CN2282972Y - Cement precast floor slab short line mould - Google Patents
Cement precast floor slab short line mould Download PDFInfo
- Publication number
- CN2282972Y CN2282972Y CN 97207191 CN97207191U CN2282972Y CN 2282972 Y CN2282972 Y CN 2282972Y CN 97207191 CN97207191 CN 97207191 CN 97207191 U CN97207191 U CN 97207191U CN 2282972 Y CN2282972 Y CN 2282972Y
- Authority
- CN
- China
- Prior art keywords
- bed die
- mold
- floor slab
- mould
- precast floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model relates to a mold for producing a cement prefabricated floor plate through a short line method. The structure of the mold is that a bottom mold is provided with a side mold, an end mold, a steel bar fixed plate, etc. Compared with the existing method of producing the cement prefabricated floor plate through a long line, when used to produce the cement prefabricated floor plate, the utility model has the advantages of land saving, high floor plate quality, low cost, easy maintenance, easy factory operation, flexibility, maneuverability, etc., and the production can be carried out near the building site.
Description
The utility model relates to building field, is a kind of short-term mould of producing concrete prefabricated floor that is applicable to.
Along with the development of socialist construction, skyscraper is also rised sheer from level ground like the mushrooms after rain, and the consumption of precast floor slab is very big.To at present, the precast floor slab that China produces all is the method that adopts long line to produce, and promptly on roomy concrete floor the reinforcing bar tensioning is produced in the open.This mode of production not only needs roomy prefabricated place, also needs certain stacking place, otherwise can't produce.In addition: also can have influence on the quality of prefabricated cement floor because of the out-of-flatness in prefabricated place and because operation in the open, meeting burning sun and severe cold just can not all-weather production.In addition: the investment that long line is produced precast floor slab is bigger, example: the production site of building 1000 floors of monthly output needs 300,000 yuan of funds approximately.
The concrete prefabricated floor short-term mould that the utility model proposes can overcome the weak point that long now line is produced concrete prefabricated floor, reaches province ground, investment-saving, guarantees purposes such as the floor quality of production.
Major technique feature of the present utility model is as follows:
Accompanying drawing 1 is a structural representation of the present utility model
Accompanying drawing 2 is the utility model precast floor slab reinforcing bar tensioning schematic diagram
Accompanying drawing 3 is the schematic diagram of precast floor slab stacking on the utility model bed die
Among the figure: 1 be bed die, 2 for the end mould, 3 for side form, 4 for conduit, 5 for the reinforcing bar fixed head, 6 for suspension ring, 7 for lever, 8 for jack, 9 for precast floor slab, 10 for reinforcing bar
As seen from the figure, the utility model by bed die 1, end mould 2, side form 3, conduit 4, Reinforcing bar fixed head 5 forms, and its bed die 1 is posture, on the bed die face both sides arrange side form 3, Top, two ends place be provided with reinforcing bar fixed head 5, inboard, two ends arrange end mould 2, conduit 4 side by side, Parallel cross two the end moulds 2 (seeing Fig. 1). And be provided with suspension ring, bed die on the bed die 1 1 below support height is greater than precast floor slab thickness, and bed die length two ends spacing is 3-5 rice.
Making on request the utility model can come into operation. Earlier equidistant between conduit Put into abreast reinforcing bar, and the tensioning reinforcing bar. During tensioning, fix an end bar, the other end By the tension of the shackle at lever two ends, with same distolateral at bed die of the very heavy topmast of small-sized hydraulic Operate jack, treat that pressure expression regulation tension force gets final product (seeing Fig. 2). The placement side form, Conduit, end mould are poured the cement concrete that mixes by ratio requirement into then in framed, After waiting to solidify, give maintenance according to specification requirement.
Adopt the utility model to carry out short-term template production cement floor and compared following advantage with long line production technology:
One, save the soil: equal production scale, short-term template are produced and are only accounted for long line production and need account for 30% of land area, adopt buttress such as small-sized hoisting machine to pile to the certain height (see figure 3) because of the former, even can be in indoor prefabricated and maintenance.
Two, improve the quality: produce when prefabricated and not influenced by terrace and cause damagedly, because of using this steel die, product quality is guaranteed easily.
Three, cost is low: do not need the construction investment of large tracts of land terrace, and equal production scale, the mould expense only accounts for 33% of long line production investment.
But four factory building equalization, round-the-clock production maintenance.Long line is produced floor, is exposed to fully summer under the burning sun, and crackle easily takes place, need the topped frost-resistant material of large tracts of land winter, the floor that short-term is produced can be concentrated stacking on bed die, be not subjected to tanning by the sun of burning sun, also only need winter an a spot of frost-resistant material just can all cover, save time, laborsaving, water-saving.
Five, maneuverability, the construction site produces nearby, can reduce expensive freight.
To sum up, the utility model production technology is simple, investment is little, good social benefit and economic benefit are arranged, and is suitable for applying.
Claims (2)
1, a kind of concrete prefabricated floor short-term mould, it is characterized in that it mainly is made up of bed die 1, end mould 2, side form 3, conduit 4, reinforcing bar fixed head 5, its bed die 1 is a posture, both sides are provided with side form 3 on the bed die face, top, two ends place is provided with reinforcing bar fixed head 5, the inboard, two ends end mould 2 is set and conduit 4 parallel side by side, cross two end moulds 2.
2, concrete prefabricated floor short-term mould according to claim 1 is characterized in that bed die 1 is provided with suspension ring, bed die 1 below support height greater than precast floor slab thickness, and bed die two ends spacing is a 3-5 rice.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 97207191 CN2282972Y (en) | 1997-02-13 | 1997-02-13 | Cement precast floor slab short line mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 97207191 CN2282972Y (en) | 1997-02-13 | 1997-02-13 | Cement precast floor slab short line mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2282972Y true CN2282972Y (en) | 1998-06-03 |
Family
ID=33927011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 97207191 Expired - Fee Related CN2282972Y (en) | 1997-02-13 | 1997-02-13 | Cement precast floor slab short line mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2282972Y (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101402222B (en) * | 2008-11-12 | 2011-02-09 | 郎佃富 | Multi-ribbed beam hollow building roof composition board fixture mould |
CN107030859A (en) * | 2017-05-15 | 2017-08-11 | 中冶建工集团有限公司 | Structure of steel die |
CN112917653A (en) * | 2021-03-09 | 2021-06-08 | 湖北七杰新材料科技有限公司 | Prestressed concrete slab mould and manufacturing method thereof |
-
1997
- 1997-02-13 CN CN 97207191 patent/CN2282972Y/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101402222B (en) * | 2008-11-12 | 2011-02-09 | 郎佃富 | Multi-ribbed beam hollow building roof composition board fixture mould |
CN107030859A (en) * | 2017-05-15 | 2017-08-11 | 中冶建工集团有限公司 | Structure of steel die |
CN107030859B (en) * | 2017-05-15 | 2019-02-19 | 中冶建工集团有限公司 | Structure of steel die |
CN112917653A (en) * | 2021-03-09 | 2021-06-08 | 湖北七杰新材料科技有限公司 | Prestressed concrete slab mould and manufacturing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101487332B (en) | Prefabricated hollow superposed beam, and cast-in-situ construction method for beam and precast slab | |
CN102259388B (en) | Construction process for precasting prestressed pretensioned concrete U-shaped beams in rail transit | |
CN211517947U (en) | Bridge case roof beam is prefabricated with shaped steel pedestal | |
CN205875092U (en) | Arc foot rectangular cross section simple beam formula aqueduct | |
CN2282972Y (en) | Cement precast floor slab short line mould | |
CN201648978U (en) | Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam | |
CN209040349U (en) | A kind of ring muscle fastening shear wall structure being easily installed | |
CN108818912A (en) | Prefabricated guide hole pervious concrete road pavement brick and its production system and technique | |
CN2486596Y (en) | Assembled concrete beam making bench in site | |
CN216865231U (en) | Prefabricated assembly beam plate type fan foundation | |
CN201730626U (en) | Concrete casting sliding die of flat hole of tunnel | |
CN209703203U (en) | The prefabricated H-type sheet-pile combined track structure of rail traffic | |
CN213829507U (en) | Hollow nut block vertical casting mold | |
CN206477356U (en) | Mounting structure of the steel bar truss floor support plate in underground pipe gallery construction | |
CN201501749U (en) | Self-climbing type tower machine | |
CN201526157U (en) | Concrete floor shaping lateral formwork | |
CN2379280Y (en) | Combination type mould for producing concrete building stairs | |
CN220503695U (en) | V-shaped bridge pier template supporting system | |
CN2856262Y (en) | Support frame of formwork | |
CN219825847U (en) | Anchor hook type steel bar truss, steel bar truss set and truss plate | |
CN213951954U (en) | Cantilever adjusting device for prefabricating concrete T-shaped beam | |
CN218912239U (en) | Toilet pipe well caisson steel frame structure | |
CN207227912U (en) | Quick Release concrete road surface punching block | |
CN221920013U (en) | Anchored truss steel bars for non-disassembly truss floor decks | |
CN210947797U (en) | Novel deviation is prevented to prefabricated balcony board device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |