CN105839846A - Prefabricated reinforced concrete composite beam - Google Patents
Prefabricated reinforced concrete composite beam Download PDFInfo
- Publication number
- CN105839846A CN105839846A CN201610165145.6A CN201610165145A CN105839846A CN 105839846 A CN105839846 A CN 105839846A CN 201610165145 A CN201610165145 A CN 201610165145A CN 105839846 A CN105839846 A CN 105839846A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- reinforced concrete
- precast
- concrete composite
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/20—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/20—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
- E04C3/22—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members built-up by elements jointed in line
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
预制装配式钢筋混凝土叠合梁,它涉及一种钢筋混凝土叠合梁。本发明解决了现有的预制梁、柱之间的连接存在断开界面,连接节点处的传力受力较大以及施工周期长问题。预制钢筋混凝土梁柱节点的梁段与柱段一体浇注制成,位于梁下部的纵向钢筋沿预制梁的长度方向预埋,位于梁上部的纵向钢筋需待预埋钢连接件安装后再进行布设和绑扎,多个筋箍沿预制梁的长度方向依次预埋在预制梁上,多个筋箍的上部外露在预制梁的两个顶面平台上,预制梁的两端分别预埋有一个预埋钢连接件,预制梁两端的预埋型钢连接件与预制钢筋混凝土梁柱节点通过高强螺栓固接,预制梁与预制钢筋混凝土梁柱节点的梁段通过二次浇筑形成完整的钢筋混凝土叠合梁。本发明用于建筑结构梁。
A prefabricated reinforced concrete composite beam relates to a reinforced concrete composite beam. The invention solves the problems of disconnected interface existing in the connection between the existing prefabricated beams and columns, large force transmission and stress at the connection node and long construction period. The beam section and the column section of the prefabricated reinforced concrete beam-column joint are made by integral casting. The longitudinal reinforcement located at the lower part of the beam is pre-embedded along the length direction of the prefabricated beam. The longitudinal reinforcement located at the upper part of the beam needs to be laid after the pre-embedded steel connector is installed and binding, a plurality of hoops are pre-embedded on the prefabricated beam sequentially along the length direction of the prefabricated beam, the upper parts of the multiple hoops are exposed on the two top platforms of the prefabricated beam, and a prefabricated hoop is embedded at both ends of the prefabricated beam respectively. Embedded steel connectors, the pre-embedded steel connectors at both ends of the prefabricated beam and the prefabricated reinforced concrete beam-column joints are fixed by high-strength bolts, and the beam sections of the prefabricated beams and the prefabricated reinforced concrete beam-column joints form a complete reinforced concrete superposition through secondary pouring beam. The invention is used for building structural beams.
Description
技术领域technical field
本发明涉及一种建筑结构梁,具体涉及一种预制装配式钢筋混凝土叠合梁。The invention relates to a building structure beam, in particular to a prefabricated assembled reinforced concrete composite beam.
背景技术Background technique
预制装配式混凝土结构是以预制构件为主要受力构件,并经装配连接而成的混凝土结构。其良好的产品质量、较高的生产效率、优越的环境效益等优点,使之得到国际上的广泛应用,并逐渐成为我国建筑结构发展的重要方向之一。目前采用的预制装配式混凝土结构体系,其梁、柱构件在工厂预制,梁、柱连接采用现场浇筑。预制梁的连接部位非常靠近梁跨的两端,上述结构存在以下不足:一、预制梁连接部位的混凝土现场浇筑,需要等待节点混凝土达到规定强度才可进行后续施工,延迟了施工周期,且浇筑质量与工厂的浇筑质量相比较差;二、由于预制梁、柱之间的连接存在断开界面,不利于连接节点处的传力。为了保证梁柱刚性连接,需单独采取加强措施,因此加大了设计和施工难度。The prefabricated concrete structure is a concrete structure made of prefabricated components as the main force-bearing components and connected by assembly. Its good product quality, high production efficiency, superior environmental benefits and other advantages make it widely used in the world, and gradually become one of the important directions for the development of building structures in our country. In the prefabricated concrete structure system currently used, the beam and column components are prefabricated in the factory, and the beam and column connections are cast on site. The connection part of the prefabricated beam is very close to the two ends of the beam span. The above-mentioned structure has the following disadvantages: 1. The concrete at the connection part of the prefabricated beam needs to wait for the joint concrete to reach the specified strength before subsequent construction can be carried out, which delays the construction period and the pouring The quality is poor compared with the pouring quality of the factory; Second, due to the disconnected interface between the prefabricated beams and columns, it is not conducive to the force transmission at the connection nodes. In order to ensure the rigid connection of beams and columns, strengthening measures need to be taken separately, which increases the difficulty of design and construction.
综上,现有的预制梁、柱之间的连接存在断开界面,连接节点处的传力受力较大以及施工周期长。To sum up, the existing prefabricated beams and columns have disconnected interfaces, the force transmission and stress at the connection nodes are relatively large, and the construction period is long.
发明内容Contents of the invention
本发明为解决现有的预制梁、柱之间的连接存在断开界面,连接节点处的传力受力较大以及施工周期长的问题,进而提供一种预制装配式钢筋混凝土叠合梁。The invention aims to solve the problems of disconnected interfaces in the connection between existing prefabricated beams and columns, large force transmission and stress at connection nodes and long construction period, and further provides a prefabricated assembled reinforced concrete composite beam.
本发明为解决上述技术问题采取的技术方案是:The technical scheme that the present invention takes for solving the problems of the technologies described above is:
本发明的预制装配式钢筋混凝土叠合梁包括预制梁、预埋钢连接件、多个纵向钢筋、多个筋箍和两个预制钢筋混凝土梁柱节点,预制钢筋混凝土梁柱节点的梁段与柱段一体浇注制成,位于梁下部的纵向钢筋沿预制梁的长度方向预埋,位于梁上部的纵向钢筋需待预埋钢连接件安装完成后再进行布设和绑扎,多个筋箍沿预制梁的长度方向依次预埋在预制梁上,多个筋箍的上部外露在预制梁的两个顶面平台上,预制梁的两端分别预埋有一个预埋钢连接件,预制梁两端的预埋型钢连接件与预制钢筋混凝土梁柱节点通过高强螺栓固接,预制梁与预制钢筋混凝土梁柱节点的梁段通过二次浇筑形成完整的钢筋混凝土叠合梁。The prefabricated assembled reinforced concrete composite beam of the present invention comprises a prefabricated beam, a pre-embedded steel connector, a plurality of longitudinal steel bars, a plurality of hoops and two prefabricated reinforced concrete beam-column nodes, and the beam sections of the prefabricated reinforced concrete beam-column nodes are connected to The column section is cast in one piece. The longitudinal reinforcement located at the lower part of the beam is embedded along the length direction of the prefabricated beam. The longitudinal reinforcement located at the upper part of the beam needs to be laid and bound after the installation of the embedded steel connectors. The length direction of the beam is pre-embedded on the prefabricated beam sequentially. The upper parts of multiple hoops are exposed on the two top platforms of the prefabricated beam. A pre-embedded steel connector is pre-embedded at both ends of the prefabricated beam. The pre-embedded steel connectors and prefabricated reinforced concrete beam-column joints are fixed by high-strength bolts, and the beam sections of prefabricated beams and prefabricated reinforced concrete beam-column joints form a complete reinforced concrete composite beam through secondary pouring.
本发明与现有技术相比具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
本发明的预制装配式钢筋混凝土叠合梁由预制梁与预制钢筋混凝土梁柱节点的梁段通过二次浇筑形成完整的钢筋混凝土叠合梁,与现有的钢筋混凝土梁直接与柱连接相比,预制梁与预制节点连接位置受力小,连接位置靠近地震作用组合下的反弯点,避开了受力较为复杂的梁柱节点区域,因此构件自身工作性能和结构抗震性能易保证;The prefabricated assembled reinforced concrete composite beam of the present invention forms a complete reinforced concrete composite beam through the secondary pouring of the beam section of the prefabricated beam and the prefabricated reinforced concrete beam-column joint, compared with the existing reinforced concrete beam directly connected to the column , the connection position of prefabricated beam and prefabricated joint is less stressed, and the joint position is close to the inflection point under the combination of seismic action, avoiding the beam-column joint area with more complicated stress, so the working performance of the component itself and the seismic performance of the structure are easy to guarantee;
本发明的预制梁的吊装可实现无支撑化施工,施工效率高、成本低;本发明的预制梁可通过两个预埋钢连接件实现快速定位安装,安装后则可作为支撑安装预制叠合板或预制墙等构件,施工全过程预制梁与预制叠合板无需额外支撑;The hoisting of the prefabricated beam of the present invention can realize unsupported construction with high construction efficiency and low cost; the prefabricated beam of the present invention can be quickly positioned and installed through two pre-embedded steel connectors, and can be used as a support to install prefabricated laminated panels after installation Or prefabricated walls and other components, prefabricated beams and prefabricated laminated panels do not need additional support during the whole construction process;
本发明的现场湿作业量少,能极大程度地减少人工操作以及对环境的影响,产品的制作及安装机械化程度高、质量好、效率高、经济性好。The present invention has less on-site wet work, can greatly reduce manual operations and the impact on the environment, and has high mechanization degree in production and installation of products, good quality, high efficiency and good economy.
附图说明Description of drawings
图1是本发明的预制装配式钢筋混凝土叠合梁的整体结构立体图;Fig. 1 is the overall structure perspective view of prefabricated assembly type reinforced concrete composite beam of the present invention;
图2是本发明的预制装配式钢筋混凝土叠合梁的整体结构装配示意图;Fig. 2 is the overall structural assembly schematic diagram of the prefabricated assembled reinforced concrete composite beam of the present invention;
图3是本发明具体实施方式一中预制梁1的立体图;Fig. 3 is a perspective view of the prefabricated beam 1 in Embodiment 1 of the present invention;
图4是图3的主剖视图;Fig. 4 is the main sectional view of Fig. 3;
图5是图3的左视图;Fig. 5 is the left view of Fig. 3;
图6是本发明具体实施方式一中钢筋混凝土柱与预制钢筋混凝土梁柱节点的立体图。Fig. 6 is a perspective view of a joint between a reinforced concrete column and a prefabricated reinforced concrete beam-column in Embodiment 1 of the present invention.
具体实施方式detailed description
具体实施方式一:如图1~6所示,本实施方式的预制装配式钢筋混凝土叠合梁包括预制梁1、预埋钢连接件2、多个纵向钢筋3、多个筋箍4和两个预制钢筋混凝土梁柱节点,预制钢筋混凝土梁柱节点的梁段与柱段一体浇注制成,位于梁下部的纵向钢筋3沿预制梁1的长度方向预埋,位于梁上部的纵向钢筋3需待预埋钢连接件2安装完成后再进行布设和绑扎,多个筋箍4沿预制梁1的长度方向依次预埋在预制梁1上,多个筋箍4的上部外露在预制梁1的两个顶面平台1-2上,预制梁1的两端分别预埋有一个预埋钢连接件2,预制梁1两端的预埋型钢连接件2与预制钢筋混凝土梁柱节点通过高强螺栓固接,预制梁1与预制钢筋混凝土梁柱节点的梁段通过二次浇筑形成完整的钢筋混凝土叠合梁。Specific Embodiment 1: As shown in Figures 1 to 6, the prefabricated reinforced concrete composite beam of this embodiment includes a prefabricated beam 1, a pre-embedded steel connector 2, a plurality of longitudinal reinforcement bars 3, a plurality of hoops 4 and two A prefabricated reinforced concrete beam-column joint, the beam section and the column section of the prefabricated reinforced concrete beam-column joint are made by integral casting, the longitudinal reinforcement 3 located at the lower part of the beam is pre-buried along the length direction of the prefabricated beam 1, and the longitudinal reinforcement 3 located at the upper part of the beam needs to be After the installation of the pre-embedded steel connector 2 is completed, laying and binding are carried out. A plurality of hoops 4 are pre-embedded on the precast beam 1 in sequence along the length direction of the prefabricated beam 1, and the upper parts of the plurality of hoops 4 are exposed on the prefabricated beam 1. On the two top platforms 1-2, a pre-embedded steel connector 2 is pre-embedded at both ends of the prefabricated beam 1. Next, the prefabricated beam 1 and the beam section of the prefabricated reinforced concrete beam-column joint form a complete reinforced concrete composite beam through secondary pouring.
预制梁1吊装时型钢连接对准校正后,下沉就位,连接好高强螺栓即可承受施工荷载,后续施工无需支撑。When the prefabricated beam 1 is hoisted, after the steel connection is aligned and corrected, it sinks in place, and the high-strength bolts are connected to bear the construction load, and subsequent construction does not need support.
本发明所指预制钢筋混凝土梁柱节点在工厂预制为一体,预制梁1在工厂预制加工,预制梁与预制节点通过梁中的预埋T型钢拼接,并用高强螺栓固定,以此承受施工荷载,然后连接梁的纵筋;型钢连接、纵筋连接和二次浇筑完成后形成完整的钢筋混凝土梁;本发明预制节点在工厂制作时,只绑扎梁下部纵筋与箍筋形成钢筋骨架,梁上部纵筋留至现场穿筋及连接;在梁端埋设T型钢并支模,随后浇筑混凝土形成预制梁;运至施工现场后,通过型钢连接头与预制节点进行定位和安装,随后采用机械连接头连接梁纵筋,接着再安装完成的预制梁上安装预制楼板;最后进行连接接头和叠合板的二次浇筑完成本层梁板施工。The prefabricated reinforced concrete beam-column joints referred to in the present invention are prefabricated as a whole in the factory, and the prefabricated beam 1 is prefabricated and processed in the factory. The prefabricated beams and the prefabricated joints are spliced through the pre-embedded T-shaped steel in the beams and fixed with high-strength bolts to bear the construction load. Then connect the longitudinal bars of the beam; form a complete reinforced concrete beam after the section steel connection, longitudinal bar connection and secondary pouring are completed; when the prefabricated node of the present invention is made in the factory, only the longitudinal bars and stirrups at the bottom of the beam are bound to form a reinforced skeleton, and the upper part of the beam The longitudinal reinforcement is left to be threaded and connected on site; T-shaped steel is buried at the end of the beam and the formwork is supported, and then concrete is poured to form a prefabricated beam; after transported to the construction site, it is positioned and installed through the steel joint and the prefabricated joint, and then the mechanical joint is used Connect the longitudinal reinforcement of the beam, and then install the prefabricated floor slab on the prefabricated beam that has been installed; finally, perform the secondary pouring of the connecting joint and the laminated slab to complete the construction of the beam slab on this floor.
具体实施方式二:如图1~图5所示,本实施方式预制梁1的混凝土底面平整,顶面沿其长度方向制作成咬合槽1-1和两个顶面平台1-2,咬合槽1-1的底面为锯齿形。如此设计,增大接触面积,以便于咬合连接部位的二次浇筑混凝土,两个顶面平台1-2分别用于支承预制楼板。其它组成及连接关系与具体实施方式一相同。Specific embodiment two: As shown in Figures 1 to 5, the concrete bottom surface of the prefabricated beam 1 in this embodiment is flat, and the top surface is made into an occlusal groove 1-1 and two top platforms 1-2 along its length direction. 1-1 has a zigzag bottom surface. In this design, the contact area is increased to facilitate the secondary pouring of concrete at the occlusal joint, and the two top platforms 1-2 are respectively used to support the prefabricated floor slab. Other components and connections are the same as those in the first embodiment.
具体实施方式三:如图3和图4所示,本实施方式预制梁1的两端制作为锯齿形状。如此设计,增大接触面积,以便于咬合连接部位的二次浇筑混凝土,其它组成及连接关系与具体实施方式一或二相同。Specific Embodiment Three: As shown in Fig. 3 and Fig. 4 , the two ends of the prefabricated beam 1 in this embodiment are made in zigzag shape. With such a design, the contact area is increased so as to facilitate the secondary pouring of concrete at the occlusal joint, and the other components and connection relations are the same as those in the first or second embodiment.
具体实施方式四:如图3、图4和图5所示,本实施方式预埋钢连接件2包括型钢预埋部分2-1和外露腹板2-2,型钢预埋部分2-1的横截面呈倒“T”字形,外露腹板2-2上加工有多个连接螺栓孔。Embodiment 4: As shown in Fig. 3, Fig. 4 and Fig. 5, the embedded steel connector 2 of this embodiment includes the pre-embedded part 2-1 of the shaped steel and the exposed web 2-2, and the pre-embedded part 2-1 of the shaped steel The cross section is in an inverted "T" shape, and a plurality of connecting bolt holes are processed on the exposed web 2-2.
具体实施方式五:如图6所示,本实施方式预制梁1长度为相邻柱间距的1/3~1/2,预制梁1与预制钢筋混凝土梁柱节点连接部位靠近设计的反弯点位置。如此设计,避免了预制梁端部与柱直接相连,将连接位置转移到了受力较小的部位,其它组成及连接关系与具体实施方式一、二或四相同。Specific implementation mode five: as shown in Figure 6, the length of the prefabricated beam 1 in this embodiment is 1/3 to 1/2 of the distance between adjacent columns, and the connection between the prefabricated beam 1 and the prefabricated reinforced concrete beam-column node is close to the designed inflection point Location. Such a design avoids the direct connection between the end of the prefabricated beam and the column, and transfers the connection position to the part with less stress. Other components and connection relations are the same as those in Embodiment 1, 2 or 4.
制作过程:Production process:
结合图1~6说明本发明制作过程:本发明对应于预制钢筋混凝土梁,如图3所示,本发明的预制梁1的制作在预制构件厂完成,包括纵向钢筋3及箍筋4绑扎、预埋钢连接件2、支模、混凝土浇筑和养护。In conjunction with Fig. 1~6, illustrate the manufacturing process of the present invention: the present invention corresponds to the prefabricated reinforced concrete beam, as shown in Figure 3, the making of prefabricated beam 1 of the present invention is finished in the prefabricated component factory, comprises longitudinal steel bar 3 and stirrup 4 binding, Embedded steel connectors 2, formwork support, concrete pouring and maintenance.
具体制作过程如下:The specific production process is as follows:
一、绑扎钢筋骨架,调整纵向钢筋3和箍筋4的位置并验收绑扎质量;二、预埋钢连接件2,在梁段端部预埋两个预埋钢连接件2;三、按设计要求支模、浇筑混凝土并在标准条件下养护,工期紧张时可选择特殊条件养护,如高温蒸汽养护;四、养护完毕,测试达到设计标准强度后拆掉模板,完成该梁的制作,随后出厂运至施工现场堆场,等待吊装;1. Bind the steel skeleton, adjust the position of the longitudinal steel bar 3 and stirrup 4 and check the binding quality; 2. Embed steel connectors 2, pre-embed two pre-embedded steel connectors 2 at the end of the beam section; 3. Support according to the design requirements Formwork, pouring concrete and curing under standard conditions. When the construction period is tight, you can choose special conditions for curing, such as high-temperature steam curing; 4. After the curing is completed, the formwork is removed after the test reaches the design standard strength, and the beam is completed. Then it is shipped to Construction site yard, waiting for hoisting;
本发明预制梁1的安装施工如图2所示:采用塔吊对其进行预制梁1的连接。利用吊装设备微调节点平面位置、竖向垂直度和标高。调整完毕后将其下沉连接固定,进行预制梁上部纵筋穿筋并绑扎好纵向钢筋3及连接处的箍筋4。利用机械连接头进行梁纵向钢筋3的连接。待预制梁连接完毕后形成梁柱框架体系,以此体系为支撑,搭接本层预制混凝土叠合板。在梁连接部位支模并与楼面整体浇筑混凝土,养护至规定强度后拆除本层支撑,完成本层施工。The installation and construction of the prefabricated beam 1 of the present invention is shown in Figure 2: the prefabricated beam 1 is connected by a tower crane. Use hoisting equipment to fine-tune the plane position, vertical verticality and elevation of the point. After the adjustment is completed, the sinking connection is fixed, the upper longitudinal reinforcement of the prefabricated beam is pierced, and the longitudinal reinforcement 3 and the stirrup 4 at the connection are tied. The connection of the beam longitudinal reinforcement 3 is carried out by means of mechanical joints. After the prefabricated beams are connected, a beam-column frame system is formed, and this system is used as a support to overlap the precast concrete laminated slabs of this layer. Set up the formwork at the beam connection and pour concrete integrally with the floor, and remove the support of this floor after curing to the specified strength to complete the construction of this floor.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610165145.6A CN105839846A (en) | 2016-03-22 | 2016-03-22 | Prefabricated reinforced concrete composite beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610165145.6A CN105839846A (en) | 2016-03-22 | 2016-03-22 | Prefabricated reinforced concrete composite beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105839846A true CN105839846A (en) | 2016-08-10 |
Family
ID=56588433
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610165145.6A Pending CN105839846A (en) | 2016-03-22 | 2016-03-22 | Prefabricated reinforced concrete composite beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105839846A (en) |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107035068A (en) * | 2017-05-04 | 2017-08-11 | 浙江绿筑集成科技有限公司 | Combine the joining method of prefabricated post in a kind of part |
CN107268888A (en) * | 2017-07-31 | 2017-10-20 | 中民筑友建筑科技(昆山)有限公司 | A kind of precast beam structure |
CN107313508A (en) * | 2017-05-04 | 2017-11-03 | 上海中建东孚投资发展有限公司 | A kind of prefabricated assembled primary-secondary beam mounting structure and installation method |
CN107558663A (en) * | 2017-10-12 | 2018-01-09 | 河北丽建丽筑集成房屋有限公司 | A kind of modularization precast beam system |
CN108149788A (en) * | 2018-01-18 | 2018-06-12 | 广州大学 | A kind of assembling frame structure and its construction method |
CN108166620A (en) * | 2017-12-25 | 2018-06-15 | 天津大学 | A kind of assembly concrete beam-column, column-column connected node |
CN108385836A (en) * | 2018-03-14 | 2018-08-10 | 青岛理工大学 | Novel beam column connection structure of cast-in-place concrete frame is run through to reinforcing bar |
CN108396859A (en) * | 2018-03-07 | 2018-08-14 | 王昆 | A kind of assembly concrete beam-column connection and its construction method |
CN108518019A (en) * | 2018-04-19 | 2018-09-11 | 沈阳建筑大学 | Prefabricated assembled steel-profiled sheet concrete combination beam |
CN108716246A (en) * | 2018-07-06 | 2018-10-30 | 沈阳三建筑设计研究有限公司 | Frame structure system |
CN109296129A (en) * | 2018-10-29 | 2019-02-01 | 南通龙哲混凝土制品有限公司 | A kind of precast beam and its construction method |
CN109911766A (en) * | 2019-04-23 | 2019-06-21 | 哈尔滨军鼎混凝土制品有限公司佳木斯分公司 | A kind of removable beam of gantry crane automobile-used track |
CN110016968A (en) * | 2019-04-18 | 2019-07-16 | 合肥工业大学 | A kind of unilateral assembled connecting node of prefabricated overlapping coupled column of precast concrete beam- |
CN111719402A (en) * | 2020-07-21 | 2020-09-29 | 肖礼经 | A kind of ultra-high performance concrete beam and ultra-high performance concrete beam group |
CN111809797A (en) * | 2019-04-12 | 2020-10-23 | 华恒建设集团有限公司 | Construction process of reinforced concrete superposed beam |
CN111926676A (en) * | 2020-08-17 | 2020-11-13 | 北京市市政专业设计院股份公司 | an assembled bridge |
CN112813979A (en) * | 2021-01-22 | 2021-05-18 | 中铁第四勘察设计院集团有限公司 | Concrete pouring system and method for wet joint of beam column connection of fabricated structure |
CN113374171A (en) * | 2021-06-08 | 2021-09-10 | 华南理工大学 | Recycled block concrete prefabricated assembled ring beam structure and construction method thereof |
CN113863574A (en) * | 2020-06-30 | 2021-12-31 | 振中建设集团有限公司 | Assembly type bearing beam structure and construction method |
CN114635502A (en) * | 2022-03-11 | 2022-06-17 | 桂林理工大学 | Node superposed prefabricated split beam and construction method thereof |
CN115233812A (en) * | 2022-07-05 | 2022-10-25 | 上海港城建筑安装工程有限公司 | Node of precast beam and precast slab and construction method thereof |
CN115434417A (en) * | 2022-08-03 | 2022-12-06 | 中建八局第二建设有限公司 | Fabricated concrete frame structure and construction method thereof |
CN117365015A (en) * | 2023-09-11 | 2024-01-09 | 上海宝冶集团有限公司 | Connecting structure of rear longitudinal ribs and downwarping stirrups on upper part of prefabricated superposed beam |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000144905A (en) * | 1998-11-12 | 2000-05-26 | Ohbayashi Corp | Mixed structural beam |
CN200946347Y (en) * | 2006-06-21 | 2007-09-12 | 王韦航 | Zigzag type light partition wall panel with inner rib |
CN201043299Y (en) * | 2007-06-01 | 2008-04-02 | 官锦禄 | reinforced-concrete structure |
CN201581502U (en) * | 2009-12-24 | 2010-09-15 | 中国京冶工程技术有限公司 | Shear resisting part |
CN101851984A (en) * | 2010-06-30 | 2010-10-06 | 哈尔滨工业大学 | A prefabricated steel-concrete composite beam |
CN201962942U (en) * | 2010-07-21 | 2011-09-07 | 李林 | A kind of template system of forming by light material module and prefabricated truss |
CN102418386A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Novel reinforced concrete prefabricated integrally-cast building structure system and construction method thereof |
JP2012180698A (en) * | 2011-03-02 | 2012-09-20 | Shimizu Corp | Precast beam joint structure and method |
CN102720304A (en) * | 2012-06-15 | 2012-10-10 | 吴方伯 | Reinforced concrete composite beam |
CN103572840A (en) * | 2012-08-05 | 2014-02-12 | 初明进 | Notch-key type prefabricated member connection node and connection method |
JP5541521B2 (en) * | 2010-10-19 | 2014-07-09 | 清水建設株式会社 | Mixed structural beam |
CN104264897A (en) * | 2014-10-27 | 2015-01-07 | 沈阳建筑大学 | Superposed beam and board with alternated teeth |
CN104675012A (en) * | 2015-03-17 | 2015-06-03 | 西安建筑科技大学 | Prefabricated polypropylene fiber sludge ceramsite concrete wall based on serrated racking connection and construction method thereof |
CN104805960A (en) * | 2015-05-11 | 2015-07-29 | 吴方伯 | Mould-stripping-free concrete beam and construction method thereof |
CN104912190A (en) * | 2015-06-17 | 2015-09-16 | 淮海工学院 | Dry type joggle frame structure |
-
2016
- 2016-03-22 CN CN201610165145.6A patent/CN105839846A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000144905A (en) * | 1998-11-12 | 2000-05-26 | Ohbayashi Corp | Mixed structural beam |
CN200946347Y (en) * | 2006-06-21 | 2007-09-12 | 王韦航 | Zigzag type light partition wall panel with inner rib |
CN201043299Y (en) * | 2007-06-01 | 2008-04-02 | 官锦禄 | reinforced-concrete structure |
CN201581502U (en) * | 2009-12-24 | 2010-09-15 | 中国京冶工程技术有限公司 | Shear resisting part |
CN101851984A (en) * | 2010-06-30 | 2010-10-06 | 哈尔滨工业大学 | A prefabricated steel-concrete composite beam |
CN201962942U (en) * | 2010-07-21 | 2011-09-07 | 李林 | A kind of template system of forming by light material module and prefabricated truss |
CN102418386A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Novel reinforced concrete prefabricated integrally-cast building structure system and construction method thereof |
JP5541521B2 (en) * | 2010-10-19 | 2014-07-09 | 清水建設株式会社 | Mixed structural beam |
JP2012180698A (en) * | 2011-03-02 | 2012-09-20 | Shimizu Corp | Precast beam joint structure and method |
CN102720304A (en) * | 2012-06-15 | 2012-10-10 | 吴方伯 | Reinforced concrete composite beam |
CN103572840A (en) * | 2012-08-05 | 2014-02-12 | 初明进 | Notch-key type prefabricated member connection node and connection method |
CN104264897A (en) * | 2014-10-27 | 2015-01-07 | 沈阳建筑大学 | Superposed beam and board with alternated teeth |
CN104675012A (en) * | 2015-03-17 | 2015-06-03 | 西安建筑科技大学 | Prefabricated polypropylene fiber sludge ceramsite concrete wall based on serrated racking connection and construction method thereof |
CN104805960A (en) * | 2015-05-11 | 2015-07-29 | 吴方伯 | Mould-stripping-free concrete beam and construction method thereof |
CN104912190A (en) * | 2015-06-17 | 2015-09-16 | 淮海工学院 | Dry type joggle frame structure |
Cited By (30)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107313508A (en) * | 2017-05-04 | 2017-11-03 | 上海中建东孚投资发展有限公司 | A kind of prefabricated assembled primary-secondary beam mounting structure and installation method |
CN107313508B (en) * | 2017-05-04 | 2023-09-15 | 上海中建东孚投资发展有限公司 | Prefabricated assembly type main and secondary beam installation structure and installation method |
CN107035068A (en) * | 2017-05-04 | 2017-08-11 | 浙江绿筑集成科技有限公司 | Combine the joining method of prefabricated post in a kind of part |
CN107268888A (en) * | 2017-07-31 | 2017-10-20 | 中民筑友建筑科技(昆山)有限公司 | A kind of precast beam structure |
CN107558663A (en) * | 2017-10-12 | 2018-01-09 | 河北丽建丽筑集成房屋有限公司 | A kind of modularization precast beam system |
CN108166620B (en) * | 2017-12-25 | 2020-02-07 | 天津大学 | Assembled concrete beam-column, post-column connected node |
CN108166620A (en) * | 2017-12-25 | 2018-06-15 | 天津大学 | A kind of assembly concrete beam-column, column-column connected node |
CN108149788A (en) * | 2018-01-18 | 2018-06-12 | 广州大学 | A kind of assembling frame structure and its construction method |
CN108396859B (en) * | 2018-03-07 | 2020-07-31 | 广东新江永安建设工程有限公司 | Assembly type concrete beam column connecting joint and construction method thereof |
CN108396859A (en) * | 2018-03-07 | 2018-08-14 | 王昆 | A kind of assembly concrete beam-column connection and its construction method |
CN108385836A (en) * | 2018-03-14 | 2018-08-10 | 青岛理工大学 | Novel beam column connection structure of cast-in-place concrete frame is run through to reinforcing bar |
CN108518019A (en) * | 2018-04-19 | 2018-09-11 | 沈阳建筑大学 | Prefabricated assembled steel-profiled sheet concrete combination beam |
CN108518019B (en) * | 2018-04-19 | 2024-02-13 | 沈阳建筑大学 | Prefabricated steel-profiled steel plate concrete composite beam |
CN108716246A (en) * | 2018-07-06 | 2018-10-30 | 沈阳三建筑设计研究有限公司 | Frame structure system |
CN109296129A (en) * | 2018-10-29 | 2019-02-01 | 南通龙哲混凝土制品有限公司 | A kind of precast beam and its construction method |
CN111809797A (en) * | 2019-04-12 | 2020-10-23 | 华恒建设集团有限公司 | Construction process of reinforced concrete superposed beam |
CN110016968A (en) * | 2019-04-18 | 2019-07-16 | 合肥工业大学 | A kind of unilateral assembled connecting node of prefabricated overlapping coupled column of precast concrete beam- |
CN110016968B (en) * | 2019-04-18 | 2024-03-15 | 合肥工业大学 | Unilateral assembled connected node of precast concrete beam-prefabricated coincide composite column |
CN109911766A (en) * | 2019-04-23 | 2019-06-21 | 哈尔滨军鼎混凝土制品有限公司佳木斯分公司 | A kind of removable beam of gantry crane automobile-used track |
CN113863574A (en) * | 2020-06-30 | 2021-12-31 | 振中建设集团有限公司 | Assembly type bearing beam structure and construction method |
CN111719402A (en) * | 2020-07-21 | 2020-09-29 | 肖礼经 | A kind of ultra-high performance concrete beam and ultra-high performance concrete beam group |
CN111926676A (en) * | 2020-08-17 | 2020-11-13 | 北京市市政专业设计院股份公司 | an assembled bridge |
CN112813979A (en) * | 2021-01-22 | 2021-05-18 | 中铁第四勘察设计院集团有限公司 | Concrete pouring system and method for wet joint of beam column connection of fabricated structure |
CN113374171A (en) * | 2021-06-08 | 2021-09-10 | 华南理工大学 | Recycled block concrete prefabricated assembled ring beam structure and construction method thereof |
CN114635502B (en) * | 2022-03-11 | 2023-06-13 | 桂林理工大学 | Prefabricated Split Beam with Superposed Nodes and Its Construction Method |
CN114635502A (en) * | 2022-03-11 | 2022-06-17 | 桂林理工大学 | Node superposed prefabricated split beam and construction method thereof |
CN115233812B (en) * | 2022-07-05 | 2023-12-05 | 上海港城建筑安装工程有限公司 | Node of precast beam and precast slab and construction method thereof |
CN115233812A (en) * | 2022-07-05 | 2022-10-25 | 上海港城建筑安装工程有限公司 | Node of precast beam and precast slab and construction method thereof |
CN115434417A (en) * | 2022-08-03 | 2022-12-06 | 中建八局第二建设有限公司 | Fabricated concrete frame structure and construction method thereof |
CN117365015A (en) * | 2023-09-11 | 2024-01-09 | 上海宝冶集团有限公司 | Connecting structure of rear longitudinal ribs and downwarping stirrups on upper part of prefabricated superposed beam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105839846A (en) | Prefabricated reinforced concrete composite beam | |
CN107165272B (en) | Prestressed assembled concrete frame node connecting structure and construction method thereof | |
CN108049498B (en) | Prefabricated column and prefabricated beam connection structure and method of prefabricated building frame structure | |
CN105804241A (en) | Single-layer prefabricated assembly type reinforced concrete beam-column joint | |
CN103104041B (en) | A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method | |
CN104988844B (en) | Two times tensioning prestressing force assembled Wavelike steel webplate combination beam | |
CN110792165B (en) | Prefabricated assembly type concrete beam column joint connecting device and method | |
CN204876059U (en) | Prefabricated assembled shaped steel concrete frame structure system | |
CN106968381B (en) | Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves | |
CN108661221A (en) | A kind of precast floor slab and its connection structure and its construction method | |
CN109457801B (en) | A kind of connection node of prefabricated reinforced concrete beam and its construction method | |
CN107476470A (en) | Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method | |
CN208618627U (en) | A kind of precast floor slab and its connection structure | |
CN110725455A (en) | A method for lateral connection of prefabricated laminated floor slabs | |
CN108104284B (en) | Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab | |
CN108775084B (en) | Steel-concrete composite prefabricated beam and prefabricated column connection structure and construction method | |
CN207794299U (en) | A kind of complete assembled steel reinforced concrete frame structure system | |
CN204112525U (en) | Band perps precast shear wall structure in strong concrete precast frame | |
CN209227836U (en) | Prefabricated concrete structure wall-column full steel key connection structure | |
CN113668750B (en) | Prefabricated floor-prefabricated shear wall connection node and construction method thereof | |
CN216475803U (en) | A Novel Prefabricated Floor Structure Applied to Shear Wall System | |
CN110644662A (en) | Prefabricated flat slab composite slab based on stress and splitting method thereof | |
CN207647033U (en) | A kind of precast reinforced basket structure | |
CN207525960U (en) | Easy connect band shear key reinforced concrete slab structure | |
CN104032861B (en) | Connecting joint structure of mixed coupled wall section steel column and non-energy dissipation beam and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Changyong Inventor after: Wang Yuyin Inventor after: Yang Ligui Inventor after: Yuan Changchun Inventor before: Liu Changyong Inventor before: Yang Ligui Inventor before: Yuan Changchun |
|
COR | Change of bibliographic data | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160810 |
|
RJ01 | Rejection of invention patent application after publication |