EP3074574B1 - Method for restoring a structure having a crack by following a curve representing the separation of the edges of the crack - Google Patents
Method for restoring a structure having a crack by following a curve representing the separation of the edges of the crack Download PDFInfo
- Publication number
- EP3074574B1 EP3074574B1 EP14805203.8A EP14805203A EP3074574B1 EP 3074574 B1 EP3074574 B1 EP 3074574B1 EP 14805203 A EP14805203 A EP 14805203A EP 3074574 B1 EP3074574 B1 EP 3074574B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- crack
- injection
- curve
- edges
- sensor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0203—Arrangements for filling cracks or cavities in building constructions
- E04G23/0211—Arrangements for filling cracks or cavities in building constructions using injection
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/10—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0203—Arrangements for filling cracks or cavities in building constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0229—Increasing or restoring the load-bearing capacity of building construction elements of foundations or foundation walls
Definitions
- the present invention relates to a method of rehabilitation of a structure resting on a collapsed soil having at least one crack resulting from the subsidence of the soil.
- the invention relates to a method for rehabilitating a structure resting on a floor, by treating its foundation soil by injecting an expansive substance to close said crack.
- a crack appearing on a structure can be a sign of a break in the materials constituting the structure and occurs when the constraints generated in the work concerned, exceed the limits of rupture for which it was conceived.
- Part A of the structure follows the settlement of the soil on which the structure of the structure rests, said ground floor and which will be defined in detail later.
- other parts of building B (often placed above the first) remain temporarily immobile in an unstable equilibrium, the two parts A, B being separated by cracks. This state of unstable equilibrium creates stresses that are often harmful for the durability of the structure.
- the diffusion is at an angle to the vertical, the stress sp being uniform within the diffusion area on a given horizontal plane.
- ⁇ is a value between 30 ° and 45 °.
- the figure 9 schematically shows the diffusion of ⁇ z with the depth from the previous equation.
- the processes for rehabilitating a structure with a crack do not therefore include the implementation of such a deep consolidation method.
- the traditional techniques of rehabilitation of a structure presenting a crack consider, after comforting the ground in depth, filling of cracks with opening, pinning, then filling with a mortar without shrinkage.
- the object of the present invention is to improve the method and the system for the rehabilitation of works disclosed in the document EP1914350A1 .
- the invention proposes a method of comforting the superficial ground surface of a structure, with a quality of finish not yet achieved, the deep soil having been previously consolidated by an appropriate technique.
- the object of the present invention is therefore to provide a method for the rehabilitation of a damaged structure, including a structure having at least one crack due to the subsidence of its ground, allowing both to improve the properties of the foundation soil of the structure and to neutralize the parasitic stresses caused by soil compaction, appeared consecutively on the structure.
- This objective is achieved with a method of rehabilitating a collapsed structure having at least one crack resulting from subsidence, wherein a reinforcement substance is injected into the soil of the structure (Z1) at the right of said crack in a primary drilling hole, the method being characterized in that it further comprises, simultaneously with the injection, the acquisition of a revealing curve of the approaching of the edges of the crack, the injection being stopped as soon as a sudden slope decrease in absolute value is detected on the curve.
- a soil reinforcement substance when injected into the soil or at the interface between the soil and the foundation of the structure, in a quantity and / or at a sufficient pressure, it exerts, on the basis of the cracked structure, an upward thrust that tends to close the crack of the structure, that is to say to bring one to the other, the lower and upper edges of the crack.
- a sensor of a revealing parameter of the approximation between the edges of the crack is placed between two points located on the facade of the work, on the part and other of the crack.
- the sensor is connected to a reading device, and, simultaneously with the injection, the curve is read on the reading device.
- the sensor may for example be a displacement sensor adapted to measure the approximation between the edges of the crack.
- the senor makes it possible to detect infinitesimal displacements of the order of 10 microns.
- the sensor may also be a pressure sensor adapted to measure between the edges of the crack a pressure increase revealing the approximation between said edges.
- the pressure variations are measured with a high degree of accuracy, for example of the order of 0.005 bar.
- the method also allows the densification and the improvement of the surface soil lift in the Z1 layer by injection of the reinforcing substance, which increases the bearing capacity of the soil (in a soil of insufficient lift) and / or decreases its permeability in the case of soil sensitive to water changes. In the same way, it makes it possible to fill the empty spaces between the ground and the foundation of the structure.
- the slope of the curve is evaluated during a first interval ⁇ T S and then during a second time interval ⁇ T D , ⁇ T S and ⁇ T D being between 10 seconds and 2 minutes, and preferably of the order of 1 minute, and even more preferably, 15 or 30 seconds.
- a sudden decrease in slope is detected when the slope in absolute value on the second interval is more than 30%, preferably more than 50% lower than the slope in absolute value on the first interval.
- the method On a cracked structure having a plurality of cracks, the method will generally be applied to those among the cracks that are most representative of the state of the structure in relation to a soil compaction problem.
- a crack when it is identified as very extensive, for example when it has a length greater than 1 meter, it will be treated by multiple injections, or by starting the injection at the level of the largest gauge at within the crack, by a first injection point I, then by successive injection points J, J ', K, K' alternately on either side of this first injection point I, either by starting injection by a first injection point K located at a first end of the crack considered, continuing the injection at a second injection point K 'located at a second end of this crack, then by successive points J , I alternately on either side of the center of the crack to close it gradually from its ends.
- the first borehole is located in a plane substantially aligned with the sensor and perpendicular to the facade.
- the injected reinforcement substance is an expansive substance, especially polyurethane foam.
- the causes of this phenomenon can be multiple, either that the soil has been more compressible in some places than others, or that the loads applied to the structure have been unequally distributed, or still due to soil moisture variations. such as orientation (the south and west facing flanks are more desiccated than the north and east flanks), the presence of tree roots absorbing water from the soil, insufficient drainage, network leaks, etc ...
- FIG. 1 there is shown a flag 10 whose seat has undergone such a differential settlement. There is a significant settlement of the ground and, in fact, a subsidence of a lower portion of the flag 10, on its right side while an upper portion B remains at the same level as before the settlement.
- active cracks are located above stabilized cracks.
- a fissure When a fissure is identified as very large, for example when it is more than 1 meter in length, it will be treated with multiple injections, starting with the injection at the level of the largest of the crack, by a first injection point I, then by successive injection points J, J ', K, K' alternately on either side of this first injection point I, or by starting injection by a first injection point K located at a first end of the crack in question, by continuing the injection at a second injection point K 'situated at a second end of this crack, then by successive points J, I alternately on either side of the center of the crack to close it gradually from its ends.
- the crack 22 is the most representative of the state of the structure.
- a prerequisite is that the soil in depth, that is to say located at a depth greater than 2B, B being the width of the sole supporting the structure, the closest to the crack, has never undergone any constraints having caused a loss of lift, because it has been redensified or consolidated by appropriate techniques.
- a second condition is the improvement and homogenization of the properties of the soil S vis-à-vis the applied loads and / or water variations, in order to avoid the subsequent occurrence of new problems of differential settlements.
- This second condition can be fulfilled by the injection into the soil S of a reinforcing substance, in particular an expansive substance, making it possible to densify the soil and thus to improve both its lift and its permeability.
- a third condition is the neutralization of parasitic stresses generated in the structure due to differential settlements and breaks in the structure. Indeed, a part of the superstructure could for example remain in overhang.
- a stress sensor 30 is placed on the front of the structure, on either side of the crack 12, preferably perpendicular to the mean direction of the crack.
- the stress sensor 30 is for example a pressure detector, connected respectively to two fixed points Q3, Q4 located on either side of the crack 22.
- An increase in pressure measured by the sensor 30 means that the two edges 24, 26 of the crack 22 tend to get closer.
- the pressure sensor 30 is connected to a reading device 40, here a computer, on which a first operator can read the curve illustrating the pressure values measured over time using the sensor 30.
- a borehole 50 as wide as an injection lance is drilled in line with the crack 22, in a slightly oblique trajectory directed towards the inside of the building 10 towards the soil layer Z1.
- This first borehole 50 is generally located in a plane P perpendicular to the facade 12 of the structure 10 and comprising the pressure sensor 30 (see FIG. figure 1 ) and is generally within the maximum gap of the crack (often coinciding with the center of the crack).
- An injection lance 51 is inserted in the borehole 50: the lance 51 is positioned so that its lower end is placed in the layer Z1 under the foundation of the flag 10. This lance 51 has at its penetrating end the seat floor, successive orifices in order to be able to spread the expansive substance both in the Z1 bed layer and in the possible voids under foundation existing between the sole and the Z1 layer.
- the reinforcing substance is injected at the interface between the foundation plate 14 and the floor S to fill the voids and to ensure that the charges are well transmitted between these two elements.
- this step is called "keying injection”.
- the expansive substance is injected into the base layer itself Z1, called consolidation injection.
- the consolidation injection is parameterized (volume of substance injected, injection pressure, coefficient of expansion of the reinforcing substance if necessary, phasing of injections, etc.) so that the ground around the injection point is reinforced, and an upward thrust is exerted on the collapsed base A of the work to the right of the crack to be treated.
- the reinforcing substance is a polyurethane foam.
- a polyurethane foam is, for example, the result of a mixture of polyol and MDI Isocyanate.
- these two products are stored in a truck, in separate tanks. Both components are routed through pipes to the spray gun of the spray lance.
- the combination of the two products mixed under pressure with air injected by a two-component pump forms by chemical reactions an expansive foam which solidifies and acquires high mechanical characteristics.
- the curve of the figure 6 gives the measured pressure values (on the ordinates) as a function of time (on the abscissa).
- the curve can be recorded indifferently by a sampling system over time (measurements at regular intervals) or continuously.
- T A 0 (point A on the curve) corresponds to the injection of the mixture of polyol and MDI Isocyanate into the depth of the seat ground with the aid of the injection lance 51. This moment, a certain time is necessary for the reaction of the two components.
- the preliminary phase during which the foam has not begun to expand and the ground has not yet been moved, is noted PH1 on the curve.
- the injection does not involve any modification of the stresses exerted on the structure 10, which results in a first plateau PH1 on the raised curve.
- the moment T B corresponds to the beginning of the movements of the collapsed part A of the structure due to the treatment of the seat floor Z1.
- the foam propagates essentially laterally from the end of the injection lance 51.
- the grains of the ground reorganize with each other.
- the soil becomes denser under the effect of the lateral thrust of the foam, but the level of the ground seat remains for the moment unchanged. Again, no influence on the structure is measured.
- the pressure curve remains flat PH2.
- the seat floor once compacted (point T C of the curve), offers increased resistance to the propagation of the foam in the horizontal direction.
- the soil resistance in the vertical direction eventually becomes lower than its lateral resistance.
- the foam then tends to propagate upward, generating, on the base of the work 10, a thrust force directed upwards.
- This thrust force naturally tends to raise the collapsed portion of the structure 10, gradually bringing the lower edge 26 of the crack 22 closer to its upper edge 24.
- the pressure measured by the sensor then increases very rapidly, as illustrated on the curve by the phase noted PH3.
- the point T C therefore corresponds to the beginning of the lifting of part A.
- the increase in pressure is slower. Indeed, at a time T D (point D on the curve), the curve shows a slope break, which corresponds to the beginning of contact between the lower and upper edges of the crack. The injection is stopped as soon as the slope break is detected. The injector gun is cut.
- an experienced operator can stop the injection as soon as he detects a sharp break in the slope of the curve with the naked eye, the slope decreasing in absolute value.
- the operator generally waits for this modification of the curve to be confirmed over a predetermined time interval, of the order of ten seconds, for example between 15 and 30 seconds, after the breaking point.
- slope D generally less than 1 minute.
- the operator will stop the injection when at a time T, he has detected a decrease in the slope of at least 30%, preferably 50%, over a time interval of less than 1 minute. This detection can also be performed automatically, using appropriate software.
- the injection is stopped at a time Ts (corresponding to a point Gs of the curve) where the slope on a first interval ⁇ T S , is more than 30% lower than the slope of the curve on a previous time interval ⁇ T D , ⁇ T S and ⁇ T D being less than or equal to 1 minute, for example 15 or 30 seconds.
- the Figure 4B illustrates the crack 22 once the consolidation injection is complete.
- the low point Q1 of the work has returned to its original level Q1 '.
- the other injection points J, J ', K, K', adjacent to the first injection point I are according to a first embodiment, made in drill holes made alternately to the left and to the right of the primary borehole. 50, substantially following the facade 12 of the building 10.
- the drill holes are spaced from the first borehole 50 and between them a predetermined constant distance d, for example equal to one meter.
- No injection shall be made more than 1 m away from the two points which are respectively at the base of the two ends of a crack.
- the senor used may be a displacement detector (elongation), in particular an optical fiber detector allowing detection of displacements to within 10 microns.
- the stress curve obtained with such a displacement sensor is illustrated on the figure 7 .
- She is the mirror of the figure 6 previously described.
- the elongation measured by a sensor respectively fixed at a point of the lower part of the crack and a point of the upper part of the crack actually changes inversely with respect to the pressure measured between the edges of the crack: When the pressure increases, elongation decreases and vice versa.
- Phases PH1 to PH5 are represented on the curve of the figure 7 . All of the comments made previously regarding the figure 6 apply mutatis mutandis to it.
- the injection into the first borehole is stopped as soon as the abrupt decrease in slope in absolute value (point D) is identified.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Agronomy & Crop Science (AREA)
- Soil Sciences (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
La présente invention concerne un procédé de réhabilitation d'un ouvrage reposant sur un sol affaissé présentant au moins une fissure résultant de l'affaissement du sol.The present invention relates to a method of rehabilitation of a structure resting on a collapsed soil having at least one crack resulting from the subsidence of the soil.
Plus particulièrement, l'invention concerne un procédé de réhabilitation d'un ouvrage reposant sur un sol, par traitement de son sol d'assise par injection d'une substance expansive pour refermer ladite fissure.More particularly, the invention relates to a method for rehabilitating a structure resting on a floor, by treating its foundation soil by injecting an expansive substance to close said crack.
Une fissure apparaissant sur un ouvrage peut être le signe d'une rupture dans les matériaux constitutifs de l'ouvrage et survient lorsque les contraintes engendrées dans l'ouvrage concerné, dépassent les limites de rupture pour lesquelles il a été conçu.A crack appearing on a structure can be a sign of a break in the materials constituting the structure and occurs when the constraints generated in the work concerned, exceed the limits of rupture for which it was conceived.
Certaines fissures apparaissent en raison d'un affaissement de l'ouvrage qui est alors le siège de contraintes parasites, c'est-à-dire de contraintes de traction et/ou de compression, normalement inexistantes sur l'ouvrage intact mais apparues suite au retrait du sol d'assise de l'ouvrage, et pouvant considérablement affaiblir l'ouvrage et engendrant ainsi des faiblesses et des désordres complémentaires.Some cracks appear due to a subsidence of the structure which is then the seat of parasitic stresses, that is to say of tensile and / or compressive stresses, normally nonexistent on the intact structure but appeared following the removal of the base of the structure, and can significantly weaken the work and thus generating weaknesses and additional disorders.
Les causes d'un affaissement de sol sont multiples. Il s'agit généralement :
- d'un défaut de portance initiale
- d'une décompression accidentelle du sol (suite à une fuite de canalisation ou la réalisation d'un terrassement incontrôlé, etc.)
- d'un tassement différentiel.
- initial lift defect
- accidental decompression of the ground (following a leak in the pipeline or uncontrolled earthworks, etc.)
- differential settlement.
Suite au phénomène de tassement, l'ouvrage subit un mouvement qui se traduit par l'apparition de fissures dans la superstructure telles que représentées sur les
Dans un cas idéal, les travaux de confortement du sol d'assise et du sol plus en profondeur, doivent permettre à l'ouvrage de retrouver son état initial.In an ideal case, the work of reinforcing the floor and the ground deeper, must allow the book to return to its original state.
Cependant, la diffusion des contraintes dans le sol est fonction de la profondeur dans le sol et les effets des travaux de confortement sur la fermeture des fissures sont également dépendants de la profondeur à laquelle le sol est conforté.However, the diffusion of stresses in the soil is a function of the depth in the soil and the effects of the reinforcement work on the closing of the cracks are also dependent on the depth at which the soil is reinforced.
La formule de Boussinesq montre en effet que les contraintes se localisent dans un faible rayon autour de la verticale du point d'application de la charge q pour une profondeur z.Boussinesq's formula indeed shows that the stresses are localized in a small radius around the vertical of the point of application of the load q for a depth z.
Ainsi, tel que représenté sur la
On exprime la valeur B1 :
D'où :
Généralement on retient pour α une valeur entre 30° à 45°.Generally, α is a value between 30 ° and 45 °.
La
Nous observons qu'à partir d'une profondeur de z∼2B, la valeur de σz devient moins importante au regard des charges apportées par l'ouvrage sur le sol. Elle converge vers zéro pour une profondeur de 8B.We observe that from a depth of z~2B, the value of σ z becomes less important with respect to the loads brought by the structure on the ground. It converges to zero for a depth of 8B.
En ce qui concerne le tassement du sol, nous pouvons établir une relation directe entre les contraintes et les déformations. Autrement dit, la valeur maximale de tassement est observée à la base des fondations et ce tassement diminue avec la profondeur pour converger vers zéro pour une profondeur de 8B.With regard to soil compaction, we can establish a direct relationship between stresses and deformations. In other words, the maximum settlement value is observed at the base of the foundations and this settlement decreases with the depth to converge towards zero for a depth of 8B.
