DE387271C - Process for the production of long iron-reinforced concrete bodies - Google Patents
Process for the production of long iron-reinforced concrete bodiesInfo
- Publication number
- DE387271C DE387271C DET25078D DET0025078D DE387271C DE 387271 C DE387271 C DE 387271C DE T25078 D DET25078 D DE T25078D DE T0025078 D DET0025078 D DE T0025078D DE 387271 C DE387271 C DE 387271C
- Authority
- DE
- Germany
- Prior art keywords
- concrete
- production
- reinforced concrete
- long iron
- concrete bodies
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Revetment (AREA)
Description
Verfahren zur Herstellung langer eisenbewehrter Betonkörper. Die als Rammpfähle Verwendung findenden langen eisenarmierten Betonkörper wurden bisher wegen ihrer Länge in liegenden Formen hergestellt, in welche vorher die Eisenarmierung eingelegt worden war. Damit dabei die nötige Haftung zwischen Beton und Eisen erzielt werden kann, muß der Beton in ziemlich wasserhaltigem, also mehr oder weniger flüssigem Zustand eingebracht werden. Dieses Verfahren hat den Nachteil, daß der eingebrachte Beton nicht gestampft werden kann und daher nicht genügend zusammengepreßt wird. Es ist auch nicht angängig, einige Stunden später, nachdem der Zement mit dem Binden begonnen und dadurch einen Teil des Wassers verarbeitet hat, den Beton einzustampfen, weil dabei der Beton im Binden gestört würde, außerdem aber auch nicht die Festigkeit erzielt werden kann, die man für solche Zwecke braucht.Process for the production of long iron-reinforced concrete bodies. As Driving piles using long iron-reinforced concrete bodies were previously Because of their length, they are made in horizontal forms, in which the iron reinforcement was previously placed had been inserted. So that the necessary adhesion between concrete and iron is achieved can be, the concrete must be in fairly water-based, i.e. more or less liquid State to be introduced. This method has the disadvantage that the introduced Concrete cannot be tamped and is therefore not compressed enough. It is also not usable a few hours later after the cement started setting has started and thereby processed some of the water to crush the concrete, because this would impair the binding of the concrete, but also not the strength can be achieved that are needed for such purposes.
Bei der Herstellung solcher Betonkörper in liegenden Formen hat sich der Übelstand besonders nachteilig gezeigt, daß der Beton an der unteren Seite bedeutend druckfester wird als an der oberen, so daß zum Beispiel bei dem Transport der Pfähle sich auf der Seite Risse zeigen, die bei der Herstellung nach oben gelegen hat. Bei- starker Beanspruchung durch den Rammbären können ebenfalls die ersten Brucherscheinungen stets auf der Seite des Pfahles festgestellt werden, die bei der Herstellung nach oben gelegen bat.In the production of such concrete bodies in lying forms has the disadvantage shown particularly disadvantageously that the concrete on the lower side is significant Is more pressure-resistant than at the top, so that, for example, when transporting the piles show cracks on the side that was facing up during manufacture. The first signs of breakage can also occur in the event of heavy use by the pile driver must always be noted on the side of the pile that was manufactured after upstairs asked.
Gemäß der Erfindung werden die aus dem geschilderten Herstellungsverfahren der eisenarmierten Betonrammpfähle sich ergebenden Nachteile dadurch beseitigt, daß die die Metallbewehrung enthaltende, ringsum geschlossene Form schrägliegend mit dickflüssigem Beton gefüllt und nach dem Füllen senkrecht aufgerichtet wird, so daß der Kopf des herzustellenden Betonkörpers nach unten weist.According to the invention, the production method described the disadvantages resulting from the iron-reinforced concrete driven piles are eliminated, that the all-round closed form containing the metal reinforcement is inclined filled with thick concrete and erected vertically after filling, so that the head of the concrete body to be produced points downwards.
Es ist zwar bereits bekannt, eisenbewehrte Betonpfähle u. dgl. in der Weise herzustellen, daß der Beton in eine ringsum -geschlossene, die Metallbewehrung enthaltende Form bei senkrechter Stellung der letzteren eingefüllt wird, und zwar so, daß der Kopf des herzustellenden Betonkörpers nach unten weist; bei diesem bekannten Verfahren handelt es sich aber ausschließlich um kurze Pfähle, wie Zaunpfähle u. dgl., die allgemein so kurz sind, daß sie die Verwendung senkrecht stehender Formen möglich machen, was bei den gemäß der Erfindung herzustellenden eisenbewehrten Betonrammpfählen wegen ihrer großen Länge vollkommen ausgeschlossen ist.It is already known to use iron-reinforced concrete piles and the like in the way to produce that the concrete in a completely closed, the metal reinforcement containing form is filled with the latter in a vertical position, namely so that the head of the concrete body to be produced points downwards; at this well-known The method is only about short posts, such as fence posts and the like. Like. Which are generally so short that they require the use of vertical shapes make possible what with the iron-reinforced concrete driven piles to be produced according to the invention because of its great length is completely excluded.
Unter Verwendung schrägliegend zu füllender Formen, die nach dem Füllen senkrecht aufgerichtet werden, ist es möglich, einen im Querschnitt durchaus gleichmäßigen Rammpfahl zu erzeugen; es lassen sich also die den Betonrammpfählen nach der bisher gebräuchlichen Herstellungsweise anhaftenden Nachteile, welche darin bestehen, daß der Beton an der unteren Seite der Form bedeutend druckfester ist als an der oberen und daß durch das im Querschnitt des Pfahles ungleiche Gefüge des Betons die Schläge des Rammbären Brucherscheinungen stets auf der Seite des Pfables hen-orrufen, die bei der Herstellung nach oben gelegen hat, vollkommen vermeiden.Using inclined shapes to be filled after filling be erected vertically, it is possible to have a cross-section that is quite uniform Generate driven pile; So it can be the concrete driven piles according to the previously Conventional production methods inherent disadvantages, which are that the concrete on the lower side of the mold is significantly more pressure-resistant than on the upper side and that the impacts due to the uneven structure of the concrete in the cross-section of the pile the battering bear's fracture phenomena always call on the side of the pile that in the preparation of upwards, avoid it completely.
Der gemäß der Erfindung erzielte Vorteil, welcher darin besteht, daß beim senkrechten Aufrichten der liegend gefüllten Form der Kopf des herzustellenden Betonrammpfahles nach unten weist, so daß der Beton die höchste Festigkeit am Kopfende des Pfahles erlangt, wird nicht dadurch geschmälert, daß bei der Herstellung von Stützpfählen, also von Pfählen kleiner Länge unter Verwendung einer auch während des Füllens senkrecht stehenden Form die Anordnung bekannt war, den Kopf des herzustellenden Betonkörpers nach unten weisen zu lassen, weil die auf diese Weise am Kopfende des Betonkörpers erlangte größere Druckfestigkeit nur bei Rammpfählen, die den starken Schlägen eines Rammbären ausgesetzt werden, praktischen Wert hat.The advantage achieved according to the invention, which is that when erecting the lying filled form vertically, the head of the to be produced Concrete driven pile points downwards, so that the concrete has the highest strength at the head end of the pile is not diminished by the fact that in the manufacture of Support piles, i.e. piles of small length using one also during of filling vertical form the arrangement was known, the head of the to be manufactured To have the concrete body face down, because that way at the head of the Concrete body achieved greater compressive strength only with driven piles that were strong Being hit by a battering bear has practical value.
Nach dem Verfahren dieser Erfindung wird eine die Metallbewehrung enthaltende Form verwendet, die ringsherum dichtgeschlossen ist und schrägliegend mit dickflüssigem Beton gefüllt wird. Nach dem Füllen wird die Form senkrecht aufgerichtet, so daß sie mit dem Kopf nach unten weist. Durch Klopfen auf die Seitenwände der Form wird in an sich bekannter Weise das im Beton enthaltene Wasser zum Aufsteigen veranlaßt, so daß sich der Beton vollständig dicht zusammensetzt, wobei die hohe Säule einen großen Druck ausübt, so daß der Beton unter diesem Druck erhärten muß.According to the method of this invention, one becomes the metal reinforcement Containing form used, which is tightly closed all around and inclined is filled with thick concrete. After filling, the mold is erected vertically, so that it's head down. By tapping the side walls of the The water contained in the concrete is used to ascend in a manner known per se caused so that the concrete is composed completely tight, with the high Column exerts a great pressure, so that the concrete must harden under this pressure.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DET25078D DE387271C (en) | 1921-03-11 | 1921-03-11 | Process for the production of long iron-reinforced concrete bodies |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DET25078D DE387271C (en) | 1921-03-11 | 1921-03-11 | Process for the production of long iron-reinforced concrete bodies |
Publications (1)
Publication Number | Publication Date |
---|---|
DE387271C true DE387271C (en) | 1923-12-22 |
Family
ID=7551842
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DET25078D Expired DE387271C (en) | 1921-03-11 | 1921-03-11 | Process for the production of long iron-reinforced concrete bodies |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE387271C (en) |
-
1921
- 1921-03-11 DE DET25078D patent/DE387271C/en not_active Expired
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CH626132A5 (en) | Process and apparatus for erecting essentially cupola-shaped structures, and a structure erected therewith | |
DE2365445C2 (en) | Process for producing a sand drain and vibrating ram for carrying out the process | |
DE387271C (en) | Process for the production of long iron-reinforced concrete bodies | |
DE2248472C3 (en) | Process for the production of T-beams from prestressed concrete | |
DE2262242A1 (en) | WALL ELEMENT | |
DE1759351A1 (en) | Device that can be moved on the track to stabilize the track system | |
DE697655C (en) | Process for lifting, lowering or straightening structures | |
DE1801984A1 (en) | Method of making pile connections | |
DE702716C (en) | Method and device for the production of in-situ concrete piles | |
DE616706C (en) | Process for the production of plug-like concrete foundation bodies | |
AT303340B (en) | Reinforcement bars | |
DE855155C (en) | Formwork for the production of loose concrete walls | |
DE2532964A1 (en) | Large framed wall block set in concrete - has tubes between glass blocks for rods and transport anchors | |
DE925457C (en) | Molded wall element as permanent formwork for structures made of cast concrete, especially for barrier walls and. like | |
DE3442913A1 (en) | Method of producing a sleeve foundation | |
DE893779C (en) | Process for the production of mixed foundation piles from reinforced concrete or the like. | |
DE1634236C (en) | Method for the foundation of prefabricated components on piles, especially under water | |
DE534086C (en) | Process for the production of concrete or reinforced concrete pile foundations by means of driven piles of short lengths | |
DE1409608C (en) | Procedure for the foundation of a floating tank with driven piles | |
DE840144C (en) | Preferably made of concrete component for the production of permanent formwork for walls, dam clamps or the like. | |
AT145104B (en) | Process for the production of upright cast concrete poles. | |
DE1409601C (en) | Shaft body made of profile rods for a composite pile | |
DE828588C (en) | Method and device for building walls for buildings or the like. | |
DE2029854A1 (en) | Pile shoe for in-place piles and a method for the production of in-place piles with the aid of jacking pipes equipped with such pile shoes | |
DE521440C (en) | Process for the production of site stakes from concrete or the like using a Schuettrohr that can be closed by a cap |