JPH10152822A - Precast landing bridge structure and wharf construction method using the structure - Google Patents
Precast landing bridge structure and wharf construction method using the structureInfo
- Publication number
- JPH10152822A JPH10152822A JP31187896A JP31187896A JPH10152822A JP H10152822 A JPH10152822 A JP H10152822A JP 31187896 A JP31187896 A JP 31187896A JP 31187896 A JP31187896 A JP 31187896A JP H10152822 A JPH10152822 A JP H10152822A
- Authority
- JP
- Japan
- Prior art keywords
- precast
- pier
- pile
- precast block
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Revetment (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、特に緊急性を要す
るなど工程の逼迫した工事に有効なプレキャスト桟橋構
造およびそれを用いた埠頭構築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast pier structure and a pier construction method using the precast pier structure, which is particularly effective for work requiring a short period of time such as urgency.
【0002】[0002]
【従来の技術】緊急性を要するなど工程の逼迫した工事
では、海象条件に左右されず、工期の短縮が強く望まれ
る。特に、杭式横桟橋上部工構造による桟橋施工におい
ては、これまでの一般的な場所打ちRC(reinfoced co
ncrete:鉄筋コンクリート)工法を採用すると、工事期
間中、台風などによる荒天時の波浪、航行船舶の航跡波
による影響を受ける。そのため、支保工架設からコンク
リート打設に至る工程にリスクを伴い、かなりの工期を
要しているのが現状である。また、土木工事従事者の高
齢化などからも施工の省力化は必要である。2. Description of the Related Art In a work requiring a short time due to urgency, it is strongly desired to shorten a construction period without being affected by sea conditions. In particular, in the case of pier construction using a pile type horizontal pier superstructure, the conventional general cast-in-place RC (reinfoced co
When the construction method is adopted, during the construction period, it will be affected by typhoons and other waves in stormy weather, and the wake waves of sailing vessels. For this reason, there is a risk in the process from the erection of the shoring work to the concrete placement, which requires a considerable construction period. In addition, labor saving of construction work is necessary due to aging of civil engineering workers.
【0003】平成7年の阪神・淡路第大震災において、
本願出願人は神戸港摩耶埠頭の復旧工事に携わった。そ
の際、従来からの場所打ちRC工法に代わる復旧工法と
して、復旧埠頭の総延長599mに対応し、RC構造に
よる長さ9.5〜26.25mのブロック化した桟橋上
部工梁部を順次架設するプレキャストブロック工法を採
用した。この場合、予めプレキャストブロックを陸上の
製作ヤードで製作し、復旧埠頭に沿って打設された鋼管
製の基礎杭まで1ブロックごと、基礎杭に架設して順に
復旧埠頭の延長まで1スパン50mに接続するというも
のである。In the 1995 Hanshin-Awaji Earthquake,
The applicant was involved in the restoration work of Kobe Port Maya Wharf. At that time, as an alternative to the conventional cast-in-place RC method, a block-type pier upper part with a length of 9.5 to 26.25 m using RC structure was installed in order to accommodate the total length of the restoration pier of 599 m. Precast block construction method was adopted. In this case, precast blocks are preliminarily manufactured in a production yard on land, and each block is erected on a foundation pile made up of steel pipe piled in along the restoration wharf. It is to connect.
【0004】係るプレキャストブロック工法は、大幅な
工期短縮を実現するという画期的な成果をあげることが
できた。復旧工事に臨むにあたって、発明者らは、プレ
キャスト化により工期短縮と省力化を実現するために、
上部工の梁部となるプレキャストブロックの1個当たり
の長さを可能な限り長大化することを念頭においた。桟
橋の1スパンの延長50mに対応する基礎杭の本数は2
0本程度が考えられた。基礎杭は海上側からクレーン付
台船のバイブロハンマーによって海底に打設される。[0004] Such a precast block construction method has achieved an epoch-making result of realizing a drastic reduction in the construction period. In the process of restoration work, the inventors tried to reduce the construction period and labor by pre-casting,
The length of each precast block to be the beam of the superstructure was made as long as possible. The number of foundation piles corresponding to the 50m extension of one span of the pier is 2
About 0 was considered. The foundation pile is driven from the seaside to the seabed by a vibrohammer of a barge with crane.
【0005】[0005]
【発明が解決しようとする課題】ところで、打設された
各基礎杭の杭頭天端にプレキャストブロックを支持する
ための支承部を設けた場合、その支承部を基準レベルに
合わせて高低差を±0とすることは不可能に近く、施工
誤差等により最大で±5mm前後の高低差を見込む必要
がある。そうした支承部の高低差によって、架設中や架
設後の上部工梁部プレキャストブロックに生じる応力等
の剛性面への影響は大なるものがある。したがって、1
スパン50mに対応する長さのプレキャストブロック
は、剛性強度的にも、あるいは架設施工時に困難を伴う
ことが想定された。そのため、1つのプレキャストブロ
ックの長さは1スパンを基本的に2分割に設定した。When a support portion for supporting a precast block is provided at the top of the pile head of each cast foundation pile, the height difference between the support portion and the reference level is adjusted. It is almost impossible to make it ± 0, and it is necessary to expect a height difference of up to around ± 5 mm due to construction errors and the like. Due to such a difference in height of the bearing, there is a large influence on a rigid surface such as a stress generated in the upper beam precast block during or after erection. Therefore, 1
It was assumed that the precast block having a length corresponding to the span of 50 m would have difficulty in rigidity and / or construction work. Therefore, the length of one precast block is set so that one span is basically divided into two.
【0006】しかしながら、そのような長さにプレキャ
ストブロックを設定した場合でも、基本的に支承部の高
低差でプレキャストブロックに部分的な応力集中が発生
することを回避する必要がある。[0006] However, even when the precast block is set to such a length, it is basically necessary to avoid the occurrence of partial stress concentration in the precast block due to the difference in height of the support portions.
【0007】そこで、本発明の主たる目的は、プレキャ
ストブロックを下方から支持する基礎杭の杭頭に設けた
支承部のレベル高低差を吸収し、架設時に桟橋上部工梁
部に与える剛性等への影響を最小限にとどめること、お
よび架設後に基礎杭に対する支持反力を均等にすること
により、場所打ちRC工法の場合と同断面でのプレキャ
スト桟橋構造およびそれを用いた埠頭構築工法を提供す
ることにある。Therefore, a main object of the present invention is to absorb a level difference of a support portion provided at a pile head of a foundation pile for supporting a precast block from below, and to reduce a rigidity or the like given to a pier upper beam portion during erection. To provide a precast pier structure with the same cross section as that of the cast-in-place RC method and a pier construction method using the same, by minimizing the influence and equalizing the supporting reaction force to the foundation pile after erection. It is in.
【0008】[0008]
【課題を解決するための手段】上記目的を達成するため
に、本発明によるプレキャスト桟橋構造は、構築される
埠頭長さに沿って水底に所定ピッチで打設された基礎杭
と、予め埠頭長さを分割したRC構造の桟橋上部工用梁
部として製作され、架設時に基礎杭の杭頭に挿入させ
て、基礎杭と一体化するための鞘管を有するプレキャス
トブロックとを備えてなっている。この構成において、
プレキャストブロックを支持する基礎杭の杭頭における
支承部にレベル調整支承機構を設置している。このレベ
ル調整支承機構では、施工誤差等による支承部の高低差
をプレキャストブロックの架設時に吸収すると共に、架
設後のプレキャストブロックの重量による基礎杭の支持
反力を均等化するようになっている。In order to achieve the above-mentioned object, a precast pier structure according to the present invention comprises a foundation pile which is installed at a predetermined pitch on a water bottom along a quay length to be constructed, and a quay length in advance. It is manufactured as a beam part for the pier upper part of RC structure with divided RC structure, and is provided with a precast block having a sheath tube for being inserted into the pile head of the foundation pile at the time of erection and integrating with the foundation pile. . In this configuration,
A level adjustment bearing mechanism is installed at the bearing at the pile head of the foundation pile supporting the precast block. In this level adjusting support mechanism, a difference in height of the support portion due to a construction error or the like is absorbed when the precast block is erected, and the support reaction force of the foundation pile due to the weight of the precast block after the erection is equalized.
【0009】また、係るプレキャスト桟橋構造を用いた
埠頭構築工法は、複数の基礎杭を構築される埠頭長さに
沿って水底に所定ピッチで打設し、RC構造の桟橋上部
工用梁部としてプレキャストブロックを埠頭長さを分割
して予め製作し、プレキャストブロックを1ブロック毎
に打設済みの基礎杭の対応する幾つかに架設する際、プ
レキャストブロックに設けてある基礎杭に対応した数の
鞘管を、基礎杭の杭頭に挿入させてプレキャストブロッ
クを位置決めする。位置決めの際、基礎杭の支承部に設
置したレベル調整支承機構によって、施工誤差等による
基礎杭の支承部の高低差を吸収すると共に、架設後のプ
レキャストブロックの重量による基礎杭の支持反力を均
等化する。In the pier construction method using such a precast pier structure, a plurality of foundation piles are driven at a predetermined pitch along the length of the pier to be constructed, and are used as a beam for the pier upper construction of the RC structure. Precast blocks are prefabricated by dividing the wharf length, and when the precast blocks are erected on corresponding ones of the foundation piles that have been cast one by one, the number corresponding to the number of foundation piles provided on the precast blocks The sheath tube is inserted into the pile head of the foundation pile to position the precast block. At the time of positioning, the level adjustment support mechanism installed on the support part of the foundation pile absorbs the height difference of the support part of the foundation pile due to construction errors, and the support reaction force of the foundation pile due to the weight of the precast block after installation. Equalize.
【0010】以下、それを繰り返して位置決め後のプレ
キャストブロックに他のプレキャストブロックを1スパ
ン50mに接続する。The above procedure is repeated to connect another precast block to the positioned precast block in a span of 50 m.
【0011】したがって、この埠頭構築工法にあって
は、海上作業と併行して桟橋上部工梁部となるプレキャ
ストブロックの製作が別途可能となり、工期短縮が図れ
る。その際、施工誤差等による支承部の高低差は、各基
礎杭の杭頭に設置したレベル調整支承機構によって吸収
される。Therefore, according to this wharf construction method, it is possible to separately manufacture a precast block to be a pier upper beam along with offshore work, thereby shortening the construction period. At that time, the height difference of the bearing part due to the construction error or the like is absorbed by the level adjustment bearing mechanism installed at the pile head of each foundation pile.
【0012】[0012]
【発明の実施の形態】以下、本発明による実施の形態の
プレキャスト桟橋構造およびそれを用いた埠頭構築方法
について、図面を参照して詳細に説明する。BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, a precast pier structure according to an embodiment of the present invention and a pier construction method using the same will be described in detail with reference to the drawings.
【0013】図1は、大震災等によって被災した埠頭に
おいて、滑動や傾斜した既設のケーソン1を本発明のプ
レキャスト桟橋構造による埠頭構築工法で復旧する形態
を示す部分断面による側面図である。その概要は、桟橋
上部工の梁部と床版部を個別にプレキャスト化し、梁部
についてはその大部分を陸上製作のプレキャストブロッ
ク10として現場架設後に基礎杭(鋼管杭)20と一体
化される。床版部については、別途工場製作が可能であ
るPCホロー桁として、陸上で横組を行った後、梁部に
一括架設される。FIG. 1 is a partial cross-sectional side view showing a form in which an existing caisson 1 that has been slid or inclined is restored by a pier construction method using a precast pier structure of the present invention on a pier damaged by a great earthquake or the like. The outline is that the beam part and the floor slab part of the pier superstructure are individually precast, and most of the beam part is integrated with the foundation pile (steel pipe pile) 20 after erection on site as a precast block 10 made on land. . The floor slab will be installed on the beam after the horizontal framing is performed on land as a PC hollow girder that can be separately manufactured at the factory.
【0014】図2〜図6は、桟橋上部工の1ブロックを
構成するプレキャストブロック10の製作フローを示し
ている。桟橋の1スパンの延長は50mであるが、剛性
や施工性等を考慮して、基本的に1スパンを2分割した
プレキャストブロック10を製作し、それらを現場にて
架設する。FIGS. 2 to 6 show a production flow of the precast block 10 constituting one block of the pier superstructure. The extension of one span of the pier is 50 m, but in consideration of rigidity, workability, etc., a precast block 10 in which one span is basically divided into two is manufactured and erected at the site.
【0015】まず、図2に示すように、陸上の製作ヤー
ドにおいてプレキャストブロック10の1つ分の型枠基
板11が準備され、この型枠基板11上に、1プレキャ
ストブロックに対して後述する基礎杭の本数に対応する
数だけ、複数個の鞘管12が適宜間隔をもって配置され
る。First, as shown in FIG. 2, a mold substrate 11 for one precast block 10 is prepared in a production yard on land. A plurality of sheath tubes 12 are arranged at appropriate intervals by the number corresponding to the number of piles.
【0016】次に、図3に示すように、プレキャストブ
ロック長さ方向へ、鞘管12と鞘管12との間をわたす
ようにしてH形鋼による架設用鋼材13が配置され、鉄
筋14を配筋し、吊筋が配置される。配筋後、型枠が組
み立てられる。Next, as shown in FIG. 3, a steel material 13 for erection of H-shaped steel is arranged in the length direction of the precast block so as to extend between the sheath pipes 12, and the reinforcing steel 14 is moved. Arrange the bars and arrange the suspension bars. After the arrangement, the formwork is assembled.
【0017】配筋および型枠組立後、図4に示すよう
に、コンクリートが打設されて1つのプレキャストブロ
ック10の製作が完了する。After the arrangement of the reinforcing bars and the formwork, as shown in FIG. 4, concrete is cast and the production of one precast block 10 is completed.
【0018】図5は、プレキャストブロック10の一例
を示す平面図であり、図6は図5のA−A線による側面
断面図を示している。この場合、2本の平行な縦桁梁1
5とこれに直交する3本の横桁梁16から駆体が構成さ
れ、基礎杭の本数に対応する数の鞘管12が埋め込まれ
た形状のものが示されている。縦桁梁15の1本に対し
その全長より接合個所まで前述の2本の架設用鋼材13
が平行に各鞘管12の上部に挿通して埋め込まれた形と
なっている。さらに、架設時等における補強に万全を期
すため、縦桁梁15の1本に対しその全長にわたって、
H形鋼による2本の架設用鋼材17が駆体上面に露出し
た形で配置されている。FIG. 5 is a plan view showing an example of the precast block 10, and FIG. 6 is a side sectional view taken along line AA of FIG. In this case, two parallel girder beams 1
5 shows a configuration in which a vehicle body is composed of 5 and three cross beams 16 orthogonal thereto, and the sheath tubes 12 are embedded in a number corresponding to the number of foundation piles. For one of the girder beams 15, the above-mentioned two erection steel members 13 from the entire length to the joint point.
Are inserted parallel to and embedded in the upper part of each sheath tube 12. Furthermore, in order to ensure thorough reinforcement during erection, etc., one of the longitudinal beams 15
Two erection steel materials 17 made of H-section steel are arranged so as to be exposed on the upper surface of the vehicle body.
【0019】一方、製作ヤードにおいて桟橋上部工のプ
レキャストブロック10の製作と併行して、復旧現場で
は、図1で示されたように、新設桟橋の法線方向に2列
に長大で大径サイズの基礎杭20がクレーン付台船のバ
イブロハンマーにより海底に打設される。図7は、基礎
杭20を設定された縦横ピッチで打設する態様を示し、
図8は基礎杭20の杭頭部を示す斜視図である。基礎杭
20の打設が終了すると、図9に示す起重機船によりプ
レキャストブロック10が製作ヤードから施工現場まで
搬送され、打ち込み済みの基礎杭20上に架設される。On the other hand, in parallel with the production of the precast block 10 for the pier superstructure at the production yard, at the restoration site, as shown in FIG. Is laid on the seabed by a vibro hammer of a barge with a crane. FIG. 7 shows a mode in which the foundation pile 20 is driven at the set vertical and horizontal pitches,
FIG. 8 is a perspective view showing a pile head of the foundation pile 20. When the placing of the foundation pile 20 is completed, the precast block 10 is transported from the production yard to the construction site by the hoist ship shown in FIG. 9 and is laid on the driven foundation pile 20.
【0020】ところで、基礎杭20の打ち込み後、その
上に設置される支承部の高さレベルの誤差は理想的には
0であることが望ましい。しかしながら、後述の図12
に示すように、プレキャストブロック10を下方から支
持する基礎杭20の杭頭支承部においては、現場施工で
あるがゆえに、基準レベルHに対して±5mm程度の高
低差hが発生することは止むを得ない。支承部の数が両
端2点の単純支持梁ではさほど問題とならない。今回の
ように、1つのプレキャストブロック10に対して例え
ば10本の基礎杭20で支持する場合(図5参照)、各
支承部の高低差hは、プレキャストブロック10に局所
的に過大な応力集中を生じさせる。このことは杭頭反力
の不均等を生じさせ、基礎杭20にとっても軸力を残留
させる結果を招く。By the way, after the driving of the foundation pile 20, it is desirable that the error of the height level of the supporting portion installed thereon is ideally zero. However, FIG.
As shown in (1), in the pile head bearing of the foundation pile 20 that supports the precast block 10 from below, the height difference h of about ± 5 mm with respect to the reference level H stops being generated because of the on-site construction. Not get. A simple support beam with two support points at both ends is not a problem. As in this case, when one precast block 10 is supported by, for example, ten foundation piles 20 (see FIG. 5), the height difference h of each bearing portion locally causes excessive stress concentration on the precast block 10. Cause. This results in an uneven pile head reaction force, resulting in a residual axial force even for the foundation pile 20.
【0021】そこで、本発明では、図11以下の各図に
示すように、各基礎杭20の支承部における高低差hを
吸収する構造が採用されている。Therefore, in the present invention, as shown in FIGS. 11 and subsequent figures, a structure for absorbing the height difference h at the support portion of each foundation pile 20 is adopted.
【0022】図11は、1本の基礎杭20の平面図であ
り、図12は図11のB−B線による基礎杭20の杭頭
における支承部断面図を示している。FIG. 11 is a plan view of one foundation pile 20, and FIG. 12 is a sectional view of a support portion at the pile head of the foundation pile 20 along the line BB in FIG.
【0023】各基礎杭20の支承部では、その杭頭に切
欠した凹部21が形成してあり、この切欠凹部21を図
6で示されたプレキャストブロック10側の平行2本の
架設用鋼材13が挿通できるようになっている。また、
基礎杭20の杭頭部は収縮補償用のコンクリートを充填
した中詰めコンクリート22によって閉塞されている。
この中詰めコンクリート22の上面には、基準レベルH
に合わせるための左右一対のレベル調整支承機構23が
設置されている。At the bearing portion of each foundation pile 20, a notch 21 is formed in the pile head, and the notch 21 is formed in the two parallel steel members 13 on the precast block 10 side shown in FIG. Can be inserted. Also,
The pile head of the foundation pile 20 is closed by an intermediate concrete 22 filled with concrete for shrinkage compensation.
The reference level H
A pair of left and right level adjustment support mechanisms 23 for adjusting the position are provided.
【0024】レベル調整支承機構23は、(a)基礎杭
20における杭頭支承部の高低差hを吸収すること、
(b)プレキャストブロック10を架設後に各基礎杭2
0における支持反力を均等化させること、の2つの目的
を達成するために設置される。したがって、(a)項の
目的を果たす対向一組の2個の緩衝ゴム材24を上部に
有し、(b)項の目的を果たす対向一組の2個の感圧硬
化ゴム材25を下部に有している。また、感圧硬化ゴム
材25を下方から支持する部材として、中詰めコンクリ
ート22の上面に設置されたベース26を有している。
このベース26と感圧硬化ゴム材25との間には、感圧
硬化ゴム材25と同一平面サイズの面圧調整板28を介
在させている。さらに、感圧硬化ゴム材25とこの上の
緩衝ゴム材24とを仕切る形で受圧仕切板27を介在さ
せ、同様な受圧仕切板27を緩衝ゴム材24の上に配置
した積層構造体となっている。係る積層構造体のレベル
調整支承部材23が架設用鋼材13を下方から支持する
形となる。The level adjusting bearing mechanism 23 (a) absorbs the height difference h of the pile head bearing part in the foundation pile 20;
(B) After the precast block 10 is erected, each foundation pile 2
It is installed to achieve the two objectives of equalizing the support reaction force at zero. Therefore, a pair of opposed cushioning rubber members 24 which fulfill the purpose of (a) is provided at the upper part, and a pair of two pressure-sensitive cured rubber materials 25 which fulfill the purpose of (b) are provided at the lower part. Have. In addition, as a member for supporting the pressure-sensitive hardening rubber material 25 from below, it has a base 26 installed on the upper surface of the filling concrete 22.
Between the base 26 and the pressure-sensitive cured rubber material 25, a surface pressure adjusting plate 28 having the same plane size as the pressure-sensitive cured rubber material 25 is interposed. Further, a pressure-receiving partitioning plate 27 is interposed in the form of partitioning the pressure-sensitive hardening rubber member 25 and the cushioning rubber member 24 thereon, and the same pressure-receiving partitioning plate 27 is arranged on the cushioning rubber member 24 to form a laminated structure. ing. The level adjusting support member 23 of the laminated structure supports the erection steel material 13 from below.
【0025】ここで、中詰めコンクリート22の上面に
設置されるベース26は鋼板が用いられ、基準レベルH
はベース26の上面をもって測量される。中詰めコンク
リート22の打設時にレベル調整したベース26を設置
する。中詰めコンクリート22の打設後、再度ベース2
6のレベル測量を行い、基準レベルHに合わせるために
必要に応じて薄い鋼板を設置する。Here, a steel plate is used for the base 26 installed on the upper surface of the filling concrete 22, and the reference level H
Is measured with the upper surface of the base 26. The base 26 whose level has been adjusted is installed when the concrete filling 22 is poured. After the concrete 22 is cast, the base 2
The level survey of No. 6 is performed, and a thin steel plate is installed as needed to match the reference level H.
【0026】上下を2枚の受圧仕切板27で挟まれた形
の上部層の緩衝ゴム材24は、架設時のプレキャストブ
ロック10の重量に対応して弾性変形する。受圧仕切板
27は緩衝ゴム材24の弾性変形に追従して変動する。
すなわち、緩衝ゴム材24は弾性変形によって基礎杭2
0の杭頭支承部における高低差h、つまりベース26の
上面の測量誤差等による高低差を吸収する。使用ゴムは
その特性から柔軟なものほど歪量は多い。すなわち、硬
度の低いものほど高低差hを吸収し易い。そのため、一
般に使用される柔軟な硬度50度のゴム材を採用してい
る。The cushioning rubber material 24 of the upper layer sandwiched between the upper and lower pressure receiving partition plates 27 is elastically deformed in accordance with the weight of the precast block 10 at the time of erection. The pressure receiving partition plate 27 fluctuates following the elastic deformation of the cushion rubber material 24.
That is, the cushioning rubber material 24 is elastically deformed so that the foundation pile 2
The height difference h at the pile head bearing portion of zero, that is, the height difference due to a measurement error on the upper surface of the base 26 is absorbed. Due to its properties, the more flexible the rubber used, the greater the amount of distortion. That is, the lower the hardness, the more easily the height difference h is absorbed. Therefore, a generally used flexible rubber material having a hardness of 50 degrees is employed.
【0027】これに対して、下部層を形成するベース2
6上の感圧硬化ゴム材25は、「硬化前の可塑性」と
「硬化後の弾性」という極めて便利な2つの特性を有す
る材料である。その構造は、2種類の未加硫ゴムの数層
を積層したもので、硬化前の塑性変形量は厚さの80%
である。硬化前の塑性変形という特性を生かして、各基
礎杭20における不均等な支持反力を均等化する機能を
発揮するゴム材である。また、この感圧硬化ゴム材25
の塑性変形量は、加圧面積当たりの載荷重(面圧)によ
り異なり、面圧の大きいものほど変形量は大きい。その
ため、ベース26上に介在させた感圧硬化ゴム材25と
同一平面サイズの面圧調整板28によって面圧均一化が
避けられるようになっている。On the other hand, the base 2 for forming the lower layer
The pressure-sensitive cured rubber material 25 on 6 is a material having two very convenient characteristics, “plasticity before curing” and “elasticity after curing”. Its structure is a laminate of several layers of two types of unvulcanized rubber. The amount of plastic deformation before curing is 80% of the thickness.
It is. It is a rubber material exhibiting a function of equalizing uneven support reaction force in each foundation pile 20 by utilizing the characteristic of plastic deformation before hardening. In addition, this pressure-sensitive cured rubber material 25
The amount of plastic deformation depends on the applied load (surface pressure) per pressed area, and the larger the surface pressure, the larger the amount of deformation. Therefore, the surface pressure adjusting plate 28 having the same plane size as the pressure-sensitive cured rubber material 25 interposed on the base 26 can prevent the surface pressure from being equalized.
【0028】そこで、図9のように、起重機船によって
1つのプレキャストブロック10を架設する際、図13
に示すように、まずプレキャストブロック10側の各鞘
管12に対応する基礎杭20の杭頭を入れ込み、微調整
による位置決めが行われる。基礎杭20の杭頭に鞘管1
2を挿入してプレキャストブロック10が載置される。
数本の基礎杭20の杭頭にプレキャストブロック10が
その平行2本の架設用鋼材13を介して載置されると、
各基礎杭20の杭頭支承部の高低差hの調整は、各基礎
杭20上のレベル調整支承機構23が模式的に示す図1
7および図18のように弾性変形することで吸収され
る。Therefore, when one precast block 10 is erected by a hoist ship as shown in FIG.
As shown in (1), first, the pile head of the foundation pile 20 corresponding to each sheath tube 12 on the precast block 10 side is inserted, and positioning by fine adjustment is performed. Sheath tube 1 on pile head of foundation pile 20
2, the precast block 10 is placed.
When the precast block 10 is placed on the pile heads of several foundation piles 20 via the two parallel steel materials 13 for erection,
Adjustment of the height difference h of the pile head bearing portion of each foundation pile 20 is schematically shown by a level adjustment bearing mechanism 23 on each foundation pile 20 in FIG.
As shown in FIG. 7 and FIG. 18, it is absorbed by elastic deformation.
【0029】図17に示すように、一方の基礎杭20が
高さの基準レベルHである場合、他方の基礎杭20の高
さレベルがそれよりもhだけ高いとする。この場合、プ
レキャストブロック10の重量によって他方の基礎杭2
0に設けたレベル調整支承機構23はその高低差hを吸
収すべく弾性変形する。例えば、ベース26の上面の施
工誤差等による高低差hが±5mmである場合、架設後
のプレキャストブロック10の重量によって緩衝ゴム材
24の歪量に差が生じ、その高低差hを吸収する。その
後、図18に示すように、感圧硬化ゴム材25の塑性変
形量に差が生じ、緩衝ゴム材24の各基礎杭20で歪量
が均一となる。感圧硬化ゴム材25は、塑性変形を生じ
た状態で約一週間放置後にその変形量を保持したままで
硬化する。As shown in FIG. 17, when one of the foundation piles 20 is at the reference level H, the height of the other foundation pile 20 is assumed to be higher by h. In this case, the other foundation pile 2
The level adjustment support mechanism 23 provided at 0 is elastically deformed to absorb the height difference h. For example, when the height difference h due to a construction error or the like on the upper surface of the base 26 is ± 5 mm, a difference occurs in the amount of distortion of the cushion rubber material 24 due to the weight of the precast block 10 after the construction, and the height difference h is absorbed. Thereafter, as shown in FIG. 18, a difference occurs in the amount of plastic deformation of the pressure-sensitive cured rubber material 25, and the amount of strain becomes uniform in each of the foundation piles 20 of the cushioning rubber material 24. The pressure-sensitive curable rubber material 25 is cured after being left for about one week in a state where plastic deformation has occurred, while maintaining the deformation amount.
【0030】このように、レベル調整支承機構23によ
って、各基礎杭20の杭頭支承部の高低差によるプレキ
ャストブロック10側のレベル調整が行われ、各基礎杭
20における支持反力が均一化される。その後、図14
に示すように、プレキャストブロック10側の各鞘管1
2と基礎杭20との間の空隙に収縮補償用のコンクリー
ト30が充填され、プレキャストブロック10と基礎杭
20とが一体化結合される。As described above, the level adjustment support mechanism 23 adjusts the level of the precast block 10 based on the height difference of the pile head support portion of each foundation pile 20, and the support reaction force in each foundation pile 20 is made uniform. You. Then, FIG.
As shown in the figure, each sheath tube 1 on the precast block 10 side
The gap between the base 2 and the foundation pile 20 is filled with concrete 30 for shrinkage compensation, and the precast block 10 and the foundation pile 20 are integrally connected.
【0031】図15は、プレキャストブロック10をこ
の長手方向から見た場合の鞘管12における基礎杭20
との一体化結合部の断面を示している。図16は、隣り
合う左右2つのプレキャストブロック10A、10Bを
それらの長手方向から見た場合の接続部における一体化
結合部の断面図である。この図16の接続部では、左右
相対するプレキャストブロック10A、10Bの対向面
からはそれぞれ架設用鋼材13が所定の長さで外部に露
出している。左右のプレキャストブロック10、10の
各架設用鋼材13における対向突端部を下方から1本の
基礎杭20で支持している。この基礎杭20の天端には
各架設用鋼材13の対向突端部に対応するレベル調整支
承機構23が配置されている。架設後は、エンクローズ
継手28で鉄筋を接合して、接続部に収縮補償用のコン
クリート30を打設して一体化する。FIG. 15 shows a foundation pile 20 in the sheath tube 12 when the precast block 10 is viewed from this longitudinal direction.
2 shows a cross section of an integrated connection portion with the above. FIG. 16 is a cross-sectional view of an integrated connection part in a connection part when two adjacent left and right precast blocks 10A and 10B are viewed from their longitudinal direction. In the connection part of FIG. 16, the steel material 13 for erection is exposed to the outside at a predetermined length from the opposing surfaces of the precast blocks 10A and 10B facing each other. The opposite protruding end portions of the left and right precast blocks 10 and 10 in the steel materials 13 for erection are supported by one foundation pile 20 from below. At the top end of the foundation pile 20, a level adjustment support mechanism 23 corresponding to the facing protruding end of each of the erection steel materials 13 is arranged. After the erection, the reinforcing bars are joined by the enclosure joint 28, and concrete 30 for shrinkage compensation is cast at the connection portion to be integrated.
【0032】なお、本実施の形態の場合、被災埠頭を緊
急復旧する際の工法を想定して説明したが、被災埠頭に
限らず新設埠頭の構築工法としても、基本的に工期短縮
と省力化は共通しているので適用可能であることは勿論
である。Although the present embodiment has been described assuming a construction method for emergency restoration of the damaged wharf, not only the construction method of a new wharf but also a construction method of a newly constructed wharf is basically used to shorten the construction period and save labor. Are of course applicable because they are common.
【0033】[0033]
【発明の効果】以上説明したように、本発明のプレキャ
スト桟橋構造およびそれを用いた埠頭構築工法は、海上
作業と併行して桟橋上部工梁部となるプレキャストブロ
ックを別途製作可能であることから、工期の短縮が図
れ、基礎杭の杭頭支承部に生じた施工誤差等による高低
差の吸収および支持反力の均等化が、各基礎杭の杭頭に
設置したレベル調整支承機構によって図られる。また、
海上作業が場所打ちRC工法と比較して省力化されるこ
とから、施工の安全性を向上させる効果がある。As described above, the precast pier structure and the pier construction method using the same according to the present invention can separately manufacture a precast block to be a pier upper beam part along with offshore work. The level adjustment support mechanism installed at the pile head of each foundation pile achieves the shortening of the construction period, absorption of height differences due to construction errors at the pile head bearing of the foundation pile, and equalization of the support reaction force. . Also,
Since the offshore work is labor-saving as compared with the cast-in-place RC method, there is an effect of improving construction safety.
【図1】被災埠頭とこれを復旧する本発明に係る実施の
形態のプレキャスト桟橋構造を示す側面断面図である。FIG. 1 is a side sectional view showing a damaged pier and a precast pier structure according to an embodiment of the present invention for restoring the pier.
【図2】本実施の形態によるRC構造のプレキャストブ
ロックを製作ヤードで製作する工程を示す斜視図であ
る。FIG. 2 is a perspective view showing a step of manufacturing a precast block having an RC structure according to the present embodiment in a manufacturing yard.
【図3】本実施の形態によるRC構造のプレキャストブ
ロックを製作ヤードで製作する工程を示す斜視図であ
る。FIG. 3 is a perspective view showing a step of manufacturing a precast block having an RC structure according to the present embodiment in a manufacturing yard.
【図4】本実施の形態によるRC構造のプレキャストブ
ロックを製作ヤードで製作する工程を示す斜視図であ
る。FIG. 4 is a perspective view showing a step of manufacturing a precast block having an RC structure according to the present embodiment in a manufacturing yard.
【図5】製作後の本実施の形態のプレキャストブロック
を示す平面図である。FIG. 5 is a plan view showing a precast block of the present embodiment after fabrication.
【図6】図5のA−A線による側面断面図である。FIG. 6 is a side sectional view taken along line AA of FIG. 5;
【図7】基礎杭の打設中の態様を示す斜視図である。FIG. 7 is a perspective view showing an aspect during the placement of the foundation pile.
【図8】基礎杭の杭頭を示す斜視図である。FIG. 8 is a perspective view showing a pile head of a foundation pile.
【図9】打設基礎杭にプレキャストブロックを架設する
態様を示す斜視図である。FIG. 9 is a perspective view showing an aspect in which a precast block is erected on a foundation pile.
【図10】打設後の基礎杭の杭頭支承部に生じた高低差
を示す斜視図である。FIG. 10 is a perspective view showing a height difference generated in a pile head bearing of a foundation pile after driving.
【図11】各基礎杭の杭頭支承部に設置された本実施の
形態のレベル調整支承機構を示す平面図である。FIG. 11 is a plan view showing a level adjustment support mechanism of the present embodiment installed on a pile head support portion of each foundation pile.
【図12】図11のB−B線による正面断面図である。FIG. 12 is a front sectional view taken along line BB of FIG. 11;
【図13】基礎杭とこの杭間に架設されて位置決め中の
プレキャストブロックとの取り合いを示す側面断面図で
ある。FIG. 13 is a side cross-sectional view showing the connection between a foundation pile and a precast block installed and positioned between the piles.
【図14】プレキャストブロック側の鞘管と基礎杭側の
杭頭との間の空隙に収縮補償用コンクリートを充填して
一体化結合した状態を示す正面断面図である。FIG. 14 is a front sectional view showing a state in which a gap between a sheath pipe on a precast block side and a pile head on a foundation pile side is filled with shrinkage compensating concrete and integrally combined.
【図15】プレキャストブロックの鞘管における基礎杭
の杭頭との結合を示す正面断面図である。FIG. 15 is a front sectional view showing the connection of the sheath pipe of the precast block with the pile head of the foundation pile.
【図16】隣り合うプレキャストブロック同士を接続す
る部分の基礎杭の杭頭との結合を示す正面断面図であ
る。FIG. 16 is a front cross-sectional view showing connection of a portion connecting adjacent precast blocks to a pile head of a foundation pile.
【図17】各基礎杭の杭頭支承部に生じた高低差hにお
けるレベル調整支承機構を模式的に示す断面図である。FIG. 17 is a sectional view schematically showing a level adjustment support mechanism at a height difference h generated in a pile head support portion of each foundation pile.
【図18】各基礎杭の杭頭支承部に生じた高低差hをレ
ベル調整支承機構によって吸収した形態を模式的に示す
断面図である。FIG. 18 is a cross-sectional view schematically showing a form in which a height difference h generated in a pile head bearing portion of each foundation pile is absorbed by a level adjustment bearing mechanism.
1 被災埠頭のケーソン 10 プレキャストブロック 12 鞘管 13 架設用鋼材 17 架設用鋼材 20 基礎杭 21 切欠凹部 22 中詰めコンクリート 23 レベル調整支承機構 24 緩衝ゴム材 25 感圧硬化ゴム材 26 ベース 27 受圧仕切板 28 面圧調整板 30 収縮補償用コンクリート DESCRIPTION OF SYMBOLS 1 Caisson of quay quay 10 Precast block 12 Sheath tube 13 Steel material for construction 17 Steel material for construction 20 Foundation pile 21 Notch recess 22 Filling concrete 23 Level adjustment support mechanism 24 Buffer rubber material 25 Pressure sensitive rubber material 26 Base 27 Pressure receiving partition plate 28 Surface pressure adjusting plate 30 Concrete for shrinkage compensation
───────────────────────────────────────────────────── フロントページの続き (72)発明者 金井 浩之 大阪府大阪市中央区備後町二丁目4番6号 佐伯建設工業株式会社内 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Hiroyuki Kanai 2-4-6 Bingo-cho, Chuo-ku, Osaka City, Osaka Prefecture Saeki Construction Industry Co., Ltd.
Claims (3)
ッチで打設された基礎杭と、 予め埠頭長さを分割したRC構造の桟橋上部工用梁部と
して製作され、架設時に基礎杭の杭頭に挿入させて一体
化するための鞘管を有するプレキャストブロックと、 プレキャストブロックを支持する基礎杭の杭頭における
支承部に設置され、施工誤差等による支承部の高低差を
プレキャストブロックの架設時に吸収すると共に、架設
後のプレキャストブロックの重量による基礎杭の支持反
力を均等化するレベル調整支承機構と、を備えているこ
とを特徴とするプレキャスト桟橋構造。1. A foundation pile which is laid at a predetermined pitch along the length of a quay along a pier length to be constructed, and a beam for a pier upper part of an RC structure having a quay length previously divided into pier lengths. A precast block that has a sheath tube to be inserted into the pile head of the pile and integrated with it, and a precast block that is installed at the bearing at the pile head of the foundation pile that supports the precast block, and the height difference of the bearing due to construction errors etc. And a level adjustment support mechanism for absorbing the weight of the precast block after the erection and equalizing the supporting reaction force of the foundation pile.
部における支承面上に設置された平板状のベースと、 このベースの上面に設置されることにより面圧均一化が
避けられ、プレキャストブロックから受ける重量に対応
して塑性変形し、その塑性変形量を保持して硬化するこ
とにより基礎杭の支持反力を均等化する感圧硬化ゴム材
とこの感圧硬化ゴム材の上位に配置され、ベースの上面
の高低差をプレキャストブロックから受ける重量に対応
して弾性変形することにより吸収する緩衝ゴム材と、 感圧硬化ゴム材とこの上に配置された緩衝ゴム材との間
に介在させ、緩衝ゴム材の弾性変形に追従する上下複数
枚からなる受圧仕切板と、を備えていることを特徴とす
る請求項1に記載のプレキャスト桟橋構造。2. A level adjustment support mechanism, wherein a flat base provided on a support surface of the support portion and a top surface of the base are provided to adjust the installation height of the support portion to a reference level. A pressure-sensitive cured rubber material that avoids uniform surface pressure, plastically deforms according to the weight received from the precast block, and hardens while retaining the amount of plastic deformation to equalize the supporting reaction force of the foundation pile A cushioning rubber material that is arranged above this pressure-sensitive cured rubber material and absorbs the height difference of the upper surface of the base by elastically deforming according to the weight received from the precast block, and a pressure-sensitive cured rubber material and placed on top 2. The precast pier according to claim 1, further comprising: a pressure receiving partition plate comprising a plurality of upper and lower pressure plates which are interposed between the shock absorbing rubber material and the elastic deformation of the shock absorbing rubber material. Elephants.
て水底に所定ピッチで打設し、 RC構造の桟橋上部工用梁部としてプレキャストブロッ
クを埠頭長さを分割して予め製作し、 プレキャストブロックを1ブロック毎に打設済みの基礎
杭の対応する幾つかに架設する際、プレキャストブロッ
クに設けてある基礎杭に対応した数の鞘管を、基礎杭の
杭頭に挿入させてプレキャストブロックを位置決めし、 位置決めの際、基礎杭上の支承部に設置したレベル調整
支承機構によって、施工誤差等による基礎杭上の支承部
の高低差を吸収すると共に、架設後のプレキャストブロ
ックの重量による基礎杭の支持反力を均等化する、こと
を特徴とするプレキャスト桟橋構造を用いた埠頭構築工
法。3. A plurality of foundation piles are cast at predetermined pitches along the length of the pier on the pier to be constructed, and a precast block is preliminarily manufactured by dividing the pier length as a beam for an upper part of a pier having an RC structure. Then, when laying the precast blocks on corresponding ones of the foundation piles that have been cast in block by block, insert the sheath pipes of the number corresponding to the foundation piles provided in the precast blocks into the pile heads of the foundation piles. When positioning the precast block, the level adjustment support mechanism installed on the support on the foundation pile during positioning absorbs the height difference of the support on the foundation pile due to construction errors, etc. A wharf construction method using a precast pier structure, characterized by equalizing the supporting reaction force of a foundation pile by weight.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31187896A JP3150634B2 (en) | 1996-11-22 | 1996-11-22 | Precast pier structure and wharf construction method using it |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP31187896A JP3150634B2 (en) | 1996-11-22 | 1996-11-22 | Precast pier structure and wharf construction method using it |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10152822A true JPH10152822A (en) | 1998-06-09 |
JP3150634B2 JP3150634B2 (en) | 2001-03-26 |
Family
ID=18022505
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP31187896A Expired - Fee Related JP3150634B2 (en) | 1996-11-22 | 1996-11-22 | Precast pier structure and wharf construction method using it |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3150634B2 (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000248526A (en) * | 1999-03-03 | 2000-09-12 | Nippon Steel Corp | Pier structure and its construction method |
JP2002294653A (en) * | 2001-04-02 | 2002-10-09 | Taisei Corp | Construction members and construction methods for floating structures |
JP2003027418A (en) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | Concrete structure and method for constructing the same |
JP2006070614A (en) * | 2004-09-03 | 2006-03-16 | Chiyoda Engineering Consultants Co Ltd | Reinforcing structure of steel girder bridge |
JP2007077575A (en) * | 2005-09-09 | 2007-03-29 | Naikai Aakit:Kk | Precast concrete girder |
JP2007197975A (en) * | 2006-01-25 | 2007-08-09 | Taisei Corp | Connection structure between pile head and precast girder and connection method thereof |
JP2008274635A (en) * | 2007-04-27 | 2008-11-13 | Ps Mitsubishi Construction Co Ltd | Construction method for truss bridge |
JP2014167216A (en) * | 2013-02-28 | 2014-09-11 | Nippon Ps Co Ltd | Pier structure and reconstruction method |
CN104631309A (en) * | 2015-01-19 | 2015-05-20 | 郑州航空工业管理学院 | Method for leveling bottom face of prefabricated beam slab installed on bridge support |
CN106536825A (en) * | 2014-06-30 | 2017-03-22 | 株式会社高知丸高 | Bridge construction method and bridge structure |
CN111945657A (en) * | 2020-09-21 | 2020-11-17 | 中交第四航务工程局有限公司 | A kind of wharf upgrading and transformation structure and wharf upgrading and transformation construction method |
CN113684785A (en) * | 2021-08-23 | 2021-11-23 | 中交(天津)疏浚工程有限公司 | Construction process of pile foundation wharf |
CN113700022A (en) * | 2020-08-19 | 2021-11-26 | 广东省建筑设计研究院有限公司 | H-shaped bidirectional row pile foundation with prestressed pull rod and anti-pushing retaining wall |
CN115324065A (en) * | 2022-07-20 | 2022-11-11 | 中铁一局集团建筑安装工程有限公司 | Bridge supporting integrated supporting system |
WO2023280260A1 (en) * | 2021-07-07 | 2023-01-12 | 中交第三航务工程勘察设计院有限公司 | Installation-type high-piled wharf structure and construction method |
WO2024007203A1 (en) * | 2022-07-06 | 2024-01-11 | 中交第二航务工程局有限公司 | New superstructure for high-piled wharf, and construction apparatus and construction method therefor |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6075748B2 (en) * | 2012-08-01 | 2017-02-08 | フューチャーイヴテクノロジー株式会社 | LED lamp |
-
1996
- 1996-11-22 JP JP31187896A patent/JP3150634B2/en not_active Expired - Fee Related
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000248526A (en) * | 1999-03-03 | 2000-09-12 | Nippon Steel Corp | Pier structure and its construction method |
JP2002294653A (en) * | 2001-04-02 | 2002-10-09 | Taisei Corp | Construction members and construction methods for floating structures |
JP4516235B2 (en) * | 2001-04-02 | 2010-08-04 | 大成建設株式会社 | Construction members and construction methods for floating structures |
JP2003027418A (en) * | 2001-07-11 | 2003-01-29 | Nippon Concrete Ind Co Ltd | Concrete structure and method for constructing the same |
JP4519368B2 (en) * | 2001-07-11 | 2010-08-04 | 日本コンクリート工業株式会社 | Concrete structure and construction method thereof |
JP2006070614A (en) * | 2004-09-03 | 2006-03-16 | Chiyoda Engineering Consultants Co Ltd | Reinforcing structure of steel girder bridge |
JP2007077575A (en) * | 2005-09-09 | 2007-03-29 | Naikai Aakit:Kk | Precast concrete girder |
JP4633584B2 (en) * | 2005-09-09 | 2011-02-16 | 株式会社ナイカイアーキット | Precast concrete girder |
JP2007197975A (en) * | 2006-01-25 | 2007-08-09 | Taisei Corp | Connection structure between pile head and precast girder and connection method thereof |
JP2008274635A (en) * | 2007-04-27 | 2008-11-13 | Ps Mitsubishi Construction Co Ltd | Construction method for truss bridge |
JP2014167216A (en) * | 2013-02-28 | 2014-09-11 | Nippon Ps Co Ltd | Pier structure and reconstruction method |
CN106536825A (en) * | 2014-06-30 | 2017-03-22 | 株式会社高知丸高 | Bridge construction method and bridge structure |
CN104631309A (en) * | 2015-01-19 | 2015-05-20 | 郑州航空工业管理学院 | Method for leveling bottom face of prefabricated beam slab installed on bridge support |
CN104631309B (en) * | 2015-01-19 | 2016-06-08 | 郑州航空工业管理学院 | The method of precast beam bottom surface leveling installed by a kind of bridge pad |
CN113700022A (en) * | 2020-08-19 | 2021-11-26 | 广东省建筑设计研究院有限公司 | H-shaped bidirectional row pile foundation with prestressed pull rod and anti-pushing retaining wall |
CN111945657A (en) * | 2020-09-21 | 2020-11-17 | 中交第四航务工程局有限公司 | A kind of wharf upgrading and transformation structure and wharf upgrading and transformation construction method |
WO2023280260A1 (en) * | 2021-07-07 | 2023-01-12 | 中交第三航务工程勘察设计院有限公司 | Installation-type high-piled wharf structure and construction method |
CN113684785A (en) * | 2021-08-23 | 2021-11-23 | 中交(天津)疏浚工程有限公司 | Construction process of pile foundation wharf |
CN113684785B (en) * | 2021-08-23 | 2023-06-16 | 中交(天津)疏浚工程有限公司 | Construction process of pile foundation wharf |
WO2024007203A1 (en) * | 2022-07-06 | 2024-01-11 | 中交第二航务工程局有限公司 | New superstructure for high-piled wharf, and construction apparatus and construction method therefor |
CN115324065A (en) * | 2022-07-20 | 2022-11-11 | 中铁一局集团建筑安装工程有限公司 | Bridge supporting integrated supporting system |
Also Published As
Publication number | Publication date |
---|---|
JP3150634B2 (en) | 2001-03-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3150634B2 (en) | Precast pier structure and wharf construction method using it | |
WO2018000879A1 (en) | Steel pipe prestressed cast-in-place stabilizing sealed pile device | |
JP5053339B2 (en) | Deadline wall | |
JP4992042B2 (en) | Precast horizontal beam and pier using it | |
CN110777661A (en) | Flange connection prefabricated assembly pier structure and construction method thereof | |
CN103469732B (en) | Construction method of preformed holes for foundation bolts of bridge support | |
WO2006038620A1 (en) | Joined part structure of pedestal and method of joining pedestal | |
CN110700113A (en) | Prestress applying device of non-prestressed beam bridge and construction method thereof | |
CN115162358A (en) | Assembled steel-concrete combined support system for foundation pit engineering and construction method | |
CN114561881A (en) | Longitudinal deviation-rectifying and resetting method suitable for soft soil foundation bridge | |
CN113152515A (en) | Modular assembly type prestress retaining wall and construction method thereof | |
CN117449261A (en) | Plate-type ship backing member mounting process | |
CN217438744U (en) | Pier reinforcing device for pushing construction of three-main-truss steel truss girder bridge | |
CN107630564B (en) | Construction method for reinforced structure of concrete beam | |
KR20120100052A (en) | Bridge leg correcting method using oil compressure jack and broken parts compensation structure | |
US20220325492A1 (en) | Prefabricated, modular hydropower foundation system for soil conditions | |
JP6031626B1 (en) | Replacing the seismic isolation device in the pile head seismic isolation structure | |
CN115354579A (en) | Prefabricated pile foundation construction platform and pile foundation construction method | |
CN111155365B (en) | Assembled floating unit plate and assembly connection construction method | |
JP5513229B2 (en) | Offshore construction method | |
JP5853415B2 (en) | Reinforcement structure and construction method for floating structures, reinforcement structure for bridges | |
Xiaokang et al. | A New Composite Wall Inner Tie System Applied in Reinforced Concrete Modular Integrated Construction | |
KR102663229B1 (en) | Low friction mold for slipform, slipform structure system, and phased wall construction method using the same | |
CN117306534B (en) | Reverse construction method for assembled marine pile foundation building | |
CN216616978U (en) | Detect hole shutoff filling structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090119 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090119 Year of fee payment: 8 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090119 Year of fee payment: 8 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090119 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090119 Year of fee payment: 8 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100119 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100119 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110119 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110119 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120119 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130119 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140119 Year of fee payment: 13 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |