JP2001207457A - Drain box for shallow sump, and work method for underground structure using the drain box - Google Patents
Drain box for shallow sump, and work method for underground structure using the drain boxInfo
- Publication number
- JP2001207457A JP2001207457A JP2000014832A JP2000014832A JP2001207457A JP 2001207457 A JP2001207457 A JP 2001207457A JP 2000014832 A JP2000014832 A JP 2000014832A JP 2000014832 A JP2000014832 A JP 2000014832A JP 2001207457 A JP2001207457 A JP 2001207457A
- Authority
- JP
- Japan
- Prior art keywords
- water
- underground
- drain box
- box
- drainage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、地下構築物の施工
現場のかま場用排水ボックス及びこれを用いて行う地下
構築物の施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a drainage box for a kamaba at a construction site of an underground structure and a method of constructing an underground structure using the same.
【0002】[0002]
【従来の技術】周知の通り、地下室等の地下構築物の構
築には、地下水の排水対策が必須となっている。通常の
地下構築物の施工現場、例えば地下室構築の施工現場に
おいては、まず基盤となる地下スラブの構築が行われ
る。この場合にも地盤の掘削作業中にも排水を行うが、
鋼矢板で囲まれた内側の掘削が終了した後は、図5
(a)に示すように、地盤の底地面の鋼矢板61沿いに
排水溝62を設け、これで集められた地下水を排水ポン
プ63で地表に排水している。2. Description of the Related Art As is well known, drainage measures for groundwater are indispensable for construction of underground structures such as basements. In a construction site of a normal underground building, for example, a construction site of a basement building, an underground slab serving as a base is first constructed. In this case, drainage is performed during the excavation work of the ground,
After excavation of the inside surrounded by steel sheet piles is completed,
As shown in (a), a drain groove 62 is provided along a steel sheet pile 61 on the bottom surface of the ground, and the collected groundwater is drained to the ground surface by a drain pump 63.
【0003】地中から排水溝62に流れ込んだ地下水は
誘導水路64を通って要所に設けられたかま場65に集
められ、ここに設置された上記の排水ポンプ63によっ
て排水するようにしている。The groundwater flowing into the drain 62 from underground is collected at a pot 65 provided at a key point through a guide channel 64, and is drained by the drain pump 63 installed here. .
【0004】図5(b)に示すように、排水溝62及び
誘導水路64はこの上に地下スラブ60が構築されるた
め、配水管又は側溝に蓋をしたものを連続するように埋
設している。これらの排水溝62及び誘導水路64の随
所には地下水が流入する透孔を設けたものを採用するこ
とにより底地面に流れ込んだり、湧き出した地下水を集
められるようにしている。As shown in FIG. 5 (b), the underground slab 60 is constructed on the drainage channel 62 and the guide channel 64, so that the drainage pipe or the side channel is covered with a lid. I have. The drainage grooves 62 and the guiding water passages 64 are provided with through holes through which the groundwater flows, so that the groundwater can flow into the bottom ground or be collected.
【0005】また、鋼矢板61の内側には、鋼矢板のす
き間から流れ込む地下水を地下スラブや地下壁へ流れ込
まずに、排水溝62に集められるようにしたへちま板6
6を設けている。[0005] Also, inside the steel sheet pile 61, the groundwater flowing from the gap of the steel sheet pile is collected in the drainage groove 62 without flowing into the underground slab or the underground wall.
6 are provided.
【0006】地下構築物の基盤となる地下スラブ60の
大まかな施工要領は、底地面67の随所にかま場65及
びこのかま場と排水溝62を結ぶ誘導水路64を設け、
かま場の上方には排水ホースの通路を設けるための型枠
68を設けている。底地面67には図示していないが防
水シートを敷き、その上に割栗石層69を敷き、その上
に捨てコンクリート層70を形成し、さらにその上に強
度的にも防水的にも優れた性質を有する耐圧コンクリー
ト層71を形成している。[0006] The rough construction procedure of the underground slab 60 serving as the base of the underground structure is as follows. A kama place 65 and a guide channel 64 connecting the kama place and the drainage groove 62 are provided everywhere on the bottom ground 67.
A mold 68 for providing a passage for a drain hose is provided above the kneading place. A waterproof sheet (not shown) is laid on the bottom ground 67, a split stone layer 69 is laid thereon, and a discarded concrete layer 70 is formed thereon, and furthermore, it has excellent strength and waterproofness. A pressure-resistant concrete layer 71 having properties is formed.
【0007】地下スラブ60ができ上がったら、次に地
下壁72を設け、最後に型枠68を除去し、かま場65
及びその上にできた空胴部を埋め、耐圧コンクリート層
71に生コンクリートを補充して塞ぎ、最後にその表面
にモルタル層73を形成している。When the underground slab 60 is completed, the underground wall 72 is provided next, and the formwork 68 is finally removed.
Then, the cavity formed thereon is filled, and the pressure-resistant concrete layer 71 is replenished with fresh concrete and closed, and finally, a mortar layer 73 is formed on the surface.
