DE910770C - Procedure for moving a longwall construction (migrating longwall construction) - Google Patents
Procedure for moving a longwall construction (migrating longwall construction)Info
- Publication number
- DE910770C DE910770C DEP15599D DEP0015599D DE910770C DE 910770 C DE910770 C DE 910770C DE P15599 D DEP15599 D DE P15599D DE P0015599 D DEP0015599 D DE P0015599D DE 910770 C DE910770 C DE 910770C
- Authority
- DE
- Germany
- Prior art keywords
- iron
- shell iron
- longwall
- stamp
- irons
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 title claims description 13
- 238000000034 method Methods 0.000 title description 9
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 84
- 229910052742 iron Inorganic materials 0.000 claims description 42
- 235000000396 iron Nutrition 0.000 claims description 8
- 230000033764 rhythmic process Effects 0.000 claims description 2
- 238000005065 mining Methods 0.000 claims 3
- 241001605695 Pareronia Species 0.000 claims 1
- 230000000284 resting effect Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
- E21D23/06—Special mine caps or special tops of pit-props for permitting step-by-step movement
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Earth Drilling (AREA)
Description
Verfahren zum Umsetzen eines Strebausbaues (Wandernder Strebausbau) Die Erfindung betrifft einen wandernden Strebaus:bau, bei welchem in abwechselndem Rhythmus ein, vom Hangenden gelöster Ausbauteil sich an einem anderen Ausbauteil abstützend bzw. von ihm getragen und anschließend der nunmehr vom Hangenden gelöste ursprünglich tragende Ausbauteil, von dem nunimehr festen Ausbauteil getragen, vorgezogen wird.Procedure for moving a longwall construction (migrating longwall construction) The invention relates to a wandering longwall: construction, in which in alternating A rhythm, an extension part detached from the hanging wall is attached to another extension part supporting or carried by him and then the now detached from the hanging wall Originally the supporting extension part, supported by the now more solid extension part, preferred will.
Ein Strebausbau dieser grundsätzlichen Art ist bereits bekannt, und zwar auch ein solcher, der in der Weise umgesetzt wird, daß das Lösen des einen Schaleisens vom Hangenden erst erfolgt, nachdem das andere, bereits gelöste und vorgezogene Schaleisen den Gebirgsdruck aufgenommen hat. Die Erfindung betrifft eine Verbesserung eines solchen: Strebausbaues. Sie besteht darin, daß beiderseits eines inneren Schaleisens, welches den einen der wechselseitig zu verschiebenden Ausbauteile bildet, den zweiten der Ausbauteile bildende Hilfsschaleisen angeordnet sind und das Umsetzen des Ausbaues im Pilgerschritt :derart erfolgt, d@aß einmal das innere Schaleisen mit seinen an ihm hängenden Stempeln, von der Stempelkonstruktion der äußeren Schaleisen getragen, vorgezogen wird und :nach Wiedersetzen der dem inneren Schaleisen zugeordneten Stempel .der die äußeren Schaleisen tragende Stempel geraubt und bis kurz hinter den vorwärtigen Stempel des inneren Schaleisens vorgezogen wird. Hierdurch wird ein Ausbauverfahren geschaffen, «-elches in bezug auf Zuverlässigkeit und Sicherlieit, insbesondere vom Gesichtspunkt der Verteilung der Beanspruchungen auf die Ausbauelemente in den einzelnen Phasen -des Ausbaues, .den. bekannten Verfahren gegenüber erhebliche Vorteile aufweist.A longwall construction of this basic type is already known and Although also one that is implemented in such a way that the loosening of the one Shell iron from the hanging wall only takes place after the other, already loosened and advanced shell iron has absorbed the rock pressure. The invention relates to an improvement of such a longwall construction. It consists in that on both sides an inner shell iron, which is one of the mutually displaceable Forms expansion parts, the second of the expansion parts forming auxiliary shells are arranged are and the implementation of the expansion in the pilgrimage: done in such a way, d @ ate once the inner cup iron with its stamps hanging on it, from the stamp construction of the outer shell iron is worn, preferred and: after replacing the dem inner shell iron associated punch .the punch carrying the outer shell iron stolen and pulled forward until just behind the forward stamp of the inner shell iron will. This creates an expansion process, «-elches in in terms of reliability and security, especially from the point of view of distribution the stresses on the extension elements in the individual phases of the extension, .the. has significant advantages over known methods.