Ainsi, en fonction de la profondeur du sol, deux types de sols peuvent être identifiés :
- 1. Sol d'assise - Il comprend une couche dite d'assise Z1 qui se situe en surface c'est à dire immédiatement sous les fondations de l'ouvrage, ainsi que les vides éventuellement présents entre la couche d'assise et les fondations de l'ouvrage. Lorsqu'il présente une mauvaise portance, il est susceptible de subir sous l'effet d'une charge, un tassement et provoquer des dégâts au sein de l'ouvrage. Le sol d'assise s'étend, conformément à la
figure 5 , sur une profondeur comprise entre « 0 » c'est à dire le niveau inférieur des fondations, et « 2B », profondeur à laquelle la contrainte σz est de l'ordre de 0,2 σ0, « B » étant la largeur de l'élément de fondation (semelle ou dallage) par l'intermédiaire duquel la charge est exercé. La valeur de « 2B » peut donc être par exemple comprise entre 1,2m à 2m.. - 2. Sol profond - Sous la couche d'assise, une couche profonde Z2, est située à une profondeur comprise entre 2B et 8B. La contrainte σz y est comprise entre 0,2 σ0 et 0,01 σ0 et est donc négligeable. A cette profondeur, une couche de sol même présentant une mauvaise portance subit un moindre tassement du fait de sa profondeur relativement importante vis à vis de la charge appliquée « q ».
- 1. Seating ground - It includes a so-called Z1 layer which is located on the surface, ie immediately below the foundations of the structure, as well as the voids that may be present between the base layer and the foundations of the book. When it has a poor lift, it is likely to suffer under the effect of a load, a settlement and cause damage within the structure. The seating floor extends, in accordance with the
figure 5 , on a depth between "0" ie the lower level of the foundations, and "2B", depth at which the stress σ z is of the order of 0.2 σ 0 , "B" being the width the foundation element (footing or pavement) through which the load is exerted. The value of "2B" can therefore be for example between 1.2m to 2m. - 2. Deep soil - Under the base layer, a deep layer Z2 is located at a depth between 2B and 8B. The constraint σ z y is between 0.2 σ 0 and 0.01 σ 0 and is therefore negligible. At this depth, a soil layer even with poor lift is less compacted due to its relatively large depth with respect to the applied load "q".
Or, pour qu'un procédé de réhabilitation d'un ouvrage en vue d'en refermer les fissures, soit efficace, il faut traiter la partie du sol où les contraintes sont maximales, c'est à dire le sol d'assise.However, for a process of rehabilitation of a structure to close the cracks, is effective, it is necessary to treat the part of the soil where the constraints are maximum, ie the ground seat.
Mais il convient, avant de tenter de les réparer pour rendre à l'ouvrage son aspect d'origine, de s'assurer que le sol en profondeur présente une portance suffisante.But it is advisable, before attempting to repair them to return the work to its original appearance, to ensure that the deep ground has sufficient lift.
Et si le sol en profondeur nécessite une consolidation, il convient d'abord de commencer le traitement de cette couche Z2, par un quelconque procédé de consolidation : « jet groutting » (pour Injection de coulis à haute pression), injection de microciment, ou par le procédé décrit dans le brevet européen
Les procédés de réhabilitation d'un ouvrage présentant une fissure, n'incluent donc pas la mise en oeuvre d'un tel procédé de consolidation en profondeur.The processes for rehabilitating a structure with a crack do not therefore include the implementation of such a deep consolidation method.
Ils sont mis en oeuvre sur le sol d'assise incluant la couche d'assise Z1, alors que la couche de sol Z2 sur lequel repose la couche Z1, est consolidée en profondeur, soit parce qu'elle n'a jamais subi de contraintes ayant entraîné une perte de portance, soit parce qu'elle a été redensifiée suite à de telles contraintes, ou qu'elle a été consolidée par des techniques appropriées.They are used on the seat floor including the Z1 foundation layer, while the Z2 layer of soil on which the Z1 layer rests, is consolidated in depth, either because it has never undergone any constraints. resulting in a loss of lift, either because it has been redensified due to such constraints, or has been consolidated by appropriate techniques.
Par exemple, les techniques traditionnelles de réhabilitation d'un ouvrage présentant une fissure envisagent, après confortation du sol en profondeur, un rebouchage des fissures avec ouverture, épinglage, puis rebouchage à l'aide d'un mortier sans retrait.For example, the traditional techniques of rehabilitation of a structure presenting a crack consider, after comforting the ground in depth, filling of cracks with opening, pinning, then filling with a mortar without shrinkage.
Ces techniques ne sont toutefois pas satisfaisantes pour les raisons suivantes :
- la partie (A) qui a subi le tassement, reste affaissée. Ainsi le propriétaire du bien, ne retrouve pas son ouvrage réparé dans le même état qu'avant le sinistre.
- Le rebouchage entre la partie (A) et (B) comporte souvent un désaffleurement qui n'est pas esthétiquement satisfaisant.
- Le rebouchage réalisé depuis l'extérieur a ses limites et ne permet pas d'assurer un contact parfait entre les éléments (A) et (B)
- et lorsque la fissure est située sur une paroi de l'ouvrage revêtue de motifs répétés, par exemple une paroi carrelée, le matériau additionnel rompant la répétition des motifs et dégradant l'aspect de la paroi en question.
- the part (A) which has undergone settlement, remains collapsed. Thus the owner of the property, does not find his repaired work in the same state as before the disaster.
- Filling between part (A) and (B) often has a misalignment which is not aesthetically pleasing.
- The filling made from the outside has its limits and does not allow to ensure a perfect contact between the elements (A) and (B)
- and when the crack is located on a wall of the structure coated with repeated patterns, for example a tiled wall, the additional material breaking pattern repetition and degrading the appearance of the wall in question.
Et parmi les procédés connus s'intéressant à l'injection de substance expansive dans le sol d'assise, le procédé décrit dans le document
L'objectif de la présente invention est donc de fournir un procédé pour la réhabilitation d'un ouvrage sinistré, notamment un ouvrage présentant au moins une fissure en raison de l'affaissement de son sol d'assise, permettant à la fois d'améliorer les propriétés du sol d'assise de l'ouvrage et de neutraliser les contraintes parasites engendrées par le tassement du sol, apparues consécutivement sur l'ouvrage.The object of the present invention is therefore to provide a method for the rehabilitation of a damaged structure, including a structure having at least one crack due to the subsidence of its ground, allowing both to improve the properties of the foundation soil of the structure and to neutralize the parasitic stresses caused by soil compaction, appeared consecutively on the structure.
Cet objectif est atteint avec un procédé de réhabilitation d'un ouvrage affaissé présentant au moins une fissure résultant de l'affaissement, dans lequel une substance de renforcement est injectée dans le sol de l'ouvrage (Z1) au droit de ladite fissure dans un trou de forage primaire, le procédé étant caractérisé en ce qu'il comprend en outre, simultanément à l'injection, l'acquisition d'une courbe révélatrice du rapprochement des bords de la fissure, l'injection étant arrêtée dès qu'une brusque diminution de pente en valeur absolue est détectée sur la courbe.This objective is achieved with a method of rehabilitating a collapsed structure having at least one crack resulting from subsidence, wherein a reinforcement substance is injected into the soil of the structure (Z1) at the right of said crack in a primary drilling hole, the method being characterized in that it further comprises, simultaneously with the injection, the acquisition of a revealing curve of the approaching of the edges of the crack, the injection being stopped as soon as a sudden slope decrease in absolute value is detected on the curve.
Plus précisément, lorsqu'on injecte dans le sol ou à l'interface entre le sol et la fondation de l'ouvrage, en quantité et/ou à pression suffisante une substance de renforcement du sol, celle-ci exerce, sur la base de l'ouvrage fissuré, une poussée ascendante qui tend à refermer la fissure de l'ouvrage, c'est-à-dire à rapprocher l'un de l'autre, les bords inférieur et supérieur de la fissure.More specifically, when a soil reinforcement substance is injected into the soil or at the interface between the soil and the foundation of the structure, in a quantity and / or at a sufficient pressure, it exerts, on the basis of the cracked structure, an upward thrust that tends to close the crack of the structure, that is to say to bring one to the other, the lower and upper edges of the crack.
Dans un premier temps, le rapprochement entre les bords de la fissure est rapide, puisque ces bords ne sont pas encore en contact.At first, the approximation between the edges of the crack is fast, since these edges are not yet in contact.
Dès que les bords entrent en contact, le rapprochement est subitement freiné.As soon as the edges come into contact, the approach is suddenly slowed down.
Le début du contact entre les bords de la fissure correspond à un moment où les contraintes parasites exercées sur l'ouvrage du fait de l'affaissement, sont neutralisées. En effet, une fois les deux bords en contact, la descente des charges de la partie haute (B) pourra se faire de façon satisfaisante vers le sol comme cela était le cas initialement.The beginning of the contact between the edges of the crack corresponds to a moment when the parasitic stresses exerted on the work because of the slump, are neutralized. Indeed, once the two edges in contact, the descent of the loads of the upper part (B) can be done satisfactorily towards the ground as it was the case initially.
Selon l'invention, on choisit donc d'arrêter l'injection dès que ce moment est détecté.According to the invention, it is therefore decided to stop the injection as soon as this moment is detected.
Il a été établi que ce moment peut être détecté facilement en traçant la courbe de variation d'un paramètre révélateur du rapprochement entre les bords de la fissure, par exemple une courbe de variation de déplacement ou de pression.It has been established that this moment can be easily detected by plotting the variation curve of a revealing parameter of the approximation between the edges of the crack, for example a variation curve of displacement or pressure.
Ainsi, selon un exemple de mise en oeuvre du procédé selon l'invention, un capteur d'un paramètre révélateur du rapprochement entre les bords de la fissure est placé entre deux points situés sur la façade de l'ouvrage, de part et d'autre de la fissure. Le capteur est relié à un dispositif de lecture, et, simultanément à l'injection, la courbe est lue sur le dispositif de lecture.Thus, according to an exemplary implementation of the method according to the invention, a sensor of a revealing parameter of the approximation between the edges of the crack is placed between two points located on the facade of the work, on the part and other of the crack. The sensor is connected to a reading device, and, simultaneously with the injection, the curve is read on the reading device.
Le capteur peut par exemple être un capteur de déplacement adapté à mesurer le rapprochement entre les bords de la fissure.The sensor may for example be a displacement sensor adapted to measure the approximation between the edges of the crack.
Selon une disposition avantageuse de l'invention, le capteur permet de détecter des déplacements infinitésimaux, de l'ordre de 10 microns.According to an advantageous arrangement of the invention, the sensor makes it possible to detect infinitesimal displacements of the order of 10 microns.
Le capteur peut aussi être un capteur de pression adapté à mesurer entre les bords de la fissure une augmentation de pression révélatrice du rapprochement entre lesdits bords.The sensor may also be a pressure sensor adapted to measure between the edges of the crack a pressure increase revealing the approximation between said edges.
Dans ce cas également, les variations de pression sont mesurées avec un degré important de précision, par exemple de l'ordre de 0,005 bars.In this case also, the pressure variations are measured with a high degree of accuracy, for example of the order of 0.005 bar.
Au moment où les bords de la fissure entrent en contact, une courbe telle qu'évoquée ci-dessus présente une brusque diminution de pente en valeur absolue.At the moment when the edges of the crack come into contact, a curve as evoked above has a sharp decrease in slope in absolute value.
En traçant la courbe d'un paramètre révélateur du rapprochement des bords de la fissure, on peut ainsi déterminer avec une grande précision le moment optimal pour l'arrêt de l'injection.By drawing the curve of a revealing parameter of the approximation of the edges of the crack, it is thus possible to determine with great precision the optimum moment for stopping the injection.
Grâce à ces dispositions, il est possible à la fois d'éviter la création de contraintes excessives dans l'ouvrage (par exemple une contrainte de compression excessive entre les bords de la fissure due à une injection trop importante), et de neutraliser de façon satisfaisante les contraintes parasites dues au sinistre (en évitant d'arrêter l'injection prématurément).Thanks to these provisions, it is possible both to avoid the creation of excessive stresses in the structure (for example an excessive compressive stress between the edges of the crack due to an excessive injection), and to neutralize in a manner satisfactory parasitic stress due to the disaster (avoiding to stop the injection prematurely).
Le procédé permet également la densification et l'amélioration de la portance du sol superficiel dans la couche Z1 grâce à l'injection de la substance de renforcement, ce qui augmente la capacité portante du sol (dans un sol de portance insuffisante) et/ou diminue sa perméabilité dans le cas d'un sol sensible aux variations hydriques. De même, elle permet de remplir les espaces vides entre le sol et la fondation de l'ouvrage.The method also allows the densification and the improvement of the surface soil lift in the Z1 layer by injection of the reinforcing substance, which increases the bearing capacity of the soil (in a soil of insufficient lift) and / or decreases its permeability in the case of soil sensitive to water changes. In the same way, it makes it possible to fill the empty spaces between the ground and the foundation of the structure.
Selon un exemple de mise en oeuvre, pour détecter la brusque rupture de pente signalant l'arrêt de l'injection, on évalue la pente de la courbe durant un premier intervalle ΔTS puis durant un deuxième intervalle de temps ΔTD, ΔTS et ΔTD étant compris entre 10 secondes et 2 minutes, et de préférence de l'ordre de 1 minute, et de façon encore plus préférée, 15 ou 30 secondes.According to an exemplary implementation, to detect the abrupt rupture of slope signaling the stop of the injection, the slope of the curve is evaluated during a first interval ΔT S and then during a second time interval ΔT D , ΔT S and ΔT D being between 10 seconds and 2 minutes, and preferably of the order of 1 minute, and even more preferably, 15 or 30 seconds.
On considère par exemple qu'une brusque diminution de pente est détectée lorsque la pente en valeur absolue sur le deuxième intervalle est inférieure de plus de 30%, de préférence plus de 50%, à la pente en valeur absolue sur le premier intervalle.For example, it is considered that a sudden decrease in slope is detected when the slope in absolute value on the second interval is more than 30%, preferably more than 50% lower than the slope in absolute value on the first interval.
Sur un ouvrage fissuré présentant une pluralité de fissures, le procédé sera généralement appliqué sur celles parmi lesdites fissures qui sont les plus représentatives de l'état de l'ouvrage en relation avec un problème de tassement de sol.On a cracked structure having a plurality of cracks, the method will generally be applied to those among the cracks that are most representative of the state of the structure in relation to a soil compaction problem.
Plus précisément, on commencera par traiter la partie de l'ouvrage où l'affaissement est le plus important, et dans cette partie, par les fissures les plus significatives c'est à dire les plus hautes et les plus larges, et les plus proches des angles de l'ouvrage, et parmi les fissures les plus significatives, par les plus étendues.More precisely, we will start by treating the part of the structure where the subsidence is the most important, and in this part, by the most significant fissures, that is to say the highest and widest, and the nearest angles of the structure, and among the most significant cracks, by the most extensive.
Et lorsqu'une fissure est identifiée comme très étendue, par exemple lorsqu'elle présente une longueur supérieure à 1 mètre, on la traitera par des injections multiples, soit en commençant l'injection à l'aplomb de l'écartement le plus important au sein de la fissure, par un premier point d'injection I, puis par des points d'injection successifs J, J', K, K' alternativement de part et d'autre de ce premier point d'injection I, soit en commençant l'injection par un premier point d'injection K situé à une première extrémité de la fissure considérée, en poursuivant l'injection à un deuxième point d'injection K' situé à une deuxième extrémité de cette fissure, puis par des points successifs J, J' alternativement de part et d'autre du centre de la fissure pour la refermer progressivement depuis ses extrémités.And when a crack is identified as very extensive, for example when it has a length greater than 1 meter, it will be treated by multiple injections, or by starting the injection at the level of the largest gauge at within the crack, by a first injection point I, then by successive injection points J, J ', K, K' alternately on either side of this first injection point I, either by starting injection by a first injection point K located at a first end of the crack considered, continuing the injection at a second injection point K 'located at a second end of this crack, then by successive points J , I alternately on either side of the center of the crack to close it gradually from its ends.
De préférence, le premier trou de forage est situé dans un plan sensiblement aligné avec le capteur et perpendiculaire à la façade.Preferably, the first borehole is located in a plane substantially aligned with the sensor and perpendicular to the facade.
Selon une disposition avantageuse, la substance de renforcement injectée est une substance expansive, notamment de la mousse de polyuréthane.According to an advantageous arrangement, the injected reinforcement substance is an expansive substance, especially polyurethane foam.
L'invention sera mieux comprise à la lecture de la description qui suit d'un mode de réalisation de l'invention donné à titre d'exemple non limitatif, en référence aux dessins annexés, sur lesquels :
- La
figure 1 est une illustration schématique d'un ouvrage sinistré pouvant être réhabilité grâce au procédé de l'invention ; - La
figure 2 montre un détail de mise en oeuvre du procédé selon l'invention ; - La
figure 3 montre l'ouvrage de lafigure 1 soumis au procédé de l'invention ; - Les
figures 4A et 4B illustrent une fissure de l'ouvrage respectivement avant et après la mise en oeuvre du procédé ; - La
figure 5 illustre schématiquement par une vue en perspective les points de forage pouvant être réalisés notamment le long des fissures étendues selon un mode de mise en oeuvre de la présente invention ; - La
figure 6 est une courbe établie grâce à un capteur de pression fixé de part et d'autre de la fissure ; - La
figure 7 est une courbe établie avec un capteur d'élongation fixé de part et d'autre de la fissure - La
figure 8 illustre schématiquement par une vue en coupe du sol d'assise d'un ouvrage, comprenant un vide entre le dallage et une couche d'assise Z1, ainsi qu'une lance d'injection à orifices multiples répartis le long de son axe à son extrémité, et permettant une distribution de la substance expansive pour combler le vide et consolider la couche Z1, - La
figure 9 représente par une vue schématique en coupe, le sol à l'aplomb d'un ouvrage supporté par une semelle, définissant une surface d'assise de profondeur z=0, une couche de surface ou d'assise Z1 à une profondeur z compriseentre 0 et 2B et une couche profonde à une profondeur comprise entre 2B et 8B, - La
figure 10 représente par une vue schématique la répartition des contraintes σz dans le sol, sous l'effet de l'application d'une charge « q ».
- The
figure 1 is a schematic illustration of a damaged work that can be rehabilitated by the method of the invention; - The
figure 2 shows a detail of implementation of the method according to the invention; - The
figure 3 shows the work of thefigure 1 subjected to the process of the invention; - The
Figures 4A and 4B illustrate a crack of the structure respectively before and after the implementation of the method; - The
figure 5 illustrates schematically by a perspective view the drilling points that can be made in particular along extended cracks according to an embodiment of the present invention; - The
figure 6 is a curve established by a pressure sensor fixed on both sides of the crack; - The
figure 7 is a curve established with an elongation sensor fixed on both sides of the crack - The
figure 8 schematically illustrates a sectional view of the base of a structure, comprising a gap between the pavement and a seat layer Z1, and a multi-port injection lance distributed along its axis to its end, and allowing a distribution of the expansive substance to fill the void and consolidate the Z1 layer, - The
figure 9 is a diagrammatic sectional view of the ground perpendicular to a structure supported by a soleplate, defining a seat surface of depth z = 0, a surface or seat layer Z1 at a depth z between 0 and 2B and a deep layer at a depth between 2B and 8B, - The
figure 10 is a schematic view of the distribution of stresses σ z in the soil, under the effect of the application of a load "q".
Dans les premières années de la vie d'un ouvrage, son sol d'assise se tasse toujours un peu sous l'effet des charges (poids propre de l'ouvrage, charges permanentes, charges d'exploitation). On parle de tassement sous charges, réparti en tout point de l'ouvrage.In the first years of the life of a structure, its base is always a little under the effect of loads (weight of the structure, permanent loads, operating costs). We speak of settlement under loads, distributed at any point of the work.
Dans certains cas, cependant, le tassement n'est pas le même en tout point de la structure. On parle de tassement différentiel.In some cases, however, the settlement is not the same at any point in the structure. We are talking about differential settlement.
Les causes de ce phénomène peuvent être multiples, soit que le sol ait été plus compressible à certains endroits qu'à d'autres, soit que les charges appliquées à l'ouvrage aient été inégalement réparties, soit encore en raison de variations hydriques du sol dues par exemple à l'orientation (les flancs orientés Sud et Ouest subissent plus de dessication que les flancs orientés Nord et Est), à la présence à proximité de racines d'arbres absorbant l'eau du sol, à un drainage insuffisant, à des fuites des réseaux, etc...The causes of this phenomenon can be multiple, either that the soil has been more compressible in some places than others, or that the loads applied to the structure have been unequally distributed, or still due to soil moisture variations. such as orientation (the south and west facing flanks are more desiccated than the north and east flanks), the presence of tree roots absorbing water from the soil, insufficient drainage, network leaks, etc ...
Sur la
Sur ce côté affaissé, la transmission des charges de l'ouvrage au sol est modifiée, l'interface entre la semelle de fondation et le sol d'assise étant incertaine, voire inexistante en cas de formation d'un vide intermédiaire entre ces deux éléments.On this collapsed side, the transmission of loads of the structure on the ground is modified, the interface between the foundation plate and the ground being uncertain or even non-existent in the event of formation of an intermediate gap between these two elements .
La réponse de la construction à la modification de la transmission des charges de la structure au sol, et aux contraintes parasites qui en résultent, se traduit par une rupture avec la fissuration du bâtiment, illustrée par le réseau de fissures 20 sur la
Un ingénieur spécialisé dans la construction pourra facilement différencier deux types de fissures : les fissures stabilisées, qui n'affectent plus l'ouvrage, et les fissures dites « actives », qui, au contraire, sont le siège de contraintes parasites.An engineer specialized in construction can easily differentiate two types of cracks: stabilized cracks, which no longer affect the structure, and so-called "active" cracks, which, on the contrary, are the seat of parasitic stresses.
Généralement, les fissures actives se situent au-dessus des fissures stabilisées.Generally, active cracks are located above stabilized cracks.
Une fois l'ouvrage et le sol sous-jacent stabilisés après confortation suite à un sinistre par exemple, on traitera en priorité la partie de l'ouvrage où l'affaissement est le plus important, et dans cette partie, par les fissures les plus significatives c'est à dire les plus hautes et les plus larges, et les plus proches des extrémités latérales de l'ouvrage (coins), et parmi les fissures les plus significatives, par les plus étendues.Once the structure and the underlying soil stabilized after comfort after a disaster, for example, we will treat the part of the structure where the slump is the most important, and in this part, by the most significant cracks ie the highest and the widest, and the closest to the lateral extremities of the structure (corners) , and among the most significant cracks, by the most extensive.
Lorsqu'une fissure est identifiée comme très étendue, par exemple lorsqu'elle présente une longueur supérieure à 1 mètre, on la traitera par des injections multiples, soit en commençant l'injection à l'aplomb de l'écartement le plus important au sein de la fissure, par un premier point d'injection I, puis par des points d'injection successifs J, J', K, K' alternativement de part et d'autre de ce premier point d'injection I, soit en commençant l'injection par un premier point d'injection K situé à une première extrémité de la fissure considérée, en poursuivant l'injection à un deuxième point d'injection K' situé à une deuxième extrémité de cette fissure, puis par des points successifs J, J' alternativement de part et d'autre du centre de la fissure pour la refermer progressivement depuis ses extrémités.When a fissure is identified as very large, for example when it is more than 1 meter in length, it will be treated with multiple injections, starting with the injection at the level of the largest of the crack, by a first injection point I, then by successive injection points J, J ', K, K' alternately on either side of this first injection point I, or by starting injection by a first injection point K located at a first end of the crack in question, by continuing the injection at a second injection point K 'situated at a second end of this crack, then by successive points J, I alternately on either side of the center of the crack to close it gradually from its ends.
Sur la
Pour réhabiliter l'ouvrage sinistré, trois conditions doivent être satisfaites.To rehabilitate the damaged structure, three conditions must be met.
Une condition préalable est que le sol en profondeur, c'est à dire situé à une profondeur supérieure à 2B, B étant la largeur de la semelle supportant l'ouvrage, la plus proche de la fissure, n'ait jamais subi de contraintes ayant entraîné une perte de portance, parce qu'il a été redensifié ou consolidé par des techniques appropriées.A prerequisite is that the soil in depth, that is to say located at a depth greater than 2B, B being the width of the sole supporting the structure, the closest to the crack, has never undergone any constraints having caused a loss of lift, because it has been redensified or consolidated by appropriate techniques.
Cette condition préliminaire doit être remplie avant la mise en oeuvre du procédé selon l'invention.This preliminary condition must be fulfilled before carrying out the process according to the invention.
Une deuxième condition est l'amélioration et l'homogénéisation des propriétés du sol S vis-à-vis des charges appliquées et/ou des variations hydriques, afin d'éviter la survenance ultérieure de nouveaux problèmes de tassements différentiels.A second condition is the improvement and homogenization of the properties of the soil S vis-à-vis the applied loads and / or water variations, in order to avoid the subsequent occurrence of new problems of differential settlements.
Cette deuxième condition peut être remplie par l'injection dans le sol S d'une substance de renforcement, notamment une substance expansive, permettant de densifier le sol et ainsi d'améliorer à la fois sa portance et sa perméabilité.This second condition can be fulfilled by the injection into the soil S of a reinforcing substance, in particular an expansive substance, making it possible to densify the soil and thus to improve both its lift and its permeability.
Une troisième condition est la neutralisation des contraintes parasites engendrées dans la structure du fait des tassements différentiels et les ruptures de la structure. En effet, une partie de la superstructure pourrait par exemple rester en porte à faux.A third condition is the neutralization of parasitic stresses generated in the structure due to differential settlements and breaks in the structure. Indeed, a part of the superstructure could for example remain in overhang.
Le procédé selon l'invention, dont les étapes successives sont décrites ci-dessous, permet de réhabiliter l'ouvrage sinistré illustré sur la
Dans une première étape du procédé illustrée sur les
Le capteur de contrainte 30 est par exemple un détecteur de pression, relié respectivement à deux points fixes Q3, Q4 situés de part et d'autre de la fissure 22.The
Une augmentation de pression mesurée par le capteur 30 signifie que les deux bords 24, 26 de la fissure 22 tendent à se rapprocher.An increase in pressure measured by the
Le capteur de pression 30 est relié à un dispositif de lecture 40, ici un ordinateur, sur lequel un premier opérateur peut lire la courbe illustrant les valeurs de pression mesurées au cours du temps à l'aide du capteur 30.The
Sur la
Ce premier trou de forage 50 est généralement situé dans un plan P perpendiculaire à la façade 12 de l'ouvrage 10 et comprenant le capteur de pression 30 (voir
Une lance d'injection 51, est insérée dans le trou de forage 50 : la lance 51 est positionnée de sorte que son extrémité inférieure soit placée dans la couche Z1 sous la semelle de fondation du pavillon 10. Cette lance 51 comporte à son extrémité pénétrant le sol d'assise, des orifices successifs afin de pouvoir répandre de la substance expansive aussi bien dans la couche d'assise Z1 que dans les vides éventuels sous fondation existant entre la semelle et la couche Z1.An
Ainsi, comme l'illustre la bulle supérieure de la
Et comme l'illustre la bulle inférieure de la
L'injection de consolidation est paramétrée (volume de substance injectée, pression d'injection, coefficient d'expansion de la substance de renforcement le cas échéant, phasage des injections, etc.) de sorte que le sol aux abords du point d'injection soit renforcé, et qu'une poussée ascendante est exercée sur la base affaissée A de l'ouvrage au droit de la fissure à traiter.The consolidation injection is parameterized (volume of substance injected, injection pressure, coefficient of expansion of the reinforcing substance if necessary, phasing of injections, etc.) so that the ground around the injection point is reinforced, and an upward thrust is exerted on the collapsed base A of the work to the right of the crack to be treated.
Dans l'exemple, la substance de renforcement est une mousse de polyuréthane. Une telle mousse de polyuréthane est, par exemple, le résultat d'un mélange de polyol et de MDI Isocyanate. Sur chantier, ces deux produits sont stockés dans un camion, dans des cuves séparées. Les deux composants sont acheminés, à travers des tuyaux, jusqu'au pistolet mélangeur de la lance de projection. L'association des deux produits mixés sous pression avec de l'air insufflé par une pompe bi-composants forme par réactions chimiques une mousse expansive qui se solidifie et acquiert de hautes caractéristiques mécaniques.In the example, the reinforcing substance is a polyurethane foam. Such a polyurethane foam is, for example, the result of a mixture of polyol and MDI Isocyanate. On site, these two products are stored in a truck, in separate tanks. Both components are routed through pipes to the spray gun of the spray lance. The combination of the two products mixed under pressure with air injected by a two-component pump forms by chemical reactions an expansive foam which solidifies and acquires high mechanical characteristics.
Durant toute l'opération d'injection, un premier opérateur lit en permanence la courbe affichée par l'ordinateur 40.During the entire injection operation, a first operator continuously reads the curve displayed by the
La courbe de la
On note que la courbe peut être relevée indifféremment par un système d'échantillonnage dans le temps (mesures à intervalles réguliers) ou en continu.It can be noted that the curve can be recorded indifferently by a sampling system over time (measurements at regular intervals) or continuously.
L'instant TA=0 (point A sur la courbe) correspond à l'injection du mélange de polyol et de MDI Isocyanate dans la profondeur du sol d'assise à l'aide de la lance d'injection 51. A compter de cet instant, un certain temps est nécessaire à la réaction des deux composants.The moment T A = 0 (point A on the curve) corresponds to the injection of the mixture of polyol and MDI Isocyanate into the depth of the seat ground with the aid of the
La phase préliminaire, durant laquelle la mousse n'a pas débuté son expansion et le sol d'assise n'a pas encore été déplacé, est notée PH1 sur la courbe. L'injection n'entraîne pour l'instant aucune modification des contraintes exercées sur l'ouvrage 10, ce qui se traduit par un premier plateau PH1 sur la courbe relevée.The preliminary phase, during which the foam has not begun to expand and the ground has not yet been moved, is noted PH1 on the curve. The injection does not involve any modification of the stresses exerted on the
L'instant TB (point B sur la courbe) correspond au début des mouvements de la partie affaissée A de l'ouvrage en raison du traitement du sol d'assise Z1. La résistance latérale du sol étant inférieure à sa résistance verticale (importante du fait du poids du bâtiment), la mousse se propage essentiellement latéralement depuis l'extrémité de la lance d'injection 51. Les grains du sol se réorganisent entre eux. Le sol se densifie sous l'effet de la poussée latérale de la mousse, mais le niveau du sol d'assise reste pour l'instant inchangé. Là encore, on ne mesure aucune influence sur l'ouvrage. La courbe de pression reste plane PH2.The moment T B (point B on the curve) corresponds to the beginning of the movements of the collapsed part A of the structure due to the treatment of the seat floor Z1. As the lateral resistance of the ground is lower than its vertical resistance (important because of the weight of the building), the foam propagates essentially laterally from the end of the
Le sol d'assise, une fois compacté (point TC de la courbe), offre une résistance accrue à la propagation de la mousse dans la direction horizontale. La résistance du sol dans la direction verticale devient finalement plus faible que sa résistance latérale. La mousse tend alors à se propager vers le haut, engendrant, sur la base de l'ouvrage 10, une force de poussée dirigée vers le haut. Cette force de poussée tend naturellement à relever la partie affaissée de l'ouvrage 10, rapprochant progressivement le bord inférieur 26 de la fissure 22 de son bord supérieur 24. La pression mesurée par le capteur augmente alors très rapidement, comme illustré sur la courbe par la phase notée PH3. Le point TC correspond donc au début du relevage de la partie A.The seat floor, once compacted (point T C of the curve), offers increased resistance to the propagation of the foam in the horizontal direction. The soil resistance in the vertical direction eventually becomes lower than its lateral resistance. The foam then tends to propagate upward, generating, on the base of the
Au bout d'un moment, l'augmentation de la pression se fait plus lente. En effet, à un instant TD (point D sur la courbe), la courbe montre une rupture de pente, qui correspond au début du contact entre les bords inférieur et supérieur de la fissure. L'injection est arrêtée dès que la rupture de pente est détectée. Le pistolet injecteur est coupé.After a while, the increase in pressure is slower. Indeed, at a time T D (point D on the curve), the curve shows a slope break, which corresponds to the beginning of contact between the lower and upper edges of the crack. The injection is stopped as soon as the slope break is detected. The injector gun is cut.
Les variations de pente de la courbe sont évaluées en permanence tout au long de l'injection.The slope variations of the curve are evaluated continuously throughout the injection.
Dans la pratique, un opérateur expérimenté peut stopper l'injection dès qu'il détecte à l'oeil nu une rupture franche de la pente de la courbe, la pente diminuant en valeur absolue. Pour écarter toute mauvaise interprétation, l'opérateur attend généralement que cette modification de la courbe se confirme sur un intervalle de temps prédéterminé, de l'ordre d'une dizaine de secondes, par exemple entre 15 et 30 secondes, après le point de rupture de pente D, généralement inférieur à 1 minute.In practice, an experienced operator can stop the injection as soon as he detects a sharp break in the slope of the curve with the naked eye, the slope decreasing in absolute value. To avoid any misinterpretation, the operator generally waits for this modification of the curve to be confirmed over a predetermined time interval, of the order of ten seconds, for example between 15 and 30 seconds, after the breaking point. slope D, generally less than 1 minute.
En général, l'opérateur arrêtera l'injection lorsqu'à un instant T, il aura détecté une diminution de la pente d'au moins 30%, de préférence de 50%, sur un intervalle de temps inférieur à 1 minute. Cette détection peut aussi être réalisée de manière automatisée, à l'aide d'un logiciel approprié.In general, the operator will stop the injection when at a time T, he has detected a decrease in the slope of at least 30%, preferably 50%, over a time interval of less than 1 minute. This detection can also be performed automatically, using appropriate software.
Dans l'exemple illustré, l'injection est arrêtée à un instant Ts (correspondant à un point Gs de la courbe) où la pente sur un premier intervalle ΔTS, est inférieur de plus de 30% à la pente de la courbe sur un intervalle de temps précédent ΔTD, ΔTS et ΔTD étant inférieurs ou égaux à 1 minute, par exemple 15 ou 30 secondes.In the illustrated example, the injection is stopped at a time Ts (corresponding to a point Gs of the curve) where the slope on a first interval ΔT S , is more than 30% lower than the slope of the curve on a previous time interval ΔT D , ΔT S and ΔT D being less than or equal to 1 minute, for example 15 or 30 seconds.
Evidemment, la stabilisation de la courbe n'est pas immédiate, la mousse continuant son expansion pendant quelques instants après l'arrêt du pistolet. Ceci est illustré par une faible et lente variation de pression notée PH4 sur la
Enfin, une fois la fissure 22 entièrement refermée, on observe une stabilisation totale de la valeur de pression mesurée, identifiable par le palier noté PH5 sur la courbe.Finally, once the
La
Si la fissure considérée s'étend sur une longueur importante, par exemple 1 mètre ou plus, et que malgré une première injection, selon le procédé ci-dessus, un écartement entre les bords de la fissure subsiste à une certaine distance, des opérations d'injection supplémentaires sont ensuite poursuivies en d'autres points d'injection J et J' puis K, K' situés de part et d'autre du premier trou de forage I et dans les zones qui se trouvent à l'aplomb de la fissure considérée, conformément à la
Les autres points d'injection J, J', K, K', adjacents au premier point d'injection I sont selon un premier mode de réalisation, effectués dans des trous de forage réalisés alternativement à gauche et à droite du trou de forage primaire 50, en suivant sensiblement la façade 12 du bâtiment 10. Les trous de forage sont espacés du premier trou de forage 50 et entre eux d'une distance constante d prédéterminée, par exemple égale à un mètre.The other injection points J, J ', K, K', adjacent to the first injection point I are according to a first embodiment, made in drill holes made alternately to the left and to the right of the primary borehole. 50, substantially following the
On ne réalisera aucune injection à plus de 1 m de distance des deux points qui se trouvent respectivement à l'aplomb des deux extrémités d'une fissure.No injection shall be made more than 1 m away from the two points which are respectively at the base of the two ends of a crack.
Selon un autre mode de mise en oeuvre du procédé selon l'invention, le capteur utilisé peut être un détecteur de déplacement (d'élongation), notamment un détecteur à fibre optique permettant une détection de déplacements à 10 microns près.According to another embodiment of the method according to the invention, the sensor used may be a displacement detector (elongation), in particular an optical fiber detector allowing detection of displacements to within 10 microns.
La courbe de contrainte obtenue avec un tel capteur de déplacement est illustrée sur la
Les phases PH1 à PH5 sont représentées sur la courbe de la
On constate qu'après un premier palier correspondant à l'expansion de la mousse et au début de la consolidation du sol, la courbe présente une pente importante, témoignant du rapprochement rapide des bords de la fissure. Lorsque les bords entrent en contact, le rapprochement devient plus lent et la pente de la courbe (en valeur absolue) diminue brusquement.It can be seen that after a first plateau corresponding to the expansion of the moss and at the beginning of the consolidation of the soil, the curve has a significant slope, testifying to the rapid approximation of the edges of the crack. When the edges come in contact, the approximation becomes slower and the slope of the curve (in absolute value) decreases sharply.
Selon l'invention, l'injection dans le premier trou de forage est arrêtée dès que la brusque diminution de pente en valeur absolue (point D) est identifiée.According to the invention, the injection into the first borehole is stopped as soon as the abrupt decrease in slope in absolute value (point D) is identified.
Claims (13)
- A method for restoring a structure resting on a collapsing ground (10), with the subgrade being reinforced, with the structure having at least one crack (22) resulting from the collapsing of the ground, wherein a reinforcing substance is injected into the subgrade of the structure at said crack (22) into a main bore hole (50), with the method being characterized in that it further comprises, simultaneously with the injection, the acquisition of a curve indicative of the moving closer together of the edges (24, 26) of the crack (22), with the injection being stopped as soon as a sudden decrease in the absolute value of the slope is detected on the curve.
- A method according to claim 1, wherein the reinforcing substance is an expansive substance, in particular polyurethane foam.
- A method according to claim 1 or 2, wherein at each time T, the slope of the curve is evaluated during a first time interval ΔTS, then during a second time interval ΔTD ranging from 10 seconds to 1 minute and preferably of the order of 15 or 30 seconds.
- A method according to any one of claims 1 to 3, wherein a sensor (30) of a parameter indicative of the moving closer together of the edges (24, 26) of the crack (22) is placed between two points (Q3, Q4) located on the facade (12) of the structure (10), on either side of the crack (22), with said sensor being connected to a reading device (40), and, simultaneously with the injection, said curve is read on the reading device (40).
- A method according to claim 4, wherein the sensor (30) is a pressure sensor adapted to measure a pressure increase indicative of the moving closer together of the edges (24, 26), between the edges (24, 26) of the crack (22).
- A method according to claim 4, wherein the sensor (30) is a displacement sensor adapted to measure the moving closer together of the edges (24, 26) of the crack (22).
- A method according to any one of claims 4 to 6, wherein a first bore hole (50) is located in a plane (P) substantially aligned with the sensor (30) and perpendicular to the facade (12) of the structure.
- A method according to any claim 7, wherein additional injections are carried out into bore holes provided alternately on one side and the other side of the first bore hole (50), away from said first bore hole (50).
- A method according to claim 8, wherein, at each additional injection point, the injection is stopped as soon as no further injection is possible.
- A method according to claim 8 or 9, wherein once the injections into the bore holes are completed, the ground bearing capacity is measured.
- A method according to one of the preceding claims, characterized in that the structure is supported by structural elements such as a slab or a sole resting on the subgrade, with the injection of the reinforcing substance being performed between the structural element and the subgrade and/or into the ground layer supporting the structure, also called the subgrade.
- A system for restoring a structure (10) resting on a collapsing ground (10), with the subgrade being reinforced, with the structure having at least one crack (22) resulting from the collapsing of the ground, comprising:- a sensor (30) for measuring the moving closer together of the longitudinal edges of the crack,- a device for injecting a reinforcing substance into the subgrade of the structure at the crack, or between the subgrade and a structural element supporting the structure, such as a slab or a sole, with the substance having, in its expanded state, a density almost similar to that of the ground prior to the collapsing thereof,- a device for the acquisition for data from the sensor as a curve indicative of the moving closer together of the edges of the crack,- an injection stop control device for the real-time collection of the curve from the acquisition device and controlling the injection stop as soon as a sudden decrease in the absolute value of the slope is detected on the curve.
- A system according to claim 12, wherein the density of the reinforcing substance is above 60kg.m3.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
LU92314A LU92314B1 (en) | 2013-11-26 | 2013-11-26 | Rehabilitation process for a structure exhibiting a crack by following a curve representative of the spacing of the edges of the crack |
PCT/EP2014/074838 WO2015078722A1 (en) | 2013-11-26 | 2014-11-18 | Method for restoring a structure having a crack by following a curve representing the separation of the edges of the crack |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3074574A1 EP3074574A1 (en) | 2016-10-05 |
EP3074574B1 true EP3074574B1 (en) | 2017-08-02 |
Family
ID=49841779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP14805203.8A Active EP3074574B1 (en) | 2013-11-26 | 2014-11-18 | Method for restoring a structure having a crack by following a curve representing the separation of the edges of the crack |
Country Status (4)
Country | Link |
---|---|
US (1) | US10138641B2 (en) |
EP (1) | EP3074574B1 (en) |
LU (1) | LU92314B1 (en) |
WO (1) | WO2015078722A1 (en) |
Families Citing this family (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2013203973A1 (en) * | 2012-12-13 | 2014-07-03 | Rigid Ground Pty Ltd | Treating particulate and connecting slab portions |
US11326310B2 (en) * | 2015-08-21 | 2022-05-10 | Donald Velazquez | Concrete and masonry restoration and ornamentation method and apparatus |
CN106894409B (en) * | 2015-12-17 | 2019-02-12 | 上海华峰材料科技研究院(有限合伙) | Rapid repair method of polyurethane grouting reinforcement and lifting for foundation settlement |
CN106703836A (en) * | 2016-12-29 | 2017-05-24 | 中铁隧道勘测设计院有限公司 | Treatment method of the bedding soft soil of existing circular shield tunnel |
IT201700037754A1 (en) * | 2017-04-06 | 2018-10-06 | Thur Srl | PROCEDURE FOR IMPROVING THE MECHANICAL AND HYDRAULIC CHARACTERISTICS OF LANDS. |
US10487473B2 (en) * | 2017-06-20 | 2019-11-26 | Charles L. Asplin | Wall lifting methods |
JP6895842B2 (en) * | 2017-07-31 | 2021-06-30 | 大成建設株式会社 | Ground improvement method |
US10465355B2 (en) * | 2017-09-06 | 2019-11-05 | Uretek Usa, Inc. | Injection tube countersinking |
CN108343102B (en) * | 2018-04-26 | 2024-02-27 | 北京恒祥宏业基础加固技术有限公司 | Pile foundation settlement reinforcement jacking leveling structure and construction method thereof |
IT201800007020A1 (en) * | 2018-07-09 | 2020-01-09 | SYSTEM AND PROCEDURE FOR INJECTION OF EXPANDING RESINS IN SOILS TO BE CONSOLIDATED. | |
US11885092B2 (en) * | 2019-01-31 | 2024-01-30 | Terracon Consultants, Inc. | Reinforcement structures for tensionless concrete pier foundations and methods of constructing the same |
US11525230B2 (en) * | 2019-03-19 | 2022-12-13 | Eaglelift, Inc. | System and method for mitigation of liquefaction |
CN112343104B (en) * | 2019-08-09 | 2022-06-17 | 北京恒祥宏业基础加固技术有限公司 | Reinforcing and lifting method for large-scale pier of high-speed rail |
US10961682B1 (en) * | 2020-01-14 | 2021-03-30 | John Dustin Williams | System and methods for concrete slab foundation repair |
CN111749198B (en) * | 2020-05-30 | 2022-11-25 | 郑州安源工程技术有限公司 | Channel slab underwater grouting stabilizing and lifting method |
CN111962577B (en) * | 2020-08-14 | 2021-07-20 | 山东建筑大学 | A method for rotation displacement and tilt correction of spatial curved surfaces of brick-concrete buildings |
CN111962576B (en) * | 2020-08-14 | 2021-07-20 | 山东建筑大学 | An inclination correction method for frame structure buildings based on space surface trajectory |
US12084825B2 (en) * | 2022-12-02 | 2024-09-10 | Alchatek, Llc | Methods to prevent soil erosion and stabilize seawalls |
Family Cites Families (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FI823299L (en) * | 1982-09-27 | 1984-03-28 | Uretaanitekniikka Oy | PROCEDURE FOR THE PURPOSE OF BUCKETS |
US4787779A (en) * | 1987-01-29 | 1988-11-29 | Clark Howard E | Method and apparatus for raising and supporting a foundation |
US4906140A (en) * | 1987-01-29 | 1990-03-06 | Clark Howard E | Method and apparatus for raising and supporting a foundation |
JPH0745722B2 (en) * | 1993-05-20 | 1995-05-17 | 株式会社ピー・エス | Method and device for raising submerged concrete paving slab |
US5369675A (en) * | 1993-06-25 | 1994-11-29 | General Electric Company | Remote load activating mechanisms |
IT1286418B1 (en) | 1996-12-02 | 1998-07-08 | Uretek Srl | PROCEDURE TO INCREASE THE WEIGHT OF FOUNDATION LANDS FOR BUILDING CONSTRUCTIONS |
US6074133A (en) * | 1998-06-10 | 2000-06-13 | Kelsey; Jim Lacey | Adjustable foundation piering system |
NL1012243C2 (en) * | 1999-06-04 | 2000-12-12 | Voorbij Groep Bv | Method and device for manufacturing a pile in the ground. |
US6923599B2 (en) * | 2002-06-24 | 2005-08-02 | Kenneth J. Kelso | In-ground lifting system and method |
ITMI20021995A1 (en) * | 2002-09-19 | 2004-03-20 | Uretek Srl | PROCEDURE FOR REPAIRING AND / OR WATERPROOFING AND / OR ISOLATING AND / OR REINFORCING AND / OR RECONSTRUCTING THE STRUCTURAL INTEGRITY OF WALL SYSTEMS |
US7421910B2 (en) * | 2004-10-07 | 2008-09-09 | The Curators Of The University Of Missouri | Strain sensitive coax cable sensors for monitoring structures |
EP1914350B2 (en) * | 2006-10-13 | 2019-06-05 | Geosec S.r.l. | A method for homogenizing and stabilising a soil by way of injections |
ITRE20070014A1 (en) * | 2007-02-09 | 2008-08-10 | Geosec Srl | METHOD OF LOCAL SEISMIC PROTECTION OF MANUFACTURING AREAS AND / OR MANUFACTURED TO THE FOUNDATIONS AND THE SURROUNDING BUILDINGS. |
JP4787779B2 (en) * | 2007-03-14 | 2011-10-05 | 株式会社リコー | Image processing apparatus, program, and preview image display method |
JP2009135169A (en) * | 2007-11-29 | 2009-06-18 | Tokyo Electron Ltd | Substrate processing system, and substrate processing method |
JP5593157B2 (en) * | 2010-08-10 | 2014-09-17 | 株式会社ソーキ | Crack displacement measurement system |
-
2013
- 2013-11-26 LU LU92314A patent/LU92314B1/en active
-
2014
- 2014-11-18 EP EP14805203.8A patent/EP3074574B1/en active Active
- 2014-11-18 US US15/039,149 patent/US10138641B2/en active Active
- 2014-11-18 WO PCT/EP2014/074838 patent/WO2015078722A1/en active Application Filing
Non-Patent Citations (1)
Title |
---|
None * |
Also Published As
Publication number | Publication date |
---|---|
EP3074574A1 (en) | 2016-10-05 |
WO2015078722A1 (en) | 2015-06-04 |
US10138641B2 (en) | 2018-11-27 |
US20160362901A1 (en) | 2016-12-15 |
LU92314B1 (en) | 2015-05-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3074574B1 (en) | Method for restoring a structure having a crack by following a curve representing the separation of the edges of the crack | |
AU731637B2 (en) | Method for increasing the bearing capacity of foundation soils for buildings | |
EP0102340A2 (en) | Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions | |
FR2523627A1 (en) | METHOD FOR CONFORTING ARCHES OR SIMILAR CONSTRUCTIONS | |
EP1045089B1 (en) | Masonry structure and associated reinforcement method | |
EP2976465B1 (en) | Method for consolidating the ground encasing a tunnel | |
EP1794375B1 (en) | Device and method for a tower reinforcing foundation | |
EP1243702B1 (en) | Buttressing apparatus for an excavation shoring and use of the apparatus | |
EP0382608B1 (en) | Method of making an excavation by the trench wall technique involving the use of releasably prestressed floor elements | |
FR3092348A1 (en) | IN-SITU REINFORCEMENT PROCESS OF A CONSOLE SLAB ANCHORED BY A THERMAL BRIDGE BREAKER | |
EP3411531B1 (en) | Modular device for creating an anchor point in the ground | |
EP2930287B1 (en) | Method for constructing a non-structural flooring | |
EP2729626B1 (en) | Method of building a structure and a load-spreading mat | |
FR3082861A1 (en) | METHOD FOR IN SITU REINFORCEMENT OF A CONSOLE SLAB | |
FR2722819A1 (en) | Wedge or pressure element for two adjacent structural components, used in civil engineering | |
FR2851316A1 (en) | PROCESS FOR LAYING BURIED TUBULAR ELEMENTS AND PREPARING MORTAR FOR IMPLEMENTATION | |
FR2807457A1 (en) | Device for correcting bridge access road profile uses measurement device for evaluating the slope increase then metallic enclosure installed within the fill in front of the bridge are injected with a fluid in order to modify their volume | |
EP1154100A1 (en) | Method and apparatuses for renovating a floor | |
WO2015075234A1 (en) | Method for consolidating soil by acquiring a curve that reveals the permeability of the soil | |
EP1452670A1 (en) | Method for reinforcing a building element and building element | |
EP0395534A1 (en) | Building construction | |
EP1045091B1 (en) | Construction element reinforcement method | |
FR2718765A1 (en) | Concrete floor slab construction resting on the ground. | |
WO1990001089A1 (en) | Process for repairing foundations including damaged pile heads, in particular for timber piles | |
FR2965572A1 (en) | Method for limiting hydric variations of ground located near building, involves covering waterproofing layer with coating material after hardening of polymeric material, and setting waterproofing layer on ground in non-hardened state |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20160624 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
DAX | Request for extension of the european patent (deleted) | ||
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R079 Ref document number: 602014012690 Country of ref document: DE Free format text: PREVIOUS MAIN CLASS: E02D0035000000 Ipc: E02D0037000000 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E02D 3/12 20060101ALI20170310BHEP Ipc: E02D 37/00 20060101AFI20170310BHEP Ipc: E02D 31/10 20060101ALI20170310BHEP |
|
INTG | Intention to grant announced |
Effective date: 20170330 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP Ref country code: AT Ref legal event code: REF Ref document number: 914625 Country of ref document: AT Kind code of ref document: T Effective date: 20170815 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: FRENCH |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602014012690 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20170802 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 914625 Country of ref document: AT Kind code of ref document: T Effective date: 20170802 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 4 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171102 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171202 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171102 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171103 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602014012690 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602014012690 Country of ref document: DE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
26N | No opposition filed |
Effective date: 20180503 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171130 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171130 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171118 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20171130 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180602 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171118 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20171130 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20141118 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20181118 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20181118 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170802 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20241022 Year of fee payment: 11 |