【0008】なお、上記の施工中は絶えず地下水がかま
場65内に流れ込むために、かま場の上にできた空胴部
内にモルタルなどの止水材の充填終了まで排水作業を続
けていなければならない。したがって止水材の充填中に
も排水ポンプ63を運転させなければならず、したがっ
て水中ポンプを除去できないので、このポンプは結局埋
め殺しにしている。In addition, during the above construction, since the groundwater constantly flows into the kiln yard 65, the drainage work must be continued until the filling of the mortar or other waterproof material into the cavity formed on the kiln yard. No. Therefore, the drainage pump 63 must be operated even during the filling of the waterproof material, and the submersible pump cannot be removed.
【0009】[0009]
【発明が解決しようとする課題】上記従来例におけるか
ま場65は、誘導水路64と常に連通状態となっている
ため、地下スラブの耐圧コンクリート層71の形成後も
なお、かま場65から地下水が逆流して地下スラブ60
の上面へ溢れ出すおそれが生じる。したがって、型枠6
8を除去後も排水ポンプ63を運転していなければなら
ない。Since the kamaba 65 in the above conventional example is always in communication with the guide water channel 64, the groundwater is still discharged from the kamaba 65 even after the formation of the pressure-resistant concrete layer 71 of the underground slab. Backflow slab 60
There is a risk of overflowing to the upper surface of the device. Therefore, the form 6
The drain pump 63 must be operated even after removing 8.
【0010】このため、型枠除去後の空胴部内にモルタ
ルなどの止水材を充填するまでポンプを停止できないの
で、上記したように結局は高価なポンプを埋め殺しにし
ている。ポンプの埋め殺しによる経済的損失を少なくす
るために、性能の低い安価なポンプを採用すれば、施工
中の排水が不十分となり、コンクリートの品質低下を生
じさせるため、安価なポンプを設置することにも限度が
ある。For this reason, the pump cannot be stopped until the cavity after the removal of the mold is filled with a water-stopping material such as mortar. As a result, as described above, the expensive pump is eventually buried and killed. If an inexpensive pump with low performance is adopted to reduce the economic loss due to burial of the pump, drainage during construction will be insufficient and the quality of concrete will deteriorate, so install an inexpensive pump. Also has limitations.
【0011】また、かま場65の上方に設けられる型枠
68は、地下スラブ60との境界における防水が不十分
であると、かま場から逆流した地下水が打設中の捨てコ
ンクリート層70や耐圧コンクリート層71中へ進入し
て強度の劣る水増しコンクリートにしてしまうおそれが
ある。If the formwork 68 provided above the kiln yard 65 is not sufficiently waterproof at the boundary with the underground slab 60, the groundwater flowing backward from the kiln yard may cause the dumping concrete layer 70 and the pressure resistant There is a possibility that the concrete enters into the concrete layer 71 and becomes inflated concrete having low strength.
【0012】さらにまた、従来技術においては、かま場
65の空洞部及び型枠68を除去した後の空胴部に充填
する止水材の防水性が完全なものではない場合には、地
下スラブ上面へ地下水が上昇したりする問題もある。Furthermore, in the prior art, if the waterproofness of the waterproof material to be filled in the cavity after removing the cavity of the kiln yard 65 and the formwork 68 is not perfect, the underground slab is required. There is also a problem that groundwater rises to the upper surface.
【0013】そこで本発明の目的は、第1に地下スラブ
の構築中における打設中のコンクリート中への地下水の
進入を防止することによりコンクリートの品質低下を防
止すること。第2に高価な排水ポンプの回収を可能にす
ること。第3に地下構築物の施工完了後におけるかま場
から地下スラブ上面への地下水の流失を完全に防止する
ことにある。Accordingly, an object of the present invention is to firstly prevent deterioration of concrete quality by preventing groundwater from entering into concrete being poured during construction of an underground slab. Second, to enable the recovery of expensive drainage pumps. Thirdly, it is to completely prevent the flow of groundwater from the kamaba to the upper surface of the underground slab after the completion of the construction of the underground structure.
【0014】[0014]
【課題を解決するための手段】上記の目的を達成するた
めに、本発明は以下の手段を採用してある。第1に、地
下構築物の施工現場のかま場に以下の要素を備えた排水
ボックスを用いて完全な排水状態の下で地下構築物の施
工を可能としてある。ここで排水ボックスとは、従来技
術におけるかま場に設けられていた排水桝に代えて、か
ま場に埋設することにより地下水の排水を促進する箱体
であり、以下の要素を備えたものである。In order to achieve the above object, the present invention employs the following means. First, it is possible to construct an underground building under complete drainage using a drain box provided with the following elements at a kneading place at the construction site of the underground building. Here, the drainage box is a box that promotes drainage of groundwater by burying in the stove instead of the drainage basin provided in the stove in the prior art, and has the following elements. .
【0015】上記の排水ボックスは、水中ポンプを設置
可能な胴部、この胴部の上端部に形成してある筒部に排
水用の水中ポンプを出し入れ可能に設けてある上部開
口、地下水をかま場に誘導するために地下構築物の施工
現場に設けられる誘導水路と接続可能に上記の胴部の周
囲に設けてある複数の導水口、及びこれらの導水口を内
部から開閉可能な止水栓を備えたものである。なお、こ
の排水ボックスは予め工場で製造し、これを施工現場に
搬入して設置するようにしたものである。The above-mentioned drain box has a body in which a submersible pump can be installed, an upper opening in which a submersible pump for drainage can be taken in and out of a cylinder formed in the upper end of the body, and a base for catching groundwater. A plurality of water inlets provided around the trunk so as to be connectable to the guide water channel provided at the construction site of the underground building to guide the site, and a water stopcock that can open and close these water inlets from the inside It is provided. In addition, this drain box is manufactured in advance in a factory, and is carried into a construction site to be installed.
【0016】上記の排水ボックスを採用することによ
り、地下構築物の施工現場に設けられるかま場の設置が
容易かつかま場を埋め戻した後の地下水の漏水を完全に
防止することができる。また、水中ポンプを回収可能と
することにより施工コストの引き下げを図ることができ
る。By employing the above drain box, it is possible to easily set up a stove installed at the construction site of the underground building, and to completely prevent leakage of groundwater after the backfill of the stove. Further, the construction cost can be reduced by making the submersible pump recoverable.
【0017】第2に、上記の排水ボックスを用いた地下
構築物の施工方法は以下の各工程を採用することにより
施工中の排水が完全に行われるようにしてある。工場で
製造された排水ボックスを地下構築物の施工現場の随所
に設けられるかま場に埋設して上記開口の上方に排水ホ
ースを通すための型枠を設ける第1工程と、上記の導水
口と施工現場の地下水をかま場に誘導するために設けら
れる誘導水路とを接続するとともに、排水ボックスの胴
部内に水中ポンプを設置する第2工程と、排水ボックス
内に導入された地下水を水中ポンプで排水しながら地下
スラブの施工を進める第3工程と、地下スラブを構築し
た後に導水口を閉めて排水ボックス内への地下水の進入
を停止させ、排水ボックス内に収納されている水中ポン
プを回収し、型枠を除去する第4工程と、上記の型枠を
除去し、排水ボックスの内部に埋め戻し材を充填し、筒
部の上端部の周囲を第1の止水材で取り囲む第5工程と
を含んだものとしてある。Secondly, the method of constructing an underground structure using the above-described drainage box employs the following steps so that drainage during construction is completely performed. A first step of burying a drain box manufactured in a factory in a stove provided at various places in the construction site of the underground construction and providing a formwork for passing a drain hose above the opening; The second step of connecting the diversion channel provided to guide the groundwater at the site to the kiln site, and installing a submersible pump in the body of the drain box, and draining the groundwater introduced into the drain box with the submersible pump The third step of constructing the underground slab while constructing the underground slab, closing the water intake and stopping the inflow of groundwater into the drain box, collecting the submersible pump stored in the drain box, A fourth step of removing the formwork, a fifth step of removing the formwork, filling the inside of the drain box with a backfill material, and surrounding the periphery of the upper end of the cylindrical portion with the first water-stopping material. Including There as.
【0018】第3に、上記の施工方法において、第3工
程は型枠で囲まれている上部開口の周囲を第2の止水材
で囲む工程を含んだものとすることにより型枠の周囲か
らの地下水の漏水を完全に防止可能としてある。Third, in the above-mentioned construction method, the third step includes a step of surrounding the periphery of the upper opening surrounded by the mold with a second waterproof material. It is possible to completely prevent the leakage of groundwater.
【0019】第4に、上記の施工方法において、第5工
程における第1の止水材としては膨潤性を有するベント
ナイトを採用することにより、かま場からの地下水の漏
水を完全に防止可能としてある。Fourthly, in the above construction method, swelling bentonite is used as the first water-stopping material in the fifth step, so that leakage of groundwater from the kiln can be completely prevented. .
【0020】[0020]
【発明の実施の形態】次に本発明の実施の形態例につい
て図面を参照して説明する。初めに図1,2を参照して
排水ボックスについて説明する。Embodiments of the present invention will be described below with reference to the drawings. First, the drain box will be described with reference to FIGS.
【0021】排水ボックス1は、外観上は直方体の容器
状の胴部2と、この胴部の上部に設けられた直方体状の
筒部3とからなる。胴部2及び筒部3はいずれも鋼板を
溶接により結合して組み立てたいわゆる板金製品からな
り、筒部の内側の胴部の上部は切欠することにより上部
開口4としてある。胴部2内は水中ポンプ5を収納可能
な大きさとしてあり、上記した上部開口4はこのポンプ
を出し入れ可能な大きさとしてある。The drainage box 1 has a rectangular parallelepiped container-shaped body 2 and a rectangular parallelepiped tube 3 provided on the upper part of the body. Each of the body 2 and the tube 3 is made of a so-called sheet metal product assembled by joining steel plates by welding, and the upper part of the body inside the tube is cut out to form an upper opening 4. The inside of the body 2 is sized to accommodate the submersible pump 5, and the above-described upper opening 4 is sized to allow the pump to be taken in and out.
【0022】また、胴部2の各辺の上部にはそれぞれ円
形の導水口6が設けてある(2か所だけ図示)。導水口
6は後述の誘導水路から地下水を排水ボックス1内に導
水する入口孔であり、それぞれ胴部内で円筒状のスリー
ブ7の基部に取り囲まれている。スリーブ7は鋼管の基
部を胴部2の内側に溶接により固着してあり、先端部に
はおねじ部7aが刻んである。Further, a circular water inlet 6 is provided at each upper part of each side of the body 2 (only two water inlets are shown). The water inlet 6 is an inlet hole for guiding groundwater from the later-described guide water channel into the drain box 1, and is surrounded by the base of the cylindrical sleeve 7 in the body. The sleeve 7 has a base portion of a steel pipe fixed to the inside of the body portion 2 by welding, and a male thread portion 7a is cut at a tip end portion.
【0023】このスリーブ7の先端には、止水栓8を被
せることにより、導水口6からの地下水の進入を停止可
能としてある。止水栓8は鋼製の袋ナットからなり、開
口側に刻んであるめねじ部8aはスリーブのおねじ部7
aと螺合可能としてある。なお、この導水口6は、施工
現場の実状に応じて個数を定められる。無用な導水口の
設置はコストアップ及び漏水の原因となるので、実状に
対応した導水口数の決定を行うべきである。A stopcock 8 is placed on the tip of the sleeve 7 so that the inflow of groundwater from the water inlet 6 can be stopped. The water stopcock 8 is made of a steel cap nut, and the female thread 8a cut on the opening side is a male thread 7 of the sleeve.
a can be screwed. The number of the water introduction ports 6 is determined according to the actual condition of the construction site. Unnecessary installation of water inlets will increase costs and cause water leakage, so the number of water inlets should be determined according to the actual situation.
【0024】次に図3,4を参照して上記の排水ボック
スを採用した地下構築物の施工方法について地下室の施
工現場を例として説明する。Next, a method of constructing an underground building employing the above drain box will be described with reference to FIGS.
【0025】図3は、上記した排水ボックス1を用いた
地下室の施工の工程状態を示すものである。この図では
地下室の最下階に位置する地下スラブ11の構築を終了
した状態になっているが、以下の説明においては、地盤
の掘下げから地下スラブ及び地下壁の完成までの工程に
ついて地下水の排水を骨子にして順次説明する。FIG. 3 shows a process state of construction of a basement using the drain box 1 described above. In this figure, the construction of the underground slab 11 located on the lowest floor of the basement has been completed. However, in the following description, drainage of groundwater will be described for the processes from the digging of the ground to the completion of the underground slab and the underground wall. Will be sequentially described.
【0026】まず、従来技術と同じく地下構築物の建設
地の周囲に鋼矢板12を打ち込み、その内側を掘削す
る。次に底地面に鋼矢板の内側に沿って地下水の排水溝
13を設け、さらに随所に誘導水路14及びかま場15
となる凹部を設ける。First, a steel sheet pile 12 is driven around a construction site of an underground structure, as in the prior art, and the inside thereof is excavated. Next, a drainage groove 13 for groundwater is provided along the inside of the steel sheet pile on the bottom ground, and a guide channel 14 and a kamajo 15 are provided everywhere.
Is provided.
【0027】また、鋼矢板12の内側には、地下掘削面
からの漏水を鋼矢板面に沿って下方へ集めるようにする
へちま板16を設けるようにする。へちま板16は下部
が鋼矢板12と排水溝13との間に位置し、上部は後述
の耐圧コンクリート層の上面とほぼ一致する高さになる
ように設ける。Further, inside the steel sheet pile 12, there is provided a stitch plate 16 for collecting water leaking from an underground excavation surface downward along the steel sheet pile surface. The stitch plate 16 is provided so that the lower part is located between the steel sheet pile 12 and the drain groove 13 and the upper part has a height substantially coincident with the upper surface of a pressure-resistant concrete layer described later.
【0028】かま場15となる凹部には、上記した排水
ボックス1を導水口6が誘導水路14と接続可能な深さ
になるように埋設する。なおこの排水路13及び誘導水
路14には、随所に地下水の進入口が設けてあり、地中
の地下水を集めて、排水ボックス1内へ導入可能として
ある。The above-mentioned drain box 1 is buried in the concave part serving as the pot place 15 so that the water inlet 6 can be connected to the guide channel 14. The drainage channel 13 and the guide channel 14 are provided with groundwater inlets everywhere, so that groundwater underground can be collected and introduced into the drainage box 1.
【0029】次に排水ボックス1の筒部3の周囲にベン
トナイトシートからなる止水部材17を貼付し、さらに
その周囲を取り囲むように型枠18を設ける(第1工
程)。止水部材の存在は、筒部3の外周部と型枠18と
の間からの漏水を防止する役目を果すものである。型枠
18は排水ポンプ5を出し入れ可能にするとともに、排
水ホース9を通す役割を果すものである。型枠18の設
置は、後述の割栗石層19の敷設後であってもよい。止
水部材17は排水ボックス1と型枠18との間からの漏
水を防止する働きをする。型枠18の上端は後述の耐圧
コンクリート層の上面よりも上に位置する高さとなるよ
うに設置する。Next, a water stop member 17 made of a bentonite sheet is attached to the periphery of the cylindrical portion 3 of the drain box 1, and a mold 18 is provided so as to surround the periphery (first step). The presence of the water blocking member serves to prevent water leakage from between the outer peripheral portion of the cylindrical portion 3 and the mold 18. The formwork 18 allows the drainage pump 5 to be taken in and out, and plays a role in passing the drainage hose 9. The installation of the formwork 18 may be performed after the laying of the split stone layer 19 described later. The water blocking member 17 functions to prevent water leakage from between the drain box 1 and the mold 18. The upper end of the formwork 18 is installed at a height higher than the upper surface of a pressure-resistant concrete layer described later.
【0030】次に、排水ボックス1内に水中ポンプ5を
設置し、止水栓8を取り外して導水口6を開けて地下水
を排水ボックス内へ集める。集められた地下水はホース
9を介して地上へ排水可能な状態とする(第2工程)。
なお、水中ポンプ5はベース5a上に載置したストレー
ナ5bを介して地下水を吸い込み可能となるように設け
る。Next, the submersible pump 5 is installed in the drain box 1, the water stopcock 8 is removed, the water inlet 6 is opened, and groundwater is collected in the drain box. The collected groundwater is drained to the ground via the hose 9 (second step).
The submersible pump 5 is provided so that groundwater can be sucked through a strainer 5b mounted on a base 5a.
【0031】次に誘導水路14を含む底地面上に防水シ
ート(図示略)を敷き、その上に中粒の玉石を敷き詰め
てなる割栗石層19を形成する。この割栗石層19の上
面は排水ボックス1の胴部2の上端とほぼ一致する高さ
とする。Next, a waterproof sheet (not shown) is laid on the bottom ground including the guide channel 14, and a split stone layer 19 is formed by laying medium-sized cobble stones thereon. The upper surface of the split chestnut stone layer 19 has a height substantially coincident with the upper end of the body 2 of the drain box 1.
【0032】次に排水ボックス1の胴部2の上面と筒部
3の中間位置とを結ぶ型枠18の周囲に、ベントナイト
粉末をほぼ三角形断面状に塗り付けて止水部20を形成
する。この止水部20はモルタルなどで形成してもよ
い。Next, bentonite powder is applied in a substantially triangular cross section around the formwork 18 connecting the upper surface of the body portion 2 of the drain box 1 and the intermediate position of the cylindrical portion 3 to form the water stopping portion 20. The water stopping portion 20 may be formed of mortar or the like.
【0033】次に割栗石層19の上面に防水シートを敷
き、その上に排水ボックス1の上端部とほぼ一致する高
さ(約160mm)まで捨てコンクリート層21を形成
する。捨てコンクリート層21が固まったら次にへちま
板16の内側に沿ってL字形断面に形成してなる防水板
22を配置し、さらにその内側に防水シート23を配置
する。防水シート23は、止水板22が設けてある範囲
ではこれに二重に重なり、へちま板16の上方の範囲で
は鋼矢板12と平行になるように設ける。Next, a waterproof sheet is laid on the upper surface of the split-stone layer 19, and a concrete layer 21 is formed on the waterproof sheet to a height (about 160 mm) substantially coincident with the upper end of the drain box 1. When the discarded concrete layer 21 has hardened, a waterproof plate 22 having an L-shaped cross section is arranged along the inside of the cling plate 16 and a waterproof sheet 23 is further arranged inside the waterproof plate 22. The waterproof sheet 23 is provided so as to double overlap with the water stop plate 22 in a range where the water stop plate 22 is provided, and to be parallel to the steel sheet pile 12 in a range above the clog plate 16.
【0034】こうして、捨てコンクリート層21の上方
が防水シート23によって覆われた状態としたら、次に
その上に耐圧コンクリート層24を打設する。耐圧コン
クリート層24は、厚さをほぼ300mmとし、型枠1
8の部分を除いて地下の底地面全体に打設する(第3工
程)。When the upper part of the discarded concrete layer 21 is covered with the waterproof sheet 23 in this way, a pressure-resistant concrete layer 24 is then cast thereon. The pressure-resistant concrete layer 24 has a thickness of approximately 300 mm,
Except for the portion 8, it is cast on the entire underground floor (third step).
