[go: up one dir, main page]

JP2009161974A - Reinforced concrete beam construction method - Google Patents

Reinforced concrete beam construction method Download PDF

Info

Publication number
JP2009161974A
JP2009161974A JP2008000025A JP2008000025A JP2009161974A JP 2009161974 A JP2009161974 A JP 2009161974A JP 2008000025 A JP2008000025 A JP 2008000025A JP 2008000025 A JP2008000025 A JP 2008000025A JP 2009161974 A JP2009161974 A JP 2009161974A
Authority
JP
Japan
Prior art keywords
reinforced concrete
column
sleeve
construction
concrete beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008000025A
Other languages
Japanese (ja)
Inventor
Yuichi Iwai
慶  祐一
Satoru Kusaka
哲 日下
Kazuto Nakahira
和人 中平
Tatsuhiko Maeda
達彦 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2008000025A priority Critical patent/JP2009161974A/en
Publication of JP2009161974A publication Critical patent/JP2009161974A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a reinforced concrete beam construction method which is applicable to construction of a both end fixed frame in which columns and a reinforced concrete beam are rigidly jointed to each other, wherein the method brings about reduction of end moment occurring at each end of the reinforced concrete beam. <P>SOLUTION: In carrying out the reinforced concrete beam construction method, at least the ends of the reinforced concrete beam 6 are formed of precast concrete products, and reinforcements 2 protruding from the column 15 in a beam longitudinal direction are inserted into sleeves 7 or 15 embedded in the ends. In the process of construction work, each beam end is pinconnected to the column, and the following construction work is continued in this state. Then after completion of predetermined steps, grout 13 is poured in the sleeves, and thus the beam ends are rigidly jointed to the columns. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、鉄筋コンクリート梁の構築方法に関し、詳しくは、柱と鉄筋コンクリート梁を剛接合した両端固定の架構において、鉄筋コンクリート梁の端部に発生する応力(端部モーメント)を抑制できるようにした鉄筋コンクリート梁の構築方法に関する。   The present invention relates to a method for constructing a reinforced concrete beam, and more particularly, a reinforced concrete beam capable of suppressing stress (end moment) generated at an end of a reinforced concrete beam in a fixed structure with both ends fixed by rigidly joining a column and a reinforced concrete beam. It relates to the construction method.

一般に、超高層建物においては、図1に示すように、1本の柱Aを耐力の大きな基礎杭Bで1本ずつ支持することが多いが、建物中央部では、隣り合う基礎杭Bによる地中での応力線が重なり合ういわゆる群杭効果によって、建物外周部よりも建物中央側において基礎杭Bの沈下が大きくなる傾向がある。この基礎杭沈下量の差(建物の不同沈下)により、図1に示すように、大梁Cに強制変形が生じるので、大梁Cの外側端部には、強制変形による端部モーメントのつりあがり(矢印a)が生じる。従って、大梁Cとして、梁成の大きな耐力の大きいものが要求されることになり、発生応力に対して断面設計が困難になるケースもある。尚、建物中央側には、複数本の柱Aが所定スパンの格子状に配置され、基礎杭Bもそれに対応して配置されるが、図1は、大梁Cの強制変形による端部モーメントのつりあがりを説明する模式図であるため、説明の便宜上、建物中央側の柱Aと基礎杭Bは、夫々、1本ずつしか示されていない。   In general, in a high-rise building, as shown in FIG. 1, one pillar A is often supported one by one with a foundation pile B having a high yield strength. Due to the so-called group pile effect in which the stress lines inside overlap, the settlement of the foundation pile B tends to be larger on the center side of the building than on the outer periphery of the building. As shown in FIG. 1, forced deformation occurs in the girder C due to the difference in the amount of settlement of the foundation piles (uneven settlement of the building). Therefore, the end moment of the girder C is balanced at the outer end of the girder C ( Arrow a) occurs. Accordingly, the large beam C is required to have a large beam strength, and there are cases where the cross-section design becomes difficult with respect to the generated stress. Incidentally, on the center side of the building, a plurality of pillars A are arranged in a lattice pattern with a predetermined span, and the foundation pile B is also arranged correspondingly, but FIG. Since it is a schematic diagram explaining lifting, for convenience of explanation, only one pillar A and one foundation pile B on the center side of the building are shown.

また、鉄筋コンクリート造建物の柱梁のような両端固定の架構においては、図2に示すように、スパン端部に、自重と、仕上げ荷重及び積載荷重の総和に起因する応力(端部モーメント)が生じ、スパン端部の応力はスパンが大きくなるにつれ、スパンの二乗に比例して増大する。そのため、ロングスパンの大梁を構築すると、スパン端部に生じる応力(矢印b)が極端に大きくなり、この応力に対処するためには、梁成を増し、梁端部の鉄筋量を増すなどの対策が講じられることになる。   In addition, in a frame fixed at both ends, such as a column beam in a reinforced concrete building, as shown in Fig. 2, the stress (end moment) resulting from the total weight of the weight, finishing load and loading load is applied to the span end. As a result, the stress at the end of the span increases in proportion to the square of the span as the span increases. Therefore, when a long span large beam is constructed, the stress (arrow b) generated at the end of the span becomes extremely large. To cope with this stress, the beam formation is increased and the amount of rebar at the end of the beam is increased. Measures will be taken.

また、大梁の重量が増すと共に、大梁端部の応力(矢印b)が大きくなることによって、大梁を支持する柱に生じる応力(矢印c)も必然的に大きくなるため、大梁と同様、断面を増す、大量の配筋をするなどの対策が必要となる。   In addition, as the weight of the large beam increases and the stress at the end of the large beam (arrow b) increases, the stress (arrow c) that occurs in the column that supports the large beam also inevitably increases. It is necessary to take measures such as increasing the number of bars.

尚、鉄骨造の大梁を対象とする技術ではあるが、鉄骨梁の端部応力を低減するために、梁端部を柱にボルト連結することによってピン接合状態とし、この状態で、デッキプレートの敷設、スラブ配筋、コンクリート打設等の工程を進め、スラブの完成後、梁端部を柱に溶接することによって剛接合状態とする柱と鉄骨梁の接合方法が、特許文献1によって提案されている。   Although it is a technology that targets steel-framed large beams, in order to reduce the stress at the end of the steel beam, the end of the beam is connected to the column by bolting, and in this state, the deck plate Patent Document 1 proposes a method of joining a column and a steel beam in which the steps of laying, slab reinforcement, concrete placement, etc. are advanced, and after the slab is completed, the beam end is welded to the column to make it rigidly connected. ing.