Außer diesem Vorteil- besteht ein weiterer des neuen Ausbaues noch darin, daß er in konstruktiver Hinsicht nur geringfügige Änderungen an vorhandenen Ausbauelementen, im wesentlichen lediglich des Stempelkopfes, bedingt, während im übrigen. normale Stempel und als Schaleisen normale Profile verwendet werden.In addition to this advantage, there is another one of the new expansion in the fact that he has made only minor changes to the existing one from a structural point of view Expansion elements, essentially only the punch head, conditionally, while in rest. normal punches and normal profiles can be used as shell irons.
Zweckmäßig wird ein vergleichsweise schweres, vorzugsweise als Breitflanschträger ausgebildetes Schaleisen von normaler Länge zwischen zwei das andere System bildenden wesentlich kürzeren und schwächeren Schaleisen, die gemeinsam von nur einem Stempel getragen sind, liegend verwendet, und das Umsetzen des Ausbaues erfolgt derart, daß einmal -das innere Schaleisen mit seinen an ihm hängenden Stempeln, von dem Stempel der äußeren Schaleisen getragen, vorgezogen wird und nach Wiedersetzen der dem inneren Schaleisen zugeordneten Stempel der die äußeren Schaleisen tragende Stempel geraubt und bis kurz hinter den vorwärtigen Stempel des inneren Schaleisens vorgezogen wird,woraufsich derVorgang wiederholt.A comparatively heavy beam, preferably a wide flange beam, is expedient formed cup iron of normal length between two forming the other system much shorter and weaker shell irons, which are shared by only one punch are carried, used lying down, and the implementation of the expansion is carried out in such a way that that once - the inner cup iron with its stamps hanging on it, from the The stamp of the outer shell iron is worn, pulled forward and after the the punch assigned to the inner shell iron is the one carrying the outer shell iron Stamp stolen and until just behind the forward stamp of the inner shell iron is preferred, whereupon the process repeats.
Weitere Einzelheiten der Erfindung gehen aus der nachstehenden Beschreibung einer beispielsweisen Ausführungsform des neuen Strebausbaues an Hand der Abbildungen hervor. Von diesen zeigt Abb. i die verschliedenen Phasen. des Umsetzvorganges bei der Ausführungsform des neuen Verfahrens mit gegenseitiger Abstützung der Schaleisen und Abb.2 die Ausbildung des die äußeren Schaleisen tragenden Stempels und die verschiedenen Lagen der Schaleisen zueinander während der einzelnen Phasen des Umsetzvorganges hierbei.Further details of the invention can be found in the description below an exemplary embodiment of the new longwall construction based on the figures emerged. Fig. I shows the various phases of these. of the repositioning process the embodiment of the new method with mutual support of the shell iron and Fig.2 shows the design of the punch carrying the outer shell irons and the various Positions of the cup irons to each other during the individual phases of the relocation process here.
Vorzugsweise wird, wie in den Abbildungen dargestellt, als inneres Schaleisen ein Breitflanschträger a verwendet, welcher von zwei daran gemäß der dargestellten vorzugsweisen Ausführungsform pendelnd angeordneten Stempeln g und lt getragen wird. Die gelenkige Verbindung dieser Stempel mit dem Träger erfolgt zweckmäßig unter Zwischenschaltung von Druckstücken zwischen Stempel und Schaleisen, welche die Aufhängung der Stempel belastungsfrei gestalten.. Beiderseits neben diesem inneren Schaleisen liegen die vergleichsweise kurzen und wesentlich leichteren Schaleisen b, die gemeinsam von nur einem Stempel f getragen werden, und zwar auf den beiden Schenkeln des gabelförmig ausgebildeten Kopfes c .dieses Stempels parallel zum Schaleisen an diesem angeordneten Konsolen d aufruhend, die die Schaleisen. b auf einem großen Teil ihrer Länge unterstützen und mit diesen vorzugsweise fest verbunden sind.Preferably, as shown in the figures, a wide flange carrier a is used as the inner shell iron, which is carried by two stamps g and lt arranged in a pendulum manner thereon according to the preferred embodiment shown. The articulated connection of these stamps with the carrier is expediently carried out with the interposition of pressure pieces between the stamp and cup iron, which make the suspension of the stamp load-free be worn, on the two legs of the fork-shaped head c .dieses stamp parallel to the shell iron on this arranged brackets d resting, which the shell iron. b support over a large part of their length and are preferably firmly connected to them.
Mit e sind auf den Schenkeln des Stempelkopfes c bzw. den Konsolen d aufgeschweißte, gegebenenfalls herunterklappbar ausgebildete Gleitstücke bezeichnet, auf welchen mit seinen oberen Flanschen aufruhend das gelöste Schaleisen a vorgeschoben wird. Gemäß Abb.2 (Ausführung 3) können außerdem noch Rollen und Hilfssetzeinrichtungen i, k vorgesehen werden.With e are on the legs of the punch head c or the consoles d designates welded-on, possibly fold-down sliding pieces, on which, resting with its upper flanges, the loosened cup iron a is pushed forward will. According to Fig. 2 (version 3), rollers and auxiliary setting devices can also be used i, k can be provided.
In Abb. i sind die einzelnen Phasen: des Umsetzvorganges veranschaulicht. In der Phase i sind sowohl das Schaleisen a wie das Schaleisen b unter das Hangende gepreßt. Von den beiden das Schal-eisen, a unterstüzenden Stempeln steht der eine, h, kurz vor dem die Schaleisen b tragenden Stempel f, der andere am rückwärtigen Ende der Schaleisen.The individual phases of the relocation process are illustrated in Fig. I. In phase i, both shell iron a and shell iron b are pressed under the hanging wall. Of the two punches supporting the shell iron, one stands, h, just in front of the punch f carrying the shell iron b , the other at the rear end of the shell iron.
Nun wird das Schaleisen a gelöst (Phase 2), so daß es auf den Gleitstücken e aufruht. Das Hangende und auch ein etwaiger Spitzenverzug bleiben unverändert durch die Schaleisen b unterstützt. Nun wird, das Schaleisen ct vorgeschoben, und die Stempel gelangen in die Lage gemäß Phase 3, d. h. der vordere Stempel steht versatzseitig des vorher nach dem stempelfreien Stoß zu umgelegten Fördermittels, während der rückwärtige Stempel des Schaleisens a sich in der Nachbarschaft des die Schaleisen b tragenden Stempels f befindet.Now the cup iron a is loosened (phase 2) so that it rests on the sliders e. The hanging wall and any peak distortion remain unchanged, supported by the cup iron b. Now the shell iron ct is advanced, and the stamps get into the position according to phase 3, that is, the front stamp is on the offset side of the previously transferred conveyor after the stamp-free push, while the rear stamp of shell iron a is in the vicinity of shell iron b bearing stamp f is located.
Nach dem Setzen der Stempel n und lt wird der Stempel f geraubt, und es -,werden nun die Schaleisen b mit .dem daran hängenden Stempel auf den unteren Flanschen des Breitflanschträgerschaleisens ca gleitend vorgeschoben. Damit ist die Ausgangslage wiederhergestellt.After the stamps n and lt have been set , the stamp f is stolen, and then the shell iron b with the stamp attached to it are slid forward on the lower flanges of the wide flange carrier shell iron ca. This has restored the starting position.
An dem mittleren Schaleisen bzw. Torpfänder a kann gegebenenfalls ein ausziehbarer Hilfsstempel in horizontaler Lage angehängt werden; der Verwendung findet, wenn der Zustand des Hangenden sein sofortiges Abfangen nach der Freilegung erforderlich macht, Durch Lösung einer Arretierung, beispielsweise Wegschlagen einer Fußraste, fällt der Fuß herunter, während der Kopf gleichzeitig bis fast unter das Hangende stößt. Nach dem Nachsetzen des Ausbaues wird -der Hilfsstempel wieder hochgezogen.On the middle shell iron or gate fence a can optionally an extendable auxiliary ram can be attached in a horizontal position; of use finds if the condition of the hanging wall its immediate interception after exposure Requires, By releasing a lock, for example knocking away a Footrest, the foot falls down while the head at the same time almost falls under the Hanging wall abuts. After resetting the expansion, the auxiliary ram is pulled up again.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEP15599D DE910770C (en) | 1948-10-02 | 1948-10-02 | Procedure for moving a longwall construction (migrating longwall construction) |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEP15599D DE910770C (en) | 1948-10-02 | 1948-10-02 | Procedure for moving a longwall construction (migrating longwall construction) |
Publications (1)
Publication Number | Publication Date |
---|---|
DE910770C true DE910770C (en) | 1954-05-06 |
Family
ID=7365680
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DEP15599D Expired DE910770C (en) | 1948-10-02 | 1948-10-02 | Procedure for moving a longwall construction (migrating longwall construction) |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE910770C (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1075518B (en) * | 1960-02-18 | Hermann Schwarz Kommanditgesellschaft, Wattenscheid | Migrating metallic lining for mining operations in mines | |
DE1091061B (en) * | 1958-10-02 | 1960-10-20 | Bwg Bergwerk Walzwerk | Wandering support frame for the expansion of underground pits |
DE1099969B (en) * | 1954-09-17 | 1961-02-23 | Gerhard Werner | Advance expansion frame |
DE1103268B (en) * | 1959-10-31 | 1961-03-30 | Bwg Bergwerks Und Walzwerk Mas | Wandering support frame for the expansion of pit rooms |
DE1134948B (en) * | 1955-11-14 | 1962-08-23 | Kloeckner Werke Ag | Longwall mining method |
DE1154424B (en) * | 1960-09-12 | 1963-09-19 | Ewald Wiemann Maschf | Wandering longwall mining |
US3138933A (en) * | 1957-08-19 | 1964-06-30 | Kemper Maxwell Fisher | Method of and apparatus for driving a tunnel through and supporting earth structure |
US3143862A (en) * | 1958-08-11 | 1964-08-11 | Dobson Ltd W E & F | Support of roofs in mines |
DE1177099B (en) * | 1956-02-28 | 1964-09-03 | Dobson Ltd W E & F | Migrating hydraulic longwall mining |
DE1189039B (en) * | 1954-04-06 | 1965-03-18 | Hans Joachim Von Hippel Dr Ing | Wandering expansion element, preferably for steep or semi-steep storage |
DE1193458B (en) * | 1958-08-11 | 1965-05-26 | Dobson Ltd W E & F | Wandering pit support |
DE1215092B (en) * | 1962-08-25 | 1966-04-28 | Nitto Tekko Kabushiki Kaisha | Gradual pit expansion with alternately shiftable ram assemblies |
US3373572A (en) * | 1963-05-23 | 1968-03-19 | Maxwell F. Kemper | Method of driving tunnels |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE245392C (en) * | ||||
DE619297C (en) * | 1934-03-17 | 1935-09-27 | Emil Schweitzer | Wandering pit lining with shell iron alternately serving as a girder and Pfaendungsschiene |
DE728577C (en) * | 1941-07-06 | 1942-12-02 | Gelsenkirchener Bergwerkes Akt | Wandering expansion to secure the hanging wall |
-
1948
- 1948-10-02 DE DEP15599D patent/DE910770C/en not_active Expired
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE245392C (en) * | ||||
DE619297C (en) * | 1934-03-17 | 1935-09-27 | Emil Schweitzer | Wandering pit lining with shell iron alternately serving as a girder and Pfaendungsschiene |
DE728577C (en) * | 1941-07-06 | 1942-12-02 | Gelsenkirchener Bergwerkes Akt | Wandering expansion to secure the hanging wall |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1075518B (en) * | 1960-02-18 | Hermann Schwarz Kommanditgesellschaft, Wattenscheid | Migrating metallic lining for mining operations in mines | |
DE1189039B (en) * | 1954-04-06 | 1965-03-18 | Hans Joachim Von Hippel Dr Ing | Wandering expansion element, preferably for steep or semi-steep storage |
DE1099969B (en) * | 1954-09-17 | 1961-02-23 | Gerhard Werner | Advance expansion frame |
DE1134948B (en) * | 1955-11-14 | 1962-08-23 | Kloeckner Werke Ag | Longwall mining method |
DE1177099B (en) * | 1956-02-28 | 1964-09-03 | Dobson Ltd W E & F | Migrating hydraulic longwall mining |
US3138933A (en) * | 1957-08-19 | 1964-06-30 | Kemper Maxwell Fisher | Method of and apparatus for driving a tunnel through and supporting earth structure |
US3143862A (en) * | 1958-08-11 | 1964-08-11 | Dobson Ltd W E & F | Support of roofs in mines |
DE1193458B (en) * | 1958-08-11 | 1965-05-26 | Dobson Ltd W E & F | Wandering pit support |
DE1091061B (en) * | 1958-10-02 | 1960-10-20 | Bwg Bergwerk Walzwerk | Wandering support frame for the expansion of underground pits |
DE1103268B (en) * | 1959-10-31 | 1961-03-30 | Bwg Bergwerks Und Walzwerk Mas | Wandering support frame for the expansion of pit rooms |
DE1154424B (en) * | 1960-09-12 | 1963-09-19 | Ewald Wiemann Maschf | Wandering longwall mining |
DE1215092B (en) * | 1962-08-25 | 1966-04-28 | Nitto Tekko Kabushiki Kaisha | Gradual pit expansion with alternately shiftable ram assemblies |
US3373572A (en) * | 1963-05-23 | 1968-03-19 | Maxwell F. Kemper | Method of driving tunnels |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE910770C (en) | Procedure for moving a longwall construction (migrating longwall construction) | |
DE1302918C2 (en) | HIKING STREET STRUCTURE | |
DE970540C (en) | Framework for progressive expansion in brown coal longwall mining | |
DE2540048B1 (en) | DEVICE WITH A REAR CYLINDER FOR A STRUCTURAL STRUCTURE MOVING WITH A STRUT CONVEYOR, IN PARTICULAR SHIELD REMOVAL FRAME AND WITH A DURING THE BACK, THE LYING SLEEVE ON THE LYING SLIDE PISTON | |
DE1009136B (en) | Extension frame for traveling longwall mining | |
DE1075518B (en) | Migrating metallic lining for mining operations in mines | |
DE2211605C3 (en) | Wandering route expansion | |
DE911961C (en) | Method and device for the moving expansion of mining struts | |
DE2743046A1 (en) | LIFTING SIGN FOR DRIVING TUNNELS, CLOUDS OR DGL. | |
DE1289805B (en) | Mechanically retractable face construction unit | |
DE2741304A1 (en) | PRE-PRESSING DEVICE | |
DE2109384C3 (en) | Method and apparatus for producing tubular tunnels, galleries or the like. in shield driving with a lining made of in-situ concrete | |
DE924625C (en) | Method and device for driving straightening sections, crosscuts or other passages, especially in underground mining | |
DE803535C (en) | Method and device for free pre-paving in moving longwall mining with shell iron | |
DE963595C (en) | Tool that can be pulled through a borehole by means of a rope or chain for gradual expansion | |
DE1882507U (en) | HIKING STREAM CONSTRUCTION. | |
DE2212994A1 (en) | DEVICE FOR THE HYDRAULIC STRUCTURAL STRUCTURE FOR SHIELDING THE DISPOSAL AREA FROM THE BEARING SPACE TO BE KEEP OPEN | |
DE2346853B2 (en) | Machine for bringing in a route extension consisting of door frames | |
DE1993012U (en) | TRAVELING FRAME FOR UNDERGROUND MINING. | |
DE441555C (en) | Flat or angle iron slide connection with screw or wedge bolts | |
DE1205036B (en) | Wandering longwall with frame | |
DE800124C (en) | Joint cap with tensile strength connection for longwall construction | |
DE3732066A1 (en) | Self-advancing support arrangement with light-alloy props for supporting various mine spaces | |
DE69019056T2 (en) | Mobile device for removal in the mining area. | |
DE1085478B (en) | Wandering pit support |