【0035】ここで鋼矢板12に沿った地下スラブ11
上に地下壁25を構築する。地下壁25は鋼矢板12の
内側に上記の防水シート23を介在させて地下水が打設
中のコンクリート中に流れ込まない状態にして行われ
る。The underground slab 11 along the steel sheet pile 12
An underground wall 25 is built on top. The underground wall 25 is formed by interposing the waterproof sheet 23 inside the steel sheet pile 12 so that groundwater does not flow into the concrete being poured.
【0036】次に水中ポンプ5による排水を行っている
状態で地下スラブ11の上面側から排水ボックス1内に
手を入れて、すべてのスリーブ7にキャップ(止水栓)
8を被せて導水口6を閉め、誘導水路14からの地下水
の進入を停止させる。この後間もなく排水ボックス1内
に残っている地下水はすべて水中ポンプにより排水され
る。次に水中ポンプ5、ストレーナ5b及びホース9を
引き上げて回収するとともに型枠18を除去する(第4
工程)。Next, while draining by the submersible pump 5, a hand is put into the drain box 1 from the upper surface side of the underground slab 11, and caps (water stopcocks) are put on all the sleeves 7.
8, the water inlet 6 is closed, and the inflow of groundwater from the guide channel 14 is stopped. Shortly thereafter, all the groundwater remaining in the drain box 1 is drained by the submersible pump. Next, the submersible pump 5, the strainer 5b and the hose 9 are pulled up and collected, and the formwork 18 is removed (fourth embodiment).
Process).
【0037】次に図4に示すように、空になった排水ボ
ックス1内に土砂やがれきなどの埋め戻し材26を充填
して突き固める。この埋め戻し材26の充填量は、筒部
2の上端部近傍までとする。次に筒部3の内部に形成さ
れた空胴部内にベントナイト粉末からなる止水材27を
入れて、筒部3の周囲や上方を取り囲み、排水ボックス
1からの地下水の漏水防止処理を行う(第5工程)。Next, as shown in FIG. 4, the emptied drain box 1 is filled with a backfill material 26 such as earth and sand or debris and squeezed. The filling amount of the backfill material 26 is set up to the vicinity of the upper end of the tubular portion 2. Next, a water-blocking material 27 made of bentonite powder is put into a cavity formed inside the cylindrical portion 3 to surround the periphery and the upper portion of the cylindrical portion 3 and to perform a process for preventing groundwater from leaking from the drain box 1 ( Fifth step).
【0038】次に水中ポンプの上方に取り残された空胴
部に生コンクリートを詰めて固化させることにより充填
コンクリート部28を設ける。なお、耐圧コンクリート
層24、充填コンクリート部28の各上面には、表面モ
ルタル層29を形成するため、排水ボックス1の上方に
取り残された空胴部に充填した充填コンクリート部28
との表面境界は地下スラブ11の表面には表われない。Next, a filled concrete portion 28 is provided by filling and solidifying ready-mixed concrete in the cavity left above the submersible pump. In order to form a surface mortar layer 29 on each of the upper surfaces of the pressure-resistant concrete layer 24 and the filled concrete portion 28, the filled concrete portion 28 filled in the cavity left over the drain box 1 is formed.
Does not appear on the surface of the underground slab 11.
【0039】以上説明した施工法は一例に過ぎず、実際
の施工例は多数存在するが、本発明は、第1に排水ボッ
クス1をかま場15に据え付けることにより排水構造の
設置が容易化すること。第2に型枠を除去した後に止水
栓8を閉めることにより排水ボックスへの地下水の流入
を停止可能であること。第3に型枠除去後に水中ポンプ
を回収可能であること。第4に水中ポンプ回収後のかま
場ボックス1内に埋め戻し材を充填後に、筒部の開口4
の周囲にベントナイトを配置することにより耐圧コンク
リート層のすき間から地下水の漏水を防止可能としてあ
ることに特徴を有するものである。Although the construction method described above is merely an example, and there are many actual construction examples, the present invention facilitates the installation of the drainage structure by first installing the drainage box 1 on the stove 15. thing. Second, the inflow of groundwater into the drain box can be stopped by closing the stop cock 8 after removing the mold. Third, the submersible pump can be recovered after removing the mold. Fourth, after filling the backfill material in the kamaba box 1 after the submersible pump is recovered, the opening 4
Is characterized in that groundwater can be prevented from leaking from the gap of the pressure-resistant concrete layer by arranging bentonite around the periphery.
【0040】この例では排水ボックスの形状を直方体と
してあるが、形状はこれに拘わるものではなく、材質も
鋼板の他、合成樹脂その他の物質で構成することも可能
である。また、止水栓はキャップ状のものとして説明し
てあるが、これを棒状とし、止水栓におねじを刻み、ス
リーブの開口部側にめねじを刻むようにしたものとして
もよい。In this example, the shape of the drain box is a rectangular parallelepiped. However, the shape is not limited to this, and the material can be made of a synthetic resin or other material in addition to a steel plate. Although the stopcock is described as a cap-shaped stopper, the stopper may be formed in a rod shape, a screw may be cut in the stopcock, and a female screw may be cut in the opening side of the sleeve.
【0041】また、型枠の設置と割栗石層及び捨てコン
クリート層の形成との工程の前後関係は上記の説明とは
逆になっても本発明の効果に影響を及ぼさない。The effect of the present invention is not affected even if the order of the steps of the installation of the formwork and the formation of the split stone layer and the discarded concrete layer is reversed from the above description.
【0042】[0042]
【発明の効果】本発明における排水ボックスを採用すれ
ば、地下構築物の施工現場におけるかま場の設置が容易
となり、しかも地下水の漏水のない施工が可能となる。
また、排水ボックスの導水口を開閉自在としてあるの
で、所定の施工時点でこれを閉じることにより排水ボッ
クス内の水を排除状態とすることができる。したがって
導水口を閉じた後に水中ポンプの回収が可能となる。こ
れとともに、ポンプ回収後に埋め戻し材を充填しても、
下から水位が上昇してくることもなくなるので余裕をも
ってかま場の埋め戻し作業をすることができる。The use of the drainage box according to the present invention facilitates installation of a kiln at a construction site of an underground structure, and also enables construction without leakage of groundwater.
Further, since the water inlet of the drain box is openable and closable, the water in the drain box can be removed by closing it at a predetermined construction time. Therefore, it is possible to recover the submersible pump after closing the water inlet. Along with this, even if backfill material is filled after pump recovery,
Since the water level does not rise from below, it is possible to backfill the kamaba with plenty of time.
【0043】また、施工時に排水ボックスの筒部の周囲
に止水部を形成することにより型枠の周囲からの地下水
の漏水を防止可能となる。Further, by forming a water stop portion around the cylindrical portion of the drain box at the time of construction, it is possible to prevent groundwater from leaking from around the formwork.
【0044】さらに、型枠除去後に開口部周辺にベント
ナイト等の止水材を配置すれば、かま場ボックスの内外
からの地下水の上昇を完全に防止することが可能とな
る。Furthermore, if a water-blocking material such as bentonite is arranged around the opening after removing the formwork, it is possible to completely prevent the rise of groundwater from inside and outside of the kamaba box.
【0045】なお、本発明を採用して地下構築物の施工
を行えば、防水対策が完全であるため、コンクリート打
設時におけるコンクリート中の水増し現象がなくなるの
で、品質の高いコンクリートからなる地下構築物が得ら
れる。If the present invention is applied to the construction of an underground building, since the waterproofing measures are complete, the phenomenon of water inflation in the concrete at the time of concrete casting is eliminated, so that an underground building made of high-quality concrete can be obtained. can get.
【図1】排水ボックスの構成例を示す断面図である。FIG. 1 is a cross-sectional view illustrating a configuration example of a drain box.
【図2】排水ボックスの外観の例を示す斜視図である。FIG. 2 is a perspective view showing an example of the appearance of a drain box.
【図3】排水ボックスを採用した地下構築物の施工例を
示す断面図である。FIG. 3 is a cross-sectional view showing a construction example of an underground building employing a drain box.
【図4】施工終了後の状態を示す断面図である。FIG. 4 is a cross-sectional view showing a state after the completion of construction.
【図5】従来例を示すもので、(a)は平面図、(b)
は(a)のB−B線断面図である。5A and 5B show a conventional example, in which FIG. 5A is a plan view and FIG.
FIG. 3 is a sectional view taken along line BB of FIG.
1 排水ボックス 2 胴部 3 筒部 4 上部開口 5 水中ポンプ 6 導水口 8 止水栓 11 地下スラブ 12 鋼矢板 13 排水溝 14 誘導水路 15 かま場 18 型枠 20 止水部 26 埋め戻し材 27 止水材(ベントナイト) DESCRIPTION OF SYMBOLS 1 Drainage box 2 Body part 3 Tube part 4 Upper opening 5 Submersible pump 6 Water inlet 8 Water stopcock 11 Underground slab 12 Steel sheet pile 13 Drainage groove 14 Guide channel 15 Kamajo 18 Formwork 20 Water stop part 26 Backfill material 27 Stop Water material (bentonite)
Claims (4)
の上端部に形成してある筒部、この筒部に上記水中ポン
プを出し入れ可能に設けてある上部開口、上記胴部の周
囲に設けてある複数の導水口、これらの導水口を内部か
ら開閉可能にする止水栓を備えていることを特徴とする
かま場用排水ボックス。1. A torso capable of accommodating a submersible pump, a tubular portion formed at an upper end of the torso, an upper opening through which the submersible pump can be inserted and removed, and a periphery of the torso. Characterized by a plurality of water inlets provided in the car, and a water stopcock for opening and closing these water inlets from the inside.