この従来技術は、鉄骨梁の端部のウエブを柱に設けられたガセットプレートにボルト締めしてピン接合とし、続いて梁端部の上下フランジを柱に突合せ溶接して剛接合し、しかる後、スラブを構築するという一般的な施工手順を、ボルト締め、スラブ構築、突合せ溶接の順序に変更するだけで、鉄骨梁の端部応力を低減できるという利点を有している。   In this prior art, the web at the end of the steel beam is bolted to a gusset plate provided on the column to make a pin connection, and then the upper and lower flanges at the end of the beam are butt welded to the column to make a rigid connection. It has the advantage that the end stress of the steel beam can be reduced by simply changing the general construction procedure of constructing the slab to the order of bolting, slab construction and butt welding.

しかしながら、鉄筋コンクリート梁には、元々、鉄骨梁のボルト締めや溶接といった工程が存在しないため、上記の従来技術を鉄筋コンクリート梁の接合に適用する訳にはいかない。また、スラブを1層ずつ構築する都度、梁端部の上下フランジを柱に突合せ溶接して剛接合とするので、建物の不同沈下に起因する鉄骨梁の強制変形に対しては、別途、対策が必要である。   However, reinforced concrete beams originally do not have steps such as bolting or welding of steel beams, so the above-described conventional technique cannot be applied to the joining of reinforced concrete beams. In addition, each time a slab is built one layer at a time, the upper and lower flanges of the beam end are butt welded to the column to make a rigid joint, so that a separate measure is taken against the forced deformation of the steel beam due to the uneven settlement of the building. is required.

特開平8−218640号公報JP-A-8-218640

本発明は、上記の問題点を踏まえてなされたものであって、その目的とするところは、柱と鉄筋コンクリート梁を剛接合した両端固定の架構において、鉄筋コンクリート梁の端部に発生する端部モーメント(例えば、建物の不同沈下による鉄筋コンクリート梁の外端部モーメントのつりあがりや、ロングスパンの鉄筋コンクリート梁の端部モーメントのつりあがりなど、)を抑制できるようにした鉄筋コンクリート梁の構築方法を提供することにある。   The present invention has been made in view of the above-mentioned problems, and its object is to provide an end moment generated at the end of a reinforced concrete beam in a frame fixed at both ends with a rigid connection between a column and a reinforced concrete beam. To provide a method for constructing a reinforced concrete beam that can suppress (for example, lifting of the end moment of a reinforced concrete beam due to uneven settlement of the building, lifting of the end moment of a long span reinforced concrete beam, etc.) It is in.

上記の目的を達成するために本発明が講じた技術的手段は、次の通りである。即ち、請求項1に記載の発明による鉄筋コンクリート梁の構築方法は、少なくとも端部がプレキャストコンクリート製品とされた鉄筋コンクリート梁の前記端部に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴としている。   The technical means taken by the present invention in order to achieve the above object are as follows. In other words, the method for constructing a reinforced concrete beam according to the first aspect of the present invention is the reinforcing bar in which the end portion of the reinforced concrete beam whose end portion is a precast concrete product is protruded in the beam longitudinal direction from the column side to the sleeve embedded in the end portion. In the middle of the construction, the beam end is pin-joined to the column in the middle of the construction, and in this state, the subsequent construction work is advanced, and after completing the predetermined process, the grout is injected into the sleeve, The beam end is rigidly connected to the column.

請求項2に記載の発明は、請求項1に記載の鉄筋コンクリート梁の構築方法であって、鉄筋コンクリート梁のうち端部だけがプレキャストコンクリート製品とされ、当該プレキャストコンクリート製品に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入し、且つ、当該スリーブを貫通した鉄筋の先端側とコンクリートの現場打ちにより構築される梁部分の梁主筋とを継手で接続することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴としている。   Invention of Claim 2 is a construction method of the reinforced concrete beam of Claim 1, Comprising: Only the edge part is made into a precast concrete product among reinforced concrete beams, and it is a column side in the sleeve embedded in the said precast concrete product. In the middle of the construction, insert a reinforcing bar that protrudes in the longitudinal direction of the beam and connect the leading end of the reinforcing bar that penetrates the sleeve and the beam main reinforcing bar of the beam part that is constructed by spotting the concrete with a joint. In this state, the beam ends are pin-joined to the columns, and after that, the building work is proceeded, and after the predetermined process is completed, the grouts are injected into the sleeves to make the beam ends rigid to the columns. It is characterized by joining.

請求項3に記載の発明は、請求項1に記載の鉄筋コンクリート梁の構築方法であって、鉄筋コンクリート梁の全体がプレキャストコンクリート製品とされ、当該プレキャストコンクリート製品の端部に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴としている。   Invention of Claim 3 is the construction method of the reinforced concrete beam of Claim 1, Comprising: The whole reinforced concrete beam is made into a precast concrete product, and it is a column side in the sleeve embedded at the edge part of the said precast concrete product. By inserting a reinforcing bar protruding in the longitudinal direction of the beam, the end of the beam is pin-bonded to the column during the construction process. It is characterized in that the end of the beam is rigidly connected to the column by injecting grout inside.

尚、請求項1〜3に記載の発明は、施工途中においては梁の両端をピン接合とし、所定の工程が完了した後、梁の両端を剛接合する場合と、施工途中においては梁の一端のみをピン接合(他端は剛接合)とし、所定の工程が完了した後、梁の前記一端を剛接合とする場合とを包含している。   The inventions according to claims 1 to 3 are such that both ends of the beam are pin-bonded in the middle of construction, and both ends of the beam are rigidly joined after completion of a predetermined process, and one end of the beam in the middle of construction. Only the pin connection (the other end is a rigid connection), and after the predetermined process is completed, the one end of the beam is a rigid connection.

請求項4に記載の発明は、請求項1〜3の何れかに記載の鉄筋コンクリート梁の構築方法であって、柱側から梁長手方向に突出させた鉄筋とプレキャストコンクリート製品に埋設された梁主筋とが同芯状に配置され、且つ、前記鉄筋と梁主筋のうち何れか一方にのみ嵌合した非接続状態と、両者に略半分ずつ嵌合した接続状態とにわたってスライド可能な継手用スリーブと、その収納スペースを形成するシース管とを備えたスライド継手により接続されることを特徴としている。   Invention of Claim 4 is the construction method of the reinforced concrete beam in any one of Claims 1-3, Comprising: The reinforcing bar made to project in the beam longitudinal direction from the column side, and the beam main reinforcement embed | buried in the precast concrete product And a joint sleeve that is slidable between a non-connected state in which only one of the reinforcing bar and the beam main bar is fitted and a connected state in which approximately half of the reinforcing bar and the beam main bar are fitted to each other. Further, it is characterized in that it is connected by a slide joint provided with a sheath tube forming the storage space.

請求項5に記載の発明は、請求項1〜4の何れかに記載の鉄筋コンクリート梁の構築方法であって、施工途中においては柱に対して鉄筋コンクリート梁の外側端部をピン接合とし、上棟後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合と
することを特徴としている。
Invention of Claim 5 is the construction method of the reinforced concrete beam in any one of Claims 1-4, Comprising: The outer edge part of a reinforced concrete beam is made into a pin connection with respect to a column in the middle of construction, The beam end is rigidly connected to the column by injecting grout into the sleeve.

請求項6に記載の発明は、請求項1〜4の何れかに記載の鉄筋コンクリート梁の構築方法であって、施工途中においては柱に対して鉄筋コンクリート梁の両端部をピン接合とし、前記梁上のスラブコンクリートの打設後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴としている。   Invention of Claim 6 is the construction method of the reinforced concrete beam in any one of Claims 1-4, Comprising: In the middle of construction, both ends of the reinforced concrete beam are made into a pin joint, After placing the slab concrete, the beam end is rigidly connected to the column by injecting grout into the sleeve.

請求項1〜3に記載の発明によれば、柱と鉄筋コンクリート梁を剛接合した両端固定の架構において、鉄筋コンクリート梁の端部に発生する端部モーメントを抑制でき、合理的な大梁断面設計が可能となる効果がある。   According to the first to third aspects of the present invention, the end moment generated at the end of the reinforced concrete beam can be suppressed in the frame with both ends fixed by rigidly connecting the column and the reinforced concrete beam, and a rational large beam cross-section design is possible. There is an effect.

即ち、超高層建物のように、施工途中で群杭効果による建物の不同沈下が予想される鉄筋コンクリート造建物の建築に際しては、鉄筋コンクリート梁の外側端部に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、具体的には、例えば、請求項5に記載の発明のように、上棟後に、スリーブ内にグラウト注入を行って梁端部を剛接合とした両端固定の架構を成立させることになる。   In other words, when building a reinforced concrete building, such as a super high-rise building, where uneven settlement of the building is expected due to the group pile effect during construction, the longitudinal direction of the beam from the column side to the sleeve embedded at the outer end of the reinforced concrete beam In the middle of construction, the end of the beam is pin-joined to the column, and the subsequent construction work is proceeded in this state. For example, as in the fifth aspect of the present invention, after the upper ridge, a grout is injected into the sleeve to establish a fixed structure in which both ends of the beam are rigidly joined.

従って、施工途中において、建物の不同沈下により鉄筋コンクリート梁に強制変形が生じても、梁端部がピン接合となっているので、鉄筋コンクリート梁の強制変形に起因する外側端部の応力(端部モーメント)が原理的にゼロとなる。そして、鉄筋コンクリート梁の強制変形が生じた後、スリーブ内にグラウト注入を行って梁端部を剛接合とした両端固定の架構を成立させるので、鉄筋コンクリート梁の端部に発生する端部モーメントを、鉄筋コンクリート梁の強制変形に起因する端部モーメントが作用しないようにした分、低減することができる。   Therefore, even if the reinforced concrete beam is forcedly deformed due to uneven settlement of the building during construction, the end of the beam is pin-jointed, so the stress at the outer end due to the forced deformation of the reinforced concrete beam (end moment) ) Is zero in principle. And after forced deformation of the reinforced concrete beam occurs, grout is injected into the sleeve to establish a fixed structure with both ends fixed, and the end moment generated at the end of the reinforced concrete beam is It can be reduced as much as the end moment caused by forced deformation of the reinforced concrete beam is prevented.

また、ロングスパンの鉄筋コンクリート梁を構築する場合であれば、鉄筋コンクリート梁の両端部に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、具体的には、請求項6に記載の発明のように、前記梁上のスラブコンクリートの打設後、スリーブ内にグラウト注入を行って梁端部を剛接合とした両端固定の架構を成立させることになる。   When constructing long-span reinforced concrete beams, insert reinforcing bars projecting in the longitudinal direction of the beam from the column side into sleeves embedded at both ends of the reinforced concrete beam. In this state, the end of the beam is made into a pin joint, and the subsequent construction work is proceeded. After the predetermined process is completed, specifically, the slab concrete on the beam is formed as in the invention according to claim 6. After the placement, grout is injected into the sleeve to form a fixed frame with both ends fixedly joined.

従って、施工途中においては、自重に対して端部ピンで構造的に成立させ、鉄筋コンクリート梁端部がピン接合となっているので、端部モーメントが原理的にゼロとなる。そして、スラブコンクリートの打設後、スリーブ内にグラウト注入を行って梁端部を剛接合するので、スラブ構築後の鉄筋コンクリート梁端部に生じる端部モーメントは、仕上げ荷重と積載荷重に起因するものだけになり、ロングスパンの鉄筋コンクリート梁であるにもかかわらず鉄筋コンクリート梁端部に発生する端部モーメントを低減できる。   Accordingly, during construction, the end pin is structurally established with respect to its own weight, and the end portion of the reinforced concrete beam is pin-connected, so that the end moment is zero in principle. And after placing the slab concrete, grout is injected into the sleeve to rigidly join the beam ends, so the end moment generated at the end of the reinforced concrete beam after the slab construction is caused by the finishing load and the loading load. However, the end moment generated at the end of the reinforced concrete beam can be reduced even though it is a long span reinforced concrete beam.

尚、施工途中において、鉄筋コンクリート梁の両端部をピン接合とすることで、スパン中央部の応力が大きくなるが、スパン中央付近は、スラブの協同効果が期待できるため、T型合成梁としての耐力を有することになり、施工時、両端部をピン支持としてスパン中央部の応力を増やしても、断面アップにはなりにくい。また、ロングスパン梁では一般的な手法でもあるが、スパン中央部にだけプレストレスを導入してもよい。   In the middle of construction, the end of the reinforced concrete beam is pin-bonded to increase the stress at the center of the span. However, near the center of the span, the joint effect of the slab can be expected. During construction, even if the stress is increased at the center of the span with both ends supported as pins, the cross-section is unlikely to be increased. Moreover, although it is a general method with a long span beam, prestress may be introduced only in the center portion of the span.

殊に、請求項2に記載の発明によれば、上述した効果に加え、長手方向の大半を現場打ちコンクリートによって構築する鉄筋コンクリート梁であるにもかかわらず施工途中において梁端部をピン接合とすることが可能となり、鉄筋コンクリート梁の端部に発生する端
部モーメントを抑制できるという効果がある。
In particular, according to the invention described in claim 2, in addition to the above-described effects, the beam ends are pin-bonded during the construction in spite of the fact that they are reinforced concrete beams in which the majority in the longitudinal direction is constructed by cast-in-place concrete. Thus, the end moment generated at the end of the reinforced concrete beam can be suppressed.

請求項4に記載の発明によれば、鉄筋コンクリート梁の全体がプレキャストコンクリート製品とされている場合であっても、プレキャストコンクリート製品を柱間に上方から吊り込んで、柱側から梁長手方向に突出させた鉄筋とプレキャストコンクリート製品に埋設された梁主筋とを継手用スリーブにより機械的に接続してピン接合とすることができるので、施工性が良い。   According to the invention described in claim 4, even when the entire reinforced concrete beam is a precast concrete product, the precast concrete product is hung from above between the columns and protrudes in the beam longitudinal direction from the column side. The workability is good because the rebars and the beam main bars embedded in the precast concrete product can be mechanically connected to each other by a joint sleeve to form a pin joint.

以下、本発明の実施形態を図面に基づいて説明する。図3〜図8は、本発明に係る鉄筋コンクリート梁の構築方法の一例を示す。この構築方法は、図1に基づいて説明した超高層建物のような施工途中で群杭効果による建物の不同沈下が予想される鉄筋コンクリート造建物において、建物外面側の柱と中央側の柱間に鉄筋コンクリート梁を架設するに際して採用されている。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. 3-8 shows an example of the construction method of the reinforced concrete beam which concerns on this invention. This construction method is used in a reinforced concrete building such as the high-rise building described with reference to Fig. 1 in the middle of the construction. It is used when reinforced concrete beams are installed.

図3において、1は鉄筋コンクリート造の柱であり、側面には、梁主筋の端部となる複数本の鉄筋2が梁長手方向に突出されている。また、柱1の側面には、仮設の梁受け金具3が取り付けられており、その上方には、コッター係合用凹部4が形成されている。図3、図4において、5は、図8に示す鉄筋コンクリート梁6の端部を構成するプレキャストコンクリート製品であり、前記鉄筋2を挿入する貫通孔形成用のスリーブ(中空管)7が埋設され、端面には、前記コッター係合用凹部4と対面するコッター係合用凹部8が形成されている。そして、図8の(B)に示すように、適当な時点で注入されたグラウト13が前記両凹部4、8に充満された状態に硬化することで、コッターとして機能するように構成されている。また、プレキャストコンクリート製品5には、グラウト注入や注入状態の確認に用いられるパイプ9がスリーブ7と連通する状態に埋設されている。   In FIG. 3, reference numeral 1 denotes a reinforced concrete column, and a plurality of reinforcing bars 2 serving as end portions of the beam main bars protrude from the side surface in the beam longitudinal direction. Further, a temporary beam receiving metal fitting 3 is attached to the side surface of the column 1, and a cotter engaging recess 4 is formed above the beam receiving metal fitting 3. 3 and 4, 5 is a precast concrete product constituting the end of the reinforced concrete beam 6 shown in FIG. 8, and a through-hole forming sleeve (hollow tube) 7 into which the reinforcing bar 2 is inserted is embedded. A cotter engagement recess 8 facing the cotter engagement recess 4 is formed on the end surface. Then, as shown in FIG. 8B, the grout 13 injected at an appropriate time is cured so as to fill the concave portions 4 and 8 so as to function as a cotter. . Further, in the precast concrete product 5, a pipe 9 used for grout injection and confirmation of the injection state is embedded in a state communicating with the sleeve 7.

鉄筋コンクリート梁6の構築方法について説明すると、先ず、図5、図6に示すように、柱1の側面から突出させた鉄筋2をプレキャストコンクリート製品5に埋設されたスリーブ7に挿入し、プレキャストコンクリート製品5のコッター8を柱側面のコッター係合用凹部4に係合させ、且つ、プレキャストコンクリート製品5を梁受け金具3で支持させる。   The construction method of the reinforced concrete beam 6 will be described. First, as shown in FIGS. 5 and 6, the rebar 2 protruded from the side surface of the column 1 is inserted into a sleeve 7 embedded in the precast concrete product 5, and the precast concrete product is inserted. The cotter 8 of 5 is engaged with the cotter engaging recess 4 on the side of the column, and the precast concrete product 5 is supported by the beam bracket 3.

しかる後、図7に示すように、梁型枠9の組立、梁配筋を行い、スリーブ7を貫通した鉄筋2の先端側とコンクリート10の現場打ちにより構築される梁部分の梁主筋11とを重ね継手、機械継手等の継手12で接続し、コンクリート10を打設して、図8の(A)に示すように、柱1に対して梁端部をピン接合とした鉄筋コンクリート梁6を構築する。   After that, as shown in FIG. 7, the beam form 9 is assembled and the beam is laid, and the beam main reinforcement 11 of the beam portion constructed by the on-site side of the rebar 2 penetrating the sleeve 7 and the concrete 10 in place. Are connected by a joint 12 such as a lap joint or a mechanical joint, and a concrete 10 is placed. As shown in FIG. 8A, a reinforced concrete beam 6 having a beam end pin-connected to a column 1 is provided. To construct.

この状態で以後の建築工事を進め、所定の工程が完了した後、具体的には、例えば上棟後、図8の(B)に示すように、スリーブ7内にグラウト13の注入を行うことにより、柱1に対して梁端部を剛接合とした鉄筋コンクリート梁6を構築する。14はスラブを示す。   In this state, the subsequent building work is advanced, and after the predetermined process is completed, specifically, for example, by injecting the grout 13 into the sleeve 7 as shown in FIG. Then, a reinforced concrete beam 6 having a beam end rigidly connected to the column 1 is constructed. Reference numeral 14 denotes a slab.

図示しないが、鉄筋コンクリート梁6の他端側(内端側)は、図8と対称になっているが、施工途中でピン接合にしなくてもよく、換言すれば、施工途中で剛接合にしてもよい。この場合、コンクリート10の打設前又は打設後、グラウト注入を行うことになる。   Although not shown, the other end side (inner end side) of the reinforced concrete beam 6 is symmetric with FIG. 8, but it is not necessary to make a pin joint in the middle of construction, in other words, make a rigid joint in the middle of construction. Also good. In this case, grout injection is performed before or after the concrete 10 is placed.

尚、仮設の梁受け金具3は、梁型枠9を解体撤去する時点で、撤去してもよい。また、仮設の梁受け金具3に代え、パイプサポート等の支保工を用いてもよい。柱1は、プレキャストコンクリート製であるが、現場打ちコンクリートによって構築してもよい。   The temporary beam support 3 may be removed when the beam form 9 is disassembled and removed. Further, instead of the temporary beam bracket 3, a support such as a pipe support may be used. The pillar 1 is made of precast concrete, but may be constructed by cast-in-place concrete.

上記の構成によれば、柱1と鉄筋コンクリート梁6を剛接合した両端固定の架構において、鉄筋コンクリート梁6の端部に発生する端部モーメントを抑制でき、合理的な大梁断面設計が可能となる。即ち、施工途中において、群杭効果による建物の不同沈下により鉄筋コンクリート梁6に強制変形が生じても、梁の端部がピン接合となっているので、鉄筋コンクリート梁6の強制変形に起因する外側端部の応力(端部モーメント)が原理的にゼロとなる。   According to the above configuration, the end moment generated at the end of the reinforced concrete beam 6 can be suppressed in the frame with both ends fixed in which the column 1 and the reinforced concrete beam 6 are rigidly joined, and a rational large beam cross-section design is possible. That is, even if the reinforced concrete beam 6 is forcedly deformed due to the group subsidence due to the group pile effect during construction, the end of the beam is a pin joint, so the outer end caused by the forced deformation of the reinforced concrete beam 6 The stress (end moment) of the part becomes zero in principle.

そして、鉄筋コンクリート梁6の強制変形が生じた後、スリーブ7内にグラウト13注入を行って梁端部を剛接合とした両端固定の架構を成立させるので、鉄筋コンクリート梁6の端部に発生する端部モーメントを、鉄筋コンクリート梁6の強制変形に起因する端部モーメントが作用しないようにした分、低減することができる。   Then, after forced deformation of the reinforced concrete beam 6 occurs, a grout 13 is injected into the sleeve 7 to form a fixed structure with both ends fixed to be rigidly joined, so that an end generated at the end of the reinforced concrete beam 6 is formed. The part moment can be reduced as much as the end moment caused by the forced deformation of the reinforced concrete beam 6 is prevented.

図9は、本発明の他の実施形態を示し、鉄筋コンクリート梁6の全体がプレキャストコンクリート製品5とされている点に特徴がある。即ち、この実施形態では、図9の(A)に示すように、プレキャストコンクリート製品5の端部に埋設された継手用のスリーブ15に柱1の側面から梁長手方向に突出させた鉄筋2を挿入することにより、施工途中においては柱1に対して梁端部をピン接合とした鉄筋コンクリート梁6を構築している。   FIG. 9 shows another embodiment of the present invention, which is characterized in that the entire reinforced concrete beam 6 is a precast concrete product 5. That is, in this embodiment, as shown in FIG. 9 (A), the reinforcing bar 2 that protrudes in the beam longitudinal direction from the side surface of the column 1 to the joint sleeve 15 embedded in the end of the precast concrete product 5 is provided. By inserting, a reinforced concrete beam 6 having a beam end pin-connected to the column 1 during construction is constructed.

そして、この状態で以後の建築工事を進め、所定の工程が完了した後、具体的には、上棟後、図9の(B)に示すように、スリーブ15内にグラウト13の注入を行うことにより、柱1に対して梁端部を剛接合とした鉄筋コンクリート梁6を構築するのである。柱1は、プレキャストコンクリート製として図示するが、現場打ちコンクリートにより、仮設の梁受け金具3を取付け可能な高さ(梁下端)まで先行して構築し、鉄筋2の先端をスリーブ15に挿入した状態で、上階へと打ち継ぐようにしてもよい。その他の構成、作用は先の実施形態と同じであるため、同一構成部材に同一符号を付し、説明を省略する。   In this state, the subsequent building work is advanced, and after the predetermined process is completed, specifically, after the upper building, as shown in FIG. 9B, the grout 13 is injected into the sleeve 15. Thus, the reinforced concrete beam 6 in which the beam end portion is rigidly connected to the column 1 is constructed. Although the pillar 1 is illustrated as being made of precast concrete, it is constructed in advance by a cast-in-place concrete up to a height at which the temporary beam support 3 can be attached (lower end of the beam), and the tip of the reinforcing bar 2 is inserted into the sleeve 15. In the state, you may make it hand over to the upper floor. Since other configurations and operations are the same as those of the previous embodiment, the same components are denoted by the same reference numerals and description thereof is omitted.

図10は、本発明の他の実施形態を示し、ヒンジゾーンLを外して、プレキャストコンクリート製品5の接合を行うようにした点に特徴がある。具体的には、図10の(A)に示すように、両側の柱1から、夫々、ヒンジゾーンLに対応する長さのプレキャストコンクリート製梁材5a、5bを突出させ、これらの間にプレキャストコンクリート製品5を配置してある。そして、一方のプレキャストコンクリート製梁材5aから突出させた鉄筋(これは柱側から突出した鉄筋の一例でもある)2をプレキャストコンクリート製品5の一端部に埋設された継手用のスリーブ15に挿入すると共に、プレキャストコンクリート製梁材5の他端から突出させた梁主筋11を、他方のプレキャストコンクリート製梁材5bに埋設された継手用のスリーブ15に挿入することにより、施工途中においては柱1に対して梁端部をピン接合とした鉄筋コンクリート梁6を構築している。   FIG. 10 shows another embodiment of the present invention, which is characterized in that the hinge zone L is removed and the precast concrete product 5 is joined. Specifically, as shown in FIG. 10A, precast concrete beam members 5a and 5b having a length corresponding to the hinge zone L are protruded from the pillars 1 on both sides, and the precast is interposed between them. A concrete product 5 is arranged. Then, a reinforcing bar (which is also an example of a reinforcing bar protruding from the column side) 2 protruded from one precast concrete beam 5a is inserted into a joint sleeve 15 embedded in one end of the precast concrete product 5. At the same time, the main beam 11 projected from the other end of the precast concrete beam member 5 is inserted into a joint sleeve 15 embedded in the other precast concrete beam member 5b, so that the column 1 is formed during the construction. On the other hand, a reinforced concrete beam 6 having a beam end pin-joined is constructed.

この状態で、以後の建築工事を進め、所定の工程が完了した後、具体的には、上棟後、図10の(B)に示すように、スリーブ15内にグラウト13の注入を行うことにより、柱1に対して梁端部を剛接合とした鉄筋コンクリート梁6を構築するのである。図中の16a、16bは、プレキャストコンクリート製梁材5a、5bを貫通する柱主筋17を差し込んでグラウト注入により一体化する柱主筋継手用スリーブである。その他の構成、作用は、図9の実施形態と同じであるため、同一構成部材に同一符号を付し、説明を省略する。   In this state, the subsequent building work is advanced, and after the predetermined process is completed, specifically, after the upper building, as shown in FIG. 10 (B), the grout 13 is injected into the sleeve 15. The reinforced concrete beam 6 is constructed in which the beam end is rigidly connected to the column 1. Reference numerals 16a and 16b in the figure denote column main reinforcement joint sleeves in which the column main reinforcement 17 penetrating the precast concrete beam members 5a and 5b is inserted and integrated by grout injection. Since other configurations and operations are the same as those in the embodiment of FIG. 9, the same reference numerals are given to the same structural members, and description thereof is omitted.

図11〜図13は、本発明の他の実施形態を示す。この実施形態は、柱1側から梁長手方向に突出させた鉄筋2とプレキャストコンクリート製品5に埋設された梁主筋11とが、何れか一方にのみ嵌合した非接続状態と、両者に略半分ずつ嵌合した接続状態とにわたってスライド可能な継手用のスリーブ15と、その収納スペースを形成するシース管18a、18bとを備えたスライド継手19により接続される点に特徴がある。   11 to 13 show another embodiment of the present invention. In this embodiment, the rebar 2 projecting in the beam longitudinal direction from the column 1 side and the beam main bar 11 embedded in the precast concrete product 5 are fitted in only one of them, and approximately half in both. It is characterized in that it is connected by a slide joint 19 provided with a sleeve 15 for a joint that can be slid over the connected state, and sheath tubes 18a and 18b that form the storage space.

具体的には、両側の柱1から、夫々、図10と同様に、ヒンジゾーンLに対応する長さのプレキャストコンクリート製梁材5a、5bを突出させた後、図12の(A)に示すように、プレキャストコンクリート製梁材5aの鉄筋2だけにスリーブ15を嵌合させた非接続状態(或いは、これと逆に、プレキャストコンクリート製品5に埋設された梁主筋11だけにスリーブ15を嵌合させた非接続状態)で、プレキャストコンクリート製品5をプレキャストコンクリート製梁材5a、5b間に吊り込む。この状態で、図12の(B)に示すように、スリーブ15を引き出して、鉄筋2と梁主筋11に略半分ずつ嵌合した接続状態とすることにより、図11の(A)に示すように、施工途中においては柱1に対して梁端部をピン接合とした鉄筋コンクリート梁6を構築している。ヒンジゾーンLは概ね梁成の1.0〜1.5倍程度となることが多い。   Specifically, after projecting precast concrete beam members 5a and 5b having a length corresponding to the hinge zone L from the pillars 1 on both sides, respectively, as shown in FIG. In this way, the sleeve 15 is fitted only to the rebar 2 of the precast concrete beam 5a (or, conversely, the sleeve 15 is fitted only to the main beam 11 embedded in the precast concrete product 5). In a non-connected state), the precast concrete product 5 is suspended between the precast concrete beam members 5a and 5b. In this state, as shown in FIG. 12 (B), the sleeve 15 is pulled out to be in a connected state in which the rebar 2 and the beam main bar 11 are approximately half-fitted, as shown in FIG. 11 (A). In the middle of the construction, a reinforced concrete beam 6 is constructed with the beam end being pin-joined to the column 1. In many cases, the hinge zone L is approximately 1.0 to 1.5 times the beam formation.

この状態で、以後の建築工事を進め、所定の工程が完了した後、具体的には、例えば上棟後、図11の(B)、図13に示すように、スリーブ15内にグラウト13の注入を行うことにより、柱1に対して梁端部を剛接合とした鉄筋コンクリート梁6を構築するのである。   In this state, the subsequent construction work is advanced, and after the predetermined process is completed, specifically, for example, after the upper building, as shown in FIGS. 11B and 13, the grout 13 is injected into the sleeve 15. By doing this, the reinforced concrete beam 6 with the beam end rigidly joined to the column 1 is constructed.

上記の構成によれば、鉄筋コンクリート梁6の全体がプレキャストコンクリート製品5とされているにもかかわらず、梁主筋がプレキャストコンクリート製品より突出しないため、プレキャストコンクリート製品5を柱間に上方から吊り込んで、柱側から梁長手方向に突出させた鉄筋2とプレキャストコンクリート製品5に埋設された梁主筋11とを継手用のスリーブ15により機械的に接続してピン接合とすることができ、施工性が良い。その他の構成、作用は、図10の実施形態と同じであるため、同一構成部材に同一符号を付し、説明を省略する。   According to the above configuration, although the entire reinforced concrete beam 6 is the precast concrete product 5, the beam main bar does not protrude from the precast concrete product, so the precast concrete product 5 is suspended between the columns from above. The rebar 2 projecting from the column side in the beam longitudinal direction and the beam main bar 11 embedded in the precast concrete product 5 can be mechanically connected by a joint sleeve 15 to form a pin joint. good. Since other configurations and operations are the same as those in the embodiment of FIG. 10, the same components are denoted by the same reference numerals and description thereof is omitted.

尚、多くの場合、群杭効果による建物の不同沈下の進行は、建物がある程度の高さまで構築されていくと緩やかなものとなり、不同沈下による影響が減少する。従って、グラウト注入は、上述した実施形態のように上棟後に行ってもよいが、上棟前であっても、不同沈下の影響が設計上問題にならない高さまで施工された時点で行ってもよい。また、上述した実施形態は、何れも、図1に基づいて説明した超高層建物のような施工途中で群杭効果による建物の不同沈下が予想される鉄筋コンクリート造建物において、建物外面側の柱と中央側の柱間に鉄筋コンクリート梁を架設する場合を対象としているが、本発明は、ロングスパンの鉄筋コンクリート梁を構築する場合にも、適用できる。この場合には、施工途中では、鉄筋コンクリート梁の両端部をピン接合とし、この鉄筋コンクリート梁で支持されるスラブのコンクリート打設後、スリーブ7又は15内にグラウト注入を行って剛接合とすることになる。   In many cases, the progress of the uneven settlement of the building due to the group pile effect becomes gradual when the building is built to a certain height, and the influence of the uneven settlement is reduced. Therefore, the grout injection may be performed after the upper building as in the above-described embodiment, but may be performed at a time when the height is set so that the influence of the uneven settlement does not cause a design problem even before the upper building. In addition, in the above-described embodiments, in the reinforced concrete building where the uneven settlement of the building due to the group pile effect is expected in the middle of construction such as the high-rise building described based on FIG. Although the case where a reinforced concrete beam is installed between the columns on the center side is targeted, the present invention can also be applied to the case where a long span reinforced concrete beam is constructed. In this case, in the middle of construction, both ends of the reinforced concrete beam are pin-bonded, and after placing the concrete of the slab supported by the reinforced concrete beam, grout is injected into the sleeve 7 or 15 to be rigidly bonded. Become.

大梁の強制変形による端部モーメントのつりあがりを説明する模式図である。It is a mimetic diagram explaining lifting of the end moment by forced deformation of a girder. 両端固定の架構におけるモーメント図である。It is a moment diagram in a frame fixed at both ends. 本発明の実施形態を示す要部の斜視図である。It is a perspective view of the principal part which shows embodiment of this invention. 要部の縦断側面図である。It is a vertical side view of the principal part. 鉄筋コンクリート梁の構築方法の説明図である。It is explanatory drawing of the construction method of a reinforced concrete beam. 図5に続く説明図である。It is explanatory drawing following FIG. 図6に続く説明図である。It is explanatory drawing following FIG. 図7に続く説明図である。It is explanatory drawing following FIG. 本発明の他の実施形態を示す鉄筋コンクリート梁の構築方法の説明図である。It is explanatory drawing of the construction method of the reinforced concrete beam which shows other embodiment of this invention. 本発明の他の実施形態を示す鉄筋コンクリート梁の構築方法の説明図である。It is explanatory drawing of the construction method of the reinforced concrete beam which shows other embodiment of this invention. 本発明の他の実施形態を示す鉄筋コンクリート梁の構築方法の説明図である。It is explanatory drawing of the construction method of the reinforced concrete beam which shows other embodiment of this invention. スライド継手を説明する要部の縦断側面図である。It is a vertical side view of the principal part explaining a slide joint. スライド継手を説明する要部の縦断側面図である。It is a vertical side view of the principal part explaining a slide joint.

符号の説明Explanation of symbols

1 柱
2 鉄筋
3 梁受け金具
4 コッター係合用凹部
5 プレキャストコンクリート製品
5a,5b プレキャストコンクリート製品
6 鉄筋コンクリート梁
7 貫通孔形成用のスリーブ
8 コッター係合用凹部
9 梁型枠
10 コンクリート
11 梁主筋
12 継手
13 グラウト
14 スラブ
15 継手用のスリーブ
16a,16b 柱主筋継手用スリーブ
17 柱主筋
18a,18b シース管
19 スライド継手
DESCRIPTION OF SYMBOLS 1 Column 2 Reinforcement 3 Beam receiving bracket 4 Recessed cotter engagement 5 Precast concrete product 5a, 5b Precast concrete product 6 Reinforced concrete beam 7 Sleeve for through-hole formation 8 Recessed cotter engagement 9 Beam formwork 10 Concrete 11 Beam main reinforcement 12 Joint 13 Grout 14 Slab 15 Joint sleeve 16a, 16b Column main reinforcement sleeve 17 Column main reinforcement 18a, 18b Sheath tube 19 Slide joint

Claims (6)

少なくとも端部がプレキャストコンクリート製品とされた鉄筋コンクリート梁の前記端部に埋設されたスリーブに、柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴とする鉄筋コンクリート梁の構築方法。   By inserting a reinforcing bar protruding in the longitudinal direction of the beam from the column side into a sleeve embedded in the end of the reinforced concrete beam whose end is a precast concrete product, the beam end with respect to the column during construction is inserted. The part is made into a pin joint, and after that, the building work is advanced in this state, and after a predetermined process is completed, a grout is injected into the sleeve to make the beam end rigidly joined to the column. To build reinforced concrete beams. 鉄筋コンクリート梁のうち端部だけがプレキャストコンクリート製品とされ、当該プレキャストコンクリート製品に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入し、且つ、プレキャストコンクリート製品のスリーブを貫通した鉄筋の先端側とコンクリートの現場打ちにより構築される梁部分の梁主筋とを接続することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴とする請求項1に記載の鉄筋コンクリート梁の構築方法。   Only the end of the reinforced concrete beam is a precast concrete product, and a reinforcing rod that protrudes in the beam longitudinal direction from the column side is inserted into a sleeve embedded in the precast concrete product, and the reinforcing rod penetrates the sleeve of the precast concrete product. By connecting the tip side of the beam and the beam main reinforcement of the beam part built by spotting concrete, the beam end is pin-bonded to the column during the construction, and the subsequent construction work proceeds in this state, The method for constructing a reinforced concrete beam according to claim 1, wherein after the predetermined process is completed, the end of the beam is rigidly joined to the column by injecting grout into the sleeve. 鉄筋コンクリート梁の全体がプレキャストコンクリート製品とされ、当該プレキャストコンクリート製品の端部に埋設されたスリーブに柱側から梁長手方向に突出させた鉄筋を挿入することにより、施工途中においては柱に対して梁端部をピン接合とし、この状態で以後の建築工事を進め、所定の工程が完了した後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴とする請求項1に記載の鉄筋コンクリート梁の構築方法。   The entire reinforced concrete beam is a precast concrete product. By inserting a reinforcing bar that protrudes in the longitudinal direction of the beam from the column side into a sleeve embedded in the end of the precast concrete product, the beam is against the column during construction. The end part is a pin joint, and in this state, the subsequent building work is proceeded. After a predetermined process is completed, the end of the beam is rigidly joined to the column by injecting grout into the sleeve. The construction method of the reinforced concrete beam of Claim 1. 柱側から梁長手方向に突出させた鉄筋とプレキャストコンクリート製品に埋設された梁主筋とが同芯状に配置され、且つ、前記鉄筋と梁主筋のうち何れか一方にのみ嵌合した非接続状態と、両者に略半分ずつ嵌合した接続状態とにわたってスライド可能な継手用スリーブと、その収納スペースを形成するシース管とを備えたスライド継手により接続されることを特徴とする請求項1〜3の何れかに記載の鉄筋コンクリート梁の構築方法。   A non-connected state in which the reinforcing bars projecting in the longitudinal direction of the beam from the column side and the main reinforcing bars embedded in the precast concrete product are arranged concentrically, and fitted to only one of the reinforcing bars and the main reinforcing bars. And a joint sleeve that is slidable over a connection state in which approximately half of them are connected to each other, and a sheath joint that forms a storage space of the joint sleeve. The construction method of the reinforced concrete beam in any one of. 施工途中においては柱に対して鉄筋コンクリート梁の外側端部をピン接合とし、上棟後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴とする請求項1〜4の何れかに記載の鉄筋コンクリート梁の構築方法。   The outer end of the reinforced concrete beam is pin-bonded to the column during construction, and the beam end is rigidly connected to the column by injecting grout into the sleeve after the upper building. The construction method of the reinforced concrete beam in any one of claim | item 1-4. 施工途中においては柱に対して鉄筋コンクリート梁の両端部をピン接合とし、前記梁上のスラブコンクリートの打設後、スリーブ内にグラウト注入を行うことにより、柱に対して梁端部を剛接合とすることを特徴とする請求項1〜4の何れかに記載の鉄筋コンクリート梁の構築方法。   During construction, both ends of the reinforced concrete beam are pin-bonded to the column, and after placing the slab concrete on the beam, grout is injected into the sleeve, so that the beam end is rigidly bonded to the column. A construction method of a reinforced concrete beam according to any one of claims 1 to 4.
JP2008000025A 2008-01-04 2008-01-04 Reinforced concrete beam construction method Pending JP2009161974A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008000025A JP2009161974A (en) 2008-01-04 2008-01-04 Reinforced concrete beam construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008000025A JP2009161974A (en) 2008-01-04 2008-01-04 Reinforced concrete beam construction method

Publications (1)

Publication Number Publication Date
JP2009161974A true JP2009161974A (en) 2009-07-23

Family

ID=40964891

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008000025A Pending JP2009161974A (en) 2008-01-04 2008-01-04 Reinforced concrete beam construction method

Country Status (1)

Country Link
JP (1) JP2009161974A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013227742A (en) * 2012-04-24 2013-11-07 Ohbayashi Corp Construction method for concrete structure, and concrete structure
CN105951986A (en) * 2016-06-17 2016-09-21 中国十七冶集团有限公司 Edge joint connecting structure and method of prefabricated integrated type frame column beam
CN107489277A (en) * 2017-08-30 2017-12-19 中建四局第建筑工程有限公司 A kind of new steel reinforced concrete bean column node constructing structure and comprehensive construction method
CN109386053A (en) * 2018-11-19 2019-02-26 湘潭大学 A kind of assembled steel reinforced concrete column and reinforced beam connection structure entirely
CN109537741A (en) * 2019-01-17 2019-03-29 重庆渝建实业集团股份有限公司 Telescopic steel-concrete girder connection connection structure and its installation method
CN110629890A (en) * 2019-09-26 2019-12-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Reinforced concrete column connecting structure and building
CN112282079A (en) * 2020-09-15 2021-01-29 青岛理工大学 Connection node and construction method of prefabricated steel structure box column and reinforced concrete beam
CN113482170A (en) * 2021-07-20 2021-10-08 上海建工一建集团有限公司 Construction method of outwards-extending connecting piece of stiff concrete joint
CN114482598A (en) * 2022-01-12 2022-05-13 广城建设集团有限公司 Building column strengthening structure and method
CN114809289A (en) * 2022-04-15 2022-07-29 中建一局集团第三建筑有限公司 Construction process of weldable sleeve
CN115370001A (en) * 2022-09-09 2022-11-22 龙信建设集团有限公司 Grouting construction process for prestress assembly type concrete frame joint
KR20230002159U (en) * 2022-05-04 2023-11-13 김찬종 Lightweight hybrid truss module and lightweight truss structure using the same
CN117719064A (en) * 2024-02-07 2024-03-19 保利长大工程有限公司 Curve beam prefabrication construction method and detection device
KR102796179B1 (en) * 2023-10-20 2025-04-16 주식회사 판스틸 An interlayer floor structure that prevents noise between floors and increases the cross-sectional strength of concrete slabs and its construction method

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013227742A (en) * 2012-04-24 2013-11-07 Ohbayashi Corp Construction method for concrete structure, and concrete structure
CN105951986A (en) * 2016-06-17 2016-09-21 中国十七冶集团有限公司 Edge joint connecting structure and method of prefabricated integrated type frame column beam
CN107489277A (en) * 2017-08-30 2017-12-19 中建四局第建筑工程有限公司 A kind of new steel reinforced concrete bean column node constructing structure and comprehensive construction method
CN107489277B (en) * 2017-08-30 2024-04-12 中建四局第一建设有限公司 Novel steel-hybrid beam column node construction structure and comprehensive construction method
CN109386053A (en) * 2018-11-19 2019-02-26 湘潭大学 A kind of assembled steel reinforced concrete column and reinforced beam connection structure entirely
CN109386053B (en) * 2018-11-19 2024-02-13 湘潭大学 Full-assembled reinforced concrete column and reinforced concrete beam connection structure
CN109537741B (en) * 2019-01-17 2023-10-24 渝建实业集团股份有限公司 Sleeve type steel-concrete beam node connecting structure and installation method thereof
CN109537741A (en) * 2019-01-17 2019-03-29 重庆渝建实业集团股份有限公司 Telescopic steel-concrete girder connection connection structure and its installation method
CN110629890A (en) * 2019-09-26 2019-12-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Reinforced concrete column connecting structure and building
CN112282079A (en) * 2020-09-15 2021-01-29 青岛理工大学 Connection node and construction method of prefabricated steel structure box column and reinforced concrete beam
CN113482170A (en) * 2021-07-20 2021-10-08 上海建工一建集团有限公司 Construction method of outwards-extending connecting piece of stiff concrete joint
CN114482598B (en) * 2022-01-12 2023-09-22 广城建设集团有限公司 Building column strengthening structure and method
CN114482598A (en) * 2022-01-12 2022-05-13 广城建设集团有限公司 Building column strengthening structure and method
CN114809289B (en) * 2022-04-15 2023-04-18 中建一局集团第三建筑有限公司 Construction process for weldable sleeve
CN114809289A (en) * 2022-04-15 2022-07-29 中建一局集团第三建筑有限公司 Construction process of weldable sleeve
KR20230002159U (en) * 2022-05-04 2023-11-13 김찬종 Lightweight hybrid truss module and lightweight truss structure using the same
KR200498382Y1 (en) * 2022-05-04 2024-09-30 김명곤 Lightweight hybrid truss module and lightweight truss structure using the same
CN115370001B (en) * 2022-09-09 2024-04-09 龙信建设集团有限公司 Grouting construction process for prestressed assembled concrete frame joints
CN115370001A (en) * 2022-09-09 2022-11-22 龙信建设集团有限公司 Grouting construction process for prestress assembly type concrete frame joint
KR102796179B1 (en) * 2023-10-20 2025-04-16 주식회사 판스틸 An interlayer floor structure that prevents noise between floors and increases the cross-sectional strength of concrete slabs and its construction method
CN117719064A (en) * 2024-02-07 2024-03-19 保利长大工程有限公司 Curve beam prefabrication construction method and detection device
CN117719064B (en) * 2024-02-07 2024-05-31 保利长大工程有限公司 Curve beam prefabrication construction method and detection device

Similar Documents

Publication Publication Date Title
JP2009161974A (en) Reinforced concrete beam construction method
KR101062592B1 (en) Reciprocal Joint Method of Reinforcement Column Assembly Columns
JP6855296B2 (en) Building foundation structure and its construction method
JP2013136922A (en) Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method
KR20120060015A (en) Precast concrete member with junction for reinforcing earthquake resistance for a window frame and method of constructing a building using it
KR100634726B1 (en) Slab construction structure of underground structure and slab and underground retaining wall construction method without frame rib
KR101216126B1 (en) Arch structure construction method using axial and longitudinal connection rebar
KR101150369B1 (en) Complex girder for building
JP5602455B2 (en) Beam members and building structures
KR101521946B1 (en) Enlarged capital of steel framed reinforced concrete column
JP5033645B2 (en) How to build a synthetic slab
KR100710583B1 (en) Composite structure of PC pillar and cheolgolbo
JP6428027B2 (en) Column rebar connection panel and rebar structure
JP2018115514A (en) Pile support structure construction method and reinforcing member used therefor
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP2020070589A (en) Reinforcement structure for column base part of steel column
KR101576865B1 (en) Construction method of slab for bridge without support bar using converse T-type beams
JP6302503B2 (en) Pca floor slab and its installation method, Pca support and its installation method
JP6766468B2 (en) Segment wall and tunnel lining
JP2002030672A (en) Joint structure between foundation pile and column base and its construction method
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP2864906B2 (en) Precast wall joining method
KR100694763B1 (en) Construction method of underground structure using concrete composite beam
JP2009108500A (en) Precast beam construction method, precast beam, precast beam joint structure, and building
JP2007218086A (en) Steel tower foundation structure