[go: up one dir, main page]

JP2006225961A - Pier head structure and construction method - Google Patents

Pier head structure and construction method Download PDF

Info

Publication number
JP2006225961A
JP2006225961A JP2005040448A JP2005040448A JP2006225961A JP 2006225961 A JP2006225961 A JP 2006225961A JP 2005040448 A JP2005040448 A JP 2005040448A JP 2005040448 A JP2005040448 A JP 2005040448A JP 2006225961 A JP2006225961 A JP 2006225961A
Authority
JP
Japan
Prior art keywords
pier
precast concrete
concrete plate
plate
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005040448A
Other languages
Japanese (ja)
Inventor
Noritaka Sugano
昇孝 菅野
Hiroshi Fukaya
浩史 深谷
Masayuki Okada
昌之 岡田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji PS Corp
Original Assignee
Fuji PS Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji PS Corp filed Critical Fuji PS Corp
Priority to JP2005040448A priority Critical patent/JP2006225961A/en
Publication of JP2006225961A publication Critical patent/JP2006225961A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【課題】 高所での作業時間を少なくするとともに、埋め殺しとなるH鋼架台や支保工等が不要で、且つプレキャストコンクリート版とコンクリートのかぶり部分での剪断破壊を防止することができる橋脚頭部構造を提供すること。
【解決手段】 脚頭部出来形に合わせ現場にてプレテンション方式でPRC版を製作、架設することができ、また、その版上で鉄筋・型枠・コンクリート打設を行えるため、高所での作業時間が激減し安全面で優れた施工方法となり、さらに、H鋼架台と支保工等が不要となるため、経済的にも有利となる。また、中空断面を有する橋脚の開口部に、周囲から複数の形鋼の突出したプレキャストコンクリート版を設置し、その上からコンクリートを打設して橋脚頭部を形成したので、脚頭部におけるプレキャストコンクリート版とコンクリートのかぶり部分での剪断破壊を防止することができる。
【選択図】 図1
PROBLEM TO BE SOLVED: To reduce working time at a high place, eliminate the need for an H-steel gantry and a supporting work to be buried, and prevent a shear failure at a precast concrete plate and a concrete covering portion. Providing a head structure.
SOLUTION: A PRC plate can be manufactured and installed by a pretension method at the site according to the shape of the leg head, and rebars, formwork, and concrete can be placed on the plate. The working time is drastically reduced and the construction method is excellent in terms of safety. Further, since the H steel frame and the supporting work are not required, it is economically advantageous. In addition, a precast concrete plate with a plurality of steel shapes protruding from the periphery was installed at the opening of the pier with a hollow cross section, and concrete was cast from above to form a pier head. It is possible to prevent shear failure at the concrete plate and the concrete cover.
[Selection] Figure 1

Description

本発明は、高架道路等を支える橋脚の頭部構造及びその施工方法に関するものである。   The present invention relates to a head structure of a bridge pier that supports an elevated road and the like and a construction method thereof.

橋脚の構造には、内部が中空状に構成されているものがある。しかし、このような中空状の橋脚であっても橋桁を支えるために頭部を中実にする必要がある。このために、中空部分に蓋をしてから、その上に配筋を行い、型枠を組んでからコンクリートを打設していた。   Some pier structures have a hollow interior. However, even such a hollow pier needs to have a solid head to support the bridge girder. For this purpose, after covering the hollow part, bar arrangement is performed on the hollow part, and after placing the formwork, concrete is placed.

従来の橋脚頭部の施工方法としては、例えば、図8、9に示すように地上で組み立てた吊り足場1をクレーン等で橋脚2の橋頭部開口3に設置する。吊り足場1には、安全ネット5を予め取り付けておく。吊り足場1は、橋脚2に埋込まれている鉄筋6に固定する。設置した吊り足場1に作業員が乗って、既設のコンクリートにケミカルアンカーを打ち込みブラケット式H鋼架台4を施工する。そして、このブラケット式H鋼架台4の上にH鋼7を並べて設置する。吊り足場1及び安全ネット5を撤去した後、残りのH鋼7を配置し合板を組み立てて完了である。   As a conventional construction method of the pier head, for example, as shown in FIGS. 8 and 9, the suspension scaffold 1 assembled on the ground is installed in the pier head opening 3 of the pier 2 with a crane or the like. A safety net 5 is attached to the suspension scaffold 1 in advance. The suspension scaffold 1 is fixed to a reinforcing bar 6 embedded in the pier 2. A worker rides on the installed suspension scaffold 1, drives a chemical anchor into the existing concrete, and constructs the bracket-type H steel frame 4. And H steel 7 is installed side by side on this bracket type H steel frame 4. After removing the suspension scaffold 1 and the safety net 5, the remaining H steel 7 is placed and the plywood is assembled to complete.

しかし、上記従来の橋脚頭部の施工方法においては、高所における吊り足場で長時間作業をしなければならず、危険であった。また、ブラケット式H鋼架台と支保工はコンクリート硬化後は不要になるにもかかわらず、橋脚頭部に埋殺しとなり不経済であった。
更に、ブラケット式H鋼架台を構築せずに、橋脚頭部の開口部に直接プレキャストコンクリート版等を載せようとしても、橋脚軸方向鉄筋までの寸法が小さく、十分なかぶり寸法を確保することができず、橋脚頭部コンクリートのかぶり部分が剪断破壊を起こす虞れが存在した。
However, in the conventional construction method of the pier head, it is dangerous because the work must be performed for a long time on the suspension scaffold at a high place. In addition, the bracket-type H steel frame and supporting work are not necessary after the concrete is hardened, but they are buried in the pier head and are uneconomical.
Furthermore, even if it is going to place a precast concrete slab directly on the opening of the pier head without constructing a bracket-type H steel frame, the dimensions to the pier axial rebar are small and sufficient cover dimensions must be secured. However, there was a possibility that the concrete cover part of the pier head part would cause shear failure.

この発明は上記に鑑み提案されたもので、橋脚の開口部を塞ぐプレキャストコンクリート版の周囲から複数の形鋼を突出させ、脚頭部コンクリートのかぶり部分での剪断破壊を防止することのできる橋脚頭部構造及びその施工方法を提供することを目的とする。   The present invention has been proposed in view of the above, and a pier capable of preventing a shear failure at a covering portion of a leg head concrete by projecting a plurality of shape steels from the periphery of a precast concrete plate that closes the opening of the pier. It aims at providing a head structure and its construction method.

上記目的を達成するために、本発明は、中空断面を有する橋脚の開口部に、周囲から複数の形鋼の突出したプレキャストコンクリート版を設置し、その上からコンクリートを打設して橋脚頭部を形成したことを特徴とする。   In order to achieve the above object, the present invention provides a pier head by installing a precast concrete plate in which a plurality of shape steels protrude from the periphery in an opening portion of a pier having a hollow cross section, and placing concrete from above. Is formed.

また、本発明において、前記プレキャストコンクリート版から突出した形鋼は、橋脚軸方向鉄筋と重ならないように配置されたことを特徴としている。   In the present invention, the section steel protruding from the precast concrete plate is arranged so as not to overlap with the pier axial rebar.

また、本発明において、前記プレキャストコンクリート版は、複数に分割されていることを特徴としている。   In the present invention, the precast concrete slab is divided into a plurality of parts.

また、本発明は、前記プレキャストコンクリート版の上面は、脚頭部コンクリートとの付着を確保するために凹凸が形成されたことを特徴としている。   Further, the present invention is characterized in that the top surface of the precast concrete plate is provided with irregularities to ensure adhesion with the leg head concrete.

また、本発明は、型枠の周囲から複数の形鋼を突出させた状態でプレキャストコンクリート版を製作する工程と、中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、前記プレキャストコンクリート版敷設後、上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成ることを特徴としている。   Further, the present invention provides a process for producing a precast concrete plate in a state in which a plurality of shape steels are protruded from the periphery of a formwork, and the plurality of shape steels protruding from the periphery at the opening of the pier having a hollow cross section. A step of installing a precast concrete plate so as not to overlap with an axial reinforcing bar, a step of installing an outer formwork and a reinforcing bar on the upper part after laying the precast concrete plate, and placing concrete on the precast concrete plate It consists of a process.

また、本発明は、型枠の周囲から複数の形鋼を突出させた状態で緊張材を緊張してプレキャストコンクリート版を製作する工程と、中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、前記プレキャストコンクリート版敷設後、上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成ることを特徴としている。   The present invention also includes a step of producing a precast concrete plate by tensioning a tension member in a state in which a plurality of shape steels are protruded from the periphery of a formwork, and an opening of a pier having a hollow cross section that protrudes from the periphery. A step of installing a precast concrete plate so that a plurality of sections do not overlap with the pier axial reinforcing bars, a step of installing an outer formwork and a reinforcing bar on the upper part after laying the precast concrete plate, and a top of the precast concrete plate It is characterized by comprising the step of placing concrete in the wall.

この発明は上記した構成からなるので、以下に説明するような効果を奏することができる。   Since this invention consists of an above-described structure, there can exist an effect which is demonstrated below.

本発明では、中空断面を有する橋脚の開口部に、周囲から複数の形鋼の突出したプレキャストコンクリート版を設置し、その上からコンクリートを打設して橋脚頭部を形成したので、脚頭部コンクリートのかぶり部分での剪断破壊を防止することができる。また、従来のように高所における吊り足場での長時間作業を必要とせず安全となり、打ち込んだケミカルアンカーの固化を待つ必要もなく工期短縮になる。また、ブラケット式H鋼架台と支保工はコンクリート硬化後は不要になるにもかかわらず、埋殺しとなり不経済となる。   In the present invention, a precast concrete plate having a plurality of steel shapes protruding from the periphery is installed in an opening of a pier having a hollow cross section, and a concrete pier is formed thereon to form a pier head. It is possible to prevent shear fracture at the concrete cover. Further, it is safe without requiring a long work on a suspended scaffolding at a high place as in the prior art, and the construction period is shortened without waiting for solidification of the driven chemical anchor. In addition, the bracket-type H steel frame and supporting work are not necessary after the concrete is hardened, but are buried and become uneconomical.

また、本発明では、前記プレキャストコンクリート版から突出した形鋼は、橋脚軸方向鉄筋と重ならないように配置されたので、橋脚10から立ち上がった橋脚軸方向鉄筋の邪魔になることなく開口部を閉鎖することができる。   Further, in the present invention, the shape steel projecting from the precast concrete plate is arranged so as not to overlap with the pier axial rebar, so that the opening is closed without obstructing the pier axial rebar rising from the pier 10. can do.

また、本発明では、前記プレキャストコンクリート版が複数に分割されているので、クレーン等で高所に吊り上げる際に設置作業が容易である。したがって、作業能率の向上を図ることができる。   In the present invention, since the precast concrete plate is divided into a plurality of parts, installation work is easy when the crane is lifted to a high place. Therefore, the work efficiency can be improved.

また、本発明では、前記プレキャストコンクリート版の上面に凹凸が形成されたので、その上に打設するコンクリートとの接合性を向上することができる。   Moreover, in this invention, since the unevenness | corrugation was formed in the upper surface of the said precast concrete plate, bondability with the concrete cast on it can be improved.

また、本発明では、型枠の周囲から複数の形鋼を突出させた状態でプレキャストコンクリート版を製作する工程と、中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、前記プレキャストコンクリート版敷設後、上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成るので効率的に橋脚頭部を施工することができる。   Further, in the present invention, a step of producing a precast concrete plate in a state where a plurality of shape steels are protruded from the periphery of the formwork, and a plurality of the shape steels protruding from the periphery at the opening portion of the pier having a hollow cross section A step of installing a precast concrete plate so as not to overlap with an axial reinforcing bar, a step of installing an outer formwork and a reinforcing bar on the upper part after laying the precast concrete plate, and placing concrete on the precast concrete plate Since it consists of a process, a pier head can be constructed efficiently.

また、本発明では、型枠の周囲から複数の形鋼を突出させた状態で緊張材を緊張してプレキャストコンクリート版を製作する工程と、中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、前記プレキャストコンクリート版敷設後、上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成るので効率的に橋脚頭部を施工することができる。   Further, in the present invention, a step of producing a precast concrete plate by tensioning a tension member in a state where a plurality of shape steels are protruded from the periphery of the formwork, and an opening of a pier having a hollow cross section protruded from the periphery. A step of installing a precast concrete plate so that a plurality of sections do not overlap with the pier axial rebar, a step of installing an outer formwork and a reinforcing bar on the upper part after laying the precast concrete plate, and a top of the precast concrete plate It is possible to construct the pier head efficiently because it comprises the step of placing concrete on the wall.

橋脚の開口部を塞ぐプレキャストコンクリート版の周囲から複数の形鋼を突出させ、脚頭部コンクリートのかぶり部分での剪断破壊を防止することのできる橋脚頭部構造及びその施工方法を実現した。   A pier head structure that can prevent shear failure at the cover part of the leg head concrete and its construction method were realized by projecting a plurality of steel shapes from the periphery of the precast concrete plate that blocks the opening of the pier.

以下、一実施の形態を示す図面に基づいて本発明を詳細に説明する。図1は本発明に係る橋脚頭部構造を示す説明図、図2は本発明に係る橋脚頭部の施工方法を示す説明図、図3は本発明に係る橋脚頭部の施工方法を示す説明図、図4は本発明の橋脚頭部の施工方法を示す平面図である。ここで、本実施例の橋脚頭部構造は、中空断面を有する橋脚10の開口部11に、周囲から複数の形鋼12の突出したプレキャストコンクリート版13を設置し、その上からコンクリートを打設して橋脚頭部14を形成したものである。   Hereinafter, the present invention will be described in detail with reference to the drawings illustrating an embodiment. FIG. 1 is an explanatory view showing a pier head structure according to the present invention, FIG. 2 is an explanatory view showing a construction method of the pier head according to the present invention, and FIG. 3 is an explanation showing a construction method of the pier head according to the present invention. 4 and 4 are plan views showing the construction method of the pier head according to the present invention. Here, in the pier head structure of the present embodiment, a precast concrete plate 13 in which a plurality of shape steels 12 protrude from the periphery is installed in the opening 11 of the pier 10 having a hollow cross section, and concrete is placed thereon. Thus, the pier head portion 14 is formed.

図2は、本発明に係る橋脚頭部の施工方法を示す説明図、図3は本発明に係る橋脚頭部の施工方法を示す説明図である。図2は、橋脚10の開口部11にプレキャストコンクリート版13を載せた状態を橋軸方向に切断した断面である。プレキャストコンクリート版13の周囲から延設された形鋼12は、橋脚10の上面に延びた橋脚軸方向鉄筋15に重ならないように配置されている。図3は、橋脚10の開口部11にプレキャストコンクリート版13を載せた状態を橋軸直角方向に切断した断面である。本実施例において、形鋼12は橋軸方向には、配設されていない。   FIG. 2 is an explanatory view showing a construction method of the pier head according to the present invention, and FIG. 3 is an explanatory view showing a construction method of the pier head according to the present invention. FIG. 2 is a cross-sectional view of the state in which the precast concrete plate 13 is placed in the opening 11 of the pier 10 cut in the bridge axis direction. The section steel 12 extending from the periphery of the precast concrete plate 13 is arranged so as not to overlap the pier axial rebar 15 extending on the upper surface of the pier 10. FIG. 3 is a cross section obtained by cutting the precast concrete plate 13 on the opening 11 of the pier 10 in a direction perpendicular to the bridge axis. In this embodiment, the section steel 12 is not arranged in the bridge axis direction.

図4は、本発明の橋脚頭部の施工方法を示す平面図である。プレキャストコンクリート版13の周囲から延設された形鋼12は橋脚軸方向鉄筋15の邪魔にならない位置に配設されている。したがって、プレキャストコンクリート版13を載せた場合に、橋脚10の端部が欠け落ちたりする虞れもない。   FIG. 4 is a plan view showing the construction method of the pier head according to the present invention. The shape steel 12 extended from the periphery of the precast concrete plate 13 is disposed at a position that does not interfere with the pier axial rebar 15. Therefore, when the precast concrete plate 13 is placed, there is no possibility that the end portion of the pier 10 is dropped off.

図5は、本発明の橋脚頭部の施工方法に使用されるプレキャストコンクリート版を示す平面図、図6は、同橋脚頭部の施工方法に使用されるプレキャストコンクリート版を示す側面図である。本実施の形態では、プレキャストコンクリート版13は、13a、13b、13cに3分割されている。また、プレキャストコンクリート版13の上面、側面は、粗面仕上げが成されており、打設するコンクリートとの接合性を向上している。プレキャストコンクリート版13の上面の適宜位置には、吊り込み用の吊り金具が埋設されている。   FIG. 5 is a plan view showing a precast concrete plate used in the construction method of the pier head according to the present invention, and FIG. 6 is a side view showing the precast concrete plate used in the construction method of the pier head. In the present embodiment, the precast concrete plate 13 is divided into three parts 13a, 13b and 13c. In addition, the upper surface and side surfaces of the precast concrete plate 13 are roughened to improve the bondability with the concrete to be placed. At appropriate positions on the upper surface of the precast concrete plate 13, hanging brackets for suspending are embedded.

次に、橋脚頭部の施工方法について説明する。
先ず、プレキャストコンクリート版(PRC版またはPC版の場合)を製作する工程では、H鋼材等を使用してプレキャストコンクリート版の周囲を囲う簡易な緊張装置(H鋼反力架台)を組み立てる。簡易な緊張装置のため、施工現場にて容易にプレストレス導入ができる。次に、型枠、鉄筋を組み立てる。型枠の周囲から複数の形鋼12を突出させ、PC鋼材を挿入した後、ジャッキ等でこのPC鋼材を緊張する。その後、コンクリートを打設し、養生する。コンクリートの表面には、凝結遅延剤が散布または塗布してあり、表面、側面に高圧水を噴射することにより、粗面仕上げを行う。コンクリートの硬化後、PC鋼材の緊張を解放することにより、プレストレスを導入する。このようにして表面、側面に粗面仕上げが成されたプレキャストコンクリート版13を製作することができる。
Next, the construction method of the pier head will be described.
First, in the process of manufacturing a precast concrete plate (in the case of a PRC plate or a PC plate), a simple tension device (H steel reaction force stand) surrounding the precast concrete plate is assembled using H steel or the like. Pre-stress can be easily introduced at the construction site due to a simple tension device. Next, formwork and rebar are assembled. A plurality of section steels 12 are protruded from the periphery of the mold, and after inserting the PC steel material, the PC steel material is tensioned with a jack or the like. After that, concrete is cast and cured. A set retarder is sprayed or applied to the surface of the concrete, and the surface is roughened by spraying high-pressure water on the surface and side. After the concrete is hardened, prestress is introduced by releasing the tension of the PC steel. In this way, the precast concrete plate 13 having a roughened surface and side surfaces can be manufactured.

プレキャストコンクリート版を設置する工程では、中空断面を有する橋脚10の開口部11に周囲から突出した複数の形鋼12が橋脚軸方向鉄筋15と重ならないように、クレーン等で吊り上げる。この際、プレキャストコンクリート版13は、3分割されているので据え付け作業が容易である。分割の数は、3に限ることなく、2分割でも4分割でもプレキャストコンクリート版13の架設重量を考慮した分割数でよい。   In the step of installing the precast concrete plate, a plurality of structural steels 12 protruding from the periphery of the opening 11 of the pier 10 having a hollow cross section are lifted by a crane or the like so as not to overlap the pier axial rebar 15. At this time, the precast concrete plate 13 is divided into three parts, so that the installation work is easy. The number of divisions is not limited to three, and may be two or four divisions considering the installation weight of the precast concrete plate 13.

外型枠と鉄筋を設置する工程では、橋脚10の上面に載置したプレキャストコンクリート版13の上部分に外型枠と鉄筋を設置する。外型枠は、橋脚頭部14を形成する周囲に設置する。次に、コンクリートを打設する工程では、プレキャストコンクリート版13の上で外型枠内にコンクリートを打設して橋脚頭部14を形成する。このようにして、中空断面を有する橋脚10の上に、橋脚頭部14を施工することができる。   In the step of installing the outer formwork and the reinforcing bar, the outer formwork and the reinforcing bar are installed on the upper part of the precast concrete plate 13 placed on the upper surface of the pier 10. The outer mold is installed around the pier head 14. Next, in the step of placing concrete, concrete is placed in the outer mold frame on the precast concrete plate 13 to form the pier head 14. In this way, the pier head 14 can be constructed on the pier 10 having a hollow cross section.

以上のような橋脚頭部の施工方法によれば、従来のように高所における吊り足場を必要とせず安全面で優れた施工方法であり、打ち込んだケミカルアンカーが固化するまで次の作業を待つ必要もなく、H鋼架台と支保工が不要となるため経済的に有利となる。また、橋脚軸方向鉄筋までの寸法が短く、十分なかぶり寸法を確保することができない場合でも、橋脚頭部コンクリートのかぶり部分が剪断破壊する虞れもない。   According to the construction method of the pier head as described above, it is a construction method that is superior in safety without requiring a suspension scaffold at a high place as before, and waits for the next work until the driven chemical anchor is solidified. There is no need, and the H steel frame and the support work are unnecessary, which is economically advantageous. Further, even when the dimension to the pier axial rebar is short and a sufficient cover dimension cannot be secured, there is no possibility that the cover part of the pier head concrete will be sheared and broken.

図1は、本発明に係る橋脚頭部構造を示す説明図である。FIG. 1 is an explanatory view showing a pier head structure according to the present invention. 図2は、本発明に係る橋脚頭部の施工方法を示す説明図である。FIG. 2 is an explanatory view showing a construction method of the pier head according to the present invention. 図3は、本発明に係る橋脚頭部の施工方法を示す説明図である。FIG. 3 is an explanatory view showing the construction method of the pier head according to the present invention. 図4は、同橋脚頭部の施工方法を示す平面図である。FIG. 4 is a plan view showing a construction method of the pier head. 図5は、同橋脚頭部の施工方法に使用されるプレキャストコンクリート版を示す平面図である。FIG. 5 is a plan view showing a precast concrete plate used in the construction method of the pier head. 図6は、同橋脚頭部の施工方法に使用されるプレキャストコンクリート版を示す側面図である。FIG. 6 is a side view showing a precast concrete plate used in the construction method of the pier head. 図7は、同脚頭の開口部にプレキャストコンクリート版を載せた際の鉄筋と形鋼との関係を示す要部説明図である。FIG. 7 is an explanatory view of a main part showing the relationship between a reinforcing bar and a shape steel when a precast concrete plate is placed on the opening of the leg head. 図8は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 8 is an explanatory view showing a construction procedure of a conventional pier head. 図9は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 9 is an explanatory view showing a construction procedure of a conventional pier head. 図10は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 10 is an explanatory view showing a construction procedure of a conventional pier head. 図11は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 11 is an explanatory view showing a construction procedure of a conventional pier head. 図12は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 12 is an explanatory view showing a construction procedure of a conventional pier head. 図13は、従来の橋脚頭部の施工手順を示す説明図である。FIG. 13 is an explanatory view showing a construction procedure of a conventional pier head. 図14は、従来の工法において橋脚頭部の開口部をI形鋼材で閉塞した状態を示す平面図である。FIG. 14 is a plan view showing a state in which an opening of a pier head is closed with an I-shaped steel material in a conventional construction method.

符号の説明Explanation of symbols

10 橋脚
11 開口部
12 形鋼
13 プレキャストコンクリート版
14 橋脚頭部
15 橋脚軸方向鉄筋
10 Pier 11 Opening 12 Shaped Steel 13 Precast Concrete Plate 14 Pier Head 15 Bridge Pier Axial Rebar

Claims (6)

中空断面を有する橋脚の開口部に、周囲から複数の形鋼の突出したプレキャストコンクリート版(RC版、PC版、PRC版)を設置し、その上からコンクリートを打設して橋脚頭部を形成したことを特徴とする橋脚頭部構造。   At the opening of the pier with a hollow cross section, a precast concrete plate (RC plate, PC plate, PRC plate) with multiple shaped steel protruding from the periphery is installed, and concrete is cast from above to form the pier head. A pier head structure characterized by 前記プレキャストコンクリート版から突出した形鋼は、橋脚軸方向鉄筋と重ならないように配置されたことを特徴とする請求項1に記載の橋脚頭部構造。   2. The pier head structure according to claim 1, wherein the section steel protruding from the precast concrete plate is arranged so as not to overlap with a pier axial rebar. 3. 前記プレキャストコンクリート版は、複数に分割されていることを特徴とする請求項1または2に記載の橋脚頭部構造。   The pier head structure according to claim 1 or 2, wherein the precast concrete plate is divided into a plurality of parts. 前記プレキャストコンクリート版の上面は、脚頭部コンクリートとの付着を確保するために凹凸が形成されたことを特徴とする請求項1〜3の何れか1に記載の橋脚頭部構造。   The pier head structure according to any one of claims 1 to 3, wherein the upper surface of the precast concrete plate is formed with irregularities to ensure adhesion with the leg head concrete. 型枠の周囲から複数の形鋼を突出させた状態でプレキャストコンクリート版を製作する工程と、
中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、
前記プレキャストコンクリート版敷設後の上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成ることを特徴とする橋脚頭部の施工方法。
Producing a precast concrete plate with a plurality of steel shapes protruding from the periphery of the formwork;
Installing a precast concrete plate so that a plurality of sections protruding from the periphery do not overlap with the pier axial rebar at the opening of the pier having a hollow section;
A construction method of a pier head comprising a step of installing an outer mold and a reinforcing bar on an upper portion after laying the precast concrete plate, and a step of placing concrete on the precast concrete plate.
型枠の周囲から複数の形鋼を突出させた状態で緊張材を緊張してプレキャストコンクリート版を製作する工程と、
中空断面を有する橋脚の開口部に前記周囲から突出した複数の形鋼が橋脚軸方向鉄筋と重ならないようにプレキャストコンクリート版を設置する工程と、
前記プレキャストコンクリート版敷設後の上部分に外型枠と鉄筋を設置する工程と、前記プレキャストコンクリート版の上にコンクリートを打設する工程とから成ることを特徴とする橋脚頭部の施工方法。
A process of producing a precast concrete plate by tensioning a tension material in a state where a plurality of shape steels are projected from the periphery of the formwork,
Installing a precast concrete plate so that a plurality of sections protruding from the periphery do not overlap with the pier axial rebar at the opening of the pier having a hollow section;
A construction method of a pier head comprising a step of installing an outer mold and a reinforcing bar on an upper portion after laying the precast concrete plate, and a step of placing concrete on the precast concrete plate.
JP2005040448A 2005-02-17 2005-02-17 Pier head structure and construction method Pending JP2006225961A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005040448A JP2006225961A (en) 2005-02-17 2005-02-17 Pier head structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005040448A JP2006225961A (en) 2005-02-17 2005-02-17 Pier head structure and construction method

Publications (1)

Publication Number Publication Date
JP2006225961A true JP2006225961A (en) 2006-08-31

Family

ID=36987560

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005040448A Pending JP2006225961A (en) 2005-02-17 2005-02-17 Pier head structure and construction method

Country Status (1)

Country Link
JP (1) JP2006225961A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103194971A (en) * 2013-03-29 2013-07-10 中国水电建设集团铁路建设有限公司 Capping construction method for hollow pier
CN107299589A (en) * 2017-07-11 2017-10-27 中铁大桥局集团第二工程有限公司 A kind of precast beam supports the bed die system and its construction method of hollow pier pier cap
CN110820546A (en) * 2019-11-21 2020-02-21 深圳大学 Prefabricated connection structure of concrete columns with high seismic performance
CN111705632A (en) * 2020-06-01 2020-09-25 上海市城市建设设计研究总院(集团)有限公司 Prefabricated hollow piers with inner steel cross anchoring and construction method thereof
WO2020211175A1 (en) * 2019-04-18 2020-10-22 广州容联建筑科技有限公司 Fabricated reinforced concrete bridge pier and construction method therefor
CN111962383A (en) * 2020-07-29 2020-11-20 中铁第四勘察设计院集团有限公司 A safety protection device for ventilation holes of hollow piers
CN118601225A (en) * 2024-06-21 2024-09-06 中国五冶集团有限公司 A construction method for hollow thin-walled pier diaphragm

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103194971A (en) * 2013-03-29 2013-07-10 中国水电建设集团铁路建设有限公司 Capping construction method for hollow pier
CN103194971B (en) * 2013-03-29 2015-12-09 中国水电建设集团铁路建设有限公司 A kind of hollow pier binds construction method
CN107299589A (en) * 2017-07-11 2017-10-27 中铁大桥局集团第二工程有限公司 A kind of precast beam supports the bed die system and its construction method of hollow pier pier cap
WO2020211175A1 (en) * 2019-04-18 2020-10-22 广州容联建筑科技有限公司 Fabricated reinforced concrete bridge pier and construction method therefor
CN110820546A (en) * 2019-11-21 2020-02-21 深圳大学 Prefabricated connection structure of concrete columns with high seismic performance
CN111705632A (en) * 2020-06-01 2020-09-25 上海市城市建设设计研究总院(集团)有限公司 Prefabricated hollow piers with inner steel cross anchoring and construction method thereof
CN111962383A (en) * 2020-07-29 2020-11-20 中铁第四勘察设计院集团有限公司 A safety protection device for ventilation holes of hollow piers
CN118601225A (en) * 2024-06-21 2024-09-06 中国五冶集团有限公司 A construction method for hollow thin-walled pier diaphragm

Similar Documents

Publication Publication Date Title
KR100820299B1 (en) Construction method of cable-stayed bridge main tower PC using temporary bracket installation structure and temporary bracket
KR20180034807A (en) Outside heat-insulation wall method and outside heat-insulation wall thereby
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
JP2994222B2 (en) Construction method of cast-in-place slab of precast concrete girder and its formwork
KR100775359B1 (en) Formwork assembly and building construction method using same
JP2006225961A (en) Pier head structure and construction method
KR100635137B1 (en) A method of constructing a bridge slab and a lattice bar deck type PC plate
KR101084993B1 (en) Prestressed steel composite panel with prestressed non-stitched parts at both ends and its manufacturing method
KR20100117309A (en) Prestress concrete composite girder with prestress non-introducing portion provided at both ends, manufacturing method thereof, and built-up type slab bridge construction method using the same
KR101118508B1 (en) Construction method and structure of anchored slabstone on concrete
JP2002030615A (en) How to build tower structures
JP4560557B2 (en) Seismic reinforcement method for bridges
KR101170077B1 (en) Prestress concrete composite with prestress non-introducing portion selectively installed at upper and lower portions to which compression force is applied, manufacturing method thereof, slab structure and construction method using the same
JP2007217108A (en) Method of supporting tower crane
KR101151773B1 (en) Prestress steel composite girder with prestress non-introducing portions respectively provided at both ends thereof and manufacturing method thereof
KR200407092Y1 (en) PC panel support structure of cantilever part
JP2008121335A (en) Construction method of tower-like PC structure and tension system device
JP2980567B2 (en) How to replace the bearing device
WO2002092935A1 (en) Buried material unit, precast concrete panel and method of manufacturing the concrete panel, and slab and method of constructing the slab
JPH11222812A (en) How to change the height of the structure
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
KR100539829B1 (en) Method of pulling-up gang form for a flash board using a shaped steel
KR100650444B1 (en) Construction method of cantilevered part of bridge
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP6653214B2 (en) Parapet structure using precast concrete members