築物の施工現場の要所に設けられたかま場に埋設し、上
記筒部の周囲に型枠を設ける第1工程と、上記胴部内に
上記水中ポンプを設置し、上記導水口を開ける第2工程
と、上記排水ボックス内に導入された地下水を上記水中
ポンプで排水しながら地下スラブ構築の施工を進める第
3工程と、上記地下スラブ構築後に上記導水口を閉め、
上記水中ポンプを上記排水ボックス内から回収するとと
もに上記型枠を除去する第4工程と、上記排水ボックス
内に埋め戻し材を充填し、この埋め戻し材の上面及び上
記筒部の上端部の周囲を止水材で取り囲んでなる止水部
を形成する第5工程とを含むことを特徴とする地下構築
物の施工方法。2. A first step of burying the drainage box according to claim 1 in a stove provided at a key point of a construction site of an underground building, and providing a formwork around the cylindrical portion; A second step of installing the submersible pump in the water tank and opening the water inlet; a third step of constructing an underground slab while draining the underground water introduced into the drain box with the submersible pump; After the construction, close the water inlet,
A fourth step of recovering the submersible pump from the drain box and removing the formwork, filling the drain box with a backfill material, and surrounding an upper surface of the backfill material and an upper end of the cylindrical portion. And a fifth step of forming a water-stopping section surrounding the water-blocking material with a water-stopping material.
胴部の上端部かつ上記型枠の周囲を止水材で取り囲む工
程を含んでいることを特徴とする地下構築物の施工方
法。3. The method according to claim 2, wherein the third step includes a step of surrounding the upper end of the trunk and the periphery of the form with a waterproof material.
る止水材はベントナイトであることを特徴とする地下構
築物の施工方法。4. The method according to claim 2, wherein the water-blocking material used in the fifth step is bentonite.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000014832A JP3451050B2 (en) | 2000-01-24 | 2000-01-24 | Construction method for underground structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000014832A JP3451050B2 (en) | 2000-01-24 | 2000-01-24 | Construction method for underground structures |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003117933A Division JP3756889B2 (en) | 2003-04-23 | 2003-04-23 | Kamaba drainage box |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001207457A true JP2001207457A (en) | 2001-08-03 |
JP3451050B2 JP3451050B2 (en) | 2003-09-29 |
Family
ID=18542226
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000014832A Expired - Fee Related JP3451050B2 (en) | 2000-01-24 | 2000-01-24 | Construction method for underground structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3451050B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112779931A (en) * | 2021-01-26 | 2021-05-11 | 中国五冶集团有限公司 | Basement construction joint waterproof device, waterproof structure and waterproof method |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104131575B (en) * | 2014-04-11 | 2016-11-23 | 中国水利水电第十一工程局有限公司 | A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation |
CN105275020B (en) * | 2014-07-07 | 2017-12-19 | 中石化洛阳工程有限公司 | A kind of underground piping antiseep facility |
CN110593284B (en) * | 2019-09-23 | 2021-09-10 | 中交第二航务工程局有限公司 | Seepage prevention method for construction of underwater bearing platform in solution hole and solution gap development area |
-
2000
- 2000-01-24 JP JP2000014832A patent/JP3451050B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112779931A (en) * | 2021-01-26 | 2021-05-11 | 中国五冶集团有限公司 | Basement construction joint waterproof device, waterproof structure and waterproof method |
Also Published As
Publication number | Publication date |
---|---|
JP3451050B2 (en) | 2003-09-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101250879B (en) | Method for processing bottom solum trickleing water of deep building pit | |
CN102797266B (en) | Well sealing waterproof construction method for dewatering well | |
CN101936010B (en) | Construction method of dewatering well in underground concrete structure | |
CN107326918B (en) | Hidden type plugging impervious water collecting well penetrating through raft plates and construction process thereof | |
CN109736340B (en) | Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab | |
KR100734047B1 (en) | Sump structure and its installation process | |
JP3756889B2 (en) | Kamaba drainage box | |
JP2001207457A (en) | Drain box for shallow sump, and work method for underground structure using the drain box | |
KR100422216B1 (en) | The method of construction prevening a waterflow of cassion basis for a bridge | |
CN108625404B (en) | Basement waterproof leaking stoppage method based on grouting and internal and external dredging combination | |
KR20050017815A (en) | Construction and design method about center wall of two arch tunnel excavation method | |
JP4809728B2 (en) | manhole | |
CN208441115U (en) | A kind of diaphram wall piping plugging structure | |
JP2001248396A (en) | Groundwater collection method | |
JPS6160948B2 (en) | ||
KR200255650Y1 (en) | Sealing device for ground concrete work | |
CN110792092A (en) | Foundation pit dewatering structure and construction method thereof | |
JP4589084B2 (en) | A retaining wall with a built-in water pipe composed of a plurality of water passages, and a method for ensuring the flow of groundwater using the retaining wall | |
CN213836755U (en) | Permanent row pile type underground road waterproof wall connecting structure | |
CN210712890U (en) | Precipitation structure of sump | |
CN114908808A (en) | Leakage stopping device and method for leakage of deep water cofferdam bottom sealing concrete | |
JPH0465932B2 (en) | ||
JP4809741B2 (en) | manhole | |
JP2634442B2 (en) | Underground wall | |
JPS6334275B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |