CN209227836U - Prefabricated concrete structure wall-column full steel key connection structure - Google Patents
Prefabricated concrete structure wall-column full steel key connection structure Download PDFInfo
- Publication number
- CN209227836U CN209227836U CN201821852295.5U CN201821852295U CN209227836U CN 209227836 U CN209227836 U CN 209227836U CN 201821852295 U CN201821852295 U CN 201821852295U CN 209227836 U CN209227836 U CN 209227836U
- Authority
- CN
- China
- Prior art keywords
- wall
- prefabricated
- column
- steel
- shear wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 79
- 239000010959 steel Substances 0.000 title claims abstract description 79
- 239000004567 concrete Substances 0.000 title claims abstract description 45
- 238000010008 shearing Methods 0.000 claims abstract 3
- 230000002787 reinforcement Effects 0.000 claims description 34
- UHOVQNZJYSORNB-UHFFFAOYSA-N Benzene Chemical compound C1=CC=CC=C1 UHOVQNZJYSORNB-UHFFFAOYSA-N 0.000 claims description 33
- 210000003205 muscle Anatomy 0.000 claims 16
- 238000005266 casting Methods 0.000 claims 1
- 239000000203 mixture Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 16
- 238000000034 method Methods 0.000 abstract description 14
- 238000009434 installation Methods 0.000 abstract description 6
- 230000008878 coupling Effects 0.000 abstract 2
- 238000010168 coupling process Methods 0.000 abstract 2
- 238000005859 coupling reaction Methods 0.000 abstract 2
- 238000004519 manufacturing process Methods 0.000 description 11
- 210000002435 tendon Anatomy 0.000 description 11
- 238000009415 formwork Methods 0.000 description 9
- 238000009826 distribution Methods 0.000 description 8
- 230000005540 biological transmission Effects 0.000 description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000003466 welding Methods 0.000 description 4
- 230000007613 environmental effect Effects 0.000 description 3
- 238000011900 installation process Methods 0.000 description 2
- 238000013475 authorization Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 229910052602 gypsum Inorganic materials 0.000 description 1
- 239000010440 gypsum Substances 0.000 description 1
- 239000011505 plaster Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000000452 restraining effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
Description
【技术领域】【Technical field】
本实用新型涉及预制装配式混凝土结构建筑领域,具体为一种装配式混凝土结构墙-柱全钢键连接结构。The utility model relates to the field of prefabricated assembled concrete structure buildings, in particular to an assembled concrete structure wall-column all-steel key connection structure.
【背景技术】【Background technique】
装配式混凝土结构具有施工速度快、节能环保、现场湿作业量小等优点,近些年在国内得到迅猛发展。混凝土框架-剪力墙结构(简称框剪结构)是我国目前应用的主要结构形式之一。因此,如何拆分连接框剪结构,形成装配式体系成为土木工程师关注的重要问题。以往有关墙-柱连接,主要采用钢筋连接然后在连接处浇筑混凝土或灌浆料的方法,施工需要湿作业,施工工艺繁琐,施工速度慢,且连接部位的质量不易保证。为此,发明人之前发明“一种装配式框剪结构弯剪型组合键槽连接结构”和“一种装配式混凝土框架剪力墙键槽连接结构”,并获得授权。上述两个专利,在处理构件间拼缝时,采用的是灌浆连接,需要湿作业,并且墙-柱连接处,限制二者脱开的能力较弱。为此,提出装配式混凝土结构墙-柱全钢键连接结构及拼装方法。The prefabricated concrete structure has the advantages of fast construction speed, energy saving and environmental protection, and small amount of wet work on site. It has developed rapidly in China in recent years. Concrete frame-shear wall structure (referred to as frame-shear structure) is one of the main structural forms currently used in my country. Therefore, how to disassemble the connected frame-shear structure and form an assembled system has become an important issue concerned by civil engineers. In the past, the wall-to-column connection was mainly connected by steel bars and then poured concrete or grout at the connection. The construction required wet work, the construction process was cumbersome, the construction speed was slow, and the quality of the connection was not easy to guarantee. For this reason, the inventor previously invented "a prefabricated frame-shear structure bending-shear composite keyway connection structure" and "a prefabricated concrete frame shear wall keyway connection structure" and obtained authorization. In the above two patents, when dealing with joints between components, grouting connection is used, which requires wet work, and the wall-column connection has a weak ability to limit the separation of the two. For this reason, a prefabricated concrete structure wall-column all-steel key connection structure and assembly method are proposed.
【实用新型内容】【Content of utility model】
本实用新型的目的在于提供一种装配式混凝土结构墙-柱全钢键连接结构,在保证各种预制混凝土构件间连接的前提下,完全不需要湿作业,大大提高施工速度及施工质量。The purpose of this utility model is to provide a prefabricated concrete structure wall-column all-steel key connection structure, under the premise of ensuring the connection between various prefabricated concrete components, no wet work is required at all, and the construction speed and construction quality are greatly improved.
本实用新型的技术方案:Technical scheme of the utility model:
一种装配式混凝土结构墙-柱全钢键连接结构,包括预制柱-墙预埋件、预制柱、预制剪力墙,预制剪力墙位于两个预制柱之间,预制柱与预制剪力墙之间的预制柱-墙预埋件相对应,相对设置的预制柱-墙预埋件之间通过工字型柱-墙连接键连接,其中:A prefabricated concrete structure wall-column all-steel key connection structure, including prefabricated column-wall embedded parts, prefabricated columns, and prefabricated shear walls. The prefabricated shear wall is located between two prefabricated columns. The prefabricated column-wall embedded parts between the walls correspond to each other, and the prefabricated column-wall embedded parts set oppositely are connected by the I-shaped column-wall connection key, where:
(1)预制柱-墙预埋件由带肋钢板和圆孔组成,带肋钢板的一侧上下平行设置横截面为L型的肋板,整块带肋钢板上设置圆孔,圆孔平行排布,剪力墙横向受力筋穿过圆孔,肋板分别与带肋钢板的侧面形成凹槽,上下两个凹槽相对;(1) The prefabricated column-wall embedded parts are composed of ribbed steel plates and round holes. One side of the ribbed steel plates is parallel to the upper and lower ribs with an L-shaped cross section. Round holes are set on the entire ribbed steel plate, and the round holes are parallel. Arrangement, the transverse stress bars of the shear wall pass through the round holes, the ribs form grooves with the sides of the ribbed steel plates respectively, and the upper and lower grooves are opposite;
(2)预制柱由预制柱内纵向受力筋、预制柱箍筋、竖向钢筋套筒和带肋钢板浇筑混凝土组成,呈方形排布的四个预制柱内纵向受力筋通过预制柱箍筋连接形成框架结构,每个预制柱内纵向受力筋的底部套装竖向钢筋套筒,所述框架结构的一侧面自上而下均匀设置预制柱-墙预埋件,混凝土浇筑于框架结构内侧和外侧;(2) The prefabricated column is composed of the longitudinal reinforcement in the prefabricated column, the prefabricated column stirrup, the vertical reinforcement sleeve and the ribbed steel plate pouring concrete. The reinforcement is connected to form a frame structure, and the bottom of the longitudinal reinforcement in each prefabricated column is equipped with a vertical reinforcement sleeve. One side of the frame structure is evenly equipped with prefabricated column-wall embedded parts from top to bottom, and the concrete is poured on the frame structure inside and outside;
(3)预制剪力墙包括钢筋骨架、预制柱-墙预埋件和混凝土,钢筋骨架的两侧分别设置预制柱-墙预埋件,混凝土浇筑于钢筋骨架内侧和外侧;钢筋骨架为剪力墙纵向受力筋、剪力墙横向受力筋、剪力墙约束边缘构件箍筋和剪力墙拉筋组成,两排剪力墙纵向受力筋平行相对设置,每排剪力墙纵向受力筋之间通过剪力墙横向受力筋连接,相对设置的剪力墙纵向受力筋之间通过剪力墙拉筋连接,两排剪力墙纵向受力筋的边缘之间外侧上下平行设置剪力墙约束边缘构件箍筋。(3) The prefabricated shear wall includes steel skeleton, prefabricated column-wall embedded parts and concrete. Prefabricated column-wall embedded parts are arranged on both sides of the steel skeleton, and concrete is poured on the inside and outside of the steel skeleton; the steel skeleton is the shear force Wall longitudinal stress tendons, shear wall transverse stress tendons, shear wall constrained edge member stirrups and shear wall tension bars, two rows of shear wall longitudinal stress tendons are arranged in parallel, each row of shear wall The tendons are connected by the transverse stress tendons of the shear wall, and the longitudinal tendons of the shear walls arranged oppositely are connected by the shear wall tension tendons, and the outer edges of the longitudinal stress tendons of the two rows of shear walls are parallel up and down Set up shear wall restraint edge member stirrups.
所述的装配式混凝土结构墙-柱全钢键连接结构,工字型柱-墙连接键4由竖向板、水平板、凸筋组成,竖向板的上下设置水平板呈工字型结构,位于上部的水平板顶部两端一体设置平行的凸筋,位于下部的水平板底部两端一体设置平行的凸筋,工字型柱-墙连接键4的两侧分别与预制柱-墙预埋件连接,工字型柱-墙连接键通过上下两个凸筋分别与预制柱-墙预埋件的上下两个凹槽插装配合。In the prefabricated concrete structure wall-column all-steel key connection structure, the I-shaped column-wall connection key 4 is composed of a vertical plate, a horizontal plate, and convex ribs, and the horizontal plates arranged above and below the vertical plate have an I-shaped structure The two ends of the top of the upper horizontal plate are integrally provided with parallel ribs, and the two ends of the bottom of the lower horizontal plate are integrally provided with parallel ribs, and the two sides of the I-shaped column-wall connection key 4 are respectively connected with the prefabricated column-wall For embedded parts connection, the I-shaped column-wall connection key is inserted and matched with the upper and lower grooves of the prefabricated column-wall embedded parts through the upper and lower convex ribs respectively.
所述的装配式混凝土结构墙-柱全钢键连接结构,预制柱与预制剪力墙间连接部位外侧设置盖板,盖板包括盖板横向分布筋、盖板纵向分布筋和钢垫板,一排平行相对的盖板横向分布筋和一排平行相对的盖板纵向分布筋组成钢筋骨架网。In the prefabricated concrete structure wall-column all-steel key connection structure, a cover plate is arranged on the outside of the connection between the prefabricated column and the prefabricated shear wall, and the cover plate includes the horizontal distribution ribs of the cover plate, the longitudinal distribution ribs of the cover plate and the steel backing plate, A row of parallel and opposite transverse distribution bars of the cover plate and a row of parallel and opposite cover plate longitudinal distribution bars form a reinforcement skeleton network.
所述的装配式混凝土结构墙-柱全钢键连接结构,钢垫板焊接在钢筋骨架网内某两根相邻盖板横向分布筋间,具体连接位置对应为预制柱与预制剪力墙间填充苯板中心。In the prefabricated concrete structure wall-column all-steel key connection structure, the steel backing plate is welded between two adjacent cover plates in the steel skeleton network, and the specific connection position corresponds to the prefabricated column and the prefabricated shear wall. Fill the center of the benzene board.
本实用新型的优点及有益效果是:Advantage and beneficial effect of the present utility model are:
1.本实用新型的主要工序不包括现场灌浆或混凝土浇筑等工序,全部工序都是预制构件的现场安装连接,不需要湿作业,大大缩短工地现场施工所需要的时间,能够极大的提高施工速度,节约成本。1. The main process of this utility model does not include on-site grouting or concrete pouring and other processes. All the processes are on-site installation and connection of prefabricated components, which does not require wet work, greatly shortens the time required for on-site construction, and can greatly improve construction. Speed and cost savings.
2.本实用新型预制柱和预制剪力墙,通过在预制剪力墙和预制柱连接部分设置预埋件和工字钢抗剪键,完成墙-柱间连接部分剪力的传递,进一步增强结构的整体性,抗震性能更好。2. The prefabricated column and prefabricated shear wall of the present utility model, by setting embedded parts and I-steel shear keys at the connection part of the prefabricated shear wall and the prefabricated column, completes the transmission of the shear force of the connection part between the wall and the column, and further enhances the The integrity of the structure, better seismic performance.
3.本实用新型制作精度要求高的部分,包括预制柱、预制剪力墙以及预制柱-墙预埋件、工字钢抗剪键的制作,均在工厂内完成。现场拼装的难度要求不高,能够节省施工人员的学习成本,大幅度提高施工效率。3. The parts of the utility model that require high manufacturing precision, including prefabricated columns, prefabricated shear walls, prefabricated column-wall embedded parts, and I-steel shear keys, are all completed in the factory. The difficulty of on-site assembly is not high, which can save the learning cost of construction personnel and greatly improve construction efficiency.
4.本实用新型构件间的传力,依靠预埋件的咬合和焊接,比单一依靠焊缝传力结构更加可靠。4. The force transmission between the components of the utility model depends on the occlusion and welding of the embedded parts, which is more reliable than the force transmission structure solely relying on the weld seam.
5.本实用新型采用大量的装配作业,比原始现浇作业大大减少,符合节能环保和经济安全的绿色建筑发展要求等装配式混凝土结构的优点。5. The utility model adopts a large number of assembly operations, which is greatly reduced compared with the original cast-in-place operation, and meets the advantages of the prefabricated concrete structure such as energy saving, environmental protection, economical and safe green building development requirements.
附图说明Description of drawings
图1是竖向钢筋套筒的三维图。Figure 1 is a three-dimensional view of a vertical reinforcement sleeve.
图2是预制柱-墙预埋件的三维图。Fig. 2 is a three-dimensional view of the prefabricated column-wall embedded parts.
图3是工字型柱-墙连接键的三维图。Fig. 3 is a three-dimensional view of the I-shaped column-wall connection key.
图4是预制柱内的钢筋布置三维图。Figure 4 is a three-dimensional diagram of the reinforcement arrangement in the prefabricated column.
图5是将预制柱-墙预埋件与预制柱内钢筋绑扎焊接完毕的三维图。Fig. 5 is a three-dimensional view of the binding and welding of the prefabricated column-wall embedded parts and the steel bars inside the prefabricated column.
图6是带预制柱-墙预埋件的预制柱的三维图。Fig. 6 is a three-dimensional view of a prefabricated column with a prefabricated column-wall embedded part.
图7是预制剪力墙内的钢筋布置三维图。Fig. 7 is a three-dimensional diagram of the reinforcement arrangement in the prefabricated shear wall.
图8是将预制柱-墙预埋件与预制剪力墙内钢筋绑扎焊接完毕的三维图。Fig. 8 is a three-dimensional view of the binding and welding of the prefabricated column-wall embedded parts and the steel bars in the prefabricated shear wall.
图9是带预制柱-墙预埋件的预制剪力墙的三维图。Fig. 9 is a three-dimensional view of a prefabricated shear wall with prefabricated column-wall embedded parts.
图10是吊装完毕后的带预制柱-墙预埋件预制柱与带预制柱-墙预埋件的预制剪力墙组合图。Figure 10 is a combination diagram of the prefabricated column with prefabricated column-wall embedded parts and the prefabricated shear wall with prefabricated column-wall embedded parts after hoisting is completed.
图11是将工字型柱-墙连接键安装于预制柱与预制剪力墙之间的预制柱-墙预埋件间的安装过程三维图。Fig. 11 is a three-dimensional view of the installation process between the prefabricated column-wall embedded parts between the I-shaped column-wall connection key installed between the prefabricated column and the prefabricated shear wall.
图12是预制柱与预制剪力墙间工字型柱-墙连接键组装完成时的三维图。Fig. 12 is a three-dimensional view when the assembly of the I-shaped column-wall connection key between the prefabricated column and the prefabricated shear wall is completed.
图13是预制柱与预制剪力墙间空隙填充用苯板。Figure 13 shows the benzene board used to fill the gap between the prefabricated column and the prefabricated shear wall.
图14是工字钢侧面凹陷空隙处填充用苯板。Figure 14 is a benzene plate for filling the recessed space on the side of the I-beam.
图15是图13安装于图12的过程三维图。Fig. 15 is a three-dimensional view of the process of Fig. 13 being installed in Fig. 12 .
图16是图14安装于图12的过程三维图。Fig. 16 is a three-dimensional view of the process of Fig. 14 being installed in Fig. 12 .
图17是预制柱与预制剪力墙间填充苯板安装完毕的三维图。Figure 17 is a three-dimensional view of the installed benzene-filled panels between the prefabricated columns and the prefabricated shear walls.
图18是盖板的钢筋布置三维图。Fig. 18 is a three-dimensional diagram of the reinforcement arrangement of the cover plate.
图19是盖板制作完成的三维图。Fig. 19 is a three-dimensional view of the completed cover plate.
图20是盖板安装过程的三维图。Fig. 20 is a three-dimensional view of the installation process of the cover plate.
图21是盖板安装完成的三维图。Fig. 21 is a three-dimensional view of the completed installation of the cover plate.
图22是盖板螺栓孔处涂抹石膏制作完成后的三维图。Fig. 22 is a three-dimensional view after the gypsum is applied to the bolt holes of the cover plate.
图中,1竖向钢筋套筒;2带肋钢板;3圆孔;4工字型柱-墙连接键;5钢筋预留缺口;6预制柱内纵向受力筋;7预制柱箍筋;8剪力墙纵向受力筋;9剪力墙横向受力筋;10剪力墙约束边缘构件箍筋;11剪力墙拉筋;12预制柱-墙间填充用苯板;13工字型柱-墙连接键填充用苯板;14钢垫板;15盖板纵向分布筋;16盖板横向分布筋;17盖板;18预制柱;19预制剪力墙;20肋板;21竖向板;22水平板;23凸筋。In the figure, 1 vertical reinforcement sleeve; 2 ribbed steel plate; 3 round hole; 4 I-shaped column-wall connection key; 8 longitudinal reinforcement of shear wall; 9 transverse reinforcement of shear wall; 10 stirrup of shear wall constraining edge member; 11 shear wall reinforcement; Benzene plate for column-wall connection key filling; 14 steel backing plate; 15 cover plate longitudinal distribution rib; 16 cover plate transverse distribution rib; 17 cover plate; 18 prefabricated column; 19 prefabricated shear wall; board; 22 horizontal boards; 23 ribs.
具体实施方式Detailed ways
如图1-图22所示,本实用新型装配式混凝土结构墙-柱全钢键连接结构,主要包括预制柱-墙预埋件、预制柱、预制剪力墙、预制连接部位盖板,以及用于上述构件间连接与填充的工字型柱-墙连接键和苯板等,预制柱与预制剪力墙之间的预制柱-墙预埋件相对应,相对设置的预制柱-墙预埋件之间通过工字型柱-墙连接键连接。As shown in Figure 1-Figure 22, the prefabricated concrete structure wall-column all-steel key connection structure of the utility model mainly includes prefabricated column-wall embedded parts, prefabricated columns, prefabricated shear walls, prefabricated connection part cover plates, and The I-shaped column-wall connection keys and benzene slabs used for the connection and filling between the above components, the prefabricated column and the prefabricated column-wall embedded parts between the prefabricated shear walls correspond, and the prefabricated column-wall prefabricated The embedded parts are connected by the I-shaped column-wall connection key.
(一)如图2所示,预制柱-墙预埋件具体结构及制作过程如下:(1) As shown in Figure 2, the specific structure and production process of prefabricated column-wall embedded parts are as follows:
(1)预制柱-墙预埋件由带肋钢板2和圆孔3组成,带肋钢板2的一侧上下平行设置横截面为L型的肋板20,整块带肋钢板上设置圆孔3,肋板20分别与带肋钢板2的侧面形成凹槽,上下两个凹槽相对。(1) The prefabricated column-wall embedded part is composed of a ribbed steel plate 2 and a round hole 3, one side of the ribbed steel plate 2 is set up and down in parallel with a rib plate 20 with an L-shaped cross section, and a round hole is set on the whole ribbed steel plate 3. The ribs 20 respectively form grooves with the sides of the ribbed steel plate 2, and the upper and lower grooves are opposite to each other.
如图3、图11和图12所示,工字型柱-墙连接键4由竖向板21、水平板22、凸筋23组成,竖向板21的上下设置水平板22呈工字型结构,位于上部的水平板22顶部两端一体设置平行的凸筋23,位于下部的水平板底部两端一体设置平行的凸筋,工字型柱-墙连接键4的两侧分别与预制柱-墙预埋件连接,工字型柱-墙连接键4通过上下两个凸筋分别与预制柱-墙预埋件的上下两个凹槽插装配合。另外,竖向板21的两侧上下端分别开设钢筋预留缺口5,工字型柱-墙连接键4装配后,可以向钢筋预留缺口5中穿设钢筋。As shown in Figure 3, Figure 11 and Figure 12, the I-shaped column-wall connection key 4 is composed of a vertical plate 21, a horizontal plate 22, and a rib 23, and the vertical plate 21 is provided with a horizontal plate 22 in an I-shaped shape. structure, the top ends of the upper horizontal plate 22 are integrally provided with parallel ribs 23, and the bottom ends of the lower horizontal plate are integrally provided with parallel ribs, and the two sides of the I-shaped column-wall connection key 4 are respectively connected with the -The connection of the wall embedded parts, the I-shaped column-wall connection key 4 is inserted and matched with the upper and lower grooves of the prefabricated column-wall embedded parts respectively through the upper and lower convex ribs. In addition, the upper and lower ends of both sides of the vertical plate 21 are respectively provided with reserved gaps 5 for steel bars. After the I-shaped column-wall connection key 4 is assembled, steel bars can be inserted into the reserved gaps 5 for steel bars.
(2)圆孔3的个数为4组8个,平行排布。圆孔3的直径为20mm,以保证剪力墙横向受力筋9能穿过圆孔3。(2) The number of round holes 3 is 8 in 4 groups, arranged in parallel. The diameter of the circular hole 3 is 20 mm, so as to ensure that the shear wall transverse force rib 9 can pass through the circular hole 3 .
(3)带肋钢板2的宽度需要比预制柱18(图6)和预制剪力墙19(图9)的宽度小20mm,防止连接钢板腐蚀的要求。(3) The width of the ribbed steel plate 2 needs to be 20mm smaller than the width of the prefabricated column 18 (Fig. 6) and the prefabricated shear wall 19 (Fig. 9) to prevent corrosion of the connecting steel plate.
(4)工字型柱-墙连接键4(图3)的数量根据其所连接的剪力墙和柱间传递的剪力计算确定的。(4) The number of I-shaped column-wall connection keys 4 (Fig. 3) is calculated and determined according to the shear force transmitted between the connected shear walls and columns.
(二)如图1、图4至图6所示,预制柱的具体结构及制作过程分别如下:(2) As shown in Figure 1, Figure 4 to Figure 6, the specific structure and manufacturing process of the prefabricated columns are as follows:
(1)预制柱18由预制柱内纵向受力筋6、预制柱箍筋7、竖向钢筋套筒1和带肋钢板2浇筑混凝土组成,呈方形排布的四个预制柱内纵向受力筋6通过预制柱箍筋7连接形成框架结构,每个预制柱内纵向受力筋6的底部套装竖向钢筋套筒1,所述框架结构的一侧面自上而下均匀设置预制柱-墙预埋件,混凝土浇筑于框架结构内侧和外侧。(1) The prefabricated column 18 is composed of the longitudinal stress bars 6 in the prefabricated column, the prefabricated column hoops 7, the vertical reinforcement sleeve 1 and the ribbed steel plate 2 pouring concrete, and the four prefabricated columns arranged in a square shape are longitudinally stressed The ribs 6 are connected by prefabricated column stirrups 7 to form a frame structure, and the bottom of each prefabricated column's inner longitudinal tendons 6 is covered with a vertical reinforcement sleeve 1, and one side of the frame structure is uniformly arranged with prefabricated columns-walls from top to bottom Embedded parts, concrete poured on the inside and outside of the frame structure.
(2)预制柱18的制作过程为:首先,将预制柱内纵向受力筋6的下端插入竖向钢筋套筒1,然后绑扎预制柱箍筋7,完成预制柱内的钢筋布置。(2) The manufacturing process of the prefabricated column 18 is as follows: firstly, insert the lower end of the longitudinal reinforcement 6 in the prefabricated column into the vertical reinforcement sleeve 1, and then bind the stirrups 7 of the precast column to complete the reinforcement arrangement in the prefabricated column.
预制柱内纵向受力筋6的上端应该预留一部分,预留部分的长度应为预制柱竖向钢筋套筒1高度的一半。A portion of the upper end of the longitudinal reinforcement 6 in the prefabricated column should be reserved, and the length of the reserved portion should be half the height of the vertical reinforcement sleeve 1 of the prefabricated column.
将预制柱-墙预埋件通过孔洞用钢丝固定在预制柱箍筋7上,预制柱-墙预埋件的个数根据预制剪力墙19和预制柱18之间需要传递的剪力计算确定,并沿预制柱18高度方向均匀分布。Fix the prefabricated column-wall embedded parts on the prefabricated column stirrups 7 with steel wires through the holes, and the number of prefabricated column-wall embedded parts is determined according to the shear force calculation that needs to be transmitted between the prefabricated shear wall 19 and the prefabricated column 18 , and distribute evenly along the height direction of the prefabricated columns 18.
在预制柱18内的钢筋外支撑模板,浇筑混凝土,混凝土在模板内应浇筑至预制柱-墙预埋件的外侧表面,混凝土凝固后拆除模板,完成预制柱的制作。The formwork is supported outside the steel bars in the prefabricated column 18, and concrete is poured. The concrete should be poured in the formwork to the outer surface of the prefabricated column-wall embedded part. After the concrete is solidified, the formwork is removed to complete the production of the prefabricated column.
(三)如图7至图9所示,预制剪力墙19的具体结构及制作过程分别如下:(3) As shown in Figures 7 to 9, the concrete structure and manufacturing process of the prefabricated shear wall 19 are as follows:
(1)预制剪力墙19主要包括钢筋骨架、预制柱-墙预埋件和混凝土,钢筋骨架的两侧分别设置预制柱-墙预埋件,混凝土浇筑于钢筋骨架内侧和外侧;钢筋骨架为剪力墙纵向受力筋8、剪力墙横向受力筋9、剪力墙约束边缘构件箍筋10和剪力墙拉筋11组成,两排剪力墙纵向受力筋8平行相对设置,每排剪力墙纵向受力筋8之间通过剪力墙横向受力筋9连接,相对设置的剪力墙纵向受力筋8之间通过剪力墙拉筋11连接,两排剪力墙纵向受力筋8的边缘之间外侧上下平行设置剪力墙约束边缘构件箍筋10。(1) The prefabricated shear wall 19 mainly includes steel reinforcement skeleton, prefabricated column-wall embedded parts and concrete, prefabricated column-wall embedded parts are respectively arranged on both sides of the steel reinforcement skeleton, and concrete is poured on the inside and outside of the steel reinforcement skeleton; the steel reinforcement skeleton is The shear wall longitudinal stress bars 8, the shear wall transverse stress bars 9, the shear wall constraining edge member stirrups 10 and the shear wall tension bars 11, two rows of shear wall longitudinal stress bars 8 are arranged parallel to each other, The longitudinal stress bars 8 of each row of shear walls are connected by the transverse stress bars 9 of the shear walls, and the longitudinal stress bars 8 of the opposite shear walls are connected by the shear wall tension bars 11. The two rows of shear walls Between the edges of the longitudinal tendons 8, stirrups 10, which are edge members constrained by shear walls, are arranged in parallel up and down on the outside.
(2)预制剪力墙的制作过程为:首先绑扎剪力墙纵向受力筋8和剪力墙约束边缘构件箍筋10,形成约束边缘构件钢筋,然后绑扎其余剪力墙纵向受力筋和剪力墙横向受力筋9,最后绑扎剪力墙拉筋11,形成预制剪力墙内的钢筋。(2) The manufacturing process of the prefabricated shear wall is as follows: firstly bind the longitudinal stress bars 8 of the shear wall and the stirrups 10 of the constrained edge members of the shear wall to form the reinforcing bars of the constrained edge members, and then bind the remaining longitudinal tendons of the shear wall and The transverse stress bars 9 of the shear wall, and finally the shear wall tension bars 11 are bound to form the steel bars in the prefabricated shear wall.
预制柱-墙预埋件是通过绑扎钢丝固定在剪力墙侧面的,绑扎钢丝穿过预制柱-墙预埋件上面的预留圆形孔洞绑扎在预制剪力墙内约束边缘构件箍筋上,墙横向均匀分布在两侧区域。The prefabricated column-wall embedded parts are fixed on the side of the shear wall by binding steel wires, and the binding steel wires pass through the reserved circular holes on the prefabricated column-wall embedded parts and are bound to the stirrups of the restraining edge members in the prefabricated shear wall , the walls are evenly distributed in the two side regions laterally.
在钢筋骨架外侧支模板,浇筑混凝土,混凝土在模板内应浇筑至柱墙预埋件的外侧表面。混凝土凝固后拆除模板,完成预制剪力墙的制作。The formwork is supported on the outside of the steel skeleton, and concrete is poured, and the concrete should be poured in the formwork to the outer surface of the embedded part of the column wall. After the concrete is solidified, the formwork is removed to complete the production of the prefabricated shear wall.
(四)如图18至图19所示,预制柱与剪力墙间连接部位外侧盖板的具体结构及制作过程如下:(4) As shown in Figure 18 to Figure 19, the specific structure and manufacturing process of the outer cover plate at the connection between the prefabricated column and the shear wall are as follows:
(1)预制柱18与预制剪力墙19间连接部位外侧设置盖板17,盖板17包括盖板横向分布筋16、盖板纵向分布筋15和钢垫板14,一排平行相对的盖板横向分布筋16和一排平行相对的盖板纵向分布筋15组成钢筋骨架网。而钢垫板14则是焊接在钢筋骨架网内某两根相邻盖板横向分布筋16间,具体连接位置对应为预制柱18与预制剪力墙19间填充苯板中心。(1) A cover plate 17 is arranged on the outside of the connection between the prefabricated column 18 and the prefabricated shear wall 19. The cover plate 17 includes the horizontal distribution ribs 16 of the cover plate, the longitudinal distribution ribs 15 of the cover plate and the steel backing plate 14, and a row of parallel and opposite cover plates The plate transversely distributed ribs 16 and a row of parallel and opposite cover plate longitudinally distributed ribs 15 form a reinforcement skeleton network. The steel backing plate 14 is welded between the transversely distributed ribs 16 of two adjacent cover plates in the steel skeleton network, and the specific connection position corresponds to the center of the benzene plate filled between the prefabricated column 18 and the prefabricated shear wall 19 .
(2)预制柱18与预制剪力墙19间连接部位外侧盖板的制作过程为:首先绑扎盖板横向分布筋16、盖板纵向分布筋15形成钢筋骨架网,然后焊接钢垫板14,在钢筋骨架网外侧支模板,浇筑混凝土,混凝土在模板内应浇筑至钢筋骨架网外侧表面。混凝土凝固后拆除模板,完成预制柱与剪力墙间连接部位外侧盖板的制作。(2) The manufacturing process of the outer cover plate at the connection between the prefabricated column 18 and the prefabricated shear wall 19 is as follows: firstly, the laterally distributed ribs 16 of the cover plate and the longitudinally distributed ribs 15 of the cover plate are bound to form a steel skeleton network, and then the steel backing plate 14 is welded. The formwork is supported on the outside of the steel skeleton net, and concrete is poured, and the concrete should be poured to the outer surface of the steel skeleton net in the formwork. After the concrete is solidified, the formwork is removed, and the outer cover plate of the joint between the precast column and the shear wall is completed.
上述预制构件在工厂内预制完成,然后运输到施工现场组装,具体吊装过程如下:The above prefabricated components are prefabricated in the factory and then transported to the construction site for assembly. The specific hoisting process is as follows:
(一)如图10所示,预制柱与预制剪力墙的吊装,先将两个预制柱18与一个预制剪力墙19吊装到位,预制剪力墙19位于两个预制柱18之间。(1) As shown in Figure 10, for the hoisting of prefabricated columns and prefabricated shear walls, two prefabricated columns 18 and a prefabricated shear wall 19 are first hoisted in place, and the prefabricated shear wall 19 is located between the two prefabricated columns 18.
(二)如图11至图12所示,在预制柱18内预制柱-墙预埋件与预制剪力墙内预制柱-墙预埋件间对应插入工字型柱-墙连接键4,使预制柱内预制柱-墙预埋件与预制剪力墙内预制柱-墙预埋件和工字型柱-墙连接键4紧密接触,而后进行焊接,完成预制柱18与预制剪力墙19之间连接键的连接。(2) As shown in Figures 11 to 12, the I-shaped column-wall connection key 4 is correspondingly inserted between the prefabricated column-wall embedded parts in the prefabricated column 18 and the prefabricated column-wall embedded parts in the prefabricated shear wall, The prefabricated column-wall embedded parts in the prefabricated column are in close contact with the prefabricated column-wall embedded parts in the prefabricated shear wall and the I-shaped column-wall connection key 4, and then welded to complete the prefabricated column 18 and the prefabricated shear wall 19 connections between connecting keys.
(三)如图13至图17所示,在预制柱-墙预埋件与预制柱18和预制剪力墙19之间空隙内随形插入预制柱-墙间填充用苯板12,而后对应随形安装工字型柱-墙连接键4侧面的工字型柱-墙连接键填充用苯板13,完成预制柱18和预制剪力墙19连接部位内空余位置苯板的连接。(3) As shown in Figures 13 to 17, insert prefabricated column-wall inter-filling benzene plates 12 into the gap between the prefabricated column-wall embedded parts and prefabricated column 18 and prefabricated shear wall 19, and then correspond The I-shaped column-wall connection key 4 side of the I-shaped column-wall connection key 4 side is installed along the shape with the benzene plate 13 for filling, and the connection of the benzene plate in the vacant position in the prefabricated column 18 and the prefabricated shear wall 19 connection part is completed.
(四)在预制柱18和预制剪力墙19连接部位对应位置外安装预制柱与剪力墙间连接部位外侧盖板17,先将预制柱18和预制剪力墙19间连接部位外侧盖板放置在连接部位对应空缺位置,而后用穿插钢筋依次穿过前后两个对应的预制柱18和预制剪力墙19间连接部位外侧盖板上的钢垫板14,再用螺母固定穿插钢筋的两端,完成柱与剪力墙间连接部位外侧盖板17的固定安装。其中,穿插钢筋的长度应为前后对应的剪力墙间连接部位外侧盖板上的钢垫板14外侧表面间距离加两侧对应固定螺母的厚度。(4) Install the outer cover plate 17 of the connection part between the prefabricated column and the shear wall outside the corresponding position of the connection part of the prefabricated column 18 and the prefabricated shear wall 19, and first install the outer cover plate of the connection part between the prefabricated column 18 and the prefabricated shear wall Place it in the corresponding vacant position of the connection part, and then pass through the steel backing plate 14 on the outer cover plate of the connection part between the front and rear corresponding prefabricated columns 18 and prefabricated shear walls 19 with interspersed steel bars, and then fix the two interspersed steel bars with nuts Complete the fixed installation of the outer cover plate 17 at the joint between the column and the shear wall. Among them, the length of interspersed steel bars should be the distance between the outer surfaces of the steel backing plate 14 on the outer cover plate of the connection between the front and rear corresponding shear walls plus the thickness of the corresponding fixing nuts on both sides.
(五)如图18至图22所示,在所有完成固定安装后的柱与剪力墙间连接部位外侧盖板17上的钢垫板14凹陷处抹石膏,使凹陷处平整,完成预制柱与预制剪力墙之间的连接。(5) As shown in Figure 18 to Figure 22, plaster is applied to the depression of the steel backing plate 14 on the outer cover plate 17 of the connection between the column and the shear wall after all the fixed installations have been completed, so that the depression is flat and the prefabricated column is completed Connections with prefabricated shear walls.
实施结果表明,本实用新型的主要工序不包括现场灌浆或混凝土浇筑等工序,全部工序都是预制构件的现场安装连接,不需要湿作业,大大缩短工地现场施工所需要的时间,能够极大的提高施工速度,节约成本。预制柱和预制剪力墙,通过在预制剪力墙和预制柱连接部分设置预制柱-墙预埋件和工字型柱-墙连接键,完成墙-柱间连接部分剪力的传递,进一步增强结构的整体性,抗震性能更好。制作精度要求高的部分,包括预制柱、预制剪力墙以及预制柱-墙预埋件、工字钢抗剪键的制作,均在工厂内完成。现场拼装的难度要求不高,能够节省施工人员的学习成本,大幅度提高施工效率。本实用新型构件间的传力,依靠预埋件的咬合和焊接,比单一依靠焊缝传力结构更加可靠。采用大量的装配作业,比原始现浇作业大大减少,符合节能环保和经济安全的绿色建筑发展要求等装配式混凝土结构的优点,具有较好的工程应用前景。The results of implementation show that the main process of the utility model does not include processes such as on-site grouting or concrete pouring, and all processes are on-site installation and connection of prefabricated components. Improve construction speed and save costs. For prefabricated columns and prefabricated shear walls, by setting prefabricated column-wall embedded parts and I-shaped column-wall connection keys at the connection part of prefabricated shear walls and prefabricated columns, the shear force transmission of the wall-column connection part is completed, and further The integrity of the structure is enhanced, and the seismic performance is better. The parts that require high manufacturing precision, including prefabricated columns, prefabricated shear walls, prefabricated column-wall embedded parts, and I-beam shear keys, are all completed in the factory. The difficulty of on-site assembly is not high, which can save the learning cost of construction personnel and greatly improve construction efficiency. The force transmission between the components of the utility model relies on the occlusion and welding of the embedded parts, which is more reliable than the force transmission structure solely relying on weld seams. It adopts a large number of assembly operations, which is greatly reduced compared with the original cast-in-place operation, and meets the advantages of the prefabricated concrete structure such as energy-saving, environmental protection, economical and safe green building development requirements, and has good engineering application prospects.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821852295.5U CN209227836U (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column full steel key connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821852295.5U CN209227836U (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column full steel key connection structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209227836U true CN209227836U (en) | 2019-08-09 |
Family
ID=67502606
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821852295.5U Expired - Fee Related CN209227836U (en) | 2018-11-09 | 2018-11-09 | Prefabricated concrete structure wall-column full steel key connection structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209227836U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109281422A (en) * | 2018-11-09 | 2019-01-29 | 沈阳建筑大学 | Prefabricated concrete structure wall-column all-steel key connection structure and assembly method |
CN110541500A (en) * | 2019-09-30 | 2019-12-06 | 陕西省建筑科学研究院有限公司 | fabricated shear wall structure and construction method |
CN113863756A (en) * | 2021-11-15 | 2021-12-31 | 东莞理工学院 | Three-phase adjacent structure damping control system suitable for building compact area |
-
2018
- 2018-11-09 CN CN201821852295.5U patent/CN209227836U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109281422A (en) * | 2018-11-09 | 2019-01-29 | 沈阳建筑大学 | Prefabricated concrete structure wall-column all-steel key connection structure and assembly method |
CN110541500A (en) * | 2019-09-30 | 2019-12-06 | 陕西省建筑科学研究院有限公司 | fabricated shear wall structure and construction method |
CN110541500B (en) * | 2019-09-30 | 2024-03-15 | 陕西省建筑科学研究院有限公司 | Assembled shear wall structure and construction method |
CN113863756A (en) * | 2021-11-15 | 2021-12-31 | 东莞理工学院 | Three-phase adjacent structure damping control system suitable for building compact area |
CN113863756B (en) * | 2021-11-15 | 2022-09-13 | 东莞理工学院 | Three-phase adjacent structure damping control system suitable for building compact area |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106968381B (en) | Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves | |
CN105839846A (en) | Prefabricated reinforced concrete composite beam | |
CN209457194U (en) | Vertical connection structure of steel rib dislocation butt joint shear wall | |
CN107401217B (en) | A kind of beamless hollow floor-chamber concrete-filled steel tube shear wall combined structure system and method | |
CN106193292A (en) | A kind of steel frame assembled integral reinforced concrete shear wall structure system | |
CN108797840A (en) | Prefabricated concrete shear force wall assembled connected node | |
CN108086488B (en) | Assembled frame shear structure wall staggered connection structure and assembling method | |
CN113653235A (en) | Laminated slab, connecting structure of laminated slab and combination beam and construction method | |
CN209227836U (en) | Prefabricated concrete structure wall-column full steel key connection structure | |
CN108301531A (en) | Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node | |
CN110748077A (en) | Prestressed truss wallboard, wall body manufactured by using wallboard and manufacturing method of wall body | |
CN103741877A (en) | Lattice anti-shearing device-steel-profiled steel plate-renewable concrete combination beam and production method | |
CN111663681A (en) | Assembled wall body connecting structure and construction method thereof | |
CN111335464A (en) | A beam-column connection node of a prefabricated concrete structure and its construction method | |
CN109267585B (en) | Assembled prismatic table type foundation and column structure and assembling method | |
CN105952044B (en) | Fully-prefabricated prestressed concrete floor structure and prestressed assembly method | |
CN110761443A (en) | Prefabricated concrete structure wall-column concrete-filled steel tubular key connection structure and its assembling method | |
CN206189590U (en) | Full precast prestressed assembly structure | |
CN109555252B (en) | Floor slab with rectangular ribs extending outwards, shear wall structure and connecting method | |
CN111749365A (en) | A prefabricated composite wall based on H-beam and its construction method | |
CN108104310B (en) | Assembled frame shear structure column staggered connection structure and assembling method | |
CN205224332U (en) | Prefabricated wall body and prefabricated wallboard | |
CN216195649U (en) | Assembled composite wall perps connection structure based on H shaped steel | |
CN110644662A (en) | Prefabricated flat slab composite slab based on stress and splitting method thereof | |
CN109281422A (en) | Prefabricated concrete structure wall-column all-steel key connection structure and assembly method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190809 Termination date: 20191109 |