676A patent/AT364917B/en not_active IP Right Cessation
- 1976-12-07 IT IT6991876A patent/IT1072141B/en active
- 1976-12-09 JP JP51147203A patent/JPS6041165B2/en not_active Expired
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5035935A (en) * | 1972-08-18 | 1975-04-04 |
Also Published As
Publication number | Publication date |
---|---|
DE2555311C3 (en) | 1980-06-12 |
JPS5270549A (en) | 1977-06-11 |
DE2555311B2 (en) | 1978-03-23 |
ATA825676A (en) | 1981-04-15 |
AT364917B (en) | 1981-11-25 |
IT1072141B (en) | 1985-04-10 |
DE2555311A1 (en) | 1977-06-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4748420B2 (en) | Construction method of corrugated steel web bridge using girder for erection work | |
JP4403051B2 (en) | Corrugated steel web bridge construction method | |
US3985480A (en) | Apparatus for the sectional cantilever construction of bridge girder systems | |
IL114850A (en) | Crane for modular bridge construction | |
JPS6024247B2 (en) | Equipment for cantilevering a multi-span bridge structure made of reinforced concrete or prestressed concrete into sections. | |
JP2000265417A (en) | Moving timbering construction method for bridge floor slab overhang section | |
CN111455852A (en) | Assembling method of movable formwork for bridge construction | |
JP5184248B2 (en) | Construction method of level crossing | |
JPS59501465A (en) | Split casting equipment for prestressed concrete bridges using cantilever construction method | |
JP3318533B2 (en) | Arch rib construction equipment for concrete arch bridges | |
JP3177904B2 (en) | Mobile work vehicle for PC cable-stayed bridge | |
JPS6041165B2 (en) | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. | |
JP4329535B2 (en) | Mobile work vehicle for overhanging slabs | |
KR100627102B1 (en) | Precast Segment Bridge Construction Method Using Lifting Traveler | |
CN114657884A (en) | Descending type movable formwork construction method for abutment assembling and segmented propelling | |
JP3065916B2 (en) | Equipment for moving formwork for floor concrete | |
CN208763671U (en) | Self-propelled integrated tunnel inverted arch device | |
JP2000104221A (en) | Combined truss bridge and erection method of the same | |
CN110438906B (en) | Arch rib construction method for deck box type arch bridge | |
JPS58523B2 (en) | The most important thing is the most important thing. | |
JPH1088521A (en) | Overhang erection work device | |
JP2000087314A (en) | Method and device for construction of floor slab | |
JP2000104220A (en) | Erection of combined truss bridge | |
JPH05195513A (en) | Lining work car for arch bridge | |
JP2000087315A (en) | Method and device for construction of floor slab |