JPH08128039A - Anchor construction method - Google Patents
Anchor construction methodInfo
- Publication number
- JPH08128039A JPH08128039A JP26753794A JP26753794A JPH08128039A JP H08128039 A JPH08128039 A JP H08128039A JP 26753794 A JP26753794 A JP 26753794A JP 26753794 A JP26753794 A JP 26753794A JP H08128039 A JPH08128039 A JP H08128039A
- Authority
- JP
- Japan
- Prior art keywords
- casing pipe
- pipe
- water
- pedestal
- packer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 132
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 77
- 238000012856 packing Methods 0.000 claims abstract description 19
- 239000000463 material Substances 0.000 claims description 95
- 238000003780 insertion Methods 0.000 claims description 55
- 230000037431 insertion Effects 0.000 claims description 55
- 239000011440 grout Substances 0.000 claims description 54
- 230000000903 blocking effect Effects 0.000 claims description 53
- 238000005553 drilling Methods 0.000 claims description 35
- 238000002347 injection Methods 0.000 claims description 31
- 239000007924 injection Substances 0.000 claims description 31
- 238000004078 waterproofing Methods 0.000 claims description 6
- 239000004744 fabric Substances 0.000 claims description 5
- 238000007789 sealing Methods 0.000 claims description 4
- 239000004576 sand Substances 0.000 claims description 3
- 239000008233 hard water Substances 0.000 claims 1
- JOYRKODLDBILNP-UHFFFAOYSA-N Ethyl urethane Chemical compound CCOC(N)=O JOYRKODLDBILNP-UHFFFAOYSA-N 0.000 abstract description 5
- 238000000034 method Methods 0.000 description 15
- 238000010586 diagram Methods 0.000 description 9
- 239000004568 cement Substances 0.000 description 7
- 230000005484 gravity Effects 0.000 description 6
- 239000008267 milk Substances 0.000 description 6
- 210000004080 milk Anatomy 0.000 description 6
- 235000013336 milk Nutrition 0.000 description 6
- 239000002689 soil Substances 0.000 description 5
- 238000004873 anchoring Methods 0.000 description 4
- 239000011343 solid material Substances 0.000 description 4
- 238000007599 discharging Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 235000019353 potassium silicate Nutrition 0.000 description 2
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 2
- 229920001875 Ebonite Polymers 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、アースアンカーを施工
する際に使用する台座兼用止水ボックスとこれを用いた
アンカー工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pedestal and water blocking box used when constructing an earth anchor, and an anchor construction method using the box.
【0002】[0002]
【従来の技術】土留壁や擁壁を保持する目的で、従来、
アンカー工法が広く用いられている。このアンカー工法
は、削孔機に接続したケーシングパイプ内に削孔用水を
送水し乍ら地盤をケーシングパイプ先端の削孔ビットで
地盤を削孔し、所望深さの削孔を終えたところで、ケー
シングパイプ内にセメントミルク等のグラウト材を一次
注入してPC鋼線等の引張材を挿入し、そして、ケーシ
ングパイプを引き抜き乍らグラウト材をアンカー孔に加
圧注入(二次注入)して地盤中にアンカー体を造成した
後、緊張した引張材の端部を土留壁の外側の台座に定着
させるもので、ケーシングパイプは削孔深さに応じて順
次接続される。2. Description of the Related Art Conventionally, for the purpose of holding retaining walls and retaining walls,
The anchor method is widely used. This anchor construction method, water for drilling is fed into the casing pipe connected to the drilling machine, and the ground is drilled with the drilling bit at the tip of the casing pipe to finish the drilling to the desired depth. Primary injection of grout material such as cement milk into the casing pipe, insertion of tensile material such as PC steel wire, and pulling out the casing pipe, pressure injection (secondary injection) of the grout material into the anchor hole. After forming the anchor body in the ground, the end of the tensioned tension member is fixed to the pedestal outside the earth retaining wall, and the casing pipes are sequentially connected according to the drilling depth.
【0003】ところで、従来、ケーシングパイプによる
削孔時に、ケーシングパイプを伝わって削孔スライム
(地下水や掘削ズリ)が上昇してくるため、土留壁の外
側に止水ボックスを取り付けてケーシングパイプと土留
壁との間の止水を行うことがある。By the way, conventionally, when drilling a casing pipe, the drilling slime (groundwater or drilling scrap) rises along the casing pipe. Therefore, a water-stop box is attached to the outside of the retaining wall to attach the casing pipe and the soil retaining pipe. Water may be stopped from the wall.
【0004】然し、従来の止水ボックスは単に止水を図
るものであるため、引張材の定着時にはこれを台座と交
換する煩わしさがあり、又、この交換作業中に出水を招
く虞も指摘されていた。However, since the conventional water shut-off box merely serves to stop the water, it is troublesome to replace the tension member with the pedestal at the time of fixing, and it is pointed out that water may come out during the replacement work. It had been.
【0005】そこで、斯かる不具合を解決するものとし
て、特開平4−198522号公報には、引張材の定着
時に台座として使用することのできる止水ボックスとこ
れを用いたアンカー工法が開示されている。As a solution to such a problem, Japanese Patent Laid-Open No. 4-198522 discloses a water-stop box that can be used as a pedestal when fixing a tension material and an anchor construction method using the same. There is.
【0006】[0006]
【発明が解決しようとする課題】然し、斯かる止水ボッ
クスにあっては、止水ボックスのケーシングパイプ挿入
孔に挿入したケーシングパイプとの水密性が必ずしも十
分なものとはいえなかった。However, in such a water shut-off box, the water tightness with the casing pipe inserted into the casing pipe insertion hole of the water shut-off box was not always sufficient.
【0007】又、斯かる止水ボックスを用いたアンカー
工法は、最終ユニットパイプとその前段のユニットパイ
プの引き抜き回収前に、ケーシングパイプ内を止水パッ
カーで閉塞し乍ら止水ボックスの注入口から止水材を注
入して止水を行うが、従来、一般に使用されるセメント
ミルクはW/C(水セメント比)=55%で比重が約
1.79であるのに対し、止水材は通常、水ガラスや水
ガラスとセメントミルクの混合物が使用され、これらは
セメントミルクより比重が軽い。In addition, the anchor construction method using such a water shut-off box is such that the inside of the casing pipe is closed by a water shut-off packer before the final unit pipe and the unit pipe of the preceding stage are pulled out and collected, and the inlet of the water shut-off box is closed. Water is stopped by injecting a water-stopping material from it, but conventionally cement milk generally used has a W / C (water-cement ratio) of 55% and a specific gravity of about 1.79. Usually uses water glass or a mixture of water glass and cement milk, which have a lower specific gravity than cement milk.
【0008】そのため、斯様に比重の小さな止水材を止
水ボックスの注入口から注入すると、止水材とセメント
ミルクが反応したゲル状の止水材固形物がケーシングパ
イプ中を浮き上がって止水ボックスから止水パッカーに
亘り付着固結し、ケーシングパイプや止水パッカーが最
後に回収できなくなる不具合が指摘されている。Therefore, when a water-stopping material having such a small specific gravity is injected from the inlet of the water-stopping box, a gel-like water-stopping material solid, which is a reaction between the water-stopping material and cement milk, floats up inside the casing pipe and stops. It has been pointed out that there is a problem that the casing pipe and the water blocking packer cannot be finally collected due to the adhesion and solidification from the water box to the water blocking packer.
【0009】本発明は斯かる実情に鑑み案出されたもの
で、ケーシングパイプとの水密性に優れた台座兼用止水
ボックスを用いたアンカー工法であって、従来に比し最
後のケーシングパイプの引き抜き回収が容易なアンカー
工法を提供することを目的とする。The present invention has been devised in view of such circumstances, and is an anchor construction method using a pedestal and water blocking box which is excellent in watertightness with the casing pipe, and is the last casing pipe compared to the conventional one. It is an object of the present invention to provide an anchor method that can be easily pulled out and collected.
【0010】[0010]
【課題を解決するための手段】斯かる目的を達成するた
め、請求項1に係るアンカー工法は、土留壁や擁壁等の
壁面にシール部材を介してボルト締めされる接合用プレ
ートと、接合用プレートを貫通してアンカー施工角度に
挿着され、ケーシングパイプの先端に装着する削孔ビッ
トより大きな内径を有し、土留壁や擁壁等のアンカー施
工位置に予め設けられたケーシングパイプ挿入孔に挿入
可能な挿入パイプと、接合用プレートに挿着された挿入
パイプの端部を覆って当該接合用プレートに取り付き、
削孔ビットより大径なケーシングパイプ挿入孔が挿入パ
イプと同軸上に形成され、側壁に削孔用水及び土砂の排
出口と止水材注入用の注入口が形成されたボックス状の
台座本体とからなる台座兼用止水ボックスの台座部を、
土留壁等に設けたケーシングパイプ挿入孔に上記挿入パ
イプを挿入してその壁面にボルト締めすると共に、上記
台座本体にフランジ部を介してボルト締め可能で外周に
左ネジが刻設され、内周にケーシングパイプの挿入方向
に順次縮径するテーパ部が成形された円筒状の止水部内
管と、止水部内管内に2層に装着され、削孔ビットより
小径な内径を有する円筒状の軟質止水用ゴムパッキン及
び削孔ビットより小径な内径を有し、外周に止水部内管
に形成されたテーパ部と合致するテーパ部を有する円筒
状の硬質止水用ゴムパッキンと、止水部内管の先端に螺
着され、中央に削孔ビットより小径なケーシングパイプ
挿入孔が形成された押しキャップとからなる台座兼用止
水ボックスの止水部を、削孔ビット上方のケーシングパ
イプ外周に仮止めし、台座部へのケーシングパイプの挿
入に伴い、止水部の止水部内管を台座部の台座本体にシ
ール部材を介してボルト締めした後、ケーシングパイプ
の外周を伝わって上昇する削孔スライムを、上記排出口
に装着したバルブで水量を調節し乍ら排出して削孔深さ
に応じケーシングパイプを順次接続して地盤を削孔し、
所望深さの削孔を終えたところで、ケーシングパイプ内
に、加圧注入されるグラウト材の注入圧でケーシングパ
イプ内を開放,閉塞するように形成された口元パッカー
と、当該口元パッカーの取付位置よりも先端側に位置
し、口元パッカーを貫通するグラウト材注入パイプに接
続した切断可能なグラウト材注入ホースから注入される
グラウト材で膨張してアンカー孔を閉塞する布袋状のフ
リーパッカーとを後端側に取り付けた引張材を挿入し、
次いで、アンカー孔へのグラウト材の加圧注入で口元パ
ッカーによるケーシングパイプ内の開放,閉塞を繰り返
して、地盤中にアンカー体を造成し乍らケーシングパイ
プを順次引き抜き回収し、最後のケーシングパイプの先
端よりフリーパッカーがアンカー孔内に突出したところ
で、フリーパッカー内にグラウト材を注入しこれを膨張
させてアンカー孔を閉塞すると共に口元パッカーを収縮
させ、止水材注入用の上記注入口より止水材を注入しつ
つケーシングパイプの後端からグラウト材を注入してケ
ーシングパイプを上下方向にスラスト運動し、止水材注
入完了後、ケーシングパイプと口元パッカーを引き抜き
回収し、台座部より止水部を取り外してグラウト材の養
生後、引張材の端部を緊張させてこれを台座部に定着す
るものである。In order to achieve such an object, an anchoring method according to a first aspect of the present invention relates to a joining plate bolted to a wall surface such as a retaining wall or a retaining wall via a seal member, and a joining plate. A casing pipe insertion hole that is inserted through the plate for installation at the anchor construction angle and has a larger inner diameter than the drill bit installed at the tip of the casing pipe, and is provided in advance at the anchor construction position such as a retaining wall or retaining wall. And an attachment pipe that can be inserted into the connection plate, and cover the end of the insertion pipe inserted into the connection plate, and attach to the connection plate.
A box-shaped pedestal body in which a casing pipe insertion hole with a diameter larger than that of the drilling bit is formed coaxially with the insertion pipe, and a side wall has an outlet for water and earth and sand and an inlet for injecting waterproofing material. The pedestal part of the water-stop box for pedestal and
Insert the above-mentioned insertion pipe into the casing pipe insertion hole provided in the earth retaining wall etc. and bolt it to the wall surface, and the pedestal body can be bolted via the flange part and the left screw is engraved on the outer circumference, the inner circumference A cylindrical water stop inner pipe with a tapered part that is gradually reduced in diameter in the direction of insertion of the casing pipe, and a cylindrical soft pipe that is installed in two layers inside the water stop inner pipe and has an inner diameter smaller than the drilling bit. Rubber packing for water stop and a rubber packing for cylindrical water stop having a smaller inner diameter than the drill bit and a taper part on the outer periphery that matches the taper part formed on the pipe inside the water stop part, and the inside of the water stop part Temporarily attach the water stop part of the pedestal water-stop box that consists of a push cap that is screwed to the tip of the pipe and has a casing pipe insertion hole with a diameter smaller than the hole drill bit to the outer periphery of the casing pipe above the hole drill bit. Stop , With the insertion of the casing pipe into the pedestal part, after tightening the inner pipe of the water blocking part to the pedestal body of the pedestal with the seal member, bolt the drilling slime that rises along the outer periphery of the casing pipe. , Adjusting the amount of water with the valve installed in the discharge port, discharging it and connecting the casing pipes sequentially according to the drilling depth to drill the ground,
At the end of drilling to the desired depth, a mouth packer formed to open and close the inside of the casing pipe by the injection pressure of the grout material to be injected under pressure, and the mounting position of the mouth packer. The cloth bag-like free packer that is located closer to the tip side than the cloth bag-like bag that expands with the grout material injected from the grout material injection hose that is connected to the grout material injection pipe that passes through the mouth packer and closes the anchor hole Insert the tension material attached to the end side,
Next, the casing pipe is repeatedly opened and closed by the mouth packer by pressure injection of grout material into the anchor hole, the anchor body is created in the ground, and the casing pipe is sequentially pulled out and collected. When the free packer protrudes from the tip into the anchor hole, grout material is injected into the free packer and expanded to close the anchor hole and contract the mouth packer, and stop from the injection port for injecting the waterproofing material. While pouring water material, grout material is injected from the rear end of the casing pipe to thrust the casing pipe up and down, and after the injection of the water blocking material, the casing pipe and mouth packer are pulled out and collected, and water is stopped from the pedestal part. After the portion is removed and the grout material is cured, the end portion of the tension material is tensioned to fix it to the pedestal portion.
【0011】[0011]
【作用】請求項1に係るアンカー工法によれば、台座兼
用止水ボックスの台座部を土留壁等に設けたケーシング
パイプ挿入孔にその挿入パイプを挿入して壁面にボルト
締めすると共に、台座兼用止水ボックスの止水部を削孔
ビット上方のケーシングパイプ外周に仮止めし、台座部
へのケーシングパイプの挿入に伴い、止水部の止水部内
管を台座部の台座本体にシール部材を介してボルト締め
すれば、台座部に止水材が連結されることとなる。According to the anchor construction method of the first aspect, the pedestal portion of the pedestal / water-stop box is inserted into the casing pipe insertion hole provided in the earth retaining wall or the like and bolted to the wall surface. Temporarily fix the water shut off part of the water shut off box to the outer circumference of the casing pipe above the drill bit, and insert the casing pipe of the water shut off part along with the insertion of the casing pipe into the pedestal part. If the bolts are tightened through, the water blocking material will be connected to the pedestal portion.
【0012】そして、ケーシングパイプの外周を伝わっ
て上昇する削孔スライムを、排出口に装着したバルブで
水量を調節し乍ら排出して削孔深さに応じケーシングパ
イプを順次接続して地盤を削孔し、所望深さの削孔を終
えたところで、ケーシングパイプ内に、口元パッカーと
フリーパッカーを装着した引張材を挿入し、アンカー孔
へのグラウト材の加圧注入で口元パッカーによるケーシ
ングパイプ内の開放,閉塞を繰り返して、地盤中にアン
カー体を造成し乍らケーシングパイプを順次引き抜き回
収し、最後のケーシングパイプの先端よりフリーパッカ
ーがアンカー孔内に突出したところで、フリーパッカー
内にグラウト材を注入しこれを膨張させてアンカー孔を
閉塞すると共に口元パッカーを収縮させ、止水材注入用
の上記注入口より止水材を注入しつつケーシングパイプ
の後端からグラウト材を注入してケーシングパイプを上
下方向にスラスト運動し、止水材注入完了後、ケーシン
グパイプと口元パッカーを引き抜き回収して、台座部よ
り止水部を取り外す。Then, the drilling slime that rises along the outer circumference of the casing pipe is discharged by adjusting the amount of water with a valve attached to the discharge port, and the casing pipes are sequentially connected according to the drilling depth to form the ground. After drilling and finishing drilling to the desired depth, insert tension material with mouth packer and free packer into the casing pipe, and pressurize grout material into anchor hole to make casing pipe by mouth packer. By repeatedly opening and closing the inside, an anchor body is created in the ground, the casing pipe is sequentially pulled out and collected, and when the free packer projects from the tip of the last casing pipe into the anchor hole, the grout is put in the free packer. Inject the material and expand it to close the anchor hole and contract the mouth packer, and from the injection port for injecting the waterproofing material. While pouring water material, grout material is injected from the rear end of the casing pipe to thrust the casing pipe up and down.After the injection of the water stop material, the casing pipe and mouth packer are pulled out and collected, and stopped from the pedestal part. Remove the water section.
【0013】そして、グラウト材の養生後、引張材の端
部を緊張させてこれを台座部に定着することでアンカー
工法が完了するが、本発明工法によれば、上述したよう
に最後のケーシングパイプの先端からフリーパッカーが
突出したところで、フリーパッカーを膨張させてアンカ
ー孔を閉塞すると共に、台座部の注入口より止水材を注
入すると同時に、ケーシングパイプ後端からグラウト材
を注入してケーシングパイプ先端よりグラウト材を排出
させ乍らケーシングパイプをスラスト運動するので、止
水材とグラウト材が反応したゲル状の止水材固形物がケ
ーシングパイプ中を浮き上がってその内周に付着固結す
ることがない。Then, after curing the grout material, the anchor construction method is completed by tensioning the end portion of the tension material and fixing it to the pedestal portion. According to the construction method of the present invention, as described above, the last casing is used. When the free packer protrudes from the tip of the pipe, the free packer is inflated to close the anchor hole, and the water blocking material is injected from the injection port of the pedestal part, and at the same time, the grout material is injected from the rear end of the casing pipe. Since the casing pipe is thrust while the grout material is discharged from the tip of the pipe, the gel-like solid material of the water-stopping material, which has reacted with the water-stopping material and the grout material, floats up inside the casing pipe and adheres to its inner circumference to be solidified. Never.
【0014】[0014]
【実施例】以下、本発明の実施例を図面に基づき詳細に
説明する。図1乃至図5は請求項1に係るアンカー工法
の一実施例に用いる台座兼用止水ボックスの構造を示
し、図1に於て、1は地盤3に設けた土留壁で、当該土
留壁1にはアンカー施工位置に予めケーシングパイプ挿
入孔5が設けられており、当該ケーシングパイプ挿入孔
5に挿入パイプ7を挿入して、本実施例に係る台座兼用
止水ボックス9が土留壁1の外側の壁面1aに取り付け
られている。Embodiments of the present invention will now be described in detail with reference to the drawings. 1 to 5 show the structure of a pedestal and water blocking box used in an embodiment of the anchor construction method according to claim 1. In FIG. 1, 1 is a soil retaining wall provided on the ground 3, and the soil retaining wall 1 A casing pipe insertion hole 5 is provided in advance at the anchor construction position, and the insertion pipe 7 is inserted into the casing pipe insertion hole 5 so that the pedestal and water blocking box 9 according to the present embodiment is located outside the earth retaining wall 1. Is attached to the wall surface 1a.
【0015】台座兼用止水ボックス9は、ウレタンスポ
ンジ(シール部材)11を介して土留壁1の壁面1aに
取り付く台座部13と、当該台座部13にゴムパッキン
(シール部材)15を介して連結される止水部17とで
構成されており、台座部13は、上記ウレタンスポンジ
11を介して壁面1aにボルト締めされる接合用プレー
ト19と、当該接合用プレート19を貫通してアンカー
施工角度に挿着された挿入パイプ7、そして、挿入パイ
プ7の端部7aを覆って接合用プレート19に取り付く
ボックス状の台座本体21を主な構成要素とする。The pedestal / waterproof box 9 is connected to a pedestal portion 13 attached to the wall surface 1a of the earth retaining wall 1 via a urethane sponge (sealing member) 11 and the pedestal portion 13 via a rubber packing (sealing member) 15. The pedestal portion 13 includes a joining plate 19 that is bolted to the wall surface 1a through the urethane sponge 11 and an anchoring angle that penetrates the joining plate 19. The main components are the insertion pipe 7 that is inserted and attached, and a box-shaped pedestal body 21 that covers the end portion 7a of the insertion pipe 7 and is attached to the joining plate 19.
【0016】而して、上記接合用プレート19は、図2
及び図3に示すようにケーシングパイプ挿入孔5の開口
部を覆う大きさをもった一枚の肉厚な矩形状の板材から
なり、その四隅に設けたボルト孔23に取付用ボルト2
5を挿入して壁面1aにボルト締めされている。The joining plate 19 is shown in FIG.
And, as shown in FIG. 3, the casing pipe insertion hole 5 is made of a single thick rectangular plate material having a size to cover the opening portion, and the mounting bolts 2 are provided in the bolt holes 23 provided at the four corners thereof.
5 is inserted and bolted to the wall surface 1a.
【0017】そして、接合用プレート19の中央に挿入
パイプ7が貫通してその端部7aが接合用プレート19
に沿って開口しており、挿入パイプ7は、接合用プレー
ト19を壁面1aに固定したとき、上記ケーシングパイ
プ挿入孔5に挿入可能な角度を以って接合用プレート1
9に挿着されている。Then, the insertion pipe 7 penetrates through the center of the joining plate 19 and the end portion 7a thereof is joined to the joining plate 19.
The insertion pipe 7 is opened along with the joining plate 1 at an angle such that it can be inserted into the casing pipe insertion hole 5 when the joining plate 19 is fixed to the wall surface 1a.
It is attached to 9.
【0018】尚、図2中、27は壁面1a側に設けたホ
ールインアンカー(メス部)で、当該ホールインアンカ
ー27に取付用ボルト25が取り付くようになってい
る。又、接合用プレート19に取り付く台座本体21
は、図1乃至図3に示すように挿入パイプ7の端部7a
を挟んで接合用プレート19上に対向立設された略三角
形状の左右側板21a,21bと、挿入パイプ7と平行
に当該各側板21a,21b間に架け渡した斜板21c
と、接合用プレート19と直交する水平板21d、そし
て、挿入パイプ7と直交する方向に配置されて側板21
a,21bと斜板21c及び水平板21dの一辺に取り
付く正方形状の蓋板21eとで形成されてボックス形状
をなしている。In FIG. 2, 27 is a hole-in anchor (female portion) provided on the wall surface 1a side, and the mounting bolt 25 is attached to the hole-in anchor 27. Also, the pedestal body 21 attached to the joining plate 19
Is the end portion 7a of the insertion pipe 7 as shown in FIGS.
Left and right side plates 21a and 21b having a substantially triangular shape, which are erected so as to be opposed to each other on the plate 19 for joining, and a swash plate 21c laid between the side plates 21a and 21b in parallel with the insertion pipe 7.
A horizontal plate 21d orthogonal to the joining plate 19, and a side plate 21d arranged in a direction orthogonal to the insertion pipe 7.
It is formed by a and 21b, a swash plate 21c, and a square-shaped cover plate 21e attached to one side of the horizontal plate 21d to form a box shape.
【0019】そして、上記斜板21cに削孔用水及び土
砂の排出口29が取り付くと共に、止水材(瞬結材)注
入用の注入口31が一方の側板21aに並列して取り付
き、又、蓋板21eには後述する削孔ビットより大径な
ケーシングパイプ挿入孔33が挿入パイプ7と同軸上に
形成されており、当該ケーシングパイプ挿入孔33を挿
通して挿入パイプ7内にケーシングパイプ35を挿入す
るようになっている。The swash plate 21c is provided with a hole 29 for discharging water for drilling and sand, and an inlet 31 for injecting a water blocking material (instant binding material) is installed in parallel with one side plate 21a. A casing pipe insertion hole 33 having a diameter larger than that of a drill bit described later is formed in the cover plate 21e coaxially with the insertion pipe 7, and the casing pipe 35 is inserted into the insertion pipe 7 through the casing pipe insertion hole 33. Is designed to be inserted.
【0020】一方、止水部17は、図1及び図2に示す
ように上記台座本体21の蓋板21eに連結される円筒
状の止水部内管37と、当該止水部内管37内に2層に
装着され、外周に止水部内管37に形成されたテーパ部
37′と合致するテーパ部41′を有する円筒状の軟質
及び硬質の止水用ゴムパッキン39,41、そして、止
水部内管37の先端に冠着される押しキャップ43を構
成要素としており、止水部内管37の下端部に、上記蓋
板21eと同一形状のフランジ部材45が取り付けられ
ている。そして、当該フランジ部材45を蓋板21eに
ボルト締めすることによって、止水部内管37が台座本
体21に連結できるようになっている。On the other hand, as shown in FIGS. 1 and 2, the water shutoff portion 17 has a cylindrical water shutoff portion inner pipe 37 connected to the lid plate 21e of the pedestal body 21, and a water shutoff portion inner pipe 37. Cylindrical soft and hard rubber packings 39, 41 having a taper portion 41 'fitted on two layers and having a taper portion 37' formed on the water stop inner tube 37, and a water stop. A push cap 43 attached to the tip of the internal pipe 37 is a constituent element, and a flange member 45 having the same shape as the lid plate 21e is attached to the lower end of the water shut internal pipe 37. Then, by bolting the flange member 45 to the cover plate 21e, the water shut-off portion inner pipe 37 can be connected to the pedestal body 21.
【0021】又、止水部内管37の外周には図1,図2
及び図4に示すように左ネジ47が刻設されると共に、
ケーシングパイプ35の挿入方向に順次縮径するテーパ
部49がその内周に形成されており、当該内周に当接し
て上記止水用ゴムパッキン39,41が2層に装着され
ている。尚、両止水用ゴムパッキン39,41は、後述
する削孔ビットより小径な内径を以って成形されてい
る。1 and 2 are provided on the outer periphery of the water shut-off inner pipe 37.
And as shown in FIG. 4, the left screw 47 is engraved,
A taper portion 49 is formed on the inner circumference thereof, the diameter of which is gradually reduced in the insertion direction of the casing pipe 35, and the water blocking rubber packings 39 and 41 are attached in two layers in contact with the inner circumference. Both of the water blocking rubber packings 39 and 41 are formed with an inner diameter smaller than that of a drill bit described later.
【0022】そして、止水部内管37の先端に押しキャ
ップ43が螺合して冠着されており、当該押しキャップ
43には削孔ビットより小径なケーシングパイプ挿入孔
51が上記挿入パイプ7と同軸上に設けられている。そ
して、この押しキャップ43を締め付けることにより、
止水用ゴムパッキン39,41が夫々内方に変形してケ
ーシングパイプ35の外周に圧接するようになっている
が、一般にケーシングパイプ35による地盤3の削孔は
左回転である。A push cap 43 is screwed onto the tip of the inner pipe 37 of the water shut off portion and is capped, and a casing pipe insertion hole 51 having a diameter smaller than that of the drill bit is formed on the push cap 43 and the insertion pipe 7. It is provided on the same axis. Then, by tightening the push cap 43,
The water blocking rubber packings 39 and 41 are respectively deformed inward and pressed against the outer circumference of the casing pipe 35. Generally, the drilling of the ground 3 by the casing pipe 35 is left rotation.
【0023】そのため、作業者が止水部内管37に冠着
する押しキャップ43を締め付けて止水用ゴムパッキン
39,41をケーシングパイプ35の外周に圧接させた
後、地盤3をケーシングパイプ35で削孔すると、ケー
シングパイプ35との摩擦で止水用ゴムパッキン39,
41がケーシングパイプ35の回転を押しキャップ43
に伝達し、押しキャップ43が更に締め付けられるよう
になっている。Therefore, after the worker tightens the push cap 43 that covers the inner pipe 37 of the water stop portion to press the rubber gaskets 39 and 41 for water stop against the outer periphery of the casing pipe 35, the ground 3 is covered by the casing pipe 35. When the holes are drilled, the rubber packing 39 for waterproofing is rubbed by friction with the casing pipe 35.
41 pushes the rotation of the casing pipe 35 and caps 43
The push cap 43 is further tightened.
【0024】従って、上記台座兼用止水ボックス9は、
ケーシングパイプ35による地盤3の削孔に伴い、押し
キャップ43が自動的に締め付けられて止水用ゴムパッ
キン39,41とケーシングパイプ35との水密性が確
実に図られることとなる。Therefore, the above-mentioned pedestal and water blocking box 9 is
With the drilling of the ground 3 by the casing pipe 35, the push cap 43 is automatically tightened, and the watertightness between the water blocking rubber packings 39 and 41 and the casing pipe 35 is reliably achieved.
【0025】尚、ケーシングパイプ35によってある程
度押しキャップ43が締め付けられると、ケーシングパ
イプ35と止水用ゴムパッキン39との間に滑りが発生
するため、削孔中、常時押しキャップ43がケーシング
パイプ35の回転で締め付けられることはない。When the pushing cap 43 is tightened to some extent by the casing pipe 35, slippage occurs between the casing pipe 35 and the water blocking rubber packing 39, so that the pushing cap 43 is constantly pushed during drilling. It is not tightened by the rotation of.
【0026】止水部17はこのように構成されており、
当該止水部17は図5に示すように削孔ビット53上方
のケーシングパイプ35の外周に仮止めされ、台座部1
3へのケーシングパイプ35の挿入に伴い、上記フラン
ジ部材45が台座部13の台座本体21にボルト締めさ
れて連結される。The water stop portion 17 is constructed in this way,
As shown in FIG. 5, the water stop portion 17 is temporarily fixed to the outer periphery of the casing pipe 35 above the drill bit 53, and the pedestal portion 1
The flange member 45 is bolted to the pedestal body 21 of the pedestal portion 13 to be connected with the insertion of the casing pipe 35 into the pedestal 3.
【0027】本実施例に用いる台座兼用止水ボックス9
はこのように構成されており、斯かる台座兼用止水ボッ
クス9を用いて請求項1に係るアンカー工法の一実施例
は以下の如く施工される。A pedestal and water-stop box 9 used in this embodiment
Is constructed in this way, and an embodiment of the anchor construction method according to claim 1 is constructed as follows using such a pedestal and water blocking box 9.
【0028】先ず、従来と同様な方法で地盤3中に土留
壁1を設けて連壁を構築した後、連壁内の地盤を掘削す
る。そして、図6に示すようにアンカーの施工位置まで
連壁内の地盤3′を掘削したところで、コアカッター
(図示せず)を用いて土留壁1のアンカーの施工位置に
ケーシングパイプ挿入孔5を設ける。First, the soil retaining wall 1 is provided in the ground 3 to construct a connecting wall by a method similar to the conventional method, and then the ground in the connecting wall is excavated. Then, as shown in FIG. 6, when the ground 3'in the connecting wall is excavated to the anchor construction position, a casing pipe insertion hole 5 is formed at the anchor construction position of the soil retaining wall 1 using a core cutter (not shown). Set up.
【0029】そして、このケーシングパイプ挿入孔5に
挿入パイプ7を挿入し乍ら、土留壁1の壁面1aにウレ
タンスポンジ11を介して接合用プレート19をボルト
締めし、台座兼用止水ボックス9の台座部13を固定す
る。Then, the insertion pipe 7 is inserted into the casing pipe insertion hole 5, and the bonding plate 19 is bolted to the wall surface 1a of the earth retaining wall 1 with the urethane sponge 11 interposed therebetween, so that the water blocking box 9 for the pedestal also serves. The pedestal 13 is fixed.
【0030】一方、図7に示すように削孔機に接続した
ケーシングパイプ35の先端には削孔ビット53を取り
付けるが、当該削孔ビット53の取付けに先立ち、台座
兼用止水ボックス9の止水部17を予め削孔ビット53
上方のケーシングパイプ35の外周に仮止めしておく。On the other hand, as shown in FIG. 7, a boring bit 53 is attached to the tip of the casing pipe 35 connected to the boring machine. Prior to the attachment of the boring bit 53, the pedestal / waterproof box 9 is stopped. The water portion 17 is preliminarily drilled with a bit 53
It is temporarily fixed to the outer circumference of the upper casing pipe 35.
【0031】次に、図7に示すように削孔ビット53を
装着したケーシングパイプ35を、台座部13の蓋板2
1eに設けたケーシングパイプ挿入孔35から挿入パイ
プ7を介してケーシングパイプ挿入孔5へと挿通させ乍
ら、止水部17の止水部内管37をフランジ部材45を
介して蓋板21eにゴムパッキン15を挟んでボルト締
めし、図8の如く台座部13に止水部17を連結させ
る。Next, as shown in FIG. 7, the casing pipe 35 fitted with the drill bit 53 is attached to the cover plate 2 of the pedestal portion 13.
The casing pipe insertion hole 35 provided in 1e is inserted into the casing pipe insertion hole 5 through the insertion pipe 7, and the water blocking portion inner pipe 37 of the water blocking portion 17 is attached to the cover plate 21e via the flange member 45. The packing 15 is sandwiched and bolted to connect the water stop portion 17 to the pedestal portion 13 as shown in FIG.
【0032】この後、図9に示すようにケーシングパイ
プ35内に削孔用水Wを送水し乍ら、従来と同様、ケー
シングパイプ35を順次接続して地盤3を削孔ビット5
3で削孔する。尚、ケーシングパイプ35の外周を伝わ
って上昇する削孔スライムW′は、図4に示すように排
出口29に装着したバルブ55で水量を調節し乍ら排出
する。After that, as shown in FIG. 9, the drilling water W is fed into the casing pipe 35, and the casing pipes 35 are sequentially connected in the same manner as in the conventional case, so that the ground 3 is drilled.
Drill at 3. The drilling slime W'which rises along the outer periphery of the casing pipe 35 is discharged by adjusting the amount of water with a valve 55 attached to the discharge port 29 as shown in FIG.
【0033】又、上述したように、削孔時のケーシング
パイプ35は左回転であるから、止水部17を台座部1
3に連結する際に、作業者が押しキャップ43を止水部
内管37に冠着させて止水用ゴムパッキン39,41を
ケーシングパイプ35の外周に軽く圧接させておけば、
ケーシングパイプ35が地盤3を削孔するに従い、ケー
シングパイプ35との摩擦で止水部17の止水用ゴムパ
ッキン39,41がケーシングパイプ35の回転を押し
キャップ43に伝達し、押しキャップ43が更に締め付
けられてケーシングパイプ35とのシール性が確保され
ることとなる。Further, as described above, since the casing pipe 35 is rotated counterclockwise at the time of drilling, the water blocking portion 17 is attached to the pedestal portion 1.
When connecting to 3, the operator caps the push cap 43 on the water blocking portion inner pipe 37 and lightly presses the water blocking rubber packings 39 and 41 onto the outer periphery of the casing pipe 35.
As the casing pipe 35 drills the ground 3, the water blocking rubber packings 39 and 41 of the water blocking portion 17 transmit the rotation of the casing pipe 35 to the pushing cap 43 by friction with the casing pipe 35, and the pushing cap 43 Further tightening ensures the sealing property with the casing pipe 35.
【0034】そして、所望深さの削孔を終えたところ
で、ケーシングパイプ35内にセメントミルク等のグラ
ウト材を一次注入して、図10に示すようにケーシング
パイプ35内に加圧注入されるグラウト材の注入圧でケ
ーシングパイプ35内を開放,閉塞するように構成され
た口元パッカー57と布袋状のフリーパッカー59を後
端側に装着した引張材61を挿入する。After finishing drilling to a desired depth, a grout material such as cement milk is primarily injected into the casing pipe 35, and the grout is pressurized and injected into the casing pipe 35 as shown in FIG. A tension member 61 having a mouth end packer 57 and a cloth bag-like free packer 59 configured to open and close the inside of the casing pipe 35 by the material injection pressure at the rear end side is inserted.
【0035】この口元パッカー57とフリーパッカー5
9は、本出願人が先に実願平5−26673号で提案し
たもので、以下、図11乃至図19に基づきその構成を
説明する。The mouth packer 57 and the free packer 5
No. 9 has been proposed by the present applicant in Japanese Patent Application No. 5-26673, and its configuration will be described below with reference to FIGS. 11 to 19.
【0036】口元パッカー57は、図11に示すように
アンカー孔63内からの被圧水圧よりも高圧な圧縮空気
の注入で膨張してケーシングパイプ35を閉塞すると共
に、被圧水圧より高い圧力で加圧注入されるグラウト材
の注入圧で収縮するように形成されたゴム製のパッカー
で、一方、フリーパッカー59は、口元パッカー57の
取付位置よりも先端側の引張材61を囲むように取り付
く布製のパッカーで、切断可能な注入ホース65を介し
て口元パッカー57を貫通するグラウト材注入パイプ6
7に接続されている。As shown in FIG. 11, the mouth packer 57 expands by injecting compressed air having a pressure higher than the pressurized water pressure from the anchor hole 63 to close the casing pipe 35, and at a pressure higher than the pressurized water pressure. A rubber packer formed so as to contract by the injection pressure of the grout material injected under pressure. On the other hand, the free packer 59 is attached so as to surround the tension material 61 on the tip side of the attachment position of the mouth packer 57. A grout material injection pipe 6 which is a cloth packer and penetrates the mouth packer 57 through a cutable injection hose 65.
Connected to 7.
【0037】そして、図12に示すように圧縮空気注入
ホース69を口元パッカー57に接続して圧縮空気Aを
注入すると、口元パッカー57は膨張してケーシングパ
イプ35を閉塞する。そして、この状態で図13に示す
ようにケーシングパイプ35の後端に装着したスイベル
71からグラウト材Gをケーシングパイプ35内に注入
していくと、図14に示すようにその注入圧で口元パッ
カー57が収縮してケーシングパイプ35の内壁35a
との間に形成された隙間73をグラウト材Gが通過して
いくので、地盤3中のアンカー定着部にアンカー体が徐
々に造成されていくこととなる。Then, as shown in FIG. 12, when the compressed air injecting hose 69 is connected to the mouth packer 57 to inject the compressed air A, the mouth packer 57 expands and closes the casing pipe 35. Then, in this state, as shown in FIG. 13, when the grout material G is injected into the casing pipe 35 from the swivel 71 mounted on the rear end of the casing pipe 35, as shown in FIG. 57 contracts to cause an inner wall 35a of the casing pipe 35.
Since the grout material G passes through the gap 73 formed between and, the anchor body is gradually formed in the anchor fixing portion in the ground 3.
【0038】そして、この注入状態で、接続されたケー
シングパイプ全体を徐々に引き抜けば、グラウト材Gの
注入圧で口元パッカー57は萎んでいるので引き抜きは
容易である。Then, in this injection state, if the entire connected casing pipe is gradually pulled out, the mouth packer 57 is shrunk by the injection pressure of the grout material G, so that the pulling out is easy.
【0039】而して、最後端側のケーシングパイプ35
を全てアンカー孔63から引き抜くと、図15に示すよ
うに口元パッカー57は次に接続されたケーシングパイ
プ35′内に位置する。そこで、斯かる状態で最後端側
のケーシングパイプ35を回収すると、次のケーシング
パイプ35′の後端開口部が大気圧状態となって圧力が
急激に低下するため、口元パッカー57はその空気圧で
瞬時に膨張してケーシングパイプ35′の内壁35a′
に圧接する。Thus, the casing pipe 35 on the rearmost end side
When all are pulled out from the anchor hole 63, the mouth packer 57 is located in the casing pipe 35 'connected next as shown in FIG. Therefore, when the casing pipe 35 on the rearmost end side is collected in such a state, the rear end opening of the next casing pipe 35 'becomes atmospheric pressure and the pressure drops sharply. The inner wall 35a 'of the casing pipe 35' expands instantaneously.
Press against.
【0040】そして、スイベル71をケーシングパイプ
35′の後端開口部に取り付けて再びアンカー孔63内
にグラウト材Gを加圧注入した後、これを引き抜き回収
するというように、削孔深さに応じ接続したケーシング
パイプに対し同じ作業を順次繰り返すことで、アンカー
定着部にアンカー体が次第に造成されていくこととな
る。Then, the swivel 71 is attached to the rear end opening of the casing pipe 35 ', the grout material G is pressure-injected into the anchor hole 63 again, and then the grout material G is extracted and recovered. By sequentially repeating the same operation for the casing pipes connected accordingly, the anchor body is gradually formed in the anchor fixing portion.
【0041】このようにアンカー体の造成が進んで、引
き上げた最後のケーシングパイプをアンカー孔63から
回収するに当たり、図16の如くフリーパッカー59が
ケーシングパイプ35″の先端から突出したところで、
グラウト材注入パイプ67にグラウト材供給ホース75
を接続してグラウト材をフリーパッカー59に注入すれ
ば、フリーパッカー59は膨張してアンカー孔63を閉
塞する。In this way, when the anchor body is constructed and the last casing pipe pulled up is recovered from the anchor hole 63, the free packer 59 projects from the tip of the casing pipe 35 "as shown in FIG.
Grout material supply hose 75 to grout material injection pipe 67
And the grout material is injected into the free packer 59, the free packer 59 expands and closes the anchor hole 63.
【0042】そして、図17に示すように、膨張して最
後のケーシングパイプ35″を閉塞している口元パッカ
ー57から圧縮空気Aを排出して、図18の如くケーシ
ングパイプ35″をアンカー孔63から引き抜いても、
アンカー孔63をフリーパッカー59が閉塞して被圧水
によるグラウト材Gの噴出を防止する。そして、図19
の如く注入ホース65を切断してその切断部を締め付
け、口元パッカー57を引張材67から取り除くことで
アンカー体の造成作業が終了する。Then, as shown in FIG. 17, the compressed air A is discharged from the mouth packer 57 which has expanded and closed the last casing pipe 35 ", and the casing pipe 35" is fixed to the anchor hole 63 as shown in FIG. Even if you pull it from
The free packer 59 closes the anchor hole 63 to prevent the grout material G from being jetted by the pressurized water. And in FIG.
As described above, the injection hose 65 is cut, the cut portion is tightened, and the mouth packer 57 is removed from the tension member 67, whereby the anchor body construction work is completed.
【0043】本実施例では、このように構成された口元
パッカー57とフリーパッカー59を用い、アンカー孔
63へのグラウト材Gの加圧注入で口元パッカー57に
よるケーシングパイプ35内の開放,閉塞を繰り返し
て、地盤3中にアンカー体を造成し乍らケーシングパイ
プ35を順次引き抜き回収していき、図20に示すよう
に引き上げた最後のケーシングパイプ35″をアンカー
孔63(ケーシングパイプ挿入孔5)から回収するに当
たり、ケーシングパイプ35″の先端からフリーパッカ
ー59が突出したところで、図16及び図17で述べた
ようにフリーパッカー59内にグラウト材を注入しこれ
を膨張させてケーシングパイプ挿入孔5を閉塞する。In the present embodiment, the mouth packer 57 and the free packer 59 thus constructed are used to open and close the inside of the casing pipe 35 by the mouth packer 57 by pressurizing the grout material G into the anchor holes 63. Repeatingly, the anchor pipe is formed in the ground 3, and the casing pipe 35 is sequentially pulled out and collected, and the last casing pipe 35 ″ pulled up is anchor hole 63 (casing pipe insertion hole 5) as shown in FIG. In recovering from the casing pipe 35 ″, when the free packer 59 projects from the tip of the casing pipe 35 ″, the grout material is injected into the free packer 59 and expanded to expand the casing pipe insertion hole 5 as shown in FIGS. To block.
【0044】次いで、図21に示すように台座部13の
注入口31からグラウト材Gと同等或いはこれよりも比
重のやや大きい止水材を注入すると同時に、口元パッカ
ー57を収縮させてケーシングパイプ35″後端のスイ
ベル71からグラウト材Gを注入する。そして、このと
き、ケーシングパイプ35″が止水部17から抜けない
ように注意し乍ら、ケーシングパイプ35″先端よりグ
ラウト材Gを排出させ乍らケーシングパイプ35″を上
下方向にスラスト運動し、止水材の注入完了後、ケーシ
ングパイプ35″と口元パッカー57を引き抜き回収し
て台座部13から止水部17を取り外し、グラウト材G
の養生後、図22の如くアンカーヘッド77とジャッキ
を用いて引張材61の端部を緊張させてこれを台座部1
3に定着することで、アンカーの施工が完了することと
なる。Next, as shown in FIG. 21, a water blocking material having a specific gravity which is equal to or slightly larger than that of the grout material G is injected from the injection port 31 of the pedestal portion 13, and at the same time, the mouth packer 57 is contracted to cause the casing pipe 35. ″ Inject the grout material G from the swivel 71 at the rear end. At this time, be careful not to let the casing pipe 35 ″ come out of the water stop portion 17, and discharge the grout material G from the tip of the casing pipe 35 ″. After the casing pipe 35 ″ is vertically thrusted to complete the injection of the water blocking material, the casing pipe 35 ″ and the mouth packer 57 are pulled out and collected to remove the water blocking portion 17 from the pedestal portion 13, and the grout material G
After curing, the tension head 61 is tensioned by using the anchor head 77 and the jack as shown in FIG.
By anchoring at 3, the anchor construction will be completed.
【0045】而して、本実施例工法によれば、上述した
ように最後のケーシングパイプ35″の先端からフリー
パッカー59が突出したところで、フリーパッカー59
を膨張させてアンカー孔63を閉塞すると共に、台座部
13の注入口31よりグラウト材Gと同等或いはこれよ
りも比重のやや大きい止水材を注入すると同時に、ケー
シングパイプ35″後端のスイベル71からグラウト材
Gを注入してケーシングパイプ35″先端よりグラウト
材Gを排出させ乍らケーシングパイプ35″を上下方向
にスラスト運動するので、従来の如く止水材とグラウト
材Gが反応したゲル状の止水材固形物がケーシングパイ
プ35″中を浮き上がってその内周に付着固結すること
がない。Thus, according to the method of this embodiment, the free packer 59 is projected from the tip of the last casing pipe 35 "as described above.
To seal the anchor hole 63, and at the same time as injecting a waterproofing material having a specific gravity which is equal to or slightly higher than that of the grout material G from the injection port 31 of the pedestal portion 13, at the same time, the swivel 71 at the rear end of the casing pipe 35 ″. Injecting grout material G from the casing pipe 35 ″ and discharging the grout material G from the tip of the casing pipe 35 ″ causes a vertical thrust movement of the casing pipe 35 ″. The solid material of the water blocking material does not float up inside the casing pipe 35 ″ and adhere to the inner periphery thereof to be solidified.
【0046】従って、最後のケーシングパイプ35″や
口元パッカー57の引き抜き回収が従来に比し極めて容
易となる利点を有する。そして、この効果は、従来の如
くグラウト材よりも比重の小さな止水材を注入口31か
ら注入した場合にも、止水材とグラウト材Gが反応した
ゲル状の止水材固形物がケーシングパイプ35″中を浮
き上がってその内周に付着固結することがなく、同様の
効果を得ることができることが現場の実施で明らかとな
っている。Therefore, there is an advantage that the last casing pipe 35 "and the mouth packer 57 can be pulled out and collected more easily than ever before. This effect has a smaller specific gravity than the conventional grout material. Even when the water is injected from the injection port 31, the gel-like solid material of the water blocking material in which the water blocking material and the grout material G have reacted does not float up inside the casing pipe 35 ″ and adhere to its inner periphery to be solidified. It has become clear in the field implementation that the same effect can be obtained.
【0047】又、本実施例に用いる台座兼用止水ボック
ス9によれば、止水部17を台座部13に連結する際
に、作業者が止水部内管37に螺着する押しキャップ4
3を締め付けておけば、ケーシングパイプ35が地盤3
を削孔するに従い、ケーシングパイプ35との摩擦で止
水部内管37内の止水用ゴムパッキン39,41がケー
シングパイプ35の回転を押しキャップ43に伝達し、
押しキャップ43が自動的に締め付けられてケーシング
パイプ35の外周に止水用ゴムパッキン39,41が圧
接するため、削孔用水Wを注入し乍ら地盤3を削孔して
いくに当たり、ケーシングパイプ35と止水部17との
良好な水密性を得ることができる。Further, according to the pedestal and water blocking box 9 used in this embodiment, when the water blocking portion 17 is connected to the pedestal portion 13, the push cap 4 screwed onto the water blocking portion inner pipe 37 by the worker.
If 3 is tightened, casing pipe 35 will be
As the holes are drilled, the rubber gaskets 39 and 41 for water stop inside the water stop inner pipe 37 transmit the rotation of the casing pipe 35 to the push cap 43 by friction with the casing pipe 35,
Since the push cap 43 is automatically tightened and the water blocking rubber packings 39 and 41 are pressed against the outer circumference of the casing pipe 35, the casing pipe is used for drilling the ground 3 while injecting the drilling water W. Good water tightness between the water blocking portion 35 and the water blocking portion 17 can be obtained.
【0048】尚、上記実施例では、挿入パイプ7を土留
壁1のケーシングパイプ挿入孔5に直接挿入したが、土
留壁1にスリーブ管を予めアンカーの施工位置に挿着し
てある場合には、当該スリーブ管内に挿入パイプ7を挿
入して台座部17を土留壁1の壁面1aに取り付ければ
よい。Although the insertion pipe 7 is directly inserted into the casing pipe insertion hole 5 of the earth retaining wall 1 in the above embodiment, when the sleeve pipe is previously attached to the earth retaining wall 1 at the anchoring position. The insertion pipe 7 may be inserted into the sleeve pipe and the pedestal 17 may be attached to the wall surface 1 a of the earth retaining wall 1.
【0049】[0049]
【発明の効果】以上述べたように、請求項1に係るアン
カー工法によれば、台座兼用止水ボックスの止水部を台
座部に連結する際に、作業者が止水部内管に冠着する押
しキャップを締め付けておけば、ケーシングパイプが地
盤を削孔するに従い、ケーシングパイプとの摩擦で止水
用ゴムパッキンがケーシングパイプの回転を押しキャッ
プに伝達し、その結果、押しキャップが自動的に締め付
けられてケーシングパイプの外周に止水用ゴムパッキン
が圧接するため、削孔用水を注入し乍ら地盤を削孔して
いくに当たり、ケーシングパイプと止水部との良好な水
密性を得ることができる。As described above, according to the anchor construction method according to the first aspect, when the water blocking portion of the pedestal / water blocking box is connected to the pedestal portion, the worker is attached to the inner pipe of the water blocking portion. By tightening the push cap, as the casing pipe drills the ground, friction with the casing pipe causes the rubber gasket for water stop to transmit the rotation of the casing pipe to the push cap, and as a result, the push cap automatically moves. Since the rubber gasket for water stop is pressed against the outer periphery of the casing pipe when it is fastened to the hole, it is possible to obtain good watertightness between the casing pipe and the water stop when drilling the ground by injecting water for hole drilling. be able to.
【0050】そして、最後のケーシングパイプの引き抜
き回収時に、従来の如く止水材とグラウト材が反応した
ゲル状の止水材固形物がケーシングパイプ中を浮き上が
って付着固結することがないため、従来に比しケーシン
グパイプの引き抜き回収が容易となった。When the last casing pipe is pulled out and recovered, the gel-like solid material of the water-stopping material in which the water-stopping material and the grout material have reacted does not float up in the casing pipe to adhere and solidify. It is easier to pull out and collect the casing pipe than before.
【図1】土留壁の壁面に取り付けた台座兼用止水ボック
スの部分断面図である。FIG. 1 is a partial cross-sectional view of a pedestal and water blocking box attached to a wall of a retaining wall.
【図2】図1に示す台座兼用止水ボックスの分解図であ
る。FIG. 2 is an exploded view of the pedestal and water blocking box shown in FIG.
【図3】図1に示す台座兼用止水ボックスの正面図であ
る。FIG. 3 is a front view of the pedestal and water blocking box shown in FIG.
【図4】図1に示す台座兼用止水ボックスの側面図であ
る。FIG. 4 is a side view of the pedestal and water blocking box shown in FIG. 1.
【図5】止水部を仮止めしたケーシングパイプ先端の断
面図である。FIG. 5 is a cross-sectional view of a casing pipe tip to which a water blocking portion is temporarily fixed.
【図6】土留壁への台座部の取付方法を示す請求項1に
係るアンカー工法の実施例の一工程図である。FIG. 6 is a process drawing of an example of the anchor construction method according to claim 1 showing a method of attaching the pedestal portion to the retaining wall.
【図7】台座部への止水部の連結方法を示すアンカー工
法の一工程図である。FIG. 7 is a process drawing of an anchor construction method showing a method of connecting a water blocking part to a pedestal part.
【図8】台座部に止水部を連結した状態を示すアンカー
工法の一工程図である。FIG. 8 is a process drawing of the anchor construction method showing a state in which the water blocking part is connected to the pedestal part.
【図9】ケーシングパイプによる地盤の削孔状態を示す
アンカー工法の一工程図である。FIG. 9 is a process drawing of an anchor construction method showing a state of drilling the ground with a casing pipe.
【図10】口元パッカーとフリーパッカーを装着した引
張材の挿入状態を示すアンカー工法の一工程図である。FIG. 10 is a process drawing of the anchor construction method showing the inserted state of the tension member with the mouth packer and the free packer attached.
【図11】本出願人の先願に係る口元パッカーとフリー
パッカーの構成を示す説明図である。FIG. 11 is an explanatory diagram showing configurations of a mouth packer and a free packer according to the applicant's prior application.
【図12】口元パッカーが膨張した状態を示す説明図で
ある。FIG. 12 is an explanatory diagram showing a state where the mouth packer is inflated.
【図13】ケーシングパイプ内へのグラウト材の注入状
態を示すアンカー工法の一工程図である。FIG. 13 is a process drawing of an anchor construction method showing a state of injecting grout material into a casing pipe.
【図14】グラウト材の加圧注入で口元パッカーが萎ん
だ状態を示す説明図である。FIG. 14 is an explanatory diagram showing a state in which the mouth packer is shrunk by the pressure injection of grout material.
【図15】最後端側のケーシングパイプを回収した際の
口元パッカーの状態を示す説明図である。FIG. 15 is an explanatory diagram showing a state of the mouth packer when the casing pipe on the rearmost end side is collected.
【図16】口元パッカーとフリーパッカーが膨張した状
態を示す説明図である。FIG. 16 is an explanatory diagram showing a state where the mouth packer and the free packer are inflated.
【図17】口元パッカー内の圧縮空気を排気した状態を
示す説明図である。FIG. 17 is an explanatory diagram showing a state in which compressed air in the mouth packer is exhausted.
【図18】最後のケーシングパイプを引き抜き回収した
状態を示す説明図である。FIG. 18 is an explanatory diagram showing a state in which the last casing pipe is pulled out and collected.
【図19】アンカー体の造成作業を完了した状態を示す
説明図である。FIG. 19 is an explanatory diagram showing a state in which the anchor body forming work has been completed.
【図20】フリーパッカーが膨張した状態を示すアンカ
ー工法の一工程図である。FIG. 20 is a process drawing of the anchor construction method showing a state where the free packer is inflated.
【図21】グラウト材及び止水材の注入状態を示すアン
カー工法の一工程図である。FIG. 21 is a process drawing of an anchor construction method showing a state of injecting grout material and water blocking material.
【図22】アンカー工法の完了状態を示す説明図であ
る。FIG. 22 is an explanatory diagram showing a completed state of the anchor construction method.
1 土留壁 1a 壁面 3 地盤 5,33,51 ケーシングパイプ挿入孔 7 挿入パイプ 9 台座兼用止水ボックス 11 ウレタンスポンジ 13 台座部 15 ゴムパッキン 17 止水部 19 接合用プレート 21 台座本体 29 排出口 31 注入口 35 ケーシングパイプ 37 止水部内管 39,41 止水用ゴムパッキン 43 押しキャップ 45 フランジ部材 47 左ネジ 53 削孔ビット 57 口元パッカー 59 フリーパッカー 61 引張材 63 アンカー孔 65 グラウト材注入ホース 1 earth retaining wall 1a wall surface 3 ground 5, 33, 51 casing pipe insertion hole 7 insertion pipe 9 pedestal / water-stop box 11 urethane sponge 13 pedestal 15 rubber packing 17 water stop 19 joining plate 21 pedestal body 29 discharge port 31 Note Inlet 35 Casing pipe 37 Water stop inner pipe 39, 41 Water stop rubber packing 43 Push cap 45 Flange member 47 Left screw 53 Drilling bit 57 Mouth packer 59 Free packer 61 Tensile material 63 Anchor hole 65 Grout material Injection hose
Claims (1)
してボルト締めされる接合用プレートと、 接合用プレートを貫通してアンカー施工角度に挿着さ
れ、ケーシングパイプの先端に装着する削孔ビットより
大きな内径を有し、土留壁や擁壁等のアンカー施工位置
に予め設けられたケーシングパイプ挿入孔に挿入可能な
挿入パイプと、 接合用プレートに挿着された挿入パイプの端部を覆って
当該接合用プレートに取り付き、削孔ビットより大径な
ケーシングパイプ挿入孔が挿入パイプと同軸上に形成さ
れ、側壁に削孔用水及び土砂の排出口と止水材注入用の
注入口が形成されたボックス状の台座本体とからなる台
座兼用止水ボックスの台座部を、 土留壁等に設けたケーシングパイプ挿入孔に上記挿入パ
イプを挿入してその壁面にボルト締めすると共に、 上記台座本体にフランジ部を介してボルト締め可能で外
周に左ネジが刻設され、内周にケーシングパイプの挿入
方向に順次縮径するテーパ部が成形された円筒状の止水
部内管と、 止水部内管内に2層に装着され、削孔ビットより小径な
内径を有する円筒状の軟質止水用ゴムパッキン及び削孔
ビットより小径な内径を有し、外周に止水部内管に形成
されたテーパ部と合致するテーパ部を有する円筒状の硬
質止水用ゴムパッキンと、 止水部内管の先端に螺着され、中央に削孔ビットより小
径なケーシングパイプ挿入孔が形成された押しキャップ
とからなる台座兼用止水ボックスの止水部を、削孔ビッ
ト上方のケーシングパイプ外周に仮止めし、 台座部へのケーシングパイプの挿入に伴い、止水部の止
水部内管を台座部の台座本体にシール部材を介してボル
ト締めした後、 ケーシングパイプの外周を伝わって上昇する削孔スライ
ムを、上記排出口に装着したバルブで水量を調節し乍ら
排出して削孔深さに応じケーシングパイプを順次接続し
て地盤を削孔し、 所望深さの削孔を終えたところで、ケーシングパイプ内
に、 加圧注入されるグラウト材の注入圧でケーシングパイプ
内を開放,閉塞するように形成された口元パッカーと、
当該口元パッカーの取付位置よりも先端側に位置し、口
元パッカーを貫通するグラウト材注入パイプに接続した
切断可能なグラウト材注入ホースから注入されるグラウ
ト材で膨張してアンカー孔を閉塞する布袋状のフリーパ
ッカーとを後端側に取り付けた引張材を挿入し、次い
で、 アンカー孔へのグラウト材の加圧注入で口元パッカーに
よるケーシングパイプ内の開放,閉塞を繰り返して、地
盤中にアンカー体を造成し乍らケーシングパイプを順次
引き抜き回収し、 最後のケーシングパイプの先端よりフリーパッカーがア
ンカー孔内に突出したところで、フリーパッカー内にグ
ラウト材を注入しこれを膨張させてアンカー孔を閉塞す
ると共に口元パッカーを収縮させ、 止水材注入用の上記注入口より止水材を注入しつつケー
シングパイプの後端からグラウト材を注入してケーシン
グパイプを上下方向にスラスト運動し、 止水材注入完了後、ケーシングパイプと口元パッカーを
引き抜き回収し、 台座部より止水部を取り外してグラウト材の養生後、引
張材の端部を緊張させてこれを台座部に定着することを
特徴とするアンカー工法。1. A joining plate which is bolted to a wall surface such as a retaining wall or a retaining wall via a sealing member, and is inserted at an anchor construction angle through the joining plate and attached to the tip of a casing pipe. An insertion pipe that has an inner diameter larger than that of the drilling bit and that can be inserted into a casing pipe insertion hole that is provided in advance at an anchor construction position such as a retaining wall or a retaining wall, and the end of the insertion pipe that is attached to the joining plate. The casing pipe insertion hole having a diameter larger than that of the drill bit is formed coaxially with the insertion pipe, and the side wall is provided with a hole for draining water and earth and sand and an inlet for injecting the waterproofing material. Insert the above-mentioned insertion pipe into the casing pipe insertion hole provided in the earth retaining wall, etc., and bolt the pedestal part of the water-stopping box that also serves as a pedestal consisting of a box-shaped pedestal body At the same time, the pedestal body can be bolted through the flange part, the left screw is engraved on the outer circumference, and the inside of the cylindrical water stop part is formed with a taper part that is gradually reduced in diameter in the insertion direction of the casing pipe. The pipe and the inner tube of the water shut-off part are installed in two layers and have a cylindrical soft water-stop rubber packing having an inner diameter smaller than that of the drill bit and an inner diameter smaller than that of the drill bit, and the inner pipe of the water stop part on the outer periphery. The cylindrical rubber gasket for hard water stoppage that has a taper part that matches the taper part that is formed on the front end, and the inner end of the pipe inside the water stoppage that is screwed into the casing pipe insertion hole that is smaller in diameter than the drill bit. The water blocking part of the pedestal water blocking box consisting of the push cap is temporarily fixed to the outer circumference of the casing pipe above the drill bit, and the inner pipe of the water blocking part of the water blocking part is inserted as the casing pipe is inserted into the pedestal. The pedestal body of the pedestal part is After the bolts are tightened through the reel member, the drilling slime that rises along the outer circumference of the casing pipe is discharged by adjusting the amount of water with the valve installed at the discharge port, and the casing pipe is adjusted according to the drilling depth. Are sequentially connected to drill the ground, and when drilling to the desired depth is completed, the casing pipe is formed to open and close by the injection pressure of the grout material injected under pressure. With a mouth packer,
A cloth bag shape that is located closer to the tip than the mounting position of the mouth packer and expands with the grout material injected from the grout material injection hose connected to the grout material injection pipe that penetrates the mouth packer and closes the anchor hole Insert the tension material with the free packer attached to the rear end side, then pressurize and inject the grout material into the anchor hole to repeatedly open and close the casing pipe by the mouth packer, and place the anchor body in the ground. The casing pipes that were created were sequentially pulled out and collected, and when the free packer protruded into the anchor hole from the tip of the last casing pipe, grout material was injected into the free packer and expanded to close the anchor hole. Shrink the mouth packer and inject the waterproof material from the above-mentioned inlet for waterproof material injection, while After pouring the grout material from the end and thrusting the casing pipe in the vertical direction, after the completion of the injection of the waterproof material, the casing pipe and the packer at the mouth are pulled out and collected, and after removing the waterproof part from the pedestal part and curing the grout material, Anchor construction method characterized by tensioning the end of the tension material and fixing it to the pedestal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26753794A JP3562731B2 (en) | 1994-10-31 | 1994-10-31 | Anchor method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26753794A JP3562731B2 (en) | 1994-10-31 | 1994-10-31 | Anchor method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08128039A true JPH08128039A (en) | 1996-05-21 |
JP3562731B2 JP3562731B2 (en) | 2004-09-08 |
Family
ID=17446207
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP26753794A Expired - Lifetime JP3562731B2 (en) | 1994-10-31 | 1994-10-31 | Anchor method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3562731B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101510297B1 (en) * | 2012-02-17 | 2015-04-10 | 양영훈 | A removable prestressing steel pipe soil nailing structure |
CN109162644A (en) * | 2018-11-09 | 2019-01-08 | 山西潞安矿业(集团)有限责任公司 | Injected hole sealing casing and its application method for underground extraction borehole operation |
CN111424659A (en) * | 2020-04-14 | 2020-07-17 | 云南建投第一勘察设计有限公司 | A new type of prefabricated bearing plate |
CN113216848A (en) * | 2021-06-23 | 2021-08-06 | 中勘资源勘探科技股份有限公司 | Sleeve thrust limiting device for large-diameter drilling on coal mine ground |
CN115341934A (en) * | 2022-07-22 | 2022-11-15 | 广西民族大学 | Anchoring method and structure of anchor rod with enlarged head |
-
1994
- 1994-10-31 JP JP26753794A patent/JP3562731B2/en not_active Expired - Lifetime
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101510297B1 (en) * | 2012-02-17 | 2015-04-10 | 양영훈 | A removable prestressing steel pipe soil nailing structure |
CN109162644A (en) * | 2018-11-09 | 2019-01-08 | 山西潞安矿业(集团)有限责任公司 | Injected hole sealing casing and its application method for underground extraction borehole operation |
CN111424659A (en) * | 2020-04-14 | 2020-07-17 | 云南建投第一勘察设计有限公司 | A new type of prefabricated bearing plate |
CN113216848A (en) * | 2021-06-23 | 2021-08-06 | 中勘资源勘探科技股份有限公司 | Sleeve thrust limiting device for large-diameter drilling on coal mine ground |
CN113216848B (en) * | 2021-06-23 | 2023-12-01 | 中勘资源勘探科技股份有限公司 | Sleeve thrust limiting device for large-caliber drilling on coal mine ground |
CN115341934A (en) * | 2022-07-22 | 2022-11-15 | 广西民族大学 | Anchoring method and structure of anchor rod with enlarged head |
Also Published As
Publication number | Publication date |
---|---|
JP3562731B2 (en) | 2004-09-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6286226A (en) | Method and apparatus for arranging assembling member in ground receiving water pressure through sheet pile | |
JPH08128039A (en) | Anchor construction method | |
JP3046548B2 (en) | Fixing material injection method | |
JP2001193064A (en) | Anchoring method for ground anchor | |
JP2762195B2 (en) | Method and apparatus for pulling out casing pipe for anchor | |
JP2945218B2 (en) | Construction method of ground anchor and waterproofing device used for it | |
JP2002180780A (en) | Sealing method for shaft arrival of shield machine and its device | |
JPH09177073A (en) | Ground anchor method and borig tool | |
JP5037276B2 (en) | Earth anchor method and water stop device used for this earth anchor method | |
JP2001214420A (en) | Method for injecting filler into water stop joint filler | |
JP2587680Y2 (en) | Mouth packer | |
JP2838479B2 (en) | Casing packer and casing extracting method using the same | |
JP2829489B2 (en) | Earth anchor method | |
JP2828237B2 (en) | Anchor body formation method and lip packer used for this | |
JP7590267B2 (en) | Earth retaining wall and construction method of earth retaining wall | |
CN113863223B (en) | Repair process for local leakage of underwater concrete wall | |
JP2865570B2 (en) | Casing handling equipment for anchor construction under pressurized water | |
JP2979304B2 (en) | Prependers | |
JP4341746B2 (en) | Packer with centering closure guide pipe | |
JP3598080B2 (en) | How to fix the manhole sheath tube | |
JPH08269992A (en) | Method and structure for connecting building frame and pipe material of underground structure | |
JP2796750B2 (en) | Flexible suction pad used for middle manhole burying method | |
JP2865571B2 (en) | Anchor construction equipment under pressurized water | |
JP2949054B2 (en) | Fixture structure of casing packer for anchor construction | |
JP3376485B2 (en) | Bolt box closing device for shield tunnel construction segment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040517 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040525 |
|
RD01 | Notification of change of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7426 Effective date: 20040528 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040528 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080611 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090611 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090611 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100611 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100611 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110611 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120611 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130611 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |