[go: up one dir, main page]

CN208136999U - A kind of mud transportation system - Google Patents

A kind of mud transportation system Download PDF

Info

Publication number
CN208136999U
CN208136999U CN201820666696.5U CN201820666696U CN208136999U CN 208136999 U CN208136999 U CN 208136999U CN 201820666696 U CN201820666696 U CN 201820666696U CN 208136999 U CN208136999 U CN 208136999U
Authority
CN
China
Prior art keywords
mud
mixing chamber
curing agent
grab bucket
conveying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820666696.5U
Other languages
Chinese (zh)
Inventor
冒盛云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Shekou Investment Harbor Engineering Co Ltd
Original Assignee
Shenzhen Shekou Investment Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Shekou Investment Harbor Engineering Co Ltd filed Critical Shenzhen Shekou Investment Harbor Engineering Co Ltd
Priority to CN201820666696.5U priority Critical patent/CN208136999U/en
Application granted granted Critical
Publication of CN208136999U publication Critical patent/CN208136999U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treatment Of Sludge (AREA)

Abstract

The utility model proposes a kind of mud transportation systems, are related to coastal engineering technical field of construction, solve it is common by mud transportation system convey at high cost, the low problem of construction efficiency, including:Positioned at the grab bucket dredger of working region operation;For taking the grab bucket of mud to seabed on the grab bucket dredger;Mud storing unit on the grab bucket dredger, for holding the mud grabbed bucket and taken;The mixing chamber being connected to the discharge port of the mud storing unit is provided with agitating device in the mixing chamber;Curing agent conveying device being connected to in the mixing chamber and to addition curing agent powder inside it;Auxiliary conveying appliance below the discharge port of the mixing chamber;And between the discharge port set on the auxiliary conveying appliance and bank mud laydown area, the main conveying device that the mud after solidification is transported to mud laydown area stack reaction, reach and improve mud transfer efficiency, reduce the purpose of conveying cost.

Description

A kind of mud transportation system
Technical field
The utility model relates to coastal engineering technical field of construction, in particular to a kind of mud transportation system.
Background technique
In depositing the ground construction works such as deep tidal-flat area, marsh, the wetland of silt clay layer, the earthwork is backfilled It is a big technological difficulties.Conventional land and marine equipment is all difficult to construct, and specific aim, which has been developed, twists suction hydraulic reclamation equipment, purlin Posture beach diker and piston type earthwork conveying ship etc. backfill earthwork conveying machinery.
Current mud transportation system is general first during bottom silt is carried out dredging and transferred out mud The mud that water is added is twisted using reamer, is sufficiently mixed mud and water, and suction pump is recycled to drink up the mud after dilution, and After carrying out curing process to mud on dredger, dredger, which is opened go back to bank and unshiped mud using digging machine, is loaded in bank heap It puts.The mode for conveying mud, needs dredger repeatedly back and forth on bank and seabed dredging region, and needing will using ancillary equipment Mud on dredger is unloaded to bank stacking, and mud conveying is at high cost, and construction efficiency is low.Admittedly need a kind of construction efficiency it is high, Convey mud transportation system at low cost.
Utility model content
The purpose of the utility model is to provide a kind of mud transportation system, have that mud conveying speed is fast, conveying is at low cost The advantages of.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of mud delivery system System, including:Positioned at the grab bucket dredger of working region operation;For taking silt to seabed on the grab bucket dredger The grab bucket of mud;Mud storing unit on the grab bucket dredger, for holding the mud grabbed bucket and taken;With institute The mixing chamber of the discharge port connection of mud storing unit is stated, is provided with agitating device in the mixing chamber;In the mixing chamber Curing agent conveying device being connected to and to addition curing agent powder inside it;It is auxiliary below the discharge port of the mixing chamber Help conveying device;And between the discharge port set on the auxiliary conveying appliance and bank mud laydown area, will be after solidification Mud is transported to the main conveying device that mud laydown area stack reaction.
By using above-mentioned technical proposal, the mud in seabed is dug out using grab bucket and is deposited by mud by grab bucket dredger It puts device and enters mixing chamber, curing agent conveying device conveys curing agent powder into mixing chamber, and agitating device is in mixing chamber Mud and curing agent powder are stirred, and are sufficiently mixed curing agent powder and mud, and sludge dewatering is cured, after solidification Mud is discharged to auxiliary conveying appliance from the discharge port of mixing chamber, and the mud after solidification is passed through main conveying device by auxiliary conveying appliance It is transported to the mud laydown area on bank;It is to deposit mud since grab bucket takes mud, construction efficiency is higher, aqueous in mud Measure lower, the dosage of curing agent is few during sludge solidification;Only need to manually manipulate grab bucket takes silt in entire mud transmission process Mud is simultaneously sent in mud storing unit, the subsequent dehydrating and curing that can automatically complete mud to the mistake for being delivered to bank stacking Journey, high degree of automation improve the transfer efficiency of mud, reduce conveying cost.
The further setting of the utility model, the mud storing unit include:It is mounted on the grab bucket dredger Mud storage compartment;It is movably arranged on the upper valve of the discharge outlet of the mud storage compartment;And it is mounted on the mud and deposits Put bucket outside, drive the upper valve motion hydraulic cylinder so that the upper valve door termination or unlatching discharge port.
By using above-mentioned technical proposal, hydraulic cylinder, which drives, goes up valve motion opening discharge port, in mud storage compartment Mud falls into mixing chamber by discharge port and is solidified, and hydraulic cylinder drives upper valve to close discharge port immediately later, and bucket connects Mud is transported in mud storage compartment;This mode makes the solidification process of last consignment of mud and next group mud be transported to silt Process in mud storage compartment can synchronize progress, improve the delivery rate of mud.
The further setting of the utility model, the agitating device include:It is mounted on the stirring electricity of the mixing chamber bottom Machine;By the agitating shaft of stirring motor driving rotation;And it is securely fitted on the agitating shaft and turns on the agitating shaft Dynamic several stirrer paddles.
By using above-mentioned technical proposal, stirring motor drives stirring blade to stir mud by agitating shaft, make mud and Curing agent powder is more fully mixed, and accelerates sludge dewatering rate, reduces the sludge solidification period.
The further setting of the utility model, the curing agent conveying device include:It is mounted on the grab bucket dredger On first support;It is mounted in the first support and tilted-putted conveying pipeline;Set on the conveying pipeline lower end to described The feed hopper of addition curing agent powder in conveying pipeline;It is mounted on the feeding motor of the conveying pipeline lower end;And it is set to institute State discharge port that is being rotated in conveying pipeline by feeding motor driving and constantly curing agent powder being promoted to the conveying pipeline The screw rod at place.
By using above-mentioned technical proposal, feeding motor drives screw turns is transported to curing agent powder in conveying pipeline Top, feed hopper setting is in conveying pipeline lower end, and convenient for manually adding curing agent powder into conveying pipeline, and curing agent powder is defeated It passes through journey to carry out in the conveying pipeline of sealing, reduces the pollution that curing agent powder disperses to surrounding enviroment, it is relatively simple for structure, Cost is relatively low.
The further setting of the utility model is also set up between the curing agent conveying device and the mixing chamber to described The meausring apparatus that the curing agent powder that conveying pipeline conveying comes is weighed and is transported in the mixing chamber, the meausring apparatus Including:It is mounted on second on the grab bucket dredger and between the curing agent conveying device and the mixing chamber Bracket;Be mounted in the second support and be located at below the discharge port of the conveying pipeline and the feed opening of the mixing chamber it Between feeding belt;It is mounted in the second support and quantitative weighing electronics is carried out to the curing agent powder on the feeding belt Scale;And it is electrically connected with the electronic scale, controls the curing agent when the load-bearing value of the electronic scale reaches predetermined value Conveying device stops feeding and controls the controller of the feeding belt movement.
By using above-mentioned technical proposal, to ensure dehydrating and curing effect and rationally addition solidification of the mud in mixing chamber The amount of agent powder determines the weight of addition curing agent powder according to the moisture content of the capacity of mud storing unit and mud, works as electricity When the weight of curing agent powder on sub- scale instruction feeding belt reaches predetermined value, control signal, control are issued to controller Device control curing agent conveying device stops feeding and controls feeding belt movement for quantitative curing agent powder carry to mixing chamber It is interior, achieve the purpose that make the dehydrating and curing effect of mud in mixing chamber good and saves hardener dose.
The further setting of the utility model, the feed opening of the mixing chamber be externally provided with from one end of the feeding belt to The inclined loading hopper of feed opening, the loading hopper lower section are equipped with the curing agent powder entered in mixing chamber for dispelling the loading hopper The blower of material.
By using above-mentioned technical proposal, loading hopper enters in mixing chamber convenient for curing agent powder, and blower can dispel entrance Curing agent powder in mixing chamber, convenient for being sufficiently mixed for curing agent powder and mud.
The further setting of the utility model, the auxiliary conveying appliance include:Positioned at the mixing chamber discharge port and Belt fixed frame between the main conveying device;And along the belt fixed frame length direction setting, be driven by motor Mud is transported to the first conveyor belt of the main conveying device.
By using above-mentioned technical proposal, the movement of Belt Conveying mode is single, compact-sized, can be continuous incessantly Mud is conveyed, conveying capacity is big;And it can be reprinted and be unloaded in the non-stop-machine situation of transmission process, it will not be because of sky It carries and conveying is caused to be interrupted.
The further setting of the utility model, the main conveying device include:It is erected at the grab bucket dredger and silt Several columns between mud laydown area on sea area;The girder truss being fixed on the column;And the length along the girder truss Direction setting, the second conveyor belt that mud is transported to mud laydown area is driven by motor.
By using above-mentioned technical proposal, the second conveyor belt and the cooperation of the first conveyor belt can directly dredge grab type Mud after solidifying on ship is transported to the mud laydown area on bank, transports mud back and forth without grab bucket dredger, improves silt Mud transfer efficiency, saves transportation cost.
In conclusion the utility model has the advantages that:
1, only grab bucket need to be manually manipulated in entire mud transmission process to take mud and be sent in mud storing unit, it is subsequent The dehydrating and curing of mud can be automatically completed to the process for being delivered to bank stacking, high degree of automation improves mud Transfer efficiency reduces conveying cost;
It 2, is to deposit mud since grab bucket takes mud, the water content in mud is lower, therefore construction efficiency is higher, and mud is solid The dosage of curing agent is few during change;
3, before adding curing agent powder into mixing chamber, curing agent is weighed, according to the capacity of mud storage compartment The weight of addition curing agent powder is determined with the moisture content of mud, reaching keeps the dehydrating and curing effect of mud in mixing chamber good and close Reason uses the purpose of curing agent.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the mud transportation system in nearly offshore construction in the utility model embodiment;
Fig. 2 is the cross-sectional view of mud storing unit and mixing chamber in the utility model embodiment;
Fig. 3 is that mixing chamber, curing agent conveying device, auxiliary conveying fill on grab bucket dredger in the utility model embodiment Set the connection relationship diagram with meausring apparatus;
Fig. 4 is the cross-sectional view of curing agent conveying device and meausring apparatus in the utility model embodiment.
Appended drawing reference:1, grab bucket dredger;2, it grabs bucket;3, mud storing unit;31, mud storage compartment;32, upper valve Door;33, hydraulic cylinder;4, mixing chamber;5, agitating device;51, stirring motor;52, agitating shaft;53, stirrer paddle;6, curing agent Conveying device;61, first support;62, conveying pipeline;63, feed hopper;64, feeding motor;65, screw rod;7, auxiliary conveying appliance; 71, belt fixed frame;72, the first conveyor belt;8, main conveying device;81, column;82, girder truss;83, the second conveyor belt; 9, meausring apparatus;91, second support;92, feeding belt;93, electronic scale;10, loading hopper;11, blower;12, mud laydown area.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:A kind of mud transportation system, as shown in Figure 1, including:2 formula dredger 1 of grab bucket positioned at work waters, It grabs bucket and is rotatably equipped with grab bucket 2 on 2 formula dredgers 1, manual control grab bucket 2 takes from grab bucket 2 formula dredger, 1 periphery sea-bed area Mud.It grabs bucket to be equipped on 2 formula dredgers 1 and is located at the mud storing unit 3 that grab bucket 2 deviates from side, mud storing unit 3 is used for 2 mud that take of grab bucket are held, the discharge port of 3 lower end of mud storing unit is communicated with mixing chamber 4, is provided in mixing chamber 4 pair The agitating device 5 that mud is stirred.4 side of mixing chamber is equipped with the solidification to 4 inner upper of mixing chamber addition curing agent powder The discharge port of agent conveying device 6,4 lower section of mixing chamber is provided with auxiliary conveying appliance 7, the discharge end and bank of auxiliary conveying appliance 7 It is provided with the mud across the main conveying device 8 above seawater, after solidification between the mud laydown area of side and passes through auxiliary conveying dress Set 7 and main conveying device 8 be transported to the mud laydown area on bank and stacked.
The mud in seabed is dug out and passes through mud storing unit 3 by grab bucket 2 to be entered in mixing chamber 4, curing agent conveying device 6 Convey curing agent powder into mixing chamber 4, agitating device 5 in mixing chamber 4 mud and curing agent powder be stirred, make solid Agent powder and mud are sufficiently mixed, and sludge dewatering is cured, and the mud after solidification is discharged to from the discharge port of 4 lower section of mixing chamber Auxiliary conveying appliance 7, and stacked by the mud laydown area that auxiliary conveying appliance 7 and main conveying device 8 are delivered directly to bank, Mud after solidification is transported to the mud laydown area on bank by main conveying device 8.People is only needed in entire mud transmission process Work manipulation grab bucket 2 takes mud and is sent in mud storing unit 3, and the subsequent dehydrating and curing that can automatically complete mud is to defeated The process stacked to bank is sent, high degree of automation improves the transfer efficiency of mud, reduces conveying cost.
Auxiliary conveying appliance 7 includes:Belt fixed frame 71 between the discharge port and main conveying device 8 of mixing chamber 4; And along the setting of 71 length direction of belt fixed frame, be driven by motor mud be transported to the first of 8 one end of main conveying device Conveyor belt 72.By the way of Belt Conveying mud, movement is single, compact-sized, and mud can be continuously conveyed incessantly, Conveying capacity is big;And it can be reprinted and be unloaded in the non-stop-machine situation of transmission process, will not be caused because of zero load Conveying interruption.
Main conveying device 8 includes:It is erected at more root posts between 2 formula dredgers 1 of grab bucket and mud laydown area on sea area 81(Four are reduced in Fig. 1);The girder truss 82 being fixed on column 81;And along girder truss 82 length direction be arranged, The second conveyor belt 83 that mud is transported to mud laydown area is driven by motor.Second conveyor belt 83 and the first conveyor belt Mud after solidification can be directly transported to the mud laydown area on bank by 72 cooperations, and without grabbing bucket, 2 formula dredgers 1 transport silt back and forth Mud improves mud transfer efficiency, saves transportation cost.
As shown in Fig. 2, mud storing unit 3 includes mud storage compartment 31, the discharge outlet of 31 lower section of mud storage compartment is living It moves and valve 32 is installed, the outside installation of mud storage compartment 31 drives upper valve 32 to move so that upper valve 32 is closed or opened Open the hydraulic cylinder 33 of discharge port.Hydraulic cylinder 33 drives the upper movement of valve 32 to open discharge port, the silt in mud storage compartment 31 Mud falls into mixing chamber 4 by discharge port and is solidified, and hydraulic cylinder 33 drives upper valve 32 to close discharge port, bucket immediately later Then mud is transported in mud storage compartment 31 and is temporarily stored;This mode makes the solidification process and next group of last consignment of mud The process that mud is transported in mud storage compartment 31 can synchronize progress, improve the delivery rate of mud.
Agitating device 5 includes:It is mounted on the stirring motor 51 of 4 bottom of mixing chamber;It is driven by stirring motor 51 in mixing chamber 4 The agitating shaft 52 of interior rotation;And it is securely fitted on agitating shaft 52 with the three groups of stirrer paddles 53 rotated on agitating shaft 52.It stirs Mix motor 51 and drive stirring blade to stir mud by agitating shaft 52, make mud do not stall it is dynamic even overturn so that mud and solid Agent powder is more fully mixed, and accelerates the rate of water loss of mud, reduces the sludge solidification period.
As shown in Figure 3 and Figure 4, curing agent conveying device 6 includes being mounted on the first support of 7 top of auxiliary conveying appliance 61, the conveying pipeline 62 of inclined placement is fixed in first support 61, the lower end of conveying pipeline 62 is equipped with adds into conveying pipeline 62 The feed hopper 63 of curing agent powder, the end of 62 lower end of conveying pipeline are equipped with feeding motor 64, are provided in conveying pipeline 62 by sending Expect the driving rotation of motor 64 and the discharge outlet constantly curing agent powder from the promotion of feed hopper 63 to conveying pipeline 62 screw rod 65.The lower end of conveying pipeline 62 is arranged in feed hopper 63, convenient for manually adding curing agent powder into conveying pipeline 62;Using screw rod 65 The process that curing agent powder is conveyed in conveying pipeline 62 carries out in sealed environment, reduces curing agent powder and disperses to peripheral ring The pollution in border, and screw rod 65 convey it is relatively simple for structure, cost is relatively low.
The meausring apparatus 9 being equipped with above auxiliary conveying appliance 7 between curing agent conveying device 6 and mixing chamber 4 claims Amount device 9 conveys after the curing agent powder to come weighs conveying pipeline 62 and is transported in mixing chamber 4 again.Meausring apparatus 9 wraps The second support 91 for being mounted on 7 top of auxiliary conveying appliance is included, second support 91 is located at curing agent conveying device 6 and mixing chamber 4 Between, the feeding skin below the discharge port of conveying pipeline 62 between the feed opening of mixing chamber 4 is installed in second support 91 Band 92 is also equipped with the electronic scale 93 weighed to the curing agent powder on feeding belt 92, electronic scale in second support 91 93 are electrically connected with the controller of control curing agent conveying device 6 and the movement of feeding belt 92.To ensure mud in mixing chamber 4 Dehydrating and curing effect and the reasonable weight of addition curing agent powder, according to the aqueous of the capacity of mud storing unit 3 and mud Rate determines the weight of addition curing agent powder, when electronic scale 93 indicates that the weight of the curing agent powder on feeding belt 92 reaches pre- When fixed number value, control signal is issued to controller, controller control curing agent conveying device 6 stops feeding and controls feeding skin simultaneously With 92 movements by quantitative curing agent powder carry to mixing chamber 4, reaching keeps the dehydrating and curing effect of mud in mixing chamber 4 good And save the purpose of hardener dose.
The feed opening of mixing chamber 4 is externally provided with from one end of feeding belt 92 to the inclined loading hopper 10 of feed opening, loading hopper 10 setting enters in mixing chamber 4 convenient for curing agent powder;Blower 11 is equipped with below loading hopper 10, blower 11 can be dispelled to enter and be stirred The curing agent powder in storehouse 4 is mixed, convenient for being sufficiently mixed for curing agent powder and mud.
Working principle:The mud in seabed is dug out and passes through mud storing unit 3 by grab bucket 2 to be entered in mixing chamber 4, curing agent Conveying device 6 conveys curing agent powder into mixing chamber 4, agitating device 5 in mixing chamber 4 mud and curing agent powder carry out Stirring, is sufficiently mixed curing agent powder and mud, and sludge dewatering is cured, and the mud after solidification is from the lower section of mixing chamber 4 Discharge port is discharged to auxiliary conveying appliance 7, and the mud on bank is delivered directly to by auxiliary conveying appliance 7 and main conveying device 8 Laydown area is stacked, and the mud after solidification is transported to the mud laydown area on bank by main conveying device 8.Entire mud conveyed Grab bucket 2 only need to be manually manipulated in journey to take mud and be sent in mud storing unit 3, it is subsequent to automatically complete the de- of mud To the process for being delivered to bank stacking, high degree of automation improves the transfer efficiency of mud, reduces conveying cost water cure.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (8)

1. a kind of mud transportation system, which is characterized in that including:
Positioned at grab bucket (2) formula dredger (1) of working region operation;
For taking the grab bucket (2) of mud to seabed on the grab bucket (2) formula dredger (1);
Mud storing unit on the grab bucket (2) formula dredger (1), for holding the mud that the grab bucket (2) takes (3);
The mixing chamber (4) being connected to the discharge port of the mud storing unit (3), the mixing chamber (4) is interior to be provided with stirring dress Set (5);
With curing agent conveying device (6) being connected in the mixing chamber (4) and to addition curing agent powder inside it;
Auxiliary conveying appliance (7) below the discharge port of the mixing chamber (4);And
It is between the discharge port and bank mud laydown area of the auxiliary conveying appliance (7), by after solidification mud convey Stack to mud laydown area the main conveying device (8) of reaction.
2. a kind of mud transportation system according to claim 1, which is characterized in that the mud storing unit (3) includes:
The mud storage compartment (31) being mounted on the grab bucket (2) formula dredger (1);
It is movably arranged on the upper valve (32) of the discharge outlet of the mud storage compartment (31);And
It is mounted on the outside of the mud storage compartment (31), the driving upper valve (32) moves so that the upper valve (32) is closed Or open the hydraulic cylinder (33) of discharge port.
3. a kind of mud transportation system according to claim 1, which is characterized in that the agitating device (5) includes:
It is mounted on the stirring motor (51) of the mixing chamber (4) bottom;
By the agitating shaft (52) of the stirring motor (51) driving rotation;And
It is securely fitted on the agitating shaft (52) with several stirrer paddles (53) rotated on the agitating shaft (52).
4. a kind of mud transportation system according to claim 1, which is characterized in that curing agent conveying device (6) packet It includes:
The first support (61) being mounted on the grab bucket (2) formula dredger (1);
It is mounted on the first support (61) and tilted-putted conveying pipeline (62);
Set on the feed hopper (63) of the conveying pipeline (62) lower end addition curing agent powder into the conveying pipeline (62);
It is mounted on the feeding motor (64) of the conveying pipeline (62) lower end;And
In the conveying pipeline (62) by the feeding motor (64) driving rotation and constantly the promotion of curing agent powder to The screw rod (65) of the discharge outlet of the conveying pipeline (62).
5. a kind of mud transportation system according to claim 4, which is characterized in that the curing agent conveying device (6) and It is also set up between the mixing chamber (4) and the curing agent powder that the conveying pipeline (62) conveying comes is weighed and is transported to institute The meausring apparatus (9) in mixing chamber (4) is stated, the meausring apparatus (9) includes:
It is mounted on grab bucket (2) the formula dredger (1) and is located at the curing agent conveying device (6) and the mixing chamber (4) Between second support (91);
It is mounted on the second support (91) and is located at the discharge port lower section and the mixing chamber (4) of the conveying pipeline (62) Feed opening between feeding belt (92);
It is mounted on the electricity for carrying out quantitative weighing on the second support (91) to the curing agent powder on the feeding belt (92) Sub- scale (93);And
It is controlled with the electronic scale (93) electric connection, when the load-bearing value of the electronic scale (93) reaches predetermined value described solid Agent conveying device (6) stops feeding and controls the controller of the feeding belt (92) movement.
6. a kind of mud transportation system according to claim 5, which is characterized in that outside the feed opening of the mixing chamber (4) Equipped with from one end of the feeding belt (92) to the inclined loading hopper of feed opening (10), it is equipped with and uses below the loading hopper (10) In the blower (11) for dispelling the curing agent powder that the loading hopper (10) enter in mixing chamber (4).
7. a kind of mud transportation system according to claim 1, which is characterized in that the auxiliary conveying appliance (7) includes: Belt fixed frame (71) between the discharge port and the main conveying device (8) of the mixing chamber (4);And along described The setting of belt fixed frame (71) length direction, be driven by motor mud be transported to the first defeated of the main conveying device (8) Send belt (72).
8. a kind of mud transportation system according to claim 1, which is characterized in that the main conveying device (8) includes:It is perpendicular Found several columns (81) between the grab bucket (2) formula dredger (1) and mud laydown area on sea area;It is fixed on the column (81) girder truss (82) on;And along the girder truss (82) length direction be arranged, be driven by motor and convey mud To the second conveyor belt (83) of mud laydown area.
CN201820666696.5U 2018-05-05 2018-05-05 A kind of mud transportation system Active CN208136999U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820666696.5U CN208136999U (en) 2018-05-05 2018-05-05 A kind of mud transportation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820666696.5U CN208136999U (en) 2018-05-05 2018-05-05 A kind of mud transportation system

Publications (1)

Publication Number Publication Date
CN208136999U true CN208136999U (en) 2018-11-23

Family

ID=64312676

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820666696.5U Active CN208136999U (en) 2018-05-05 2018-05-05 A kind of mud transportation system

Country Status (1)

Country Link
CN (1) CN208136999U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629517A (en) * 2018-11-28 2019-04-16 上海港湾基础建设(集团)股份有限公司 A kind of method in reclaiming land around sea domain
CN110616762A (en) * 2019-10-11 2019-12-27 中交天津航道局有限公司 Marine dredging sludge solidification integrated treatment equipment
CN111945655A (en) * 2020-08-19 2020-11-17 河海大学 Construction ship and method of use
CN112281968A (en) * 2020-11-08 2021-01-29 侯钦娅 Sea pond silt clearance structure
CN112431161A (en) * 2020-11-11 2021-03-02 中铁二十五局集团第五工程有限公司 Underwater dredging construction process
CN112681429A (en) * 2020-12-18 2021-04-20 刘红丹 Port sludge cleaning structure
CN118653536A (en) * 2024-08-20 2024-09-17 山西省水利建筑工程局集团有限公司 A river management device that is beneficial to optimizing river ecosystem

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629517A (en) * 2018-11-28 2019-04-16 上海港湾基础建设(集团)股份有限公司 A kind of method in reclaiming land around sea domain
CN110616762A (en) * 2019-10-11 2019-12-27 中交天津航道局有限公司 Marine dredging sludge solidification integrated treatment equipment
CN110616762B (en) * 2019-10-11 2024-07-09 中交天津航道局有限公司 Marine dredging sludge solidification integrated treatment equipment
CN111945655A (en) * 2020-08-19 2020-11-17 河海大学 Construction ship and method of use
CN112281968A (en) * 2020-11-08 2021-01-29 侯钦娅 Sea pond silt clearance structure
CN112281968B (en) * 2020-11-08 2022-10-04 侯钦娅 Sea pond silt clearance structure
CN112431161A (en) * 2020-11-11 2021-03-02 中铁二十五局集团第五工程有限公司 Underwater dredging construction process
CN112681429A (en) * 2020-12-18 2021-04-20 刘红丹 Port sludge cleaning structure
CN118653536A (en) * 2024-08-20 2024-09-17 山西省水利建筑工程局集团有限公司 A river management device that is beneficial to optimizing river ecosystem
CN118653536B (en) * 2024-08-20 2024-10-29 山西省水利建筑工程局集团有限公司 A river management device that is beneficial to optimizing river ecosystem

Similar Documents

Publication Publication Date Title
CN208136999U (en) A kind of mud transportation system
CN102040328B (en) Silt solidification processor
CN201842751U (en) Sludge solidification treatment machine
CN113024057A (en) Construction method for preparing engineering bag by solidifying marine sludge
CN206308042U (en) One kind is for water body and in-situ sediment remediation device
CN104314129A (en) Filling and dredging mud adding stirring machine for constructional engineering and construction method thereof
CN215511644U (en) Foundation reinforcing device
CN215038989U (en) Preparation system of solidified soil
CN108058269B (en) Cement soil preparation system suitable for soil bodies with different fluidity
CN107975036A (en) Three four axis working ships of Underwater Deep Silt basement process
CN211571723U (en) Fluidized soil construction equipment
CN214520965U (en) Preparation system capable of pumping, pouring, backfilling and solidifying soil
CN204238282U (en) For construction work embankment dredged mud filling Mixing Machine
CN115366255A (en) A multi-mixer type fluidization processing device
JP2005330731A (en) Artificial tidal flat material using clay soil, manufacturing equipment and artificial tidal flat construction method.
JP3480699B2 (en) Land transfer method for sediment transfer such as dredging
JPH0551942A (en) Water-containing mud continuous solidification device
CN207646740U (en) Three four axis working ships of Underwater Deep Silt basement process
JP3344711B2 (en) Agitation / mixing type soil improvement machine
JPH02167996A (en) Continuous solidifying system of high moisture-content mud
CN220499556U (en) Silt flow solidified soil preparation system for pouring type roadbed
JP2895595B2 (en) Landfill work boat
CN219134444U (en) Water multifunctional concrete single-tank stirring and conveying ship
CN218776871U (en) Slurrying device for drilling and grouting operation of underground coal mine goaf of expressway
EP0699633A2 (en) Solidification and pneumatic transportation equipment for soft mud

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant