JP2871458B2 - Steel pipe pile and construction method of steel pipe pile - Google Patents
Steel pipe pile and construction method of steel pipe pileInfo
- Publication number
- JP2871458B2 JP2871458B2 JP8996794A JP8996794A JP2871458B2 JP 2871458 B2 JP2871458 B2 JP 2871458B2 JP 8996794 A JP8996794 A JP 8996794A JP 8996794 A JP8996794 A JP 8996794A JP 2871458 B2 JP2871458 B2 JP 2871458B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- steel pipe
- spiral
- pipe pile
- tip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Earth Drilling (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、中低層住宅等の建築物
あるいは小規模構造物等の基礎として用いられるラセン
翼付きの鋼管杭とその施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel pipe pile with spiral wings used as a foundation for buildings such as low-rise buildings or small-scale structures, and a construction method thereof.
【0002】[0002]
【従来の技術】従来より、中底層建築物基礎杭として鋼
管製の杭本体の先端、あるいは先端と一定間隔を隔てた
杭本体に一巻き以上に連続するラセン状の翼を持つ杭が
使用されている。この杭は例えば特開昭59−8502
8号公報に示されているもので、図6にように示すよう
にして、鋼管の下端部外周に2倍程度の外径を有する約
一巻きのラセン翼が設けられた構造になっている。この
杭は杭頭に回転トルクを与え、ねじり込みによって地中
に埋設されるものである。2. Description of the Related Art Conventionally, a pile having a spiral wing continuous with one or more turns on a tip of a steel pipe pile body or a pile body at a certain distance from the tip has been used as a foundation pile for an intermediate floor building. ing. This pile is disclosed in, for example, Japanese Patent Laid-Open No. 59-8502.
No. 8, as shown in FIG. 6, the steel pipe has a structure in which approximately one turn of a spiral wing having an outer diameter of about twice is provided on the outer periphery of the lower end of the steel pipe. . This pile gives a rotating torque to the pile head and is buried underground by screwing.
【0003】この杭は、鋼管1の先端に設けられた掘削
刃5によって先端地盤を掘削軟化し、杭体積分の土を杭
側面に押し出し、杭側面の土を圧縮して地盤を圧密しな
がら無排土で推進沈設される。従って、杭の側面に圧縮
した土砂体積が杭を締め付けて摩擦力として作用し、ラ
セン翼2と合わせて大きな支持力が発現できるものであ
る。In this pile, the excavation blade 5 provided at the tip of the steel pipe 1 excavates and softens the ground at the tip, extrudes soil corresponding to the pile volume to the side of the pile, compresses the soil on the side of the pile, and consolidates the ground. It will be propelled and set without any earth removal. Therefore, the volume of the earth and sand compressed on the side surface of the pile acts as a frictional force by tightening the pile, and together with the spiral blade 2, a large supporting force can be developed.
【0004】[0004]
【発明が解決しようとする課題】しかしながら従来の杭
では、1枚のみラセン翼が連続した状態で一枚のみ取り
付けられているため杭芯に杭先端をセットしても、杭を
回転すると同時に杭芯から杭がずれてしまい、杭ずれが
発生しやすいといった問題があった。また、従来の杭は
やや硬い地盤を掘削する場合には、貫入性が悪くなり杭
体に傾斜が生じると共に時間がかかるといった問題もあ
った。更に、ラセン翼がレキに当たって変形したり、あ
るいはレキとの摩擦によって擦りへってしまい、所定の
鉛直支持力が発現できないといった問題もあった。However, in the conventional pile, only one spiral wing is mounted in a continuous state, so that even if the tip of the pile is set on the pile core, the pile is rotated and the pile is rotated at the same time. There was a problem that the pile was displaced from the core, and the pile was likely to be displaced. In addition, in the case of excavating a slightly hard ground, the conventional pile has a problem that the penetrability deteriorates, the pile body is inclined, and it takes time. Further, there is another problem that the spiral wings are deformed by hitting the wrench or are rubbed by friction with the wrench, so that a predetermined vertical supporting force cannot be exhibited.
【0005】そこで本発明の目的は、施工精度を向上
し、やや固い地盤においても充分に大きな支持力が発現
可能な鋼管杭とその施工方法を提供することである。[0005] It is an object of the present invention to provide a steel pipe pile capable of improving construction accuracy and exhibiting a sufficiently large supporting force even on a slightly hard ground, and a construction method therefor.
【0006】[0006]
【課題を解決するための手段】本発明は、複数枚のラセ
ン翼が鋼管杭の下端部外周面の同じ高さ位置でラセン方
向を同じにして周方向に等間隔に固定され、該ラセン翼
の1枚当たりの長さは[1÷(ラセン翼の枚数+1)]
巻き以上[1÷(ラセン翼の枚数)×1.1 ]巻き以下で
あり、且つ杭先端に底板を取り付けて閉塞された鋼管
杭、および複数枚のラセン翼が鋼管杭の下端部外周面の
同じ高さ位置でラセン方向を同じにして周方向に等間隔
に固定され、該ラセン翼の1枚当たりの長さは[1÷
(ラセン翼の枚数+1)]巻き以上[1÷(ラセン翼の
枚数)×1.1 ]巻き以下であり、且つ杭先端に底板を取
り付けて閉塞された鋼管杭に回転力を与えることによ
り、杭体積分の土を杭側方に押し出し、杭側面の土を圧
縮しながら杭を沈設して支持力を向上させることを特徴
とする鋼管杭の施工方法である。According to the present invention, a plurality of spiral blades are fixed at the same height position on the outer peripheral surface of the lower end portion of a steel pipe pile at equal intervals in the circumferential direction with the same spiral direction. The length per sheet is [1 ÷ (number of spiral wings + 1)]
A steel pipe pile that is not less than winding and not more than [1 ÷ (number of spiral wings) × 1.1] and is closed by attaching a bottom plate to the tip of the pile, and a plurality of spiral wings have the same height at the outer peripheral surface of the lower end of the steel pipe pile. At the same position, the helical direction is fixed at equal intervals in the circumferential direction with the same helical direction, and the length of each helical wing is [1 ÷
(Number of spiral wings + 1)] or more and [1 [(number of spiral wings) × 1.1] or less, and by attaching a bottom plate to the tip of the pile and applying a rotational force to the closed steel pipe pile, the pile volume is increased. This is a method for constructing a steel pipe pile, which extrudes soil to the side of the pile, compresses the soil on the side of the pile, lays the pile, and improves the bearing capacity .
【0007】[0007]
【作用】本発明は、複数枚のラセン翼が鋼管杭の下端部
外周面の同じ高さ位置でラセン方向を同じにして周方向
に等間隔に固定されているので、掘推開始時に杭芯のず
れが防止できる。且つ、安定した推進力を得ることがで
きると共に施工能率を上げることができる。やや硬い地
盤を掘削する際にも杭体の傾斜がなく施工能率もまた上
げることができる。更にまた、ラセン翼の変形および擦
り減りと土砂の地上搬出を抑止でき、摩擦力が発現され
るため極限支持力も向上することができる。According to the present invention, since a plurality of spiral blades are fixed at equal intervals in the circumferential direction at the same height position on the outer peripheral surface of the lower end portion of the steel pipe pile, the pile core is fixed at the start of excavation. Misalignment can be prevented. In addition, a stable propulsion force can be obtained, and construction efficiency can be improved. Even when excavating a slightly hard ground, the pile body does not tilt and the construction efficiency can also be increased. Furthermore, the deformation and abrasion of the spiral blade and the removal of earth and sand from the ground can be suppressed, and a frictional force is developed, so that the ultimate supporting force can be improved.
【0008】[0008]
【実施例】以下、図面を用いて説明する。図1は本発明
の杭の側面図である。また、図4, 5は本発明の半巻き
2枚のラセン翼を有する杭の底面図である。杭本体は鋼
管1であり、通常外径100〜200mm、厚さ4〜1
0mm、長さ5〜20mである。この鋼管1の先端部外
周面に複数枚のラセン翼2が巻きつけられている。ラセ
ン翼2は鋼製であり、交互に且つ不連続に取り付けられ
ている。その外径は鋼管の1.5倍〜3倍程度が望まし
く、さらに好ましくは1. 8〜2. 2倍である。前記の
範囲であると支持力が高くなりつつも施工能率がより向
上するため、好ましいと言える。ラセン翼2の厚さは6
〜20mmが好ましく、地盤のN値が30以上のときは
厚さ6mm以上、N値が40以上のときは厚さ9mm以
上、N値が50以上のときは厚さ12mm以上が実用上
好ましい。ストロークLは50〜200mmが施工性の
面で好ましい。ラセン翼2は通常溶接によって鋼管1に
取り付けられる。図1は、杭周方向に該ラセン翼2枚を
用いた例であり、1枚あたりの該ラセン翼は半巻きであ
る。ラセン翼先端6は左右対称に2箇所に設けられてい
るため、従来の1枚ラセン翼に比べ2倍の掘削効果があ
る。図2は同じく杭周方向に等間隔で該ラセン翼3枚を
設けた例であり、1枚あたりの該ラセン翼は3分の1巻
きである。このようにラセン翼の枚数を多くすると掘削
効果は向上するが実用上好ましい該ラセン翼の長さは4
分の1巻き以上半巻き以下である。1 枚あたりのラセン
翼の長さは〔1÷(ラセン翼の枚数+1)〕以上〔1÷
ラセン翼の枚数)×1.1以下であり2枚のラセン翼の
ときは1枚あたり0.33巻き〜0.55巻き、3枚の
ラセン翼のときは1枚あたり0.25巻き〜0.37巻
き、4枚のラセン翼のときは1枚あたり0.20巻き〜
0.28巻きである。また施工時の掘削ピッチを同じに
すれば杭軸方向に多段に設けてもよい。以上のようにラ
セン翼を不連続に鋼管に取り付けることによって施工時
にはラセン翼1枚あたりの負担を低減でき、やや硬い地
盤を掘削する場合にもラセン翼の変形や擦り減りが少な
くなる。更にまた、ラセン翼が不連続に鋼管に取り付け
られているためラセン翼が連続で1巻き或いはそれ以上
鋼管に巻き付けられている従来の鋼管杭に比べると、掘
削した杭体積分の土砂を地上に搬出することはなく排土
量が極めて少ない。Embodiments will be described below with reference to the drawings. FIG. 1 is a side view of the pile of the present invention. FIGS. 4 and 5 are bottom views of a pile having two spiral wound wings of the present invention. The pile body is a steel pipe 1 and usually has an outer diameter of 100 to 200 mm and a thickness of 4-1.
0 mm, length 5-20 m. A plurality of spiral blades 2 are wound around the outer peripheral surface of the tip of the steel pipe 1. The spiral blades 2 are made of steel and are attached alternately and discontinuously. Its outer diameter is desirably about 1.5 to 3 times the steel pipe, and more preferably 1.8 to 2.2 times. It can be said that the above range is preferable because the construction efficiency is further improved while the supporting force is increased. The thickness of the spiral wing 2 is 6
The thickness is preferably 6 mm or more when the N value of the ground is 30 or more, 9 mm or more when the N value is 40 or more, and 12 mm or more when the N value is 50 or more. The stroke L is preferably 50 to 200 mm in terms of workability. The spiral wing 2 is attached to the steel pipe 1 usually by welding. FIG. 1 shows an example in which two spiral wings are used in the pile circumferential direction, and the spiral wings per sheet are half-wound. Since the spiral blade tip 6 is provided symmetrically at two places, the excavation effect is twice as large as that of the conventional single spiral blade. FIG. 2 shows an example in which three spiral blades are provided at equal intervals in the pile circumferential direction, and the number of spiral blades per sheet is one-third. When the number of spiral blades is increased as described above, the excavation effect is improved, but the practically preferable length of the spiral blade is 4
It is one-half turn or more and half turn or less. The length of the spiral wings per piece is [1 ÷ (number of spiral wings + 1)] or more [1 ÷
(The number of spiral wings) × 1.1 or less, and 0.33 to 0.55 turns per one for two spiral wings and 0.25 to 0 for each three spiral wings .37 turns, 0.20 turns per sheet for four spiral wings
0.28 turns. Moreover, if the excavation pitch at the time of construction is made the same, it may be provided in multiple stages in the pile axis direction. As described above, by attaching the spiral wings discontinuously to the steel pipe, the load per spiral wing can be reduced at the time of construction, and deformation and abrasion of the spiral wings can be reduced even when excavating a somewhat hard ground. Furthermore, since the spiral wing is discontinuously attached to the steel pipe, compared to a conventional steel pipe pile in which the spiral wing is continuously wound around the steel pipe one or more times, the earth and sand corresponding to the excavated pile volume is placed on the ground. It is not carried out and the amount of soil removed is extremely small.
【0009】本発明の鋼管杭は、杭の頭部に回転力を与
えることにより、杭を沈設されるものである。杭側面の
土を圧縮するため鋼管1の先端は底板4を取り付けて閉
塞されている。本発明によれば掘削によって杭体積分の
土を杭側面に押し出し、杭側面の土を圧縮して地盤を圧
密しながら無排土で推進沈設されるため、本発明のラセ
ン翼付き鋼管杭の所期の目的が達成できる。また、鋼管
1の下端には地盤によって掘削刃を設けても良い。更
に、硬い地盤を掘削する場合には図3のように補強プレ
ート3を設けると良い。補強プレート3を設ける場合に
は先端6に刃を有するが、その形状は図4のように鋭角
に尖っているものでもよく、図5のようにギザギザとし
ても良い。In the steel pipe pile of the present invention, the pile is laid down by applying a rotational force to the head of the pile. To compress the soil on the side of the pile, the tip of the steel pipe 1 is closed with a bottom plate 4 attached. According to the present invention, the soil of the pile volume is extruded to the side of the pile by excavation, and the soil on the side of the pile is compressed and the ground is propelled and set without draining while consolidating the ground. The intended purpose can be achieved. Further, an excavation blade may be provided at the lower end of the steel pipe 1 by the ground. Further, when excavating hard ground, a reinforcing plate 3 may be provided as shown in FIG. When the reinforcing plate 3 is provided, the tip 6 has a blade, but the shape may be sharp at a sharp angle as shown in FIG. 4 or may be jagged as shown in FIG.
【0010】以下、実施例により本発明を詳細に説明す
る。 実施例 本発明の杭として、外径200mm、厚さ8mm、長さ
10mの鋼管に、外径400mm、厚さ9mmのラセン
翼2を図1に示すようにストロークLを150mmとし
て1枚あたり0.55巻きであるラセン翼2枚を取り付
け、これに厚さ16mmの補強プレート3をラセン翼2
の下側に全面にわたって取り付けたものを使用した。但
し、補強プレート3は先端を図5のようにカギ状にギザ
ギザとし鋼管よりも30mm下に突出させた。杭先端は
底板4を取り付けて閉塞とした。この杭をGL−0〜1
1m(地表面からの距離)の間はN値10以下の軟弱地
盤であるがGL−11〜16mの間はN値30〜40で
あるレキ地盤に施工した。杭はGL−12mまで沈設
し、杭先端はレキ地盤中に1m貫入させた。その後、土
質工学会「クイの鉛直載荷試験基準」による載荷試験を
実施した。本試験には本発明の杭を20本用いた。Hereinafter, the present invention will be described in detail with reference to examples. EXAMPLE As a pile of the present invention, a spiral pipe 2 having an outer diameter of 400 mm and a thickness of 9 mm was formed on a steel pipe having an outer diameter of 200 mm, a thickness of 8 mm and a length of 10 m by setting a stroke L to 150 mm as shown in FIG. .55 helical wings of 55 turns were attached, and a reinforcing plate 3 having a thickness of 16 mm was attached thereto.
Used over the entire surface underneath. However, the reinforcing plate 3 was formed so that its tip was notched in a key shape as shown in FIG. 5 and protruded 30 mm below the steel pipe. The pile tip was closed by attaching a bottom plate 4. This pile is GL-0-1
It was constructed on soft ground with an N value of 10 or less during 1 m (distance from the ground surface), but with an N value of 30 to 40 during GL-11 to 16 m. The pile was sunk to GL-12m, and the tip of the pile was penetrated 1m into the ground. After that, a loading test was conducted according to the Japan Society of Geotechnical Engineers, "Cui's Vertical Loading Test Standard." In this test, 20 piles of the present invention were used.
【0011】その結果、施工速度はGL−11mまでは
平均約1.5分であり、GL−11〜12mのN値の高
い地盤への貫入には平均約7分かかった。また、掘削開
始時に本発明の杭は杭ずれが全く生じなかった。施工完
了時には全く杭体の傾斜が生じていなかった。載荷試験
の結果、杭の極限支持力が120tonであった。As a result, the construction speed was about 1.5 minutes on average up to GL-11m, and it took about 7 minutes on average to penetrate GL-11 to 12m into the ground with a high N value. Further, at the start of excavation, the pile of the present invention did not undergo any pile displacement. At the time of the completion of the construction, no inclination of the pile had occurred. As a result of the loading test, the ultimate bearing capacity of the pile was 120 ton.
【0012】比較例 一方、比較として従来の杭を同じ条件で施工し載荷試験
を行った。従来の杭は図6に示すもので、本発明と同じ
く外径200mm、厚さ8mm、長さ10mの鋼管に、
外径400mm、厚さ9mmのラセン翼をストロークL
を150mmとして約一巻き取り付けたものであるが補
強プレートは有さず、先端は底板と掘削刃を取り付けた
ものを使用し、この従来の杭も20本用いた。Comparative Example On the other hand, as a comparison, a conventional pile was constructed under the same conditions and a load test was performed. The conventional pile is shown in FIG. 6 and, like the present invention, a steel pipe having an outer diameter of 200 mm, a thickness of 8 mm, and a length of 10 m,
Stroke L with 400 mm outer diameter and 9 mm thick spiral wing
Was set at about 150 mm, but without a reinforcing plate. The tip was provided with a bottom plate and a cutting blade, and 20 conventional piles were used.
【0013】その結果、施工速度はGL−11mまでは
平均約1. 5分と同じあったが、GL−11〜12mの
N値の高い地盤への貫入には平均約12分を要した。ま
た、掘削開始時に杭ずれが5cm生じた上、施工完了時
には、20本中14本に100分の1勾配を超える杭体
の傾斜が生じていた。載荷試験の結果、杭は95ton
であった。As a result, the construction speed was about 1.5 minutes on average until GL-11m, but it took about 12 minutes on average to penetrate the GL-11 to 12m ground with a high N value. At the start of the excavation, a pile displacement of 5 cm occurred, and at the completion of the construction, 14 of the 20 piles had an inclination of the pile body exceeding 1/100. As a result of the loading test, the pile was 95 tons
Met.
【0014】[0014]
【発明の効果】本発明の鋼管杭は、従来のラセン翼を有
し先端が底板により閉塞された鋼管杭と比較して、レキ
等の硬い地盤においても掘削開始時の杭芯のずれや推進
時の杭体の傾斜がなく施工精度が高い上、安定した推進
力を上宇ことができる。また従来のラセン翼を有し先端
が底板により閉塞された鋼管杭と比較して、掘削刃の擦
り減りや変形及び排土量も少なく、ラセン翼の回転数も
少なくて同じ掘削効果を発現できる。このため支持力の
向上につながる。また本発明の施工方法によれば、先端
には底板を取り付けて閉塞され且つ上記特定条件のラセ
ン翼を取り付けた鋼管杭に回転力を与えて掘削すること
によって、杭体積分の土を杭側面に押し出し、杭側面の
土を圧縮して地盤を圧密しながら無排土で推進沈設され
るため、本発明のラセン翼付きの鋼管杭の所期の目的が
達成されるとともに上記した施工上の効果が発現され
る。The steel pipe pile of the present invention has a conventional spiral wing.
Compared to steel pipe piles whose tip is closed by a bottom plate , there is no displacement of the pile core at the start of excavation and no inclination of the pile body at the time of excavation even on hard ground such as rake, and the construction accuracy is high and stable propulsion force Can be up. Also has a conventional spiral wing tip
As compared with a steel pipe pile closed by a bottom plate, the same excavation effect can be exhibited with less wear and deformation of the excavation blade and less amount of earth removal and a lower rotation speed of the spiral blade. This leads to an improvement in the supporting force. Further, according to the construction method of the present invention, a bottom plate is attached to the tip and closed, and
By excavating the steel pipe pile on which the wing wings are attached by applying rotational force, the soil of the pile volume is pushed out to the side of the pile, and the soil on the side of the pile is compressed to consolidate the ground, and the soil is propelled and settled without discharging the soil. Therefore, the desired object of the steel pipe pile with a spiral wing of the present invention is achieved, and the above-described effects on construction are exhibited.
【図1】本発明の杭の一実施例を示す側面図である。FIG. 1 is a side view showing an embodiment of a pile according to the present invention.
【図2】3分の1巻き3枚のラセン翼を設けた杭を示す
側面図である。FIG. 2 is a side view showing a pile provided with three thirds of spiral wings.
【図3】補強プレートを有する杭を示す図である。FIG. 3 is a diagram showing a pile having a reinforcing plate.
【図4】図1の杭を示す底面図である。FIG. 4 is a bottom view showing the pile of FIG. 1;
【図5】本発明の杭の他例を示す底面図である。FIG. 5 is a bottom view showing another example of the pile of the present invention.
【図6】従来の杭を示す側面図である。FIG. 6 is a side view showing a conventional pile.
1 鋼管杭 2 ラセン翼 3 補強プレート 4 底板 5 掘削刃 6 ラセン翼の先端 DESCRIPTION OF SYMBOLS 1 Steel pipe pile 2 Spiral wing 3 Reinforcement plate 4 Bottom plate 5 Drilling blade 6 Tip of spiral wing
Claims (2)
面の同じ高さ位置でラセン方向を同じにして周方向に等
間隔に固定され、該ラセン翼の1枚当たりの長さは[1
÷(ラセン翼の枚数+1)]巻き以上[1÷(ラセン翼
の枚数)×1.1]巻き以下であり、且つ杭先端に底板
を取り付けて閉塞された鋼管杭。1. A plurality of spiral blades are fixed at equal intervals in the circumferential direction at the same height position on the outer peripheral surface of the lower end portion of a steel pipe pile, at equal intervals in the circumferential direction, and the length of each spiral blade is one. [1
A steel pipe pile that is not less than {(number of spiral blades + 1)] winding and not more than [1 {(number of spiral blades) × 1.1] winding, and is closed by attaching a bottom plate to the tip of the pile.
面の同じ高さ位置でラセン方向を同じにして周方向に等
間隔に固定され、該ラセン翼の1枚当たりの長さは[1
÷(ラセン翼の枚数+1)]巻き以上[1÷(ラセン翼
の枚数)×1.1 ]巻き以下であり、且つ杭先端に底板を
取り付けて閉塞された鋼管杭に回転力を与えることによ
り、杭体積分の土を杭側方に押し出し、杭側面の土を圧
縮しながら杭を沈設して支持力を向上させることを特徴
とする鋼管杭の施工方法。2. A plurality of spiral wings are fixed at equal intervals in the circumferential direction at the same height position on the outer peripheral surface of the lower end portion of the steel pipe pile in the circumferential direction, and the length of each spiral wing is one. [1
÷ (number of spiral wings + 1)] or more and [1 ÷ (number of spiral wings) × 1.1] or less, and by attaching a bottom plate to the tip of the pile to apply rotational force to the closed steel pipe pile, A method for constructing steel pipe piles, which extrudes a volume of soil to the side of the pile, compresses the soil on the side of the pile, lays the pile, and improves the bearing capacity .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8996794A JP2871458B2 (en) | 1994-04-27 | 1994-04-27 | Steel pipe pile and construction method of steel pipe pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8996794A JP2871458B2 (en) | 1994-04-27 | 1994-04-27 | Steel pipe pile and construction method of steel pipe pile |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH07292666A JPH07292666A (en) | 1995-11-07 |
JP2871458B2 true JP2871458B2 (en) | 1999-03-17 |
Family
ID=13985462
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8996794A Expired - Lifetime JP2871458B2 (en) | 1994-04-27 | 1994-04-27 | Steel pipe pile and construction method of steel pipe pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2871458B2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08105287A (en) * | 1994-10-06 | 1996-04-23 | Ito Yosetsu Kogyo Kk | Agitating device for excavator |
JP2003074054A (en) * | 2001-08-30 | 2003-03-12 | Asahi Kasei Corp | Steel pipe pile |
JP2009257081A (en) * | 2009-08-03 | 2009-11-05 | Asahi Kasei Homes Co | Steel pipe pile for heat exchange |
JP6085485B2 (en) * | 2013-01-24 | 2017-02-22 | 三和機工株式会社 | Pile driver |
JP6709464B2 (en) * | 2016-09-16 | 2020-06-17 | 株式会社シグマベース | Steel pipe pile |
JP2022190512A (en) * | 2021-06-14 | 2022-12-26 | 株式会社ガイアF1 | Rotary penetration steel pipe pile with tip blade |
-
1994
- 1994-04-27 JP JP8996794A patent/JP2871458B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH07292666A (en) | 1995-11-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100388263B1 (en) | Rotation buried pile and execution management method therefor | |
KR101620380B1 (en) | Spiral steel pipe pile | |
JP5360276B2 (en) | Screwed pile | |
JP2871458B2 (en) | Steel pipe pile and construction method of steel pipe pile | |
JP2592079B2 (en) | Small diameter steel pipe pile | |
JPH11140869A (en) | Screwed-in type steel pipe pile with wing | |
JP3917728B2 (en) | Steel pipe pile and foundation method using the same steel pipe pile | |
JP3372627B2 (en) | Burying method of inverted conical multi-wing steel pipe pile | |
EP0370396B1 (en) | A reinforced concrete load-bearing pile with multi-branches and enlarged footings and means for forming the pile | |
JP4189550B2 (en) | Construction method of ready-made pile with spiral blade, casing for propulsion | |
JP2007032044A (en) | Support structure for foundation pile and steel pipe pile | |
JPH11303069A (en) | Screwed type steel pipe pile with blade and execution method therefor | |
JP2691831B2 (en) | Conical multi-blade steel pipe friction pile and its burying method | |
JPS6218684B2 (en) | ||
JP2000096560A (en) | Screwing-type steel pipe pile and its execution | |
JPH09100532A (en) | Bearing pile and tip member for bearing pile | |
JP3031245B2 (en) | Screw-in type steel pipe pile | |
JP3661863B2 (en) | Expanded bottom plate for rotating buried steel pipe pile, and method of attaching the expanded plate to the rotated buried steel pipe pile | |
JPH0711637A (en) | Steel pipe pile | |
JP3586861B2 (en) | Rotary penetration steel pipe pile | |
JP3754419B2 (en) | Steel pipe pile | |
JP2001193061A (en) | Winged pile | |
JP3694824B2 (en) | Threaded steel pipe pile and its construction method | |
JPH11172669A (en) | Screwing steel tube pile | |
JP2861937B2 (en) | Screw-in type steel pipe pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19981215 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080108 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090108 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090108 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100108 Year of fee payment: 11 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100108 Year of fee payment: 11 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110108 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110108 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120108 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120108 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130108 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140108 Year of fee payment: 15 |
|
EXPY | Cancellation because of completion of term |